AU2021102904A4 - A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project - Google Patents
A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project Download PDFInfo
- Publication number
- AU2021102904A4 AU2021102904A4 AU2021102904A AU2021102904A AU2021102904A4 AU 2021102904 A4 AU2021102904 A4 AU 2021102904A4 AU 2021102904 A AU2021102904 A AU 2021102904A AU 2021102904 A AU2021102904 A AU 2021102904A AU 2021102904 A4 AU2021102904 A4 AU 2021102904A4
- Authority
- AU
- Australia
- Prior art keywords
- cost
- construction
- optimization
- prefabricated
- duration
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
- 238000010276 construction Methods 0.000 title claims abstract description 66
- 238000005457 optimization Methods 0.000 title claims abstract description 31
- 238000000034 method Methods 0.000 title claims abstract description 25
- 230000002068 genetic effect Effects 0.000 claims abstract description 8
- 238000013507 mapping Methods 0.000 claims abstract description 6
- 238000012360 testing method Methods 0.000 claims 2
- 238000007726 management method Methods 0.000 abstract description 5
- 125000004122 cyclic group Chemical group 0.000 abstract description 3
- 238000012986 modification Methods 0.000 abstract description 3
- 230000004048 modification Effects 0.000 abstract description 3
- 238000007689 inspection Methods 0.000 abstract 2
- 239000000463 material Substances 0.000 description 4
- 238000005259 measurement Methods 0.000 description 3
- 238000004364 calculation method Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 238000009430 construction management Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B13/00—Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion
- G05B13/02—Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric
- G05B13/04—Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators
- G05B13/047—Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators the criterion being a time optimal performance criterion
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06N—COMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
- G06N3/00—Computing arrangements based on biological models
- G06N3/12—Computing arrangements based on biological models using genetic models
- G06N3/126—Evolutionary algorithms, e.g. genetic algorithms or genetic programming
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Health & Medical Sciences (AREA)
- Geometry (AREA)
- Evolutionary Computation (AREA)
- Life Sciences & Earth Sciences (AREA)
- Strategic Management (AREA)
- Biophysics (AREA)
- General Engineering & Computer Science (AREA)
- Computer Hardware Design (AREA)
- Economics (AREA)
- Bioinformatics & Computational Biology (AREA)
- Tourism & Hospitality (AREA)
- General Health & Medical Sciences (AREA)
- Entrepreneurship & Innovation (AREA)
- Marketing (AREA)
- Software Systems (AREA)
- Artificial Intelligence (AREA)
- Bioinformatics & Cheminformatics (AREA)
- Evolutionary Biology (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Genetics & Genomics (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Biomedical Technology (AREA)
- Computational Linguistics (AREA)
- Data Mining & Analysis (AREA)
- Development Economics (AREA)
- Molecular Biology (AREA)
- Computing Systems (AREA)
- Primary Health Care (AREA)
- Mathematical Physics (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Physiology (AREA)
- Quality & Reliability (AREA)
Abstract
The invention relates to a BIM-based optimization method for the cost and construction period
of prefabricated construction project, including prefabricated building valuation module and
construction duration to cost optimization module. The prefabricated building valuation module
includes extracting the information of model components, mapping the engineering quantity of
components in accordance with the list mapping rules, and generating the engineering cost data.
The construction duration to cost optimization module includes the establishment of the
duration-cost function model, the optimization of the original duration-cost data by genetic
algorithm, the introduction of the optimization results into BIM for collision inspection, the
modification of the construction plan according to the inspection results, the cyclic optimization
of the duration-cost, and the final construction plan derived after the operation of the model. The
solution provided by the invention can realize the information management of prefabricated
building and better carry out the project cost work and construction scheme planning.
1/1
DRAWING
2 1 The bill of quantities valuation module construction time-cost optimization module
The time-cost function 21
11 model
Extract the information 22
of prefabricated Preparation of the
components construction plan
12 13
The quota Map the component Genetic
Algorithm optimize
database o amount with the quota
the original time-cost data
database 24
The bill of Collision checking
quantity
NO
The construction cost Reasonable
14ntrution plan 14
15/t
15 YES 25
The final construction
plan
Description
1/1 DRAWING
1 The bill of quantities valuation module construction time-cost optimization module 2
The time-cost function 21 11 model
Extract the information 22 of prefabricated Preparation of the components construction plan 12 13
Map the component Genetic Algorithm optimize The quota o amount with the quota the original time-cost data database database 24
The bill of Collision checking quantity
NO The construction cost Reasonable 14 14ntrution plan 15/t
15 YES 25
The final construction plan
A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project
[0001] The presented invention relates to a method for engineering price computation and time-cost optimization of prefabricated building based on BIM.
[0002] At present, with the rapid economic development and increasingly prominent environmental problems, the traditional construction industry has been criticized for its high rate of resource waste and serious environmental damage. Meanwhile, prefabricated buildings have been increasingly applied to the construction industry due to their low pollution and fast construction speed. However, the existing valuation codes of prefabricated buildings is not perfect, and the valuation method cannot meet the requirements of valuation management of prefabricated buildings. Area and volume are still the dominant measurement unit and the bill of quantities cannot reflect the fundamental component-based characteristics of prefabricated buildings. In order to pursue greater economic benefits, the optimization of project time-cost has been concerned by developer. BIM can manage the time-cost information of construction in real time, and realize the linkage between the building model and the actual time-cost data. From the perspective of construction management, this invention puts forward the valuation mode of BIM-based prefabricated building and uses BIM-GA to optimize the construction time and cost, which can strengthen the information management of the project and improve the economic benefits of construction enterprises.
[0003] In view of the above, the present invention provides a method for engineering price computation and time-cost optimization of prefabricated building based on BIM. The invention takes a single prefabricated component as the basic unit, optimizes the time and cost of prefabricated building, and improves the economic benefit of construction enterprises.
[0004] This invention includes: a prefabricated building pricing module and a construction time-cost optimization module.
[0005] In accordance with a first aspect of the present invention, there is provided a prefabricated building pricing module. The prefabricated building valuation module is the new bill of quantities valuation mode. The bill of quantities valuation mode standardizes the content of bill of quantities information demand, including the structure of quantities bill, the content of quantities bill and the method of quantities bill.
[0006] Further, the bill of quantities includes the primary bill of quantities, the secondary bill of quantities and the tertiary bill of quantities. The preliminary bill of quantities meets the requirements of project estimation, which is divided into construction, structure, HVAC and electrical. The second-level bill of quantities meets the requirements of the budget estimate. The third-level bill of quantities meets the requirements of working drawing budget.
[0007] Further, the content of bill of quantities includes code setting, name description, calculation rule and unit of measurement, characteristic expression and description of work content. The coding setting is used for the hierarchical coding according to the separated parts of project, and generate the list coding corresponding to the list coding rules. The name description is used to name project entities and non-entities. Calculation rules and units of measurement are used to calculate and represent the space of a single prefabricated component. Feature expression is used to describe component design requirements and functions. The working description is used to reflect the construction characteristics and processes of prefabricated building.
[0008] Further, the bill of quantities valuation mode includes the comprehensive unit price method, take a single prefabricated component as the basic unit. Each unit price includes the labor cost, material cost, machinery cost, management fee and profit of a single component.
[0009] Further, the prefabricated building pricing module includes extracting the information of prefabricated components, mapping the engineering amount with the quota database according to the pricing specification of bill of quantities, and generating the construction cost.
[0010] Further, model engineering information consists of two parts, one is the physical and geometric information of the engineering entity, mainly describing the dimension, height and area. The other is function, material type, construction technology and construction method.
[0011] In accordance with an embodiment of the present invention, the construction cost information unit connects the construction plan unit, and the cost data is used to compile the construction plan.
[0012] Further, the construction time-cost optimization module includes the establishment of the time-cost function model, preparation of the construction plan, the optimization of the original time-cost data by Genetic Algorithm, the introduction of the optimization results into BIM for collision checking, the modification of the construction plan according to the checking results, the cyclic optimization of the time-cost, and the final construction plan derived after the operation of the model.
[0013] Further, the time-cost function model includes direct cost and indirect cost, and the time is calculated to the sum of the critical path.
[0014] The preparation of the construction plan includes dividing the construction flow section, sorting the working procedure according to the project progress, and calculating the cost and time of each working procedure respectively.
[0015] MATLAB was selected as the platform of Genetic Algorithm. Float-encoding was selected as the encoding method.
[0016] FIG.1 is a detailed block diagram of a method for engineering price computation and time-cost optimization of prefabricated building based on BIM.
[0017] Hereinafter, the embodiments of the present invention will be described in detail with reference to the accompanying drawings.
[0018] Referring to FIG.1, a method for engineering price computation and time-cost optimization of prefabricated building based on BIM, including prefabricated building valuation module and construction time-cost optimization module 2.
[0019] The prefabricated building valuation module is the new bill of quantities valuation model. The bill of quantities valuation model standardize the content of bill of quantities information demand, including the structure of quantities bill, the content of quantities bill and the method of quantities bill.
[0020] The bill of quantities valuation model includes the comprehensive unit price method, take a single prefabricated component as the basic unit. Each unit price includes the labor cost, material cost, machinery cost, management fee and profit of a single component.
[0021] The prefabricated building pricing module includes extracting the information of prefabricated components 11, mapping the component amount13 with the quota databasel2, mapping component pricing information with the new bill of quantities14, and generating the construction cost15.
[0022] Model engineering information 11 consists of two parts, one is the physical and geometric information of the engineering entity, mainly describing the dimension, height and area. The other is function, material type, construction technology and construction method.
[0023] The construction cost information 15 connects the construction plan 22, and the cost data is used to construction time-cost optimization module 2.
[0024] The construction time-cost optimization module2 includes the establishment of the time-cost function model21, preparation of the construction plan22, the optimization of the original time-cost data by Genetic Algorithm23, the introduction of the optimization results into BIM for collision checking24, the modification of the construction plan according to the checking results, the cyclic optimization of the time-cost, and the final construction plan derived after the operation of the mode25.
[0025] Further, the time-cost function model includes direct cost and indirect cost, and the time is calculated to the sum of the critical path.
[0026] The preparation of the construction plan includes dividing the construction flow section, sorting the working procedure according to the project progress, and calculating the cost and time of each working procedure respectively.
[0027] MATLAB was selected as the platform of Genetic Algorithm. Float-encoding was selected as the encoding method.
Claims (5)
1. A BIM-based optimization method for the cost and construction duration of prefabricated construction project, its features include prefabricated building valuation module and construction period - cost optimization module;
2. According to the method mentioned in Claim 1, the characteristic of the prefabricated building valuation module is that it includes the following steps: deriving model engineering information according to component classification, mapping component quantity in quota database, classifying valuation norm to corresponding component quantity, and generating project cost data;
3. According to the method mentioned in claim 1, the method of construction period and cost optimization module includes the followings: setting up time-cost function model, preparing the construction plan, optimizing the genetic algorithm to the original construction cost data, importing the optimization results to BTM for a collision test, testing results according to modify the construction scheme, looping optimization time-cost model, outputting the best construction scheme;
4. According to the method mentioned in Claim 2, its feature lies in that the project cost information unit connects the cost data to prepare the construction plan unit, and the cost data is used to prepare the construction plan;
5. According to the method mentioned in Claim 2, its characteristic is that the model engineering information takes a single prefabricated component as the basic unit.
EDITORIAL NOTE 27 May 2021
2021102904
There are 2 drawings only.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2021102904A AU2021102904A4 (en) | 2021-05-27 | 2021-05-27 | A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2021102904A AU2021102904A4 (en) | 2021-05-27 | 2021-05-27 | A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project |
Publications (1)
Publication Number | Publication Date |
---|---|
AU2021102904A4 true AU2021102904A4 (en) | 2021-07-15 |
Family
ID=76785354
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
AU2021102904A Ceased AU2021102904A4 (en) | 2021-05-27 | 2021-05-27 | A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project |
Country Status (1)
Country | Link |
---|---|
AU (1) | AU2021102904A4 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113987644A (en) * | 2021-10-26 | 2022-01-28 | 广东天元建筑设计有限公司 | Engineering quantity list generation method, device, equipment and storage medium |
CN117391264A (en) * | 2023-12-12 | 2024-01-12 | 中建三局集团有限公司 | Method, system and medium for calculating construction period quota based on BIM model |
-
2021
- 2021-05-27 AU AU2021102904A patent/AU2021102904A4/en not_active Ceased
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113987644A (en) * | 2021-10-26 | 2022-01-28 | 广东天元建筑设计有限公司 | Engineering quantity list generation method, device, equipment and storage medium |
CN117391264A (en) * | 2023-12-12 | 2024-01-12 | 中建三局集团有限公司 | Method, system and medium for calculating construction period quota based on BIM model |
CN117391264B (en) * | 2023-12-12 | 2024-03-19 | 中建三局集团有限公司 | Method, system and medium for calculating construction period quota based on BIM model |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111259535B (en) | Method for developing logistics simulation system of ship pipeline production line | |
AU2021102904A4 (en) | A BIM-Based Optimization Method of Construction Cost and Construction Duration-Cost of Prefabricated Construction Project | |
Pavlovskis et al. | Application of MCDM and BIM for evaluation of asset redevelopment solutions | |
CN114971597B (en) | BIM-based calculated amount and metering payment road cost calculation system and method | |
CN110533389A (en) | The determination method and device of Project Cost | |
CN106845925A (en) | Engineering based on the BIM amount of calculating quickly and project high in the clouds collaborative platform soon is to amount method | |
CN112862446B (en) | BIM (building information modeling) intelligent engineering quantity list generation method based on feature recognition | |
CN107967522A (en) | A kind of power grid technological transformation overhaul engineering Cost Management System and its control method | |
CN103268526A (en) | Interval-taylor-model-based system and method for forecasting short-term load of power system | |
Ding et al. | Construction cost management strategy based on BIM technology and neural network model | |
CN109064126A (en) | Hydroelectric project metrical information management method based on quality driving | |
CN113065783A (en) | BIM (building information modeling) engineering quantity application method of waste incineration power plant based on BIM technology | |
Jensen et al. | Developing products in product platforms in the AEC industry | |
CN116415199B (en) | Business data outlier analysis method based on audit intermediate table | |
CN111507760A (en) | Method and system for screening reasonableness of bidding documents | |
CN115577424A (en) | Method, device, equipment and storage medium for calculating construction engineering quantity | |
Kong et al. | Urban building energy modeling (UBEM): a systematic review of challenges and opportunities | |
CN111882206B (en) | Application value evaluation method for building information model used in building engineering | |
Sheikhkhoshkar et al. | Integrating building information modelling (BIM) and system dynamics approaches to decrease cost overrun in mass housing projects | |
Kim et al. | An analysis of the problems of BIM-based drawings and implementation during the construction document phase | |
CN113781011A (en) | Verification method and system for project cost of power distribution network | |
CN103236383B (en) | Dynamically determining and optimization method of plasma panel process parameters importance | |
KR102668849B1 (en) | Automatic calculation system for quantity and construction cost of railway facility based on building information modelling (bim) | |
Zaki et al. | BIM-based bill of quantities generator following POMI and NRM2 methods of measurement | |
Yu et al. | Application of BIM Technology in Construction Project Cost Compilation |