CH402750A - Process for the production of a watertight construction pit with a floor below the existing water table - Google Patents

Process for the production of a watertight construction pit with a floor below the existing water table

Info

Publication number
CH402750A
CH402750A CH184562A CH184562A CH402750A CH 402750 A CH402750 A CH 402750A CH 184562 A CH184562 A CH 184562A CH 184562 A CH184562 A CH 184562A CH 402750 A CH402750 A CH 402750A
Authority
CH
Switzerland
Prior art keywords
concrete
pit
base
construction
anchors
Prior art date
Application number
CH184562A
Other languages
German (de)
Inventor
Wilhelm Dipl Ing Degen
Original Assignee
Wilhelm Dipl Ing Degen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wilhelm Dipl Ing Degen filed Critical Wilhelm Dipl Ing Degen
Priority to CH184562A priority Critical patent/CH402750A/en
Publication of CH402750A publication Critical patent/CH402750A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Description

  

  Verfahren zur Herstellung einer wasserdichten Baugrube mit einer unterhalb des  anstehenden Grundwasserspiegels     befindlichen    Sohle    Diese Erfindung betrifft ein Verfahren zur Her  stellung einer wasserdichten Baugrube mit einer un  terhalb des anstehenden Grundwasserspiegels befind  lichen Sohle.  



  Die Gründung von Bauwerken unterhalb des  Grundwasserspiegels in wasserfreier Baugrube erfolgt  im allgemeinen im Schutze einer     Grundwasserabsen-          kung    oder offenen Wasserhaltung. Bei sehr schwieri  gen     Grundwasserverhältnissen    bedient man sich der       Druckluftgründung    und bei sehr grossen Tiefen  schliesslich der     Gefriergründung.    Es sind auch Ver  fahren zur Gründung von Bauwerken unterhalb des  Grundwasserspiegels in wasserfreier Baugrube ohne  Wasserhaltung durch Herstellung einer dichten  Umschliessung und einer dichten     Baugrubensohle     bekannt.

   So ist es bereits bekannt, als dichte       Baugrubensohle    eine     Unterwasserbetonsohle    her  zustellen. Jedoch musste bisher eine solche Sohle,  wenn es sich nicht um eine sehr schmale  Baugrube handelte, immer als Schwergewichtssohle  dimensioniert werden. In einigen Fällen     gestatten    die  anstehenden Bodenarten auch die Herstellung einer  wasserfreien Baugrube durch Injizieren des wasser  durchlässigen Bodens. Durchgeführte Injektionen mit  Chemikalien zur Herstellung einer dichten     Baugru-          bensohle    ergaben aber bisher eine zu geringe mecha  nische Festigkeit des injizierten Bodens.

   Injizierung  durch Zement setzt ausserdem eine grosse und gleich  zeitig eine gleichmässige Durchlässigkeit des Bodens  voraus, damit das verhältnismässig grobe Zement  korn in die Hohlräume des Bodens eindringen kann,  ohne dass anderseits das Injektionsgut durch Boden  schichten grösserer Durchlässigkeit unkontrolliert ab  fliessen kann. Ausserdem ist bei der Herstellung einer  wasserdichten Sohle durch Injektionen eine grosse    Bodenüberlagerung notwendig, damit der erforder  liche     Einpressdruck    bei der Injektion ausgeübt werden  kann.  



  Zur Vermeidung dieser Nachteile ist es ein Ziel  der Erfindung, eine dichte Baugrube unterhalb des  Grundwasserspiegels herzustellen, ohne dabei eine       Grundwasserabsenkung    oder Bodeneinfrierungen vor  nehmen oder die Grubensohle als Schwergewichts  sohle ausführen zu müssen.  



  Das Verfahren zur Herstellung einer wasserdich  ten Baugrube mit einer unterhalb des anstehenden  Grundwasserspiegels befindlichen Sohle und inner  halb eines durchlässigen Bodenmateriales ist erfin  dungsgemäss dadurch gekennzeichnet, dass man zu  nächst Teile zur Bildung von dichten     Umfassungs-          wänden    in den Boden einbringt und erst anschliessend  den eingeschlossenen Boden aushebt und hierauf An  ker im durchlässigen Boden befestigt, mit denen der  die Sohle bildende Beton verbunden wird und dass  man nach dessen Verfestigung die Baugrube leer  pumpt.  



  Durch das vorliegende Verfahren sollen zweck  mässig bei der Herstellung der Baugrube unkontrol  lierbare Injektionen zur Herstellung einer dichten       Baugrubensohle    vermieden und solche Injektionen  gegebenenfalls nur zur Ausfüllung von Spalten zwi  schen der Sohle der ausgehobenen Grube und der  darauf eingebrachten Betonsohle vorgenommen wer  den.  



  Eine auf die     Baugrubensohle    unter Wasser ein  gebrachte Betonsohle, in die die Sohlenanker zur  Aufnahme des auf der Betonsohle wirkenden Auf  triebes einbinden, verhindert nach Erhärtung des  Betons und     anschliessendem    Leerpumpen des in der  Baugrube angesammelten Grundwassers zusammen      mit der wasserdichten Umschliessung das Eindringen  von weiterem Wasser in die Baugrube, so dass dann  die Ausführung der eigentlichen Bauarbeiten in was  serfreier Baugrube erfolgen kann.  



  Soweit nach Leerpumpen der Baugrube durch  den dann auftretenden Auftrieb auf die Betonsohle,  etwa infolge elastischer Formänderung der Sohlen  anker, sich zwischen Beton- und     Baugrubensohle    ein  Spalt bildet, kann dieser durch     Injektionen    durch die  Betonsohle hindurch,     vornehmlich    mittels Zement  milch, geschlossen werden.  



  Die Sohlenanker können beispielsweise aus Stahl  oder Drahtseil bestehen, wobei das untere Ende der  Ankerstange mit einer Ankerplatte in Eisen- oder  Betonkonstruktion fest verbunden ist. Zweckmässiger  weise ragen die Sohlenanker noch aus der einge  brachten     Unterwasserbetonsohle    heraus, so dass sie  später auch in den eigentlichen Konstruktionsbeton  einbinden. In diesem Falle braucht bei der     Dimen-          sionierung    des Bauwerkes selbst der Wasserauftrieb  so weit nicht mehr in Rechnung gesetzt zu werden,  als dieser bereits von den Sohlenankern und der     Un-          terwasserbetonsohle    aufgenommen wird.  



  Zuweilen kann die     Unterwasserbetonsohle    bereits  so ausgeführt werden, dass sie später einen Teil des  zu errichtenden Bauwerkes, wie z. B. die Sohle einer  Schleuse, eines Docks oder Tunnels bildet. Die Ober  fläche des Unterwasserbetons kann auch als Teil der  Baugrube ausgebildet werden, d. h. der Konstruk  tionsbeton des Bauwerks besteht in seinem unteren  Teil aus Beton oder Stahlbeton, der unter Wasser  eingebracht wurde und während des Baues gleich  zeitig als Schutz gegen Wassereintritt in die Baugrube  diente.  



  Die Einbringung von     senkrechten    Sohlenankern  in der     Baugrubensohle    und die Einbindung dieser  Anker in den Bauwerksbeton zur Aufnahme des  Wasserauftriebs ist zwar bekannt, jedoch musste vor  Ankereinbringung als Bauhilfsmassnahme zunächst  eine wasserfreie Baugrube, beispielsweise durch       Grundwasserabsenkung,    hergestellt werden. Nach  vorliegender Erfindung ist die Einbringung der Soh  lenanker unter Wasser jedoch selbst     Hilfsbaumass-          nahme,    die dem Zweck dient, eine wasserfreie Bau  grube an Stelle einer Wasserhaltung oder Druck  luftgründung herzustellen.  



  Naturgemäss erfordert die     Einbringung    der Soh  lenanker unter Wasser die Lösung verschiedener  Probleme, denn die Anker müssen an ihrem oberen  Ende, also unter Wasser, eine Verbindung besitzen,  welche vom Arbeitspodium aus nach Einbringen  des Ankers gelöst werden kann. Sie wird zweck  mässigerweise so kräftig ausgebildet, dass vor Lösung  der Verbindung unter Wasser jeder Anker einer  kurzen Probebelastung unterworfen werden     kann.     Bei Stahlankern     kann    diese Verbindung z. B. aus  einer     Stahlmuffe        mit    Gewinde bestehen, wenn die  Verbindung des weiter nach oben zur Arbeitsbühne  führenden Hilfsgestänges ein gegen Aufdrehen ge  sichertes Gewinde besitzt.

   Bei     Drahtseilankern    endet    beispielsweise das obere Seilende in einer sogenannten  Seilbirne. Die Seilbirne kann in einem sogenannten  Fahrstuhl hängen, wie er in der     Tiefbohrtechnik    be  kannt ist. Die Schliessung des Fahrstuhles, d. h. die  Herstellung der Verbindung unter Wasser, geschieht  zweckmässig durch einen hydraulischen Kolben, wel  cher vom Arbeitspodium aus bedient wird, während  die     Schliessung    durch eine in den Fahrstuhl einge  baute Feder bei Wegnahme des     Pressdruckes    erfolgen  kann.  



  Wenn man sich die bekannten Vorteile einer An  kerspannung zunutze machen will, müssen die nach  der Einbringung der Anker unter Wasser gelösten  oberen Enden der Anker wieder mit kräftigen Zug  vorrichtungen von über Tage her verbunden und vor  dem     Betoniervorgang    in     Vorspannung        versetzt    wer  den können. Bei Stahlankern enthält z. B. das untere  Ende des Zuggestänges eine Führungsglocke, mittels  derer der Gewindezapfen in die Muffe des oberen  Endes des Ankers eingeführt werden kann. Durch  geführte Versuche haben ergeben, dass ein grobes  konisches     Spritzgewinde    sich am besten zu diesem  Zweck eignet.  



  Werden jedoch Seilanker verwendet, so kann man  beispielsweise die Seilbirne am oberen Ende des  Ankers mit einem leichten Seil verbunden lassen,  nachdem der Anker versenkt ist. Vor dem Betonie  ren der Sohle wird der Anker durch das an die Seil  birne angeschlossene Seil von der Arbeitsbühne aus  aufgerichtet. Wenn der Seilanker vorgespannt wer  den soll, wird eine entsprechend starke Zugvorrich  tung mit der Seilbirne unter Wasser verbunden.  



  Das erfindungsgemässe Gründungsverfahren er  setzt nicht nur in vielen Fällen eine viel teurere       Druckluftgründung,    sondern bietet z. B. auch in den  Fällen Vorteile, in welchen die Herstellung einer  wasserfreien Baugrube mittels     Grundwasserabsen-          kung    oder     offener    Wasserhaltung auf Schwierigkeiten  stösst. Diese können in der Bodenbeschaffenheit be  gründet sein. Ein sehr durchlässiger Boden ergibt  insbesondere bei einer tiefen Absenkung grosse zu  pumpende Wassermengen, was bei einer langen Bau  zeit zu Unwirtschaftlichkeit führt. Häufig sind auch  die Platzverhältnisse auf der Baustelle so beengt,  dass die Anlage einer Wasserhaltung räumlich kaum  möglich ist.

   Oft bringt auch eine Wasserhaltung in  der näheren und weiteren Umgebung der Baugrube  die Gefahr mit sich, dass Bodensetzungen auftreten,  wie beispielsweise bei U-Bahn-Bauten im Stadtgebiet.  



  Bei dem vorgeschlagenen Verfahren kann die       Unterwasserbetonsohle    nach einer oder mehreren Sei  ten geneigt sein, wie beispielsweise bei einer Helling.  An den Stellen, wo diese geneigte Betonsohle selbst  aus dem Grundwasser oder offenem Wasser heraus  ragt, erübrigt sich naturgemäss eine dichte     Umschlies-          sung.     



  Die Zeichnung zeigt als Beispiel schematisch zwei  verschiedene Bauzustände, und zwar zeigt       Fig.    1 einen Querschnitt durch eine mit Grund  wasser angefüllte Baugrube, welche nach Herstellung      einer dichten Umschliessung unter Wasser ausgehoben  wurde. In die     Baugrubensohle    werden von schwim  menden Pontons aus Sohlenanker unter Wasser nach  dem Rütteldruckverfahren versenkt.  



       Fig.    2 zeigt einen Querschnitt durch die gleiche  Baugrube. Die Sohlenanker sind fertig eingebracht.  Es wird der     Betoniervorgang    der Betonsohle unter  Wasser von den schwimmenden Pontons aus gezeigt.  



       Fig.    3 zeigt eine Ausbildung einer Hilfseinrich  tung für die Ankereinbringung und die     Vorspannung     unter Wasser, wenn der Ankerschaft aus einer Stahl  stange besteht,       Fig.    4 eine Ausbildung einer Hilfsvorrichtung für  die Ankereinbringung und die     Vorspannung    unter  Wasser, wenn der Ankerschaft aus einem Stahlseil  besteht.  



  In     Fig.    1 ist die Baugrube 1 mit dem Grund  wasserstand 1 unter Wasser ausgehoben, nachdem  zuvor die wasserdichte     Baugrubenumschliessung    3  hergestellt wurde. Von schwimmenden Pontons 4 aus  werden die Sohlenanker 5 mittels zweier     Tiefenrüttler     6 versenkt.  



       Fig.2    zeigt den Querschnitt der gleichen Bau  grube. Die Sohlenanker 5 sind fertig versenkt. Von  den schwimmenden Pontons 4 aus geschieht die Ein  bringung des Sohlenbetons 7 durch den     Einfülltrich-          ter    8 und die Rohrleitung 9. Aus der unter Wasser  eingebrachten Betonsohle 7 ragen die oberen Enden  10 der Sohlenanker 5 zwecks Verbindung mit dem  später nach Leerpumpen der Baugrube einzubringen  den Bauwerksbeton heraus.  



       Fig.3    zeigt den Stahlanker 5 mit den beiden       Betonankerplatten    11. Der konische Gewindezapfen  12 am oberen Ende des Stahlankers kann unter  Wasser von der Arbeitsbühne aus gelöst werden.  Eine etwaige Gewindeverbindung 13 des Gestänges  14 ist gegen Verdrehen gesichert. Am unteren Ende  des Gestänges 14 befindet sich die Gewindemuffe 15  mit konischem Spitzgewinde. An die Gewindemuffe  15 ist die Glocke 16 befestigt, die zur etwaigen  Wiederherstellung der Verbindung unter Wasser  dient, wie beispielsweise beim späteren     Vorspannen     der Anker.  



       Fig.    4 zeigt das Stahlseil 17 mit den beiden     Be-          tonankerplatten    11. Am oberen Ende des Stahlseiles  befindet sich die Seilbirne 18. An der Seilbirne 18  ist ein Hilfsseil 19 befestigt. Mit diesem Hilfsseil 19    wird vor dem Betonieren unter Wasser der     Seilanker     17 aufgerichtet. Die Seilbirne 18 hängt     während    sei  ner Einbringung und seiner eventuellen     Vorspannung     in einem Fahrstuhl 20.

   Der Fahrstuhl 20 kann unter  Wasser von der Arbeitsbühne aus geschlossen wer  den     mit        Hilfe    einer eingebauten kleinen     hydraulischen     Presse mit Kolben 21 und dem     Pressschlauch    22.  Durch Wegnahme des Druckes wird der Fahrstuhl 20  durch die eingebaute Feder 23 wieder     geöffnet.    Soll  der Seilanker 17 vorgespannt werden,     kann    das Hilfs  seil 19 als Leitseil dienen, um den Fahrstuhl 20  mit dem Gestänge 24 unter Wasser genau über die  Seilbirne 18 zu führen.



  Method for making a watertight excavation with a floor below the existing water table This invention relates to a method for making a watertight construction pit with a floor below the existing water table.



  The foundation of structures below the groundwater level in an anhydrous excavation is generally carried out under the protection of a groundwater lowering or open dewatering. In the case of very difficult groundwater conditions, compressed air foundations are used, and at very great depths, freeze foundations are used. There are also known methods of founding structures below the water table in an anhydrous excavation pit without dewatering by producing a tight enclosure and a tight excavation bottom.

   It is already known to produce an underwater concrete base as a dense excavation base. However, until now such a base always had to be dimensioned as a heavyweight base, unless it was a very narrow excavation pit. In some cases the existing soil types also allow the creation of a water-free excavation by injecting the water-permeable soil. Injections carried out with chemicals for the production of a dense construction pit base have so far resulted in insufficient mechanical strength of the injected soil.

   Injection through cement also requires a high and at the same time uniform permeability of the soil so that the relatively coarse cement grain can penetrate into the cavities of the soil without, on the other hand, the injected material being able to flow off uncontrollably through soil layers of greater permeability. In addition, when making a waterproof sole through injections, a large amount of floor overlay is necessary so that the required pressure can be applied during the injection.



  To avoid these disadvantages, it is an object of the invention to produce a tight excavation below the water table without having to lower the ground water or freeze the ground or have to run the bottom of the pit as a heavyweight sole.



  The method for producing a watertight excavation pit with a floor below the existing water table and inside a permeable soil material is characterized according to the invention in that parts for the formation of tight enclosing walls are first introduced into the soil and only then the enclosed soil excavates and then anchors attached to the permeable soil, with which the concrete forming the bottom is connected and that the excavation pit is emptied after it has solidified.



  The present method should expediently avoid uncontrollable injections for the production of a dense excavation base during the production of the excavation pit and such injections may only be made to fill gaps between the base of the excavated pit and the concrete base placed on it.



  A concrete base placed under water on the base of the construction pit, in which the base anchors are incorporated to absorb the uplift acting on the concrete base, prevents further water from penetrating after the concrete has hardened and the groundwater collected in the construction pit has been pumped out, together with the watertight enclosure the construction pit, so that the actual construction work can then be carried out in what is free of the construction pit.



  If, after the excavation is pumped out, a gap forms between the concrete and excavation base due to the buoyancy that then occurs on the concrete base, for example as a result of elastic deformation of the base anchors, this gap can be closed by injections through the concrete base, primarily with cement milk.



  The sole anchors can consist of steel or wire rope, for example, with the lower end of the anchor rod being firmly connected to an anchor plate in an iron or concrete structure. The base anchors expediently protrude from the underwater concrete base so that they are later integrated into the actual structural concrete. In this case, when dimensioning the structure itself, the water buoyancy need not be taken into account to the extent that it is already absorbed by the base anchors and the underwater concrete base.



  Sometimes the underwater concrete floor can already be designed so that it will later be part of the structure to be constructed, such as B. forms the bottom of a lock, a dock or tunnel. The upper surface of the underwater concrete can also be formed as part of the construction pit, i.e. H. The lower part of the construction concrete of the structure consists of concrete or reinforced concrete that was placed under water and at the same time served as protection against water ingress into the excavation pit during construction.



  The introduction of vertical base anchors in the base of the construction pit and the integration of these anchors into the structural concrete to absorb the water buoyancy is known, but as an auxiliary construction measure, a water-free construction pit had to be created, for example by lowering the groundwater, before the anchors were installed. According to the present invention, the introduction of the sole anchor under water is itself an auxiliary construction measure, which serves the purpose of creating a water-free construction pit instead of a dewatering or pressurized air foundation.



  Naturally, the introduction of the sole anchor under water requires the solution of various problems, because the anchors must have a connection at their upper end, i.e. under water, which can be released from the work platform after the anchor has been introduced. It is expediently made so strong that each anchor can be subjected to a brief test load before the connection under water is released. In the case of steel anchors, this connection can e.g. B. consist of a threaded steel sleeve if the connection of the auxiliary rods leading up to the work platform has a thread secured against turning ge.

   With wire rope anchors, for example, the upper end of the rope ends in a so-called rope pear. The rope pear can hang in a so-called elevator, as it is known in deep drilling technology. The closure of the elevator, d. H. the connection under water is conveniently done by a hydraulic piston, wel cher is operated from the work platform, while the closing can be done by a built-in spring in the elevator when the pressure is removed.



  If you want to take advantage of the well-known advantages of an anchor tension, the upper ends of the anchor loosened after the anchor is inserted under water must be connected again with powerful pulling devices from above days and put in bias before the concreting process who can. For steel anchors z. B. the lower end of the pull rod a guide bell by means of which the threaded pin can be inserted into the sleeve of the upper end of the anchor. Conducted tests have shown that a coarse conical injection thread is best suited for this purpose.



  However, if rope anchors are used, the rope pear at the top of the anchor can be left connected to a light rope after the anchor has been sunk. Before the bottom is concreted, the anchor is raised from the working platform using the rope connected to the rope pear. If the rope anchor is to be pre-tensioned, a correspondingly strong pulling device is connected to the rope pear under water.



  The foundation method according to the invention it not only sets in many cases a much more expensive compressed air foundation, but also offers z. B. Advantages also in cases in which the creation of a water-free excavation pit by means of lowering the groundwater or open dewatering encounters difficulties. These can be due to the nature of the soil. A very permeable soil results in large amounts of water to be pumped, especially in the case of a deep subsidence, which leads to inefficiency in a long construction period. Often the space on the construction site is so cramped that it is hardly possible to install a water drainage system.

   Dewatering in the near and far surroundings of the excavation often also brings with it the risk of subsidence, for example in the case of underground railway structures in urban areas.



  In the proposed method, the underwater concrete floor can be inclined after one or more Be th, such as a slipway. At the points where this inclined concrete base protrudes from the groundwater or open water, a tight enclosure is naturally not necessary.



  The drawing shows, as an example, schematically two different stages of construction, namely FIG. 1 shows a cross section through a construction pit filled with ground water, which was dug under water after a tight enclosure had been produced. Floating pontoons made of base anchors are sunk under water into the base of the excavation using the vibration pressure method.



       Fig. 2 shows a cross section through the same construction pit. The sole anchors are already installed. The process of concreting the concrete base under water from the floating pontoons is shown.



       Fig. 3 shows an embodiment of an auxiliary device for the anchor introduction and bias under water when the anchor shaft consists of a steel rod, Fig. 4 shows an embodiment of an auxiliary device for the anchor introduction and the bias under water when the anchor shaft consists of a steel cable .



  In Fig. 1, the construction pit 1 with the ground water level 1 is excavated under water after the waterproof construction pit enclosure 3 was previously made. The sole anchors 5 are sunk from floating pontoons 4 by means of two depth vibrators 6.



       Fig.2 shows the cross section of the same construction pit. The sole anchors 5 are completely sunk. From the floating pontoons 4, the concrete base 7 is introduced through the filling funnel 8 and the pipeline 9. The upper ends 10 of the base anchors 5 protrude from the concrete base 7 introduced under water for the purpose of connecting to the excavation pit to be introduced later after pumping out Structural concrete out.



       3 shows the steel anchor 5 with the two concrete anchor plates 11. The conical threaded pin 12 at the upper end of the steel anchor can be released from the work platform under water. Any threaded connection 13 of the rod 14 is secured against rotation. At the lower end of the rod 14 is the threaded sleeve 15 with a conical point thread. The bell 16 is attached to the threaded sleeve 15 and is used to restore the connection under water, for example when the anchor is later tensioned.



       4 shows the steel cable 17 with the two concrete anchor plates 11. The cable pear 18 is located at the upper end of the steel cable. An auxiliary cable 19 is attached to the cable pear 18. With this auxiliary rope 19, the rope anchor 17 is erected before concreting underwater. The cable pear 18 hangs in an elevator 20 during its introduction and its possible pretensioning.

   The elevator 20 can be closed under water from the work platform with the help of a built-in small hydraulic press with piston 21 and the press hose 22. By removing the pressure, the elevator 20 is opened again by the built-in spring 23. If the rope anchor 17 is to be pre-tensioned, the auxiliary rope 19 can serve as a guide rope to guide the elevator 20 with the linkage 24 under water exactly over the cable pear 18.

 

Claims (1)

PATENTANSPRUCH Verfahren zur Herstellung einer wasserdichten Baugrube mit einer unterhalb des anstehenden Grundwasserspiegels befindlichen Sohle und inner halb eines durchlässigen Bodenmaterials, dadurch ge kennzeichnet, dass man zunächst Teile zur Bildung von dichten Umfassungswänden in den Boden ein bringt und erst anschliessend den eingeschlossenen Boden aushebt und hierauf Anker im durchlässigen Boden befestigt, mit denen der die Sohle bildende Beton verbunden wird, und dass man nach dessen Verfestigung die Baugrube lerrpumpt. UNTERANSPRÜCHE 1. PATENT CLAIM A method for producing a watertight excavation pit with a bottom located below the existing groundwater level and inside a permeable soil material, characterized in that parts are first introduced into the soil to form tight enclosing walls and only then the enclosed soil is excavated and anchors are then applied fixed in the permeable soil, with which the concrete forming the bottom is connected, and that the excavation pit is pumped after it has solidified. SUBCLAIMS 1. Verfahren nach Patentanspruch, dadurch ge kennzeichnet, dass ein zwischen Beton- und Baugru- bensohle auf Grund des Wasserauftriebs nach Leer pumpen der Baugrube sich bildender Spalt durch Injektionen durch die Betonsohle hindurch, vornehm lich mittels Zementmilch, geschlossen wird. 2. Verfahren nach Patentanspruch und Unter anspruch 1, dadurch gekennzeichnet, dass so lange Sohlenanker verwendet werden, dass sie aus der ein gebrachten Unterwasserbetonsohle noch nach oben zwecks späterer Einbindung in den eigentlichen Kon struktionsbeton herausragen. 3. Method according to patent claim, characterized in that a gap that forms between the concrete and construction pit base due to the buoyancy of water after pumping empty of the construction pit is closed by injections through the concrete base, primarily by means of cement milk. 2. The method according to claim and sub-claim 1, characterized in that sole anchors are used for so long that they still protrude upwards from the underwater concrete sole brought for the purpose of later integration in the actual construction concrete. 3. Verfahren nach Patentanspruch, dadurch ge kennzeichnet, dass die Unterwasserbetonsohle derart in der Baugrube ausgeformt wird, dass sie in ihrer Formgebung dem zu errichtenden Bauwerk in diesem Bereich entspricht. Method according to patent claim, characterized in that the underwater concrete base is shaped in the construction pit in such a way that its shape corresponds to the structure to be erected in this area.
CH184562A 1962-02-15 1962-02-15 Process for the production of a watertight construction pit with a floor below the existing water table CH402750A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH184562A CH402750A (en) 1962-02-15 1962-02-15 Process for the production of a watertight construction pit with a floor below the existing water table

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH184562A CH402750A (en) 1962-02-15 1962-02-15 Process for the production of a watertight construction pit with a floor below the existing water table

Publications (1)

Publication Number Publication Date
CH402750A true CH402750A (en) 1965-11-15

Family

ID=4219949

Family Applications (1)

Application Number Title Priority Date Filing Date
CH184562A CH402750A (en) 1962-02-15 1962-02-15 Process for the production of a watertight construction pit with a floor below the existing water table

Country Status (1)

Country Link
CH (1) CH402750A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627206A (en) * 2020-11-18 2021-04-09 武汉科技大学 Simple and easy processing apparatus of local little infiltration of deep basal pit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627206A (en) * 2020-11-18 2021-04-09 武汉科技大学 Simple and easy processing apparatus of local little infiltration of deep basal pit
CN112627206B (en) * 2020-11-18 2024-03-29 武汉科技大学 Local micro-penetration simple treatment device for deep foundation pit

Similar Documents

Publication Publication Date Title
DE1583833B1 (en) Arrangement for underwater work
DE2359540A1 (en) UNDERWATER FUNDABLE EQUIPMENT AND PROCEDURE FOR ESTABLISHING IT ON THE SEA FLOOR
DE3445965A1 (en) COMPACTING DEPTH, METHOD AND DEVICE FOR PRODUCING THE SAME
DE2365950A1 (en) POTING PROCESS FOR AN OFFSHORE CONSTRUCTION
DE10239278B4 (en) Foundation for hydraulic structures
DE10013446A1 (en) Method and device for producing an in-situ concrete pile
EP0109397B1 (en) Hollow foundation element and manufacturing method thereof
DE2229383C3 (en)
DE2240935C3 (en) Process for the production of an underwater concrete base secured against buoyancy and device for carrying out the process
CH402750A (en) Process for the production of a watertight construction pit with a floor below the existing water table
DE3524253C1 (en) Method and apparatus for producing a shaft, in particular for mining
AT241362B (en) Procedure for the foundation of structures below the water table
DE19525590C2 (en) Construction of an excavation pit with anchoring below the water table
DE970760C (en) Process for the production of concrete piles in the ground by pressing the sunk borehole filled with aggregate with cement milk or the like while gradually withdrawing the press pipe
DE3716750A1 (en) Method of constructing and sinking foundation structures
CH312082A (en) Method for producing a seal which has the purpose of shielding a room against the ingress of water from the adjacent soil.
AT225621B (en) Method of manufacturing storage tanks
DE609238C (en) Method for producing a sufficiently watertight construction pit enclosure within the soil surrounding the pit
DE873529C (en) Procedure to increase the stability of all types of foundation structures
DE2851619A1 (en) Concrete post foundation hole prodn. - involves lowering pipe into ground using vibrator and core is removed using differential air pressure
AT388406B (en) Pile foundation structure and apparatus and concreting tank for producing the same
DE19739106C1 (en) Construction method for foundations etc. in water-filled excavation
DE682798C (en) Method for observing soil changes in slope layers
DE2710456A1 (en) Masonry wall inclined pile and underpinning - is made of reinforced concrete with common reinforcing core to base of wall
AT238107B (en) Procedure for the foundation of prefabricated structures