CN100381830C - 相量测量装置(pmu)现场校验方法 - Google Patents

相量测量装置(pmu)现场校验方法 Download PDF

Info

Publication number
CN100381830C
CN100381830C CNB2005101104051A CN200510110405A CN100381830C CN 100381830 C CN100381830 C CN 100381830C CN B2005101104051 A CNB2005101104051 A CN B2005101104051A CN 200510110405 A CN200510110405 A CN 200510110405A CN 100381830 C CN100381830 C CN 100381830C
Authority
CN
China
Prior art keywords
pmu
tester
error
data
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2005101104051A
Other languages
English (en)
Other versions
CN1760686A (zh
Inventor
潘勇伟
徐晨亮
王洪青
奚国富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Nanri Industrial Co., Ltd.
Shanghai Rui Hao Information Technology Co., Ltd.
Original Assignee
SHANGHAI NANRI INDUSTRIAL Co Ltd
HUADONG POWER INFORMATION ENGINEERING TECH Co Ltd SHANGHAI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI NANRI INDUSTRIAL Co Ltd, HUADONG POWER INFORMATION ENGINEERING TECH Co Ltd SHANGHAI filed Critical SHANGHAI NANRI INDUSTRIAL Co Ltd
Priority to CNB2005101104051A priority Critical patent/CN100381830C/zh
Publication of CN1760686A publication Critical patent/CN1760686A/zh
Application granted granted Critical
Publication of CN100381830C publication Critical patent/CN100381830C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Data Exchanges In Wide-Area Networks (AREA)
  • Monitoring And Testing Of Transmission In General (AREA)

Abstract

本发明公开了一种用于同步相量测量装置(PMU)进行现场校验的方法,用一台PMU测试仪和一台装有模拟主站通信软件的PC机,被测PMU装置和PMU测试仪接入相同的交流信号源;被测PMU装置和PMU测试仪分别接收各自的GPS卫星时钟同步信号;PC机通过数据局域网同时接收被测PMU装置和PMU测试仪的实时相量数据;对来自被测PMU装置和PMU测试仪的实时相量数据,按各自数据报文携带的GPS时标进行时间同步排序,再对一段时间内各相同时刻的两组数据进行误差比对、均方根误差计算;给出均方根误差和误差置信区间。

Description

相量测量装置(PMU)现场校验方法
技术领域
本发明公开了一种用于相量测量装置(PMU)进行现场校验的方法,该方法采用被测PMU的测量数据与PMU测试仪的标准测量数据同步对比的误差分析。本发明主要应用于广域测量系统(WAMS)的工程建设,属于电力系统及其自动化领域。
背景技术
为了确保区域电网安全稳定运行,国内外各大电网加快了广域测量系统(WAMS)和相量测量装置(PMU)的应用,在一些枢纽变电站及大型发电厂安装PMU装置进行同步相量测量,向WAMS主站系统传送动态相量信息,WAMS主站根据PMU的测量信息对电网实施动态稳定监控。在实际工程应用中,为了使现场的PMU能在保证要求的的情况下运行,必须对PMU的各项性能指标进行测试、校验。而目前的校验方法一般局限在比较好的实验室条件下。
PMU装置的现场校验,包括实时数据精度的校验(额定频率下精度校验、变频率下的精度校验、谐波条件下精度校验、三相不平衡状态下精度校验、功率因数变化条件下精度校验),实时记录测试,通信性能测试(数据帧上传速度、报文平均间隔、帧头出错率、帧长出错率、CRC校验出错率检测)、通信规约的正确性检验、GPS时钟精度校验等部分。
PMU装置采用4800-10000点/秒的采样速率对电流、电压进行采样,由快速富利叶变换(FFT)算法得到的动态相量数据按每秒25-100帧速率传输。电网的相量数据随着时间的变化而快速变化,传统的校验装置或交流采样变送器等不能提供动态相量数据,只能提供电网稳态的幅值数据。长期以来,大量PMU现场性能测试仅检验其幅值精度,其他指标只能在比较好的实验室条件下进行,尤其对其中关键性的卫星时间同步精度、机组内电势功角和线路相量、通信规约和传输性能等缺乏直接的测试手段,一般通过系统联网后,由主站粗略核对相角测量的正确性,故只能对其定性,不能进行定量的误差分析,对分布在不同厂站的PMU采集的大量电网动态数据,难以按照技术标准确定测量精度和鉴别超差数据,严重影响技术评价、竣工验收和运行维护。
发明内容
为解决前述存在的问题,本发明提供一种对同步相量测量装置(PMU)进行现场校验的方法,该方法采用被测数据与标准测量数据同步比对的方法对现场PMU进行在线校验,该方法包括一台PMU测试仪和一台模拟主站的PC机,该方法的校验步骤是:
1)将现场输入被测PMU装置的电压信号并连接入、电流信号串联接入PMU测试仪,使PMU测试仪和被测PMU装置获得同源交流电压和电流信号;
2)被测PMU装置和PMU测试仪分别接收各自的GPS卫星时钟同步信号,使同步相量的测量误差包含各自GPS卫星时钟和同步的误差;
3)载有模拟主站通信软件的PC机,通过数据局域网同时接收被测PMU装置和PMU测试仪的实时相量数据;
4)对来自被测PMU装置和PMU测试仪的实时相量数据,按各自数据报文携带的GPS时标进行时间同步排序,再对一段时间内各相同时刻的两组数据进行误差比对、均方根误差计算;
5)采用正态分布误差统计法,分析被测PMU装置的数据误差,给出均方根误差和误差置信区间。
6)由装载模拟主站通信软件的PC机检测被测PMU装置的通信报文和传输过程与标准通信规约的符合性,还可对通信流量的平稳性、数据桢的出错率、命令管道的正确响应率等进行测试和分析。
附图说明
附图是本发明的被测PMU装置、PMU测试仪和模拟主站的PC机之间信息交换示意图。
具体实施方式
附图揭示了本发明的被测PMU装置、PMU测试仪和模拟主站的PC机之间信息交换示意图;装有模拟主站通信软件的PC机,通过数据局域网同时接收被测PMU装置和PMU测试仪的实时相量数据;按各自数据报文携带的GPS时标进行时间同步排序,再对一段时间内各相同时刻的数千点采样的两组数据,进行误差比对、均方根误差计算。
误差分析采用绝对误差最大值、均方根误差、随机误差分布:
绝对误差最大值: err max = MAX ( | x i - x - i | )
均方根误差: err sqn = Σ i = 1 N ( x i - x - i ) 2 N
随机误差分布:
(1)正态分布的概率密度函数: f ( x ) = 1 2 π e - ( x - x - ) 2 2 σ 2 .
(2)标准正态分布计算: φ ( u ) = 1 2 π ∫ - ∞ u e - x 2 2 dx ( u ≥ 0 ) .
(3)其中 σ = Σ i = 1 n ( x i - x - ) 2 n - 1 , 其中 x - = Σ i = 1 n x i n . x是误差值。
(4)根据测量数据,求出误差值,根据给定的置信度,查正态分布表或者根据概率密度函数计算数值积分,计算误差区间。查表和数值积分值设为δ。
(5)取置信区间为 [ x - - δ * σ , x - + δ * σ ]

Claims (1)

1.一种相量测量装置PMU现场校验方法,包括一台PMU测试仪和一台模拟主站的PC机,其特征在于:该方法的校验步骤是:
1)将现场输入被测PMU的电压信号并连接入、电流信号串联接入PMU测试仪,使PMU测试仪和被测PMU获得同源交流电压和电流信号;
2)被测PMU和PMU测试仪分别接收各自的GPS卫星时钟同步信号,使同步相量的测量误差包含各自GPS卫星时钟和同步的误差;
3)载有模拟主站通信软件的PC机,通过数据局域网同时接收被测PMU和PMU测试仪的实时相量数据;
4)对来自被测PMU和PMU测试仪的实时相量数据,按各自数据报文携带的GPS时标进行时间同步排序,再对一段时间内各相同时刻的两组数据进行误差比对、均方根误差计算;
5)采用正态分布误差统计法,分析被测PMU的数据误差,给出均方根误差和误差置信区间。
CNB2005101104051A 2005-11-16 2005-11-16 相量测量装置(pmu)现场校验方法 Expired - Fee Related CN100381830C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005101104051A CN100381830C (zh) 2005-11-16 2005-11-16 相量测量装置(pmu)现场校验方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005101104051A CN100381830C (zh) 2005-11-16 2005-11-16 相量测量装置(pmu)现场校验方法

Publications (2)

Publication Number Publication Date
CN1760686A CN1760686A (zh) 2006-04-19
CN100381830C true CN100381830C (zh) 2008-04-16

Family

ID=36706832

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005101104051A Expired - Fee Related CN100381830C (zh) 2005-11-16 2005-11-16 相量测量装置(pmu)现场校验方法

Country Status (1)

Country Link
CN (1) CN100381830C (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101242231B (zh) * 2008-03-03 2011-06-01 电子科技大学 面向电力系统同步相量测量的时钟同步装置
CN101592695B (zh) * 2009-04-22 2010-12-01 北京四方继保自动化股份有限公司 同步相量测量单元pmu的动态性能测试方法
CN102590675B (zh) * 2012-02-28 2014-07-23 江西省电力科学研究院 多节点同步仿真测试方法
CN103809190A (zh) * 2012-11-15 2014-05-21 中国科学院沈阳自动化研究所 一种卫星校准源检测装置及实现方法
CN106771599B (zh) * 2016-11-21 2019-08-20 国网四川省电力公司电力科学研究院 智能变电站同步相量测量装置的测试装置
CN107942167A (zh) * 2017-11-22 2018-04-20 国网四川省电力公司电力科学研究院 智能变电站同步相量测量装置主子站测试系统及方法
CN111668932A (zh) * 2020-06-11 2020-09-15 国网山东省电力公司电力科学研究院 一种变电站全站pmu装置的实验室同步测试系统及方法
CN112532472B (zh) * 2020-11-09 2022-11-04 广东电网有限责任公司广州供电局 一种相量测量单元上传延时的测试方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1477401A (zh) * 2003-07-18 2004-02-25 清华大学 高精度的同步相量测量方法
US6754597B2 (en) * 2000-03-10 2004-06-22 Abb Schweiz Ag Method and device for assessing the stability of an electric power transmission network

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6754597B2 (en) * 2000-03-10 2004-06-22 Abb Schweiz Ag Method and device for assessing the stability of an electric power transmission network
CN1477401A (zh) * 2003-07-18 2004-02-25 清华大学 高精度的同步相量测量方法

Also Published As

Publication number Publication date
CN1760686A (zh) 2006-04-19

Similar Documents

Publication Publication Date Title
Song et al. Smart sensors and standard-based interoperability in smart grids
CN100381830C (zh) 相量测量装置(pmu)现场校验方法
US20200309829A1 (en) On-line monitoring system for the performance of the measurement equipment in the entire power grid based on wide-area synchronous measurement
US9784799B2 (en) Multi-node synchronous on-site test method
CN102928810A (zh) 一种数字电能表准确度评估系统及其方法
CN201886095U (zh) 一种合并单元的测试装置
CN102435912B (zh) 电网中故障扰动点的定位方法
CN208188313U (zh) 一种具有内置监控基表的电能表检定装置
CN203069774U (zh) 一种数字电能表准确度评估系统
CN106443326A (zh) 配电网故障定位装置测试系统及测试方法
CN105301552A (zh) 电能计量装置在线校验系统
CN106921522A (zh) 智能变电站网络报文记录分析装置联网信息模型检测装置
CN105116246A (zh) 一种电网运行保护实时在线分析方法
CN110187193B (zh) 基于全站电压互感器稳定性判断的介损监测系统及方法
CN106526317A (zh) 同步相量测量单元的相量测量精度评估方法及评估装置
CN102621512A (zh) 一种合并单元守时性能的动态模拟测试方法
Music et al. Integrated power quality monitoring system and the benefits of integrating smart meters
CN106569165A (zh) 一种电子式电能表计量性能远程在线检测系统
CN202939299U (zh) 一种基于同步脉冲输出电源的电子式互感器校验装置
Ananthan et al. Model-based approach integrated with fault circuit indicators for fault location in distribution systems
CN103616653B (zh) 一种电能质量监测终端对时与时钟精度测试系统及其方法
CN112162226B (zh) 一种量测特性分离测试装置、方法及终端设备
CN106199489A (zh) 实验室复现式数字化电能计量设备远程校准系统及方法
CN103344937A (zh) 智能电能表功耗检测设备及检测方法
CN117330864A (zh) 一种分支线路线损智能测量方法及装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI RUI HAO INFORMATION TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: SHANGHAI EAST CHINA ELECTRIC POWER INFORMATION ENGINEERING TECHNOLOGY CO., LTD.

CP03 Change of name, title or address

Address after: Room 202, No. 3, GuangYue Road, GuangYue Road, Shanghai: 200083

Co-patentee after: Shanghai Nanri Industrial Co., Ltd.

Patentee after: Shanghai Rui Hao Information Technology Co., Ltd.

Address before: No. 1102, room 180, Tianjin Road, Shanghai: 200001

Co-patentee before: Shanghai Nanri Industrial Co., Ltd.

Patentee before: Shanghai Huadong Electric Power Information Engineering Technology Co., Ltd.

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080416

Termination date: 20101116