Prior art keywords
steel strand
hammer
pressure welding
strand wire
transmission line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2005100383832A
Other languages
English (en)
Other versions
CN1674378A (zh
Inventor
孔德春
张静华
李谋祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Shuanghui Power Development Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2005100383832A priority Critical patent/CN100395930C/zh
Publication of CN1674378A publication Critical patent/CN1674378A/zh
Application granted granted Critical
Publication of CN100395930C publication Critical patent/CN100395930C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Springs (AREA)

Abstract

本发明输电线路防振锤可用于输电线路中。防振锤由钢绞线(1)、锤体(2)、压接套(3)和夹头本体(7)、夹头盖板(8)等组成,其特征是在钢绞线(1)的两端分别加装压接有一个压接套(3),压接套(3)大端分别铆接在各个锤体(2)的锤头上,夹头本体(7)压固在钢绞线(1)上。这种台阶式的中空圆柱形压接套(3),一端外径较大,另一端外径较小,其外径较大一端分别放置在钢绞线的两个外顶端处,而外径较小一端的中部则分别压接在钢绞线(1)上。锤体(2)的锤头孔穿入套装在压接套(3)外表面上,压接套(3)的大端分别被打入铆接在锤体(2)的锤头孔内。优点是安装工艺过程简单、牢固可靠,劳动强度小。

Description

输电线路防振锤
技术领域:
本发明防振锤用于输电线路中,以便吸收和减轻输电导线在空中的振动和摆动。
背景技术:
以往在防振锤组装体的两端钢绞线上,各加装一个中空圆柱形套,将这两个中空圆柱形套分别与钢绞线压接在一直,然后,在防振锤锤体的锤头与该圆柱形压接套的外端面分别加铝、锌等金属灌装在其中,这样的安装工艺过程显然十分复杂、麻烦、劳动强度很大。
发明内容:
本发明的目的是提供一种输电线路防振锤,将原来的中空圆柱形套改设计为带有台阶式的中空圆柱形压接套,以便达到简化安装工艺过程的目的。
一种由钢绞线(1)、锤体(2)、压接套(3)和夹头本体(7)、夹头盖板(8)组成的输电线路防振锤,其特征在于中空圆柱形压接套(3)为台阶式,一端外径较小,另一端外径较大,压接套(3)的外径较大一端分别位于钢绞线(1)的两个外顶端处,压接套(3)外径较小的一端中部分别压接在钢绞线(1)上。
钢绞线采用多股镀锌的钢绞线扭绞而成,先将夹头本体采用冷压法压固在钢绞线的中部,再用螺栓、弹簧垫片及螺母等紧固件穿入夹头本体及夹头盖板,使夹头本体和夹头盖板连接在一起,然后,再在钢绞线两端分别各穿入锤体,最后,将两只压接套分别穿入钢绞线的两端。
这种带有台阶式的中空圆柱形压接套,一端外径较小,另一端外径较大;其外径较大的一端分别放置在钢绞线的两个外顶端处,而外径较小一端的中部则分别压接在钢绞线上,然后,将两个锤体的锤头孔分别穿入套装在各个压接套的外表面上,最后,将两个压接套的大端分别打入铆接在两个锤体的锤头孔内,使其铆接牢固,不得转动。两个锤体的锤头中心线的夹角应为90°。
附图说明:
图1:输电线路防振锤组装体正视半剖示意图。
图中:(1)钢绞线,(2)锤体,(3)压接套。
图2;输电线路防振锤组装体侧视局部剖视示意图。
图中:(4)螺栓,(5)弹簧垫片,(6)螺母,(7)夹头本体,(8)夹头盖板,(9)垫块。
图3:输电线路防振锤锤体(2)的锤头局部剖视示意图。
具体实施方式:
现对本发明输电线路防振锤组装体实施例说明如下:
钢绞线(1)采用镀锌的19股钢绞线扭绞而成,其每股直径为2.6毫米,钢绞线(1)的全长为520毫米,钢绞线(1)外径为
Figure C20051003838300041
毫米。
夹头本体(7)和夹头盖板(8)均采用铸造铝合金材料,型号均为ZL102,夹头本体(7)宽度为60毫米,通过冷压法压固在钢绞线(1)的中部位置处,压后不得有松脱及裂缝。
两个压接套(3)分别压接在钢绞线(1)的两侧,压接套(3)的中部与钢绞线(1)压接在一起,压接套(3)的中部压接长度为38毫米,压接后应牢固可靠。压接套(3)为中空圆柱体,其外径较大的一端分别安装放置在钢绞线(1)的两端外。
压接套(3)的材料采用碳钢,型号为Q235A,压接套(3)全长为60毫米,压接套(3)的大端外径为
Figure C20051003838300051
毫米,大端长度为3毫米,压接套(3)的小端外径为毫米,小端内径为
Figure C20051003838300053
毫米,小端中空部分圆柱长度为50毫米。压接套(3)应热镀锌,并且无锌刺。
两个锤体(2)在压接套(3)压接在钢绞线(1)之前,已经被分别穿入在钢绞线(1)的两端内,当压接套(3)与钢绞线(1)压接好后,再将左、右两个锤体(2)的锤头分别套装在压接套(3)上,再分别将两个左、右锤体(2)的内端固定,然后,再将锤体(2)的锤头与压接套(3)铆接在一起,铆接后应牢固,不得转动,其方法是将压接套(3)铆接打入到锤体(2)的锤头孔内。
锤体(2)材料为可锻铸铁,铸件表面应光滑,无铸造缺陷,铸造圆角应为圆滑过渡,其表面热镀锌。锤体(2)的锤头内圆通孔应与压接套(3)外径相匹配。锤体(2)全长为180毫米。
本发明输电线路防振锤可适用于输电导线截面为35~50平方毫米至500~630平方毫米的输电线路上。
本发明输电线路防振锤的优点是安装工艺过程简单,牢固可靠,劳动强度小。

Claims (1)

1.一种输电线路防振锤,其由钢绞线(1)、锤体(2)、压接套(3)和夹头本体(7)、夹头盖板(8)所组成,其特征在于夹头本体(7)和夹头盖板(8)通过紧固件连接在一起,夹头本体(7)压固在钢绞线(1)中部;中空圆柱形压接套(3)为台阶式,一端外径较小,另一端外径较大,压接套(3)的外径较大一端分别位于钢绞线(1)的两个外顶端处,压接套(3)的外径较小一端中部分别压接在钢绞线(1)上。
CNB2005100383832A 2005-02-21 2005-02-21 输电线路防振锤 Active CN100395930C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100383832A CN100395930C (zh) 2005-02-21 2005-02-21 输电线路防振锤

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100383832A CN100395930C (zh) 2005-02-21 2005-02-21 输电线路防振锤

Publications (2)

Publication Number Publication Date
CN1674378A CN1674378A (zh) 2005-09-28
CN100395930C true CN100395930C (zh) 2008-06-18

Family

ID=35046716

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100383832A Active CN100395930C (zh) 2005-02-21 2005-02-21 输电线路防振锤

Country Status (1)

Country Link
CN (1) CN100395930C (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7569769B2 (en) * 2007-04-02 2009-08-04 Preformed Line Products Company Damper assembly staking system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4159393A (en) * 1976-07-09 1979-06-26 Dulmison Australia Pty Ltd Vibration damper
CN2439742Y (zh) * 2000-07-17 2001-07-18 湖州泰仑电力线路器材总厂 一种防振锤
CN2548341Y (zh) * 2002-04-30 2003-04-30 江苏捷凯电力器材集团公司 大截面导线配套的电力金具的防振锤
CN2717082Y (zh) * 2004-03-17 2005-08-10 李谋祥 输电线路防振锤

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4159393A (en) * 1976-07-09 1979-06-26 Dulmison Australia Pty Ltd Vibration damper
CN2439742Y (zh) * 2000-07-17 2001-07-18 湖州泰仑电力线路器材总厂 一种防振锤
CN2548341Y (zh) * 2002-04-30 2003-04-30 江苏捷凯电力器材集团公司 大截面导线配套的电力金具的防振锤
CN2717082Y (zh) * 2004-03-17 2005-08-10 李谋祥 输电线路防振锤

Also Published As

Publication number Publication date
CN1674378A (zh) 2005-09-28

Similar Documents

Publication Publication Date Title
US9175715B2 (en) Functional element having features providing security against rotation and also a component assembly consisting of the functional element and a sheet metal part
US20090060640A1 (en) Lightweight heavy duty bushing with easy assembly
CN101920302A (zh) 电致塑性自冲铆接装置
CN100395930C (zh) 输电线路防振锤
CN2717082Y (zh) 输电线路防振锤
CN213628576U (zh) 一种工程车专用的离合器从动盘
CN203377756U (zh) 电动机机壳内止口的车夹具
CN206128447U (zh) 一种自动锚固装置及钢绞线预应力张拉系统
CN203514796U (zh) 一种组合式铝模板用单孔保护套
CN205183661U (zh) 一种液压全自动自冲刺铆接枪
CN205310158U (zh) 一种简便连杆轴套拆装工具
CN210193133U (zh) 一种电梯焊接型绳头组件
CN202225145U (zh) 发动机缸盖的气门座圈压装用压装工具
RU76087U1 (ru) Штанга реактивная с резинометаллическими шарнирами (варианты)
CN210616330U (zh) 两用加长套筒扳手
CN209648603U (zh) 一种适用于狭小空间内轴的拆卸工具
CN205889022U (zh) 一种曲轴衬套装配工具
CN201858273U (zh) 用于汽车底盘传动的万向节叉
CN210034071U (zh) 一种钢板紧固组件
CN209767038U (zh) 一种冲压式重型电缆保护器
CN220151837U (zh) 一种新型护套电机组件
WO2020051873A1 (en) Pilot assembly, processing method of pilot assembly and hydraulic torque converter
CN216464386U (zh) 一种返回弹簧限位钢丝挡圈装拆装置
CN212421157U (zh) 一种用于取出空心花键轴中分配器衬套的专用机构
CN214976822U (zh) 一种用于塔式起重机标准节主肢的矫扭装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JIANGSU SHUANGHUI ELECTRIC POWER DEVELOPMENT CO.,

Free format text: FORMER OWNER: LI MOUXIANG

Effective date: 20090612

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20090612

Address after: No. 51, Xian Xian Road, Jiangsu, Jiangdu

Patentee after: Jiangsu Shuanghui Power Development Co., Ltd.

Address before: Gemini Shuanggou town of Jiangdu City in Jiangsu Province Road No. 51

Patentee before: Li Mouxiang

EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangsu Shuanghui Power Development Co., Ltd.

Assignor: Li Mouxiang

Contract fulfillment period: 2009.3.12 to 2025.2.20 contract change

Contract record no.: 2009320000878

Denomination of invention: Transmission line antivibration hammer

Granted publication date: 20080618

License type: Exclusive license

Record date: 2009.5.14

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2009.3.12 TO 2025.2.20; CHANGE OF CONTRACT

Name of requester: JIANGSU SHUANGHUI ELECTRIC POWER DEVELOPMENT CO.,

Effective date: 20090514