CH692207A5 - Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe - Google Patents

Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe Download PDF

Info

Publication number
CH692207A5
CH692207A5 CH146497A CH146497A CH692207A5 CH 692207 A5 CH692207 A5 CH 692207A5 CH 146497 A CH146497 A CH 146497A CH 146497 A CH146497 A CH 146497A CH 692207 A5 CH692207 A5 CH 692207A5
Authority
CH
Switzerland
Prior art keywords
shaft
base layer
shaft collar
collar
height adjustment
Prior art date
Application number
CH146497A
Other languages
German (de)
Inventor
Peter Neuweiler
Original Assignee
Peter Neuweiler
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Peter Neuweiler filed Critical Peter Neuweiler
Priority to CH146497A priority Critical patent/CH692207A5/en
Publication of CH692207A5 publication Critical patent/CH692207A5/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers
    • E02D29/1409Covers for manholes or the like; Frames for covers adjustable in height or inclination

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The equipment for installation of shaft covers in road construction incorporates a height adjustment device (7) laid on the upper edge of a shaft pipe (1). A shaft collar (2) is installed on the height adjustment device. Where necessary, a casing (11,12) is incorporated, extending from the inside of the shaft pipe to the inside of the shaft collar, which between a basic layer (2) surrounding the shaft pipe fills out with at least one support layer (8,9) an intermediate space between a lining (10) and the shaft collar. The height adjustment device has several adjustable distance holders, preferably in the form of adjustment screws.

Description

       

  



  Die Erfindung bezieht sich auf ein Verfahren zum Einsetzen von Schachtabdeckungen insbesondere im Strassenbau nach dem Oberbegriff des Anspruchs 1 sowie auf eine Vorrichtung zum Durchführen eines solchen Verfahrens nach dem Oberbegriff des Anspruchs 3. 



  Bei einem aus der Praxis bekannten Verfahren wird auf den oberen Rand der Schachtröhre sowie der die Schachtröhre umgebenden Basisschicht eine so genannte Facettenschicht aus Beton aufgebracht. Auf diese Facettenschicht wird der Schachtkragen aufgelegt und so weit in Richtung auf die Schachtröhre in die Facettenschicht gepresst, bis der Schachtkragen passgenau eingesetzt ist, d.h. die Oberkante des auf den Schachtkragen aufgelegten Deckels mit der Oberkante des Belages fluchtet. Anschliessend wird etwa bis zur halben Höhe des Schachtkragens eine untere Tragschicht, in aller Regel eine so genannte Verdämmschicht, und darauf eine obere Tragschicht, die so genannte Heiss-Misch-Tragschicht, aufgebracht, deren Oberkante mit derjenigen des Belages und des Deckels fluchtet. 



  Daraus folgt, dass sich bei der bekannten Vorrichtung eine Zwischenschicht, nämlich die vorgenannte Facettenschicht, zwischen der Schachtröhre und der Basisschicht auf der einen Seite und dem Schachtkragen auf der anderen Seite befindet. 



  Nachteilig ist das vorgenannte Verfahren vor allem bei Strassen mit hohem Gefälle, da die Facettenschicht parallel zur Neigung der Strasse aufzubringen ist. Probleme können sich bei dem vorgenannten Verfahren auch dann ergeben, wenn der Schachtkragen zu weit in die Facettenschicht hineingepresst wurde. In diesem Fall ist der Schachtkragen wieder anzuheben und der beim Anheben sich ergebende Zwischenraum zwischen dem Schachtkragen und der Facettenschicht mit weiterem Material aufzufüllen. Diese Vorgehensweise ist zeitaufwändig und damit teuer. Um die Lage eines fehlausgerichteten Schachtkragens noch ändern zu können, wurde dem Beton der Facettenschicht üblicherweise ein die Verfestigung des Betons verzögerndes Mittel beigemischt. Dies hat zwar zur Folge, dass die Lage des Schachtkragens über einen längeren Zeitraum verändert werden kann.

   Dies hat aber auch zur Folge, dass sich die Facettenschicht nur langsam verfestigt und damit die Strasse nur mit einer Zeitverzögerung wieder befahrbar ist. 



  Bei dem bekannten Verfahren kann auch eine Verschalung verwendet werden. Diese besteht üblicherweise aus einem gebogenen Band, dessen Enden durch einen Steg oder Bügel zusammengehalten werden. Der Durchmesser des gebogenen Bandes kann mithilfe einer Spannschraube eingestellt werden. Bei handelsüblichen Bändern kann die Spannschraube und damit der Durchmesser des etwa zylindrisch geformten Bandes nicht so stark verstellt werden, dass eine solche Verschalung bei Schachtkragen mit in den Innenraum einragenden Noppen nachträglich wieder entfernt werden kann. Insofern wird die vorbeschriebene Verschalung überwiegend bei Schachtkrägen ohne Noppen verwendet.

   Bei Schachtkrägen mit Noppen erfolgt das Ausgiessen des zwischen der Schachtröhre, der Basisschicht, dem Belag und dem Schachtkragen angeordneten Zwischenraums üblicherweise in mehreren Schritten, was die für das Einsetzen von Schachtabdeckungen erforderliche Zeit zusätzlich verlängert. 



  Ferner sind aus den DE-A1-2 533 289, CH-A5-677 684, US-A-5 513 926 und DE-A1-4 400 846 Schachtabdeckungen bekannt, bei denen der Schachtkragen auch mittels Abstandsringen unterschiedlicher Höhe passgenau einsetzbar ist. Gemäss den EP-A1-0 231 454, EP-A20 311 884, DE-A1-4 230 006, EP-A1-0 485 649, US-A-5 412 911 und US-A-5 344 253 sind Schachtabdeckungen mit Schraubbolzen aufweisenden Höheneinstellvorrichtungen bekannt. 



  Ein Verfahren und eine Vorrichtung der eingangs erwähnten Art sind aus der CH-A5-609 119 bekannt, gemäss welcher als Höheneinstellvorrichtung am Schachtkragen vorgesehene Gewindelöcher verwendet werden, in die auf der Schachtröhre abstützbare Stell schrauben passen. Nachteilig bei den aus dem Stand der Technik bekannten Verfahren und Vorrichtungen ist, dass diese aufwändig und teuer sind, da zumindest der Schachtkragen speziell an die jeweilige Höheneinstellvorrichtung anzupassen ist, und dass die lediglich auf Schraubbolzen ruhenden Schachtabdeckungen in aller Regel nicht mit schweren Fahrzeugen befahrbar sind. 



  Der Erfindung liegt die Aufgabe zu Grunde, ein Verfahren der eingangs erwähnten Art zu schaffen, mit dem Schachtabdeckungen wirtschaftlicher eingesetzt und auch mit schweren Fahrzeugen befahren werden können. Der Erfindung liegt auch die Aufgabe zu Grunde, eine Vorrichtung zum Durchführen des Verfahrens anzugeben. 



  Diese Aufgabe wird verfahrensseitig durch die Merkmale des Patentanspruchs 1 und vorrichtungsseitig durch die Merkmale des Patentanspruchs 3 gelöst. 



  Die erfindungsgemässen Vorteile sind vor allem darin zu sehen, dass die Höheneinstellvorrichtung keine Anpassung/Änderung herkömmlicher Schachtabdeckungen erfordert und die Ausrichtung des Schachtkragens mithilfe der Distanzhalter schnell und unproblematisch erfolgen kann. Auch ein nachträgliches Verändern der Lage des Schachtkragens ist mit wenigen Handgriffen und damit geringen Zeitverlusten durchführbar. Die Verschalung wird erst dann angebracht, wenn sich der Schachtkragen relativ zum Belag und zur Schachtröhre bereits in seiner passgenauen Position befindet. Vorteilhaft ist ferner, dass bei mehreren passgenau ausgerichteten Schachtkragen diese in einem Zug mit der wenigstens einen Tragschicht vergossen werden können. Hierbei ist es möglich, einen schnell sich verfestigenden Beton zu verwenden, sodass die Strasse schneller wieder befahrbar ist.

   Vorteilhaft ist ferner, dass die fertig eingebaute Schachtabdeckung sowohl auf der Höheneinstellvorrichtung als auch auf der wenigstens einen Tragschicht aufliegt. Dadurch treten in der Schachtabdeckung auch bei hoher Belastung keine lokalen Druckspitzen auf, die die passgenaue Lage der Schachtabdeckung dauerhaft verändern könnten. 



  Vorteilhafte Weiterbildungen der Erfindung sind Gegenstand der jeweiligen abhängigen Patentansprüche. 



  Ein Ausführungsbeispiel des Erfindungsgegenstandes wird nachfolgend anhand der Zeichnung näher erläutert. Es zeigt: 



  Fig. 1 einen vertikalen Schnitt durch einen eine Verschalung aufweisenden Schacht. 



  Gemäss Fig. 1 ist eine Schachtröhre 1 von einer Basisschicht 2 derart umgeben, dass die Oberkanten von Schachtröhre 1 und Basisschicht 2 miteinander fluchten. Oberhalb der Schachtröhre 1 befindet sich ein Schachtkragen 3, welcher in seinem oberen Abschnitt einen Schachtrahmen 4 zentrisch aufweist, in den ein Deckel 5 derart eingesetzt ist, dass dessen Oberkante mit der Oberkante des Schachtrahmens 4 etwa fluchtet. 



  Unmittelbar unterhalb des Deckels 5 befindet sich ein mit dem Schachtrahmen 4 fest verbundener Noppen 6. Dieser hat eine nicht dargestellte Ausnehmung, in welche ein am Deckel vorgesehener Dorn (nicht gezeigt) im eingebauten Zustand des Deckels eingreift. Dadurch ist der Deckel verdrehfest in Schachtrahmen und Schachtkragen gehalten. 



  Erfindungsgemäss befindet sich auf dem oberen Rand der Schachtröhre 1 eine Höheneinstellvorrichtung 7, die mehrere, verstellbare Distanzhalter aufweist. Auf diesen ruht der Schachtkragen 3 und damit auch der Schachtrahmen 4 sowie der Deckel 5. 



  Oberhalb der Schachtröhre 1 und der Basisschicht 2 befindet sich unterhalb und seitlich vom Schachtrahmen 4 eine untere Tragschicht 8, die sich etwa bis zur halben Höhe des Schachtkragens 3 nach oben erstreckt. Daran schliesst sich nach oben hin eine obere Tragschicht 9 an, deren Oberkante mit derjenigen des Dec kels 5 und mit derjenigen eines auf der Basisschicht vorgesehenen Belages 10 fluchtet. 



  Zum Auffüllen des Zwischenraumes unterhalb und neben dem Schachtkragen 3 mit der unteren Tragschicht 8 ist gemäss Fig. 1 eine Verschalung 11 mit vorzugsweise zylindrischem Querschnitt vorgesehen, wobei eine etwa horizontale Verstrebung der Verschalung 12 die Verschalungsseiten miteinander verbindet und von der unteren Tragschicht 8 radial nach innen, d.h. quer zur Längsachse der Schachtröhre und des Schachtkragens wirkende Druckkräfte aufnimmt. 



  Die Distanzhalter 7 sind als Verstellschrauben ausgebildet. Pro Schachtkragen 3 sind etwa drei Verstellschrauben vorgesehen, wobei in der Fig. 1 aus zeichnungstechnischen und erläuterungstechnischen Gründen zwei Distanzhalter 7 dargestellt sind. Es ist klar, dass insbesondere bei Schachtkragen mit grossem Durchmesser auch mehr als drei Verstellschrauben vorgesehen sein können, um den Schachtkragen passgenau ausrichten zu können. 



  Die untere Tragschicht 8 besteht vorzugsweise aus Flüssigbeton, während die obere Tragschicht 9 vorzugsweise eine so genannte Heiss-Misch-Tragschicht ist. Der Belag besteht vorzugsweise aus Asphalt. Die Basisschicht 2 ist ein so genannter Kieskoffer. Der Schachtkragen 3 ist üblicherweise aus Beton, die Verschalung 11 zumindest teilweise aus Holz gefertigt. 



  An Stelle einer Verschalung aus Holz mit einer horizontalen Verstrebung 12 kann insbesondere bei Schachtkragen ohne Noppen 6 auch ein mittels einer nicht dargestellten Spannschraube verstellbares, gebogenes Band verwendet werden. Bei Schachtkragen mit Noppen 6 ist vorzugsweise sicherzustellen, dass die Verschalung 11 entweder vor dem Einsetzen des den Noppen 6 aufweisenden Schachtrahmens 4 oder aber nach dem Einsetzen des den Noppen aufweisenden Schachtrahmens aus dem Schacht entfernt werden kann. Im letztgenannten Fall erfordert dies entweder eine Verschalung aus mehreren voneinander trennbaren Teilen oder aber ein gebogenes, etwa zylindrisch geformtes Band, dessen Durchmesser so weit reduziert werden kann, dass das Band an dem Noppen 6 vorbei nach oben aus dem Schacht herausgezogen werden kann. 



  Nachfolgend wird das erfindungsgemässe Verfahren zum Einsetzen von Schachtabdeckungen insbesondere im Strassenbau im Einzelnen erläutert. 



  Auf den oberen Rand der von der Basisschicht 2 umgebenen Schachtröhre 1 werden mehrere voreingestellte Distanzhalter 7 aufgelegt. Anschliessend wird der Schachtkragen 3 auf die Distanzhalter aufgesetzt. Da die Distanzhalter 7 als Verstellschrauben ausgebildet sind, kann die Lage des Schachtrahmens durch ein Verstellen der Distanzhalter unproblematisch geändert werden. Die Feinausrichtung des Schachtkragens erfolgt so, dass die Oberkante des in den Schachtrahmen 4 des Schachtkragens 3 eingesetzten Deckels 5 mit der Oberkante des Belages 10 fluchtet. Für diese Feinausrichtung des Schachtkragens kann auch eine Latte verwendet werden. 



  Anschliessend wird die Verschalung 11 angebracht, die sich von der Innenseite des Schachtkragens 3 bis zur Innenseite der Schachtröhre 1 erstreckt. Nunmehr wird der Zwischenraum zwischen Basisschicht 2, Schachtröhre 1, Verschalung 11, Schachtkragen 3 und Belag 10 mittels einer unteren Tragschicht 8 aus Flüssigbeton aufgefüllt. Diese Auffüllung erfolgt etwa bis zur halben Höhe des Schachtkragens 3. Dann wird der verbliebene Zwischenraum zwischen unterer Tragschicht 8, Schachtkragen 3, Schachtrahmen 4 und Belag 10 derart aufgefüllt, dass im zusammengebauten Zustand der gesamten Schachtabdeckung die Oberkanten von Schachtrahmen 4, Deckel 5, oberer Tragschicht 9 und Belag 10 miteinander fluchten. Vor dem Einsetzen des Deckels 5 wird die Verschalung 11 entfernt und nach oben aus dem Schachtkragen 3 herausgezogen. Der Schachtkragen 3 wird mit dem Deckel 5 verschlossen.

   Wenn die Verschalung 11 entfernt worden ist, ist die Oberfläche, welche durch die Verschalung gebildet worden ist, normalerweise so fein, dass sie nicht mehr verputzt werden muss. Da keine Nachbearbeitung mehr notwendig ist, ist damit die Arbeit bereits beendet. 



  Mithilfe des erfindungsgemässen Verfahrens und der erläuterten Vorrichtung ist es somit möglich, Schachtabdeckungen, welche mit hohem Gewicht belastbar sind, schnell und kostengünstig, letztlich also sehr wirtschaftlich, zu versetzen. Im Weiteren ist dieses Verfahren selbstverständlich auch für vier- oder mehreckige Schachtabdeckungen anwendbar.



  



  The invention relates to a method for inserting manhole covers, in particular in road construction, according to the preamble of claim 1 and to a device for carrying out such a method according to the preamble of claim 3.



  In a method known from practice, a so-called facet layer made of concrete is applied to the upper edge of the shaft tube and to the base layer surrounding the shaft tube. The manhole collar is placed on this facet layer and pressed into the facet layer in the direction of the shaft tube until the manhole collar is inserted precisely, i.e. the upper edge of the cover placed on the shaft collar is flush with the upper edge of the covering. Subsequently, a lower base layer, usually a so-called insulating layer, and then an upper base layer, the so-called hot-mixed base layer, are applied to about half the height of the shaft collar, the upper edge of which is flush with that of the covering and the cover.



  It follows from this that in the known device there is an intermediate layer, namely the aforementioned facet layer, between the shaft tube and the base layer on one side and the shaft collar on the other side.



  The above-mentioned method is disadvantageous especially in the case of streets with a high gradient, since the facet layer must be applied parallel to the inclination of the street. Problems can also arise with the aforementioned method if the shaft collar has been pressed too far into the facet layer. In this case, the manhole collar must be raised again and the space between the manhole collar and the facet layer resulting from the lifting must be filled with additional material. This procedure is time consuming and therefore expensive. In order to be able to change the position of a misaligned manhole collar, an agent that retards the hardening of the concrete was usually added to the concrete of the facet layer. This means that the position of the shaft collar can be changed over a longer period of time.

   However, this also means that the facet layer solidifies only slowly and therefore the road can only be driven on again with a time delay.



  In the known method, formwork can also be used. This usually consists of a curved band, the ends of which are held together by a web or bracket. The diameter of the bent band can be adjusted using a clamping screw. In the case of commercially available belts, the tensioning screw and thus the diameter of the approximately cylindrically shaped belt cannot be adjusted so much that such casing with shaft collars with knobs protruding into the interior can be subsequently removed again. In this respect, the formwork described above is mainly used for manholes without knobs.

   In the case of manhole collars with knobs, the space between the manhole tube, the base layer, the covering and the manhole collar is usually poured out in several steps, which additionally increases the time required for inserting manhole covers.



  Furthermore, shaft covers are known from DE-A1-2 533 289, CH-A5-677 684, US-A-5 513 926 and DE-A1-4 400 846, in which the shaft collar can also be used with a precise fit by means of spacer rings of different heights. According to EP-A1-0 231 454, EP-A20 311 884, DE-A1-4 230 006, EP-A1-0 485 649, US-A-5 412 911 and US-A-5 344 253, manhole covers are included Screw adjusting height adjustment devices known.



  A method and a device of the type mentioned at the outset are known from CH-A5-609 119, according to which threaded holes provided on the shaft collar are used as the height adjusting device, into which screws which can be supported on the shaft tube fit adjusting screws. A disadvantage of the methods and devices known from the prior art is that they are complex and expensive, since at least the shaft collar has to be specially adapted to the respective height adjustment device and that the shaft covers, which are merely resting on screw bolts, are generally not accessible to heavy vehicles ,



  The invention is based on the object of providing a method of the type mentioned at the outset with which shaft covers can be used more economically and can also be driven on with heavy vehicles. The invention is also based on the object of specifying a device for carrying out the method.



  This object is achieved on the process side by the features of patent claim 1 and on the device side by the features of patent claim 3.



  The advantages according to the invention can be seen above all in the fact that the height adjustment device does not require any adaptation / modification of conventional manhole covers and the alignment of the manhole collar can be carried out quickly and easily using the spacers. Subsequent changes to the position of the shaft collar can also be carried out in a few simple steps and thus with little loss of time. The formwork is only attached when the shaft collar is already in its precisely fitting position relative to the covering and the shaft tube. It is also advantageous that if there are several precisely aligned shaft collars, these can be cast in one go with the at least one base layer. It is possible to use a quickly solidifying concrete, so that the road can be driven on again faster.

   It is also advantageous that the fully installed manhole cover rests both on the height adjustment device and on the at least one base layer. As a result, there are no local pressure peaks in the manhole cover, even under high loads, which could permanently change the exact position of the manhole cover.



  Advantageous developments of the invention are the subject of the respective dependent claims.



  An embodiment of the subject matter of the invention is explained in more detail with reference to the drawing. It shows:



  Fig. 1 shows a vertical section through a casing having a casing.



  1, a manhole 1 is surrounded by a base layer 2 such that the upper edges of the manhole 1 and base layer 2 are flush with one another. Above the shaft tube 1 there is a shaft collar 3, which has a shaft frame 4 centrally in its upper section, into which a cover 5 is inserted such that the upper edge thereof is approximately flush with the upper edge of the shaft frame 4.



  Immediately below the cover 5 there is a knob 6 firmly connected to the manhole frame 4. This has a recess, not shown, in which a mandrel provided on the cover (not shown) engages when the cover is installed. As a result, the cover is held against rotation in the shaft frame and shaft collar.



  According to the invention, on the upper edge of the shaft tube 1 there is a height adjustment device 7 which has a plurality of adjustable spacers. The shaft collar 3 and thus also the shaft frame 4 and the cover 5 rest on these.



  Above the shaft tube 1 and the base layer 2 there is a lower support layer 8 below and to the side of the shaft frame 4, which extends up to approximately half the height of the shaft collar 3. This is followed at the top by an upper base layer 9, the upper edge of which is aligned with that of Dec 5 and with that of a covering 10 provided on the base layer.



  To fill the space below and next to the shaft collar 3 with the lower support layer 8, a casing 11 with a preferably cylindrical cross section is provided according to FIG. 1, with an approximately horizontal bracing of the casing 12 connecting the casing sides to one another and from the lower support layer 8 radially inwards , ie absorbs compressive forces acting transversely to the longitudinal axis of the shaft tube and the shaft collar.



  The spacers 7 are designed as adjusting screws. About three adjusting screws are provided for each shaft collar 3, two spacers 7 being shown in FIG. 1 for reasons of drawing and explanation. It is clear that, particularly in the case of manhole collars with a large diameter, more than three adjusting screws can also be provided in order to be able to align the manhole collar with a precise fit.



  The lower base layer 8 is preferably made of liquid concrete, while the upper base layer 9 is preferably a so-called hot-mixed base layer. The surface is preferably made of asphalt. The base layer 2 is a so-called gravel case. The shaft collar 3 is usually made of concrete, the casing 11 is at least partially made of wood.



  Instead of a wooden cladding with a horizontal strut 12, a curved band adjustable by means of a tensioning screw, not shown, can also be used, in particular in the case of a shaft collar without knobs 6. In the case of a shaft collar with knobs 6, it is preferably to be ensured that the casing 11 can be removed from the shaft either before the shaft frame 4 having the knobs 6 is inserted or after the shaft frame having the knobs is inserted. In the latter case, this either requires a casing made of several parts that can be separated from one another or else a curved, approximately cylindrical-shaped band, the diameter of which can be reduced to such an extent that the band can be pulled past the knobs 6 upwards out of the shaft.



  The method according to the invention for inserting manhole covers, in particular in road construction, is explained in detail below.



  Several preset spacers 7 are placed on the upper edge of the shaft tube 1 surrounded by the base layer 2. The shaft collar 3 is then placed on the spacers. Since the spacers 7 are designed as adjusting screws, the position of the manhole frame can be changed without problems by adjusting the spacers. The shaft collar is fine-tuned so that the upper edge of the cover 5 inserted into the shaft frame 4 of the shaft collar 3 is flush with the upper edge of the covering 10. A slat can also be used for this fine alignment of the shaft collar.



  Then the casing 11 is attached, which extends from the inside of the shaft collar 3 to the inside of the shaft tube 1. The space between base layer 2, shaft tube 1, casing 11, shaft collar 3 and covering 10 is now filled by means of a lower base layer 8 made of liquid concrete. This filling takes place approximately up to half the height of the shaft collar 3. Then the remaining space between the lower base layer 8, shaft collar 3, shaft frame 4 and covering 10 is filled in such a way that, in the assembled state of the entire shaft cover, the upper edges of the shaft frame 4, cover 5, upper one Base layer 9 and covering 10 are aligned. Before inserting the cover 5, the casing 11 is removed and pulled up out of the shaft collar 3. The shaft collar 3 is closed with the cover 5.

   When the casing 11 has been removed, the surface formed by the casing is usually so fine that it no longer needs to be plastered. Since post-processing is no longer necessary, the work is already finished.



  With the aid of the method according to the invention and the device explained, it is thus possible to move manhole covers, which can be loaded with high weight, quickly and inexpensively, and thus ultimately very economically. In addition, this method can of course also be used for quadrangular or polygonal manhole covers.


    

Claims (8)

1. Verfahren zum Einsetzen von Schachtabdeckungen insbesondere im Strassenbau, bei welchem ein Schachtkragen (3) oberhalb einer von einer Basisschicht (2) umgebenen Schachtröhre (1) mittels einer Höheneinstellvorrichtung (7) passgenau insbesondere bezüglich eines auf der Basisschicht (2) vorgesehenen Belages (10) angeordnet und anschliessend der zwischen der Basisschicht (2), dem Belag (10) und dem Schachtkragen (3) verbliebene Zwischenraum mit wenigstens einer Tragschicht (8, 9) aufgefüllt und der Schachtkragen (3) abgedeckt wird, gekennzeichnet durch die folgenden Schritte: a) Auflegen der Höheneinstellvorrichtung (7) auf den oberen Rand der Schachtröhre (1); b) Aufsetzen des Schachtkragens (3) auf die Höheneinstellvorrichtung (7) und, sofern erforderlich, Ausrichten des Schachtkragens (3) durch Verstellen der Höheneinstellvorrichtung (7);   1. Method for inserting manhole covers, particularly in road construction, in which a manhole collar (3) above a manhole pipe (1) surrounded by a base layer (2) by means of a height adjustment device (7) fits precisely, in particular with respect to a covering provided on the base layer (2) ( 10) and then the space remaining between the base layer (2), the covering (10) and the shaft collar (3) is filled with at least one base layer (8, 9) and the shaft collar (3) is covered, characterized by the following steps :  a) placing the height adjustment device (7) on the upper edge of the shaft tube (1);  b) placing the shaft collar (3) on the height adjustment device (7) and, if necessary, aligning the shaft collar (3) by adjusting the height adjustment device (7); c) Anbringen einer sich von der Innenseite des Schachtkragens (3) bis zur Innenseite der Schachtröhre (1) erstreckenden Verschalung (11); d) Auffüllen des verbliebenen Zwischenraumes mit der wenigstens einen Tragschicht (8, 9); e) Entfernen der Verschalung (11, 12) und Abdecken des Schachtkragens (3).  c) attaching a casing (11) extending from the inside of the shaft collar (3) to the inside of the shaft tube (1);  d) filling the remaining space with the at least one base layer (8, 9);  e) removing the casing (11, 12) and covering the shaft collar (3). 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass der Zwischenraum bis zur halben Höhe des Schachtkragens (3) mit einer unteren Tragschicht (8) und anschliessend bis zur Oberkante des Belages (10) mit einer oberen Tragschicht (9) aufgefüllt wird. 2. The method according to claim 1, characterized in that the space is filled up to half the height of the shaft collar (3) with a lower base layer (8) and then up to the upper edge of the covering (10) with an upper base layer (9). 3. Third Vorrichtung zum Durchführen des Verfahrens nach Anspruch 1 oder 2, mit einem oberhalb einer von einer Basisschicht (2) umgebenen Schachtröhre (1) mittels einer Höheneinstellvorrichtung (7) passgenau angeordneten Schachtkragen (3), wenigstens einer Tragschicht (8, 9) zum Auffüllen des zwischen der Basisschicht (2), einem auf der Basisschicht (2) vorgesehenen Belag (10) und dem Schachtkragen (3) verbliebenen Zwischenraumes und mit einem den Schachtkragen (3) verschliessenden Deckel (5), dadurch gekennzeichnet, dass die Höheneinstellvorrichtung mehrere, verstellbare Distanzhalter (7) aufweist, die auf dem oberen Rand der Schachtröhre (1) zum Aufnehmen des Schachtkragens (3) angeordnet sind, eine sich von der Innenseite des Schachtkragens (3) bis zur Innenseite der Schachtröhre (1) erstreckende Verschalung (11, 12) vorgesehen ist und der durch die Basisschicht (2),  Device for carrying out the method according to claim 1 or 2, with a shaft collar (3) arranged above a shaft tube (1) surrounded by a base layer (2) by means of a height adjustment device (7), at least one base layer (8, 9) for filling the between the base layer (2), a covering (10) provided on the base layer (2) and the shaft collar (3), and with a cover (5) closing the shaft collar (3), characterized in that the height adjustment device has a plurality of adjustable ones Spacer (7), which are arranged on the upper edge of the shaft tube (1) for receiving the shaft collar (3), a formwork (11, 12) extending from the inside of the shaft collar (3) to the inside of the shaft tube (1) ) is provided and through the base layer (2), die Schachtröhre (1), die Verschalung (11), den Schachtkragen (3) und die Ober- und Seitenkante des Belages (10) begrenzte Zwischenraum mit wenigstens einer Tragschicht (8, 9) auffüllbar ist.  the shaft tube (1), the casing (11), the shaft collar (3) and the upper and side edges of the covering (10) can be filled with at least one base layer (8, 9). 4. Vorrichtung nach Anspruch 3, dadurch gekennzeichnet, dass die Distanzhalter (7) Verstellschrauben haben und pro Schachtkragen (3) drei Verstellschrauben vorhanden sind. 4. The device according to claim 3, characterized in that the spacers (7) have adjusting screws and three adjusting screws are available per shaft collar (3). 5. Vorrichtung nach Anspruch 3 oder 4, dadurch gekennzeichnet, dass die wenigstens eine Tragschicht (8, 9) eine untere Tragschicht (8), vorzugsweise aus Flüssigbeton, und eine obere Tragschicht (9), vorzugsweise eine Heiss-Misch-Tragschicht, aufweist. 5. The device according to claim 3 or 4, characterized in that the at least one base layer (8, 9) has a lower base layer (8), preferably made of liquid concrete, and an upper base layer (9), preferably a hot-mixed base layer , 6. Vorrichtung nach einem der Ansprüche 3 bis 5, dadurch gekennzeichnet, dass die Basisschicht (2) ein Kieskoffer ist und der Schachtkragen (3) aus Beton sowie die Verschalung (11, 12) zumindest teilweise aus Holz gefertigt sind. 6. Device according to one of claims 3 to 5, characterized in that the base layer (2) is a gravel case and the shaft collar (3) made of concrete and the casing (11, 12) are at least partially made of wood. 7. 7th Vorrichtung nach einem Ansprüche 3 bis 6, dadurch gekennzeichnet, dass die Verschalung (11) vorzugsweise bei Schachtkragen (3) ohne Noppen (6) ein mittels einer Spannschraube verstellbares, gebogenes Band ist.  Device according to one of claims 3 to 6, characterized in that the casing (11), preferably in the case of a shaft collar (3) without knobs (6), is a curved band which can be adjusted by means of a tensioning screw. 8. Vorrichtung nach einem der Ansprüche 3 bis 7, dadurch gekennzeichnet, dass der Schachtkragen (3) einen Schachtrahmen (4) aufweist, dessen Oberkante mit derjenigen des Belages (10) fluchtet. 8. Device according to one of claims 3 to 7, characterized in that the shaft collar (3) has a shaft frame (4), the upper edge of which is flush with that of the covering (10).
CH146497A 1997-06-16 1997-06-16 Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe CH692207A5 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH146497A CH692207A5 (en) 1997-06-16 1997-06-16 Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH146497A CH692207A5 (en) 1997-06-16 1997-06-16 Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe

Publications (1)

Publication Number Publication Date
CH692207A5 true CH692207A5 (en) 2002-03-15

Family

ID=4211089

Family Applications (1)

Application Number Title Priority Date Filing Date
CH146497A CH692207A5 (en) 1997-06-16 1997-06-16 Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe

Country Status (1)

Country Link
CH (1) CH692207A5 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144427A (en) * 2020-10-27 2020-12-29 南京工业大学 Prefabricated culvert on-site dislocation adjusting device and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144427A (en) * 2020-10-27 2020-12-29 南京工业大学 Prefabricated culvert on-site dislocation adjusting device and method

Similar Documents

Publication Publication Date Title
EP0642620B1 (en) Process, tubular spreader and device for erecting concrete walls by means of braced shutterings
DE102005019648A1 (en) Riser line used on building sites to carry liquid concrete, comprises series of coupled pipes supported by system of fixed mountings and guides
DE1933573A1 (en) Process for straightening vehicle bodies and frames as well as equipment for carrying out this process
DE19549535C2 (en) Adjustment device for placing a wall element
CH692207A5 (en) Equipment for installation of shaft covers in road construction incorporates height adjustment device laid on upper edge of shaft pipe
DE1684143A1 (en) Cladding
EP0796950A1 (en) Method and apparatus for exchanging a manhole frame installed in an asphalt layer
DE3443451C1 (en) Apparatus for installing a support
DE102021107534A1 (en) Frame formwork element for a wall formwork system, insert part for a frame formwork element, wall formwork system and method for producing a formwork system
DE10045735A1 (en) Pillar for rotary pillar crane has flange on underside detachably directly connected with extension resistance to anchor rods cast in concrete foundation
DE2057263A1 (en) Device for supporting trench walls
WO2010130454A2 (en) Foundation cage, foundation, and process for forming a foundation
DE3324301C2 (en)
DE29604536U1 (en) Channel element and swimming pool with an overflow channel having such a channel element
EP0052761A2 (en) Means for bracing shuttering elements
CH696206A5 (en) Height-adjustable cable and duct carrier.
DE202009002406U1 (en) ground anchor
DE7343325U (en) Device for lifting manhole rings
DE2309723C3 (en) Method and device for adjusting prefabricated walls and columns of buildings
DE60125495T2 (en) Gripping device for attaching straight stairs
DE2436088A1 (en) Tunnel or other hollow space movable formwork - comprising height-adjustable ceiling form on movable substructure, hinged to side forms
DE19620638A1 (en) Track superstructure
AT412358B (en) SUPPORTING
DE266834C (en)
DE29918996U1 (en) Device for bracing building boards

Legal Events

Date Code Title Description
PL Patent ceased