CN100518966C - Method for building garbage landfill field and the landfill field - Google Patents

Method for building garbage landfill field and the landfill field Download PDF

Info

Publication number
CN100518966C
CN100518966C CNB2006100314983A CN200610031498A CN100518966C CN 100518966 C CN100518966 C CN 100518966C CN B2006100314983 A CNB2006100314983 A CN B2006100314983A CN 200610031498 A CN200610031498 A CN 200610031498A CN 100518966 C CN100518966 C CN 100518966C
Authority
CN
China
Prior art keywords
landfill
plane
refuse landfill
yard
landfill yard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2006100314983A
Other languages
Chinese (zh)
Other versions
CN101054804A (en
Inventor
龙岳林
陈琼琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LONG YUELIN CHEN QIONGLIN
Original Assignee
LONG YUELIN CHEN QIONGLIN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LONG YUELIN CHEN QIONGLIN filed Critical LONG YUELIN CHEN QIONGLIN
Priority to CNB2006100314983A priority Critical patent/CN100518966C/en
Publication of CN101054804A publication Critical patent/CN101054804A/en
Application granted granted Critical
Publication of CN100518966C publication Critical patent/CN100518966C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/30Landfill technologies aiming to mitigate methane emissions

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The invention relates to a processing method for the solid waste, wherein an ecology inert type landfill site is built to process the solid waste. The technical proposal of the invention is to satisfy two conditions at the site selection: one is the relative position is higher, and the other one is the depth of excavation is not lower than the water table. The invention makes the garbage in the relatively dry state by effectively reducing the natural rain water into the dustheap and no margin water exosmosis in the garbage landfill, thereby rigidly controlling the rubbish pollution range restricted to the inside of the landfill without polluting the external environment.

Description

Build the method and the refuse landfill of refuse landfill
Invention field
The present invention relates to the processing method of solid waste, build a kind of refuse landfill of ecological safety type and handle solid waste.
The invention still further relates to the refuse landfill of handling solid waste.
Background of invention
Garbage environment pollution is a global significant problem, the improper sustainable development that will have a strong impact on ecological safety and society of garbage disposal, and countries and regions especially underdeveloped are more outstanding.Trash processing way generally has three kinds at present: burning, sanitary landfills and compost.
The sanitary landfills of rubbish be the centralized treatment of urban garbage of present China main mode [Du Jiajing, Wang Fengqing. Design of Valley-Type Landfill Site is inquired into. environmental hygiene engineering .2005, (3) 53~54.].The step of building refuse landfill comprises addressing, design, steps such as excavation, antiseepage processing, landfill, covering.Existing refuse landfill addressing all is on the level land or the valley floor, and therefore, landfill yard is subjected to underground water inevitably, and the infiltration of rainwater etc. causes the pollution to the landfill yard surrounding enviroment, and is serious even can produce underground water source and pollute.The most headachy problem is the processing of garbage leachate in the design and running management of refuse landfill, has proposed many methods how the disposal of refuse landfill yard oozes drop liquid in the prior art, for example CN200410016079.3.Because garbage leachate water quality composition is extremely complicated, and water quality and quantity is subjected to that the variation, weather of landfill yard service life and rubbish composition etc. are multiple to be difficult to the factor affecting of artificial control and to change in very big amplitude range, and this gives determining of the process choice of oozing drop liquid and handling, design parameter and operational management brings great difficulty.
On the other hand, also there is people (CN02145261.X) to propose to eliminate vertical rain penetration in the prior art, makes rainwater and sewage separation with the method for coverlay.Though this has reduced the amount that enters the water in the refuse landfill, rainwater can be stoped owing on landfill yard, cover, but underground water can not be stoped, therefore still need handle and ooze drop liquid.Simultaneously, also not environmental protection of the film that is covered itself is unfavorable for setting up good ecological environment in refuse landfill.
Summary of the invention
The present invention is directed to conventional garbage landfill yard construction method and have the insurmountable drop liquid problem of oozing, propose a kind of brand-new method of building refuse landfill.
Technical scheme of the present invention is when addressing, satisfies two conditions, the one, and relative position is higher; The 2nd, cutting depth is not less than level of ground water.
Traditional refuse landfill all is to build on the level land or low-lying place.The present invention proposes refuse landfill and builds on the highland that can not suffer flood harm, top, for example hillside fields, or massif.For economical operation, easy to operate, preferably select the gradient less nearby, and can lead to the mountain region of haulage vehicle, or select the terraced fields that will concede the land to forestry for use.Such addressing has solved the big problem of refuse landfill polluted underground water.
Simultaneously, consider the gradient of selected location, build barricade in the lower side of landfill yard or around whole landfill yard.Build barricade at the lower edge of relative position, selected place two effects arranged: the one, the scope of control garbage loading embeading, as with the line of demarcation of environment outside the venue; The 2nd, help increasing the degree of depth of garbage loading embeading, because the downward pressure that weight produces, and prevent the rubbish landslide to bear rubbish in the landfill yard, the structure of barricade is decided according to the concrete landform of the landfill yard of being built.The barricade in soot is different with general straight retaining wall, and on the spot position and profile change and change according to site topography, can have complications and height to change.The barricade material preferably selects for use the nature scree to build, raise as higher maybe need the continuation of barricade, then should be according to the needs of engineering safety, adopt reinforced concrete pile, beam and plate to reinforce, the tor of best natural imitation circle of profile of barricade, make every effort to make a distinction between the important and the lesser one, height is in picturesque disorder, can become the view with certain artistic appeal.In addition, in order to reduce construction costs, barricade also can adopt easy Tu Shan to replace, but must take the necessary engineering measure that prevents the Tu Shan landslide.Barricade also can adopt native stone in conjunction with construction, mild part soil, precipitous part stone.
Before the inherent heap garbage in field, the table soil that will have certain fertility forwards the both sides of dumping part to, makes to cover the standby soil and the plantation soil of rubbish.The order of digging is progressively to dig commentaries on classics at the bottom of the mountain on the mountain, and the degree of depth of digging must preferably be no more than 1m more than level of ground water, and width is decided according to the quantity of refuse of landfill, can be wide can be narrow.The table soil of digging can be used to enclose the hole temporarily and be scattered to both sides to stop rubbish before rubbish is not piled design height.
If the place is milder mountain region, rubbish can directly be transported to interior a stacking; If the place gradient is bigger, then can select a higher position, conveyer is installed, utilize conveyer belt that rubbish is gone to and stack the place.After the dumping, the biologic garbage in the rubbish heap easily produces a large amount of biogas and forms potential safety hazard in the environment of anaerobism, therefore, before dumping, must the guide tracheae be installed earlier, for example adopts the filter pipe of DN100mm, per 15~20m 2Install one, and notice that control rubbish blocks blast pipe in the process of rubbish Bian Dui limit compacting, the biogas that rubbish heap is produced in time is discharged into out-pile.In the dumping process, should in time the rubbish of having stacked be covered with film or other coverings, a rainwash of managing to stack the some top draws away, and pollutes environment and underground water outside the venue to prevent rainwater from infiltrating in the rubbish heap, and remaining does not have bulk water more than needed and exosmose in the rubbish heap.
In dumping to design height, the table soil of digging in both sides is covered on the rubbish heap, and it is banded that the soil that will cover is organized into ladder, the ladder band is made up of alternate table top and inclined-plane, surface slope is 25~35 °, and surface width generally must not surpass 5 meters, and the less regional inclined-plane of rainfall can be narrow, otherwise the inclined-plane can be wide.But the width of each table top is advisable with 1-3 meters.
Formed tableland behind the whole ground of earthing utilizes table top optionally to plant indigenous plant in case the forest ecology view is built in soil erosion.Characteristics such as green tree species possesses preferably that antipollution is drought-resistant, salt tolerant alkali and anti-low level management are as trees such as black pine, Cong Zhu, Chinese tallow tree, locust tree, oleander, paper mulberries; Perennial plants such as the ground selected tuber of dwarf lilyturf, iris, fringed iris, Lysimachia christinae.One of every earthing is then in time afforested one, to recover forest ecological environment as early as possible.
The refuse landfill of building according to the designing institute of mountain region provided by the invention ecological safety type refuse landfill has following architectural feature: (1) builds barricade in the lower side of landfill yard or around whole landfill yard; (2) the landfill yard end face is the ladder band shape, and the ladder band is made up of alternate table top and inclined-plane, and the gutter that water can be discharged to outside the landfill yard is arranged in the bottom on each inclined-plane; (3) on above-mentioned all or part of inclined-plane table soil, cover watt; Partly plant plant at unlapped table top.
Preferred surface slope is with 25~35 °, and width is no more than 5 meters, and table top is 1-3 meters.
The present invention enters the state that makes rubbish be in relatively dry in the rubbish heap by the natural rainwater of effective minimizing, and refuse landfill does not have water more than needed and exosmoses.Thereby the scope of strict control refuse pollution is confined in the landfill yard, is unlikely to pollute external environment.Behind the rubbish earthing, select the configuration of suitable plant by science, fast quick-recovery or reproduce vegetation forms more stable artificial plant group, refuse landfill is recovered as early as possible or strengthens its Ecosystem Service.
Description of drawings
Fig. 1 is a landfill yard plane partial schematic diagram in the embodiment of the invention;
Fig. 2 is the local A-A cutaway view of landfill yard in the embodiment of the invention.
The specific embodiment
Embodiment 1
As shown in Figure 1, 2, the embodiment of the invention refuse landfill of building is built on the hillside.During digging, the table soil that will have certain fertility forwards the both sides of dumping part to, makes to cover the standby soil and the plantation soil 4 of rubbish.The order of digging is progressively to dig commentaries on classics at the bottom of the mountain on the mountain, and the degree of depth of digging is more than level of ground water.Ground 6 geological conditions in mountain region are stable.The table soil of digging can be used to enclose the hole temporarily and be scattered to both sides to stop rubbish before rubbish is not piled design height.A lower end is built the barricade 1 that useful natural scree is built in the position.Before rubbish 3 was stacked, the filter pipe of DN100mm was installed as guide tracheae 2 by elder generation, every 20m 2Install one.In rubbish 3 stacking process, should in time the rubbish of having stacked be covered with film or other coverings, a rainwash of stacking the some top is drawn away, pollute environment and underground water outside the venue to prevent rainwater from infiltrating in the rubbish heap, remaining does not have bulk water more than needed and exosmoses in the rubbish heap.When rubbish 3 is stacked to design height, the table soil of digging in both sides is covered on the rubbish heap.Covering table soil 4 is organized into into several inclined-planes and table top, each inclined-plane the bottom gutter 5 that water can be discharged to outside the landfill yard is arranged, surface width is no more than 5 meters, mesa width is 1-3 meters.Show on the native inclined-plane to cover at interval watts 7 in above-mentioned part.Plantation plant 8 on the table top that does not cover watt.

Claims (7)

1, build the method for refuse landfill, comprise addressing, excavation, landfill, covering step, it is characterized in that when addressing, satisfy two conditions, the one, relative position is higher; The 2nd, cutting depth is not less than level of ground water; The degree of depth of digging and is no more than 1m more than level of ground water; Build barricade in the lower side of landfill yard or around whole landfill yard; After dumping is intact, cover rubbish with soil, and the covering table regolith to be organized into ladder banded, the ladder band is made up of alternate table top and inclined-plane, each inclined-plane the bottom gutter that water can be discharged to outside the landfill yard is arranged; It is characterized in that described surface slope is 25~35 °.
2, method of building refuse landfill according to claim 1 is characterized in that barricade material selection nature scree block, and profile is imitated natural tor.
3, method of building refuse landfill according to claim 1 is characterized in that on above-mentioned all or part of inclined-plane table soil covering watt, partly plants plant at unlapped table top.
4, method of building refuse landfill according to claim 3, it is characterized in that covering and the inclined-plane that do not cover separately.
5, the refuse landfill of building according to the described method of building refuse landfill of one of claim 1 to 4 is characterized in that: (1) builds barricade in the lower side of landfill yard or around whole landfill yard; (2) the landfill yard end face is the ladder band shape, and the ladder band is made up of alternate table top and inclined-plane, and the gutter that water can be discharged to outside the landfill yard is arranged in the bottom on each inclined-plane; (3) on the native inclined-plane of above-mentioned all or part of table, cover watt; Partly plant plant at unlapped table top.
6, refuse landfill according to claim 5 is characterized in that surface slope is 25~35 °, and width is less than 5 meters, and mesa width is 1-3 meters.
7, refuse landfill according to claim 5 is characterized in that there is a watt covering compartment of terrain, inclined-plane.
CNB2006100314983A 2006-04-14 2006-04-14 Method for building garbage landfill field and the landfill field Expired - Fee Related CN100518966C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100314983A CN100518966C (en) 2006-04-14 2006-04-14 Method for building garbage landfill field and the landfill field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100314983A CN100518966C (en) 2006-04-14 2006-04-14 Method for building garbage landfill field and the landfill field

Publications (2)

Publication Number Publication Date
CN101054804A CN101054804A (en) 2007-10-17
CN100518966C true CN100518966C (en) 2009-07-29

Family

ID=38794834

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100314983A Expired - Fee Related CN100518966C (en) 2006-04-14 2006-04-14 Method for building garbage landfill field and the landfill field

Country Status (1)

Country Link
CN (1) CN100518966C (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669395B (en) * 2012-09-13 2015-12-16 上海老港废弃物处置有限公司 Control the cofferdam device of the landfill yard rubbish scope of operation
CN105926645B (en) * 2016-04-27 2018-06-12 谢铁冬 A kind of ecological restoring method of Waste Landfill Site
CN105921482A (en) * 2016-07-11 2016-09-07 中国环境科学研究院 Rural domestic waste treatment system and process based on quasi-aerobic landfill
CN107661894B (en) * 2017-08-16 2020-10-16 上海老港废弃物处置有限公司 Three-dimensional operation method for landfill of household garbage
CN108746141A (en) * 2018-05-17 2018-11-06 迁西县五为生物科技有限公司 Rural area Harmful Waste are sealed up for safekeeping and the method for utilizing
CN113006053A (en) * 2021-03-05 2021-06-22 北京高能时代环境技术股份有限公司 Capacity-increasing and height-increasing landfill structure and construction method
CN113522922B (en) * 2021-07-12 2022-09-16 中兰环保科技股份有限公司 Device and method for collecting gas in garbage pile body of storage garbage landfill
CN113737863B (en) * 2021-09-13 2022-10-11 生态环境部华南环境科学研究所 Mixed solid waste pile point soil pollution risk control method based on horizontal barrier technology

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
山谷型垃圾填埋场设计探讨. 杜佳靖,王峰青.环境卫生工程,第13卷第3期. 2005
山谷型垃圾填埋场设计探讨. 杜佳靖,王峰青.环境卫生工程,第13卷第3期. 2005 *
生活垃圾卫生填埋技术. 赵由才,龙燕,张华,第1章,化学工业出版社,环境科学与工程出版中心. 2004
生活垃圾卫生填埋技术. 赵由才,龙燕,张华,第1章,化学工业出版社,环境科学与工程出版中心. 2004 *

Also Published As

Publication number Publication date
CN101054804A (en) 2007-10-17

Similar Documents

Publication Publication Date Title
CN100518966C (en) Method for building garbage landfill field and the landfill field
US3705851A (en) Waste disposal system
CN110541420B (en) Safe mining method and mining structure for valley type domestic garbage landfill
CN107366251A (en) A kind of construction method of sludge lagoon place original position Ecosystem restoration system
CN112709233A (en) Mine waste rock and concentrated tailing cooperative disposal system and construction method
CN211113444U (en) Ecological protective structure of riverway bank slope under unfavorable geological conditions
CN110644427B (en) Ecological protection structure of river bank slope under unfavorable geological conditions and dredging method
KR100667262B1 (en) Waste landfill site preventing landfill gas escape by using waterproof mat
CN107321752A (en) A kind of sludge lagoon place Ecosystem restoration system in situ
CN216865196U (en) Sealing covering structure of municipal solid waste landfill
CN114457855B (en) Sinking type horizontal seepage-proofing and vertical seepage-proofing combined structure
CN111335362B (en) Structural arrangement mode of common industrial solid waste storage place
CN1850369A (en) Inertial-garbage dry burying method
CN212153470U (en) Household garbage landfill yard closing system and household garbage landfill yard
CN216007052U (en) Rigid refuse landfill
Palaniandy et al. Sanitary Landfill Types and Design
CN110528538B (en) Refuse landfill and construction method thereof
Cointreau Sanitary landfill design and siting criteria
RU2235610C1 (en) Method of storing solid and water-saturated waste
CN213390180U (en) Ecological restoration system for abandoned mine and garbage yard
CN212896492U (en) Landfill yard closing structure
CN114658079B (en) Method for stacking waste soil in dumping site based on rain intensity
CN219503430U (en) Vertical partition structure of household garbage landfill
CN111335363B (en) New method for storing and disposing general industrial solid waste
CN217419751U (en) Slope slip casting reinforcement type protective structure of rubbish filling field

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090729

Termination date: 20100414