BR102015019612A2 - process of using an aerostat on transmission lines - Google Patents

process of using an aerostat on transmission lines Download PDF

Info

Publication number
BR102015019612A2
BR102015019612A2 BR102015019612A BR102015019612A BR102015019612A2 BR 102015019612 A2 BR102015019612 A2 BR 102015019612A2 BR 102015019612 A BR102015019612 A BR 102015019612A BR 102015019612 A BR102015019612 A BR 102015019612A BR 102015019612 A2 BR102015019612 A2 BR 102015019612A2
Authority
BR
Brazil
Prior art keywords
aerostat
transmission line
airship
maintenance
equipment
Prior art date
Application number
BR102015019612A
Other languages
Portuguese (pt)
Inventor
Bernadino Guedes Geraldo
Augusto De Felippes Marcelo
Carlos Daud Filho Antonio
Antonio Frederico Lopes Romulus
Charone Junior Wady
Original Assignee
Airship Do Brasil Indústria Aeronáutica Ltda
Centrais Elétricas Do Norte Do Brasil S/A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Airship Do Brasil Indústria Aeronáutica Ltda, Centrais Elétricas Do Norte Do Brasil S/A filed Critical Airship Do Brasil Indústria Aeronáutica Ltda
Priority to BR102015019612A priority Critical patent/BR102015019612A2/en
Priority to PCT/BR2016/000012 priority patent/WO2017027939A1/en
Publication of BR102015019612A2 publication Critical patent/BR102015019612A2/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B64AIRCRAFT; AVIATION; COSMONAUTICS
    • B64BLIGHTER-THAN AIR AIRCRAFT
    • B64B1/00Lighter-than-air aircraft
    • B64B1/70Ballasting arrangements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B64AIRCRAFT; AVIATION; COSMONAUTICS
    • B64BLIGHTER-THAN AIR AIRCRAFT
    • B64B1/00Lighter-than-air aircraft
    • B64B1/06Rigid airships; Semi-rigid airships
    • B64B1/24Arrangement of propulsion plant
    • B64B1/30Arrangement of propellers
    • B64B1/34Arrangement of propellers of lifting propellers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B64AIRCRAFT; AVIATION; COSMONAUTICS
    • B64BLIGHTER-THAN AIR AIRCRAFT
    • B64B1/00Lighter-than-air aircraft
    • B64B1/40Balloons
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • H02G1/04Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B64AIRCRAFT; AVIATION; COSMONAUTICS
    • B64BLIGHTER-THAN AIR AIRCRAFT
    • B64B1/00Lighter-than-air aircraft

Abstract

processo de utilização de um aeróstato em linhas de transmissão a presente invenção refere-se a um processo que utiliza como insumo um aeróstato, mais especificamente, um dirigível tripulado com uma plataforma aérea para solucionar os atuais problemas em sistema de transmissão de energia elétrica. tais problemas estão relacionados aos complexos processos operacionais, os quais possuem altos custos e elevado tempo de execução dos serviços de construção, operação, inspeção e manutenção, melhorando a sua produtividade. esse processo se dá por meio do sobrevoo das linhas de transmissão e pelo acesso aos pontos de trabalho, de forma descendente, utilizando uma estrutura de transferência de cargas. a invenção apresenta vantagens econômicas, sociais e ambientais muito relevantes quando em comparação aos processos utilizados atualmente, pois define uma nova logística de acesso ao sistema de transmissão.Method of Using an Aerostat on Transmission Lines The present invention relates to a process using as an input an aerostat, more specifically, a manned airship with an aerial platform to solve current problems in power transmission system. These problems are related to complex operational processes, which have high costs and high execution time of construction, operation, inspection and maintenance services, improving their productivity. This process takes place by overflowing the transmission lines and by accessing the work points downwards using a load transfer structure. The invention has very relevant economic, social and environmental advantages when compared to the processes used today, as it defines a new logistics of access to the transmission system.

Description

Relatório Descritivo da Patente de Invenção para “PROCESSO DE UTILIZAÇÃO DE UM AERÓSTATO EM LINHAS DE TRANSMISSÃO" [001] A presente invenção refere-se a um processo, que utiliza um aeróstato (aeronave mais leve do que o ar) para solucionar os atuais problemas relacionados aos complexos processos operacionais que envolvem a construção, manutenção, inspeção e operação de linhas de transmissão de sistemas de energia elétrica. Mais especificamente a presente invenção utiliza um dirigível adaptado para realizar as missões aqui descritas.[001] The present invention relates to a process which utilizes an aerostat (lighter-than-air aircraft) to solve current problems. related to the complex operational processes involving the construction, maintenance, inspection and operation of transmission lines of electric power systems More specifically the present invention utilizes an airship adapted to accomplish the missions described herein.

[002] Descrição da Técnica Anterior [003] Em sistemas elétricos com predominância da transformação de energia hidráulica, como é o caso do sistema brasileiro, as fontes geradoras (cerca de 80 % da geração de energia elétrica) estão localizadas distante dos grandes centros de cargas. Para transportar a energia, são construídas longas linhas de transmissão, compostas de torres e condutores de energia, que fazem o escoamento da energia elétrica das usinas para os centros de consumo residencial e industrial. As linhas de transmissão possuem um comprimento na ordem de centenas de quilômetros e operam em níveis de alta e extra-alta tensão. Na verdade, as linhas de transmissão são os elos entre as fontes geradoras e os diversos mercados consumidores de energia e têm um papel de alta relevância, pois possibilitam interligações entre vários centros de cargas, bem como trocas energéticas entre várias usinas geradoras de energia. Um sistema de transmissão confiável é a garantia da continuidade de energia aos consumidores e, para tanto, exige um sistema de manutenção com alta eficiência e qualidade.[002] Description of the Prior Art [003] In electrical systems with predominance of hydraulic power transformation, as is the case of the Brazilian system, the generating sources (about 80% of the electric power generation) are located far from the major centers of loads. To carry the energy, long transmission lines are built, made up of towers and power conductors, which flow the electricity from the plants to the residential and industrial consumption centers. The transmission lines are hundreds of kilometers long and operate at high and extra-high voltage levels. In fact, the transmission lines are the links between the generating sources and the various energy consuming markets and play a high role as they enable interconnections between various load centers as well as energy exchanges between various power plants. A reliable transmission system is a guarantee of power continuity for consumers and, therefore, requires a maintenance system with high efficiency and quality.

[004] As linhas de transmissão de energia elétrica são responsáveis pela ligação entre o centro produtor e o centro consumidor. Elas são constituídas basicamente pelos seguintes componentes: faixa de linha transmissão; estrutura; cadeia de isoladores; cabos condutores e acessórios; cabos pára-raios e vãos.[004] Electricity transmission lines are responsible for the connection between the producing center and the consuming center. They are basically made up of the following components: transmission line range; structure; insulator chain; conductor cables and accessories; lightning conductor cables and gaps.

[005] As estruturas são os suportes dos cabos condutores das linhas de transmissão e constituem-se na parcela mais onerosa das mesmas por serem compostos de dezenas de componentes bastante resistentes e duráveis. As referidas linhas de transmissão podem ser divididas basicamente em dois grupos: Autoportantes ou estaiadas.[005] The structures are the supports of the conductor cables of the transmission lines and constitute the most expensive part of them because they are composed of dozens of very resistant and durable components. Said transmission lines can be divided basically into two groups: Self-supporting or cable-stayed.

[006] São as estruturas que transmitem todos os esforços diretamente para as suas fundações, comportando-se como vigas engastadas verdadeiras, ou seja, não necessitam de estais para se manterem em pé. Em consequência, são estruturas pesadas ou fabricadas com perfis de aço especial e exigem grandes fundações. São as mais utilizadas nas linhas de transmissão do Brasil.[006] These are the structures that transmit all efforts directly to their foundations, behaving like true crushed beams, ie they do not need to stay to stand. As a result, they are heavy structures or made of special steel profiles and require large foundations. They are the most used in transmission lines in Brazil.

[007] Entre as autoportantes, existem vários tipos básicos: autoportante tipo delta; autoportante tipo vela; e autoportante compacta;Among the self-supporting, there are several basic types: self-supporting delta type; self-supporting candle type; and compact self-supporting;

[008] As estruturas estaiadas são normalmente estruturas flexíveis ou mistas que são enrijecidas através de estais. Os estais absorvem parte dos esforços horizontais, transmitindo-os diretamente ao solo através de âncoras. A outra parte dos esforços é transmitida axialmente pela estrutura. O uso de estais permite obter estruturas de baixo peso, resistindo às mesmas condições de carregamento das estruturas autoportantes. As estruturas estaiadas, tinham emprego limitado às linhas com estrutura de madeira ou concreto nas tensões até 230 kV. Atualmente o uso dessas estruturas está sendo amplamente difundido e aplicado nas linhas até 750 kV.Cable-stayed structures are usually flexible or mixed structures that are stiffened through clicks. The stalks absorb part of the horizontal efforts, transmitting them directly to the ground through anchors. The other part of the efforts is transmitted axially by the structure. The use of stays allows to obtain low weight structures, resisting the same loading conditions of the self supporting structures. The cable-stayed structures had limited use to lines with wood or concrete structure at voltages up to 230 kV. Currently the use of these structures is being widespread and applied to lines up to 750 kV.

[009] As estruturas também podem ser de outros materiais como madeira, aroeira, ipê, carnaúba, faveiro, eucalipto e pinho paranaense, concreto, concreto protendido “armadura tensionada”; concreto com armaduras convencionais e metais.[009] The structures can also be made of other materials such as wood, mastic, ipe, carnauba, faveiro, eucalyptus and parana pine, concrete, prestressed concrete “tensioned reinforcement”; concrete with conventional reinforcement and metals.

[010] As estruturas metálicas são largamente utilizadas. A sua principal vantagem é a fabricação de peças em série e facilidade no transporte das peças em veículos de carga comuns. Apresentam alta durabilidade e resistência se devidamente protegidas com pintura ou galvanização. A proteção mais comum é a galvanização à quente em banho de zinco, cuja durabilidade sem necessidade de manutenção pode ser de até 30 anos, dependendo da agressividade atmosférica da região.[010] Metal structures are widely used. Its main advantage is the manufacture of serial parts and ease of transportation of parts in standard cargo vehicles. They feature high durability and strength if properly protected with paint or galvanization. The most common protection is hot dip galvanizing in a zinc bath, whose maintenance-free durability can be up to 30 years, depending on the region's atmospheric aggressiveness.

[011] As estruturas quanto à fixação dos cabos se classificam em estrutura de suspensão (recebem este nome porque os cabos condutores são suspensos através das cadeias de isoladores e acessórios, e não são interrompidos, ou seja, passam suspensos pela estrutura); estrutura de ancoragem (os cabos condutores são ancorados nas mesmas através das cadeias de isoladores e acessórios e geralmente eles são seccionados); estruturas de transposição ou rotação de fases (dimensionadas para permitir a transposição ou rotação de fases a fim de assegurar a simetria elétrica da linha); estruturas de derivação (estruturas apropriadas para a derivação de linhas de transmissão).[011] Cable attachment structures are classified as suspension structures (they are named because the conductor cables are suspended through the insulator and accessory chains and are not interrupted, ie they are suspended by the structure); anchor structure (the conductor cables are anchored to them through the insulator and accessory chains and generally they are sectioned); phase transposition or rotation structures (sized to allow phase transposition or rotation to ensure electrical symmetry of the line); branch structures (structures suitable for branching transmission lines).

[012] As dimensões principais das estruturas são determinadas principalmente pela tensão de operação e sobretensões previstas.[012] The main dimensions of the structures are mainly determined by the expected operating voltage and overvoltages.

[013] Como fatores secundários, temos a flecha dos condutores e a forma de sustentação dos condutores.[013] As secondary factors we have the conductor arrow and the conductor support.

[014] Em função dos elementos acima, as normas dos diversos países fixaram a forma de se determinarem as distâncias entre condutores, altura dos seus pontos de suspensão e distâncias destes às partes aterradas da estrutura. Essas dimensões variam grandemente de país para país, dependendo das normas adotadas. No Brasil, esses elementos são fixados em norma pela ABNT.[014] Depending on the above elements, the rules of the various countries set out how to determine the distances between conductors, the height of their suspension points and their distances to the grounded parts of the structure. These dimensions vary greatly from country to country, depending on the standards adopted. In Brazil, these elements are set in standard by ABNT.

[015] Nas estruturas das linhas de transmissão, atuam as seguintes cargas: cargas verticais; cargas horizontais transversais e cargas horizontais longitudinais.[015] In the transmission line structures, the following loads act: vertical loads; horizontal transverse loads and longitudinal horizontal loads.

[016] As cargas verticais são os componentes verticais dos esforços de tração dos cabos condutores e pára-raios, peso dos acessórios de fixação dos cabos (ferramentas e isoladores), peso próprio da estrutura e eventuais cargas verticais devido ao estaiamento, sobrecargas de montagem, etc. Já as cargas horizontais são causadas pela ação do vento sobre os cabos e respectivos acessórios de fixação, ação do vento sobre a estrutura, na direção transversal da linha, componentes horizontais transversais dos esforços de tração dos cabos e eventuais esforços horizontais introduzidos pelo estaiamento.[016] Vertical loads are the vertical components of the tensile stresses of the conductor and lightning conductor, the weight of the cable fixing accessories (tools and insulators), the frame's own weight and any vertical loads due to the staging, mounting overloads. , etc. On the other hand, horizontal loads are caused by the wind action on the cables and their fastening accessories, wind action on the structure, in the transverse direction of the line, transverse horizontal components of the tensile stresses of the cables and eventual horizontal forces introduced by the tensioning.

[017] As cargas horizontais longitudinais são causadas pelos esforços de tração dos cabos, pela ação do vento sobre a estrutura, na direção da linha, e eventuais esforços introduzidos pelo estaiamento. As cargas acima relacionadas podem ser consideradas como normais, sobrepõem-se a cargas anormais, ou excepcionais, às quais, sob certas condições, as estruturas devem resistir. São cargas provocadas pelo rompimento de um ou mais cabos.[017] Longitudinal horizontal loads are caused by the tensile stresses of the cables, the action of the wind on the structure in the direction of the line, and any stresses introduced by the stretch. The loads listed above may be considered normal, overlap with abnormal or exceptional loads which, under certain conditions, structures must withstand. They are loads caused by the breaking of one or more cables.

[018] A construção de linhas de transmissão exige alguns procedimentos e técnicas específicas. O primeiro passo é um levantamento topográfico, de onde sai o perfil do terreno para que o projetista faça a localização das torres. Feito o traçado da linha de transmissão, é necessário retirar a vegetação para formação dos corredores de passagem das linhas (faixa de servidão), as quais serão, também, as áreas de acesso para as equipes de manutenção da linha. Nestes corredores de passagens não é permitida a construção de casas, currais, entre outros, e a vegetação não pode possuir árvores de grande porte. A largura da faixa de servidão é definida pela ABNT/NBR número 5422.[018] The construction of transmission lines requires some specific procedures and techniques. The first step is a topographic survey, from which the terrain profile comes out for the designer to locate the towers. Once the transmission line has been traced, it is necessary to clear the vegetation to form the line corridors (easement lane), which will also be the access areas for the line maintenance teams. In these corridors of passage is not allowed to build houses, corrals, among others, and the vegetation can not have large trees. The width of the easement range is defined by ABNT / NBR number 5422.

[019] Para se iniciar a construção são dimensionados e construídos os canteiros e suas instalações, levando em conta o volume das obras e serviços a executar, de acordo com o cronograma de construção e montagem das linhas. As áreas de circulação interna dos canteiros são feitas com drenagem, iluminação e locais de lazer para os empregados.[019] To begin construction, the construction sites and their facilities are dimensioned and built, taking into account the volume of works and services to be performed, according to the construction and assembly schedule of the lines. The internal circulation areas of the flower beds are made with drainage, lighting and leisure places for the employees.

[020] No projeto define-se a localização das torres, utilizam-se instrumentos de precisão para marcá-las e sequencialmente faz-se a sondagem do solo para definição do tipo de fundação a ser usada naquele local identificado. Para definição do tipo e quantidade de aterramento de cada torre, faz-se a medição de resistividade do solo.[020] In the project the location of the towers is defined, precision instruments are used to mark them and the soil is sequentially probed to define the type of foundation to be used in that identified location. To define the type and amount of grounding of each tower, the soil resistivity is measured.

[021] Para processar a fundação dos pés das torres, fazem-se escavações de forma manual ou mecanizada, sendo a segunda a mais aplicada. O processo de fundação é realizado com armação de ferragens para receber o concreto.[021] To process the foundation of the tower feet, excavations are made manually or mechanically, the second being the most widely applied. The foundation process is carried out with hardware fittings to receive the concrete.

[022] Concluída a fundação, seja ela em concreto ou em grelha, a instalação da malha de aterramento é imprescindível à segurança do pessoal que trabalha na continuidade da construção da torre.[022] Once the foundation is completed, whether concrete or grid, the installation of the grounding loop is essential for the safety of personnel working on the continuity of tower construction.

[023] A montagem de torre exige um processo de seleção e organização das peças que são montadas e segue passo a passo uma lógica projetada e espaços adequados. As torres usualmente são constituídas de peças metálicas treliçadas destinadas à sustentação dos cabos condutores de energia elétrica. A montagem, geralmente, é feita no solo e a torre içada através de guindastes. Na impossibilidade de deslocamento de guindastes ao longo da linha de transmissão, usa-se a montagem manual de peça por peça. As torres variam de altura de acordo com o relevo da região e a classe de tensão de operação da linha de transmissão.[023] Tower assembly requires a process of selecting and organizing parts that are assembled and follows step by step designed logic and proper spaces. The towers are usually made of lattice metal parts designed to support the conductor cables. Mounting is usually done on the ground and the tower is hoisted up by cranes. If cranes cannot be moved along the transmission line, manual part-by-part assembly is used. The towers vary in height according to the relief of the region and the operating voltage class of the transmission line.

[024] A instalação dos cabos (para-raios, OPGW, condutor) requer escolha de área compatível com a quantidade de bobinas dos cabos e acesso seguro para as carretas de transporte. Posteriormente, na etapa de regulação, a qual consiste em realizar o processo de esticar os condutores de energia em cada trecho de torres adjacentes, posicionam-se os cabos conforme definido no projeto e realiza-se o grampeamento, o qual faz a fixação do cabo esticado nas cadeias de isoladores. Para tanto, são requeridos instrumentos de precisão e equipes especializadas.[024] Cable installation (lightning rod, OPGW, conductor) requires area selection compatible with the number of cable reels and secure access to the transport wagons. Subsequently, in the regulation stage, which consists in carrying out the process of stretching the energy conductors in each section of adjacent towers, the cables are positioned as defined in the project and the stapling is performed, which makes the cable fixing stretched on the insulator chains. For this, precision instruments and specialized teams are required.

[025] Durante a fase de construção são instalados muitos aterramentos temporários, portanto, é necessária a inspeção final que, geralmente, é a busca por algum que tenha ficado esquecido e na sequência é realizada a energização da linha de transmissão.[025] During the construction phase many temporary grounds are installed, so a final inspection is required, which is usually the search for one that has been forgotten and then the transmission line energized.

[026] O serviço de manutenção é realizado por equipes especializadas, as quais iniciam os seus processos executando inspeções terrestres, percorrendo vários trajetos nos corredores de passagem das linhas de transmissão, monitorando vários pontos, como as cadeias de isoladores, os cabos para-raios, o estado das torres, o sistema de aterramento e as vegetações em sua volta. O processo de inspeção terrestre detalhada é feita através da escalada da torre pelo mantenedor onde verifica cabos, as peças frouxas, corroídas, danificadas ou faltantes, além de observar na faixa de servidão as malhas de aterramento e possíveis erosões. A inspeção aérea é realizada com uso de helicóptero e ocorre de duas maneiras, visual ou instrumentalizada para se identificar defeitos antes que gerem desligamentos inesperados ou, em casos de emergência, para encontrar os defeitos que causaram o desligamento. Os instrumentos utilizados são basicamente o analisador do efeito corona, termovisor e câmera de filmagens em alta resolução.[026] The maintenance service is performed by specialized teams who begin their processes by performing ground inspections, traversing various paths in transmission line corridors, monitoring various points such as insulator chains, lightning conductor cables. , the state of the towers, the grounding system and the surrounding vegetation. The detailed ground inspection process is done by climbing the tower by the maintainer where it checks cables, loose, corroded, damaged or missing parts, and observes grounding mesh and possible erosion in the right of way. The aerial inspection is performed using a helicopter and occurs in two ways, visual or instrumented to identify defects before they generate unexpected shutdowns or, in emergencies, to find the defects that caused the shutdown. The instruments used are basically the corona effect analyzer, thermal imager and high resolution video camera.

[027] As inspeções terrestres são feitas com deslocamentos dos mantenedores sobre os corredores de passagem ao longo do sistema de transmissão, trecho por trecho, ou seja, as equipes percorrem centenas de quilômetros, terminando as inspeções quando findar o último trecho. Devido às áreas alagadas que impossibilitam o tráfego de veículos, muitos percursos são feitos a pé ou de barco.[027] Ground inspections are made by maintainer displacements over the passage corridors along the transmission system, section by section, that is, teams travel hundreds of kilometers, ending inspections when the last section ends. Due to the flooded areas that prevent vehicle traffic, many routes are on foot or by boat.

[028] Os serviços de manutenção tem origem nas inspeções das linhas de transmissão. Um exemplo de manutenção programada é a troca de isoladores com a linha energizada, realizada pelos eletricistas escalando as torres munidos de vestimentas condutivas, de bastão de equalização de potencial, ferramentas e aparelhos de comunicação. Existem vários fatores de segurança envolvidos, devido ser um trabalho executado em campo, a céu aberto, em alturas que variam de 20 a mais de 100 metros, com temperatura ambiente desconfortante (fora dos padrões normais entre 15°C a 30°C), e, geralmente, distante de cidades ou vilarejos. O processo envolve a escalada de estruturas, bloqueio de circuitos elétricos, comunicação de voz “online” com os centros de operação exigindo cuidados com as ferramentas, campos elétricos e distâncias de segurança conforme a tensão nominal da linha.[028] Maintenance services originate from transmission line inspections. An example of scheduled maintenance is the switching of insulators with the energized line, performed by electricians climbing the towers with conductive clothing, potential equalizing rod, tools and communication devices. There are several safety factors involved, such as field work, in the open, at heights ranging from 20 to over 100 meters, with uncomfortable ambient temperature (non-standard 15 ° C to 30 ° C), and usually far from towns or villages. The process involves climbing structures, blocking electrical circuits, online voice communication with operating centers requiring care of tools, electrical fields and safety distances to the rated line voltage.

[029] A escalada nas estruturas é feita com a utilização de mosquetão, corda de segurança e trava quedas, mantendo o eletricista todo o tempo conectado a algum ponto da estrutura. A equipe de linha executa uma pré-montagem das ferramentas no solo, dispondo-as junto com os materiais sobre uma lona em ordem de içamento para o local de trabalho no alto da torre, analisando a melhor forma de executar a manobra. Os eletricistas iniciam a escalada nas estruturas até o local de trabalho, levando as cordas de segurança e de serviço para suspensão da cadeira isolante que os levará ao potencial com os bastões e a corda para rabicho. Outro eletricista que fez a escalada da torre, junto àquele que vai acessar o potencial, fica próximo ao ponto de entrada do primeiro e o auxilia na passagem para a cadeira de translado de entrada ao potencial e realização do serviço. A função do eletricista auxiliar é de passar o talabarte na estrutura e segurar a cadeira para que o trabalhador com vestimenta condutiva possa sentar e ser levado até o cabo condutor de energia. Desta forma, os demais puxam o eletricista que se encontra sentado na cadeira, até o cabo energizado, e esperam que o mesmo se equalize (fique no mesmo potencial do circuito elétrico) e se ancore no cabo energizado, passando a cadeira de volta à estrutura. Com o eletricista no potencial, o material necessário para manobra é suspenso até local do serviço. Em seguida, são usadas ferramentas específicas, como jugo, bastão e outros acessórios. O processo é concluído quando todos os eletricistas se encontrem no chão e com as ferramentas e materiais recolhidos.[029] Climbing the structures is done with the use of carabiner, safety rope and fall arrest, keeping the electrician always connected to some point of the structure. The line crew pre-assembles the tools to the ground, arranging them along with the materials on a tarp in order of lifting to the tower top work site, analyzing how best to perform the maneuver. Electricians begin climbing the structures to the workplace, bringing the safety and service ropes to the insulating chair suspension that will take them to potential with the rods and the tail rope. Another electrician who climbed the tower, next to the one who will access the potential, is near the point of entry of the first and assists him in the passage to the chair of potential entry and performance of the service. The function of the auxiliary electrician is to pass the lanyard into the structure and hold the chair so that the worker in conductive clothing can sit and be carried to the power cable. In this way, the others pull the electrician sitting on the chair to the live cable and expect it to equalize (stay at the same potential as the electrical circuit) and anchor the live cable, passing the chair back to the structure. . With the potential electrician, the material required for maneuvering is suspended to the place of service. Then specific tools such as yoke, stick and other accessories are used. The process is completed when all electricians are on the floor and with the tools and materials collected.

[030] Dentre os problemas que se apresentam para a realização deste tipo de serviço podemos citar a dificuldade de escalada das estruturas, o deslocamento das cadeias de isoladores que variam de peso (centenas de kg) conforme a classe de tensão e o manuseio da cadeira de translado do eletricista ao potencial. O grau de dificuldade aumenta ainda mais quando os serviços são realizados em locais dentro da floresta e em região alagada que impedem trânsito de veículos, obrigando o carregamento braçal dos materiais, ferramentas e equipamentos ou por meio de helicóptero para deixar os eletricistas e materiais necessários para a manutenção. Assim, o helicóptero faz o devido transporte deixando as pessoas em uma das fases laterais dos circuitos de energia. No entanto, tem-se um inconveniente, pois o helicóptero, após o posicionamento de pessoas e materiais, se retira da área e somente retorna na hora prevista para o término dos serviços, ficando a equipe isolada no local da manutenção. Este inconveniente é decorrente da baixa autonomia de voo do helicóptero e da poucas áreas viáveis para pouso próximas às linhas de transmissão, impedindo-o de permanecer no local. Outra desvantagem é a impossibilidade de se usar helicópteros para serviços a serem realizados na fase central da torre por ser uma operação de alto risco de acidente para este tipo de aeronave [031] Mais dificuldades aparecem quando linhas de transmissão percorrem longas distâncias sem estradas próximas. O que frequentemente acontece no norte do Brasil, onde os serviços de inspeções e manutenções pelos eletricistas são dificultados, pois são regiões de difícil acesso por possuírem áreas alagadas ou alagáveis ao longo do empreendimento. Para realizar esses serviços, é necessária uma logística para deslocamentos de pessoas e materiais, utilizando helicópteros ou barcos, gerando um custo adicional no processo de manutenção devido não ser permitido aberturas de vias de acesso, pois implica em impactos ambientais e rompimento das condicionantes previamente estabelecidas pelos órgãos governamentais na ocasião dos licenciamentos [032] Nesse contexto, destacam-se os casos de sinistros, como uma queda de torre ou de cabo. Se este ocorrer em pontos sem acesso de veículos terrestres, o tempo de restabelecimento do sistema de transmissão sinistrado aumenta em média 12 horas por dia, pois os serviços são paralisados durante o período noturno por questões de segurança das equipes, haja vista a inexistência de iluminação adequada devido à impossibilidade de transporte e instalação de geradores de emergência.[030] Among the problems that arise for performing this type of service we can mention the difficulty of climbing the structures, the displacement of insulator chains that vary in weight (hundreds of kg) depending on the tension class and the handling of the chair. of the electrician's transfer to the potential. The degree of difficulty increases further when services are performed in places within the forest and in a flooded region that prevent vehicle traffic, forcing the manual loading of materials, tools and equipment or by helicopter to leave the electricians and materials needed for the maintenance. Thus, the helicopter is properly transported leaving people in one of the side phases of the power circuits. However, there is an inconvenience, because the helicopter, after the placement of people and materials, withdraws from the area and only returns at the scheduled time for completion of services, leaving the team isolated at the maintenance site. This inconvenience is due to the helicopter's low flight range and the few viable landing areas near the transmission lines, preventing it from remaining in place. Another disadvantage is the impossibility of using helicopters for services to be performed in the central phase of the tower as it is a high-risk accident operation for this type of aircraft. [031] More difficulties arise when transmission lines travel long distances with no nearby roads. This is often the case in northern Brazil, where inspection and maintenance services by electricians are difficult, as they are regions that are difficult to access because they have flooded or flooded areas throughout the project. To perform these services, a logistics is required for the movement of people and materials, using helicopters or boats, generating an additional cost in the maintenance process due to not allowing openings of access roads, as it implies environmental impacts and disruption of previously established conditions. by government agencies at the time of licensing [032] In this context, there are cases of claims such as a tower or cable fall. If this occurs at points without access by land vehicles, the recovery time of the damaged transmission system increases by an average of 12 hours per day, as services are stopped during the night due to team safety, given the lack of lighting. due to the impossibility of transporting and installing emergency generators.

[033] O processo de lavagem de isoladores em linhas de transmissão que percorrem áreas de alta salinidade ou outro tipo de poluição é realizado com jato de alta pressão, de água tratada, pelos mantenedores que ficam nas torres presos com cintos de segurança para realização do serviço. A lavagem depende do acesso do caminhão tanque até a base da torre.[033] The process of washing insulators on transmission lines running through high salinity areas or other pollution is carried out with high pressure jet of treated water by the maintainers who are in the towers secured with seat belts to perform the service. Washing depends on the access of the tanker truck to the tower base.

[034] Por fim, destaca-se que as atividades dos eletricistas de linhas de transmissão exigem muitos esforços físicos. Os mesmos têm que escalar altas torres, içar equipamentos e ferramentas, contribuindo para que a vida média de trabalho desses eletricistas seja de 48 anos, isto é, após esta idade, eles são afastados desta atividade, implicando na necessidade de realocá-los em outras áreas ou transformando-os em supervisores, inspetores ou instrutores.Finally, it is noteworthy that the activities of transmission line electricians require a lot of physical efforts. They have to climb high towers, lift equipment and tools, contributing to the average working life of these electricians is 48 years, that is, after this age, they are removed from this activity, implying the need to relocate them in other areas or turning them into supervisors, inspectors or instructors.

[035] Para a construção de um novo sistema de transmissão, os maiores desafios enfrentados são as restrições ambientais e as dificuldades de obtenção de novos corredores de transmissão.[035] In constructing a new transmission system, the biggest challenges are environmental constraints and difficulties in obtaining new transmission corridors.

[036] Existe regulamentação (no Brasil a NBR 5422) que fixa as condições básicas para o projeto de linhas de transmissão de energia elétrica de modo a garantir níveis mínimos de segurança e limitar perturbações em instalações próximas.[036] There is regulation (in Brazil NBR 5422) that establishes the basic conditions for the design of electricity transmission lines in order to guarantee minimum safety levels and limit disturbances in nearby installations.

[037] Tal regulamentação exige que, onde for necessário, deverá ser prevista uma faixa limpa com largura suficiente para permitir a implantação, operação e manutenção da linha.[037] Such regulation requires that, where necessary, a clean strip of sufficient width should be provided to permit the deployment, operation and maintenance of the line.

[038] É estipulado que o desmatamento da faixa deverá ser reduzido ao mínimo estritamente necessário para assegurar condições satisfatórias de construção, operação e manutenção da linha. O revestimento vegetal existente na faixa deverá ser objeto de limpeza segundo o critério estabelecido em norma. Ou seja, os sistemas convencionais de construção, operação, manutenção e inspeção de linhas de transmissão estão sujeitos à dificuldades impostas não apenas pelo meio ambiente mas também pelas regulamentações existentes.[038] It is stipulated that strip deforestation should be reduced to the minimum strictly necessary to ensure satisfactory construction, operation and maintenance of the line. The existing vegetal covering in the strip should be cleaned according to the criteria established in the standard. In other words, conventional transmission line construction, operation, maintenance and inspection systems are subject to difficulties imposed not only by the environment but also by existing regulations.

[039] São elaborados estudos que mostram vários aspectos, dentre eles os impactos socioambientais. Estes têm criticidade nos corredores de passagem das linhas, nos quais são identificadas as maiores complexidades para a implantação das instalações de transmissão, e isto reflete um aumento crescente dos custos. Conforme for ocorrendo os cortes das vegetações, corre-se o risco de serem encontrados sítios arqueológicos implicando em parada da construção, novas exigências e atrasos no empreendimento, potencializando a redução da taxa de retorno aos acionistas.[039] Studies are conducted that show various aspects, including social and environmental impacts. These are critical in line corridors, where the greatest complexities for the deployment of transmission facilities are identified, and this reflects an increasing cost increase. As the vegetation cuts occur, there is a risk that archaeological sites will be found implying construction stoppages, new demands and delays in the project, potentially reducing the return rate to shareholders.

[040] Em uma ampla análise da literatura com o intuito de estabelecer o estado da técnica vigente frente ao processo para construção, operação, inspeção e manutenção em linhas de transmissão, objeto da presente patente, não foram revelados documentos que relacionem processo específico do que está sendo reivindicado, contudo foram referenciados alguns documentos que, apesar de não serem impeditivos frente a presente patente, retratam ferramentas de manutenção e operação do sistema elétrico.[040] In a broad analysis of the literature in order to establish the current state of the art regarding the process for construction, operation, inspection and maintenance of transmission lines, object of the present patent, documents that relate specific process of what was not disclosed. It is being claimed, however some documents have been referenced which, while not impeding the present patent, depict tools for maintenance and operation of the electrical system.

[041] No documento de patente US 4.818.990 foi proposta a utilização de um robô aéreo pilotado remotamente, o qual é adaptado para voo próximo às linhas de transmissão, além de capacidade de pairar a fim de detectar condições anormais ao longo das linhas. O robô possui equipamentos capazes de observar e gravar informações relacionadas à situação das linhas e regiões no entorno. Uma estação em solo controla a operação do robô aéreo, e ainda, armazena as informações obtidas. No entanto, para sistemas de transmissão que não possuem estradas de acessos próximas, a área de alcance do robô torna-se um grande limitador. Além disto, tem-se o risco de uma perda do sinal de comunicação entre a estação transmissora e o robô ocasionar a queda deste sobre a rede elétrica, desencadeando defeito permanente no sistema de transmissão, interrompendo a continuidade do fluxo de energia nas linhas de transmissão até que sejam reparados os danos provocados pela queda do robô. Ressalta-se que o robô consegue fazer apenas as atividades de inspeção devido à limitação do peso e tamanho da carga paga.[041] In US Patent 4,818,990 it has been proposed to use a remotely piloted aerial robot which is adapted for flight close to the transmission lines, as well as the ability to hover to detect abnormal conditions along the lines. The robot has equipment capable of observing and recording information related to the situation of the surrounding lines and regions. A ground station controls the operation of the aerial robot, and also stores the information obtained. However, for transmission systems that do not have close access roads, the robot's range becomes a major constraint. In addition, there is a risk of a loss of communication signal between the transmitting station and the robot causing it to fall over the power grid, triggering a permanent defect in the transmission system, interrupting the continuity of the power flow in the transmission lines. until damage from falling robot is repaired. It is noteworthy that the robot can only perform inspection activities due to the limited weight and size of the paid load.

[042] Já na patente US 3.176.795 tem-se a utilização de estação de trabalho elevada para linhas de alta tensão onde essa é suportada por um helicóptero, ou um balão, além de um paraquedas em uma posição intermediária entre a estação de trabalho e o helicóptero. Ainda, linhas de ancoragem fixas ao solo têm o propósito de manter a estação de trabalho suspensa em uma posição relativamente fixa. A configuração proposta neste documento para utilização do helicóptero na realização da manutenção em linhas de transmissão, além dos limitantes de voo, pode ser perigosa e gerar riscos elevados para a segurança operacional, pois tal documento descreve que o helicóptero pode ser liberado para outro serviço sendo substituído por um balão sem operador e/ou um paraquedas conforme demonstrado em suas ilustrações, essa modelagem pode desestabilizar e cair sobre a torre. A patente US 3.196.980 projeta a utilização de escada erguida a partir do solo através de um veículo com provisões de isolação elétrica em relação à terra e equivalência de potencial elétrico em relação ao condutor para acesso, inspeção e manutenção de linhas de alta tensão. Porém, o uso da escada possui uma limitação de altura e requer manejo e transporte do veículo até a Linha de Transmissão.Already in US Patent 3,176,795 there is the use of elevated workstation for high voltage lines where it is supported by a helicopter, or a balloon, in addition to a parachute in an intermediate position between the workstation. And the helicopter. In addition, grounded anchor lines are intended to keep the workstation suspended in a relatively fixed position. The configuration proposed in this document for the use of the helicopter for transmission line maintenance in addition to flight limitations may be hazardous and pose high risks to operational safety, as this document describes that the helicopter may be released for another service. replaced by an unmanned balloon and / or a parachute as shown in his illustrations, this modeling can destabilize and fall onto the tower. US 3,196,980 designates the use of ladders raised from the ground through a vehicle with provisions for electrical isolation from ground and electrical potential equivalence with respect to conductor for access, inspection and maintenance of high voltage lines. However, the use of the ladder has a height limitation and requires handling and transportation of the vehicle to the Transmission Line.

[043] As patentes US 4.478.312 e US 4.422.528 utilizam uma estrutura aérea do tipo cesta, carregada por helicóptero, para transporte de técnicos de inspeção e manutenção de linhas de alta tensão, além de servir de acoplamento temporário na linha. A manutenção de linhas e de cabos descritas nesses documentos refere-se à utilização apenas de uma estrutura tipo "cadeirinha" onde os operadores de linha são deixados por um helicóptero no ponto da manutenção. Em razão das condições de clima, tempo e limitações do voo do helicóptero, o serviço pode ser cancelado, outra questão que envolve segurança é a orientação do helicóptero, deslocamento de vento nos cabos, e desenvolvimento de manobras incontroláveis da aeronave.[043] US 4,478,312 and US 4,422,528 use a helicopter-loaded basket-type overhead structure for the transportation of high-voltage line inspection and maintenance technicians, as well as temporary coupling on the line. The line and cable maintenance described in these documents refers to the use of only a "car seat" type structure where the line operators are left by a helicopter at the point of maintenance. Due to weather conditions, weather and flight limitations of the helicopter, the service may be canceled, another issue that involves safety is the helicopter orientation, cable wind displacement, and the development of uncontrollable aircraft maneuvers.

[044] O documento de patente US 4.637.575 utiliza uma plataforma fixa no esqui do helicóptero para transporte e apoio de um técnico de inspeção e manutenção de linhas de alta tensão. O técnico apoiado na plataforma é capaz de realizar a inspeção e reparo pelo fato do helicóptero pairar adjacente à linha de alta tensão com a plataforma próxima à região de trabalho. O processo de manutenção e inspeção descrito neste documento de patente traz riscos para a segurança operacional, visto que a aeronave descrita para este tipo de serviço estará muito próxima aos cabos e que qualquer instabilidade ocasionará balanço ao voo. Os serviços de manutenção para esta aplicação devem ser extremamente rápidos visto que a autonomia da aeronave pode comprometer a qualidade e término do serviço. Na patente US 4.673.059 tem-se a utilização de um meio de suporte aéreo, como um helicóptero, a fim de posicionar uma carga ou um operador em um assento em uma linha de alta tensão. O veículo aéreo consiste em um suporte não aterrado que sustenta uma plataforma aérea também não aterrada por meio de componentes isolantes, possibilitando assim contato da carga ou operador com a linha de transmissão energizada sem que ocorram descargas elétricas. A técnica descrita nesse documento é a mesma descrita anteriormente, onde se deixa um operador e um carrinho de ferramenta para a referida manutenção naquele ponto. A aeronave segue voo e após um período determinado retorna para retirar o operador do local. O documento de patente US 5.328.133 trata do uso de helicóptero com cestos nas laterais, capazes de carregar equipamentos e um operador, suportados por vigas alongadas feitas de materiais isolantes ao longo do eixo transversal horizontal da aeronave. O helicóptero é capaz de realizar voo pairado de forma a aproximar o cesto com equipamentos e o operador de uma linha de alta tensão. A operação de inspeção e manutenção pode ser realizada com o cesto fixo ao helicóptero, e, portanto com a aeronave pairando em uma posição relativamente fixa com o cesto suficientemente próximo à linha de transmissão. Outrossim, o cesto pode ser montado na linha de transmissão ou na torre, de forma que o helicóptero possa se afastar enquanto as operações de inspeção e manutenção são realizadas. O sistema descrito refere-se a uma plataforma montada na lateral da aeronave, o que se assemelha com a plataforma montada nos esquis do helicóptero, fazendo com que a aeronave fique muito próxima ao cabo ou da estrutura da torre onde o deslocamento de ar gerado pelos rotores do motor pode danificar e comprometer o conjunto montado cabo/torre.[044] US Patent Document 4,637,575 utilizes a fixed helicopter ski platform for transport and support of a high voltage line inspection and maintenance technician. The platform-supported technician is able to perform inspection and repair by the fact that the helicopter hovers adjacent to the high voltage line with the platform near the work region. The maintenance and inspection process described in this patent document poses operational safety risks, as the aircraft described for this type of service will be very close to the cables and any instability will cause flight swing. Maintenance services for this application must be extremely fast as the autonomy of the aircraft may compromise the quality and termination of service. US 4,673,059 employs an air support means such as a helicopter to position a load or an operator on a seat on a high voltage line. The aerial vehicle consists of an ungrounded support that supports an ungrounded aerial platform by means of insulating components, thus enabling contact of the load or operator with the energized transmission line without the occurrence of electrical discharges. The technique described in this document is the same as described above, where an operator and a tool cart are left for said maintenance at that point. The aircraft follows flight and after a certain period returns to remove the operator from the site. US 5,328,133 deals with the use of side-basketed helicopter capable of carrying equipment and an operator supported by elongated beams made of insulating materials along the horizontal transverse axis of the aircraft. The helicopter is capable of hovering to bring the basket with equipment and the operator to a high voltage line. The inspection and maintenance operation can be performed with the basket attached to the helicopter, and thus with the aircraft hovering in a relatively fixed position with the basket sufficiently close to the transmission line. In addition, the basket can be mounted on the transmission line or tower so that the helicopter can move away while inspection and maintenance operations are performed. The described system refers to a platform mounted on the side of the aircraft, which resembles the platform mounted on the helicopter skis, making the aircraft very close to the cable or tower structure where the air displacement generated by the Motor rotors can damage and compromise the cable / tower mounted assembly.

[045] É importante notar que todas as patentes que utilizam helicópteros para executarem atividades recaem nos problemas básicos de limitação de autonomia de voo, de altos custos, de maiores riscos de acidentes. As técnicas que são apresentadas, tendo a presença do helicóptero durante a realização de serviços, não impedem que haja deslocamentos de ar promovidos pelos seus rotores dificultando a realização dos trabalhos pelas equipes de manutenção, mesmo se elas estiverem sobre um cesto. Além disso, os tempos de realização das tarefas teriam que ser relativamente curtos devido à autonomia de voo. Outro problema está relacionado ao uso de paraquedas, o que aumenta o risco de acidentes pelo contato com a Linha de Transmissão e/ou por quedas. A ancoragem no solo requer uma equipe em terra e não potencializa um aumento de produtividade dos atuais processos existentes de inspeção, de manutenção e de construção.[045] It is important to note that all patents that use helicopters to perform activities fall under the basic problems of limited flight range, high costs, and increased accident risks. The techniques that are presented, having the helicopter present while performing services, do not prevent air displacements promoted by its rotors making it difficult for maintenance teams to perform their work, even if they are in a basket. In addition, task completion times would have to be relatively short due to flight autonomy. Another problem is related to the use of parachutes, which increases the risk of accidents by contact with the Transmission Line and / or by falls. Ground anchoring requires a ground crew and does not enhance productivity increases from existing inspection, maintenance and construction processes.

[046] A patente US 6,231,007 descreve um método de posicionamento em solo ou de pegar uma carga utilizando dirigível. A aeronave se aproxima do local de carga ou descarga e abaixa uma estrutura de suporte de cargas. Essa estrutura libera cabos para serem fixados ao solo. Os cabos são esticados e mantidos sob tensão ao serem puxados por meio de guinchos no solo e ao se produzir maior sustentação pelo dirigível com a liberação de lastro. Isso permite que a aeronave possa se mover livremente enquanto o suporte de cargas fica em uma posição fixa. Todo o conjunto é então puxado para baixo a fim de aproximar a plataforma de suporte de cargas com o solo. Esta plataforma é então fixa ao solo e as operações de carga e descarga podem se iniciar. Assim que as operações terminem, a plataforma de cargas pode ser solta, os guinchos aliviam as tensões nos cabos e a aeronave ganha altitude. Por fim, os cabos são liberados do solo e o dirigível pode retornar à condição de voo.US 6,231,007 describes a method of positioning on the ground or catching a load using airship. The aircraft approaches the loading or unloading location and lowers a load-bearing structure. This structure releases cables to be fixed to the ground. The cables are stretched and kept under tension by being pulled by winches on the ground and by producing greater support by the airship with the release of ballast. This allows the aircraft to move freely while the load support is in a fixed position. The entire assembly is then pulled down to bring the load support platform closer to the ground. This platform is then fixed to the ground and loading and unloading operations can begin. Once operations are complete, the loading platform can be released, the winches relieve tension on the cables and the aircraft gains altitude. Finally, the cables are released from the ground and the airship can return to flight condition.

[047] No pedido de patente US2012/0085864A1 tem-se um método de posicionamento de um dirigível em um gerador eólico em que seções de ancoragem do dirigível são acoplados em ao menos uma das estruturas do gerador eólico como a nacelle, o cubo, uma ou mais pás, a torre, a fundação ou uma subestação do gerador eólico. A ancoragem permite operações de carga e descarga entre o dirigível e o gerador eólico como componentes, equipamentos ou pessoas por meio de uma escotilha no topo da nacelle. A carga ou descarga para o gerador eólico pode ser feita por meio de guinchos ou guindaste no dirigível. Pode, também, ser feita utilizando escadas ou plataforma que conecte o dirigível ao gerador eólico.[047] In patent application US2012 / 0085864A1 there is a method of positioning a blimp on a wind generator wherein anchor sections of the blimp are coupled to at least one of the wind generator structures such as the nacelle, the hub, a or more blades, the tower, the foundation or a wind generator substation. Anchoring allows loading and unloading operations between the airship and the wind generator as components, equipment or people by means of a hatch at the top of the nacelle. Loading or unloading to the wind generator can be done by winches or crane in the airship. It can also be done using stairs or a platform that connects the airship to the wind generator.

[048] Já o documento de número US2012/0091274A1 propõe um método de movimentação de componentes de gerador eólico o qual é carregado ao dirigível em um local diferente daquele de instalação. Os componentes são transportados pelo dirigível até o local de aplicação. Estes são descarregados e instalados em outro componente de gerador eólico, ou no solo, no mar, em um veículo terrestre, em uma embarcação através de um ou mais elementos guias estendidos.[048] Document US2012 / 0091274A1 proposes a method of moving wind generator components which is loaded to the airship at a location other than that of installation. The components are transported by the airship to the application site. These are unloaded and installed on another wind generator component, or on the ground, at sea, in a land vehicle, on a vessel through one or more extended guide elements.

[049] Estes processos existentes não se adequam às necessidades de terem, em um mesmo local, condições de carregamento e de descargas a serem movimentadas, retardando em muito o tempo para construção e de reparar sinistros em linhas de transmissão. O sistema da aplicação de guias estendidos, descartada na patente requerida, engessa o processo de trabalho dos eletricistas para atuarem em linhas energizadas e não mitiga riscos de acidentes. Toda metodologia apresentada configura uma necessidade de movimentação focando uma única ação de carga e descarga, impedindo o processo de lançamento de cabos elétricos sobre as estruturas das torres de forma contínua, ou seja, limita logísticas para construção, impede a aplicação para o atendimento de quedas de torres ou de cabos condutores de linhas de transmissão e devido à impossibilidade de lançamento dos cabos elétricos nas estruturas das torres não reduz os impactos ambientais com relação aos corredores de passagens destes cabos entre as estruturas.[049] These existing processes do not fit the needs of having in one place loading and unloading conditions to be moved, greatly delaying construction time and repairing transmission line claims. The system of application of extended guides, discarded in the required patent, constrains the working process of electricians to act on energized lines and does not mitigate accident risks. Every methodology presented configures a movement need focusing on a single action of loading and unloading, preventing the process of launching electrical cables on the structures of the towers continuously, ie, limits logistics for construction, prevents the application to meet falls. towers or cables leading to transmission lines and due to the impossibility of throwing electrical cables into the tower structures does not reduce the environmental impacts with respect to the passageways of these cables between the structures.

[050] Com relação à operação das linhas de transmissão, a referida operação das instalações de maneira geral se dá por duas modalidades: assistidas ou desassistidas. O órgão que dita as regras de operação do Sistema Elétrico Interligado no Brasil é o Operador Nacional do Sistema (ONS), onde encontramos as seguintes diretrizes: [051] Sempre que houver manutenção na LT, será necessária a presença de um operador em cada extremidade da linha para inibir a atuação de religadores automáticos.[050] Regarding the operation of the transmission lines, the referred operation of the installations in general happens by two ways: assisted or unattended. The governing body for the rules of operation of the Interconnected Electric System in Brazil is the National System Operator (ONS), where we find the following guidelines: [051] Whenever there is maintenance in the LT, an operator will be required at each end. of the line to inhibit the action of automatic reclosers.

[052] Sempre que a equipe estiver executando a manutenção de uma LT e havendo desligamento desta por qualquer motivo a reenergização só poderá ocorrer após comunicação com a equipe de manutenção da LT.[052] Whenever the team is performing maintenance of a LT and having it shut down for any reason, reenergization can only occur after communication with the LT maintenance team.

[053] A inspeção nas redes elétricas e as Intervenções para eliminação de falhas e/ou defeitos são atividades de manutenção em linhas de transmissão sujeitas à aprovação e liberação pela operação do sistema elétrico.[053] Inspection on electrical networks and Interventions to eliminate faults and / or defects are maintenance activities on transmission lines subject to approval and clearance by the operation of the electrical system.

[054] Algumas atividades da Operação de uma concessionária de energia elétrica por ocasião da manutenção em linhas de transmissão são listadas abaixo: 1- Aprovação e liberação de documento para realização dos serviços; 2- Solicitação de autorização junto ao ONS (Operador Nacional de Sistemas) para realização dos serviços; 3- Mediação junto ao ONS da solicitação da manutenção antes, durante e depois da realização dos serviços; 4- Manobras de abertura/fechamento de equipamentos elétricos e bloqueio/desbloqueio de sistema de comando, controle e proteção; 5- Disponibilização da rede elétrica, interrupção (se necessária) e definição do período da realização dos serviços; e 6- Supervisão da segurança e condições operacionais da rede elétrica e acompanhamento da execução das atividades.[054] Some activities of Operation of a utility company during the maintenance of transmission lines are listed below: 1- Approval and release of document to perform the services; 2- Request for authorization from ONS (National System Operator) to perform the services; 3- Mediation with the ONS of the maintenance request before, during and after the performance of the services; 4- Maneuvers of opening / closing of electrical equipment and locking / unlocking of command, control and protection system; 5- Availability of the electric network, interruption (if necessary) and definition of the period of the performance of the services; and 6- Supervision of safety and operational conditions of the electricity grid and monitoring the execution of activities.

[055] Alguns requisitos necessários e imprescindíveis para realização de atividades de manutenção em linhas de transmissão são listados abaixo: 1- Existência de documentação especifica no sistema de gerencia SAP/R3 aprovada e liberada pela operação do sistema elétrico para manutenção; 2- Existência de meios de comunicação operantes e funcionais para suporte à operação e manutenção; 3- Atendimento às normas e diretrizes operacionais / ONS para trabalhos em linha viva e/ou em linha morta.[055] Some necessary and indispensable requirements for maintenance activities on transmission lines are listed below: 1- Existence of specific documentation in the SAP / R3 management system approved and released by the operation of the electrical system for maintenance; 2- Existence of operative and functional media to support the operation and maintenance; 3- Compliance with ONS operational and guidelines for live and / or dead line work.

[056] Os tipos de instalações que devem ser atendidas por plataforma aérea de manutenção são: 1- Linhas de transmissão de alta e extra-alta tensão com faixa de servidão e sem faixa de servidão; 2- Subestações assistidas em regime de turno, semi-assistidas e desassistidas.[056] The types of installations that must be serviced by aerial maintenance platform are: 1- High and extra-high voltage transmission lines with servitude range and without servitude range; 2- Shift-assisted, semi-assisted and unassisted substations.

[057] As linhas vivas (energizadas) e linhas mortas (desenergizadas) referem-se a condições de operação de linhas de transmissão em estado de manutenção.[057] Live (energized) and dead (de-energized) lines refer to operating conditions of maintenance transmission lines.

[058] Os tipos de intervenções para a manutenção são: programada, urgente, emergente e extraordinária.[058] Types of maintenance interventions are: scheduled, urgent, emergent and extraordinary.

[059] A rotina de operação do sistema elétrico para atendimento às demandas de manutenção de linhas depende do tipo de intervenção, este tipo dita o ritmo de processamento da solicitação de intervenção.[059] The operating routine of the electrical system to meet line maintenance demands depends on the type of intervention, this type dictates the processing pace of the intervention request.

[060] Atualmente o rito prevê uma inspeção anual programada em toda linha atendendo o plano de manutenção anual. As inspeções são atividades programadas e o prazo para apreciação e liberação pela operação corresponde a 15 dias. Caso seja identificado algum ponto de não conformidade nova inspeção detalhada é solicitada à operação com nova programação com novos prazos para liberação.[060] The rite currently provides for a scheduled annual inspection across the board to meet the annual maintenance plan. Inspections are scheduled activities and the deadline for consideration and release by the operation is 15 days. If any non-compliance points are identified, a detailed inspection is requested to the operation with a new schedule with new release deadlines.

[061] As atividades de inspeção são tratadas ao nível de operação local e centro regional de operação, não sendo necessária a participação do Operador Nacional de Sistema - ONS para autorização e liberação da atividade.[061] Inspection activities are handled at the local operation level and regional center of operation, and the participation of the National System Operator (ONS) is not required to authorize and release the activity.

[062] O ONS é o agente responsável pela coordenação e controle da operação, da geração e transmissão de energia elétrica no Sistema Interligado Nacional - SIN.[062] ONS is the agent responsible for coordinating and controlling the operation, generation and transmission of electricity in the National Interconnected System - SIN.

[063] Com exceção das inspeções, toda e qualquer intervenção da manutenção de linhas de transmissão deve ser autorizada pelo ONS e deve seguir as diretrizes e normativas contidas no documento denominado Procedimentos de Rede, que abrange as normas técnicas e de segurança e regem os prazos para liberação de documentos.[063] With the exception of inspections, any intervention of transmission line maintenance shall be authorized by ONS and shall follow the guidelines and regulations contained in the document entitled Network Procedures, which covers technical and safety standards and govern the deadlines. for document release.

[064] Objetivos da Invenção [065] É um objetivo da presente invenção executar novos processos para construir, operar, inspecionar e manter linhas de transmissão reduzindo a dependência do acesso terrestre, reduzindo, acentuadamente, os esforços físicos das equipes em escaladas nas estruturas das torres, bem como os de içamento de equipamentos pesados para o alto das mesmas e o desmatamento.[064] Objectives of the Invention [065] It is an object of the present invention to perform new processes for constructing, operating, inspecting and maintaining transmission lines by reducing ground access dependency, markedly reducing the physical efforts of teams climbing the structures of the facilities. towers, as well as the lifting of heavy equipment to the top of it and deforestation.

[066] É um objetivo da presente invenção executar atividades em linhas de transmissão em trechos sem acesso, como por exemplo florestas de alta densidade, áreas alagadas e travessia de rios, por meio de veículo terrestre.[066] It is an object of the present invention to perform activities on transmission lines in stretches without access, such as high density forests, wetlands and river crossing, by land vehicle.

[067] É um objetivo da presente invenção reduzir custos no processo de construção, operação, inspeção e manutenção de linhas de transmissão.[067] It is an object of the present invention to reduce costs in the process of construction, operation, inspection and maintenance of transmission lines.

[068] É um objetivo da presente invenção evitar riscos desnecessários devido a rajadas de ventos súbitas e inesperadas, intensas o suficiente de forma a movimentar ou danificar as estruturas do dirigível ou da torre.[068] It is an object of the present invention to avoid unnecessary hazards due to sudden and unexpected gusts of wind strong enough to move or damage the airship or tower structures.

[069] É um objetivo da presente invenção evitar a utilização de elementos guias estendidos entre a plataforma aérea e a torre, ou elementos da torre a serem instalados, e o solo, o que também implicaria em riscos à aeronave e sua tripulação em condições meteorológicas adversas.[069] It is an object of the present invention to avoid the use of guide elements extended between the aerial platform and the tower, or tower elements to be installed, and the ground, which would also pose hazards to the aircraft and its crew in weather conditions. adverse.

[070] É um objetivo da presente invenção permitir a remoção da conexão mecânica prolongada entre a plataforma aérea e os elementos fixos ao solo, para poder abortar uma missão rapidamente ao se observar uma condição meteorológica adversa, de forma que a aeronave pode rapidamente adquirir altitude e se afastar dos elementos em solo.[070] It is an object of the present invention to allow the removal of the extended mechanical connection between the aerial platform and the grounding elements, so that a mission can be aborted rapidly upon observing an adverse weather condition, so that the aircraft can quickly acquire altitude. and move away from the ground elements.

[071] É um objetivo da presente invenção reduzir o impacto ambiental e melhorar as condições de trabalho, reduzindo substancialmente o risco de acidentes.[071] It is an object of the present invention to reduce environmental impact and improve working conditions by substantially reducing the risk of accidents.

[072] É um objetivo da presente invenção que o tempo de execução das atividades em uma linha de transmissão seja reduzido pela não dependência terrestre através da utilização de um veículo mais rápido, com maior alcance e autonomia.[072] It is an object of the present invention that the time taken to perform activities on a transmission line is reduced by non-ground dependency through the use of a faster vehicle with greater range and autonomy.

[073] É um objetivo da presente invenção realizar inspeções de múltiplas funções com apenas um sobrevoo pelo uso de vários equipamentos acoplados à plataforma.[073] It is an object of the present invention to perform multi-function inspections with only one overflight by the use of various equipment coupled to the platform.

[074] É um objetivo da presente invenção permitir e garantir que a comunicação entre as equipes de manutenção local e operação remota seja feita de maneira mais ampla e flexível com o apoio da plataforma com ganhos na segurança e na eficácia do processo de operação.[074] It is an object of the present invention to enable and ensure that communication between local maintenance and remote operation teams is made more broad and flexible with platform support with gains in safety and efficiency of the operation process.

[075] É um objetivo da presente invenção permitir o trabalho noturno nas linhas de transmissão.[075] It is an object of the present invention to permit night work on the transmission lines.

[076] É um objetivo da presente invenção propiciar a eliminação da formação dos corredores de passagens das linhas de transmissão, fato gerador de maior impacto ambiental do empreendimento.[076] It is an object of the present invention to provide for the elimination of the formation of transmission line passage corridors, which generate the greatest environmental impact of the enterprise.

[077] É um objetivo da presente invenção permitir a entrega de materiais, pessoas e equipamentos para executarem os serviços, assegurando todas as devidas distâncias de seguranças para desenvolverem seus trabalhos, mantendo a continuidade do circuito elétrico de potência.[077] It is an object of the present invention to permit the delivery of materials, persons and equipment to perform the services, ensuring all appropriate safety distances to carry out their work, while maintaining the continuity of the electrical power circuit.

[078] É um objetivo da presente invenção permitir maior velocidade aos acessos dos sistemas de transmissão, minimizando os tempos e os riscos de falta de equipamentos, principalmente quando houver necessidade de reparar sinistros em linhas de transmissão.[078] It is an object of the present invention to allow greater speed to access of transmission systems, minimizing the times and risks of equipment shortages, especially when there is a need to repair transmission line claims.

[079] É um objetivo da presente invenção ajudar na escolha do traçado da linha de transmissão ao proporcionar o levantamento de possíveis obstáculos pela varredura do terreno por meio de instrumentos e observação visual.[079] It is an object of the present invention to assist in the choice of transmission line layout by providing the survey of possible obstacles by scanning the ground by means of instruments and visual observation.

[080] É um objetivo da presente invenção, para as fases de seccionamento e aterramento de cercas, limpeza da faixa de servidão, construção das fundações, escavação e reaterro das escavações, facilitar o transporte de equipe e materiais.[080] It is an object of the present invention for the phases of fencing sectioning and grounding, easement strip cleaning, foundation construction, excavation and excavation backfilling, to facilitate the transportation of staff and materials.

[081] É um objetivo da presente invenção diminuir o tempo de reparo das linhas de transmissão e, consequentemente, aumento de disponibilidade.[081] It is an object of the present invention to decrease transmission line repair time and, consequently, increase availability.

[082] É um objetivo da presente invenção evitar a necessidade de dois deslocamentos (um para inspeção e outro para realizar a manutenção) das equipes e ter o problema agravado devido o descasamento do tempo da inspeção com o da realização da manutenção.[082] It is an object of the present invention to avoid the need for two offsets (one for inspection and one for maintenance) of teams and to have the problem aggravated due to mismatch of inspection time with that of performing maintenance.

[083] Sumário da invenção [084] O processo da presente invenção objetiva a construção de linhas de transmissão e compreende as seguintes etapas: disponibilizar um aeróstato adaptado com uma plataforma aérea, o referido aeróstato para ser utilizado em voos de prestação de serviços em linhas de transmissão; sobrevoar com o aeróstato a área onde as linhas de transmissão serão construídas para realizar o levantamento de dados e analisar a viabilidade da construção de linhas de transmissão ali; após a determinação da área, transportar com o aeróstato uma equipe técnica encarregada de preparar a área a ser utilizada para a instalação das linhas de transmissão e de realizar a montagem das linhas de transmissão; e transportar, com o referido aeróstato, materiais e equipamentos necessários para a construção das linhas de transmissão.[083] Summary of the Invention [084] The process of the present invention aims at the construction of transmission lines and comprises the following steps: providing an aerostat adapted with an aerial platform, said aerostat for use in line service flights transmission fly over with the aerostat the area where the transmission lines will be built to collect data and analyze the feasibility of building transmission lines there; After determining the area, transport with the aerostat a technical team responsible for preparing the area to be used for the installation of the transmission lines and for the assembly of the transmission lines. and to transport, with said airship, materials and equipment necessary for the construction of transmission lines.

[085] O processo de construção compreende ainda as seguintes etapas: recolher com o aeróstato a equipe e os materiais de preparação da área escolhida para instalação das linhas de transmissão; e realizar o lançamento de cabos condutores com o aeróstato em torres de linhas de transmissão.[085] The construction process also comprises the following steps: collecting with the aerostat the team and the preparation materials of the chosen area for the installation of the transmission lines; and conduct the laying of conductor cables with the aerostat on towers of transmission lines.

[086] A etapa de disponibilização de um aeróstato adaptado para ser utilizado em voos de prestação de serviços em linhas de transmissão refere-se à disponibilização de um dirigível adaptado.[086] The provision of an adapted airship for use on transmission line service flights refers to the provision of an adapted airship.

[087] As adaptações necessárias ao dirigível são: presença de um conjunto de hélices com capacidade de controle de direção sentido e magnitude de tração ao longo de seu eixo principal, além de capacidade de girar o eixo principal das hélices configurando possibilidade de vetoração de tração, assim a aeronave possui capacidades de voo horizontal e voo pairado estáveis e controlados. Presença de um conjunto de guinchos com carretéis e motores presos na gôndola com capacidade de suspensão de carga externa por meio de conexão por cabos, os quais tem o seu comprimento controlado pelos guinchos, possibilitando assim o controle de posicionamento da carga externa suspensa pelo movimento de descida e ascensão da carga, bem como controle de posicionamento no plano transversal à direção de descida e ascensão, esse conjunto de guinchos é denominado sistema de posicionamento de cargas suspensas. Presença de equipamentos de comunicação por rádio entre equipes em solo ou suspensas com a tripulação no dirigível, e da tripulação no dirigível com centros de controle e operação em locais remotos.[087] The necessary adaptations to the airship are: the presence of a set of propellers with direction control capability and traction magnitude along its main axis, as well as the ability to rotate the main axis of the propellers configuring traction vectorability. thus the aircraft has stable and controlled horizontal flight and hover flight capabilities. Presence of a set of winches with spools and motors attached to the gondola with external load suspension capacity by means of cable connections, which have their length controlled by the winches, thus enabling the positioning control of the suspended external load by the movement of load down and lift, as well as position control in the transverse plane to the down and up direction, this set of winches is called the suspended load positioning system. Presence of radio communication equipment between teams on the ground or suspended with the crew in the airship, and the crew in the airship with remote control and operation centers.

[088] A etapa de transporte da equipe técnica encarregada de preparar a área a ser utilizada para a instalação das linhas de transmissão compreende a descida da referida equipe até o solo dentro de um cesto por meio de um sistema de posicionamento de cargas suspensas. Sendo que não ocorre a transferência de massa na etapa de transporte da equipe. Além disso, a etapa de transporte de materiais e equipamentos necessários à construção das linhas de transmissão compreende ainda a entrega de equipamentos para preparação do terreno.[088] The transport step of the technical team in charge of preparing the area to be used for the installation of the transmission lines comprises the lowering of said team to the ground in a basket by means of a suspended load positioning system. Since there is no mass transfer in the team transport stage. In addition, the transportation of materials and equipment necessary for the construction of transmission lines also includes the delivery of equipment for land preparation.

[089] A entrega de equipamentos como tratores, retroescavadeiras e equipamentos afins para preparação do terreno acontece com ou sem a troca de carga e a etapa de entrega de equipamentos compreende o transporte e entrega de lastros para a área de montagem das torres de linhas de transmissão para, dessa forma, permitir a troca de cargas.[089] Delivery of equipment such as tractors, backhoe loaders and related ground preparation equipment takes place with or without load shifting and the equipment delivery stage comprises the transportation and delivery of ballast to the assembly line of the towers of transmission to allow load shifting.

[090] No processo aqui descrito a etapa de entrega de equipamentos compreende o transporte de pelo menos uma torre de linha de transmissão ou parte dessa e compreende a descida de pelo menos uma torre de linha de transmissão ou parte dessa utilizando o sistema de posicionamento de cargas suspensas, com um cabo guia apoiado em arestas da torre.In the process described herein the equipment delivery step comprises the transport of at least one transmission line tower or part thereof and comprises the descent of at least one transmission line tower using part positioning system. suspended loads, with a guide cable resting on tower edges.

[091] Uma equipe de solo é disponibilizada para realizar a fixação do cabo guia a um lastro posicionado a uma distância segura da torre. Sendo que a possibilidade de desacoplar o dirigível por meio do cabo guia existe. O recolhimento do cabo guia é realizado pelo sistema de posicionamento de cargas suspensas.[091] A ground crew is provided to secure the guide wire to a ballast positioned at a safe distance from the tower. The possibility of uncoupling the airship by means of the guide cable exists. The guide wire retraction is performed by the suspended load positioning system.

[092] A utilização de lastro para o recolhimento dos equipamentos do local de construção das linhas de transmissão está prevista. Sendo que haverá o uso de lastros que sejam capazes de garantir o heaviness (operação em que a aeronave está mais pesada que o ar) e lightness máximo (operação em que a aeronave está mais leve que o ar) do aeróstato adaptado.[092] The use of ballast to collect equipment from the transmission line construction site is planned. We will use ballasts that are capable of ensuring the heaviness (operation where the aircraft is heavier than air) and maximum lightness (operation where the aircraft is lighter than air) of the adapted aerostat.

[093] O recolhimento da equipe e dos materiais de preparação da área escolhida para instalação das linhas de transmissão é realizada, preferencialmente, sem a troca de carga e, preferencialmente, com o aeróstato em voo pairado.[093] The team and preparation materials for the area chosen for the installation of the transmission lines are collected preferably with no load change and preferably with the airship in hover.

[094] O posicionamento da equipe e dos materiais no cesto acontece sem necessidade de fazer transferência de cargas. Logo depois há o içamento do cesto e sua entrada em uma gôndola.[094] The positioning of staff and materials in the basket takes place without the need to transfer loads. Soon after there is the lifting of the basket and its entry in a gondola.

[095] O lançamento de cabos condutores com o aeróstato em torres de linhas de transmissão compreende primeiramente o lançamento de cabos guia ao longo das torres e permite o lançamento de cabos piloto, os quais por sua vez, permite o lançamento de cabos condutores. O lançamento de cabos guia ao longo das torres compreende a etapa de estender o cabo no chão ao longo da linha; e erguer os mesmos para o alto das torres. O içamento dos cabos guia é realizado por pessoas por meio de roldanas.[095] Laying conductive cables with the aerostat on transmission line towers primarily comprises laying guide cables along the towers and permitting the launching of pilot cables, which in turn allows the laying of conductive cables. Laying guidewires along the towers comprises the step of extending the cable to the ground along the line; and raise them to the top of the towers. Hoisting of the guide ropes is performed by people by pulleys.

[096] Já a etapa de lançamento de cabos guia é feito por um aeróstato e compreende ainda o transporte dos equipamentos de lançamento. O referido lançamento de cabos guia é realizado por um aeróstato ao sobrevoar uma linha de transmissão e liberar progressivamente o cabo guia de uma bobina.[096] The guide wire launching stage is performed by an airship and also includes the transportation of launching equipment. Said guide wire release is performed by an aerostat when flying over a transmission line and progressively releasing the guide cable from a coil.

[097] O posicionamento da bobina é realizado por meio do sistema de posicionamento de cargas suspensas.[097] Coil positioning is performed by means of the suspended load positioning system.

[098] Ao término do lançamento de cabo guia de um tramo, o aeróstato passa por uma transição de voo com velocidade para voo pairado. A extremidade do cabo é liberada da bobina e acoplada em um apoio pela equipe em solo.[098] At the end of a branch cable launch, the airship undergoes a speed-to-hover flight transition. The cable end is released from the coil and attached to a support by the ground crew.

[099] A invenção ainda compreende um processo de inspeção de linhas de transmissão compreendendo as seguintes etapas: sobrevoar o trecho da linha a ser inspecionado com um aeróstato adaptado com uma plataforma aérea; e realizar a inspeção durante o sobrevoo da etapa anterior.[099] The invention further comprises a transmission line inspection process comprising the following steps: overflying the stretch of line to be inspected with an aerostat adapted with an aerial platform; and perform the inspection during the overflight of the previous step.

[100] A inspeção compreende ainda a etapa de aproximar o aeróstato das torres a serem inspecionadas. O aeróstato ao se aproximar das torres na altura correta em relação às mesmas e em uma faixa de velocidade adequada até 120 Km/h, inicia a missão de inspeção de fato.[100] The inspection also comprises the step of bringing the aerostat closer to the towers to be inspected. By approaching the towers at the correct height in relation to them and at a suitable speed range up to 120 km / h, the aerostat begins the actual inspection mission.

[101] O sobrevoo das linhas é realizado com o aeróstato suficiente próximo, em distância entre 10 m e 100 m, de forma a permitir que equipamentos de inspeção detectem possíveis defeitos. A manutenção da altura do sobrevoo em relação ao topo das torres é praticamente constante ao longo da missão de inspeção e o sobrevoo é realizado em velocidade em relação ao solo que permite que os equipamentos de medição sejam utilizados.[101] Overflight of the lines is performed with sufficient airship nearby at a distance of 10 m to 100 m to allow inspection equipment to detect possible defects. Maintaining overflight height relative to the top of the towers is virtually constant throughout the inspection mission and overflight is performed at ground speed allowing the measuring equipment to be used.

[102] O processo de inspeção é realizado por um dirigível adaptado para uso em linhas de transmissão.[102] The inspection process is performed by an airship adapted for use on transmission lines.

[103] A inspeção compreende a coleta de dados da situação da linha de transmissão por meio de inspeção visual por um técnico habilitado.[103] Inspection comprises the collection of transmission line situation data by visual inspection by a qualified technician.

[104] A inspeção compreende a coleta de dados georreferenciados da situação da linha de transmissão por meio de inspeção instrumentalizada para verificações: de temperatura nas conexões de cabos por meio de termovisor, de efeito corona resultado de possíveis anomalias por meio do analisador de efeito corona, de escaneamento por laser para levantamento de altura e tipo de vegetação, de medição de altura cabo-solo “flecha”, de erosões ao longo da faixa de servidão, e de captura de imagens por câmera de vídeo de alta resolução.[104] Inspection comprises the collection of georeferenced data from the transmission line situation through instrumented inspection to verify: temperature in cable connections via thermal imager, corona effect resulting from possible anomalies through the corona effect analyzer. laser scanning for vegetation and height surveys, cable-to-ground height measurement, erosion along the easement strip, and high-resolution video camera capture.

[105] As etapas de inspeção podem ocorrer de forma simultânea ou individualizada. Ademais, as inspeções de múltiplas funções podem ser realizadas com apenas um sobrevoo pelo uso de vários equipamentos acoplados ao aeróstato adaptado.[105] Inspection steps may occur simultaneously or individually. In addition, multi-function inspections can be performed with just one overflight by the use of various equipment coupled to the adapted airship.

[106] A invenção compreende ainda um processo de manutenção de linhas de transmissão com as seguintes etapas: sobrevoar o trecho da linha a ser feita a manutenção com um aeróstato adaptado; e realizar a manutenção no local escolhido da linha de transmissão.[106] The invention further comprises a transmission line maintenance process with the following steps: overflying the section of line to be maintained with an adapted aerostat; and perform maintenance at the chosen location of the transmission line.

[107] A etapa de aproximar o aeróstato das torres que necessitam de manutenção é realizada para que a manutenção seja praticável. Nesse caso, o aeróstato permanece em voo pairado para a realização da referida manutenção.[107] The step of bringing the aerostat closer to the towers in need of maintenance is performed so that maintenance is practicable. In this case, the aerostat remains in hover flight for the accomplishment of said maintenance.

[108] Os técnicos especializados são posicionados suficientemente perto dos componentes a sofrer a manutenção. Após o posicionamento acontece a etapa de descida dos técnicos do aeróstato para a torre por meio de um cesto. Ou seja, o procedimento de manutenção pode ser realizado de pelo menos duas formas: os técnicos descerem do cesto para a torre com suas ferramentas, ou realizarem a manutenção de dentro do cesto.[108] Specialist technicians are positioned close enough to serviceable components. After positioning, the technician descends the aerostat to the tower by means of a basket. That is, the maintenance procedure can be performed in at least two ways: technicians get down from the basket to the tower with their tools, or perform maintenance from inside the basket.

[109] Na verdade, o procedimento de manutenção adotado depende do tempo necessário para realizar os trabalhos e da acessibilidade do cesto do local na torre a ser reparado.[109] In fact, the maintenance procedure adopted depends on the time required to complete the work and the accessibility of the basket on the tower to be repaired.

[110] Na manutenção, o aeróstato pode operar em heaviness, e a massa total descarregada pode ser menor do que o valor do heaviness do instante para os técnicos e suas ferramentas descerem do cesto sem precisar realizar transferência de massa.[110] In maintenance, the airship can operate at heaviness, and the total discharged mass may be less than the instantaneous heaviness value for technicians and their tools to descend from the basket without having to perform mass transfer.

[111] A manutenção compreende a etapa de direcionar jato de água nos componentes de linha de transmissão para efetuar a limpeza.[111] Maintenance comprises the step of directing water jet at the transmission line components to perform cleaning.

[112] A manutenção é realizada por um dirigível adaptado para uso em linhas de transmissão.[112] Maintenance is performed by an airship adapted for use on transmission lines.

[113] Um processo de operação também faz parte da presente invenção e compreende as etapas de: disponibilizar um aeróstato adaptado para ser utilizado em voos de prestação de serviços em linhas de transmissão; e posicionar o aeróstato adaptado em uma posição que permita realizar a comunicação entre as equipes de inspeção e manutenção com as subestações e/ou centros de operação regional. O processo de operação é realizado por um dirigível adaptado para uso em linhas de transmissão.[113] An operation process is also part of the present invention and comprises the steps of: providing an aerostat adapted for use on transmission line service flights; and position the adapted aerostat in a position that enables communication between inspection and maintenance teams with substations and / or regional operation centers. The operation process is carried out by an airship adapted for use on transmission lines.

[114] Portanto, o processo da presente invenção define uma nova logística de acesso ao sistema de transmissão, eliminando o acesso terrestre, reduzindo, acentuadamente, os esforços físicos das equipes em escaladas nas estruturas das torres, bem como os de içamento de equipamentos pesados para o alto das mesmas, que geralmente estão em locais de difícil acesso, como em áreas alagadas ou sem estradas ao longo do empreendimento. A plataforma fornece o acesso com facilidade, maior segurança, sem provocar grandes impactos ambientais, minimizando os custos atuais. Na construção de um sistema de transmissão, a plataforma transporta pessoas e equipamentos, bem como torres montadas, para os locais de instalação, eliminando os impactos ambientais para formar corredores de passagens, na vegetação existente ao longo do trajeto do sistema, configurando apenas impactos na região das bases das torres, com a vantagem de permanecer sobre o local por horas ou dias.[114] Therefore, the process of the present invention defines a new transmission system access logistics, eliminating ground access, markedly reducing the physical efforts of teams climbing the tower structures as well as lifting heavy equipment. to the top, which are usually in hard-to-reach places, such as flooded areas or no roads along the venture. The platform provides easy access, increased security without major environmental impacts while minimizing current costs. In the construction of a transmission system, the platform transports people and equipment, as well as mounted towers, to the installation sites, eliminating environmental impacts to form passageways in the vegetation along the system path, setting only impacts on the base region of the towers, with the advantage of remaining on the site for hours or days.

[115] A presente invenção tem como objetivo notadamente evitar os inconvenientes supracitados apresentando novos processos.[115] The present invention is particularly intended to avoid the above drawbacks by introducing new processes.

[116] Ainda, a patente requerida não exige que seções de ancoragem da plataforma aérea fiquem acopladas rigidamente à torre da linha de transmissão, pois, isso pode implicar em riscos desnecessários devido a rajadas de ventos súbitas e inesperadas, intensas o suficiente de forma que podem movimentar ou danificar as estruturas do dirigível ou da torre. Além do mais, para o processo de construção não se reivindica a utilização de elementos guias estendidos entre a plataforma aérea e a torre, ou elementos da torre a serem instalados, o que também implicaria em riscos à aeronave e sua tripulação em condições meteorológicas adversas. Removendo a conexão mecânica prolongada entre a plataforma aérea e os elementos fixos ao solo, pode-se abortar a missão rapidamente ao se observar uma condição meteorológica adversa, de forma que a aeronave pode rapidamente adquirir altitude e se afastar dos elementos em solo.[116] Further, the required patent does not require aerial platform anchor sections to be rigidly coupled to the transmission line tower, as this may entail unnecessary risks due to sudden and unexpected gusts of wind sufficiently intense that may move or damage the airship or tower structures. Moreover, the construction process does not claim to use guide elements extended between the aerial platform and the tower, or tower elements to be installed, which would also pose risks to the aircraft and its crew in adverse weather conditions. By removing the prolonged mechanical connection between the aerial platform and grounded elements, the mission can be quickly aborted by observing an adverse weather condition so that the aircraft can quickly gain altitude and move away from ground elements.

[117] O pedido de patente proposto reduz o custo do processo de construção, operação, inspeção e manutenção por sua sustentabilidade através da diminuição das atividades em solo que corroboram com a redução do impacto ambiental e melhoria das condições de trabalho, reduzindo substancialmente o risco de acidentes. Além do mais, o tempo de execução das atividades é reduzido pela não dependência terrestre através da utilização de um veículo mais rápido, com maior alcance e autonomia, o qual é capaz de realizar as inspeções de múltiplas funções com apenas um sobrevoo pelo uso de vários equipamentos acoplados à plataforma. Da mesma forma, a comunicação é feita de maneira mais ampla, flexível pelo uso de equipamentos instalados na plataforma, e ainda possui a vantagem da comunicação ser feita acima das copas das árvores que podem interferir na qualidade do sinal. O processo, no qual se refere esse pedido de patente, permite o trabalho noturno, através de iluminação artificial instalada ao longo da extensa plataforma, quando requerido em situações de emergência possibilitando o aumento da disponibilidade das linhas de transmissão.[117] The proposed patent application reduces the cost of the construction, operation, inspection and maintenance process by its sustainability by reducing soil activities that corroborate the reduction of environmental impact and improving working conditions, substantially reducing the risk. of accidents. In addition, the time taken to perform activities is reduced by non-ground dependency through the use of a faster, longer-range vehicle capable of performing multiple-function inspections with only one overflight by the use of multiple equipment attached to the platform. Likewise, communication is done more broadly, flexibly through the use of equipment installed on the platform, and still has the advantage of communication being above tree tops that can interfere with signal quality. The process, which refers to this patent application, allows night work, through artificial lighting installed along the extensive platform, when required in emergency situations allowing the increased availability of transmission lines.

[118] A presente invenção configura um processo utilizando uma plataforma aérea de trabalho para ser usada nos serviços de construção, operação, inspeção e manutenção de sistema de transmissão de energia elétrica energizada, a qual revoluciona a atual forma de trabalho, tendo uma inversão da atual lógica de trabalho, colocando a gravidade a favor dos serviços que são realizados. No processo de construção, se tem a redução acentuada dos impactos no meio ambiente ao propiciar a eliminação da formação dos corredores de passagens das linhas de transmissão, fato gerador de maior impacto ambiental do empreendimento.[118] The present invention provides a process utilizing an aerial work platform for use in the construction, operation, inspection and maintenance services of an energized electric power transmission system which revolutionizes the current form of work by having an inversion of the current work logic, placing gravity in favor of the services that are performed. In the construction process, there is a marked reduction of impacts on the environment by providing the elimination of the formation of transmission line passage corridors, which generates the greatest environmental impact of the project.

[119] Desta forma, para aplicação do novo método de trabalho utilizando a plataforma aérea, a qual permite a entrega de materiais, pessoas e equipamentos para executarem os serviços, assegurando todas as devidas distâncias de seguranças para desenvolverem seus trabalhos, mantendo a continuidade do circuito elétrico de potência. Permite ainda, maior velocidade aos acessos dos sistemas de transmissão, minimizando os tempos e os riscos de falta de equipamentos, principalmente quando houver necessidade de reparar sinistros em linhas de transmissão, beneficiando a sociedade e os consumidores na continuidade da energia elétrica. Assim, evita-se a necessidade de escalada das torres e de pessoas para içamento de materiais para a realização dos serviços por meio terrestre.[119] Thus, for the application of the new working method using the aerial platform, which allows the delivery of materials, people and equipment to perform the services, ensuring all the necessary safety distances to perform their work, maintaining the continuity of the work. electric power circuit. It also allows greater speed to access the transmission systems, minimizing the times and risks of equipment shortages, especially when there is a need to repair transmission line claims, benefiting society and consumers in the continuity of electricity. This avoids the need for climbing the towers and people for lifting materials to perform the services by land.

[120] O novo processo muda a atual forma de trabalho dos eletricistas de linhas de transmissão, invertendo a lógica de baixo para cima por descida de carga da plataforma na torre, caracterizando um processo descendente a partir da plataforma aérea, contribuindo diretamente na motivação e na segurança da equipe no exercício de suas atividades.[120] The new process changes the current way of working of transmission line electricians, reversing the bottom-up logic by lowering the platform load on the tower, characterizing a downward process from the aerial platform, directly contributing to the motivation and in the safety of the team in the exercise of their activities.

[121] A utilização da plataforma aérea, na fase de escolha do traçado da linha de transmissão, proporciona levantamento de possíveis obstáculos pela varredura do terreno por meio de instrumentos e observação visual, contribuindo para a escolha e o georeferenciamento dos prováveis locais de instalação das torres além do transporte de pessoal e equipamentos. Com a utilização da plataforma aérea a construção de estradas de acesso torna-se irrelevantes.[121] The use of the aerial platform, at the transmission line layout phase, allows for the survey of possible obstacles by scanning the terrain through instruments and visual observation, contributing to the choice and geo-referencing of the probable installation sites. towers in addition to the transportation of personnel and equipment. With the use of the aerial platform the construction of access roads becomes irrelevant.

[122] Para as fases de seccionamento e aterramento de cercas, limpeza da faixa de servidão, construção das fundações, escavação e reaterro das escavações, irá facilitar o transporte de equipe e materiais, ocasionando em economia de tempo e dinheiro.[122] For fencing sectioning and grounding, easement strip cleaning, foundation construction, excavation and excavation backfilling will facilitate the transportation of staff and materials, saving time and money.

[123] A montagem das torres poderá ser peça por peça ou por seções premontadas ou em uma peça completa no solo, e depois içadas e colocadas no seu lugar definitivo por meio do uso da plataforma aérea em tempo reduzido. A montagem das torres ou suas seções serão realizadas em pátios pré-selecionados que facilitem a montagem e o acesso, não sendo necessariamente no local de instalação final da torre.[123] Towers may be assembled piece by piece or by pre-assembled sections or as a complete piece on the ground, then lifted and placed in their final place by using the aerial platform in a short time. The towers will be assembled or sectioned in pre-selected courtyards that facilitate assembly and access, not necessarily at the tower's final installation site.

[124] O lançamento dos cabos se dará através do dirigível, estando a bobina no solo ou acoplada ao mesmo para posterior regulação e grampeamento pela equipe especializada.[124] The cables will be released through the airship, with the coil on the ground or attached to it for later adjustment and stapling by the specialized team.

[125] O uso da plataforma implicará em melhoria para a operação devido à facilidade de sobrevoar a linha de transmissão verificando possíveis danos e imediata comunicação ao centro de operação objetivando autorização para intervenção, diminuindo tempo de reparo e, consequentemente, aumento de disponibilidade.[125] The use of the platform will result in improved operation due to the ease of overflying the transmission line, checking for possible damage and immediate communication to the operation center for authorization to intervene, reducing repair time and consequently increasing availability.

[126] Com o uso da plataforma aérea, além da análise visual, as inspeções serão feitas ao longo da linha através de equipamentos para identificação de possíveis defeitos. Dependendo do problema identificado, a manutenção será feita imediatamente ou será programada para outra oportunidade.[126] Using the aerial platform, in addition to visual analysis, inspections will be made along the line through equipment to identify possible defects. Depending on the identified problem, maintenance will be done immediately or scheduled for another opportunity.

[127] A medição de resistência do pé de torre e do estado de corrosão serão realizadas através do dirigível com a descida do inspetor.[127] Measurement of turret strength and corrosion will be measured by the airship as the inspector descends.

[128] A plataforma será equipada com identificadores a laser de altura e tipo de vegetação definindo quando será necessária a intervenção para remoção da mesma.[128] The platform will be equipped with height and vegetation type laser identifiers defining when intervention will be required to remove it.

[129] Com a utilização da plataforma aérea não existirá mais a necessidade de dois deslocamentos (um para inspeção e outro para realizar a manutenção) e nem de ter o problema agravado devido o descasamento do tempo da inspeção com o da realização da manutenção.[129] With the use of the aerial platform there will no longer be a need for two offsets (one for inspection and one for maintenance) and the problem is aggravated due to mismatch of inspection time with that of maintenance.

[130] O custo de manter os diversos acessos para se chegar ao sistema de transmissão é eliminado, pois, o acesso passa a ser somente aéreo.[130] The cost of maintaining the various accesses to reach the transmission system is eliminated as access becomes air only.

[131] O maior obstáculo para a expansão do sistema de transmissão está relacionado ao problema socioambiental devido ao desmatamento. Com o novo processo, o custo para mitigar os impactos socioambientais será mínimo e o tempo para construir o empreendimento diminui consideravelmente em relação ao atual, pois, o maior tempo está justamente nas aberturas dos corredores de passagem das linhas de transmissão e no lançamento dos cabos.[131] The major obstacle to the expansion of the transmission system is related to the social and environmental problem due to deforestation. With the new process, the cost to mitigate the social and environmental impacts will be minimal and the time to build the project decreases considerably compared to the current one, since the longest time is precisely in the opening of the transmission line corridors and the launching of the cables. .

[132] O aeróstato da presente invenção também será importantíssimo para a operação do Sistema Elétrico na localização rápida e precisa de defeitos que tenham causados desligamentos permanentes ou intermitentes nas LTs, pois, ao sobrevoar a LT haverá disponíveis equipamentos de precisão que auxiliarão os inspetores na localização de defeitos. Uma vez localizado o defeito haverá disponível no aeróstato comunicação confiável para que os mantenedores entrem em ação e o Sistema seja restabelecido no menor tempo possível.[132] The aerostat of the present invention will also be very important for the operation of the Electrical System in the rapid and accurate localization of defects that have caused permanent or intermittent shutdowns in the LTs, as overflying the LT will provide precision equipment to assist inspectors in troubleshooting. Once the defect is found, reliable communication will be available on the airship so that the maintainers will take action and the System will be restored in the shortest possible time.

[133] Com relação à comunicação, haverá no aeróstato comunicação confiável, com duplicidade de equipamentos para que os mantenedores estejam em contato permanente com as subestações das extremidades da LT. Assim será garantida a segurança dos mantenedores bem como do Sistema Elétrico durante as manutenções programadas e daquelas emergências.[133] With regard to communication, there will be reliable communication with duplicate equipment in the airship so that maintainers are in permanent contact with the LT substations. This will ensure the safety of the maintainers as well as the electrical system during scheduled maintenance and emergencies.

[134] Portanto, com base nas considerações anteriores podemos afirmar que a maior alteração na forma de atuação da operação do sistema elétrico diz respeito aos prazos para apreciação dos pedidos de intervenção para manutenção uma vez que devemos resguardar as condicionantes técnicas e de segurança. Neste sentido tanto a operação local quanto os centros regionais e ONS devem conhecer a programação de inspeção de modo a antecipar analise e cumprir os prazos, que devem ser revistos para atender essa nova realidade, de modo a casar o cronograma de inspeção com o ritmo de navegação e prazos operacionais, será a nova realidade da operação do sistema elétrico de potência.[134] Therefore, based on the above considerations, we can state that the biggest change in the operation of the electric system operation concerns the deadlines for consideration of requests for maintenance intervention since we must safeguard the technical and safety constraints. In this regard, both local operation and regional and ONS centers should know the inspection schedule in order to anticipate analysis and meet deadlines, which must be revised to meet this new reality, so as to match the inspection schedule with the pace of navigation and operational deadlines, will be the new reality of the operation of the electric power system.

[135] Outra alteração significativa na rotina de operação conjuga aspectos técnicos e de segurança uma vez que diz respeito aos sistemas de comunicações com as equipes de manutenção. Essa alteração consiste em nova forma de comunicação com as equipes em campo, agora por meio da plataforma aérea que estará no local da manutenção em altitude que pode evitar as dificuldades de comunicação em visada direta com as subestações da extremidade do trecho de linha e representa segurança nas manobras operacionais posto que garante a comunicação com as subestações limítrofes ou mesmo com o centro regional de operação, para os casos de instalações desassistidas.[135] Another significant change in routine operation combines safety and technical aspects as it relates to maintenance team communications systems. This change is a new way of communicating with field teams, now through the aerial platform that will be at the altitude maintenance site that can avoid the difficulties of direct sight communication with the line-end substations and represents safety. in operational maneuvers since it ensures communication with neighboring substations or even with the regional center of operation, in the case of unattended installations.

[136] Descrição resumida dos desenhos [137] A Figura 1 ilustra o processo de inspeção de linhas de transmissão.[136] Brief Description of the Drawings [137] Figure 1 illustrates the transmission line inspection process.

[138] A Figura 2 ilustra o processo de manutenção de linhas de transmissão.[138] Figure 2 illustrates the transmission line maintenance process.

[139] A Figura 3 ilustra o processo de transporte e posicionamento com troca de carga de torre, parte de torre ou equipamento.[139] Figure 3 illustrates the process of transport and positioning with load shifting tower, tower part or equipment.

[140] A Figura 4 ilustra o processo de transporte, posicionamento e recolhimento de equipes e/ou equipamentos.[140] Figure 4 illustrates the process of transporting, positioning, and gathering teams and / or equipment.

[141] A Figura 5 ilustra o processo de lançamento de cabos guia.[141] Figure 5 illustrates the process of laying guidewires.

[142] A Figura 6 ilustra o processo de comunicação para operar linhas de transmissão.[142] Figure 6 illustrates the communication process for operating transmission lines.

[143] Descrição detalhada dos desenhos das figuras [144] A Figura 1 é representada pelo dirigível 1 que possui um envelope 2 responsável pela sustentação da maior parte do peso da aeronave, um conjunto de estabilizadores aerodinâmicos 3 que auxiliam no controle, uma gôndola 4 que possui os compartimentos funcionais, e hélices 5 responsáveis pela propulsão.[143] Detailed description of the drawings of the figures [144] Figure 1 is represented by the airship 1 which has an envelope 2 responsible for supporting most of the aircraft's weight, a set of aerodynamic stabilizers 3 that aid in control, a gondola 4 which has the functional compartments, and propellers 5 responsible for propulsion.

[145] O processo de inspeção se utiliza do sobrevoo de uma linha de inspeção com a capacidade de focar instrumentos específicos de detecção de defeitos na linha de transmissão realizando a coleta de dados georreferenciados da situação da linha de transmissão para verificações: de temperatura nas conexões de cabos por meio de termovisor, de efeito corona resultado de possíveis anomalias por meio do analisador de efeito corona, de escaneamento por laser para levantamento de altura e tipo de vegetação, de medição de altura cabo-solo “flecha”, de erosões ao longo da faixa de servidão, e de captura de imagens por câmera de vídeo de alta resolução., ou mesmo possibilitar o transporte de um técnico com capacidade de detectar defeitos apenas por meios visuais. O sobrevoo da linha deve, portanto, ser realizada em uma velocidade adequada que permita aos instrumentos obter eficientemente as imagens e dados necessários para que a situação da linha seja mapeada.[145] The inspection process utilizes over-inspection of an inspection line with the ability to focus on specific transmission line defect detection instruments by collecting georeferenced transmission line situation data for: temperature checks on connections. corona effect thermal imager result of possible anomalies via corona effect analyzer, laser scan for height and vegetation type, cable-to-ground height measurement, erosion along servitude range, and image capture by high-resolution camcorder, or even enable the transport of a technician who can detect defects only by visual means. Line overflight should therefore be performed at an appropriate speed that will allow the instruments to efficiently obtain the images and data needed to map the line situation.

[146] A velocidade de inspeção em relação ao solo está na faixa de 0 a 120 km/h, mais preferencialmente entre 60 e 80 km/h.[146] The ground inspection speed is in the range 0 to 120 km / h, more preferably between 60 and 80 km / h.

[147] Ainda, o dirigível deve se manter a uma distância segura da linha de transmissão, mas, ainda permitir a coleta de imagens e dados pelos instrumentos de inspeção e mesmo a inspeção visual. A distância durante o voo de inspeção deve ficar entre 10 m e 100 m, mais preferencialmente entre 30 e 50 m.[147] Still, the airship must be kept at a safe distance from the transmission line, but still allow the collection of images and data by the inspection instruments and even the visual inspection. The distance during the inspection flight should be between 10 m and 100 m, more preferably between 30 and 50 m.

[148] Assim, na Figura 1 pode-se notar o dirigível 1 sobrevoando a linha de inspeção abaixo composta de torres 8 e cabos condutores, OPGW e para raio 9. O prolongamento dos cabos de linha de transmissão é ilustrado por 10, visto que uma linha de transmissão se estende por vários quilômetros, logo o processo de inspeção também ocorre ao longo de vários quilômetros de linha de transmissão.[148] Thus, in Figure 1 one can see the airship 1 flying over the inspection line below composed of towers 8 and conductor cables, OPGW and radius 9. The extension of the transmission line cables is illustrated by 10, as a transmission line spans several kilometers, so the inspection process also takes place over several kilometers of the transmission line.

[149] O sobrevoo é mantido em velocidade praticamente constante com o dirigível sendo impulsionado por hélices 5. Os instrumentos de inspeção 6 são posicionados na gôndola 4 e focados em pontos a serem inspecionados na linha, representado pelo campo de inspeção visual e/ou instrumentalizada 7.[149] Overflight is maintained at nearly constant speed with the propeller-powered airship 5. Inspection instruments 6 are positioned on gondola 4 and focused on points to be inspected on the line, represented by the visual and / or instrumented inspection field. 7

[150] O processo de manutenção de linhas de transmissão é realizado após a identificação de defeitos na mesma, captados ao realizar o processo de inspeção de linhas de transmissão, ou mesmo é realizado devido a manutenções periódicas na linha, ou seja, não necessariamente resultado de detecção de defeitos por meio de inspeção.[150] The transmission line maintenance process is performed after identifying defects in the transmission line, which have been detected while performing the transmission line inspection process, or even due to periodic line maintenance, ie not necessarily a result. defect detection by inspection.

[151] A Figura 2 ilustra o processo de manutenção de linhas de manutenção que pode ser realizada de três formas: transferência de técnicos do dirigível para a linha de transmissão para realizar manutenção em componentes da linha de transmissão com posterior resgate dos técnicos na linha para o dirigível, representado pelas Figuras 2.1 a 2.5, 2.10 e 2.11; realização de manutenção em componentes da linha com os técnicos dentro de cesto suspenso pelo dirigível sem descida para a linha de transmissão, representado pelas Figuras 2.1, 2.6, 2.7, 2.10 e 2.11; e realização de limpeza de componentes com técnico direcionando jato de água de dentro de cesto suspenso, representado pelas Figuras 2.1,2.8, 2.9, 2.10 e 2.11.[151] Figure 2 illustrates the maintenance line maintenance process that can be performed in three ways: technician transferring the airship to the transmission line to perform maintenance on transmission line components with subsequent rescue of the line technicians to the airship, represented by Figures 2.1 to 2.5, 2.10 and 2.11; performing line component maintenance with technicians in basket suspended by the drivable without descending into the transmission line, represented by Figures 2.1, 2.6, 2.7, 2.10 and 2.11; and performing component cleaning with a technician directing water jet from the overhead basket, represented by Figures 2.1,2.8, 2.9, 2.10 and 2.11.

[152] A Figura 2.1 ilustra o início de qualquer uma das três formas de manutenção, onde o dirigível 1 é mantido em voo pairado com as hélices 5 direcionadas de forma que a tração controle a altura do dirigível 1. Ainda, técnicos com equipamentos 15 de manutenção de linha de transmissão são transferidos para um cesto 14 e descidos pelo sistema de posicionamento de cargas suspensas 11, visando aproximação da torre de linha de transmissão 8 e/ou dos cabos de linha de transmissão 9.[152] Figure 2.1 illustrates the beginning of any of the three forms of maintenance, where airship 1 is held in hover flight with propellers 5 directed so that traction controls the height of airship 1. Still, technicians with equipment 15 Transmission line maintenance devices are transferred to a basket 14 and lowered by the suspended load positioning system 11 to approximate transmission line tower 8 and / or transmission line cables 9.

[153] Seguindo agora com o processo de manutenção de linhas de transmissão com transferência de técnicos do dirigível para a linha de transmissão, a próxima etapa é a da Figura 2.2. Esta figura ilustra a descida e posicionamento em cima de torre de linha de transmissão 8, dos técnicos com equipamentos de manutenção 15 dentro do cesto 14, por meio do sistema de posicionamento de cargas suspensas 11, enquanto o dirigível 1 é mantido em voo pairado com auxílio das hélices 5.[153] Now following the process of maintaining transmission lines with technicians transferring the airship to the transmission line, the next step is that of Figure 2.2. This figure illustrates the descent and positioning above transmission line tower 8 of technicians with maintenance equipment 15 within basket 14 by means of suspended load positioning system 11 while airship 1 is maintained in hover flight. propeller assistance 5.

[154] A seguir se inicia a etapa da Figura 2.3 onde os técnicos e equipamentos 15 descem do cesto 14 para a torre de linha de transmissão 8. Então o cesto 14 é erguido pelo sistema de posicionamento de cargas suspensas 11 enquanto o dirigível 1 é mantido em voo pairado com auxílio das hélices 5.[154] Next begins the step in Figure 2.3 where technicians and equipment 15 descend from basket 14 to driveline tower 8. Then basket 14 is lifted by suspended load positioning system 11 while airship 1 is maintained in hovered flight with the aid of the propellers 5.

[155] A Figura 2.4 então ilustra o início dos procedimentos de manutenção em componentes da linha de transmissão pelos técnicos com equipamentos 15. O dirigível 1 então permanece em voo pairado ou realiza voo de espera. O cesto 14 é então recolhido pelo sistema de posicionamento de cargas suspensas 11.[155] Figure 2.4 then illustrates the initiation of maintenance procedures on transmission line components by technicians with equipment 15. Airship 1 then remains in a hover or performs a standby flight. The basket 14 is then collected by the suspended load positioning system 11.

[156] Com o término dos procedimentos de manutenção pelos técnicos 15 em cima da torre de linha de transmissão 8, o dirigível retorna para resgatá-los, o que é mostrado na Figura 2.5. O sistema de posicionamento de cargas suspensas 11 aproxima o cesto 14 dos técnicos e equipamentos 15, para que estes então entrem no cesto 14.[156] Upon completion of maintenance procedures by technicians 15 on transmission line tower 8, the airship returns to rescue them, as shown in Figure 2.5. Suspended load positioning system 11 brings basket 14 closer to technicians and equipment 15 so that they then enter basket 14.

[157] A próxima etapa é mostrada na Figura 2.10 onde os técnicos e equipamentos 15 dentro do cesto 14 são erguidos pelo sistema de posicionamento de cargas suspensas 11 para dentro da gôndola 4. O dirigível é então acelerado pelas hélices 5.[157] The next step is shown in Figure 2.10 where technicians and equipment 15 inside basket 14 are lifted by suspended load positioning system 11 into gondola 4. The airship is then accelerated by propellers 5.

[158] A última etapa deste processo de manutenção de linha de transmissão é mostrada na Figura 2.11, onde o dirigível 1 prossegue com voo horizontal propulsionado pelas hélices 5, com os técnicos e equipamentos no interior da gôndola 4.[158] The last step of this transmission line maintenance process is shown in Figure 2.11, where airship 1 proceeds with horizontal flight propelled by propellers 5, with technicians and equipment inside gondola 4.

[159] A segunda forma de manutenção de linha de transmissão onde os técnicos são mantidos dentro do cesto suspenso pelo dirigível sem descida para a linha de transmissão, é iniciada pela etapa da Figura 2.1 descrita anteriormente.[159] The second form of driveline maintenance where technicians are held within the basket suspended by the drivable without descending into the driveline is initiated by the step of Figure 2.1 described above.

[160] A próxima etapa é ilustrada na Figura 2.6 onde o dirigível 1 mantem voo pairado enquanto técnicos com equipamentos 15 dentro do cesto 14, suspensos pelo sistema de posicionamento de cargas suspensas 11 realizam procedimentos de manutenção em componentes da linha de transmissão, próximos de torre de linha de transmissão 8 e/ou cabos de linha de transmissão (condutores, OPGW, para raio) 9.[160] The next step is illustrated in Figure 2.6 where airship 1 is hovering while technicians with equipment 15 in basket 14 suspended by overhead load positioning system 11 perform maintenance procedures on transmission line components close to transmission line tower 8 and / or transmission line cables (conductors, OPGW, to lightning) 9.

[161] Ao término dos procedimentos de manutenção em componentes da linha de transmissão em um ponto, o dirigível 1 pode se deslocar por meio de ação de hélices 5 para outro ponto próximo onde os técnicos com equipamentos 15, dentro do cesto 14, suspensos pelo sistema de posicionamento de cargas suspensas 11, possam realizar procedimentos de manutenção em componentes de linha de transmissão em um ponto diferente do anterior, próximos de torre de linha de transmissão 8 e/ou cabos de linha de transmissão (condutores, OPGW, para raio) 9. Essa etapa é mostrada na Figura 2.7.[161] At the completion of maintenance procedures on driveline components at one point, airship 1 may be driven by propeller 5 to another near point where technicians with equipment 15 inside basket 14 are suspended by suspended load positioning system 11, can perform maintenance procedures on transmission line components at a point other than above, near transmission line tower 8 and / or transmission line cables (conductors, OPGW, to lightning) 9. This step is shown in Figure 2.7.

[162] A próxima etapa é mostrada na Figura 2.10, onde os técnicos e equipamentos 15 dentro do cesto 14 são erguidos pelo sistema de posicionamento de cargas suspensas 11 para dentro da gôndola 4. O dirigível é então acelerado pelas hélices 5.[162] The next step is shown in Figure 2.10, where technicians and equipment 15 inside basket 14 are lifted by suspended load positioning system 11 into gondola 4. The airship is then accelerated by propellers 5.

[163] A última etapa deste processo de manutenção de linha de transmissão é mostrada na Figura 2.11, onde o dirigível 1 prossegue com voo horizontal propulsionado pelas hélices 5, com os técnicos e equipamentos no interior da gôndola 4.[163] The last step of this transmission line maintenance process is shown in Figure 2.11, where airship 1 proceeds with horizontal flight propelled by propellers 5, with technicians and equipment inside gondola 4.

[164] A terceira e última forma de manutenção de linha de transmissão onde os técnicos são mantidos dentro do cesto suspenso pelo dirigível sem descida para a linha de transmissão e direcionam jato de água para limpeza de componentes de linha de transmissão, é iniciada pela etapa da Figura 2.1 descrita anteriormente.[164] The third and last form of driveline maintenance where technicians are kept inside the basket suspended by the drivable without dropping to the driveline and directing water jet to clean driveline components, is initiated by step of Figure 2.1 described above.

[165] A seguir inicia-se a etapa da Figura 2.8, onde os técnicos e equipamentos 15, dentro de cesto 14, mantidos suspensos pelo sistema de posicionamento de cargas suspensas 11, direcionam jato de água 16, com tanque de água no interior da gôndola 4 conectado por uma mangueira 18, para limpeza de componentes de linha de transmissão, como isoladores 17, próximos de torre de linha de transmissão 8 e/ou cabos de linha de transmissão (condutores, OPGW, para raio).[165] Next begins the step of Figure 2.8, where technicians and equipment 15, in basket 14, held suspended by the suspended load positioning system 11, direct water jet 16, with water tank inside the gondola 4 connected by a hose 18 for cleaning transmission line components such as insulators 17, near transmission line tower 8 and / or transmission line cables (conductors, OPGW, to lightning).

[166] A etapa seguinte mostrada na Figura 2.9 também mostra procedimento de manutenção de limpeza de componentes de linha de transmissão, onde o dirigível 1 se desloca por meio de ação de hélices 5 para que os técnicos com equipamentos 15, dentro de cesto 14, suspenso pelo sistema de posicionamento de cargas suspensas 11, consigam atingir um ponto diferente com jato de água 16, com tanque de água no interior da gôndola 4 conectado por uma mangueira 18, para limpeza de componentes de linha de transmissão, como isoladores 17, próximos de torre de linha de transmissão 8 e/ou cabos de linha de transmissão (condutores, OPGW, para raio).[166] The next step shown in Figure 2.9 also shows transmission line component cleaning maintenance procedure, where airship 1 moves by propeller action 5 so that technicians with equipment 15, in basket 14, suspended by the suspended load positioning system 11, can reach a different point with water jet 16, with water tank inside gondola 4 connected by a hose 18, for cleaning transmission line components such as insulators 17 nearby transmission line tower cables and / or transmission line cables (conductors, OPGW, to lightning).

[167] Segue-se então para a etapa da Figura 2.10, onde os técnicos e equipamentos 15 dentro do cesto 14 são erguidos pelo sistema de posicionamento de cargas suspensas 11 para dentro da gôndola 4. O dirigível é então acelerado pelas hélices 5.[167] Then goes to the step of Figure 2.10, where technicians and equipment 15 inside the basket 14 are lifted by the suspended load positioning system 11 into the gondola 4. The airship is then accelerated by the propellers 5.

[168] A última etapa deste processo de manutenção de linha de transmissão é mostrada na Figura 2.11, onde o dirigível 1 prossegue com voo horizontal propulsionado pelas hélices 5, com os técnicos e equipamentos no interior da gôndola 4.[168] The last step of this transmission line maintenance process is shown in Figure 2.11, where airship 1 proceeds with horizontal flight propelled by propellers 5, with technicians and equipment inside gondola 4.

[169] O processo de transporte e posicionamento, com troca de carga, de torre, parte de torre ou equipamento ocorre como um processo para construção de linhas de transmissão, ou mesmo recomposição de uma linha de transmissão onde torre, ou torres sofreram danos e devem ser substituídas.[169] The process of transporting and positioning, with load shifting, tower, tower part or equipment occurs as a process for building transmission lines, or even rebuilding a transmission line where tower or towers have been damaged and should be replaced.

[170] O processo completo é descrito na Figura 3, que se inicia pela etapa da Figura 3.1 onde o dirigível 1 transporta até o local de construção a torre, parte de torre ou equipamento 19, suspenso pelo sistema de posicionamento de cargas suspensas 11 e a propulsão é devido às hélices 5.[170] The complete process is described in Figure 3, beginning with the step of Figure 3.1 where the airship 1 carries the tower, tower part or equipment 19 suspended by the suspended load positioning system 11 and propulsion is due to propellers 5.

[171] A próxima etapa é ilustrada na Figura 3.2, onde ao se aproximar do local de construção, o dirigível 1 com a torre, parte de torre ou equipamento 19, suspenso pelo sistema de posicionamento de cargas suspensas 11 reduz a velocidade de voo até permanecer em voo pairado, com ajustes de velocidade com auxílio das hélices 5. Enquanto isso, uma equipe de técnicos e equipamentos 15 com lastro 20, aguardam no solo.[171] The next step is illustrated in Figure 3.2, where as you approach the construction site, the airship 1 with the tower, tower part or equipment 19 suspended by the suspended load positioning system 11 reduces the flight speed to remain in a hover flight, with propeller 5 speed adjustments. Meanwhile, a team of technicians and equipment 15 with ballast 20 await on the ground.

[172] Na Figura 3.3, próxima etapa, o dirigível 1 permanece em voo pairado enquanto a torre, parte de torre ou equipamento 19, é mantido suspenso pelo sistema de posicionamento de cargas suspensas 11. Um cabo guia de transferência de cargas 21, preso em uma extremidade ao sistema de posicionamento de cargas suspensas 11 e outra extremidade livre, é descido até a equipe de técnicos e equipamentos 15 com lastro 20.[172] In Figure 3.3, next step, airship 1 remains in hovered flight while the tower, tower part or equipment 19 is held suspended by the suspended load positioning system 11. A load transfer guide cable 21 is secured at one end the suspended load positioning system 11 and the other free end is lowered to the ballast 20 technicians and equipment 15.

[173] A seguir, mostrado na Figura 3.4, o cabo guia de transferência de cargas 21 é preso no lastro 20 pela equipe em solo de técnicos e equipamentos 15. Ainda, a torre, parte de torre ou equipamento 19 é descido e posicionado no solo pelo sistema de posicionamento de cargas suspensas, enquanto o dirigível 1 é mantido em voo pairado com o auxílio das hélices 5.[173] Next, shown in Figure 3.4, the load transfer guide cable 21 is secured to ballast 20 by the ground crew of technicians and equipment 15. In addition, the tower, tower part or equipment 19 is lowered and positioned in the suspended loads positioning system, while airship 1 is maintained in hovered flight with the aid of propellers 5.

[174] Uma vez posicionado o cabo guia de transferência de cargas no lastro e a torre, parte de torre ou equipamento posicionado no seu devido lugar, pode-se iniciar a etapa da Figura 3.5. Nesta etapa o sistema de posicionamento de cargas suspensas 11 se desacopla da torre, parte de torre ou equipamento 19, o que provoca o movimento de ascensão do dirigível 1 pela condição de lightness resultante, provocada pela força de sustentação do envelope 2 acima do peso da aeronave. As hélices 5 podem desacelerar o movimento de ascensão ao aplicar tração no sentido contrário ao movimento de subida. O movimento de subida será encerrado no momento que o dirigível 1 atingir o auge permitido pela extensão máxima do cabo guia de transferência de cargas 21.[174] Once the load transfer guide cable is positioned on the ballast and the tower, tower part or equipment in place, the step in Figure 3.5 can be started. In this step the suspended load positioning system 11 decouples from the tower, tower part or equipment 19, which causes the upward movement of the airship 1 by the resulting lightness condition, caused by the holding force of the envelope 2 above the weight of the aircraft. Propellers 5 may slow up the upward movement by applying traction counterclockwise. The upward movement will be terminated when the airship 1 reaches the height allowed by the maximum extension of the load transfer guide cable 21.

[175] A etapa da Figura 3.6 mostra o dirigível 1 no auge do movimento de ascensão, e está com movimentação estabilizada. Nesta condição o dirigível 1 é mantido na posição pela fixação ao lastro 20 por meio do cabo guia de transferência de cargas 21 e pelo sistema de posicionamento de cargas suspensas 11. Nesta condição o dirigível pode iniciar a enrolar o cabo guia de transferência de cargas 21, de forma a aproximar a extremidade do sistema de posicionamento de cargas suspensas 11 do lastro 20, trazendo simultaneamente o dirigível 1 para baixo.[175] The step in Figure 3.6 shows airship 1 at the height of the upward movement, and has stabilized movement. In this condition the airship 1 is held in position by securing to the ballast 20 by means of the load transfer guide cable 21 and the suspended load positioning system 11. In this condition the airship can start to wind the load transfer guide cable 21 , so as to bring the end of the suspended load positioning system 11 closer to the ballast 20 while bringing the airship 1 downwards.

[176] A etapa da Figura 3.7 mostra a condição em que o cabo guia de transferência de cargas está completamente enrolado, com o dirigível 1 abaixado, e o sistema de posicionamento de cargas suspensas 11 é acoplado ao lastro 20 com auxílio da equipe de técnicos e equipamentos 15 em solo.[176] The step in Figure 3.7 shows the condition in which the load transfer guide cable is completely coiled, with airship 1 lowered, and the suspended load positioning system 11 is coupled to ballast 20 with the help of the technical team. and equipment 15 on the ground.

[177] A seguir inicia-se a etapa da Figura 3.8, onde o dirigível 1 realiza decolagem vertical com atuação das hélices 5, e o lastro 20 é mantido suspenso pelo sistema de posicionamento de cargas suspensas 11.0 lastro 20 é então aproximado da gôndola 4 sendo erguido pelo sistema de posicionamento de cargas suspensas 11.[177] Next begins the step of Figure 3.8, where airship 1 performs vertical take-off with propeller actuation 5, and ballast 20 is held suspended by the suspended load positioning system 11.0 ballast 20 is then approached from gondola 4 being lifted by the suspended load positioning system 11.

[178] Uma vez erguido o lastro, inicia-se a etapa da Figura 3.9, onde o dirigível 1 é acelerado pela ação das hélices 5, enquanto o lastro 20 é mantido suspenso pelo sistema de posicionamento de cargas suspensas 11.[178] Once the ballast has been lifted, the step in Figure 3.9 begins, where the airship 1 is accelerated by the action of the propellers 5, while the ballast 20 is held suspended by the suspended load positioning system 11.

[179] A etapa final é mostrada na Figura 3.10 que ilustra o transporta do lastro 20, pelo dirigível 1, mantido suspenso pelo sistema de posicionamento de cargas suspensas 11, cuja propulsão é devida às hélices 5.[179] The final step is shown in Figure 3.10 which illustrates the transport of the ballast 20 by the airship 1 held suspended by the suspended load positioning system 11, whose propulsion is due to the propellers 5.

[180] O processo de transporte, posicionamento e recolhimento de equipes e/ou equipamentos, é utilizado nas missões em que é necessário transferir equipes e equipamentos do dirigível para o solo, e os mesmos do solo para o dirigível.[180] The process of transporting, positioning, and gathering teams and / or equipment is used in missions where it is necessary to transfer teams and equipment from the airship to the ground, and from the ground to the airship.

[181] Os dois processos completos são mostrados na Figura 4. O processo de entrega de equipes e/ou equipamentos ao solo é ilustrado pelas etapas da Figura 4.1 à Figura 4.5, e o processo de recolhimento de equipes e/ou equipamentos do solo para o dirigível é ilustrado pelas etapas da Figura 4.6 à Figura 4.10.[181] The two complete processes are shown in Figure 4. The process of delivering teams and / or equipment to the ground is illustrated by the steps in Figure 4.1 to Figure 4.5, and the process of collecting teams and / or equipment from the ground to The airship is illustrated by the steps from Figure 4.6 to Figure 4.10.

[182] Primeiramente para o processo de entrega de equipes e/ou equipamentos ao solo, o início se dá na etapa da Figura 4.1 onde o dirigível 1 em voo pairado sobre o local de entrega inicia a descida dos técnicos e equipamentos 15, dentro do cesto 14, pelo sistema de posicionamento de cargas suspensas 11.[182] Primarily for the ground and / or equipment delivery process, the start is at the stage in Figure 4.1 where airship 1 hovering over the delivery site initiates the descent of technicians and equipment 15 into the basket 14 by the suspended load positioning system 11.

[183] A Figura 4.2 ilustra a etapa seguinte onde o cesto 14, com os técnicos e equipamentos 15, estão próximos ao solo no ponto mais baixo de descida pelo sistema de posicionamento de cargas suspensas 11, enquanto o dirigível 1 se mantém em voo pairado.[183] Figure 4.2 illustrates the next step where basket 14, with technicians and equipment 15, is close to the ground at the lowest point of descent by overhead load positioning system 11, while airship 1 remains in hover flight. .

[184] Segue-se com a etapa da Figura 4.3, onde os técnicos e equipamentos 15 desembarcam do cesto 14 para o solo, então o sistema de posicionamento de cargas suspensas 11 ergue o cesto 14, enquanto o dirigível 1 se mantém em voo pairado.[184] This is followed by the step in Figure 4.3, where technicians and equipment 15 disembark from basket 14 to the ground, then the suspended load positioning system 11 lifts basket 14, while airship 1 remains in hover flight. .

[185] A próxima etapa é mostrada na Figura 4.4 com os técnicos e equipamentos 15 já em solo, o cesto 14 terminando de ser erguido pelo sistema de posicionamento de cargas suspensas 11 para entrar no interior da gôndola 4. Assim, o dirigível 1 inicia a acelerar para seguir com o voo horizontal com atuação propulsiva das hélices 5.[185] The next step is shown in Figure 4.4 with the technicians and equipment 15 already on the ground, the basket 14 just being lifted by the suspended load positioning system 11 to get inside the gondola 4. Thus the airship 1 starts accelerating to continue with horizontal propulsive propeller flight 5.

[186] Por fim, a Figura 4.5 mostra a etapa final desse processo, onde o cesto encontra-se no interior da gôndola 4, e o dirigível 1 prossegue com voo horizontal com propulsão devido às hélices 5.[186] Finally, Figure 4.5 shows the final step of this process, where the basket is inside the gondola 4, and the airship 1 proceeds with horizontal propelled flight due to the propellers 5.

[187] Agora, o processo que envolve o recolhimento de equipes e/ou equipamentos do solo para o dirigível é iniciado pela etapa da Figura 4.6, onde a equipe de técnicos e equipamentos 15 em solo aguarda, enquanto o dirigível 1 em voo pairado inicia a descida do cesto 14 por meio do sistema de posicionamento de cargas suspensas 11.[187] Now the process that involves gathering crews and / or equipment from the ground to the airship is started by the step in Figure 4.6, where the ground crew of technicians and equipment 15 awaits, while the airship 1 in hover flight begins. lowering the basket 14 by means of the suspended load positioning system 11.

[188] A Figura 4.7 mostra a etapa seguinte, onde o cesto 14 suspenso pelo sistema de posicionamento de cargas suspensas 11 encontra-se próximo ao solo de forma que os técnicos e equipamentos 15 possam ser embarcados, enquanto o dirigível 1 mantém voo pairado.[188] Figure 4.7 shows the next step, where the basket 14 suspended by the suspended load positioning system 11 is close to the ground so that technicians and equipment 15 can be boarded while the airship 1 maintains a hover flight.

[189] A seguir na Figura 4.8, a etapa seguinte, o cesto com os técnicos e equipamentos 15 embarcados no cesto 14 são erguidos pelo sistema de posicionamento de cargas suspensas 11, enquanto o dirigível 1 é mantido em voo pairado.[189] Next in Figure 4.8, the next step, the basket with the technicians and equipment 15 embedded in the basket 14 is lifted by the suspended load positioning system 11, while the airship 1 is held in hover flight.

[190] A etapa seguinte na Figura 4.9 mostra o cesto 14 com os técnicos e equipamentos terminando de serem erguidos pelo sistema de posicionamento de cargas suspensas 11 para entrarem na gôndola 4, enquanto o dirigível 1 inicia a aceleração para voo horizontal devido à ação propulsiva das hélices 5.[190] The next step in Figure 4.9 shows basket 14 with technicians and equipment just being lifted by overhead load positioning system 11 to enter gondola 4, while airship 1 initiates acceleration for horizontal flight due to propulsive action. of the propellers 5.

[191] Por fim, a Figura 4.10 ilustra a etapa final deste processo onde o cesto encontra-se no interior da gôndola 4, e o dirigível 1 prossegue com voo horizontal com propulsão devido às hélices 5.[191] Finally, Figure 4.10 illustrates the final step of this process where the basket is inside the gondola 4, and the airship 1 proceeds with horizontal propelled flight due to the propellers 5.

[192] O processo de lançamento de cabos guia é utilizado durante missões de construção de linhas de transmissão após a instalação das torres para instalação posterior de cabos de linha de transmissão (condutor, OPGW e para raio).[192] The cable routing process is used during transmission line construction missions after the installation of the towers for subsequent installation of transmission line cables (conductor, OPGW and lightning).

[193] A Figura 5 ilustra esse processo onde um dirigível 1 sobrevoando com velocidade praticamente constante em relação ao solo de até 120 km/h, uma linha de transmissão composta no momento apenas pelas torres 8, libera progressivamente cabos guia de instalação de cabos de linha de transmissão 13 ao desenrolar bobina de cabos guia 12, suspensa pelo sistema de posicionamento de cargas suspensas 11. O prolongamento do posicionamento dos cabos guia em cima das torres de linha de transmissão ao longo da extensão da linha é ilustrado por 10. Esse processo deve ser realizado com o dirigível 1 a uma distância segura das torres de linha de transmissão 8 de 10 m a 100 m.[193] Figure 5 illustrates this process where an airship 1 flying at practically constant ground speed of up to 120 km / h, a transmission line currently composed only of towers 8, progressively releases installation cables from driveline 13 when unwinding guidewire 12 suspended by the suspended load positioning system 11. Extending the positioning of the guidewires over the driveline towers along the line extension is illustrated by 10. This process must be made with airship 1 at a safe distance from transmission line towers 8 of 10 m to 100 m.

[194] Em todas as missões de operação de linhas de transmissão com o uso do dirigível deve ser possível a comunicação das equipes em solo, suspensas no cesto pelo sistema de posicionamento de cargas suspensas, ou em cima da linha de transmissão com a tripulação no dirigível, e também a comunicação da tripulação no dirigível com estações de controle e operação do operador da linha de transmissão.[194] In all transmission line operation missions using the airship, it shall be possible for teams to communicate on the ground, suspended in the basket by the suspended load positioning system, or above the transmission line with the crew in the airship, and also communication of the airship crew with transmission line operator control and operation stations.

[195] Assim, a Figura 6 ilustra esse processo de comunicação para operar linhas de transmissão, onde a equipe de técnicos e equipamento 15 em solo, ou no cesto suspenso pelo sistema de posicionamento de cargas suspensas, ou em cima da linha de transmissão, e a tripulação no dirigível 1 possuem equipamentos de comunicação via rádio que permitem a comunicação entre eles, representado pela seta bidirecional 22. Ainda, a tripulação no dirigível 1 possui equipamentos de comunicação via rádio que permite a comunicação, representada pela seta bidirecional 23, com equipes em estações de controle e operação em local remoto 24 do operador da linha de transmissão.[195] Thus, Figure 6 illustrates this communication process for operating transmission lines, where the team of technicians and equipment 15 on the ground, or in the basket suspended by the suspended load positioning system, or on top of the transmission line, and the crew in airship 1 have radio communication equipment that allows communication between them, represented by the two-way arrow 22. Also, the crew in airship 1 has radio communication equipment that allows communication, represented by the two-way arrow 23, with personnel at remote control station and operation stations 24 of the transmission line operator.

[196] Conforme pode ser verificado, a presente invenção descreve um método de utilização de um aeróstato adaptado capaz de prestar serviços de construção, operação, inspeção e manutenção e em linhas de transmissão, os quais se caracterizam basicamente por: I. transportar equipamentos, carga e pessoal em compartimentos distintos. II. realizar a construção ou a recomposição de linhas de transmissão por meio do transporte e posicionamento da estrutura da torre inteira ou por partes III. viabilizar a construção, a operação, a inspeção e a manutenção, de forma descendente, isto é, da plataforma aérea em uma posição elevada para as torres , cabos e ao solo. IV. Realizar o lançamento de cabos diretamente da plataforma aérea para as torres. V. Realizar a inspeção ou o monitoramento de linhas de transmissão através de verificação visual e/ou por meio de equipamentos de inspeção acoplados à plataforma aérea. VI. realizar serviços noturnos. VII. realizar serviços de manutenção em cadeias de isoladores, esferas sinalizadoras, espaçadores, amortecedores de vibração, balizores, em cabos e em torres. Pelo que foi exposto, a manutenção preventiva e corretiva possibilitada pela inversão da lógica atual de trabalho das equipes de linhas de transmissão e pela mudança da forma da logística de construção de novos empreendimentos em sistemas de transmissão elétrica utilizando uma plataforma aérea por meio de um dirigível proposto nesta patente, apresenta inúmeras vantagens aos modelos utilizados e/ou existentes, tais como: grande segurança operacional, confiabilidade e agilidade na aplicação; segurança em aplicação no sistema de transmissão energizado, garantia de baixo impacto ambiental nas expansões, grande performance na sua aplicação em virtude de sua concepção geral; elevado conforto ao mantenedor, comodidade e segurança aos usuários e ao sistema elétrico; redução de custos gerais, incluindo custo da manutenção da plataforma aérea que é totalmente acessível e possibilita uma ótima relação custo/benefício; prática e segura utilização por qualquer técnico habilitado e autorizado para manutenção; grande faixa de alcance; baixíssima e prática manutenção geral. Pode ser ainda aplicada a diversos tipos de serviços tais como em subestações e usinas geradoras de energia, garantindo o atendimento de segurança operacional de manutenção, atendendo plenamente as normas vigentes e as condições básicas necessárias a sua aplicação.[196] As can be seen, the present invention describes a method of using an adapted aerostat capable of providing construction, operation, inspection and maintenance services and on transmission lines, which are basically characterized by: I. transporting equipment, cargo and personnel in separate compartments. II. construct or recompose transmission lines by transporting and positioning the entire tower structure or parts III. enable downward construction, operation, inspection and maintenance of the aerial platform from an elevated position to the towers, cables and ground. IV. Perform cable launching directly from the aerial platform to the towers. V. Conduct inspection or monitoring of transmission lines by visual verification and / or by means of inspection equipment coupled to the aerial platform. SAW. perform night services. VII. perform maintenance services on insulator chains, signal balls, spacers, vibration dampers, beacons, cables and towers. Therefore, the preventive and corrective maintenance made possible by the inversion of the current work logic of the transmission line teams and by the change in the logistics of the construction of new projects in electric transmission systems using an aerial platform by means of an airship. proposed in this patent, presents numerous advantages to the used and / or existing models, such as: great operational safety, reliability and agility in the application; safety in application in the energized transmission system, guarantee of low environmental impact in the expansions, great performance in its application due to its general conception; high maintainer comfort, convenience and safety to users and the electrical system; overall cost savings, including cost of maintaining the fully accessible aerial platform for optimum cost effectiveness; practical and safe use by any qualified service technician; wide range; very low and practical general maintenance. It can also be applied to various types of services such as substations and power plants, ensuring the maintenance operational safety compliance, fully meeting the current standards and the basic conditions necessary for their application.

[197] Com o que já fora descrito é possível classificar o objeto desta patente como um processo totalmente versátil, eficiente, prático e seguro para executar a construção, operação, inspeção e manutenção do sistema de transmissão de energia elétrica, que independente das características gerais das diversas configurações e dos diversos tipos de estruturas existentes no setor elétrico, gerando grande facilidade para a execução dos serviços, permitindo um manuseio totalmente seguro com a rede energizada.[197] With what has already been described, it is possible to classify the object of this patent as a totally versatile, efficient, practical and safe process to perform the construction, operation, inspection and maintenance of the power transmission system, which regardless of the general characteristics. of the various configurations and the different types of structures existing in the electric sector, making it easy to perform the services, allowing a totally safe handling with the energized network.

[198] Portanto, deve ser entendido que o processo da presente invenção e suas partes componentes descritas acima fazem parte de uma modalidade preferida e de exemplos de situações que poderíam ocorrer, o real escopo do objeto da invenção encontra-se definido nas reivindicações.[198] Therefore, it should be understood that the process of the present invention and its component parts described above are part of a preferred embodiment and examples of situations which could occur, the actual scope of the object of the invention is defined in the claims.

[199] índice dos elementos das figuras 1 - Dirigível 2 - Envelope 3 - Estabilizadores 4 - Gôndola 5 - Hélices 6 - Instrumentos de inspeção 7 - Campo de inspeção visual e/ou instrumentalizada 8 - Torre de linha de transmissão 9 - Cabos de linha de transmissão (condutores, OPGW, para raio) 10 - Prolongamento dos cabos de linha de transmissão 11 - Sistema de Posicionamento de Cargas Suspensas 12 - Bobina de cabos guia 13 - Cabos guias de instalação de cabos de linha de transmissão 14 - Cesto 15 - Técnicos e equipamentos 16 - Jato de água 17 - Isoladores 18 - Mangueira 19 - Torre, parte de torre ou equipamento 20 - Lastro 21 - Cabo guia de transferência de cargas 22 - Comunicação via rádio entre técnicos em solo e dirigível 23 - Comunicação via rádio entre tripulação no dirigível e estação de controle e operação 24 - Estação de controle e operação em local remoto REIVINDICAÇÕES[199] Index of Elements in Figures 1 - Airship 2 - Envelope 3 - Stabilizers 4 - Gondola 5 - Propellers 6 - Inspection Instruments 7 - Visual and / or Instrumented Inspection Field 8 - Transmission Line Tower 9 - Line Cables (conductors, OPGW, lightning) 10 - Transmission line cable extension 11 - Suspended Load Positioning System 12 - Guide cable reel 13 - Transmission line cable installation guide 14 - Basket 15 - Technicians and equipment 16 - Water jet 17 - Insulators 18 - Hose 19 - Tower, tower part or equipment 20 - Ballast 21 - Load transfer guide cable 22 - Radio communication between ground and airship technicians 23 - Radio communication between crew in the airship and control and operation station 24 - Remote control and operation station

Claims (51)

1. Processo para construção de linhas de transmissão caracterizado por compreender as seguintes etapas: disponibilizar um aeróstato adaptado com uma plataforma aérea, o referido aeróstato para ser utilizado em voos de prestação de serviços em linhas de transmissão; sobrevoar com o aeróstato a área onde as linhas de transmissão serão construídas para realizar o levantamento de dados e analisar a viabilidade da construção de linhas de transmissão ali; após a determinação da área, transportar com o aeróstato uma equipe técnica encarregada de preparar a área a ser utilizada para a instalação das linhas de transmissão e de realizar a montagem das linhas de transmissão; e transportar, com o referido aeróstato, materiais e equipamentos necessários para a construção das linhas de transmissão.Process for the construction of transmission lines, comprising the following steps: providing an aerostat adapted with an aerial platform, said aerostat for use in transmission service lines; fly over with the aerostat the area where the transmission lines will be built to collect data and analyze the feasibility of building transmission lines there; After determining the area, transport with the aerostat a technical team responsible for preparing the area to be used for the installation of the transmission lines and for the assembly of the transmission lines. and to transport, with said airship, materials and equipment necessary for the construction of transmission lines. 2. Processo de acordo com a reivindicação 1, caracterizado por compreender ainda as seguintes etapas: recolher com o aeróstato a equipe e os materiais de preparação da área escolhida para instalação das linhas de transmissão; e realizar o lançamento de cabos guia com o aeróstato em torres de linhas de transmissão.Method according to Claim 1, characterized in that it further comprises the following steps: collecting with the aerostat the team and the preparation materials of the chosen area for installation of the transmission lines; and launch guidewires with the airship on transmission line towers. 3. Processo de acordo com a reivindicação 1, caracterizado pelo fato da etapa de disponibilização de um aeróstato adaptado para ser utilizado em voos de prestação de serviços em linhas de transmissão compreender mais especificamente a disponibilização de um dirigível adaptado.Method according to claim 1, characterized in that the step of providing an adapted aerostat for use on transmission line service flights comprises more specifically providing an adapted airship. 4. Processo de acordo com a reivindicação 1, caracterizado pelo fato da etapa de transporte da equipe técnica encarregada de preparar a área a ser utilizada para a instalação das linhas de transmissão compreender a descida da referida equipe até o solo dentro de um cesto por meio de um sistema de posicionamento de cargas suspensas.Method according to claim 1, characterized in that the transporting step of the technical team in charge of preparing the area to be used for the installation of the transmission lines comprises the lowering of said equipment to the ground in a basket by means of of a suspended load positioning system. 5. Processo de acordo com a reivindicação 1 ou 4, caracterizado pelo fato de não ocorrer transferência de massa na etapa de transporte da equipe.Process according to Claim 1 or 4, characterized in that no mass transfer occurs at the team transport stage. 6. Processo de acordo com a reivindicação 1, caracterizado pelo fato da etapa de transporte de materiais e equipamentos necessários à construção das linhas de transmissão compreender ainda a entrega de equipamentos para preparação do terreno.Process according to Claim 1, characterized in that the step of conveying materials and equipment necessary for the construction of the transmission lines further comprises the delivery of equipment for the preparation of the land. 7. Processo de acordo com a reivindicação 1 ou 6, caracterizado pelo fato da etapa da entrega de equipamentos como tratores, retroescavadeiras e equipamentos afins para preparação do terreno acontecer com ou sem a troca de carga.Process according to claim 1 or 6, characterized in that the stage of delivery of equipment such as tractors, backhoes and related equipment for land preparation takes place with or without load shifting. 8. Processo de acordo com a reivindicação 1, caracterizado pelo fato da etapa da entrega de equipamentos compreender o transporte e entrega de lastros para a área de montagem das torres de linhas de transmissão para permitir a troca de cargas.Process according to Claim 1, characterized in that the equipment delivery step comprises the transport and delivery of ballast to the transmission line tower assembly area to allow load shifting. 9. Processo de acordo com a reivindicação 1 ou 8, caracterizado pelo fato da etapa de entrega de equipamentos compreender o transporte de pelo menos uma torre de linha de transmissão ou parte dessa.Method according to Claim 1 or 8, characterized in that the equipment delivery step comprises the transport of at least one transmission line tower or part thereof. 10. Processo de acordo com a reivindicação 1, 8 ou 9, caracterizado pelo fato de compreender a descida de pelo menos uma torre de linha de transmissão ou parte dessa utilizando o sistema de posicionamento de cargas suspensas, com um cabo guia apoiado em arestas da torre.Method according to Claim 1, 8 or 9, characterized in that it comprises the lowering of at least one transmission line tower or part thereof using the suspended load positioning system, with a guide cable supported on edges of the tower. 11. Processo de acordo com a reivindicação 10, caracterizado pelo fato de compreender de uma equipe de solo para realizar a fixação do cabo guia a um lastro posicionado a uma distância segura da torre.Method according to claim 10, characterized in that it comprises a ground crew for fixing the guide cable to a ballast positioned at a safe distance from the tower. 12. Processo de acordo com a reivindicação 11, caracterizado pelo fato de compreender a possibilidade de desacoplar o dirigível por meio do cabo guia.Method according to Claim 11, characterized in that it comprises the possibility of uncoupling the airship by means of the guide cable. 13. Processo de acordo com a reivindicação 11 ou 12, caracterizado pelo fato de compreender o recolhimento do cabo guia pelo sistema de posicionamento de cargas suspensas.Method according to Claim 11 or 12, characterized in that it comprises the retraction of the guide cable by the suspended load positioning system. 14. Processo de acordo com a reivindicação 2 ou 11, caracterizado pelo fato de compreender a possibilidade da utilização de lastro para o recolhimento dos equipamentos do local de construção das linhas de transmissão.Process according to Claim 2 or 11, characterized in that it comprises the possibility of using ballast to collect equipment from the construction site of the transmission lines. 15. Processo de acordo com qualquer uma da reivindicação 1 a 14, caracterizado pelo fato de compreender a possibilidade de uso de lastros que sejam capazes de garantir o heaviness e lightness máximo do aeróstato adaptado.Process according to any one of claims 1 to 14, characterized in that it comprises the possibility of using ballasts which are capable of guaranteeing the maximum heaviness and lightness of the adapted aerostat. 16. Processo de acordo com a reivindicação 2, caracterizado pelo fato da etapa de recolher a equipe e os materiais de preparação da área escolhida para instalação das linhas de transmissão ser realizada, preferencialmente, sem a troca de carga.Process according to claim 2, characterized in that the step of collecting the crew and preparation materials from the area chosen for the transmission line installation is preferably carried out without load shifting. 17. Processo de acordo com a reivindicação 16, caracterizado pelo fato da etapa de recolher a equipe e os materiais de preparação da área escolhida para instalação das linhas de transmissão ser realizada, preferencialmente, com o aeróstato em voo pairado.Process according to Claim 16, characterized in that the step of collecting the crew and preparation materials from the area chosen for installation of the transmission lines is preferably performed with the airship in hover. 18. Processo de acordo com a reivindicação 16 ou 17, caracterizado pelo fato de a equipe e os materiais serem posicionados no cesto sem necessidade de fazer transferência de cargas.Process according to Claim 16 or 17, characterized in that the staff and materials are positioned in the basket without the need to transfer loads. 19. Processo de acordo com a reivindicação 18, caracterizado pelo fato de compreender o içamento do cesto e sua entrada em uma gôndola.Process according to claim 18, characterized in that it comprises lifting the basket and entering it into a gondola. 20. Processo de acordo com a reivindicação 2, caracterizado pelo fato da etapa de realizar o lançamento de cabos condutores compreender primeiramente o lançamento de cabos guia ao longo das torres utilizando o aeróstato.Method according to Claim 2, characterized in that the step of conducting cable routing comprises firstly laying guide cables along the towers using the aerostat. 21. Processo de acordo com a reivindicação 20, caracterizado pelo fato da etapa de realizar o lançamento de cabos guia ao longo das torres permitir o lançamento de cabos piloto de forma tradicional.Method according to Claim 20, characterized in that the step of laying guide ropes along the towers allows the laying of pilot cables in a traditional manner. 22. Processo de acordo com a reivindicação 20 ou 21, caracterizado pelo fato da etapa de realizar o lançamento de cabos piloto de forma tradicional permitir o lançamento de cabos condutores de forma tradicional.Method according to Claim 20 or 21, characterized in that the step of traditionally laying pilot cables permits the laying of traditionally conductive cables. 23. Processo de acordo com a reivindicação 21, caracterizado pelo fato da etapa de realizar o lançamento de cabos guia ao longo das torres compreender a etapa de estender os cabos no chão ao longo da linha; e erguer os mesmos para o alto das torres, ou estendê-los em cima das torres.Method according to claim 21, characterized in that the step of laying the guide ropes along the towers comprises the step of extending the cables on the floor along the line; and lift them up to the top of the towers, or extend them on top of the towers. 24. Processo de acordo com a reivindicação 22 ou 23, caracterizado pelo fato da etapa de erguer o cabo guia ser realizado por pessoas por meio de roldanas.Method according to Claim 22 or 23, characterized in that the step of lifting the guide rope is carried out by persons by means of pulleys. 25. Processo de acordo com a reivindicação 21, caracterizado pelo fato da etapa de realizar o lançamento de cabos guia ser feito por um aeróstato e compreender ainda o transporte dos equipamentos de lançamento.Method according to Claim 21, characterized in that the step of carrying out guide ropes is carried out by an aerostat and further comprises transporting the launching equipment. 26. Processo de acordo com a reivindicação 25, caracterizado pelo fato da etapa de realizar o lançamento de cabos guia ser feito por um aeróstato ao sobrevoar uma linha de transmissão e liberar progressivamente o cabo guia de uma bobina.Method according to Claim 25, characterized in that the step of carrying out guidewires is made by an aerostat when flying over a transmission line and progressively releasing the guidewire from a coil. 27. Processo de acordo com a reivindicação 26, caracterizado pelo fato de compreender o posicionamento da bobina por meio de um sistema de posicionamento de cargas suspensas.Method according to Claim 26, characterized in that it comprises positioning the coil by means of a suspended load positioning system. 28. Processo de acordo com a reivindicação 27, caracterizado pelo fato de ao término do lançamento de cabo guia de um tramo, o aeróstato passar por transição de voo com velocidade para voo pairado e a extremidade do cabo ser liberada da bobina e acoplada em um apoio pela equipe em solo.Method according to Claim 27, characterized in that at the end of the launching of the guide wire of a branch, the aerostat is transitioned from speed to hover flight and the end of the cable is released from the coil and coupled to a support by the team on the ground. 29. Processo de inspeção de linhas de transmissão caracterizado por compreender as seguintes etapas: sobrevoar o trecho da linha a ser inspecionado com um aeróstato adaptado com uma plataforma aérea; e realizar a inspeção durante o sobrevoo da etapa anterior;29. Transmission line inspection process comprising the following steps: overflying the section of line to be inspected with an airship adapted with an aerial platform; and perform the inspection during the overflight of the previous step; 30. Processo de acordo com a reivindicação 29, caracterizado pelo fato de compreender a etapa de aproximar o aeróstato das torres a serem inspecionadas.Method according to claim 29, characterized in that it comprises the step of bringing the aerostat closer to the towers to be inspected. 31. Processo de acordo com a reivindicação 30, caracterizado pelo fato de o aeróstato ao se aproximar das torres na altura correta em relação às mesmas e em uma faixa de velocidade adequada até 120 Km/h, inicia a missão de inspeção de fato.Process according to claim 30, characterized in that the aerostat when approaching the towers at the correct height in relation to them and in a suitable speed range up to 120 km / h, initiates the actual inspection mission. 32. Processo de acordo com qualquer uma das reivindicações 29 a 31, caracterizado pelo fato de compreender o sobrevoo das linhas com o aeróstato suficiente próximo, em distância entre 10 m e 100 m, de forma a permitir que equipamentos de inspeção detectem possíveis defeitos.Method according to any one of Claims 29 to 31, characterized in that it comprises the overflight of the lines with the sufficient nearby airship, at a distance between 10 m and 100 m, to enable inspection equipment to detect possible defects. 33. Processo de acordo com qualquer uma das reivindicações 29 a 32, caracterizado pelo fato de compreender a manutenção da altura do sobrevoo em relação ao topo das torres praticamente constante ao longo da missão de inspeção.Method according to any one of claims 29 to 32, characterized in that the maintenance of the overflight height relative to the top of the towers is substantially constant throughout the inspection mission. 34. Processo de acordo com qualquer uma das reivindicações 29 a 33, caracterizado pelo fato do sobrevoo ser realizado em velocidade em relação ao solo que permite que os equipamentos de medição sejam utilizados.Process according to any one of claims 29 to 33, characterized in that the overflight is performed at ground speed allowing the measuring equipment to be used. 35. Processo de acordo com qualquer uma das reivindicações 29 a 34, caracterizado pelo fato de ser realizado por um dirigível adaptado para uso em linhas de transmissão.A method according to any one of claims 29 to 34, characterized in that it is carried out by an airship adapted for use on transmission lines. 36. Processo de acordo com qualquer uma das reivindicações 29 a 35, caracterizado pelo fato da inspeção compreender a coleta de dados da situação da linha de transmissão por meio de inspeção visual por um técnico habilitado.A method according to any one of claims 29 to 35, characterized in that the inspection comprises collecting data from the transmission line situation by visual inspection by a qualified technician. 37. Processo de acordo com qualquer uma das reivindicações 29 a 35, caracterizado pelo fato da inspeção compreender a coleta de dados georreferenciados da situação da linha de transmissão por meio de inspeção instrumentalizada para verificações: de temperatura nas conexões de cabos por meio de termovisor, de efeito corona resultado de possíveis anomalias por meio do analisador de efeito corona, de escaneamento por laser para levantamento de altura e tipo de vegetação, de medição de altura cabo-solo “flecha”, de erosões ao longo da faixa de servidão, e de captura de imagens por câmera de vídeo de alta resolução.Process according to any one of claims 29 to 35, characterized in that the inspection comprises the collection of georeferenced data from the transmission line situation by means of instrumented inspection for temperature checks on cable connections by means of a thermal imager, corona effect resulting from possible anomalies through the corona effect analyzer, laser scanning for height and vegetation type survey, cable-to-ground height measurement, erosion along the easement strip, and Capture images by high resolution camcorder. 38. Processo de acordo com a reivindicação 36 ou 37 caracterizado pelo fato de as etapas de inspeção definidas na reivindicação 36 ou 37 ocorrerem de forma simultânea ou individualizada.Process according to claim 36 or 37, characterized in that the inspection steps defined in claim 36 or 37 occur simultaneously or individually. 39. Processo de acordo com qualquer uma das reivindicações 29 a 38, caracterizado pelo fato das inspeções de múltiplas funções poderem ser realizadas com apenas um sobrevoo pelo uso de vários equipamentos acoplados ao aeróstato adaptado.A method according to any one of claims 29 to 38, characterized in that multipurpose inspections can be performed with only one overflight by the use of various equipment coupled to the adapted aerostat. 40. Processo de manutenção de linhas de transmissão caracterizado por compreender as seguintes etapas: sobrevoar o trecho da linha a ser feita a manutenção com um aeróstato adaptado; e realizar a manutenção no local escolhido da linha de transmissão.40. Transmission line maintenance process comprising the following steps: flying over the section of line to be maintained with an adapted aerostat; and perform maintenance at the chosen location of the transmission line. 41. Processo de acordo com a reivindicação 40, caracterizado pelo fato de compreender a etapa de aproximar o aeróstato das torres que necessitam de manutenção.Process according to Claim 40, characterized in that it comprises the step of bringing the aerostat closer to the towers in need of maintenance. 42. Processo de acordo com a reivindicação 40, caracterizado pelo fato do aeróstato permanecer em voo pairado para a realização da manutenção.Process according to Claim 40, characterized in that the aerostat remains in a hover flight for maintenance purposes. 43. Processo de acordo com qualquer uma das reivindicações 40 a 42, caracterizado pelo fato de compreender a etapa de posicionar técnicos especializados suficientemente perto dos componentes a sofrer a manutenção.Process according to any one of claims 40 to 42, characterized in that it comprises the step of positioning skilled technicians sufficiently close to the components to be serviced. 44. Processo de acordo com a reivindicação 43, caracterizado pelo fato de compreender a etapa de descida dos técnicos do aeróstato para a torre por meio de um cesto após o posicionamento.Process according to Claim 43, characterized in that it comprises the step of descending the aerostat technicians to the tower by means of a basket after positioning. 45. Processo de acordo com a reivindicação 40, caracterizado pelo fato do procedimento de manutenção poder ser realizado de pelo menos duas formas: os técnicos descerem do cesto para a torre com suas ferramentas, ou realizarem a manutenção de dentro do cesto.Process according to Claim 40, characterized in that the maintenance procedure can be carried out in at least two ways: the technicians descend from the basket to the tower with their tools, or perform maintenance from within the basket. 46. Processo de acordo com a reivindicação 45, caracterizado pelo fato do procedimento de manutenção adotado depender do tempo necessário para realizar os trabalhos e da acessibilidade do cesto do local na torre a ser reparado.Process according to Claim 45, characterized in that the maintenance procedure adopted depends on the time required to carry out the work and the accessibility of the basket on the tower to be repaired. 47. Processo de acordo com qualquer uma das reivindicações 43 a 46, caracterizado pelo fato do aeróstato operar em heaviness, e a massa total descarregada ser menor do que o valor do heaviness do instante para os técnicos e suas ferramentas descerem do cesto sem precisar realizar transferência de massa.Process according to any one of claims 43 to 46, characterized in that the aerostat operates at heaviness, and the total mass discharged is less than the instant heaviness value for technicians and their tools to descend from the basket without having to perform mass transference. 48. Processo de acordo com qualquer uma das reivindicações 40 a 47 caracterizado pelo fato da manutenção compreender a etapa de direcionar jato de água nos componentes de linha de transmissão para efetuar a limpeza.Process according to any one of Claims 40 to 47, characterized in that the maintenance comprises the step of directing water jet on the transmission line components to perform the cleaning. 49. Processo de acordo com qualquer uma das reivindicações 40 a 48, caracterizado pelo fato de ser realizado por um dirigível adaptado para uso em linhas de transmissão.A method according to any one of claims 40 to 48, characterized in that it is carried out by an airship adapted for use on transmission lines. 50. Processo de operação de linhas de transmissão caracterizado pelo fato de compreender as etapas de: disponibilizar um aeróstato adaptado para ser utilizado em voos de prestação de serviços em linhas de transmissão; e posicionar o aeróstato adaptado em uma posição que permita realizar a comunicação entre as equipes de inspeção e manutenção com as subestações e/ou centros de operação regional.50. Transmission line operation process comprising the steps of: providing an aerostat adapted for use on transmission line service flights; and position the adapted aerostat in a position that enables communication between inspection and maintenance teams with substations and / or regional operation centers. 51. Processo de acordo com a reivindicação 50, caracterizado pelo fato de ser realizado por um dirigível adaptado para uso em linhas de transmissão.Process according to Claim 50, characterized in that it is carried out by an airship adapted for use on transmission lines.
BR102015019612A 2015-08-14 2015-08-14 process of using an aerostat on transmission lines BR102015019612A2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
BR102015019612A BR102015019612A2 (en) 2015-08-14 2015-08-14 process of using an aerostat on transmission lines
PCT/BR2016/000012 WO2017027939A1 (en) 2015-08-14 2016-02-15 Process of using an aerostat in transmission lines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
BR102015019612A BR102015019612A2 (en) 2015-08-14 2015-08-14 process of using an aerostat on transmission lines

Publications (1)

Publication Number Publication Date
BR102015019612A2 true BR102015019612A2 (en) 2017-02-21

Family

ID=58043686

Family Applications (1)

Application Number Title Priority Date Filing Date
BR102015019612A BR102015019612A2 (en) 2015-08-14 2015-08-14 process of using an aerostat on transmission lines

Country Status (2)

Country Link
BR (1) BR102015019612A2 (en)
WO (1) WO2017027939A1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10521960B2 (en) * 2017-05-03 2019-12-31 General Electric Company System and method for generating three-dimensional robotic inspection plan
JP6428973B1 (en) * 2018-02-22 2018-11-28 中国電力株式会社 Transmission and distribution equipment inspection system
CN112543537B (en) * 2019-09-21 2022-10-21 黄涛 Suspension following intelligent lighting system
CN110806711B (en) * 2019-11-27 2022-06-03 福建航空装备维修中心 Integrated management system and method for cleaning, airing and storing parachuting equipment of pilots on sea
KR102398978B1 (en) * 2021-04-29 2022-05-18 주식회사 제노코 FOREST FIRE MONITORING AND EXTINGUISHING SYSTEM USING UAVs AND AN AIRSHIP
CN113744673B (en) * 2021-08-17 2023-07-18 佛山市鹰火微峰科技有限公司 Ground-air linkage projection system and method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6325330B1 (en) * 1998-08-18 2001-12-04 Lockheed Martin Corporation Power generation, transmission, and distribution system for an aerostat using a lightweight tether
US7510142B2 (en) * 2006-02-24 2009-03-31 Stealth Robotics Aerial robot

Also Published As

Publication number Publication date
WO2017027939A1 (en) 2017-02-23

Similar Documents

Publication Publication Date Title
BR102015019612A2 (en) process of using an aerostat on transmission lines
CN101789569B (en) Construction method of unfolding preliminary leading rope with remotely pilotless helicopter
US11608169B2 (en) Unmanned aerial system and method for contact inspection and otherwise performing work on power line components
US11225950B2 (en) Multirotor wind turbine
CN108163179B (en) Near space aerostat issuing method and apparatus
JP6344879B1 (en) Suspension scaffold construction method and suspension scaffold in bridge structure
CN110820555B (en) Bridge maintenance vehicle and method for avoiding bridge pier by maintenance platform
RU2715682C1 (en) Robot system and method of its operation at high-rise facilities related to power engineering and radio communication
US11952119B2 (en) Payload support frame for unmanned aerial system
Júnior et al. A novel environmental friendly approach to enhance the maintenance and construction of high voltage transmission lines in the Amazon region
CN215071347U (en) Unmanned aerial vehicle electric wire netting maintenance auxiliary operation device
Ishikura et al. Stonecutters Bridge, Hong Kong: main span erection
Wang et al. Live Line Repair of Ground Wire for UHV/EHV Transmission Line Based on Helicopter Winch Hanging Chair Method
CN116365418B (en) Construction method of high-voltage overhead transmission line
Imai et al. Improvement of inspection and maintenance gantries in the Honshu Shikoku Bridges
KR100523762B1 (en) Construction wire connection system
CN107804481A (en) Dirigible assist system
de Parny Helicopter airborne services live line work
Liu et al. Study on Construction Technology Standardization of Primary Guide Rope Laying by Multi-rotor Aircraft in Stringing Construction of Transmission Line
Green et al. Transmission Line Construction and Maintenance
TR202004674A2 (en) AN INSPECTION TEST ANALYSIS SYSTEM
Oltean et al. Live Rehabilitation of 400kV OHL Mintia-Sibiu
Christoforato et al. A new airship ground handling system that works
Pezzotti Bridge Inspection without Traffic Disruptions—Installation of a Motorized Bridge Inspection Traveler Platform beneath the Burlington-Bristol Bridge
Kaji et al. An introduction to Stonecutters bridge, Hong Kong: Erection of the steel segments, hydraulic buffers and lateral bearings

Legal Events

Date Code Title Description
B03A Publication of a patent application or of a certificate of addition of invention [chapter 3.1 patent gazette]
B06F Objections, documents and/or translations needed after an examination request according [chapter 6.6 patent gazette]
B06U Preliminary requirement: requests with searches performed by other patent offices: procedure suspended [chapter 6.21 patent gazette]
B07A Application suspended after technical examination (opinion) [chapter 7.1 patent gazette]
B09B Patent application refused [chapter 9.2 patent gazette]
B12B Appeal against refusal [chapter 12.2 patent gazette]