CN110607905A - An all-steel support reinforcement formwork system and construction method - Google Patents
An all-steel support reinforcement formwork system and construction method Download PDFInfo
- Publication number
- CN110607905A CN110607905A CN201910973330.1A CN201910973330A CN110607905A CN 110607905 A CN110607905 A CN 110607905A CN 201910973330 A CN201910973330 A CN 201910973330A CN 110607905 A CN110607905 A CN 110607905A
- Authority
- CN
- China
- Prior art keywords
- wall
- formwork
- column
- slab
- flute
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009415 formwork Methods 0.000 title claims abstract description 208
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 52
- 239000010959 steel Substances 0.000 title claims abstract description 52
- 230000002787 reinforcement Effects 0.000 title claims abstract description 48
- 238000010276 construction Methods 0.000 title claims description 18
- 238000009434 installation Methods 0.000 claims description 27
- 210000001503 joint Anatomy 0.000 claims description 20
- 239000010410 layer Substances 0.000 claims description 18
- 238000011900 installation process Methods 0.000 claims description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 7
- 238000013461 design Methods 0.000 claims description 5
- 239000011241 protective layer Substances 0.000 claims description 5
- 239000003795 chemical substances by application Substances 0.000 claims description 4
- 230000000149 penetrating effect Effects 0.000 claims description 3
- 238000012360 testing method Methods 0.000 claims description 2
- 239000002023 wood Substances 0.000 description 9
- 238000000034 method Methods 0.000 description 7
- 230000008569 process Effects 0.000 description 5
- 230000009467 reduction Effects 0.000 description 4
- 230000007306 turnover Effects 0.000 description 4
- 239000002344 surface layer Substances 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000010408 sweeping Methods 0.000 description 2
- 241000264877 Hippospongia communis Species 0.000 description 1
- 244000007853 Sarothamnus scoparius Species 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000003490 calendering Methods 0.000 description 1
- 239000011083 cement mortar Substances 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000032798 delamination Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 201000001371 inclusion conjunctivitis Diseases 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 239000013643 reference control Substances 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000005204 segregation Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000004381 surface treatment Methods 0.000 description 1
- 206010044325 trachoma Diseases 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/02—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/08—Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/02—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/04—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/06—Tying means; Spacers ; Devices for extracting or inserting wall ties
- E04G17/065—Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
- E04G17/0651—One-piece elements
- E04G17/0652—One-piece elements fully recoverable
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明的一种全钢支撑加固模板体系,包括柱模板支撑结构、剪力墙模板支撑结构和梁板模板支撑结构,其中:柱模板支撑结构包括四面柱模板、柱次楞和柱主楞,相对的柱模板之间设有柱对拉螺杆,柱对拉螺杆的两端分别设置在柱体相对两侧的柱主楞上;剪力墙模板支撑结构包括剪力墙模板、墙次楞和墙主楞,相对的剪力墙模板之间设有墙对拉螺杆,墙对拉螺杆的两端分别连接在墙体相对两侧的墙主楞上;梁板模板支撑结构包括梁板模板,梁板模板位于混凝土楼板的下方,梁板模板的下方设有梁板次楞,梁板次楞的下方设有梁板主楞,梁板主楞下方设有梁板支撑架。该体系减少了木制龙骨的使用量,工艺可靠、操作方便,降低了工程成本。
An all-steel support reinforcement formwork system of the present invention includes a column formwork support structure, a shear wall formwork support structure and a beam slab formwork support structure, wherein: the column formwork support structure includes a four-sided column formwork, a column secondary flute and a column main flute, The opposite column formworks are provided with column opposite tension screws, and the two ends of the column opposite tension screws are respectively arranged on the column main flutes on the opposite sides of the column body; the shear wall formwork support structure includes shear wall formwork, wall secondary flute and For the main wall flute, there are wall-to-wall tension screws between the opposite shear wall formwork, and the two ends of the wall tension screws are respectively connected to the wall main flute on the opposite sides of the wall; the support structure of the beam-slab formwork includes the beam-slab formwork, The beam slab formwork is located below the concrete floor slab, the beam slab secondary flute is arranged under the beam slab formwork, the beam slab main flute is arranged below the beam slab secondary flute, and the beam slab supporting frame is arranged below the beam slab main flute. The system reduces the use of wooden keels, has reliable technology, convenient operation, and reduces engineering costs.
Description
技术领域technical field
本发明涉及一种全钢支撑加固模板体系,属于房建施工技术领域。The invention relates to an all-steel support and reinforcement formwork system, which belongs to the technical field of house construction.
背景技术Background technique
传统的建筑施工单位多采用钢管木方加固体系来对模板进行加固,钢管木方加固体系加固较为困难,普遍存在跑模、涨模、漏浆等现象,而混凝土拆模后,又常常会出现麻面、烂根、砂带等施工难题。此外,施工中需要使用大量的木方,由于木方的保持性较差,在经过一定时间的使用之后,强度不能达到支撑模板的要求,不能重复使用,造成了浪费。此外,钢管木方体系不能够应施工环境的要求进行长短伸缩,也会浪费大量的木材。不符合目前我国在建筑市场大力推行的绿色施工和节能减排的目标。Traditional building construction units often use steel pipe and wood square reinforcement system to strengthen the formwork. The steel pipe and wood square reinforcement system is more difficult to reinforce. There are common phenomena such as mold running, mold expansion, and grout leakage. After the concrete formwork is removed, it often occurs. Pockmarked surface, rotten root, abrasive belt and other construction problems. In addition, a large number of wooden squares are needed in the construction. Due to the poor retention of the wooden squares, after a certain period of use, the strength cannot meet the requirements of the supporting formwork and cannot be reused, resulting in waste. In addition, the steel pipe and wood square system cannot be stretched or expanded according to the requirements of the construction environment, and a large amount of wood will be wasted. It does not meet the goals of green construction and energy saving and emission reduction that my country is vigorously promoting in the construction market.
用于替代钢管木方体系的全钢支撑由于拼装快捷、周转率高、以钢代木现浇结构成型质量好等优点得到了逐步的应用。发明人在工程项目施工中,对传统钢管木方加固体系进行了改进,采用全钢支撑体系,通过在这两个工程的施工实践,总结后形成本发明。The all-steel support used to replace the steel pipe wood square system has been gradually applied due to the advantages of quick assembly, high turnover rate, and good quality of steel instead of wood cast-in-place structures. In the construction of engineering projects, the inventor improved the traditional steel tube wood square reinforcement system, adopted the all-steel support system, and formed the present invention after summarizing the construction practice in these two projects.
发明内容Contents of the invention
为克服现有技术的不足,本发明提出一种全钢支撑加固模板体系,减少了木制龙骨的使用量,能够节约资源消耗,绿色施工,增加了周转率,达到节能减排的目的,并且还能够提高主体结构的质量,工艺可靠、操作方便,降低了工程成本。In order to overcome the deficiencies of the prior art, the present invention proposes a formwork system with all-steel support and reinforcement, which reduces the amount of wooden keels used, can save resource consumption, green construction, increases the turnover rate, and achieves the purpose of energy saving and emission reduction, and The quality of the main structure can also be improved, the process is reliable, the operation is convenient, and the engineering cost is reduced.
为实现上述目的,本发明的一种全钢支撑加固模板体系,包括柱模板支撑结构、剪力墙模板支撑结构和梁板模板支撑结构,其中:In order to achieve the above object, a kind of all-steel support reinforced formwork system of the present invention includes column formwork support structure, shear wall formwork support structure and beam slab formwork support structure, wherein:
柱模板支撑结构包括四面柱模板,四面柱模板围设形成截面呈矩形的柱体成型空间,柱模板背离柱体的一面设有沿竖直方向延伸的柱次楞,柱次楞外设有沿水平方向延伸的柱主楞,相对的柱模板之间还设有贯穿的柱对拉螺杆,柱对拉螺杆的两端分别设置在柱体相对两侧的柱主楞上;The support structure of the column formwork includes a four-sided column formwork, which is surrounded by a rectangular column forming space with a cross-section. For the column main flute extending in the horizontal direction, there is also a penetrating column tension screw between the opposite column formwork, and the two ends of the column tension screw are respectively arranged on the column main flute on the opposite sides of the column body;
剪力墙模板支撑结构包括四面剪力墙模板,四面剪力墙模板围设形成截面呈矩形的剪力墙成型空间,剪力墙模板上设有沿竖直方向延伸的墙次楞,墙次楞外设有沿水平方向延伸的墙主楞,相对的剪力墙模板之间还设有贯穿的墙对拉螺杆,墙对拉螺杆的两端分别连接在墙体相对两侧的墙主楞上;The support structure of the shear wall formwork includes a four-sided shear wall formwork. The four-side shear wall formwork encloses a shear wall forming space with a rectangular cross-section. There is a wall main flute extending in the horizontal direction outside the flute, and there are also wall-to-wall tension screws penetrating between the opposite shear wall formwork. superior;
梁板模板支撑结构包括梁板模板,梁板模板位于混凝土楼板的下方,梁板模板的下方设有梁板次楞,梁板次楞的下方设有梁板主楞,梁板主楞下方设有梁板支撑架。The supporting structure of the beam slab formwork includes the beam slab formwork. The beam slab formwork is located below the concrete floor slab. There are beam support frames.
进一步地,剪力墙模板包括互相连接的若干墙模板片,相邻墙模板片之间的对缝上设有次背楞,次背楞的厚度与墙次楞相同。Further, the shear wall formwork includes several wall formwork sheets connected to each other, and the joints between adjacent wall formwork sheets are provided with secondary back flute, and the thickness of the secondary back flute is the same as that of the wall secondary flute.
进一步地,剪力墙模板支撑结构的外墙部分在墙主楞与另一墙主楞固定时采用阳角对接,阳角上两个墙主楞错搭,两个墙主楞的连接点上设有用于固定的钩子带母,剪力墙模板支撑结构的内墙部分在墙主楞与另一墙主楞固定时采用阴角对接,阴角的拼缝处采用压脚木方压脚,压脚木方的厚度与墙次楞厚度相同。Furthermore, when the outer wall part of the shear wall formwork support structure is fixed with the main flute of the other wall, the external corner is used to butt the two main flutes of the wall. There are hooks for fixing. The inner wall part of the shear wall formwork support structure adopts the inner corner butt joint when the main wall is fixed with the other wall main flute. The thickness of the wooden side of the presser foot is the same as the thickness of the second flute of the wall.
进一步地,梁板支撑架包括有沿竖直方向延伸的梁板支撑杆,梁板支撑杆支撑在梁板主楞的下方,各梁板支撑杆之间连接有水平杆,水平杆在水平方向上交叉设置,梁板支撑杆上设有剪刀撑斜杆,剪刀撑斜杆的两端分别连接在梁板支撑杆和水平杆上,剪刀撑斜杆的两端分别设有用于连接的旋转扣件。Further, the beam-slab support frame includes beam-slab support rods extending vertically, the beam-slab support rods are supported under the beam-slab main corrugation, horizontal rods are connected between each beam-slab support rods, and the horizontal rods are connected in the horizontal direction. The upper cross setting, the beam-slab support rod is equipped with a scissors brace rod, the two ends of the scissors brace rod are respectively connected to the beam-slab support rod and the horizontal rod, and the two ends of the scissors brace rod are respectively provided with rotating buckles for connection pieces.
进一步地,柱次楞、墙次楞和梁板次楞均采用方钢管,柱主楞、墙主楞和梁板主楞均采用成对的型钢龙骨,柱主楞、墙主楞和梁板主楞各自之间的对接均采用对接用接头,对接用接头上设有四根用于连接固定的插销。Furthermore, square steel pipes are used for the secondary corrugation of columns, secondary corrugations of walls, and secondary corrugations of beams and slabs; The butt joints between the main flutes are all joints, and the joints are provided with four bolts for connection and fixation.
进一步地,柱对拉螺杆和墙对拉螺杆上均套设有PVC管。Further, PVC pipes are sleeved on both the column-to-column and wall-to-column screws.
进一步地,柱主楞和柱对拉螺杆之间、墙主楞和墙对拉螺杆之间均垫设有十字垫片。Further, cross gaskets are arranged between the main flute of the column and the tension screw of the column, and between the main flute of the wall and the tension screw of the wall.
本发明还提出一种一种全钢支撑加固模板体系的施工方法,包括如下步骤:The present invention also proposes a construction method for an all-steel support reinforcement formwork system, comprising the following steps:
S1:墙柱钢筋安装:首先检查地面平整度,板面最高处低于设计标高,若高出涉及标高,需要进行打凿处理,安装墙柱钢筋,控制钢筋保护层厚度,在墙对拉螺杆和柱对拉螺杆的位置安装PVC管并控制好垂直度;S1: Installation of wall column reinforcement: first check the flatness of the ground, the highest part of the board surface is lower than the design elevation, if it is higher than the relevant elevation, it needs to be chiseled, install the wall column reinforcement, control the thickness of the reinforcement protective layer, and pull the screw on the wall Install the PVC pipe at the position of the pull screw with the column and control the verticality;
S2:柱模板及剪力墙模板安装:根据图纸安装柱模板和剪力墙模板,先竖起剪力墙模板,然后在剪力墙模板外侧固定墙次楞,在墙次楞的外侧设置墙主楞,然后在PVC管中穿过墙对拉螺杆并将墙对拉螺杆的两端连接在两侧的墙主楞上,在墙对拉螺杆位于墙主楞的外侧的端部扣上十字垫片,柱模板的安装过程与剪力墙模板的安装过程相同;S2: Installation of column formwork and shear wall formwork: Install column formwork and shear wall formwork according to the drawings, first erect the shear wall formwork, then fix the wall secondary wall outside the shear wall formwork, and set the wall outside the wall secondary wall Main flute, then pass through the wall-to-wall screw in the PVC pipe and connect the two ends of the wall-to-wall screw to the wall main flute on both sides, and buckle the cross at the end of the wall to-pull screw located outside the wall main flute The installation process of gasket and column formwork is the same as that of shear wall formwork;
S3:柱模板及剪力墙模板校调及加固:柱模板和剪力墙模板安装完毕后,在其两侧安装临时支撑固定,并使用线锤自由落下检测垂直度;S3: Adjustment and reinforcement of column formwork and shear wall formwork: After the column formwork and shear wall formwork are installed, install temporary supports on both sides to fix them, and use a wire hammer to freely fall to test the verticality;
S4:梁板模板安装:在混凝土楼板的底部依次安装梁板模板、梁板次楞和梁板主楞,并竖立梁板支撑杆连接在梁板主楞的底部,在梁板支撑杆上沿水平方向纵、横设置水平杆,最下层的水平杆距离地面的距离小于等于350mm,当层高大于3.5m时,在梁板主楞的底部设置展开的剪刀撑斜杆;S4: Beam and slab formwork installation: Install the beam and slab formwork, the beam and slab secondary flute and the beam and slab main flute at the bottom of the concrete slab in sequence, and erect the beam and slab support rods to connect to the bottom of the beam and slab main flute. Horizontal rods are installed vertically and horizontally in the horizontal direction, and the distance between the bottom horizontal rod and the ground is less than or equal to 350mm. When the floor height is greater than 3.5m, the scissors support inclined rods are installed at the bottom of the beam and slab main flute;
S5:梁板钢筋安装:安装过程中需要控制好钢筋保护层厚度;S5: Beam and slab reinforcement installation: During the installation process, it is necessary to control the thickness of the protection layer of the reinforcement;
S6:梁板模板校调及加固:采用线锤自由下落检查垂直度,并且使用水平仪测定其平整度和本层安装标高;S6: Calibration and reinforcement of the beam and slab formwork: Check the verticality by free-falling a wire hammer, and use a level to measure its flatness and the installation elevation of this floor;
S7:浇筑混凝土:浇筑混凝土应从中间向四周扩散浇筑,先浇筑剪力墙和柱,然后浇筑梁板,柱和剪力墙一次性从下至上分层浇筑,浇筑后找平收面。S7: Concrete pouring: Concrete pouring should be spread from the middle to the surroundings. The shear walls and columns should be poured first, and then the beams and slabs should be poured. The columns and shear walls should be poured layer by layer from bottom to top at one time.
进一步地,在剪力墙模板和柱模板安装前,其表面需清理干净,并涂抹水性脱模剂。Furthermore, before the shear wall formwork and column formwork are installed, the surface needs to be cleaned and a water-based release agent should be applied.
进一步地,下一层的柱模板、剪力墙模板周转至上一层安装时,当出现结构尺寸不一致会导致柱模板或剪力墙模板上有多余的对拉螺栓眼,需要使用堵头。Furthermore, when the column formwork and shear wall formwork of the next floor are transferred to the upper floor for installation, when there are inconsistencies in structural dimensions, there will be redundant bolt holes on the column formwork or shear wall formwork, and plugs need to be used.
本发明的一种全钢支撑加固模板体系减少了木制龙骨的使用量,能够节约资源消耗,绿色施工,增加了周转率,达到节能减排的目的,并且还能够提高主体结构的质量,工艺可靠、操作方便,降低了工程成本。The all-steel-supported and reinforced formwork system of the present invention reduces the usage of wooden keels, saves resource consumption, green construction, increases the turnover rate, achieves the purpose of energy saving and emission reduction, and can also improve the quality of the main structure and the process Reliable, easy to operate, reduced engineering costs.
附图说明Description of drawings
下面结合附图对本发明作进一步描写和阐述。The present invention will be further described and illustrated below in conjunction with the accompanying drawings.
图1是本发明首选实施方式的一种全钢支撑加固模板体系中柱模板支撑结构的侧视图;Fig. 1 is the side view of column formwork support structure in a kind of all-steel support reinforcement formwork system of preferred embodiment of the present invention;
图2是柱模板支撑结构的俯视图;Fig. 2 is the top view of column template support structure;
图3是剪力墙模板支撑结构的侧视图;Fig. 3 is a side view of the shear wall formwork support structure;
图4是梁板模板支撑结构的侧视图;Fig. 4 is a side view of the beam-slab formwork support structure;
图5是梁板模板支撑结构的底视图。Figure 5 is a bottom view of the beam slab formwork support structure.
附图标记:11、柱模板;12、柱主楞;13、柱次楞;14、柱对拉螺杆;21、剪力墙模板;22、墙主楞;23、墙次楞;24、墙对拉螺杆;31、梁板模板;32、梁板主楞;33、梁板次楞;4、十字垫片。Reference signs: 11, column formwork; 12, column main flute; 13, column secondary flute; 14, column opposite tension screw; 21, shear wall formwork; 22, wall main flute; 23, wall secondary flute; 24, wall 31. Beam and slab formwork; 32. Main beam and slab flute; 33. Beam and slab secondary flute; 4. Cross gasket.
具体实施方式Detailed ways
下面将结合附图、通过对本发明的优选实施方式的描述,更加清楚、完整地阐述本发明的技术方案。The technical solution of the present invention will be explained more clearly and completely through the description of preferred embodiments of the present invention in conjunction with the accompanying drawings.
本发明首选实施方式的一种全钢支撑加固模板体系,包括柱模板支撑结构、剪力墙模板支撑结构和梁板模板支撑结构,其中:An all-steel-supported reinforcement formwork system in the preferred embodiment of the present invention includes a column formwork support structure, a shear wall formwork support structure and a beam-slab formwork support structure, wherein:
如图1和图2所示,柱模板支撑结构包括四面柱模板11,四面柱模板11围设形成截面呈矩形的柱体成型空间,柱模板11背离柱体的一面设有沿竖直方向延伸的柱次楞13,柱次楞13外设有沿水平方向延伸的柱主楞12,相对的柱模板11之间还设有贯穿的柱对拉螺杆14,柱对拉螺杆14的两端分别设置在柱体相对两侧的柱主楞12上;As shown in Figures 1 and 2, the column formwork support structure includes a four-sided column formwork 11. The four-sided column formwork 11 surrounds a column forming space with a rectangular cross section. Column secondary corrugated 13, column secondary corrugated 13 is provided with column main corrugated 12 extending in the horizontal direction, and column opposite pull screw 14 is also provided between the opposite column templates 11, and the two ends of column opposite pull screw 14 are respectively Set on the column main flute 12 on opposite sides of the column;
如图3所示,剪力墙模板支撑结构包括四面剪力墙模板21,四面剪力墙模板21围设形成截面呈矩形的剪力墙成型空间,剪力墙模板21上设有沿竖直方向延伸的墙次楞23,墙次楞23外设有沿水平方向延伸的墙主楞22,相对的剪力墙模板21之间还设有贯穿的墙对拉螺杆24,墙对拉螺杆24的两端分别连接在墙体相对两侧的墙主楞22上;剪力墙模板21包括互相连接的若干墙模板片,相邻墙模板片之间的对缝上设有次背楞,次背楞的厚度与墙次楞23相同。剪力墙模板支撑结构的外墙部分在墙主楞22与另一墙主楞22固定时采用阳角对接,阳角上两个墙主楞22错搭,两个墙主楞22的连接点上设有用于固定的钩子带母,剪力墙模板支撑结构的内墙部分在墙主楞22与另一墙主楞22固定时采用阴角对接,阴角的拼缝处采用压脚木方压脚,压脚木方的厚度与墙次楞23厚度相同。As shown in Figure 3, the shear wall formwork support structure includes four-sided shear wall formwork 21, and the four-side shear wall formwork 21 encloses a shear wall forming space with a rectangular cross section. The wall secondary flute 23 extending in the horizontal direction is provided outside the wall secondary flute 23 with the wall main flute 22 extending in the horizontal direction, and the wall opposite tension screw 24 is also provided between the opposite shear wall formwork 21, and the wall opposite tension screw 24 The two ends of the two sides are respectively connected to the wall main flutes 22 on the opposite sides of the wall; the shear wall formwork 21 includes a number of wall formwork sheets connected to each other, and a secondary back flute is arranged on the seam between adjacent wall formwork pieces. The thickness of the back flute is the same as the wall flute 23. The outer wall part of the shear wall formwork support structure adopts the external corner butt joint when the main wall flute 22 and the other wall main flute 22 are fixed. There is a hook belt mother for fixing, and the inner wall part of the shear wall formwork support structure adopts the inner corner butt joint when the wall main flute 22 and the other wall main flute 22 are fixed, and the joint of the inner corner is made of presser foot wooden square Presser foot, the thickness of the presser foot wooden side is identical with the thickness of wall second corrugated 23.
如图4和图5所示,梁板模板支撑结构包括梁板模板31,梁板模板31位于混凝土楼板的下方,梁板模板31的下方设有梁板次楞33,梁板次楞33的下方设有梁板主楞32,梁板主楞32下方设有梁板支撑架。梁板支撑架包括有沿竖直方向延伸的梁板支撑杆,梁板支撑杆支撑在梁板主楞32的下方,各梁板支撑杆之间连接有水平杆,水平杆在水平方向上交叉设置,梁板支撑杆上设有剪刀撑斜杆,剪刀撑斜杆的两端分别连接在梁板支撑杆和水平杆上,剪刀撑斜杆的两端分别设有用于连接的旋转扣件。As shown in Fig. 4 and Fig. 5, the beam slab formwork support structure comprises a beam slab formwork 31, the beam slab formwork 31 is positioned at the below of the concrete floor, and the beam slab formwork 31 is provided with a beam slab secondary flute 33, and the beam slab secondary flute 33 The beam and slab main flute 32 is arranged below, and the beam and slab supporting frame is arranged below the beam and slab main flute 32 . The beam-slab support frame includes beam-slab support rods extending vertically. The beam-slab support rods are supported under the beam-slab main flute 32. Horizontal rods are connected between the beam-slab support rods, and the horizontal rods cross in the horizontal direction. For setting, the beam slab support rod is provided with a scissors brace, and the two ends of the scissors brace are respectively connected to the beam slab support rod and the horizontal bar, and the two ends of the scissors brace are respectively provided with rotating fasteners for connection.
柱次楞13、墙次楞23和梁板次楞33均采用方钢管,柱主楞12、墙主楞22和梁板主楞32均采用成对的型钢龙骨,柱主楞12、墙主楞22和梁板主楞32各自之间的对接均采用对接用结构,对接用接头上设有四根用于连接固定的插销。柱对拉螺杆14和墙对拉螺杆24上均套设有PVC管。柱主楞12和柱对拉螺杆14之间、墙主楞22和墙对拉螺杆24之间均垫设有十字垫片4。The column secondary flute 13, the wall secondary flute 23 and the beam plate secondary flute 33 are all made of square steel pipes; The butt joints between the flute 22 and the beam-slab main flute 32 each adopt a butt joint structure, and the butt joints are provided with four bolts for connecting and fixing. Both the column-to-pull screw rod 14 and the wall-to-pull screw rod 24 are sheathed with PVC pipes. Between the column main flute 12 and the column opposite tension screw 14, between the wall main flute 22 and the wall opposite tension screw 24, cross gaskets 4 are arranged.
本发明的一种全钢支撑加固模板体系的施工方法,包括如下步骤:A construction method of an all-steel support reinforcement formwork system of the present invention comprises the following steps:
S1:墙柱钢筋安装:首先检查地面平整度,板面最高处低于设计标高,若高出涉及标高,需要进行打凿处理,安装墙柱钢筋,控制钢筋保护层厚度,在墙对拉螺杆24和柱对拉螺杆14的位置安装PVC管并控制好垂直度。S1: Installation of wall column reinforcement: first check the flatness of the ground, the highest part of the board surface is lower than the design elevation, if it is higher than the relevant elevation, it needs to be chiseled, install the wall column reinforcement, control the thickness of the reinforcement protective layer, and pull the screw on the wall 24 and post install PVC pipe and control verticality to the position of pull screw rod 14.
S2:柱模板11及剪力墙模板21安装:在剪力墙模板21和柱模板11安装前,其表面需清理干净,并涂抹水性脱模剂。根据图纸安装柱模板11和剪力墙模板21,先竖起剪力墙模板21,然后在剪力墙模板21外侧固定墙次楞23,在墙次楞23的外侧设置墙主楞22,然后在PVC管中穿过墙对拉螺杆24并将墙对拉螺杆24的两端连接在两侧的墙主楞22上,在墙对拉螺杆24位于墙主楞22的外侧的端部扣上十字垫片4,柱模板11的安装过程与剪力墙模板21的安装过程相同。S2: Installation of the column formwork 11 and the shear wall formwork 21: Before the shear wall formwork 21 and the column formwork 11 are installed, the surface needs to be cleaned and a water-based release agent should be applied. Install the column formwork 11 and the shear wall formwork 21 according to the drawings, first erect the shear wall formwork 21, then fix the wall secondary flute 23 outside the shear wall formwork 21, set the wall main flute 22 outside the wall secondary flute 23, and then Pass through the wall-to-wall screw 24 in the PVC pipe and connect the two ends of the wall-to-wall screw 24 to the wall main flute 22 on both sides, and buckle the end of the wall to-pull screw 24 located on the outside of the wall main flute 22 The installation process of the cross gasket 4 and the column formwork 11 is the same as that of the shear wall formwork 21.
S3:柱模板11及剪力墙模板21校调及加固:柱模板11和剪力墙模板21安装完毕后,在其两侧安装临时支撑固定,并使用线锤自由落下检测垂直度,下一层的柱模板11、剪力墙模板21周转至上一层安装时,当出现结构尺寸不一致会导致柱模板11或剪力墙模板21上有多余的对拉螺栓眼,需要使用堵头。S3: Adjustment and reinforcement of column formwork 11 and shear wall formwork 21: After the column formwork 11 and shear wall formwork 21 are installed, install temporary supports on both sides and use a wire hammer to freely fall to detect the verticality. Next When the column formwork 11 and shear wall formwork 21 of the first floor are transferred to the upper floor for installation, if the structural dimensions are inconsistent, there will be redundant bolt holes on the column formwork 11 or shear wall formwork 21, and plugs need to be used.
S4:梁板模板31安装:在混凝土楼板的底部依次安装梁板模板31、梁板次楞33和梁板主楞32,并竖立梁板支撑杆连接在梁板主楞32的底部,在梁板支撑杆上沿水平方向纵、横设置水平杆,最下层的水平杆距离地面的距离小于等于350mm,当层高大于3.5m时,在梁板主楞32的底部设置展开的剪刀撑斜杆;S4: Installation of beam slab formwork 31: install beam slab formwork 31, beam slab secondary flute 33 and beam slab main flute 32 at the bottom of the concrete floor in sequence, and erect beam slab support rods connected to the bottom of beam slab main flute 32. Horizontal rods are arranged vertically and horizontally on the slab support rods in the horizontal direction, and the distance between the bottom horizontal rod and the ground is less than or equal to 350mm. When the floor height is greater than 3.5m, an expanded scissors support diagonal rod is installed at the bottom of the beam and slab main flute 32 ;
S5:梁板钢筋安装:安装过程中需要控制好钢筋保护层厚度。S5: Beam and slab reinforcement installation: During the installation process, the thickness of the reinforcement protection layer needs to be well controlled.
S6:梁板模板31校调及加固:采用线锤自由下落检查垂直度,并且使用水平仪测定其平整度和本层安装标高。S6: Calibration and reinforcement of beam and slab formwork 31: Use a wire hammer to freely fall to check the verticality, and use a level to measure its flatness and the installation elevation of this floor.
S7:浇筑混凝土:浇筑混凝土应从中间向四周扩散浇筑,先浇筑剪力墙和柱,然后浇筑梁板,柱和剪力墙一次性从下至上分层浇筑,浇筑后找平收面。S7: Concrete pouring: Concrete pouring should be spread from the middle to the surroundings. The shear walls and columns should be poured first, and then the beams and slabs should be poured. The columns and shear walls should be poured layer by layer from bottom to top at one time.
具体地:在步骤S1中,在开始安装模板之前,必须检查地面的平整度,板面最高处不能高出设计标高,若超出设计标高时,需进行打凿处理,剪力墙模板21与楼面板间的缝隙用水泥砂浆堵塞。钢筋安装时,重点控制钢筋安装偏位情况和水电管线预埋情况,严格控制保护层厚度。项目部通知钢筋验收合格后,在钢筋上纵向间距每根穿墙螺杆位置,横向间距每根穿墙螺杆位置与墙体相同宽度的内撑(PVC管),严格要求内撑表面上、下方向水平,左、右方向与墙线成直角,该工序直接影响墙面的平整度、垂直度,应专人检查。Specifically: in step S1, before starting to install the formwork, the flatness of the ground must be checked, and the highest point of the slab surface cannot be higher than the design elevation. The gaps between the panels are plugged with cement mortar. When installing steel bars, focus on controlling the installation deviation of steel bars and the pre-embedding of water and electricity pipelines, and strictly control the thickness of the protective layer. After the project department notifies the steel bars to pass the inspection, the vertical spacing of each wall-through screw position on the steel bar, and the horizontal spacing of each wall-through screw position with the inner support (PVC pipe) of the same width as the wall, strictly require the upper and lower directions of the inner support surface Horizontal, left and right directions are at right angles to the wall line. This process directly affects the flatness and verticality of the wall surface and should be checked by a special person.
在步骤S2中,柱最大尺寸为400mmx900mm。柱模板11采用15mm厚木模板,40x40型方钢作为柱次楞13,φ14的柱对拉螺杆14加固,采用型钢龙骨做柱主楞12,第一道柱主楞12距楼(地)面的高度应≤200mm,其余每道箍间距500mm。剪力墙厚度主要为200mm厚。以200mm厚墙体加固为例。墙次楞23:横截面40×40㎜,壁厚2.5㎜方钢;墙主楞22为方钢,墙次楞23间距200mm,墙主楞22间距500mm。墙对拉螺杆24的水平间距是450mm,墙对拉螺杆24竖直间距500mm。第一道墙主楞22距地小于200mm。In step S2, the maximum size of the column is 400mmx900mm. Column formwork 11 adopts 15mm thick wood formwork, 40x40 type square steel is used as column and secondary corrugation 13, and φ14 column is reinforced by tension screw 14. Sectional steel keel is used as column main corrugation 12, and the first column and main corrugation 12 are separated from the building (ground) surface The height should be ≤200mm, and the distance between each hoop is 500mm. The thickness of the shear wall is mainly 200mm thick. Take 200mm thick wall reinforcement as an example. Second wall flute 23: cross-section 40×40㎜, wall thickness 2.5㎜ square steel; wall main flute 22 is square steel, wall secondary flute 23 spacing 200mm, wall main flute 22 spacing 500mm. The horizontal distance between the wall and the pull screw 24 is 450mm, and the vertical distance between the wall and the pull screw 24 is 500mm. The distance between the main flute 22 of the first wall and the ground is less than 200mm.
在墙体内外两侧同时竖起两块墙模板片,墙模板片的立边分别固定两根次背楞和以后的墙模板片固定连接,也就是说:每块墙模板片与墙模板片的对接缝都要用一根次背楞相接。经过预制和穿紧墙对拉螺杆24,对拉螺杆套上PVC管,PVC管尺度就是浇注混凝土的厚度,(PVC管:第一,内外两块模板定尺支撑;第二,墙对拉螺杆24可以重复使用),在墙次楞23的外侧分别经过墙对拉螺杆24装配一道墙主楞22,墙主楞22外侧经过墙对拉螺杆24扣上十字垫片4,将内外剪力墙模板21固定连接。第一块剪力墙模板21固定连接第二块剪力墙模板21的对缝处放一根木方(木方厚度同墙次楞23厚度),用普通钉定好。Two wall formwork sheets are erected on both sides inside and outside the wall at the same time, and the vertical edges of the wall formwork sheets are respectively fixed with two secondary back ribs and the subsequent wall formwork sheets are fixedly connected, that is to say: each wall formwork sheet is connected to the wall formwork sheet The butt seams must be connected with a secondary back. Through prefabrication and tight wall tensioning screw 24, the PVC pipe is put on the tensioning screw, and the PVC pipe scale is exactly the thickness of pouring concrete, (PVC pipe: first, the two templates inside and outside are fixed-length support; second, the wall tensioning screw 24 can be reused), assemble a main wall flute 22 on the outside of the wall secondary flute 23 respectively through the wall-to-pull screw 24, and buckle the cross gasket 4 on the outside of the wall main flute 22 through the wall-to-pull screw 24 to connect the inner and outer shear walls Template 21 is fixedly connected. The first piece of shear wall formwork 21 is fixedly connected to the opposite seam of the second piece of shear wall formwork 21 and puts a wooden side (the thickness of the wooden side is the same as the wall second corrugated 23 thickness), fixed with common nails.
将墙次楞23抽到墙体净高度,在剪力墙模板21剩余空间对缝处的那根墙次楞23为基准每隔200mm(指中心距,模板厚1.5CM时)放一根墙次楞23,用普通钉固定好后,将所有墙次楞23布满,依次类推,将整个房间安装完。墙次楞23距墙顶及墙底不得大于100mm。第一道墙主楞22距地面200mm,固定在墙对拉螺杆24上,用十字垫片4卡好,内外墙同时进行,并用螺母固定,墙主楞22与墙主楞22之间对接用接头。接头采用四根插销进行连接固定。Draw the wall corrugation 23 to the net height of the wall, and place a wall every 200mm (referring to the center distance, when the template thickness is 1.5CM) on the basis of the wall corrugation 23 at the seam in the remaining space of the shear wall formwork 21 After the second corrugated 23 is fixed with ordinary nails, all the walls are covered with the second corrugated 23, and so on, the whole room is installed. The distance between wall corrugated 23 and the top and bottom of the wall shall not be greater than 100mm. The first wall main flute 22 is 200mm away from the ground, fixed on the wall opposite tension screw 24, fastened with the cross gasket 4, the inner and outer walls are carried out at the same time, and fixed with nuts, and the wall main flute 22 and the wall main flute 22 are used for docking connector. The connector is connected and fixed by four pins.
横向每450mm固定一根墙对拉螺杆24,将每道墙主楞22上固定墙对拉螺杆24,用十字垫片4卡住,并用螺母固定(内外对称)。加固次序为阴角向两端,先短肢墙后长肢墙,内外同时加固。十字垫片4使用在墙对拉螺杆24上,当墙主楞22固定在墙对拉螺杆24上之后,内外墙用十字垫片4卡住,并用螺母固定(内外对称)。Horizontally every 450mm fixes a wall opposite tension screw rod 24, fixes the wall opposite tension screw rod 24 on the main flute 22 of every road wall, blocks with cross spacer 4, and fixes with nut (inside and outside symmetry). The order of reinforcement is to both ends of the inner corner, first the short limb wall and then the long limb wall, and the inside and outside are reinforced at the same time. Cross washer 4 is used on the wall to pull screw rod 24, after wall main flute 22 is fixed on the wall to pull screw rod 24, interior and exterior walls are blocked with cross washer 4, and fix with nut (inside and outside symmetry).
内墙在建立与横梁之间遇到拐角时用阴角相接。阴角拼缝处设置木方压脚,木方厚度同次楞厚度When the interior wall meets the corner between the building and the beam, it meets with the inner corner. Wooden square presser feet are set at the joints of the inner corners, and the thickness of the wooden squares is the same as the thickness of the second corrugation
外墙在墙主楞22与墙主楞22之间固定时遇到拐角时用阳角相接。本次项目采用两根墙主楞22错搭,用两根钩子带母固定。下一层的柱模板11、剪力墙模板21周转至上一层柱墙安装时,如有因为结构尺寸不一致而致使模板上有多余的对拉螺杆眼,该对拉螺杆眼必须用堵头在模板上进行封堵,以避免从该孔眼漏浆。另所有竖向柱模板11、剪力墙模板21的对拉螺杆两端必须采用橡胶堵头封堵。外墙、楼梯间等处上层结构模板施工时,在下层墙体预埋对拉螺杆,将上层墙模板下挂,并在下挂部分设置一道墙主楞22进行加固。Outer wall joins with external angle when running into corner when fixing between wall main corrugated 22 and wall main corrugated 22. In this project, two main walls with 22 rafters are used in a wrong way, and they are fixed with two hooks and mothers. When the column formwork 11 and shear wall formwork 21 of the next layer are transferred to the column wall of the previous layer for installation, if there are redundant pull screw holes on the formwork due to inconsistent structural dimensions, the pull screw holes must be plugged in Formwork is plugged to prevent slurry leakage from this hole. In addition, rubber plugs must be used at both ends of the tension screw rods of all vertical column formwork 11 and shear wall formwork 21. During the construction of the upper structure formwork on the outer wall, stairwell, etc., pre-embed the pull screw in the lower wall, hang the upper wall formwork, and set a wall main flute 22 on the lower hanging part for reinforcement.
在步骤S3中,剪力墙模板21和柱模板11安装前做好表面清理干净,涂抹适量的水性脱模剂。安装剪力墙模板21必须从转角或门窗洞或端板的位置开始。将剪力墙模板21两端固定并校正好以后,再固定墙中间部分的剪力墙模板21。剪力墙模板21安装完毕后的平整度≤5mm,垂直度≤5mm。楼板浇筑时预埋可调斜拉杆的固定板,并按照模板图纸所示安装可调节斜杆,可调节拉杆的上端安装在第三道方钢高度。安装过程中遇到墙对拉螺杆24位置,需要将胶管及杯头套住墙对拉螺杆24,两头穿过对应的剪力墙模板21孔位。剪力墙模板21安装完毕后,需用临时支撑固定,再安装两边的墙次楞23和墙主楞22加固,拧紧墙对拉螺杆24。墙对拉螺杆24的螺母拧紧力应适度,以保证墙身厚度。在剪力墙模板21顶部转角处,固定线锤自由落下,线锤尖部对齐楼面垂直度控制线。如有偏差,通过调节斜撑进行调节,直到线锤尖部和参考控制线重合为止。In step S3, the surfaces of the shear wall formwork 21 and the column formwork 11 are cleaned before installation, and an appropriate amount of water-based release agent is applied. The installation of the shear wall formwork 21 must start from the corner or the position of the door and window hole or the end plate. After the two ends of the shear wall formwork 21 are fixed and corrected, the shear wall formwork 21 in the middle part of the wall is fixed. After the shear wall formwork 21 is installed, the flatness is ≤5mm, and the verticality is ≤5mm. When the slab is poured, the fixed plate of the adjustable tie rod is pre-buried, and the adjustable tie rod is installed as shown in the template drawing. The upper end of the adjustable tie rod is installed at the height of the third square steel. During the installation process, when encountering the position of the wall opposite pull screw 24, it is necessary to cover the rubber hose and the cup head with the wall opposite pull screw 24, and the two ends pass through the corresponding 21 holes of the shear wall formwork. After the shear wall template 21 has been installed, it needs to be fixed with a temporary support, and then the wall secondary flute 23 and the wall main flute 22 on both sides are installed for reinforcement, and the wall pair pull screw 24 is tightened. The tightening force of the nut of the wall to the pull screw rod 24 should be moderate to ensure the thickness of the wall. At the top corner of the shear wall formwork 21, the fixed wire hammer falls freely, and the tip of the wire hammer is aligned with the verticality control line of the floor. If there is a deviation, adjust it by adjusting the diagonal brace until the tip of the line hammer coincides with the reference control line.
在步骤S4中,首先进行梁板支撑架的搭设:小高层主楼标准层采用承插式钢管脚手架,使用Φ48.3×3钢管。扫地杆距楼面的距离不大于350mm。In step S4, the beam-slab support frame is erected first: the standard floor of the main building of the small high-rise adopts socket-type steel pipe scaffolding, and Φ48.3×3 steel pipes are used. The distance between the sweeping rod and the floor is not more than 350mm.
搭设时应对梁板支撑杆和水平杆等钢管进行认真检查,发现有裂缝,锈蚀严重及弯曲变形均不得使用。其中用于梁板支撑杆的钢管壁厚不得小于3.0mm。梁板支撑杆采用对接。梁板支撑杆接头与相近水平杆的距离不得大于步高的三分之一。相邻两梁板支撑杆的接头应相互错开,不应在同一步高和同一间距内。相邻梁板支撑杆接头的高度差应大于500mm。满堂架必须纵、横两个方向设置扫地杆。When erecting, steel pipes such as beam-slab support rods and horizontal rods should be carefully inspected, and cracks, serious corrosion and bending deformation should not be used. Among them, the wall thickness of the steel pipe used for the beam-slab support rod shall not be less than 3.0mm. The beam-slab support rods are butt jointed. The distance between beam-slab support rod joints and adjacent horizontal rods shall not be greater than one-third of the step height. The joints of two adjacent beam-slab support rods should be staggered from each other, and should not be within the same step height and the same distance. The height difference between adjacent beam-slab support rod joints should be greater than 500mm. The full hall frame must be equipped with sweeping poles in both vertical and horizontal directions.
为保证梁板支撑架有足够的稳定性,除了设置双向水平杆外,在层高大于3.5米时还要在纵横方向设置剪刀撑,特别是框架梁的梁板支撑架必须沿纵向设置剪刀撑采用刚性支撑,用钢管搭设。剪刀撑斜杆的最下面一个连接点距地面不大于500mm,以保证梁板支撑架的刚度及稳定。剪刀撑的宽度不应小于6m,剪刀撑斜杆与地面间的夹角须在45°~60°之间。剪刀撑斜杆的接长宜采用搭接,搭接长度不小于1m,应采用不少于两个旋转扣件固定,端部的旋转扣件盖板边缘至剪刀撑斜杆杆端距离不小于100mm。剪刀撑斜杆应用旋转扣件固定在与之相交的水平杆或梁板支撑杆上。In order to ensure sufficient stability of the beam-slab support frame, in addition to setting two-way horizontal bars, scissor braces must be installed in the vertical and horizontal directions when the storey height is greater than 3.5 meters, especially the beam-slab support frame of the frame beam must be installed along the longitudinal direction. It adopts rigid support and is erected with steel pipes. The bottom connection point of the scissors brace is not more than 500mm from the ground to ensure the rigidity and stability of the beam and slab support frame. The width of the scissors support should not be less than 6m, and the angle between the scissors support inclined bar and the ground must be between 45° and 60°. The length of the scissors brace diagonal rod should be lapped, and the lap length should not be less than 1m. It should be fixed with no less than two rotating fasteners. 100mm. The scissors braces should be fixed to the intersecting horizontal rods or beam-slab support rods with rotary fasteners.
在模板支撑架搭设完成后,必须经过验收合格后方能进入下一道作业。混凝土浇注期间,派专人观察模板及其支撑系统的变形情况。满堂支撑承重架必须等到顶板混凝土强度达到80%以上时方可拆除,大跨度及悬挑部位需达到100%以上方可拆除。严禁随意拆除满堂架任何杆件。After the template support frame is erected, it must pass the acceptance before entering the next operation. During the pouring of concrete, send special personnel to observe the deformation of the formwork and its supporting system. The supporting load-bearing frame of the whole hall must wait until the concrete strength of the roof reaches more than 80% before dismantling, and the large-span and overhanging parts must reach more than 100% before dismantling. It is strictly forbidden to dismantle any rods of the full hall frame at will.
梁板模板31、梁板主楞32及梁板次楞33搭设要求:顶板的梁板主楞32应平行于顶板的短边方向,梁板主楞32自由端悬挑≦300mm,间距按模板方案要求配置。顶板的梁板次楞33满足边到边间距≦200mm,且满足梁板次楞33端头到墙边距离≦100mm,梁板模板31接缝位置可采用钢包木或木方打钉固定。梁板次楞33在梁板主楞32部位进行搭接,搭接长度≧300mm。短边方向的梁板支撑杆离墙端≦300mm,跨中间距≦1200mm,顶托自由高度≦200mm,梁板支撑杆顶层的水平杆至梁板模板31支撑点间距≦500mm。梁板支撑杆底部放置垫板。顶板的梁板模板31配板时使用标准整板及配板组合,优化配模图后,按照配模图编号使用精密裁板锯进行集中配板,并于板反面注明编号及规格,分类堆放保管。平台板调整宜采用就高不就低的方法,布料机位置应进行提前定点,支撑体系进行加强处理。Requirements for erecting beam slab formwork 31, beam slab main flute 32 and beam slab secondary flute 33: the beam and slab main flute 32 of the roof should be parallel to the short side direction of the roof, the free end of the beam and slab main flute 32 cantilever ≦ 300mm, and the distance should be according to the formwork The scheme requires configuration. The beam-board secondary flute 33 of the top plate meets the side-to-side distance ≤ 200mm, and the distance from the end of the beam-plate secondary flute 33 to the wall edge ≤ 100mm, and the joint position of the beam-slab formwork 31 can be fixed by ladle wood or wooden square nails. The secondary flute 33 of the beam and slab is lapped at the main flute 32 of the beam and slab, and the lap length is ≧300mm. The beam slab support rod in the short side direction is ≦300mm from the wall end, the mid-span distance is ≦1200mm, the free height of the jacking is ≦200mm, and the distance between the horizontal rod on the top layer of the beam slab support rod and the 31 support points of the beam slab formwork is ≦500mm. The backing plate is placed at the bottom of the beam support bar. The beam slab formwork 31 of the top plate is assembled using the standard whole board and matching board combination. After optimizing the matching diagram, use a precision panel saw to carry out centralized matching according to the number of the matching diagram, and mark the number and specification on the back of the board, and classify Stacked for storage. The adjustment of the platform board should adopt the method of making it higher than lower, the position of the distribution machine should be fixed in advance, and the support system should be strengthened.
在步骤S5和步骤S6中,梁板钢筋安装,应有专人监看。主要为了防止工人野蛮施工破坏或移动已施工好的梁板模板31。梁板钢筋安装完毕后,应控制好钢筋保护层厚度,严禁钢筋直接接触模板导致模板变形移位。梁板钢筋应按标准验收程序组织验收,验收未通过不得浇筑混凝土。墙身垂直校正完毕后进行楼面梁底的梁板模板31安装,楼面梁的梁板模板31应先安装底模,校正垂直后安装侧模。楼面对角线检查无误时,开始安装楼面模板,为了安装快捷,楼面模板要平行逐件排放,在安装期间一次性用单支顶托调好水平度。每个单元模板全部安装完毕后,应用水平仪测定其平整度及本层安装标高,如有偏差通过模板系统的可调节支撑进行校正,直至达到整体平整及相应的标高。每个单元的水平及标高调整完毕后,需对整个楼面做一次水平和标高的校核,楼面平整度≤8mm。检查墙对拉螺杆24是否拧紧,检查梁板支撑架顶托是否顶紧。In steps S5 and S6, the installation of beam and slab reinforcement should be supervised by a special person. Mainly in order to prevent workers from destroying or moving the beam-slab formwork 31 that has been constructed. After the beam and slab steel bars are installed, the thickness of the protective layer of the steel bars should be well controlled, and it is strictly forbidden for the steel bars to directly contact the formwork to cause deformation and displacement of the formwork. Beam and slab reinforcement shall be checked and accepted according to the standard acceptance procedure, and no concrete shall be poured if the acceptance is not passed. Carry out the beam slab formwork 31 installation at the bottom of the floor beam after the vertical correction of the wall body is completed, the beam slab formwork 31 of the floor beam should be installed with the bottom form earlier, and install the side form after correcting the vertical. When the diagonal line of the floor is checked correctly, the floor formwork will be installed. For quick installation, the floor formwork should be arranged in parallel one by one. During the installation period, the levelness should be adjusted with a single support. After the formwork of each unit is installed, use a level to measure its flatness and the installation elevation of this floor. If there is any deviation, it will be corrected through the adjustable support of the formwork system until the overall flatness and corresponding elevation are achieved. After the level and elevation of each unit are adjusted, the level and elevation of the entire floor shall be checked once, and the flatness of the floor shall be ≤8mm. Check whether the pull screw 24 of the wall is tightened, and check whether the supporting frame of the beam is tight.
在步骤S7中,混凝土浇筑时应从中间向四周扩散浇筑,防止模板产生整体移位。先浇筑墙柱,后浇筑梁板。所有柱及剪力墙一次性浇筑,但需分两次浇捣,从下至上分层浇筑,确保每次浇筑不超过1.5米,并捣均匀。浇筑混凝土时,应注意防止混凝土的分层离析。楼梯部位分三次浇筑,每次浇筑时必需打开踏步板上的透气口,以防止气泡和蜂窝产生。双层窗台板浇筑时需上下分开浇筑,以防止窗台板浇筑时,内部气体过多而起拱。垂直混凝土泵管不能和钢支撑模板硬性接触。必须在工作面以下的两层固定泵管,在楼面上的泵管需要用胶垫防震。浇筑混凝土时,应注意保护钢筋,一旦钢筋骨架发生变形或位移,应及时纠正。钢筋骨架重要节点应采取加固措施。梁板混凝土浇筑,先浇筑梁,根据梁高分层浇筑成阶梯形,当达到板底位置时再与板的混凝土一起浇筑,随着阶梯形不断延伸,梁板混凝土浇筑连续向前进行。混凝土振捣:混凝土采用插入式振动棒振动浇筑,混凝土浇筑后必须振捣密实,振捣棒要快插慢拔,上下略为抽动,以使上下振捣均匀。插点要均匀排列,逐点移动,顺序进行,不得遗漏,移动间距不大于振捣棒作用半径的1.5倍,控制在30~40cm,每一振动点的振捣时间控制在15~30s之间,表现为混凝土开始泛浆和不冒气泡为准,并且在20~30min后对其进行二次复振。振捣上一层时应插入下层5cm,以消除两层间的接缝。在整个振捣作业中,不要振模振筋,不得碰撞各种预埋件。在浇筑过程中,要组织木工、钢筋工及时配合混凝土的浇筑以便对出现的问题及时进行修整。平板振捣器的移动间距,应能保证振捣器的平板覆盖已振捣的边缘。在混凝土初凝前,在浇筑交接处及柱、墙、梯井壁与底板交接部分的底板面上用平板式振动器进行二次振动,提高混凝土的抗裂性。混凝土振捣后,初凝前进行混凝土的表面处理。组织瓦工班在混凝土浇筑后,初凝前收水时,用木模子打磨压实,以闭合收水裂缝。找平收面:混凝土浇筑完成以后,瓦工开始进行找平工作,瓦工用3m刮杆依照事先焊好的标高控制筋将混凝土刮平。顶板混凝土分两次进行压光,第一次用木抹子按照标高将混凝土表面搓平。第二遍抹压:当面层开始凝结,地面面层有脚印但不下陷,用铁抹子进行第二遍抹压,注意不得漏压,并将面层的凹坑、砂眼和脚印压平,并用直条扫把沿房间长向扫出顺直条纹。In step S7, the concrete should be spread from the middle to the surroundings during pouring to prevent overall displacement of the formwork. The wall columns are poured first, and then the beams and slabs are poured. All columns and shear walls are poured at one time, but they need to be poured twice and poured in layers from bottom to top to ensure that each pouring does not exceed 1.5 meters and is evenly pounded. When pouring concrete, care should be taken to prevent delamination and segregation of the concrete. The stairs are poured three times, and the air vents on the step must be opened each time they are poured to prevent air bubbles and honeycombs. When pouring double-layer window sills, the upper and lower parts need to be poured separately to prevent arching due to excessive internal gas when pouring the window sills. The vertical concrete pump pipe cannot be in rigid contact with the steel support formwork. The pump pipe must be fixed on the two floors below the working surface, and the pump pipe on the floor needs to be shock-proof with rubber pads. When pouring concrete, attention should be paid to protecting the steel bars, and once the steel bar skeleton is deformed or displaced, it should be corrected in time. Reinforcement measures should be taken for important joints of steel skeleton. For beam slab concrete pouring, beams are poured first, and then poured in layers according to the height of the beam into a ladder shape. When the bottom of the slab is reached, it is poured together with the concrete of the slab. As the ladder shape continues to extend, the beam slab concrete pouring proceeds continuously. Concrete Vibration: Concrete is poured by vibrating with a plug-in vibrating rod. After the concrete is poured, it must be vibrated and compacted. The vibrating rod should be inserted quickly and pulled out slowly. The insertion points should be evenly arranged, moved point by point, and carried out sequentially, without omission, the moving distance should not be greater than 1.5 times the radius of action of the vibrating rod, controlled within 30-40cm, and the vibrating time of each vibration point should be controlled between 15-30s , the performance is that the concrete starts to bleed and does not bubble, and it is re-vibrated after 20 to 30 minutes. When vibrating the upper layer, insert 5cm into the lower layer to eliminate the seam between the two layers. During the whole vibrating operation, do not vibrate the mold and vibrate the ribs, and do not collide with various embedded parts. During the pouring process, it is necessary to organize carpenters and steel workers to cooperate with the pouring of concrete in time to repair the problems that arise in time. The moving distance of the flat vibrator shall be such that the flat plate of the vibrator covers the vibrated edge. Before the initial setting of the concrete, a plate vibrator is used to carry out secondary vibration on the bottom surface of the pouring junction and the junction of the column, wall, ladder well wall and the bottom slab to improve the crack resistance of the concrete. After the concrete is vibrated, the surface treatment of the concrete is carried out before the initial setting. After the concrete is poured and the water is collected before the initial setting, the bricklayer team shall be organized to grind and compact it with wooden molds to close the water collection cracks. Leveling and closing: After the concrete pouring is completed, the bricklayer starts to level the work. The bricklayer uses a 3m scraper to level the concrete according to the previously welded elevation control bars. The roof concrete is calendered twice, and the first time the concrete surface is smoothed according to the elevation with a wooden trowel. The second time of smearing: when the surface layer starts to condense, and there are footprints on the ground surface layer but not sinking, use an iron trowel to perform the second time of smearing, pay attention not to leak pressure, and flatten the pits, trachoma and footprints on the surface layer, And use a straight broom to sweep out straight stripes along the length of the room.
本发明的一种全钢支撑加固模板体系减少了木制龙骨的使用量,能够节约资源消耗,绿色施工,增加了周转率,达到节能减排的目的,并且还能够提高主体结构的质量,工艺可靠、操作方便,降低了工程成本。The all-steel-supported and reinforced formwork system of the present invention reduces the usage of wooden keels, saves resource consumption, green construction, increases the turnover rate, achieves the purpose of energy saving and emission reduction, and can also improve the quality of the main structure and the process Reliable, easy to operate, reduced engineering costs.
上述具体实施方式仅仅对本发明的优选实施方式进行描述,而并非对本发明的保护范围进行限定。在不脱离本发明设计构思和精神范畴的前提下,本领域的普通技术人员根据本发明所提供的文字描述、附图对本发明的技术方案所作出的各种变形、替代和改进,均应属于本发明的保护范畴。本发明的保护范围由权利要求确定。The above specific embodiments are only descriptions of preferred embodiments of the present invention, rather than limiting the protection scope of the present invention. On the premise of not departing from the design concept and spirit of the present invention, all the modifications, substitutions and improvements made by those skilled in the art to the technical solution of the present invention according to the written description and drawings provided by the present invention shall belong to protection scope of the present invention. The protection scope of the present invention is determined by the claims.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910973330.1A CN110607905A (en) | 2019-10-14 | 2019-10-14 | An all-steel support reinforcement formwork system and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910973330.1A CN110607905A (en) | 2019-10-14 | 2019-10-14 | An all-steel support reinforcement formwork system and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110607905A true CN110607905A (en) | 2019-12-24 |
Family
ID=68894780
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910973330.1A Pending CN110607905A (en) | 2019-10-14 | 2019-10-14 | An all-steel support reinforcement formwork system and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110607905A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335628A (en) * | 2020-04-03 | 2020-06-26 | 中铁建设集团中南建设有限公司 | Connecting piece for reinforcing longitudinal formwork of shear wall and mounting method thereof |
CN112593700A (en) * | 2020-11-26 | 2021-04-02 | 中核华辰工程管理有限公司 | Square upright column template mounting structure and mounting method thereof |
CN113685018A (en) * | 2021-08-25 | 2021-11-23 | 重庆市渝海建设(集团)有限公司 | Column wall formwork structure and installation process |
CN114412172A (en) * | 2022-01-28 | 2022-04-29 | 中国建筑第八工程局有限公司 | Construction method of concrete column |
CN115977391A (en) * | 2023-02-04 | 2023-04-18 | 中建八局第四建设有限公司 | Construction method for reinforcing corner wall constructional column template |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0054524A2 (en) * | 1980-12-17 | 1982-06-23 | Mario Marino | A casting form system consisting of modular members for the construction of buildings, storey by storey |
CN104032948A (en) * | 2014-06-30 | 2014-09-10 | 龙信建设集团有限公司 | Steel-wood combined formwork and construction method |
CN205875705U (en) * | 2016-07-25 | 2017-01-11 | 青岛建设集团有限公司 | Wall form external corner gib head |
CN211037802U (en) * | 2019-10-14 | 2020-07-17 | 中建二局第二建筑工程有限公司 | All-steel support reinforced template system |
-
2019
- 2019-10-14 CN CN201910973330.1A patent/CN110607905A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0054524A2 (en) * | 1980-12-17 | 1982-06-23 | Mario Marino | A casting form system consisting of modular members for the construction of buildings, storey by storey |
CN104032948A (en) * | 2014-06-30 | 2014-09-10 | 龙信建设集团有限公司 | Steel-wood combined formwork and construction method |
CN205875705U (en) * | 2016-07-25 | 2017-01-11 | 青岛建设集团有限公司 | Wall form external corner gib head |
CN211037802U (en) * | 2019-10-14 | 2020-07-17 | 中建二局第二建筑工程有限公司 | All-steel support reinforced template system |
Non-Patent Citations (1)
Title |
---|
张朝阳;: "大面积碗扣式支撑加固体系设计", 中华民居(下旬刊), no. 05, pages 126 - 128 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335628A (en) * | 2020-04-03 | 2020-06-26 | 中铁建设集团中南建设有限公司 | Connecting piece for reinforcing longitudinal formwork of shear wall and mounting method thereof |
CN112593700A (en) * | 2020-11-26 | 2021-04-02 | 中核华辰工程管理有限公司 | Square upright column template mounting structure and mounting method thereof |
CN113685018A (en) * | 2021-08-25 | 2021-11-23 | 重庆市渝海建设(集团)有限公司 | Column wall formwork structure and installation process |
CN113685018B (en) * | 2021-08-25 | 2024-04-30 | 山东千乘建工有限公司 | Column wall mold structure and mounting process |
CN114412172A (en) * | 2022-01-28 | 2022-04-29 | 中国建筑第八工程局有限公司 | Construction method of concrete column |
CN115977391A (en) * | 2023-02-04 | 2023-04-18 | 中建八局第四建设有限公司 | Construction method for reinforcing corner wall constructional column template |
CN115977391B (en) * | 2023-02-04 | 2024-09-24 | 中建八局第四建设有限公司 | Construction method for reinforcing corner wall constructional column formwork |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110607905A (en) | An all-steel support reinforcement formwork system and construction method | |
CN211037802U (en) | All-steel support reinforced template system | |
CN201649623U (en) | Large basement shearing wall truss type steel tube unilateral formwork supporting structure | |
CN108677962B (en) | Subway entrance and exit segment foundation pit formwork installing and dismantling method | |
CN108678193B (en) | Post-cast strip and construction method thereof | |
CN203834926U (en) | Formwork erecting structure for bare concrete basement exterior wall | |
CN105952140B (en) | Tool-type steel framework Wood-plastic formwork system and its construction technology for cast-in-place concrete | |
CN107401279A (en) | Disposable one-piece casting staircase wall ladder combined steel formwork installation construction method | |
CN111236631B (en) | Semicircular concrete roof building supporting structure | |
CN212866842U (en) | Frame structure type building scaffold | |
CN217353538U (en) | Disposable integral molding construction structure for sunken well and reversed ridge | |
CN110878640A (en) | Anti-seismic reinforcing structure for frame shear wall filler wall body | |
CN107165280B (en) | A kind of large span open-spandrel sandwich board stay in place form support system and construction method | |
CN116696038A (en) | A kind of cast-in-place concrete sloping roof structure and its construction method | |
CN215670176U (en) | Detachable outer wall waterproof deformation joint construction structures | |
CN113266035A (en) | Construction method for upper structure of steam turbine base | |
CN115492371A (en) | Installation method of multi-curved-surface combined high and large template | |
CN211447712U (en) | I-shaped steel beam overhanging scaffold for open caisson | |
CN115404911B (en) | Reverse construction method of underground structure | |
CN212927033U (en) | Formwork support frame for large-span post-tensioned prestressed beam haunch structure | |
CN220167506U (en) | Supporting structure for reinforcing side beam template | |
CN222686119U (en) | Basement outer wall formwork system | |
CN221856179U (en) | An adjustable support frame for installing super-high building steel beams | |
CN110593461A (en) | A high-efficiency and fast integrated energy-saving wall | |
CN110258890A (en) | A kind of broken line type exterior wall is connected the construction method of concrete structure with roofing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191224 |
|
RJ01 | Rejection of invention patent application after publication |