CN100534935C - Sub-dam construction method of Bayer process red-mud dry-stacking field - Google Patents

Sub-dam construction method of Bayer process red-mud dry-stacking field Download PDF

Info

Publication number
CN100534935C
CN100534935C CNB2006102004638A CN200610200463A CN100534935C CN 100534935 C CN100534935 C CN 100534935C CN B2006102004638 A CNB2006102004638 A CN B2006102004638A CN 200610200463 A CN200610200463 A CN 200610200463A CN 100534935 C CN100534935 C CN 100534935C
Authority
CN
China
Prior art keywords
dam
sub
red mud
mud
red
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2006102004638A
Other languages
Chinese (zh)
Other versions
CN1850666A (en
Inventor
李明阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CNB2006102004638A priority Critical patent/CN100534935C/en
Publication of CN1850666A publication Critical patent/CN1850666A/en
Application granted granted Critical
Publication of CN100534935C publication Critical patent/CN100534935C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses a subdam constructing method using Bayer red mud dry storage ground, constructing a subdam on the red mud on inner edges of an initial-stage dam staked with red mud, and comprising the steps of: batching, subdam foundation firming, subdam body rolling moudling, and subdam body finishing. And it is aimed at the red mud dry storing mode in the Bayer production, able to meet mechanical strength for stabilizing the red mud storage ground in the dry storing mode, and able to obtain larger storage capacity in a limited storage ground area.

Description

A kind of sub-dam construction method of Bayer process red-mud dry-stacking field
Technical field
The present invention relates to the sub-dam construction method of a kind of sub-dam construction method of dry-method red mud storage yard, particularly a kind of Bayer process red-mud dry-stacking field.
Background technology
In the alumina producing, adopt different production technique with the difference of raw material.What generally adopt at present is the alkaline process production technique, in the alkaline process production technique, specifically also can be divided into Bayer process, sintering process and integrated process.The waste residue that produces in the alumina producing is red mud, need be sent to special red mud dump and store up.Red mud dump is by the acquisition storage capacity of building a dam, and initial dam is constructed with materials such as native stones by general elder generation, constructs sub-dam with red mud again after initial dam piles with and increases step by step, so that obtain bigger storage capacity on limited storage space.
The material of sintering process and integrated process red mud contains β-2CaOSiO2 (Dicalcium Phosphate (Feed Grade)) more than 50% in forming, and has the hydraulic gelling under the certain condition, and its mechanical index is near cement of low index.At present, sintering process and integrated process red mud all adopt wet method to store up mode, and initial dam piles with increasing of stockyard, back and adopts hydraulic fill method to form sub-dam, promptly increases nature in time and form firm sub-dam in discharge, the height of dam on every grade of sub-dam mostly surpasses 6m, and the gradient is more than 45 ° outside the sub-dam.
In the red mud with the generation of Bayer process production technique, CaO and SiO 2Chemical Composition content low, about 20% and 7%, compare with the integrated process red mud respectively with sintering process, mechanical index is much lower.For guaranteeing the stability of stack, the suitable dry method that adopts of Bayer process red mud is stored up mode, the red mud that the stockyard is delivered in i.e. control is starched its water ratio and (is being equivalent to the water content 89% on the soil mechanics meaning) below 47%, and carry out natural drying in the stockyard, a series of operations such as mechanical assistance teds.
The Bayer process red mud stockyard will continue upwards to store up after the dam piles with in the early stage, just must construct Zi Ba again.Because Bayer process red mud exists than big-difference with sintering process and integrated process red mud on mechanical property, therefore, the domestic sintering process that generally adopts and the rule of thumb data of integrated process red mud dump all can not be applied mechanically in aspects such as the mode of building a dam, height of dam, the dam slope on sub-dam compares, and the sub-dam construction method of existing red mud dump all not too adapts to the sub-dam construction of Bayer process red-mud dry-stacking field.
Summary of the invention
The objective of the invention is to: a kind of sub-dam construction method with the dry-method red mud storage yard that discharges in the alumina producing Bayer process process is provided, so that the Bayer process red mud stockyard can be implemented on the red mud dam foundation after the dam piles with in the early stage and construct Zi Ba with dried red mud as dam material, realize the lasting stacking in stockyard.
The present invention constitutes like this: a kind of sub-dam construction method of Bayer process red-mud dry-stacking field, on the red mud on sub-dam construction edge in the initial dam that piles with red mud, the construction method on sub-dam 1 is finished by following step: get the raw materials ready, reinforce the dam foundation, roller-compaction dam body, dam body finishing.
The sub-dam construction method of above-mentioned Bayer process red-mud dry-stacking field, in material preparation step, select for use the red mud of water content 25%~35% to make dam material, dam material is deposited near the sub-dam dam site, and at the wet red mud slurry of the red mud surface discharge of water content 25%~35% with its surface coverage, stand-by.
The sub-dam construction method of aforesaid Bayer process red-mud dry-stacking field, in reinforcing dam foundation step, with dozer the red mud layer that is in the dam foundation 2 scopes is carried out broken shell and preliminary rolling operation earlier, further roll with vibrating roller again, until reaching 35% when following in the dam foundation scope 3m degree of depth with interior red mud water content, finish stabilization of dam foundation through sampling Detection.
The sub-dam construction method of aforesaid Bayer process red-mud dry-stacking field, in roller-compaction dam body step, transport to the Zi Ba position with choosing stand-by material, and carry out fragmentation, shakeout, the vibroroller cmpacting operation is carried out in layering then, and every layer is rolled gauge control at 300~400mm, water content 20%~23% that is compacted to every layer of red mud o'clock is qualified, width by lower floor to upper strata successively successively decreases, but should be than the wide 0.5~2m in dam body both sides after finishing, and the height until sub-dam reaches 5.5~6.5M.
The sub-dam construction method of aforesaid Bayer process red-mud dry-stacking field, in the dam body pre-shaping step, after sub-dam rolls and finishes dam body being carried out deburring handles, medial and lateral respectively trim redundance 3, outside the sub-dam, inner slope all is trimmed to 1: 2~1: 2.5 the gradient, width at dam crest 4.5~the 6M on sub-dam, the sub-dam after the finishing should symmetry along dam axis direction two sides.
Compared with prior art, The present invention be directed to the dry-method red mud that produces in the Bayer process production and store up mode, and the sub-dam construction method of invention can satisfy dry method and store up the stockyard of mode and stablize needed mechanical strength, can obtain bigger storage capacity on limited storage space.
Description of drawings
Accompanying drawing 1 is that sub-dam of the present invention forms synoptic diagram.
Embodiment
Embodiments of the invention: as shown in Figure 1; at first; prepare dam material; with tedded in the red mud layer of stockyard, water content reaches 25%~35% red mud and elects; stack near being transported to sub-dam to be constructed with machineries such as dozer, excavators; and take measures (as at a small amount of red mud of surface discharge slurry) protected, to keep its water content.
Secondly, the dam foundation on antithetical phrase dam is reinforced, and sub-dam 1 is seated on the red mud layer, with the red mud layer as sub-dam foundation plinth.With dozer the red mud layer that is in the dam foundation 2 scopes is carried out broken shell and preliminary rolling operation earlier, further roll with vibrating roller again, reach 35% when following until the 3m degree of depth in sampling Detection dam foundation scope with interior red mud water content, finish stabilization of dam foundation.
Then, the operation of on the dam foundation after the reinforcing, building a dam, good red mud as dam material will be stacked, transport to the Zi Ba position with machineries such as dozer, excavators, and carry out fragmentation, shakeout, layering is carried out rolling operation with vibrating roller then, and every layer is rolled thickness 300mm, is qualified when being compacted to sub-dam dam body red mud water content 20%.Every layer width progressively successively decreases, and rolls width and should many 2m (inboard, the outside respectively have more 1m) than the required width of dam body, with the compacting intensity of the dam body that guarantees whole sub-dam and the job safety of street roller.When reaching 6m, finishes group height of dam degree dam compacting operation.
At last, dam body is carried out deburring handle, medial and lateral respectively trim redundance 3, and sub-dam Wai Po, inner slope all are trimmed to 1: 2 the gradient, and the top width on sub-dam is 5m, guarantee mechanical current the needs.The finishing back is same numerical value along the wide and inside and outside dam slope of the dam crest of each section of dam axis direction.
Through above step, finish constructing of the high sub-dam of 6m, can carry out the blowing operation on the sub-dam and come into operation.The dam foundation red mud water content on sub-dam detects every the 30m sampling, and the dam body red mud water content on sub-dam detects every the 15m sampling.Lower floor's red mud detects and can spread out cloth after qualified, rolls the last layer red mud during rolling operation.The gradient of sub-dam outer slope should be appraised and decided according to the stack stability Calculation.

Claims (3)

1. the sub-dam construction method of a Bayer process red-mud dry-stacking field, it is characterized in that: sub-dam (1) is constructed on the red mud on edge in the initial dam that piles with red mud, and the construction method of sub-dam (1) is finished by following step: get the raw materials ready, reinforce the dam foundation, roller-compaction dam body, dam body finishing; In material preparation step, select for use the red mud of water content 25%~35% to make dam material, dam material is deposited near the sub-dam dam site, and at the wet red mud slurry of the red mud surface discharge of water content 25%~35% with its surface coverage, stand-by; In reinforcing dam foundation step, with dozer the red mud layer that is in the dam foundation (2) scope is carried out broken shell and preliminary rolling operation earlier, further roll with vibrating roller again, until reaching 35% when following in the dam foundation scope 3m degree of depth with interior red mud water content, finish stabilization of dam foundation through sampling Detection.
2. the sub-dam construction method of Bayer process red-mud dry-stacking field according to claim 1, it is characterized in that: in roller-compaction dam body step, transport to the Zi Ba position with choosing stand-by material, and carry out fragmentation, shakeout, the vibroroller cmpacting operation is carried out in layering then, every layer is rolled gauge control at 300~400mm, water content 20%~23% that is compacted to every layer of red mud o'clock is qualified, width by lower floor to upper strata successively successively decreases, but should be than the wide 0.5~2m in dam body both sides after finishing, the height until sub-dam reaches 5.5~6.5M.
3. the sub-dam construction method of Bayer process red-mud dry-stacking field according to claim 1, it is characterized in that: in the dam body pre-shaping step, after sub-dam rolls and finishes dam body being carried out deburring handles, medial and lateral respectively trim redundance (3), outside the sub-dam, inner slope all is trimmed to 1: 2~1: 2.5 the gradient, width at dam crest 4.5~the 6M on sub-dam, the sub-dam after the finishing should symmetry along dam axis direction two sides.
CNB2006102004638A 2006-05-18 2006-05-18 Sub-dam construction method of Bayer process red-mud dry-stacking field Active CN100534935C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006102004638A CN100534935C (en) 2006-05-18 2006-05-18 Sub-dam construction method of Bayer process red-mud dry-stacking field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006102004638A CN100534935C (en) 2006-05-18 2006-05-18 Sub-dam construction method of Bayer process red-mud dry-stacking field

Publications (2)

Publication Number Publication Date
CN1850666A CN1850666A (en) 2006-10-25
CN100534935C true CN100534935C (en) 2009-09-02

Family

ID=37132168

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006102004638A Active CN100534935C (en) 2006-05-18 2006-05-18 Sub-dam construction method of Bayer process red-mud dry-stacking field

Country Status (1)

Country Link
CN (1) CN100534935C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409684A (en) * 2011-08-04 2012-04-11 中国铝业股份有限公司 Storage-yard damming method of red mud by mixed self-solidifying dry process

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101033074A (en) * 2007-02-13 2007-09-12 沈阳铝镁设计研究院 Stacking method for red mud damming of sintering method and red mud discharging of Bayer method
CN101363217A (en) * 2007-08-09 2009-02-11 沈阳铝镁设计研究院 Dam construction method of red mud permeable dam by sintering process
CN101929160B (en) * 2009-06-24 2012-05-23 鞍钢集团矿业公司 Method for building impermeable tailings dams with high scattered piles by waste rocks
CN101871216A (en) * 2010-06-13 2010-10-27 中国铝业股份有限公司 Method for damming with red mud in winter
CN104631386B (en) * 2015-01-16 2016-06-15 中冶京诚(秦皇岛)工程技术有限公司 Winter ore drawing damming method
CN106284373B (en) * 2016-08-30 2018-10-09 金堆城钼业股份有限公司 A kind of method of construction of Tailings Dam
CN112655515A (en) * 2020-12-16 2021-04-16 中铝环保生态技术(湖南)有限公司 Method for converting red mud into soil

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409684A (en) * 2011-08-04 2012-04-11 中国铝业股份有限公司 Storage-yard damming method of red mud by mixed self-solidifying dry process
CN102409684B (en) * 2011-08-04 2014-08-13 中国铝业股份有限公司 Storage-yard damming method of red mud by mixed self-solidifying dry process

Also Published As

Publication number Publication date
CN1850666A (en) 2006-10-25

Similar Documents

Publication Publication Date Title
CN100534935C (en) Sub-dam construction method of Bayer process red-mud dry-stacking field
CN101718086B (en) Concrete-enrockment mixed dam and construction method thereof
CN102864782A (en) Construction method for fast filling clay core rock-fill dam body
CN104762949B (en) A kind of manufacturing process of straw solidification blowing-filling sludge stake
CN104556766A (en) Construction method for building foundation bed employing recycled concrete
CN102650128A (en) Cement mixing pile with stiffness core capable of draining and pre-pressing firstly and then grouting as well as construction method thereof
CN101899828A (en) Construction method of bagged rammed small-diameter soil-cement pile composite foundation
CN103215950A (en) Pile foundation extension construction method in backfilling area
CN107503370B (en) The high barricade of one seed sand well combined type reinforced earth and production method
CN107142902B (en) High head and large flow tunneling boring damming method
CN106758559B (en) A kind of construction method of high-speed railway silt, flour sand embankment structure
CN102409660A (en) Given-force engineering method for multisection expanded head discrete material pile composite foundation
CN206986906U (en) A kind of slurry dry method red mud storage yard constructs the structure of fill dam
CN107558490A (en) Composite foundation reinforcement rockfill barrier wall structure and construction method
CN110409413A (en) The construction method of self-expansion type compaction pile
CN109747024A (en) A kind of light composite wallboard and its preparation process
CN209620076U (en) A kind of construction structure of thermal power plant gypsum as the grey field fill dam dam foundation
CN202755438U (en) Integrative structure with functions of anchoring, drainage and flood interception in refuse landfill
CN113529757B (en) Step type water permeability building rubbish slope supporting structure and construction method
CN110258459A (en) A kind of calculation method of earth and rockfill dam longitudinal direction reinforcement safety coefficient
CN206752210U (en) A kind of high-speed railway silt, flour sand embankment structure
CN115613595A (en) Application of waste concrete as backfill material and backfill construction method thereof
CN105019487B (en) A kind of rectifying of leaned building method of raft plate shallow foundation
CN101164925B (en) Sintering method red mud and Bayer method red mud mixed dam building method
CN100458090C (en) Concrete large capacity movable combined water-accumulating body and its preparation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INSTITUTE C

Free format text: FORMER OWNER: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

Effective date: 20110524

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 550004 NO. 208, BEIJING ROAD, GUIYANG CITY, GUIZHOU PROVINCE TO: 550081 NO.2, JINZHU ROAD, JINYANG NEW DISTRICT, GUIYANG CITY

TR01 Transfer of patent right

Effective date of registration: 20110524

Address after: 550081 2 Jin Zhu Road, Jinyang New District, Guiyang

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.