AU2001262494B2 - Pile driving - Google Patents

Pile driving Download PDF

Info

Publication number
AU2001262494B2
AU2001262494B2 AU2001262494A AU2001262494A AU2001262494B2 AU 2001262494 B2 AU2001262494 B2 AU 2001262494B2 AU 2001262494 A AU2001262494 A AU 2001262494A AU 2001262494 A AU2001262494 A AU 2001262494A AU 2001262494 B2 AU2001262494 B2 AU 2001262494B2
Authority
AU
Australia
Prior art keywords
pile
guide
finned
pair
substrate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
AU2001262494A
Other versions
AU2001262494A1 (en
Inventor
Clive Jones
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHC Sea Steel Ltd
Original Assignee
IHC Sea Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from GB0013136A external-priority patent/GB0013136D0/en
Priority claimed from GB0105843A external-priority patent/GB0105843D0/en
Application filed by IHC Sea Steel Ltd filed Critical IHC Sea Steel Ltd
Publication of AU2001262494A1 publication Critical patent/AU2001262494A1/en
Application granted granted Critical
Publication of AU2001262494B2 publication Critical patent/AU2001262494B2/en
Assigned to IHC SEA STEEL LIMITED reassignment IHC SEA STEEL LIMITED Request for Assignment Assignors: FAST FRAMES (UK) LIMITED
Anticipated expiration legal-status Critical
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/02Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers specially adapted for placing or removing bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)
  • Transition And Organic Metals Composition Catalysts For Addition Polymerization (AREA)
  • Seal Device For Vehicle (AREA)

Abstract

A pile guide (20) comprises a base frame (22) and a guide member (24) mounted in the base frame (22). The guide member (24) comprises a pair of upright guide channels (30) for receiving and guiding a pair of stabilizing fins associated with a finned pile during pile driving. A finned pile follower is also provided for continued pile driving once the finned pile is embedded in the substrate. The finned pile follower has a pair of stabilizing fins which likewise are received and guided in the guide channels (30).

Description

WO 01/92645 PCT/GB01/02389 1 TITLE: PILE DRIVING BACKGROUND OF THE INVENTION FIELD OF THE INVENTION The invention relates to pile driving, and more particularly, but not exclusively, to underwater pile driving, e.g. for stabbing piles directly into the seabed.
DESCRIPTION OF THE BACKGROUND ART It is known to provide a guide for aligning a pile with the surface of a substrate into which the pile is to be driven and to provide stability for a piling hammer.
Particularly when piling underwater there is the problem that after the pile has been introduced into the seabed or the like, the guide must be removed to allow the pile to be driven into its final position. This guide removal is time consuming and thus expensive. Accordingly, the present applicant proposed in International patent CONFIRMATION COPY WO 01/92645 PCT/GB01/02389 2 publication W099/11872 a pile guide which allows pile driving to continue from start to finish without any need to interrupt driving to remove the guide.
The pile driving apparatus described in W099/11872 is supported on a base frame, a plan view of which is reproduced in Figure 1. The base frame 10 has a substantially rectangular footprint (made up of a welded framework of girders and mudmats) with a centrally-placed aperture (12) through which a pile (14) is guided. The base frame 10 thus surrounds the pile It will be seen however, that the base frame is formed with an aperture or slot (16) extending through the frame from its exterior to the central aperture (12) and through which a tether or rigging (18) fixed to the pile (14) can be passed.
The present applicant has appreciated certain problems associated with transporting a pile guide of the kind shown in W099/11872. The rectangular footprint of the base frame may have an area exceeding 100m2, effectively ruling out all forms of transport other than by sea. The present applicant has sought to obviate or at least alleviate such problems.
SUMMARY OF THE INVENTION In accordance with the present invention, there is provided a pile guide for supporting a pile as it is driven into a substrate, comprising a base frame and a pile guide member mounted on the base frame characterised in that the base frame comprises a rigid member, WO 01/92645 PCT/GB01/02389 3 preferably substantially U-shaped and at least one groundengaging panel releasably coupled to the rigid member.
Advantageously, the releasable coupling between the U-shaped member and the at least one ground engaging panel enables the pile guide to be transported in more than one piece to the site where it will be used. This fact overcomes dependence on transport by sea alone, since each piece may be moved, for example, by road, albeit with a police escort if required. Such improved transportability is important since it is in the very nature of pile driving that the pile guide must be moved from site to site if it is to be reused.
The substantially U-shaped rigid member may support the pile guide member. The rigid member has a central aperture through which a pile guided by the pile guide member may be driven. Being substantially U-shaped, there is a channel, communicating with the central aperture, through which a tether or rigging fixed to a pile may pass in order to disengage the pile guide from the pile once driven into the substrate. The present applicant has appreciated that the U-shaped rigid member is the backbone of the pile guide, having to withstand the stresses of supporting the pile guide member even during pile driving.
The pile guide member may be of conventional form an immobile channel adapted to receive slidingly a pile to be driven into the substrate) or of improved form of two part and pivotable construction, each part being adapted to pivot away from the pile once partially driven WO 01/92645 PCT/GB01/02389 4 into the seabed, see W099/11872).
The at least one ground-engaging panel, or mudmat, may extend laterally of the substantially U-shaped rigid member. The at least one ground-engaging panel may be releasably coupled to the rigid member by a plurality of bolts.
The base frame may include a pair of ground-engaging panels, releasably coupled one per opposing side of the substantially U-shaped rigid member. Each ground- engaging panel may extend laterally of the respective side of the U-shaped rigid member to which it is releasably coupled.
The at least one substrate-engaging panel or the substantially U-shaped rigid member may comprise receptors for engagement by fork means of a fork-lift truck. The receptors may comprise a pair of flanges which project laterally such that their undersides are contactable by the fork means of a fork-lift truck. Each flange may form part of a channel, either of open- or closed-box construction. The pile guide may further comprise means for attaching lifting lines ropes or cables) to the base frame. The attaching means may be selected from the group consisting of hooks, rings and apertures.
The substantially U-shaped rigid member and the at least one substrate-engaging panel may include location means for secure stacking of one on top of the other. The location means may comprise complementary profiles which enable one to nest against the other.
In accordance with another aspect of the present WO 01/92645 PCT/GB01/02389 invention, there is provided a pile guide for supporting a finned pile as it is driven into a substrate, comprising a base frame and a guide member mounted on the base frame, characterised in that the guide member comprises a pair of upright guide channels for receiving and guiding a pair of stabilising fins associated with a finned pile during pile driving.
The present applicant has appreciated that the use of such a pile guide with finned piles has a number of significant advantages. Firstly, there may be sufficient clearance space between the pair of guide channels to enable finned piles to be driven fully into the seabed in one operation. With conventional pile guides and conventional piles, the pile driving operation needed to be interrupted to remove the pile guide before the pile could be driven all the way into the seabed. Secondly, for a given size of pile, the finned piles are anchored more securely to the seabed than conventional piles because of the lateral resistance to movement offered by the fins in silty layers above underlying hard layers.
Thus, in order to achieve an anchorage with specific lateral loading resistance against tip rotation, finned piles of a smaller diameter than conventional piles may be used. The use of more lightweight finned piles enables a consequential reduction in the build specification of the corresponding pile guide; leading to cost savings in terms of both materials and transportation considerations.
A third and potentially more significant advantage WO 01/92645 PCT/GB01/02389 6 arises from the flexibility of using a pile guide which guides fins associated with a pile, rather than the main body of the pile. Provided the fins achieve a given "wing span", variable diameter piles may be supported by the same pile guide. This in turn has a knock-on benefit of speeding up pile driving a set of finned piles of different sizes, since the same guide may be used for each.
In one embodiment, the pair of upright guide channels may be positioned opposite each other, with channel openings facing each other. In this way, the guide channels are configured to receive a finned pile having a pair of diametrically opposed stabilising fins extending in an axial direction along the curved periphery of the pile. The upright guide channels may be supported by inclined struts extending from an outer periphery of the base frame.
In accordance with yet another aspect of the present invention, there is provided apparatus for driving a pile into a substrate, comprising a pile follower for transmitting impact from a pile driver to a pile being driven into a substrate, wherein the pile follower has a pair of fins for engaging corresponding guide channels of a pile guide.
When pile driving below water level, a pile may be part-driven into a substrate seabed) with the aid of a pile guide. Once one end of the pile is embedded in the sea floor, a follower can be fitted to the exposed end of WO 01/92645 PCT/GB01/02389 7 the pile. In order to transmit pile hammer impacts squarely to the pile in such a way as to drive the pile vertically, the follower has traditionally been machined to very tight tolerances which is expensive with such a large object. However, by providing a pair of fins, the follower can be guided in the same way as a finned pile.
In this way, the need for accurate machinery is substantially reduced.
The pair of fins may extend in a common plane to engage diametrically opposed guide channels of the pile guide. The pile follower may have an end profile comprising a driving face and an alignment member projecting axially beyond the driving face. The alignment member aids registration of the driving face with the exposed end of the pile by providing a positive locating action therewith. The alignment member may be configured to engage the radially inner periphery of a tubular pile.
The alignment member may comprise a plurality of plates arranged around the radially inner or outer periphery of the pile follower.
The apparatus may further comprise a pile guide in accordance with earlier aspects and embodiments of the present invention.
BRIEF DESCRIPTION OF THE DRAWINGS Embodiments of the invention will now be described by way of example with reference to the accompanying drawings in which: Figure 1 is a plane view of a prior art base frame; WO 01/92645 PCT/GB01/02389 8 Figure 2 is a plane view of a pile guide embodying one aspect of the present invention; Figure 3 is a front view of the pile guide of Figure 2; Figure 4 is a perspective exploded view showing base frame detail of the pile guide of Figure 2; Figure 5 is a schematic front view of a finned follower embodying another aspect of the present invention; and Figure 6 is a partial cross-sectional view along A-A in Figure 5 showing detail of the finned follower.
DESCRIPTION OF EMBODIMENTS OF THE INVENTION Figures 2 and 3 show plan and front view respectively of a pile guide (20) embodying the present invention. The pile guide (20) comprises a base frame (22) and a pile guide member (24) mounted on the base frame The base frame (22) comprises a generally U-shaped rigid member (26) and a pair of substrate-engaging panels or mudmats (28) which are releasably coupled to the rigid member The pile guide member (27) comprises a pair of upright guide channels (30) mounted on the rigid member (26) and supported by inclined struts (32) extending from the peripheral corners of the base frame The pile guide (20) may be dismantled to improve ease of transportation, and, in particular, the base frame (22) constituents may be decoupled into three more manageable pieces, namely two mudmats (28) and the rigid member (26).
Figure 4 illustrates the construction of the base WO 01/92645 PCT/GB01/02389 9 frame (22) in more detail. The generally U-shaped rigid member (26) forms the backbone of the structure and is also fundamental to the operation of the pile guide The rigid member not only provides the points of anchorage for the pile guiding member (24) and -nudma:s but also defines a central aperture (40) through which a pile is driven into the substrate. Thereafter, the base frame (22) may be disengaged from around the pile by moving the base frame (22) to pass the pile through channel or peripheral opening the peripheral opening having a span which exceeds the diameter of the pile. The mudmats (28) are bolted to, and extend laterally of the sides (44) of the rigid member. Thus, in use, the base frame (22) may have a footprint covering something in excess of 100m 2 However, when being stored or in transit to the pile driving site, the mudmats (28) may be detached from the rigid member (26) to reduce the overall area which must be made available to accommodate the pile guide.
As shown in Figure 4, the sides of the rigid member (26) and mudmats (28) are provided with receptors (50) for receiving the forks of fork-lift trucks. The receptors comprise a pair of flanges (52) forming an open channel into which the prongs of a fork-lift may be inserted. The uppermost flange in each pair then bears the weight of the component during lifting. Padeyes are also provided at the corners of the rigid member (26) for attaching lifting lines cables) and thereby lifting the base frame (22).
WO 01/92645 PCT/GB01/02389 The pile guide member (24) illustrated in Figures 2 and 3 is just one of several different designs which could be used in combination with the base frame For example, the pile guide member (24) could be replaced by a pivoting/counterweighted arrangement as described in W099/11872, the whole contents of which are incorporated herein by reference. Nonetheless, for completeness, the pile guide member (24) will now be described in detail.
The pile guide member (24) is adapted to guide a pile having a pair of diametrically opposed stabilising fins extending in an axial direction along the curved periphery of the pile. The pair of upright guide channels (30) are positioned opposite each other with channel openings facing each other. In this way, the channels receive and guide the stabilising fins during pile driving. Once the pile has been driven into the substrate seabed) the pile guide (20) may be lifted over the protuberant part of the pile to disengage the stabilising fins from the pile guide member. Of course, if the stabilising fins have been driven into the substrate, the upright guide channels no longer engage the pile, and the pile guide (20) may disengage the pile by sliding the pile guide (20) to pass the pile through the opening (42).
Figures 5 and 6 show a pile follower (100) embodying another aspect of the present invention. The pile follower (100) is illustrated in use between a pile driving hammer (102) and a finned pile (104), both of which are shown in phantom lines. The pile follower (100) WO 01/92645 PCT/GB01/02389 I1 has a pair of diametrically opposed fins (106) which are configured to be a sliding fit inside the guide channels of pile guide The pile follower (100) has an end profile (110) comprising a driving face (112) and an alignment ring (114). The alignment ring (114) comprises a plurality of members (116) which extend axially beyond the driving face (112). The alignment ring (114) is a snug fit inside the bore (118) of the finned pile (104) to achieve registration between the driving face (112) and the exposed end of the finned pile (104).
The operation of the pile guide the finned pile (104) and the pile follower (100) will now be described to illustrate the interaction therebetween. The pile guide is positioned on a substrate seabed) and finned pile (104) is loaded into the pile guide (20) with its fins slidingly received in the upright guide channels The finned pile (104) is driven into the seabed as far as the reciprocating motion of the drive hammer (102) will allow. The drive hammer (102) is then raised clear of the exposed end of the finned pile (104) so that follower (100) may be fitted to it. The fins (106) of the follower (100) are aligned with those of the pile (104) so that the fins (106) are slidably received in the guide channels The alignment ring (114) engages the bore of the finned pile (104) as the latter is lowered into position, ensuring that the driving face (112) of the follower (100) registers with and abuts the end of the finned pile. The hammer (102) is then re-engaged, with WO 01/92645 PCT/GB01/02389 the follower (100) now transmitting impact to the finned pile (104).

Claims (1)

  1. 22-05-2002,. GBO1 02389 1. A pile Iguide (20' for' suprigaa ti driven into a substrate by a pile driver, comprising a base framTe (22) and a guide men~per mnounted on the base f rame (22) and conf igured to, guide a pile as it is. driven. into the substrate, characte3 ised in that the guide member (24) comprises a pair of Iupright guide channels configured to receiive and guide a.-pair .of stabilising fins of a finned pile during pile driving. 2. -A pile 'guide' (20) according' to claim 1, in which the uprigrht. guide. channels (30) are positioned opposite each other, with 6hannel openings.iacing each other.' 3. A pil .e guide (20) according to claim 1 or claim 2, in which the upright guide channels (30) are supported by inclined struts e-xtendin-g from. an outer periphery of' the base fracfie (22). 4. Apparatus for dT-rving a pile into a substrate, comprising a-pile guide (20) laccording to any one of claims I to 3, and 'a pile follower:1 (100) for. transiuittina impact from a pile driver to a pile Ibeing driven into a substrate, the pile follower (100) having a pair of fins (106) configured t'p slidably enga Te the pair of upright guide *channel~s (30)*-of the pile guide Apparatus according to 6z1aimn 4,F in which the pair of fins (106) exktend in a commoniplane. 6. Apparatus according to claim 4 or claim 5, in which the pile follower (100) has adn enda prbfile (110) comprising diigfc (12 fo gaging a pile and an alignment. E agAMENDED SHEET 22-05-2002.G O028 14 mnember (114)i projecting axi Llly beyond the drivingface (112) for aligz ing the' drivi'ng face (112) with a pile. 7. Apparat~is according to dlaim 6, in which the alignment member (3.14) 1 sannular. 8. Apparati s according to claim 7, in which the alignment member (3.14) Qcomprlses a plutality, of plates (116) ar'ranged in a ring. 9.A Method of driving a finned pile int6 a- substrate, comprising: providi~g a pile guidel (20) copiiga base frame (22) and a ;guide member (24) jmounted on the base frame (22)- and configurpd. to guide a p i.1e as it is driven into the substrate, the guide member 1(24) having a pair of -upright guide ohanfiels (30) conffigur-ed to receive and guide a pair of stabilisizig fins of a finned pile; positioning a finned pille (104)- in -the pile gFuide wihthe fin's sialengngthe upright guide channels~ and pile driving the finned pile (104) into the substrate. 10. A method 'according to claim' 9, further comprising: interruptin pile dii fittuingia pile follower 1(100) to ani exposed end of the. finned pile, :the-pile follower (100) having a pair of fins 6) which lidably engage the upight guide channels of the pile !guide and further'pile driving the finned pile ()104) into the substrate, using the pile follower (100) to transmit iimpact to the finned pile. Empfanga AMENDED SHEET
AU2001262494A 2000-05-31 2001-05-30 Pile driving Expired AU2001262494B2 (en)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
GB0013136.7 2000-05-31
GB0013136A GB0013136D0 (en) 2000-05-31 2000-05-31 Pile driving
GB0105843.7 2001-03-09
GB0105843A GB0105843D0 (en) 2001-03-09 2001-03-09 Pile driving
PCT/GB2001/002389 WO2001092645A2 (en) 2000-05-31 2001-05-30 Pile driving

Publications (2)

Publication Number Publication Date
AU2001262494A1 AU2001262494A1 (en) 2002-02-28
AU2001262494B2 true AU2001262494B2 (en) 2005-06-02

Family

ID=26244385

Family Applications (2)

Application Number Title Priority Date Filing Date
AU6249401A Pending AU6249401A (en) 2000-05-31 2001-05-30 Pile driving
AU2001262494A Expired AU2001262494B2 (en) 2000-05-31 2001-05-30 Pile driving

Family Applications Before (1)

Application Number Title Priority Date Filing Date
AU6249401A Pending AU6249401A (en) 2000-05-31 2001-05-30 Pile driving

Country Status (6)

Country Link
EP (1) EP1285138B1 (en)
AT (1) ATE272752T1 (en)
AU (2) AU6249401A (en)
CA (1) CA2409694C (en)
DE (1) DE60104681T2 (en)
WO (1) WO2001092645A2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0524825D0 (en) 2005-12-06 2006-01-11 Fast Frames Uk Ltd Pile driving
GB2473683B (en) 2010-01-05 2012-01-11 Fast Frames Uk Ltd Method and apparatus for driving a pile into a substrate
GB201104612D0 (en) 2011-03-18 2011-05-04 Fast Frames Uk Ltd Method and apparatus for driving a pile into a substrate
GB201106783D0 (en) 2011-04-21 2011-06-01 Fast Frames Uk Ltd Method and apparatus for driving a pile into a substrate
GB201119340D0 (en) 2011-11-09 2011-12-21 Fast Frames Uk Ltd
NL2009610C2 (en) 2012-10-11 2014-04-14 Ihc Sea Steel Ltd Pile driving guide.
NL2010375C2 (en) 2013-02-28 2014-09-01 Ihc Sea Steel Ltd Pile driving guide.
NL2017560B1 (en) 2016-09-30 2018-04-10 Ihc Iqip Uk Ltd Pile guide comprising a base frame and a guide member

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202814C (en) *
US1359956A (en) * 1919-04-15 1920-11-23 Lackawanna Steel Co Pile-follower
US5104264A (en) * 1989-03-23 1992-04-14 Bernard Castagner System for driving anchors in the ground
WO1999011872A1 (en) * 1997-08-28 1999-03-11 Fast Frames (Uk) Limited Pile driving

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2678011B1 (en) * 1991-06-19 1993-11-05 Christian Badaroux SIMPLIFIED PYROTECHNIC DEVICE FOR LANDING MICRO-PILES INTO THE GROUND.

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202814C (en) *
US1359956A (en) * 1919-04-15 1920-11-23 Lackawanna Steel Co Pile-follower
US5104264A (en) * 1989-03-23 1992-04-14 Bernard Castagner System for driving anchors in the ground
WO1999011872A1 (en) * 1997-08-28 1999-03-11 Fast Frames (Uk) Limited Pile driving

Also Published As

Publication number Publication date
CA2409694A1 (en) 2001-12-06
EP1285138B1 (en) 2004-08-04
EP1285138A2 (en) 2003-02-26
DE60104681T2 (en) 2005-08-11
WO2001092645A2 (en) 2001-12-06
ATE272752T1 (en) 2004-08-15
WO2001092645A3 (en) 2002-04-25
DE60104681D1 (en) 2004-09-09
AU6249401A (en) 2001-12-11
CA2409694C (en) 2009-12-15

Similar Documents

Publication Publication Date Title
AU2001262494B2 (en) Pile driving
EP1007792B1 (en) Pile guide
EP2557232B1 (en) A pile driving assembly
CN103103987B (en) Combined steel plate pile construction guide frame and construction method of combined steel plate pile
AU2001262494A1 (en) Pile driving
US6994493B2 (en) Pile driving system and pile for engagement with said system
AU2012288595B2 (en) Pile guide
EP1304415B1 (en) Pile guide
US6368023B1 (en) Jack-in piling systems' apparatus and their method of use
ZA200207630B (en) Pile driving.
CN102587377B (en) Drop hammer type pile sinking device and pile sinking method thereof
CN210395482U (en) Swing platform truck spud pile device
CN210917364U (en) Steel pipe pile positioning platform for crane ship
JPS61242205A (en) Carrying and building method
CN211171969U (en) Pile pressing and hammer combined type tubular pile construction equipment
NL2019065B1 (en) Pile guide
CN113718810B (en) Sinking-assisting construction method for open caisson
EP0192481B1 (en) Transportation and construction method
CN217839995U (en) Pile pulling platform is demolishd to self-navigation jack-up lifting formula support on water
JP2021070949A (en) Pile support structure and construction method thereof
US20230294964A1 (en) Mobile crane having a counterweight device
CN114960543A (en) Construction method of jacket structure wharf
JP2003239302A (en) Length adjusting device of mooring wire
CN117926811A (en) Device suitable for sinking and ultra-long pile driver of steel pipe piles with different diameters and construction method thereof
JPH0227020A (en) Pile driver

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)
PC Assignment registered

Owner name: IHC SEA STEEL LIMITED

Free format text: FORMER OWNER WAS: FAST FRAMES (UK) LIMITED

MK14 Patent ceased section 143(a) (annual fees not paid) or expired