AU2021102904A4 - A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project - Google Patents

A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project Download PDF

Info

Publication number
AU2021102904A4
AU2021102904A4 AU2021102904A AU2021102904A AU2021102904A4 AU 2021102904 A4 AU2021102904 A4 AU 2021102904A4 AU 2021102904 A AU2021102904 A AU 2021102904A AU 2021102904 A AU2021102904 A AU 2021102904A AU 2021102904 A4 AU2021102904 A4 AU 2021102904A4
Authority
AU
Australia
Prior art keywords
cost
construction
optimization
prefabricated
duration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2021102904A
Inventor
Yuanjing JIANG
Yufeng Shi
Jiayi Wu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Forestry University
Original Assignee
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Forestry University filed Critical Nanjing Forestry University
Priority to AU2021102904A priority Critical patent/AU2021102904A4/en
Application granted granted Critical
Publication of AU2021102904A4 publication Critical patent/AU2021102904A4/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B13/00Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion
    • G05B13/02Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric
    • G05B13/04Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators
    • G05B13/047Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators the criterion being a time optimal performance criterion
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06NCOMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
    • G06N3/00Computing arrangements based on biological models
    • G06N3/12Computing arrangements based on biological models using genetic models
    • G06N3/126Evolutionary algorithms, e.g. genetic algorithms or genetic programming
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Health & Medical Sciences (AREA)
  • Geometry (AREA)
  • Evolutionary Computation (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Strategic Management (AREA)
  • Biophysics (AREA)
  • General Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Economics (AREA)
  • Bioinformatics & Computational Biology (AREA)
  • Tourism & Hospitality (AREA)
  • General Health & Medical Sciences (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Software Systems (AREA)
  • Artificial Intelligence (AREA)
  • Bioinformatics & Cheminformatics (AREA)
  • Evolutionary Biology (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Genetics & Genomics (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Biomedical Technology (AREA)
  • Computational Linguistics (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Molecular Biology (AREA)
  • Computing Systems (AREA)
  • Primary Health Care (AREA)
  • Mathematical Physics (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Physiology (AREA)
  • Quality & Reliability (AREA)

Abstract

The invention relates to a BIM-based optimization method for the cost and construction period of prefabricated construction project, including prefabricated building valuation module and construction duration to cost optimization module. The prefabricated building valuation module includes extracting the information of model components, mapping the engineering quantity of components in accordance with the list mapping rules, and generating the engineering cost data. The construction duration to cost optimization module includes the establishment of the duration-cost function model, the optimization of the original duration-cost data by genetic algorithm, the introduction of the optimization results into BIM for collision inspection, the modification of the construction plan according to the inspection results, the cyclic optimization of the duration-cost, and the final construction plan derived after the operation of the model. The solution provided by the invention can realize the information management of prefabricated building and better carry out the project cost work and construction scheme planning. 1/1 DRAWING 2 1 The bill of quantities valuation module construction time-cost optimization module The time-cost function 21 11 model Extract the information 22 of prefabricated Preparation of the components construction plan 12 13 The quota Map the component Genetic Algorithm optimize database o amount with the quota the original time-cost data database 24 The bill of Collision checking quantity NO The construction cost Reasonable 14ntrution plan 14 15/t 15 YES 25 The final construction plan

Description

1/1 DRAWING
1 The bill of quantities valuation module construction time-cost optimization module 2
The time-cost function 21 11 model
Extract the information 22 of prefabricated Preparation of the components construction plan 12 13
Map the component Genetic Algorithm optimize The quota o amount with the quota the original time-cost data database database 24
The bill of Collision checking quantity
NO The construction cost Reasonable 14 14ntrution plan 15/t
15 YES 25
The final construction plan
TITLE OF INVENTION
A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project
TECHNICAL FIELD
[0001] The presented invention relates to a method for engineering price computation and time-cost optimization of prefabricated building based on BIM.
BACKGROUND OF THE INVENTION
[0002] At present, with the rapid economic development and increasingly prominent environmental problems, the traditional construction industry has been criticized for its high rate of resource waste and serious environmental damage. Meanwhile, prefabricated buildings have been increasingly applied to the construction industry due to their low pollution and fast construction speed. However, the existing valuation codes of prefabricated buildings is not perfect, and the valuation method cannot meet the requirements of valuation management of prefabricated buildings. Area and volume are still the dominant measurement unit and the bill of quantities cannot reflect the fundamental component-based characteristics of prefabricated buildings. In order to pursue greater economic benefits, the optimization of project time-cost has been concerned by developer. BIM can manage the time-cost information of construction in real time, and realize the linkage between the building model and the actual time-cost data. From the perspective of construction management, this invention puts forward the valuation mode of BIM-based prefabricated building and uses BIM-GA to optimize the construction time and cost, which can strengthen the information management of the project and improve the economic benefits of construction enterprises.
SUMMARY OF INVENTION
[0003] In view of the above, the present invention provides a method for engineering price computation and time-cost optimization of prefabricated building based on BIM. The invention takes a single prefabricated component as the basic unit, optimizes the time and cost of prefabricated building, and improves the economic benefit of construction enterprises.
[0004] This invention includes: a prefabricated building pricing module and a construction time-cost optimization module.
[0005] In accordance with a first aspect of the present invention, there is provided a prefabricated building pricing module. The prefabricated building valuation module is the new bill of quantities valuation mode. The bill of quantities valuation mode standardizes the content of bill of quantities information demand, including the structure of quantities bill, the content of quantities bill and the method of quantities bill.
[0006] Further, the bill of quantities includes the primary bill of quantities, the secondary bill of quantities and the tertiary bill of quantities. The preliminary bill of quantities meets the requirements of project estimation, which is divided into construction, structure, HVAC and electrical. The second-level bill of quantities meets the requirements of the budget estimate. The third-level bill of quantities meets the requirements of working drawing budget.
[0007] Further, the content of bill of quantities includes code setting, name description, calculation rule and unit of measurement, characteristic expression and description of work content. The coding setting is used for the hierarchical coding according to the separated parts of project, and generate the list coding corresponding to the list coding rules. The name description is used to name project entities and non-entities. Calculation rules and units of measurement are used to calculate and represent the space of a single prefabricated component. Feature expression is used to describe component design requirements and functions. The working description is used to reflect the construction characteristics and processes of prefabricated building.
[0008] Further, the bill of quantities valuation mode includes the comprehensive unit price method, take a single prefabricated component as the basic unit. Each unit price includes the labor cost, material cost, machinery cost, management fee and profit of a single component.
[0009] Further, the prefabricated building pricing module includes extracting the information of prefabricated components, mapping the engineering amount with the quota database according to the pricing specification of bill of quantities, and generating the construction cost.
[0010] Further, model engineering information consists of two parts, one is the physical and geometric information of the engineering entity, mainly describing the dimension, height and area. The other is function, material type, construction technology and construction method.
[0011] In accordance with an embodiment of the present invention, the construction cost information unit connects the construction plan unit, and the cost data is used to compile the construction plan.
[0012] Further, the construction time-cost optimization module includes the establishment of the time-cost function model, preparation of the construction plan, the optimization of the original time-cost data by Genetic Algorithm, the introduction of the optimization results into BIM for collision checking, the modification of the construction plan according to the checking results, the cyclic optimization of the time-cost, and the final construction plan derived after the operation of the model.
[0013] Further, the time-cost function model includes direct cost and indirect cost, and the time is calculated to the sum of the critical path.
[0014] The preparation of the construction plan includes dividing the construction flow section, sorting the working procedure according to the project progress, and calculating the cost and time of each working procedure respectively.
[0015] MATLAB was selected as the platform of Genetic Algorithm. Float-encoding was selected as the encoding method.
BRIEF DESCRIPYION OF THE DRAWINGS
[0016] FIG.1 is a detailed block diagram of a method for engineering price computation and time-cost optimization of prefabricated building based on BIM.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0017] Hereinafter, the embodiments of the present invention will be described in detail with reference to the accompanying drawings.
[0018] Referring to FIG.1, a method for engineering price computation and time-cost optimization of prefabricated building based on BIM, including prefabricated building valuation module and construction time-cost optimization module 2.
[0019] The prefabricated building valuation module is the new bill of quantities valuation model. The bill of quantities valuation model standardize the content of bill of quantities information demand, including the structure of quantities bill, the content of quantities bill and the method of quantities bill.
[0020] The bill of quantities valuation model includes the comprehensive unit price method, take a single prefabricated component as the basic unit. Each unit price includes the labor cost, material cost, machinery cost, management fee and profit of a single component.
[0021] The prefabricated building pricing module includes extracting the information of prefabricated components 11, mapping the component amount13 with the quota databasel2, mapping component pricing information with the new bill of quantities14, and generating the construction cost15.
[0022] Model engineering information 11 consists of two parts, one is the physical and geometric information of the engineering entity, mainly describing the dimension, height and area. The other is function, material type, construction technology and construction method.
[0023] The construction cost information 15 connects the construction plan 22, and the cost data is used to construction time-cost optimization module 2.
[0024] The construction time-cost optimization module2 includes the establishment of the time-cost function model21, preparation of the construction plan22, the optimization of the original time-cost data by Genetic Algorithm23, the introduction of the optimization results into BIM for collision checking24, the modification of the construction plan according to the checking results, the cyclic optimization of the time-cost, and the final construction plan derived after the operation of the mode25.
[0025] Further, the time-cost function model includes direct cost and indirect cost, and the time is calculated to the sum of the critical path.
[0026] The preparation of the construction plan includes dividing the construction flow section, sorting the working procedure according to the project progress, and calculating the cost and time of each working procedure respectively.
[0027] MATLAB was selected as the platform of Genetic Algorithm. Float-encoding was selected as the encoding method.

Claims (5)

1. A BIM-based optimization method for the cost and construction duration of prefabricated construction project, its features include prefabricated building valuation module and construction period - cost optimization module;
2. According to the method mentioned in Claim 1, the characteristic of the prefabricated building valuation module is that it includes the following steps: deriving model engineering information according to component classification, mapping component quantity in quota database, classifying valuation norm to corresponding component quantity, and generating project cost data;
3. According to the method mentioned in claim 1, the method of construction period and cost optimization module includes the followings: setting up time-cost function model, preparing the construction plan, optimizing the genetic algorithm to the original construction cost data, importing the optimization results to BTM for a collision test, testing results according to modify the construction scheme, looping optimization time-cost model, outputting the best construction scheme;
4. According to the method mentioned in Claim 2, its feature lies in that the project cost information unit connects the cost data to prepare the construction plan unit, and the cost data is used to prepare the construction plan;
5. According to the method mentioned in Claim 2, its characteristic is that the model engineering information takes a single prefabricated component as the basic unit.
EDITORIAL NOTE 27 May 2021
2021102904
There are 2 drawings only.
AU2021102904A 2021-05-27 2021-05-27 A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project Ceased AU2021102904A4 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2021102904A AU2021102904A4 (en) 2021-05-27 2021-05-27 A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AU2021102904A AU2021102904A4 (en) 2021-05-27 2021-05-27 A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project

Publications (1)

Publication Number Publication Date
AU2021102904A4 true AU2021102904A4 (en) 2021-07-15

Family

ID=76785354

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2021102904A Ceased AU2021102904A4 (en) 2021-05-27 2021-05-27 A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project

Country Status (1)

Country Link
AU (1) AU2021102904A4 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113987644A (en) * 2021-10-26 2022-01-28 广东天元建筑设计有限公司 Engineering quantity list generation method, device, equipment and storage medium
CN117391264A (en) * 2023-12-12 2024-01-12 中建三局集团有限公司 Method, system and medium for calculating construction period quota based on BIM model

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113987644A (en) * 2021-10-26 2022-01-28 广东天元建筑设计有限公司 Engineering quantity list generation method, device, equipment and storage medium
CN117391264A (en) * 2023-12-12 2024-01-12 中建三局集团有限公司 Method, system and medium for calculating construction period quota based on BIM model
CN117391264B (en) * 2023-12-12 2024-03-19 中建三局集团有限公司 Method, system and medium for calculating construction period quota based on BIM model

Similar Documents

Publication Publication Date Title
CN111259535B (en) Method for developing logistics simulation system of ship pipeline production line
AU2021102904A4 (en) A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project
Pavlovskis et al. Application of MCDM and BIM for evaluation of asset redevelopment solutions
CN114971597B (en) BIM-based calculated amount and metering payment road cost calculation system and method
CN110533389A (en) The determination method and device of Project Cost
CN106845925A (en) Engineering based on the BIM amount of calculating quickly and project high in the clouds collaborative platform soon is to amount method
CN112862446B (en) BIM (building information modeling) intelligent engineering quantity list generation method based on feature recognition
CN107967522A (en) A kind of power grid technological transformation overhaul engineering Cost Management System and its control method
CN103268526A (en) Interval-taylor-model-based system and method for forecasting short-term load of power system
Ding et al. Construction cost management strategy based on BIM technology and neural network model
CN109064126A (en) Hydroelectric project metrical information management method based on quality driving
CN113065783A (en) BIM (building information modeling) engineering quantity application method of waste incineration power plant based on BIM technology
Jensen et al. Developing products in product platforms in the AEC industry
CN116415199B (en) Business data outlier analysis method based on audit intermediate table
CN111507760A (en) Method and system for screening reasonableness of bidding documents
CN115577424A (en) Method, device, equipment and storage medium for calculating construction engineering quantity
Kong et al. Urban building energy modeling (UBEM): a systematic review of challenges and opportunities
CN111882206B (en) Application value evaluation method for building information model used in building engineering
Sheikhkhoshkar et al. Integrating building information modelling (BIM) and system dynamics approaches to decrease cost overrun in mass housing projects
Kim et al. An analysis of the problems of BIM-based drawings and implementation during the construction document phase
CN113781011A (en) Verification method and system for project cost of power distribution network
CN103236383B (en) Dynamically determining and optimization method of plasma panel process parameters importance
KR102668849B1 (en) Automatic calculation system for quantity and construction cost of railway facility based on building information modelling (bim)
Zaki et al. BIM-based bill of quantities generator following POMI and NRM2 methods of measurement
Yu et al. Application of BIM Technology in Construction Project Cost Compilation