CH585823A5 - Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough - Google Patents

Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough

Info

Publication number
CH585823A5
CH585823A5 CH1787273A CH1787273A CH585823A5 CH 585823 A5 CH585823 A5 CH 585823A5 CH 1787273 A CH1787273 A CH 1787273A CH 1787273 A CH1787273 A CH 1787273A CH 585823 A5 CH585823 A5 CH 585823A5
Authority
CH
Switzerland
Prior art keywords
foundation
wall
pit
building
trench
Prior art date
Application number
CH1787273A
Other languages
German (de)
Original Assignee
Maurer Alfred
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maurer Alfred filed Critical Maurer Alfred
Priority to CH1787273A priority Critical patent/CH585823A5/en
Publication of CH585823A5 publication Critical patent/CH585823A5/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/30Foundations made with permanent use of sheet pile bulkheads, walls of planks, or sheet piling boxes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Abstract

Parallel trenches are excavated for a foundation wall (2). A central excavation section (3) between these walls is excavated down to the bottom of the foundations. The trench has sloping walls (4). Into this middle section is made a concrete baseplate (5). The sloping sides are removed to the foundation walls (2). This is facilitated by the support provided by the foundation wall. The central section baseplate is extended to the foundation to form a closed trough. This building method eliminates the use of sheet piling and pumping out of water.

Description

  

  
 



   Die Erfindung bezieht sich auf ein Verfahren zur Herstellung eines Bau-Fundamentes.



   Die Erstellung einer   Baugrube    im Grundwasserbereich erfordert üblicherweise einen erheblichen Aufwand. Gewöhnlich werden senkrechte Spundwände errichtet und das Wasser mit fortschreitendem Aushub abgepumpt. Das Errichten solcher Spundwände ist zeitraubend und verhältnismässig kostspielig.



   Mit dem erfindungsgemässen Verfahren soll ein Weg aufgezeigt werden zur billigeren Erstellung eines Bau-Fundamentes.



   Die Erfindung ist dadurch gekennzeichnet, dass ein die Baugrube zu umfassen bestimmter, mindestens der Baugrubentiefe entsprechender Graben ausgehoben wird, hierauf in diesem Graben eine Fundationswand errichtet wird, ein mittlerer Baugrubenteil bis auf die Gründungssohle ausgehoben wird unter Belassung schräger Böschungen, in diesem mittleren Baugrubenteil eine Grundplatte betoniert wird, hernach die Böschungen bis zur Fundationswand abgetragen werden unter Abstützung der Fundationswand und sodann die Grundplatte bis zur Fundationswand ergänzt wird, so dass ein geschlossener Trog entsteht.



   Auf diese Weise gelingt es, den Aufwand zur Herstellung einer Umfassungswand, namentlich bei Grundwasservorkommen, wesentlich zu reduzieren.



   In der Zeichnung sind als Ausführungsbeispiel die verschiedenen Herstellungsstadien schematisch dargestellt. Es zeigen:
Fig. 1 eine die Baugrube zu umgeben bestimmte Wand,
Fig. 2 die teilweise ausgehobene Baugrube,
Fig. 3 das fertige Bau-Fundament.



   In den aus Lockergestein od.dgl. bestehenden Baugrund 1 wird vorerst ein Graben ausgebogen, der sich entlang den Aussenkonturen des zu erstellenden Fundamentes erstreckt.



  Die Tiefe dieses Grabens reicht mindestens bis zur vorgesehenen Gründungssohle. Hernach werden mit Hilfe einer als Führung dienenden Aufhängevorrichtung Wandelemente in diesen Graben abgesenkt, deren Höhe etwa der Grabentiefe entspricht. Diese Wandlemente werden sodann seitlich untereinander verbunden, so dass sich eine zusammenhängende, dichte Umfassungswand 2 ergibt. Der noch verbleibende Grabenteil wird wieder zugeschüttet.



   Die Wandelemente bestehen vorzugsweise aus zwei zueinander parallel verlaufenden Betonplatten von etwa 5 cm Dikke, zwischen denen ein Abstand von vorzugsweise etwa der fünffachen Plattendicke besteht. Diese beiden Betonplatten werden durch einbetonierte Armierungsbügel im Abstand voneinander starr zusammengehalten. An den vertikalen Stossstellen benachbarter Wandelemente wird ein der Führung dienender Korb aus Armierungseisen in den Zwischenraum zwischen die beiden Betonplatten eingelegt und der Zwischenraum zwischen diesen Betonplatten sodann mit Ortsbeton ausgefüllt, so dass eine massive, zusammenhängende Umfassungs- oder Fundationswand 2 entsteht, welche die Baugrube umgibt.



   Anschliessend wird der mittlere Teil der Baugrube 3 bis auf die Gründungssohle ausgehoben, wobei auf allen Seiten Böschungen 4 aus Erde verbleiben, so dass eine pyramidenstumpfförmige Grube entsteht. Sodann wird im mittleren Teil der Baugrube eine üblicherweise rechteckige, horizontale Bodenplatte 5 aus Ortsbeton hergestellt.



   Nach dem Erhärten der Grund- oder Bodenplatten wird auch die schräge Böschung 4 bis auf Gründungssohlentiefe abgetragen, so dass schliesslich eine prismatische Baugrube entsteht. Damit die Fundationswand 2 nicht einstürzt, wird sie von der Grube her durch schräge Spriessen 6 ringsherum abgestützt. Hernach wird die Bodenplatte 5 ringsherum bis zur Fundationswand 2 betoniert und mit dieser verbunden. Dadurch entsteht ein Wasserdichter Betontrog oder -Wanne als Baufundament, der den Wasser- und Erddruck aufnimmt. Es ist auch möglich, dass die Fundazionswand 2 etwas tiefer in das Terrain hinabreicht als die Bodenplatte.

 

   PATENTANSPRUCH



   Verfahren zur Herstellung eines Bau-Fundamentes, dadurch gekennzeichnet, dass ein die Baugrube zu umfassen bestimmter, mindestens der Baugrubentiefe entsprechender Graben ausgenommen wird, in diesem Graben eine Fundationswand (2) errichtet wird, ein mittlerer Baugrubenteil (3) bis auf die Gründungssohle ausgehoben wird unter Belassung schräger Böschungen (4), in diesem mittleren Baugrubenteil eine Grundplatte (5) betoniert wird, hernach die Böschungen bis zur Fundationswand (2) abgetragen werden unter Abstützung der Fundationswand und sodann die Grundplatte bis zur Fundationswand ergänzt wird, so dass ein geschlossener Trog entsteht.

**WARNUNG** Ende DESC Feld konnte Anfang CLMS uberlappen**.



   



  
 



   The invention relates to a method for producing a building foundation.



   The creation of a construction pit in the groundwater area usually requires considerable effort. Usually vertical sheet piling is built and the water is pumped out as the excavation progresses. The erection of such sheet piling is time consuming and relatively expensive.



   The method according to the invention is intended to show a way to create a building foundation more cheaply.



   The invention is characterized in that a trench intended to encompass the building pit and at least corresponding to the building pit depth is dug, a foundation wall is then built in this trench, a middle building pit part is excavated down to the foundation base, leaving inclined slopes, one in this middle building pit part The base plate is concreted, after which the slopes are removed up to the foundation wall with the support of the foundation wall and then the base plate is added to the foundation wall, so that a closed trough is created.



   In this way, it is possible to significantly reduce the cost of producing a surrounding wall, especially in the case of groundwater deposits.



   In the drawing, the various manufacturing stages are shown schematically as an exemplary embodiment. Show it:
1 shows a wall intended to surround the excavation,
Fig. 2 the partially excavated construction pit,
Fig. 3 the finished building foundation.



   In the loose rock or the like. existing subsoil 1, a trench is first excavated, which extends along the outer contours of the foundation to be created.



  The depth of this trench extends at least to the intended foundation level. Thereafter, wall elements are lowered into this trench with the help of a suspension device serving as a guide, the height of which corresponds approximately to the depth of the trench. These wall elements are then laterally connected to one another, so that a coherent, tight surrounding wall 2 results. The remaining part of the trench is filled in again.



   The wall elements preferably consist of two mutually parallel concrete slabs of about 5 cm thick, between which there is a distance of preferably about five times the plate thickness. These two concrete slabs are held together rigidly at a distance from one another by means of reinforcement stirrups embedded in concrete. At the vertical joints of adjacent wall elements, a cage made of reinforcing iron is inserted into the space between the two concrete slabs and the space between these concrete slabs is then filled with in-situ concrete, so that a massive, coherent surrounding or foundation wall 2 is created which surrounds the excavation .



   The middle part of the construction pit 3 is then excavated down to the base of the foundation, with earth slopes 4 remaining on all sides, so that a truncated pyramid-shaped pit is created. Then a usually rectangular, horizontal floor slab 5 made of in-situ concrete is produced in the middle part of the construction pit.



   After the base or floor slabs have hardened, the inclined slope 4 is also removed down to the foundation base depth, so that a prismatic construction pit is ultimately created. So that the foundation wall 2 does not collapse, it is supported all around from the pit by inclined struts 6. Thereafter, the floor slab 5 is concreted all around up to the foundation wall 2 and connected to it. This creates a waterproof concrete trough or tub as a building foundation that absorbs the water and earth pressure. It is also possible that the foundation wall 2 extends a little deeper into the terrain than the floor slab.

 

   PATENT CLAIM



   A method for producing a building foundation, characterized in that a trench intended to encompass the building pit and at least corresponding to the depth of the building pit is excluded, a foundation wall (2) is built in this trench, a central building pit part (3) is excavated down to the foundation base leaving inclined embankments (4), a base plate (5) is concreted in this middle part of the construction pit, then the embankments are removed up to the foundation wall (2) with the support of the foundation wall and then the base plate is added to the foundation wall, so that a closed trough arises.

** WARNING ** End of DESC field could overlap beginning of CLMS **.



   

 

Claims (1)

**WARNUNG** Anfang CLMS Feld konnte Ende DESC uberlappen **. ** WARNING ** Beginning of CLMS field could overlap end of DESC **. Die Erfindung bezieht sich auf ein Verfahren zur Herstellung eines Bau-Fundamentes. The invention relates to a method for producing a building foundation. Die Erstellung einer Baugrube im Grundwasserbereich erfordert üblicherweise einen erheblichen Aufwand. Gewöhnlich werden senkrechte Spundwände errichtet und das Wasser mit fortschreitendem Aushub abgepumpt. Das Errichten solcher Spundwände ist zeitraubend und verhältnismässig kostspielig. The creation of a construction pit in the groundwater area usually requires considerable effort. Usually vertical sheet piling is built and the water is pumped out as the excavation progresses. The erection of such sheet piling is time consuming and relatively expensive. Mit dem erfindungsgemässen Verfahren soll ein Weg aufgezeigt werden zur billigeren Erstellung eines Bau-Fundamentes. The method according to the invention is intended to show a way to create a building foundation more cheaply. Die Erfindung ist dadurch gekennzeichnet, dass ein die Baugrube zu umfassen bestimmter, mindestens der Baugrubentiefe entsprechender Graben ausgehoben wird, hierauf in diesem Graben eine Fundationswand errichtet wird, ein mittlerer Baugrubenteil bis auf die Gründungssohle ausgehoben wird unter Belassung schräger Böschungen, in diesem mittleren Baugrubenteil eine Grundplatte betoniert wird, hernach die Böschungen bis zur Fundationswand abgetragen werden unter Abstützung der Fundationswand und sodann die Grundplatte bis zur Fundationswand ergänzt wird, so dass ein geschlossener Trog entsteht. The invention is characterized in that a trench intended to encompass the building pit and at least corresponding to the building pit depth is dug, a foundation wall is then built in this trench, a middle building pit part is excavated down to the foundation base, leaving inclined slopes, one in this middle building pit part The base plate is concreted, after which the slopes are removed up to the foundation wall with the support of the foundation wall and then the base plate is added to the foundation wall, so that a closed trough is created. Auf diese Weise gelingt es, den Aufwand zur Herstellung einer Umfassungswand, namentlich bei Grundwasservorkommen, wesentlich zu reduzieren. In this way, it is possible to significantly reduce the cost of producing a surrounding wall, especially in the case of groundwater deposits. In der Zeichnung sind als Ausführungsbeispiel die verschiedenen Herstellungsstadien schematisch dargestellt. Es zeigen: Fig. 1 eine die Baugrube zu umgeben bestimmte Wand, Fig. 2 die teilweise ausgehobene Baugrube, Fig. 3 das fertige Bau-Fundament. In the drawing, the various manufacturing stages are shown schematically as an exemplary embodiment. Show it: 1 shows a wall intended to surround the excavation, Fig. 2 the partially excavated construction pit, Fig. 3 the finished building foundation. In den aus Lockergestein od.dgl. bestehenden Baugrund 1 wird vorerst ein Graben ausgebogen, der sich entlang den Aussenkonturen des zu erstellenden Fundamentes erstreckt. In the loose rock or the like. existing subsoil 1, a trench is first excavated, which extends along the outer contours of the foundation to be created. Die Tiefe dieses Grabens reicht mindestens bis zur vorgesehenen Gründungssohle. Hernach werden mit Hilfe einer als Führung dienenden Aufhängevorrichtung Wandelemente in diesen Graben abgesenkt, deren Höhe etwa der Grabentiefe entspricht. Diese Wandlemente werden sodann seitlich untereinander verbunden, so dass sich eine zusammenhängende, dichte Umfassungswand 2 ergibt. Der noch verbleibende Grabenteil wird wieder zugeschüttet. The depth of this trench extends at least to the intended foundation level. Thereafter, wall elements are lowered into this trench with the help of a suspension device serving as a guide, the height of which corresponds approximately to the depth of the trench. These wall elements are then laterally connected to one another, so that a coherent, tight surrounding wall 2 results. The remaining part of the trench is filled in again. Die Wandelemente bestehen vorzugsweise aus zwei zueinander parallel verlaufenden Betonplatten von etwa 5 cm Dikke, zwischen denen ein Abstand von vorzugsweise etwa der fünffachen Plattendicke besteht. Diese beiden Betonplatten werden durch einbetonierte Armierungsbügel im Abstand voneinander starr zusammengehalten. An den vertikalen Stossstellen benachbarter Wandelemente wird ein der Führung dienender Korb aus Armierungseisen in den Zwischenraum zwischen die beiden Betonplatten eingelegt und der Zwischenraum zwischen diesen Betonplatten sodann mit Ortsbeton ausgefüllt, so dass eine massive, zusammenhängende Umfassungs- oder Fundationswand 2 entsteht, welche die Baugrube umgibt. The wall elements preferably consist of two mutually parallel concrete slabs of about 5 cm thick, between which there is a distance of preferably about five times the plate thickness. These two concrete slabs are held together rigidly at a distance from one another by means of reinforcement stirrups embedded in concrete. At the vertical joints of adjacent wall elements, a cage made of reinforcing iron is inserted into the space between the two concrete slabs and the space between these concrete slabs is then filled with in-situ concrete, so that a massive, coherent surrounding or foundation wall 2 is created which surrounds the excavation . Anschliessend wird der mittlere Teil der Baugrube 3 bis auf die Gründungssohle ausgehoben, wobei auf allen Seiten Böschungen 4 aus Erde verbleiben, so dass eine pyramidenstumpfförmige Grube entsteht. Sodann wird im mittleren Teil der Baugrube eine üblicherweise rechteckige, horizontale Bodenplatte 5 aus Ortsbeton hergestellt. The middle part of the construction pit 3 is then excavated down to the base of the foundation, with earth slopes 4 remaining on all sides, so that a truncated pyramid-shaped pit is created. Then a usually rectangular, horizontal floor slab 5 made of in-situ concrete is produced in the middle part of the construction pit. Nach dem Erhärten der Grund- oder Bodenplatten wird auch die schräge Böschung 4 bis auf Gründungssohlentiefe abgetragen, so dass schliesslich eine prismatische Baugrube entsteht. Damit die Fundationswand 2 nicht einstürzt, wird sie von der Grube her durch schräge Spriessen 6 ringsherum abgestützt. Hernach wird die Bodenplatte 5 ringsherum bis zur Fundationswand 2 betoniert und mit dieser verbunden. Dadurch entsteht ein Wasserdichter Betontrog oder -Wanne als Baufundament, der den Wasser- und Erddruck aufnimmt. Es ist auch möglich, dass die Fundazionswand 2 etwas tiefer in das Terrain hinabreicht als die Bodenplatte. After the base or floor slabs have hardened, the inclined slope 4 is also removed down to the foundation base depth, so that a prismatic construction pit is ultimately created. So that the foundation wall 2 does not collapse, it is supported all around from the pit by inclined struts 6. Thereafter, the floor slab 5 is concreted all around up to the foundation wall 2 and connected to it. This creates a waterproof concrete trough or tub as a building foundation that absorbs the water and earth pressure. It is also possible that the foundation wall 2 extends a little deeper into the terrain than the floor slab. PATENTANSPRUCH PATENT CLAIM Verfahren zur Herstellung eines Bau-Fundamentes, dadurch gekennzeichnet, dass ein die Baugrube zu umfassen bestimmter, mindestens der Baugrubentiefe entsprechender Graben ausgenommen wird, in diesem Graben eine Fundationswand (2) errichtet wird, ein mittlerer Baugrubenteil (3) bis auf die Gründungssohle ausgehoben wird unter Belassung schräger Böschungen (4), in diesem mittleren Baugrubenteil eine Grundplatte (5) betoniert wird, hernach die Böschungen bis zur Fundationswand (2) abgetragen werden unter Abstützung der Fundationswand und sodann die Grundplatte bis zur Fundationswand ergänzt wird, so dass ein geschlossener Trog entsteht. A method for producing a building foundation, characterized in that a trench intended to encompass the building pit and at least corresponding to the depth of the building pit is excluded, a foundation wall (2) is built in this trench, a central building pit part (3) is excavated down to the foundation base leaving inclined embankments (4), a base plate (5) is concreted in this middle part of the construction pit, then the embankments are removed up to the foundation wall (2) with the support of the foundation wall and then the base plate is added to the foundation wall, so that a closed trough arises.
CH1787273A 1973-12-20 1973-12-20 Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough CH585823A5 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH1787273A CH585823A5 (en) 1973-12-20 1973-12-20 Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH1787273A CH585823A5 (en) 1973-12-20 1973-12-20 Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough

Publications (1)

Publication Number Publication Date
CH585823A5 true CH585823A5 (en) 1977-03-15

Family

ID=4428732

Family Applications (1)

Application Number Title Priority Date Filing Date
CH1787273A CH585823A5 (en) 1973-12-20 1973-12-20 Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough

Country Status (1)

Country Link
CH (1) CH585823A5 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2733263A1 (en) * 2012-11-16 2014-05-21 Bayer MaterialScience AG Method and protective wall for securing a civil engineering site
CN109610465A (en) * 2018-12-17 2019-04-12 中国建筑第八工程局有限公司 Super large area deep foundation pit excavation construction method
CN110219304A (en) * 2019-06-27 2019-09-10 云南建投第十二建设有限公司 Foundation ditch excavation method for soft modeling soil
CN113653062A (en) * 2021-08-16 2021-11-16 中国建筑第八工程局有限公司 Construction method for quickly unearthing deep foundation pit by utilizing trestle to combine with road in pit
CN117266172A (en) * 2023-11-23 2023-12-22 北京建工集团有限责任公司 Shallow-first-deep excavation method for adjacent foundation pit without coordination of construction progress

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2733263A1 (en) * 2012-11-16 2014-05-21 Bayer MaterialScience AG Method and protective wall for securing a civil engineering site
CN109610465A (en) * 2018-12-17 2019-04-12 中国建筑第八工程局有限公司 Super large area deep foundation pit excavation construction method
CN109610465B (en) * 2018-12-17 2021-05-25 中国建筑第八工程局有限公司 Excavation construction method for ultra-large-area deep foundation pit
CN110219304A (en) * 2019-06-27 2019-09-10 云南建投第十二建设有限公司 Foundation ditch excavation method for soft modeling soil
CN110219304B (en) * 2019-06-27 2021-04-06 云南建投第十二建设有限公司 Foundation pit excavation method for soft plastic land
CN113653062A (en) * 2021-08-16 2021-11-16 中国建筑第八工程局有限公司 Construction method for quickly unearthing deep foundation pit by utilizing trestle to combine with road in pit
CN117266172A (en) * 2023-11-23 2023-12-22 北京建工集团有限责任公司 Shallow-first-deep excavation method for adjacent foundation pit without coordination of construction progress
CN117266172B (en) * 2023-11-23 2024-02-27 北京建工集团有限责任公司 Shallow-first-deep excavation method for adjacent foundation pit without coordination of construction progress

Similar Documents

Publication Publication Date Title
DE2751972A1 (en) METHOD OF MANUFACTURING REINFORCED UNDERGROUND BUILDING PANEL
DE1947249C3 (en) Method for producing a diaphragm wall in the ground and prefabricated part for carrying out the method
CH585823A5 (en) Concrete foundation for waterlogged ground - uses preliminary foundation walls and extending baseplate to form trough
DE2821340A1 (en) METHOD AND DEVICE FOR SUPPORTING A BUILDING CONSTRUCTION
DE19521986A1 (en) Mfg. dry construction pit sole located below ground water level
DE3620650A1 (en) Method for producing multi-storey underground structures, in particular underground garages
DE1634589B2 (en) PILE GRATING MADE FROM CONCRETE PILES
EP0333639B1 (en) Method of constructing a sheet pile wall
EP1553230B1 (en) Method for rehabilitating retaining walls
DE593664C (en) Installation on caissons for the foundation of structures
DE2062612A1 (en) Procedure for creating an underpass
DE4025176A1 (en) Basement construction in water-bearing ground - has frame for walls constructed, lowered and soil is pumped out
AT317092B (en) Process for the production of a trough arranged in the ground below the groundwater level and for this purpose prefabricated reinforced concrete girders for their production
EP1964978B1 (en) Method for erecting a wharfage and wharfage
DE2030259C3 (en) Process for the production of a structure below the water table
DE609976C (en) Process for the production of a watertight construction pit enclosure
AT225621B (en) Method of manufacturing storage tanks
AT265982B (en) Procedure for undertaking the foundation, which is only accessible from the outside of the building
AT318492B (en) Method for sealing the base plate of a foundation structure reaching below the water table, consisting of a lower plate made of underwater poured concrete and an upper plate made of reinforced concrete above it
DE815327C (en) Process for the production of deep foundations
DE869178C (en) Process for the production of deep foundations
DE19739106C1 (en) Construction method for foundations etc. in water-filled excavation
AT238107B (en) Procedure for the foundation of prefabricated structures
CH492835A (en) Process for the production of cesspools, caissons or shafts
DE627938C (en) Method for reinforcing retaining walls, in particular embankment walls based on post gratings

Legal Events

Date Code Title Description
PL Patent ceased