Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2021106236A
Inventor
Deepak Kumar Gupta
Sandeep Raina
Pushpendra Kumar SHARMA
Vishaldeep SINGH
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lovely Professional University
Original Assignee
Lovely Professional University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lovely Professional University filed Critical Lovely Professional University
Priority to AU2021106236A priority Critical patent/AU2021106236A4/en
Application granted granted Critical
Publication of AU2021106236A4 publication Critical patent/AU2021106236A4/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings

Abstract

FOOT OVER BRIDGE The present invention relates to a foot over bridge for working staff for proper laying of RCC works which consists of reinforcement bars (1), mild Steel frame (2), a welded metal sheet (3) covered with antiskid mat, and leg/ foot (4). In the present disclosure, the mild steel frame (2) is attached with six legs or foot (4) each with rectangular cross-section and particular length. Here, the M.S frame (2) transfers the labour load directly to the form work or the shuttering without damaging reinforcement or any PVC pipe laid for future underground electrification. 6 Applicant: Lovely Professional University Sheet No: 1/2 LLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLL LLLLLLLLLL L LLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL -LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLI LLLLLLLLL LLLLLLL Figure 1 7

Description

Applicant: Lovely Professional University Sheet No: 1/2
LLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLL LLLLLLLLLL L LLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL -LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLLL LLLLLLLLLLLLLLLLLLI LLLLLLLLL LLLLLLL
Figure 1
TECHNICAL FIELD
[01] The present invention relates to the field of Reinforced Cement Concrete (RCC) related work, more particularly, related to a foot over bridge for proper laying of RCC works with great comfort for labour without any defect.
BACKGROUND
[02] In case of Reinforced Cement Concrete (RCC) works, as the shuttering is removed reinforcement bars appear on the surface which usually get deteriorated by rusting after coming in contact with water, humidity, whitewashing, and painting. This problem extends even up to covered bars later. Also, if slabs are made of RCC, the PVC pipes are also damaged by the working and walking labour over the reinforcement bars during the RCC laying activity resulting in issues related to underground electrification of building.
[03] Additionally, the walking load impacts the mild steel bars resulting in depression causing the bars to stick with shuttering and on removal of shuttering, these bars are exposed to the air. Furthermore, if plaster covering is provided over these bars, due to differential expansions at the junction of two materials, cracks develop and plaster falls down. So plaster is also not the solution of this problem.
[04] There are many accidents of falling labour and other staff getting entrapped in reinforcement bars. The shoes of working are also damaged by these bars. So, the working and walking labor during RCC work is the root cause of the problem which can only be solved during RCC laying activity and not at all by plastering which is the traditional solution. Hence, there is a need to solve this issue.
[051 CN104805866B relates to a prefabricated pipe gallery and construction method which include prefabricated panel, one group of outer surbase is provided with prefabricated panel, outer surbase and precast facade connection wherein the invention is integrated for improving city integrated piping lane. However, this invention has a complex design and is quite different from the disclosed invention.
[06] US9458576B2 discloses a dual direction pre-stressed pre-tensioned precast concrete slabs and process for it having a casting bed which has the capability of permitting pre-tensioning of a concrete cast to be carried out within the casting bed in both the longitudinal direction and in the transverse direction. However, this invention does not address the stated problem and is costly too.
[071 JP6027983B2 provides a precast wall panel construction method ofhigh rise building using this panel.
[08] W02007039887A2 discloses a method of constructing a roof or floor slab for domestic, commercial, or industrial buildings. The method includes erecting a support grid of a plurality of elongate, laterally spaced, parallel, longitudinally extending, pre-cast reinforced concrete beams, and a plurality of orthogonally disposed elongate pre-cast reinforced concrete cross ribs interconnecting adjacent pairs of beams.
[09] The present invention addresses the above shortcomings of the prior art. However, the present invention is entirely different from the prior art in terms of novelty and technological advancement.
SUMMARY
[0010] The present invention discloses a foot over bridge for proper laying of RCC works with great comfort for labour without any defect. The present invention comprises of a mild steel frame (2) attached with six legs or foot (4) each with mild steel hollow rectangular cross-section and a particular length.
the length and width of the frame (2) can be modified and also a number of such bridges can be used as per requirement.
[0011] In one implementation, the present invention works on bridge theory that bypass the labour load to the form work/ shuttering without any damage to the RCC bars and PVC pipes laid for underground electrification.
[0012] In one of the implementations, the present invention is a cost effective approach to bypass labour load without damaging MS bars of RCC and PVC pipes for underground electrification.
BRIEF DESCRIPTION OF THE DRAWINGS
[00131 The foregoing detailed description of embodiments is betterunderstood when read in conjunction with the attached drawing.
[0014] Figure 1 illustrates the schematic illustration of the presentinvention.
[0015] Figure 2 illustrates the block diagram of the process taking place inthe present invention
[00161 Both figures depict an embodiment of the present disclosure for the purpose of illustration and better understanding only.
DETAILED DESCRIPTION
[0017] Some embodiments of this disclosure, illustrating all its features, will now bediscussed in detail.
[0018] The present disclosure provides a solution for proper laying of RCC works with great comfort to the working staff without any defect. The present invention consists of reinforcement bars (1), mild Steel frame (2), a welded metal sheet (3) covered with antiskid mat, and leg/ foot (4). Thepresent invention works on bridge theory that bypass the labour load to the form work/ shuttering without any damage to the RCC bars and PVC pipes laid for underground electrification. The present invention is a cheap approachto bypass labour load without damaging MS bars of RCC and PVC pipes for underground electrification.
[0019] In one embodiment, a mild steel frame (2) of1" (inch) angle section, attached with six legs or foot (4) each with mild steel 1"* 1" hollow rectangular cross-section and 6" (inch) in length.
[0020] In another embodiment, the metal sheet is covered with antiskid mat (3) of rubber or any other material is welded over the M.S frame (2).
[0021] In an exemplary embodiment, the length and width of the frame (2) can be modified and also a number of such bridges can be used as perrequirement.
[00221 In another exemplary embodiment, the M.S frame (2) is quite strong to transfer the labour load directly to the form work or the shuttering without damaging reinforcement or any PVC pipe laid for future underground electrification.
[0023] In one of the embodiments, the legs or foot (4) is placed between the MS bars of reinforcement (1).
[0024] In yet another embodiment, the metal sheet (3) welded to the frame is covered by some antiskid material so as to avoid any skidding of working labour or staff
[0025] In another embodiment, the present invention not only provides great comfort and ease to the working staff but also prevents injuries while performing RCC laying work.
[0026] Referring to figure 1 indicates the schematic illustration of the present invention consisting of reinforcement bars (1), mild Steel frame (2), a welded metal sheet (3) covered with antiskid mat, and leg/ foot (4).
[00271 Referring to figure 2 indicates the block diagram explaining thestep by step process taking place in the present invention.

Claims (5)

We claim:
1. A system of foot over bridge for labour for proper laying of RCC workswhich consists of a) reinforcement bars (1); b) a mild Steel frame (2); c) a welded metal sheet (3) covered with antiskid mat; and d) leg/ foot (4) which is placed between the MS bars of reinforcement (1).
2. The system as claimed in claim 1 wherein the mild steel frame (2) is attached with six legs or foot (4) each with rectangular cross-section and particular length.
3. The system as claimed in claim 1 wherein the length and width of the frame (2) can be modified and also a number of such bridges can be used as per requirement.
4. The system as claimed in claim 1 wherein the metal sheet (3) is welded over the M.S frame (2) and covered with antiskid mat of rubber or any other material so as to avoid any skidding of working labour or staff
5. The system as claimed in claim 1 wherein the M.S frame (2) transfers the labour load directly to the form work or the shuttering without damaging reinforcement or any PVC pipe laid for future underground electrification.
Applicant: Lovely Professional University Sheet No: 1/2 2021106236
Figure 1
Applicant: Lovely Professional University Sheet No: 2/2 2021106236
Figure 2
AU2021106236A 2021-08-20 2021-08-20 Foot over bridge Ceased AU2021106236A4 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2021106236A AU2021106236A4 (en) 2021-08-20 2021-08-20 Foot over bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AU2021106236A AU2021106236A4 (en) 2021-08-20 2021-08-20 Foot over bridge

Publications (1)

Publication Number Publication Date
AU2021106236A4 true AU2021106236A4 (en) 2021-12-16

Family

ID=78887543

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2021106236A Ceased AU2021106236A4 (en) 2021-08-20 2021-08-20 Foot over bridge

Country Status (1)

Country Link
AU (1) AU2021106236A4 (en)

Similar Documents

Publication Publication Date Title
CN111734126B (en) Single-curved-surface fair-faced concrete textured roof template system and construction method thereof
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
CN103806647A (en) Assembly and disassembly process for large-span concrete bidirectional dense rib beam formwork case
CN107396836A (en) A kind of full assembled pig house
CN105780992B (en) A kind of orthogonal spatial Rc Open-web Sandwich Plates floor construction engineering method
CN211037802U (en) All-steel support reinforced template system
CN107401279A (en) Disposable one-piece casting staircase wall ladder combined steel formwork installation construction method
CN110607905A (en) All-steel support reinforced formwork system and construction method
AU2021106236A4 (en) Foot over bridge
RU165803U1 (en) Prefabricated Monolithic Overlapping of the Frame Building
CN212026574U (en) Adopt building floor slab rebar structure of encorbelmenting of steel bar truss template
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
EP0790364A1 (en) Reinforced or prestressed semi-precast concrete structure for building
CA1151892A (en) Prefabricated load bearing structure
WO2019102438A1 (en) Permanent formwork and support system
CN105926820B (en) Construction method for precast beam steel support plate resistance mesh combined floor
CN212866855U (en) Arc wood grain clear water concrete roof template system
US9464437B1 (en) Precast I-beam concrete panels
CN109707152B (en) Aluminum alloy formwork system and construction method thereof
KR101056395B1 (en) The water-storage tank of assembly type and method for constructing thereof
Philip et al. Comparative study of conventional slab with slab constructed using AAC block and steel grid
CN109667222A (en) Dripping eaves and its construction method
CN114575491B (en) Composite construction method for special-shaped complex secondary structure
Akramovna et al. DESIGN CHANGE OF A DETAIL AND ADDITION OF A USEFUL ELEMENT
CN217353538U (en) Disposable integral molding construction structure for sunken well and reversed ridge

Legal Events

Date Code Title Description
FGI Letters patent sealed or granted (innovation patent)
MK22 Patent ceased section 143a(d), or expired - non payment of renewal fee or expiry