CH347147A - Process for establishing an underground gallery containing an armored pipe laid in a concrete coating, gallery obtained by the method and pipe for its implementation - Google Patents

Process for establishing an underground gallery containing an armored pipe laid in a concrete coating, gallery obtained by the method and pipe for its implementation

Info

Publication number
CH347147A
CH347147A CH347147DA CH347147A CH 347147 A CH347147 A CH 347147A CH 347147D A CH347147D A CH 347147DA CH 347147 A CH347147 A CH 347147A
Authority
CH
Switzerland
Prior art keywords
drains
gallery
pipe
cement
concrete coating
Prior art date
Application number
Other languages
French (fr)
Original Assignee
Ind Soc Gen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ind Soc Gen filed Critical Ind Soc Gen
Publication of CH347147A publication Critical patent/CH347147A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • CCHEMISTRY; METALLURGY
    • C12BIOCHEMISTRY; BEER; SPIRITS; WINE; VINEGAR; MICROBIOLOGY; ENZYMOLOGY; MUTATION OR GENETIC ENGINEERING
    • C12PFERMENTATION OR ENZYME-USING PROCESSES TO SYNTHESISE A DESIRED CHEMICAL COMPOUND OR COMPOSITION OR TO SEPARATE OPTICAL ISOMERS FROM A RACEMIC MIXTURE
    • C12P1/00Preparation of compounds or compositions, not provided for in groups C12P3/00 - C12P39/00, by using microorganisms or enzymes
    • C12P1/06Preparation of compounds or compositions, not provided for in groups C12P3/00 - C12P39/00, by using microorganisms or enzymes by using actinomycetales
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Zoology (AREA)
  • Wood Science & Technology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Architecture (AREA)
  • Mycology (AREA)
  • General Chemical & Material Sciences (AREA)
  • Microbiology (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Biotechnology (AREA)
  • Health & Medical Sciences (AREA)
  • Biochemistry (AREA)
  • Bioinformatics & Cheminformatics (AREA)
  • General Engineering & Computer Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Genetics & Genomics (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

  

  Procédé pour l'établissement d'une galerie souterraine  contenant une conduite blindée posée dans un enrobage de béton,  galerie obtenue par le procédé et conduit pour sa     mise    en     aeuvre       Le présent brevet a pour objet un procédé pour       l'établissement    d'une galerie souterraine contenant  une     conduite        blindée    posée dans un enrobage de  béton.     L'expérience    prouve que les pressions exter  nes subies par une     conduite    blindée     posée    dans une  galerie sont souvent plus, élevées que les pressions  internes.

   Ces pressions externes sont dues, à la pres  sion de l'eau incluse dans les     interstices    du sol ou de  la roche qui ne peut     être    évacuée. En conséquence,  il est généralement nécessaire de prévoir l'épaisseur  de la     conduite    blindée en fonction des pressions ex  ternes auxquelles cette conduite sera     soumise.    Or,

   le  calcul montre que     cette    épaisseur     nécessaire    pour       supporter    les     poussées    externes est souvent nettement  plus grande que l'épaisseur qui serait nécessaire pour       supporter    la pression     interne.    En réduisant les pous  sées externes agissant sur la conduite, il serait donc  possible de réduire l'épaisseur de la conduite     blindée     et donc de réduire son prix de revient : c'est le but  que vise le procédé, objet du présent brevet ;

   il est       caractérisé    par le fait qu'on noie au moins partielle  ment dans ledit enrobage de béton, coulé entre le  terrain et le blindage, un     collecteur    et des conduits  reliés à ce collecteur,     afin    de provoquer une détente  des pressions interstitielles et donc une réduction des  pressions     exercées    sur les parois externes de la con  duite blindée.  



  Le brevet a également pour objet une galerie  avec     conduite        blindée,    obtenue par     ce        procédé,    carac  térisée par le fait qu'elle     comporte    des conduits dis  posés autour de la conduite blindée et noyés au moins  partiellement dans un enrobage de béton     remplissant       l'espace compris entre la conduite     blindée    et les  parois de la galerie et par le fait que     ces    conduits  sont reliés à un     collecteur    également noyé dans     cet     enrobage de béton.  



  Le brevet a encore pour objet un conduit pour  la mise en     #uvre    du procédé, caractérisé par le fait  qu'il     présente    une paroi     s'opposant    au passage des  grains de ciment, lors de la     mise    en place de l'enro  bage de béton et d'injections de ciment pour renfor  cer ou étancher le rocher.  



  Le dessin annexé illustre, schématiquement et à  titre d'exemple, une forme d'exécution d'une galerie  traversée par une     conduite        blindée    et réalisée selon  le procédé.  



  La     fig.    1 est une vue en     coupe    longitudinale à  travers la galerie et une     partie    du     terrain.     



  La     fig.    2 est une vue en     coupe    de la galerie et du  terrain à l'endroit d'une faille.  



  La     fig.    3 est une vue en     coupe    d'un drain annu  laire.  



  La     fig.    4 est une vue     d'un,    tronçon de ce drain.  La     fig.    5 est une vue en coupe d'un drain radial.  La     fig.    6 est une vue d'un tronçon de ce     drain.     Selon le dessin annexé, une galerie 1 est creusée  dans le rocher en vue de la pose d'une conduite       blindée    2.     11    est clair que     cette    galerie draine l'eau  suintant à travers la roche.

   Or,     afin,    d'éviter la cor  rosion de la conduite 2 et pour faire collaborer le           terrain    à la résistance de l'ensemble, il est d'usage  courant de couler un enrobage de béton 3 dans l'es  pace compris entre la     conduite    et les parois de la  galerie. Or, bien que ce béton puisse présenter une  quantité de fissures, et qu'un canal collecteur 4 soit  ménagé dans la masse de cet enrobage de béton       celui-ci    n'est pas     suffisamment    perméable à l'eau  pour provoquer la détente des pressions interstitiel  les dans les fissures.

   Les mesures     effectuées    dans  des ouvrages     réalisés    ont montré que cette quantité  d'eau peut     atteindre    de 10 à 40 litres par seconde et  par     kilomètre    de     galerie.    Cette quantité d'eau ne       pouvant    pas être évacuée à travers l'enrobage de  béton,     il    est clair que la nappe qui se forme autour  de la conduite     blindée    soumet celle-ci à de très for  tes pressions externes qui sont généralement d'autant  plus élevées que la hauteur du terrain au-dessus de  la     galerie    est grande.  



  Selon le procédé     décrit,    on     place,    autour de la  conduite blindée 2, des     drains    annulaires 5, de pré  férence à une     certaine    distance de cette     conduite,     afin que     ces        drains    soient situés     dans    une zone de  l'enrobage de béton présentant de nombreuses fissu  res. Ces drains 5 sont en une matière     imputrescible     et perméable à l'eau, mais ne laissant pas passer le  ciment.

   A cet     effet,    on peut     utiliser    des drains, dont  les parois 7 sont en tissu de verre, par exemple, dont  la dimension des mailles est choisie de manière -à  retenir les     suspensions    de ciment. Ce tube, à parois  non perméables au ciment, est rempli de sable 6, par  exemple,     afin    de lui     conférer    sa rigidité.  



       Les    deux extrémités de chaque drain     annulaire     sont fermées à l'aide d'un     lien    à la manière d'une  saucisse et sont engagées dans. des manchons 8 du  canal     collecteur    4, disposé parallèlement à la con  duite 2. Ce     collecteur    est formé d'un tube en ciment,  par exemple,     comportant    à intervalles réguliers des  ouvertures qui peuvent être obturées par des couver  cles c munis desdits     manchons    8. On coule alors  l'enrobage de béton 3     dans,    l'espace compris entre la  conduite 2 et les parois de la galerie 1. Les drains  5 et le collecteur 4 sont alors noyés dans la masse  de béton.

   Les suspensions de ciment ne peuvent pas  pénétrer à l'intérieur de ces drains, de sorte qu'il  n'existe aucun risque d'obturation de     ces    drains par  du ciment.  



  Dans une variante, le     collecteur    peut également  être formé d'un tube métallique sans     joint    et muni  des     manchons    8 métalliques. Pendant la mise en place  du béton et les injections de ciment, on fait passer  de l'eau     dans    le     collecteur    4, afin de laver et d'em  mener, au fur et à mesure, le     ciment    qui pourrait  éventuellement entrer dans ce     collecteur    par les man  chons 8.  



  Les essais effectués ont montré que, en utilisant  des drains 5 remplis de sable, tels que     décrit,    ces  drains fonctionnent     parfaitement        correctement    après       mise    en place de l'enrobage de béton 3, de sorte  qu'ils sont susceptibles d'évacuer facilement l'eau de  suintement drainée par la galerie.

      Il est clair que, selon la nature de la roche, la       distance    a entre drains annulaires sera choisie plus  ou moins grande, mais les calculs effectués ont mon  tré que des drains de 12 à 15 cm de diamètre, placés  à une distance de 5 mètres les uns des autres, per  mettent d'obtenir une évacuation pratiquement com  plète de l'eau drainée par la galerie ou, dans tous  les cas, une évacuation     suffisante    pour que les pres  sions     exercées    par l'eau sur les parois externes de la  conduite blindée 2 soient inférieures aux pressions  internes.

   De cette manière, il est possible de prévoir  l'épaisseur de la conduite blindée 2, non plus, comme       jusqu'à    ce jour, suffisante pour     supporter    les pres  sions     extérieures    agissant sur elle, mais seulement       suffisante    pour résister aux pressions régnant à l'in  térieur.  



  Les failles i traversées par la galerie sont géné  ralement étanchées et     consolidées    par des     injections     de ciment. Dans le procédé décrit à l'endroit d'une  faille i, la roche est forée sur une profondeur de 2  à 3 mètres à l'aide d'un fleuret, puis on introduit,  dans     ces    forages, des drains 9 formés d'un tube  rigide 10 fendu sur toute sa longueur et recouvert  d'une gaine 11 en une matière imputrescible et per  méable à l'eau, mais s'opposant au passage des sus  pensions de ciment. Après mise en place de ces  drains 9, on     injecte    sous pression de la manière  habituelle du ciment dans le terrain, afin de consoli  der celui-ci et d'étancher au moins partiellement la  faille i.  



  De     bons    résultats sont obtenus à l'aide de drains  9 d'un diamètre de 3 à 4 cm dont la paroi interne  10 rigide est en. une matière synthétique résistant à  la     corrosion,    tandis que la     gaine    11 est formée d'un  tube en fibre de verre dont la dimension des mailles  est choisie de     manière    à être perméable à l'eau, mais  s'opposant au passage des suspensions de ciment.  



  Aucune     précaution    spéciale ne doit être prise  pour relier des drains 9 aux     drains    5. Il     suffit,    en  fait, de poser     l'extrémité    des     drains    9 sur la surface  des.     drains    5     pour        réaliser    une     liaison    entre     ceux-ci     et     obtenir    l'évacuation des eaux     filtrant    à travers la  faille i.  



  Dans le cas d'une zone de la galerie très mouillée  mais sans faille     caractérisée,    on effectue une     saignée     circulaire dans la paroi de la     galerie,    puis fore plu  sieurs trous radiaux, par exemple, dans lesquels on  introduit des     drains    9. On pose alors un ou plusieurs  drains.     annulaires        secondaires    dans la saignée et rac  corde     ceux-ci    au collecteur 4. Ce drain annulaire       secondaire    est en tous points semblable aux drains  annulaires 5     décrits    plus haut.

   Ce travail terminé, on  peut     remplir    la saignée d'une matière connue sur le  marché sous la désignation de       Gunit     .  



       Ainsi,    l'eau suintant à travers le rocher est obli  gatoirement captée par l'un ou, l'autre des drains  radiaux ou annulaires secondaires, puisqu'il n'existe  plus d'issue s'ouvrant sur la galerie.      De ce qui précède, il est aisé     pour    tout homme  du métier de se rendre compte des avantages que  peut présenter, en pratique, le procédé décrit et des       économies    qu'il permet de réaliser, tout en assurant  une grande sécurité     contre    des     avaries,    de la con  duite blindée grâce à la réduction des pressions exter  nes auxquelles elle est soumise.  



  Il est clair que de multiples variantes de mise en       oeuvre    du procédé peuvent être prévues, en particu  lier les gaines filtrantes 7 et 11 des drains 5 et 9  peuvent être prévues en toute matière imputrescible,  perméable à l'eau, mais s'opposant au passage des  suspensions de ciment. En outre, le tube 10 des  drains 9 peut être prévu en toute matière présentant  une rigidité     suffisante    pour maintenir la forme du  drain. Ce tube peut soit être fendu sur toute sa lon  gueur, comme décrit ci-dessus, soit comporter une  multitude de perforations permettant le passage de  l'eau.

   Il est clair que les drains 5 peuvent présenter  la forme d'un anneau fermé, comme décrit et repré  senté, mais peuvent également présenter la forme  d'un anneau ouvert ou toute autre forme désirée et  permettant de relier un ou plusieurs drains 9 au col  lecteur. De même, les drains 9 sont de     préférence     radiaux, mais sont généralement disposés suivant des  directions définies par les conditions et la nature du  terrain.  



  Il est évident que le     procédé    décrit est     utilisable,     non seulement dans le cas de galeries horizontales,  mais également et surtout dans. le cas de galeries  très inclinées ou de puits.



  Process for the establishment of an underground gallery containing an armored pipe laid in a concrete coating, gallery obtained by the method and conduit for its implementation The present patent relates to a process for the establishment of an underground gallery containing an armored pipe laid in a concrete cover. Experience proves that the external pressures undergone by an armored pipe laid in a gallery are often higher than the internal pressures.

   These external pressures are due to the pressure of the water included in the interstices of the soil or of the rock which cannot be evacuated. Consequently, it is generally necessary to provide the thickness of the armored pipe as a function of the external pressures to which this pipe will be subjected. Gold,

   the calculation shows that this thickness necessary to support the external thrusts is often significantly greater than the thickness which would be necessary to support the internal pressure. By reducing the external thrusts acting on the pipe, it would therefore be possible to reduce the thickness of the armored pipe and therefore to reduce its cost price: this is the aim of the process, the subject of this patent;

   it is characterized by the fact that in said concrete coating, poured between the ground and the shielding, a collector and conduits connected to this collector are at least partially flooded in order to cause a relaxation of the interstitial pressures and therefore a reduction pressure exerted on the outer walls of the shielded pipe.



  The patent also relates to a gallery with armored pipe, obtained by this process, charac terized by the fact that it comprises conduits arranged around the armored pipe and embedded at least partially in a concrete coating filling the space included between the armored pipe and the walls of the gallery and by the fact that these pipes are connected to a collector also embedded in this concrete coating.



  The patent also relates to a conduit for the implementation of the process, characterized in that it has a wall opposing the passage of the cement grains, during the placement of the concrete coating. and injections of cement to reinforce or seal the rock.



  The appended drawing illustrates, schematically and by way of example, an embodiment of a gallery crossed by a shielded pipe and produced according to the process.



  Fig. 1 is a view in longitudinal section through the gallery and part of the land.



  Fig. 2 is a sectional view of the gallery and the land at the location of a fault.



  Fig. 3 is a sectional view of an annular drain.



  Fig. 4 is a view of a section of this drain. Fig. 5 is a sectional view of a radial drain. Fig. 6 is a view of a section of this drain. According to the attached drawing, a gallery 1 is hollowed out in the rock with a view to laying an armored pipe 2. It is clear that this gallery drains the water seeping through the rock.

   However, in order to avoid corrosion of the pipe 2 and to make the ground work together with the resistance of the assembly, it is common practice to pour a concrete coating 3 in the space between the pipe and the walls of the gallery. Now, although this concrete may have a number of cracks, and a collector channel 4 is provided in the mass of this concrete coating, the latter is not sufficiently permeable to water to cause the relaxation of the interstitial pressures. them in the cracks.

   Measurements carried out in completed structures have shown that this quantity of water can reach 10 to 40 liters per second and per kilometer of gallery. As this quantity of water cannot be evacuated through the concrete coating, it is clear that the sheet which forms around the armored pipe subjects it to very strong external pressures which are generally all the more so high that the height of the ground above the gallery is great.



  According to the method described, annular drains 5 are placed around the armored pipe 2, preferably at a certain distance from this pipe, so that these drains are located in an area of the concrete covering exhibiting numerous cracks. res. These drains 5 are made of an imputrescible material permeable to water, but not allowing the cement to pass.

   For this purpose, one can use drains, whose walls 7 are made of glass fabric, for example, the mesh size of which is chosen so as to retain the cement suspensions. This tube, with walls not permeable to cement, is filled with sand 6, for example, in order to give it its rigidity.



       The two ends of each annular drain are closed with a sausage-like tie and are engaged in. sleeves 8 of the collector channel 4, arranged parallel to the duct 2. This collector is formed of a cement tube, for example, comprising at regular intervals openings which can be closed by covers c provided with said sleeves 8. The concrete coating 3 is then poured into the space between the pipe 2 and the walls of the gallery 1. The drains 5 and the collector 4 are then embedded in the mass of concrete.

   Cement suspensions cannot penetrate inside these drains, so that there is no risk of these drains becoming blocked by cement.



  In a variant, the manifold can also be formed from a seamless metal tube and provided with metal sleeves 8. During the placement of the concrete and the cement injections, water is passed through the collector 4, in order to wash and remove, as and when, the cement which could possibly enter this collector through the sleeves 8.



  The tests carried out have shown that, by using drains 5 filled with sand, as described, these drains function perfectly correctly after placing the concrete cover 3, so that they are capable of easily draining the water. seepage water drained by the gallery.

      It is clear that, depending on the nature of the rock, the distance a between annular drains will be chosen more or less, but the calculations carried out have shown that drains of 12 to 15 cm in diameter, placed at a distance of 5 meters from each other, make it possible to obtain a practically complete evacuation of the water drained by the gallery or, in all cases, a sufficient evacuation so that the pressure exerted by the water on the external walls of the pipe shielded 2 are lower than internal pressures.

   In this way, it is possible to provide for the thickness of the armored pipe 2, no longer, as hitherto, sufficient to withstand the external pressures acting on it, but only sufficient to withstand the pressures prevailing at the interior.



  The faults i crossed by the gallery are generally sealed and consolidated by injections of cement. In the process described at the location of a fault i, the rock is drilled to a depth of 2 to 3 meters using a foil, then we introduce, in these drillings, drains 9 formed of a rigid tube 10 split over its entire length and covered with a sheath 11 of a rot-proof material permeable to water, but opposing the passage of the cement suspensions. After placing these drains 9, cement is injected under pressure in the usual way into the ground, in order to consolidate the latter and at least partially to seal the fault i.



  Good results are obtained using drains 9 with a diameter of 3 to 4 cm, the rigid internal wall 10 of which is made of. a synthetic material resistant to corrosion, while the sheath 11 is formed of a fiberglass tube, the mesh size of which is chosen so as to be permeable to water, but opposing the passage of cement suspensions .



  No special precaution should be taken to connect the drains 9 to the drains 5. It suffices, in fact, to lay the end of the drains 9 on the surface of. drains 5 to make a connection between them and obtain the evacuation of the water filtering through the fault i.



  In the case of a very wet but flawless area of the gallery, a circular groove is made in the wall of the gallery, then several radial holes are drilled, for example, into which drains 9 are introduced. one or more drains. secondary annulars in the groove and rac cord these to the collector 4. This secondary annular drain is in all points similar to the annular drains 5 described above.

   Once this work is finished, the bleeding can be filled with a material known on the market under the name of Gunit.



       Thus, the water seeping through the rock is obligatorily captured by one or the other of the secondary radial or annular drains, since there is no longer an outlet opening onto the gallery. From the foregoing, it is easy for any person skilled in the art to realize the advantages which the method described can present, in practice, and the savings which it makes possible to achieve, while ensuring great safety against damage, shielded pipe thanks to the reduction of the external pressures to which it is subjected.



  It is clear that multiple implementation variants of the method can be provided, in particular the filter sheaths 7 and 11 of the drains 5 and 9 may be provided in any rot-proof material, permeable to water, but opposing the passage of cement suspensions. In addition, the tube 10 of the drains 9 can be provided in any material having sufficient rigidity to maintain the shape of the drain. This tube can either be split over its entire length, as described above, or have a multitude of perforations allowing the passage of water.

   It is clear that the drains 5 can have the shape of a closed ring, as described and shown, but can also have the shape of an open ring or any other desired shape and allowing one or more drains 9 to be connected to the neck. reader. Likewise, the drains 9 are preferably radial, but are generally arranged in directions defined by the conditions and the nature of the terrain.



  It is obvious that the method described can be used, not only in the case of horizontal galleries, but also and above all in. the case of very inclined galleries or wells.

 

Claims (1)

REVENDICATIONS I. Procédé pour l'établissement d'une galerie sou terraine contenant une conduite blindée posée dans un enrobage de béton, caractérisé par le fait qu'on noie au moins partiellement dans ledit enrobage de béton, coulé entre le terrain et le blindage, un collec teur et des conduits reliés à ce collecteur afin de provoquer une détente des pressions. intertitielles et donc une réduction des pressions exercées sur les parois externes de la conduite blindée. II. CLAIMS I. Method for establishing an underground gallery containing an armored pipe laid in a concrete coating, characterized by the fact that at least partially flooding in said concrete coating, poured between the ground and the armor, a manifold and conduits connected to this manifold in order to relieve the pressures. intitial and therefore a reduction in the pressures exerted on the outer walls of the armored pipe. II. Galerie avec conduite blindée obtenue par le procédé selon la revendication I, caractérisée par le fait qu'elle comporte des conduits disposés autour de la conduite blindée et noyés au moins partiellement dans un enrobage de béton, remplissant l'espace com pris entre la conduite blindée et les parois de la gale rie et par le fait que ces conduits sont reliés à un collecteur également noyé dans cet enrobage de béton. III. Gallery with armored pipe obtained by the method according to claim I, characterized in that it comprises conduits arranged around the armored pipe and embedded at least partially in a concrete coating, filling the space between the armored pipe and the walls of the tunnel and by the fact that these conduits are connected to a collector also embedded in this concrete coating. III. Conduit pour la mise en oeuvre du procédé selon la revendication I, caractérisé par le fait qu'il présente une paroi s'opposant au passage des grains de ciment lors de la mise en place de l'enrobage de béton et d'injections de ciment pour renforcer et étancher le rocher. Conduit for carrying out the method according to Claim I, characterized in that it has a wall opposing the passage of the cement grains during the placement of the concrete coating and cement injections to strengthen and waterproof the rock. SOUS-REVENDICATIONS 1. Procédé selon la revendication I, caractérisé par le fait que, à l'endroit d'une faille dans la roche, on fore des trous dans le terrain et place dans ceux- ci des drains, qu'on relie aux collecteurs et par le fait qu'on consolide et étanche partiellement le terrain de la faille par injection de ciment sous pression. SUB-CLAIMS 1. A method according to claim I, characterized in that, at the location of a fault in the rock, holes are drilled in the ground and drains are placed therein, which are connected to the. collectors and by the fact that the ground of the fault is partially consolidated and sealed by injection of cement under pressure. 2. Procédé selon la revendication I et la sous- revendication 1, caractérisé par le fait qu'on utilise des conduits présentant une paroi filtrante en. 2. Method according to claim I and sub-claim 1, characterized in that one uses conduits having a filtering wall. une matière imputrescible et perméable à l'eau, et qu'on confère à ces conduits une rigidité suffisante pour supporter les. pressions externes auxquelles ils sont soumis lors de la mise en place de l'enrobage de béton et d'injections de ciment pour, renforcer et étancher le rocher. a rot-proof and water-permeable material, and that these conduits are given sufficient rigidity to withstand them. external pressures to which they are subjected during the placement of the concrete cover and the injections of cement to reinforce and seal the rock. 3. Procédé selon la revendication I et les sous- revendications 1 et 2, caractérisé par le fait que, pen dant la mise en place de l'enrobage de béton, on fait passer de l'eau dans le collecteur, afin. de laver et d'emmener, au fur et à mesure, le béton pouvant pénétrer dans celui-ci. 4. 3. Method according to claim I and sub-claims 1 and 2, characterized in that, during the installation of the concrete coating, water is passed into the collector, so. to wash and remove, as and when, the concrete that can penetrate into it. 4. Procédé selon la revendication I et la sous- revendication 2, caractérisé par le fait que, à l'en droit d'une zone mouillée mais sans faille caractéri sée, on pratique une saignée circulaire dans la paroi du rocher et fore des trous. dans le terrain, puis intro duit des drains dans ces forages, les relie à un con duit posé dans cette saignée et raccordé au collec teur, et enfin remplit cette saignée. Process according to Claim I and sub-Claim 2, characterized in that, in the area of a wet area without characterized fault, a circular groove is made in the wall of the rock and holes are drilled. in the ground, then introduces drains into these boreholes, connects them to a pipe placed in this bleeding and connected to the collector, and finally fills this bleeding. 5. Galerie selon la revendication II, caractérisée par le fait que, à l'endroit d'une faille, elle comporte des drains placés dans des forages pratiqués dans le terrain, ces drains étant reliés à au moins un drain noyé dans du ciment injecté dans le terrain en vue de sa consolidation et de son étanchement. 6. 5. Gallery according to claim II, characterized in that, at the location of a fault, it comprises drains placed in boreholes made in the ground, these drains being connected to at least one drain embedded in injected cement. in the land with a view to its consolidation and waterproofing. 6. Galerie selon la revendication II, caractérisée par le fait que, à l'endroit d'une zone mouillée, elle comporte, d'une part, au moins un drain secondaire noyé dans une saignée pratiquée dans la paroi du rocher et relié au collecteur et, d'autre part, des drains posés dans des forages et reliés audit drain secondaire, et par le fait que cette saignée est ob turée. 7. Gallery according to Claim II, characterized in that, at the location of a wet zone, it comprises, on the one hand, at least one secondary drain embedded in a groove made in the wall of the rock and connected to the collector and , on the other hand, drains placed in boreholes and connected to said secondary drain, and by the fact that this bleeding is blocked. 7. Galerie selon la revendication II et les sous- revendications 5 et 6, caractérisée par le fait que les conduits constitués par les drains disposés autour de la conduite blindée et les drains placés dans des forages pratiqués dans le terrain comportent une paroi filtrante imputrescible, perméable à l'eau, mais s'opposant au passage des, suspensions de ciment. 8. Gallery according to claim II and sub-claims 5 and 6, characterized in that the conduits constituted by the drains arranged around the armored conduit and the drains placed in boreholes made in the ground comprise a rot-proof filtering wall, permeable to water, but opposing the passage of, cement suspensions. 8. Galerie selon la revendication II, caractérisée par le fait que le collecteur présente des ouvertures disposées à intervalles réguliers et obturées chacune par un couvercle muni de manchons pour le raccor dement des drains. 9. Galerie selon la revendication II, caractérisée par le fait que la paroi. filtrante des conduits est constituée par une gaine en, fibre de verre. 10. Gallery according to Claim II, characterized in that the collector has openings arranged at regular intervals and each closed by a cover provided with sleeves for connecting the drains. 9. Gallery according to claim II, characterized in that the wall. filtering of the ducts consists of a glass fiber sheath. 10. Galerie selon la revendication II et la sous- revendication 9, caractérisée par le fait que les drains placés dans les forages sont constitués par un tube rigide muni d'ouvertures permettant le passage de l'eau et recouvert par ladite gaine. 11. Conduit selon la revendication III,. caracté risé par le fait qu'il est rempli de sable et fermé à ses deux extrémités. Gallery according to claim II and sub-claim 9, characterized in that the drains placed in the boreholes consist of a rigid tube provided with openings allowing the passage of water and covered by said sheath. 11. Conduit according to claim III ,. characterized by the fact that it is filled with sand and closed at both ends.
CH347147D 1958-05-31 1958-05-31 Process for establishing an underground gallery containing an armored pipe laid in a concrete coating, gallery obtained by the method and pipe for its implementation CH347147A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH347147T 1958-05-31

Publications (1)

Publication Number Publication Date
CH347147A true CH347147A (en) 1960-06-15

Family

ID=4507892

Family Applications (1)

Application Number Title Priority Date Filing Date
CH347147D CH347147A (en) 1958-05-31 1958-05-31 Process for establishing an underground gallery containing an armored pipe laid in a concrete coating, gallery obtained by the method and pipe for its implementation

Country Status (1)

Country Link
CH (1) CH347147A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2280747A1 (en) * 1974-07-30 1976-02-27 Senn Georg METHOD AND DEVICE FOR MAKING DRAINAGE CHANNELS IN A WALL, IN PARTICULAR TUNNEL
US4247221A (en) * 1978-05-02 1981-01-27 Kali Und Salz Ag Process for lining tunnels
FR2482186A1 (en) * 1980-05-07 1981-11-13 Toyo Bussan Kk DEVICE FOR COLLECTING WATER FILING INTO TUNNEL BY JOINT OR CRACK
AT378239B (en) * 1982-01-29 1985-07-10 Dynamit Nobel Ag SEALING WALLS AGAINST PRESSURE AND OR OR SEPARATE WATER
CN113982631A (en) * 2021-10-29 2022-01-28 成都未来智隧科技有限公司 Tunnel supporting structure and tunnel supporting method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2280747A1 (en) * 1974-07-30 1976-02-27 Senn Georg METHOD AND DEVICE FOR MAKING DRAINAGE CHANNELS IN A WALL, IN PARTICULAR TUNNEL
US4247221A (en) * 1978-05-02 1981-01-27 Kali Und Salz Ag Process for lining tunnels
FR2482186A1 (en) * 1980-05-07 1981-11-13 Toyo Bussan Kk DEVICE FOR COLLECTING WATER FILING INTO TUNNEL BY JOINT OR CRACK
AT378239B (en) * 1982-01-29 1985-07-10 Dynamit Nobel Ag SEALING WALLS AGAINST PRESSURE AND OR OR SEPARATE WATER
CN113982631A (en) * 2021-10-29 2022-01-28 成都未来智隧科技有限公司 Tunnel supporting structure and tunnel supporting method
CN113982631B (en) * 2021-10-29 2024-04-05 成都未来智隧科技有限公司 Tunnel supporting structure and tunnel supporting method

Similar Documents

Publication Publication Date Title
CN207960676U (en) One kind is for spraying pipe network drainage system in anchor single shell lining
CH347147A (en) Process for establishing an underground gallery containing an armored pipe laid in a concrete coating, gallery obtained by the method and pipe for its implementation
CA3062299A1 (en) Method and device for freezing a mass of soil
FR2656821A1 (en)
FR2747703A1 (en) MOLDED WALL WITH CONTINUOUS REINFORCEMENT, PROCESS FOR PRODUCING SUCH A MOLDED WALL IN THE GROUND AND FORMWORK FOR MAKING SUCH A MOLDED WALL
CN203411970U (en) Flexible vacuum preloading type water discharging pipe
CN205918434U (en) Cold region tunnel heat preservation blind pipe
EP0041462B1 (en) Building method for a hydraulically supported house, and such a house
EP3180479B1 (en) Method for renovating a sewer
CN211597433U (en) Pipeline waterproof device extending out of roof
CN204644998U (en) A kind of light and shade double-decker gutter
EP0029400A1 (en) Apparatus for protecting buildings and civil engineering constructions against water and moisture
WO1995000421A1 (en) Method for setting in operation an underground storage cavity for low temperature hydrocarbons and plant for storing low temperature hydrocarbons
CN204491575U (en) Fast vacuum dewatering installation under high-fill roadbed
EP0377541A1 (en) Process and apparatus for anchoring the shieldings of a reinforced-earth wall
CN210194631U (en) Novel foundation pit backfilling structure
BE898692A (en) BENDED BEAM IN PRE-STRESSED CONCRETE OR REINFORCED CONCRETE
CN216715607U (en) Water pipe structure for well
FR2560634A1 (en) UNDERGROUND TUBULAR INSTALLATION SUCH AS CIRCULATING TUNNEL, TUBULAR PIPING OR THE LIKE, MANUFACTURING METHOD AND DEVICE FOR IMPLEMENTING THE METHOD
CN211646337U (en) Assembled water drain pipe device for foundation pit side slope
WO1989012721A1 (en) Process for waterproofing a deteriorated drainage channel and giving it mechanical strength and chemical resistance
CN110985118B (en) Semicircular heat-preservation annular blind pipe used in highway tunnel in cold region
CN218466578U (en) Drainage guide device for beautifying drain hole of retaining wall
CN113832954B (en) Multi-disaster defense structure
FR2668514A1 (en) Method and device for chopping the tops off concrete constructions