CN100395417C - A construction method of cast-in-situ concrete hollow floor - Google Patents
A construction method of cast-in-situ concrete hollow floor Download PDFInfo
- Publication number
- CN100395417C CN100395417C CNB2004100775942A CN200410077594A CN100395417C CN 100395417 C CN100395417 C CN 100395417C CN B2004100775942 A CNB2004100775942 A CN B2004100775942A CN 200410077594 A CN200410077594 A CN 200410077594A CN 100395417 C CN100395417 C CN 100395417C
- Authority
- CN
- China
- Prior art keywords
- cavity
- floor
- cast
- ribs
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims abstract description 43
- 239000004567 concrete Substances 0.000 title claims abstract description 40
- 238000011065 in-situ storage Methods 0.000 title claims 2
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 34
- 239000010959 steel Substances 0.000 claims abstract description 34
- 238000000034 method Methods 0.000 claims abstract description 21
- 230000003014 reinforcing effect Effects 0.000 claims description 32
- 238000009415 formwork Methods 0.000 claims description 25
- 239000000463 material Substances 0.000 claims description 8
- 239000004570 mortar (masonry) Substances 0.000 claims description 8
- 239000011150 reinforced concrete Substances 0.000 claims description 8
- 238000004519 manufacturing process Methods 0.000 claims description 7
- 239000000835 fiber Substances 0.000 claims description 6
- 239000011083 cement mortar Substances 0.000 claims description 4
- 238000012423 maintenance Methods 0.000 claims description 3
- 230000003601 intercostal effect Effects 0.000 claims description 2
- 238000005516 engineering process Methods 0.000 abstract description 4
- 239000004744 fabric Substances 0.000 description 5
- 238000009413 insulation Methods 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 239000000853 adhesive Substances 0.000 description 2
- 230000001070 adhesive effect Effects 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000011490 mineral wool Substances 0.000 description 2
- 210000002435 tendon Anatomy 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 239000012615 aggregate Substances 0.000 description 1
- 238000004378 air conditioning Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 239000006260 foam Substances 0.000 description 1
- 239000011491 glass wool Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000003562 lightweight material Substances 0.000 description 1
- 150000002894 organic compounds Chemical class 0.000 description 1
- 239000010451 perlite Substances 0.000 description 1
- 235000019362 perlite Nutrition 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 229910052902 vermiculite Inorganic materials 0.000 description 1
- 239000010455 vermiculite Substances 0.000 description 1
- 235000019354 vermiculite Nutrition 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明属于建筑结构中的钢筋或钢混凝土施工技术领域。尤其适用于工业与民用建筑中混凝土一次成型浇注的暗密肋无板式楼盖使用预制构件时的现场施工技术。通过本发明的施工方法制作的楼盖,是采用大量的预制好的空腔构件,结合网格状肋中的少量现浇混凝土,制作楼盖,所形成的楼盖中楼板是由空腔构件上下两个端面构成,实际上是通过预制构件本体构成的无板式空心楼盖。不但节约成本,而且其主要的特点在于节约层高,浇灌楼盖的厚度与空腔的厚度相同、底面平整美观,同时施工过程简单,现场浇灌混凝土量较少,还可保证很高的使用强度,完全满足正常的设计和使用要求。
The invention belongs to the technical field of steel bar or steel concrete construction in building structures. It is especially suitable for the on-site construction technology when prefabricated components are used for the densely ribbed and plateless floor of the industrial and civil buildings where the concrete is poured at one time. The floor made by the construction method of the present invention adopts a large number of prefabricated cavity components, combined with a small amount of cast-in-place concrete in the grid-like ribs to make the floor, and the floor in the formed floor is made of cavity components Composed of upper and lower end faces, it is actually a plateless hollow floor composed of prefabricated component bodies. It not only saves cost, but also its main feature is to save floor height, the thickness of the pouring floor is the same as the thickness of the cavity, the bottom surface is flat and beautiful, and the construction process is simple, the amount of concrete poured on site is small, and it can also ensure high use strength , fully meet the normal design and use requirements.
Description
【技术领域】 【Technical field】
本发明属于建筑结构中的钢筋或钢混凝土施工技术领域。尤其适用于工业与民用建筑中混凝土一次成型浇注的暗密肋无板式楼盖使用预制构件时的现场施工技术。The invention belongs to the technical field of steel bar or steel concrete construction in building structures. It is especially suitable for the on-site construction technology when prefabricated components are used for the densely ribbed and plateless floor of the industrial and civil buildings where the concrete is poured at one time.
【背景技术】 【Background technique】
目前,砖混结构和框架结构的建筑物大部分采用预制空心板作为楼盖板,这种楼盖板具有施工速度快,造价低等优点,但由于相邻两块预制空心板之间没有牢固连结,仅用砂浆填充缝隙,因而不但整体性差,抗震性能低,而且经常出现缝隙开裂、渗水,给住户造成很大不便和心理压力。为解决上述问题,很多楼宇采用了现浇楼板(实心、空心)的方法。现浇楼板虽然解决了抗震和开裂等问题,但是工作量大、自重大、钢筋用量大,同时增加了柱和基础的荷载,很不经济。预制空心板适用跨度小、易裂缝、易渗漏,结构整体性差,只能是单向板使用,抗地震性能差、不能抵抗地基不均匀沉降等因素引起的变形,多用于多层、小跨度建筑,不能用于高层建筑。传统的现浇肋形梁板体系在板底露出很多主次梁或小肋梁,不美观,需吊顶,不能进行大开间分隔,不利于水电空调管线的安装。其梁降低了净空高度。顶板很薄,隔音差,此种肋形梁板体系不经济,使用功能差。虽然现在有些建筑施工中在使用密肋平板楼盖技术,但是由于预制构件的结构不合理,无法使用震动棒,导致在施工过程中存在着浇灌混凝土时存在空隙,或者不够密实,影响施工质量,同时在施工时需要大面积使用的模板,严重影响施工的速度,同时增加建筑成本。现行的现浇混凝土空心楼盖施工工艺方法,一般是在混凝土中预埋空腔构件,需在空腔构件的上部或下部,甚至上下部同时浇捣钢筋混凝土,空心率低、自重大,施工极不方便,未能真正解决好空心楼盖的施工工艺。At present, most buildings with brick-concrete structure and frame structure use prefabricated hollow slabs as floor slabs. This kind of floor slab has the advantages of fast construction speed and low cost. As a result, not only the integrity is poor and the seismic performance is low, but also cracks and water seepage often occur in the gaps, which cause great inconvenience and psychological pressure to the residents. In order to solve the above problems, many buildings have adopted the method of cast-in-place floor slabs (solid, hollow). Although the cast-in-place floor slab solves the problems of earthquake resistance and cracking, it is uneconomical due to its large workload, heavy self-heavy, large amount of steel bars, and increased loads on columns and foundations. Prefabricated hollow slabs are suitable for small spans, are prone to cracks and leakage, and have poor structural integrity. They can only be used as one-way slabs. They have poor seismic performance and cannot resist deformation caused by factors such as uneven settlement of the foundation. Construction, cannot be used for high-rise buildings. The traditional cast-in-place rib-shaped beam-slab system exposes many primary and secondary beams or small rib beams at the bottom of the slab, which is unsightly, requires a suspended ceiling, and cannot be separated by large bays, which is not conducive to the installation of water, electricity, and air-conditioning pipelines. Its beams reduce headroom. The roof is very thin, and the sound insulation is poor. This kind of rib-shaped beam-slab system is uneconomical and has poor performance. Although some buildings are now using the ribbed slab floor technology, due to the unreasonable structure of the prefabricated components, vibrating rods cannot be used, resulting in gaps in the construction process when pouring concrete, or not dense enough, affecting the construction quality. At the same time, large-area formwork is required during construction, which seriously affects the speed of construction and increases construction costs. The current construction method of cast-in-place concrete hollow floors generally pre-embeds the cavity components in the concrete, and needs to pour reinforced concrete on the upper or lower parts of the cavity components, or even the upper and lower parts at the same time. The hollow rate is low and the weight is heavy. Extremely inconvenient, can't really solve the construction technology of hollow floor.
【发明内容】 【Content of invention】
本发明的目的是提供一种施工时大大减少模板用量、同时能够满足施工质量要求增加施工速度的一种简便易行的施工方法。The purpose of the present invention is to provide a simple and easy construction method which greatly reduces the amount of formwork used during construction and can meet the requirements of construction quality and increase the construction speed at the same time.
为实现上述技术目的,本发明技术解决方案:一种现浇混凝土空心楼盖施工工艺方法,其特征在于:包括以下部分In order to achieve the above technical purpose, the technical solution of the present invention is a construction method of cast-in-place concrete hollow floor, which is characterized in that it includes the following parts
(1)空腔构件的制作,使用增强纤维砂浆或加筋混凝土制作长方体或者倒梯台形状构件,该构件中部具有空腔,并存放一定时间,(1) For the manufacture of cavity components, reinforced fiber mortar or reinforced concrete is used to make cuboid or inverted terrace-shaped components, which have a cavity in the middle and are stored for a certain period of time.
a、设模板制作上部开口的长方体或倒梯台形空腔构件主体,在制作时该空腔构件主体的时候,保证至少预留一个面开口部分;a. Set the template to make the main body of the cuboid or inverted terrace-shaped cavity component with the upper opening. When making the main body of the cavity component, at least one surface opening must be reserved;
b、据上述的空腔构件中预留的开口部分的形状,支设相应的模板并浇灌砂浆或加筋混凝土制作空腔构件的盖板部分;b. According to the shape of the opening part reserved in the above-mentioned cavity component, support the corresponding formwork and pour mortar or reinforced concrete to make the cover part of the cavity component;
c、在上述的空腔构件中的主体部分和盖板部中,至少其中一个部件的砂浆或混凝土凝结前,将上述的两部分进行组合,使用水泥砂浆等粘接,并进行养护后完成空腔构件的制作;c. Before the mortar or concrete of at least one part of the main body part and the cover part of the above-mentioned cavity component is set, the above two parts are combined, bonded with cement mortar, etc., and the cavity is completed after curing. Fabrication of cavity components;
(2)楼盖的施工,采用以下步骤,(2) The construction of the floor cover adopts the following steps,
a、支模,按照设计要求,在暗密肋楼盖的底部或者只在肋的底部支设模板,模板宽比肋底宽略宽;a. Support the formwork. According to the design requirements, the formwork is set at the bottom of the hidden ribbed floor or only at the bottom of the ribs. The width of the formwork is slightly wider than the width of the bottom of the ribs;
b、放线,通过在模板上画线用来精确定位肋的位置;b. Setting out the line, which is used to accurately locate the position of the rib by drawing a line on the template;
c、放置并绑扎肋中的钢筋或安放钢筋网片、型钢或其他受力材料,安装预埋件,并使上述的钢筋按照画线的位置呈正交或斜交状设置;c. Place and bind the steel bars in the ribs or place steel mesh, section steel or other stress-bearing materials, install embedded parts, and make the above-mentioned steel bars be arranged orthogonally or obliquely according to the position of the drawn line;
d、放空腔构件,在肋间空隙处按照设计要求放置空腔构件;d. Empty cavity components, and place cavity components in the intercostal space according to the design requirements;
e、注混凝土振捣,将网格状肋与空腔构件制成整体,之后进行养护、拆模,形成本发明的现浇混凝土空心楼盖。e. Injecting concrete and vibrating, making the grid-like ribs and cavity components integral, and then performing maintenance and form removal to form the cast-in-place concrete hollow floor of the present invention.
在进行所述的(1)步骤时,在预制空腔构件中设置加强筋。When performing the step (1), a reinforcing rib is provided in the prefabricated cavity member.
在进行所述(2)步骤时,安放空腔构件在网格状肋钢筋空隙中后,对空腔构件中的伸出的加强筋和肋中钢筋或钢进行定位绑扎或焊接。When carrying out the above (2) step, after placing the cavity component in the grid-like rib reinforcement space, perform positioning binding or welding on the protruding reinforcing rib in the cavity component and the reinforcing bar or steel in the rib.
在空腔构件中设置加强筋时,上述加强筋横竖成行设置,且加强筋在空腔构件的上表面或下表面或上、下表面同时设置,加强筋伸出空腔构件之外一段长度。When reinforcing ribs are arranged in the cavity member, the reinforcing ribs are arranged in horizontal and vertical rows, and the reinforcing ribs are arranged on the upper surface or the lower surface of the cavity member or both upper and lower surfaces, and the reinforcing ribs protrude out of the cavity member for a certain length.
在制作空腔构件过程中,在进行其中的步骤c之前,在空腔构件的空腔中设置与空腔形状相应的支撑件。In the process of manufacturing the cavity member, before performing step c, a support corresponding to the shape of the cavity is provided in the cavity of the cavity member.
现浇混凝土空心楼盖中是钢筋混凝土或钢混凝土。The cast-in-place concrete hollow floor is reinforced concrete or steel concrete.
本发明通过采用上述的技术解决方案,获得了以下的积极技术效果:通过采用长方体或者倒梯台形状的空腔构件,同时配合交叉密肋的方式,获得了在施工过程中节省了模板的用量和支模时间,提高了施工的速度,同时大幅降低了施工成本;通过采用将空腔构件上设有的钢筋与网格状肋中的钢筋固接的方式,使空腔构件和网格状肋构成整体,增加了楼盖的强度,同时简化了施工的工艺。The present invention obtains the following positive technical effects by adopting the above-mentioned technical solution: by adopting the cavity member in the shape of a cuboid or an inverted terrace, and at the same time cooperating with the way of intersecting dense ribs, the amount of formwork is saved in the construction process The construction speed is improved and the construction cost is greatly reduced at the same time; by adopting the method of fixing the steel bars on the cavity components with the steel bars in the grid ribs, the cavity The ribs form a whole, which increases the strength of the floor and simplifies the construction process.
【附图说明】 【Description of drawings】
图1为空腔构件的主视图;Fig. 1 is the front view of cavity member;
图2为空腔构件的侧视图;Figure 2 is a side view of a cavity member;
图3为空腔构件的仰视图;Fig. 3 is the bottom view of cavity member;
图4为空腔构件的俯视图;Figure 4 is a top view of a cavity member;
图5为具有网格状肋楼盖的俯视图;Figure 5 is a top view of a grid-shaped ribbed floor;
图6为具有网格状肋楼盖的剖视图。Fig. 6 is a cross-sectional view of a floor with lattice ribs.
【具体实施方式】 【Detailed ways】
下面结合附图对本发明进行进一步的说明:Below in conjunction with accompanying drawing, the present invention is further described:
如图1-4所示,图中所示的构件为混凝土制作,该构件上、下两端面呈矩形或者菱形,侧面为方形或者倒梯形,其中部为形状与其外形的形状相应的空腔。上端面4中设有加强筋1,该加强筋1位于混凝土中,沿水平方向平行设置。在强度要求较高的时候,上述的加强筋1可以呈十字型或者井字型有序排列,在构件的尺寸较小或者强度要求不高的情况下,也可不设加强筋1;在强度要求很高的情况下,其下表面2中可以同样设加强筋1。加强筋1的数量、强度及是否配置加强筋应按结构设计要求确定。从而使本发明的空腔构件的强度和刚度大大提高,同时,它具有结构简单、水密性好、重量轻、施工运输方便等特点。在空腔构件内有加强筋1或采用加强网或者两者的组合,加强筋1分别为钢筋、预应力钢筋、钢丝、钢纤维、纤维丝、束或其它增强筋,加强网分别为钢筋网、钢丝网、纤维网、无纺胶粘布网或其它增强布、网。这些筋、丝、网分别用于不同场合,形成的结构、形状、局部构造、受力特点也就不同,如钢筋承受主要作用力,丝、网主要承受局部作用力和防裂构造用。预应力钢筋可给结构底板预加应力,使结构底板强度更高,抗变形和裂缝能力更强。由于空腔构件与结构底板有加强筋或加强网,因此,整个空腔构件强度高,受力传力更合理,使用这种空腔构件浇注成暗肋无板式楼盖,能够吊挂和承载较大重量的物体。另外在制作上述的空腔构件时,还可将加强筋设置有露筋、露网或露束。这样露筋或露网能更好地提高空腔构件与现浇肋之间的粘结力,有效地防止现浇与预制结合界面开裂,有利于楼盖受力传力和协同受力,露筋、露网或露束所形成的结构、形状和效果不完全相同。As shown in Figure 1-4, the component shown in the figure is made of concrete, the upper and lower ends of the component are rectangular or diamond-shaped, the side is square or inverted trapezoidal, and the middle part is a cavity with a shape corresponding to its shape. A reinforcing
上述的空腔构件中,侧面3的厚度最好小于其上端面4和下表面2的厚度,这样可以更好的减轻整个空腔构件的重量。空腔构件的外表面为波纹状或齿状或拉毛或者其它形状的粗糙表面。这样,空腔构件在应用于楼板时,能更好地提高它与肋之间的粘结力。空腔构件为至少二层以上的层状结构,由一层胶结料一层布或网,再一层胶结料一层布或网再一层胶结料等多层叠合胶结组成,布或网至少一层以上。胶结料可为各种类型的水泥、树脂或有机或无机或混合物胶粘剂,也可适当掺加集料或填料。如图5和图6中所示,上述的空腔中还设有支撑件,支撑件的形状为十字型,支撑件的高度一般应当与空腔的内空高度相同,这样的设置可以使上、下表面通过支撑件的作用,共同承受压力,防止将上表面压破。支撑件由增强纤维水泥砂浆、加强混凝土、木材、有机化合物或者其他材料制成。在空腔构件的尺寸较大或者要求强度较高的时候,可以使用井字型的支撑件,在空腔构件尺寸较小或者强度要求低的情况下,可以使用一字型支撑或者不使用支撑件。另外还有一种空腔的充填方式,空腔内部分或全部填充或粘贴泡沫塑料、膨胀珍珠岩、膨胀蛭石、发泡或加气轻质砼、岩棉、矿棉或者玻璃棉等轻质材料。这样空腔构件具有较好的保温与隔热和隔声性能,不同材料的构造其作用和功能不同,可根据实际设计选用不同的充填方式。空腔构件上还可预留有穿线管的孔洞或预埋有穿线的套管,这样更方便网线的布置与施工。In the cavity component mentioned above, the thickness of the
以下为上述的空腔构件的制作过程,首先,支设模板,模板的支设一般采用带有铰链连接的活动式模板,即以制作在空腔构件的下底面的模板上,通过铰链连接其他四个侧面模板,上述的模板在使用时呈开口箱状,在其侧面及下底面部分浇灌砂浆或混凝土层,该层的厚度由设计需求而定,使其中部形成空腔结构。空腔构件的上表面部分单独制作,根据设计要求铺设加强筋,浇灌砂浆或混凝土制成平板状,其中设置的加强筋露出构件外一定长度。待上述的两部分箱体,保证其中之一处于半干状态时,进行组合,在组合时还可结合处添加水泥砂浆,使其粘接的更牢固。在箱体要求强度较高时,在进行组合前,还需在空腔中安放支撑件,进一步提高空腔构件的强度。最后进行养护后,即完成空腔构件整体的制作。The following is the manufacturing process of the above-mentioned cavity components. First, the formwork is supported. The support of the formwork generally adopts a movable formwork with hinge connection, that is, it is made on the formwork on the lower bottom of the cavity component and connected to other parts through hinges. Four side formworks, the above-mentioned formwork is in the shape of an open box when used, and a mortar or concrete layer is poured on the side and lower bottom of the formwork. The thickness of the layer is determined by the design requirements, so that the middle part forms a cavity structure. The upper surface of the cavity component is made separately, and reinforcing ribs are laid according to the design requirements, and then poured with mortar or concrete to form a flat plate, wherein the reinforcing ribs are exposed to a certain length outside the component. When the above-mentioned two parts of the box body are guaranteed to be in a semi-dry state, they are combined. During the combination, cement mortar can also be added to the joint to make it more firmly bonded. When the strength of the box is required to be high, it is necessary to place supports in the cavity before assembly to further increase the strength of the cavity components. Finally, after curing, the overall fabrication of the cavity component is completed.
如图5和图6所示,本发明中的空腔构件的使用过程。如图6,上述的空腔构件放置在大小和尺寸与空腔相应的网状密肋中,上述肋内部设有钢筋8。楼盖的施工工艺过程一般为,首先,根据设计要求,确定密肋的间距、断面、配筋,通过这些数据确定空腔构件的尺寸,所用的加强筋数量和加强筋的布置,支撑件的尺寸和强度等数据,制作相应的空腔构件。As shown in Fig. 5 and Fig. 6, the use process of the cavity member in the present invention. As shown in Fig. 6, the above-mentioned cavity member is placed in a mesh-shaped dense rib whose size and size correspond to the cavity, and a
其过程为首先在施工现场支设模板,该模板的支设只在网格状肋的下方支设即可,因浇灌混凝土过程中只在网格肋部分中浇灌,所以不必象一般施工中楼盖下方全部支设模板,模板的支设方法与传统的施工方法中相同。在模板支设好之后,开始放线的工序;放线依据设计时肋的位置和分布进行,画线主要是确定肋的准确位置;然后按照放线的位置安装肋的钢筋或型钢,放置空腔构件在网格空隙中,在放置空腔构件的过程中,可以将空腔构件上伸出的加强筋,固接在网格状肋中的钢筋或钢上,具体可使用焊接、绑扎等方式固接。将空腔构件中的加强筋与肋中的钢筋固接在一起,使浇注后的楼盖形成一个整体,增加楼盖的强度和刚度,同时方便浇注过程中,由于振捣混凝土而产生的错位现象;再进行混凝土的浇灌,并进行振捣,最后进行养护。The process is to first set up the formwork on the construction site, and the support of the formwork can only be set up under the grid-shaped ribs. Because the concrete is only poured in the grid ribs during the pouring process, it is not necessary to pour concrete like a general construction middle building. Formwork is all supported under the cover, and the formwork support method is the same as in the traditional construction method. After the formwork is supported, start the process of setting out the line; setting out the line is carried out according to the position and distribution of the rib at the time of design, and drawing the line is mainly to determine the exact position of the rib; The cavity member is in the grid space. During the process of placing the cavity member, the reinforcing rib protruding from the cavity member can be fixed to the steel bar or steel in the grid rib. Specifically, welding, binding, etc. can be used. fixed way. The reinforcing ribs in the cavity member and the steel bars in the ribs are fixed together, so that the poured floor forms a whole, increases the strength and rigidity of the floor, and at the same time facilitates the dislocation caused by vibrating concrete during the pouring process Phenomenon; then pour the concrete, vibrate it, and finally maintain it.
通过上述方法制作的楼盖,是采用大量的预制好的空腔构件,结合网格状肋中的少量现浇混凝土,制作楼盖,所形成的楼盖中楼板是由空腔构件上下两个端面构成,实际上是通过预制构件本体构成的无板式空心楼盖。由于本发明中的混凝土浇灌,只在网格状肋中使用,因此其浇灌过程简单,施工难度低,同时不会产生空隙而影响施工质量。最后进行养护和拆模板工作。通过采用上述施工方法所制作的楼盖,不但节约成本,而且其主要的特点在于节约层高,浇灌楼盖的厚度与空腔的厚度相同、底面平整美观,同时施工过程简单,现场浇灌混凝土量较少,还可保证很高的使用强度,完全满足正常的设计和使用要求。The floor made by the above method is to use a large number of prefabricated cavity components, combined with a small amount of cast-in-place concrete in the grid ribs, to make the floor, and the floor in the formed floor is composed of two upper and lower cavity components. The end face is actually a plateless hollow floor formed by the prefabricated component body. Since the concrete pouring in the present invention is only used in the grid-shaped ribs, the pouring process is simple, the construction difficulty is low, and at the same time, no voids will be generated to affect the construction quality. Finally, maintenance and demolition of the formwork are carried out. The floor made by using the above construction method not only saves cost, but also its main feature is to save the floor height, the thickness of the poured floor is the same as the thickness of the cavity, the bottom surface is flat and beautiful, and the construction process is simple, and the amount of concrete poured on site Less, but also to ensure high strength, fully meet the normal design and use requirements.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNB2004100775942A CN100395417C (en) | 2004-12-27 | 2004-12-27 | A construction method of cast-in-situ concrete hollow floor |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNB2004100775942A CN100395417C (en) | 2004-12-27 | 2004-12-27 | A construction method of cast-in-situ concrete hollow floor |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN1796680A CN1796680A (en) | 2006-07-05 |
| CN100395417C true CN100395417C (en) | 2008-06-18 |
Family
ID=36817976
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNB2004100775942A Expired - Lifetime CN100395417C (en) | 2004-12-27 | 2004-12-27 | A construction method of cast-in-situ concrete hollow floor |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN100395417C (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101761229B (en) * | 2009-12-14 | 2012-02-01 | 山东万鑫建设有限公司 | Method for constructing hollow overlapped rib plate support system |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101644082B (en) * | 2009-08-21 | 2011-08-24 | 贵州金三利科技建材有限公司 | Assembling method of gypsum evacuated mould |
| CN103015598B (en) * | 2012-12-20 | 2016-01-06 | 湖北大成空间科技股份有限公司 | A kind of construction method of energy-conservation close rib cavity floor |
| CN103015597B (en) * | 2012-12-20 | 2016-05-11 | 湖北大成空间科技股份有限公司 | A kind of construction method of energy-conservation close rib cavity floor |
| CN103243848B (en) * | 2013-05-13 | 2015-09-30 | 王惠滨 | The construction technology of cast-in-place concrete floor or superstructure and the spring support member of employing |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB1364118A (en) * | 1970-11-27 | 1974-08-21 | Lemming Pedersen Og Eriksson R | Prefabricated deck elemenst of reinforced concrete |
| CN2157243Y (en) * | 1993-05-22 | 1994-02-23 | 吉首市建筑建材科学研究所 | Small block combined floor slab |
| CN2160693Y (en) * | 1993-03-20 | 1994-04-06 | 于少华 | Shuttering member |
| CN1348040A (en) * | 2001-11-23 | 2002-05-08 | 邱则有 | Cavity member for floor slab with hidden and dense ribs |
| CN2522492Y (en) * | 2002-01-28 | 2002-11-27 | 邱则有 | Board-rib combined steel reinforced concrete hollow floor |
-
2004
- 2004-12-27 CN CNB2004100775942A patent/CN100395417C/en not_active Expired - Lifetime
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB1364118A (en) * | 1970-11-27 | 1974-08-21 | Lemming Pedersen Og Eriksson R | Prefabricated deck elemenst of reinforced concrete |
| CN2160693Y (en) * | 1993-03-20 | 1994-04-06 | 于少华 | Shuttering member |
| CN2157243Y (en) * | 1993-05-22 | 1994-02-23 | 吉首市建筑建材科学研究所 | Small block combined floor slab |
| CN1348040A (en) * | 2001-11-23 | 2002-05-08 | 邱则有 | Cavity member for floor slab with hidden and dense ribs |
| CN2522492Y (en) * | 2002-01-28 | 2002-11-27 | 邱则有 | Board-rib combined steel reinforced concrete hollow floor |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101761229B (en) * | 2009-12-14 | 2012-02-01 | 山东万鑫建设有限公司 | Method for constructing hollow overlapped rib plate support system |
Also Published As
| Publication number | Publication date |
|---|---|
| CN1796680A (en) | 2006-07-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN114108917B (en) | Height-adjustable assembly type composite floor slab construction method | |
| CN202012136U (en) | U-shaped closed rib connection structure for horizontal seam of assembling shear wall structure | |
| CN106968381B (en) | Prefabricated precast shear wall and composite panel joints connected by combined grouting sleeves | |
| CN103046665B (en) | Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof | |
| CN205776348U (en) | A kind of overlapping monoblock type pipe gallery prefabricated assembly structural | |
| CN110670770A (en) | Combined structure and construction method of solid shear wall and laminated plate edge member | |
| CN105804292A (en) | Environment-friendly and energy-saving integrated cast-in-situ lightweight concrete wall and construction method thereof | |
| CN108301531A (en) | Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node | |
| CN104878836A (en) | Prefabricated house and construction method thereof | |
| CN1329601C (en) | A cavity formwork member | |
| CN204645253U (en) | A kind of prefabricated house | |
| CN207314655U (en) | Fill concrete wallboard in a kind of prefabricated thermal insulation | |
| CN112982692A (en) | One-way superimposed sheet joint connecting structure and construction method | |
| CN113668730A (en) | An assembled mixed recycled aggregate concrete composite wallboard and preparation method thereof | |
| CN216475803U (en) | A Novel Prefabricated Floor Structure Applied to Shear Wall System | |
| CN100395417C (en) | A construction method of cast-in-situ concrete hollow floor | |
| CN204435616U (en) | Truss bars double layer fibre gypsum plank, non-dismantling formwork wall body structure | |
| CN112538915A (en) | Precast concrete wallboard and manufacturing method thereof | |
| CN218758102U (en) | Energy-conserving integration assembled shear force wall | |
| CN105888282A (en) | Seismic strengthening structure and method for enlarging opening of substation masonry wall | |
| CN201103182Y (en) | PCM cast-in-situ reinforced concrete hidden rib non-plate internal mold | |
| CN211286164U (en) | A self-compacting recycled block concrete composite shear wall | |
| CN205663131U (en) | Atress wallboard | |
| CN219753696U (en) | Skeleton structures and prefabricated walls | |
| CN117231029B (en) | Outer frame for reinforcing and reforming precast slab brick concrete structure and construction method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Assignee: HUBEI DACHENG SPACE BUILDING TECHNOLOGY CO.,LTD. Assignor: Fu Li Xie Contract record no.: 2010420000051 Denomination of invention: Construction technique method by using hollow cover of storied building fabricated from cast in-site reinforcing steel bar concrete Granted publication date: 20080618 License type: Exclusive License Open date: 20060705 Record date: 20100519 |
|
| ASS | Succession or assignment of patent right |
Owner name: HUBEI SYNTHETIC SPACE CONSTRUCTION TECHNOLOGY CO., Free format text: FORMER OWNER: FU LIXIE Effective date: 20120203 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 433300 JINGZHOU, HUBEI PROVINCE TO: 430074 WUHAN, HUBEI PROVINCE |
|
| TR01 | Transfer of patent right |
Effective date of registration: 20120203 Address after: Luo East Lake Development Zone 430074 Hubei city of Wuhan Province Yu Road B Optics Valley International Plaza, No. 889 room 2401 Patentee after: HUBEI DACHENG SPACE BUILDING TECHNOLOGY CO.,LTD. Address before: 433300 No. 8, Lane No. 2, Rong town, Jianli County, Hubei Province Patentee before: Fu Li Xie |
|
| EC01 | Cancellation of recordation of patent licensing contract |
Assignee: HUBEI DACHENG SPACE BUILDING TECHNOLOGY CO.,LTD. Assignor: Fu Li Xie Contract record no.: 2010420000051 Date of cancellation: 20140217 |
|
| EC01 | Cancellation of recordation of patent licensing contract | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Construction technique method by using hollow cover of storied building fabricated from cast in-site reinforcing steel bar concrete Effective date of registration: 20140219 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI DACHENG SPACE BUILDING TECHNOLOGY CO.,LTD. Registration number: 2014990000109 |
|
| PLDC | Enforcement, change and cancellation of contracts on pledge of patent right or utility model | ||
| C56 | Change in the name or address of the patentee |
Owner name: HUBEI SYNTHETIC SPACE TECHNOLOGY CO., LTD. Free format text: FORMER NAME: HUBEI SYNTHETIC SPACE BUILDING TECHNOLOGY CO., LTD. |
|
| CP01 | Change in the name or title of a patent holder |
Address after: Luo East Lake Development Zone 430074 Hubei city of Wuhan Province Yu Road B Optics Valley International Plaza, No. 889 room 2401 Patentee after: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Address before: Luo East Lake Development Zone 430074 Hubei city of Wuhan Province Yu Road B Optics Valley International Plaza, No. 889 room 2401 Patentee before: HUBEI DACHENG SPACE BUILDING TECHNOLOGY CO.,LTD. |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20141225 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI DACHENG SPACE BUILDING TECHNOLOGY CO.,LTD. Registration number: 2014990000109 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Construction technique method by using hollow cover of storied building fabricated from cast in-site reinforcing steel bar concrete Effective date of registration: 20141226 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Registration number: 2014990001137 |
|
| PLDC | Enforcement, change and cancellation of contracts on pledge of patent right or utility model | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20151228 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Registration number: 2014990001137 |
|
| PLDC | Enforcement, change and cancellation of contracts on pledge of patent right or utility model | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Construction technique method by using hollow cover of storied building fabricated from cast in-site reinforcing steel bar concrete Effective date of registration: 20151230 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Registration number: 2015420000035 |
|
| PLDC | Enforcement, change and cancellation of contracts on pledge of patent right or utility model | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20161228 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Registration number: 2015420000035 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Construction technique method by using hollow cover of storied building fabricated from cast in-site reinforcing steel bar concrete Effective date of registration: 20161229 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Registration number: 2016420000061 |
|
| PLDC | Enforcement, change and cancellation of contracts on pledge of patent right or utility model | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20181023 Granted publication date: 20080618 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HUBEI SYNTHETIC SPACE TECHNOLOGY CO.,LTD. Registration number: 2016420000061 |
|
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20080618 |
