AT402546B - Method and apparatus for laying underground pipelines at an accurate gradient - Google Patents

Method and apparatus for laying underground pipelines at an accurate gradient Download PDF

Info

Publication number
AT402546B
AT402546B AT183595A AT183595A AT402546B AT 402546 B AT402546 B AT 402546B AT 183595 A AT183595 A AT 183595A AT 183595 A AT183595 A AT 183595A AT 402546 B AT402546 B AT 402546B
Authority
AT
Austria
Prior art keywords
pipeline
pipe
borehole
pipe sections
supporting liquid
Prior art date
Application number
AT183595A
Other languages
German (de)
Other versions
ATA183595A (en
Original Assignee
Drill Gesteuerte Bohrtechnik G
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Drill Gesteuerte Bohrtechnik G filed Critical Drill Gesteuerte Bohrtechnik G
Priority to AT183595A priority Critical patent/AT402546B/en
Publication of ATA183595A publication Critical patent/ATA183595A/en
Application granted granted Critical
Publication of AT402546B publication Critical patent/AT402546B/en

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

In order to lay underground pipelines 1, the hole in the ground 2 is first of all produced along the predetermined pipeline run and the drilled hole 3 is, if necessary, expanded before the pipeline 1, which may be composed of individual pipe sections 4, is inserted into the hole in the ground 2 while a curing supporting liquid 10 is at the same time used for backfilling. In order to achieve a pipeline run with an accurate gradient in an economic manner in this way, the relative densities of the pipeline 1, or of the pipe sections 4, and of the supporting liquid 10 are matched to one another and, after being pulled in, the pipeline 1 is secured in the correct position at both ends and is then subjected to internal pressure in order to align it by stretching. <IMAGE>

Description

       

   <Desc/Clms Page number 1> 
 



   Die Erfindung bezieht sich auf ein Verfahren zum neigungsgenauen Verlegen unterirdische   Rohrleitun-   gen, bel dem zuerst entlang dem vorbestimmten Leitungsverlauf eine Bodenbohrung hergestellt und 
 EMI1.1 
 



   Zum Herstellen von Bohrlöchern für das untenrdlsche Verlegen von Rohrleitungen od. dgl sind bereits verschiedene Bohrverfahren, sogenannte   Honzontalbohrverfahren   bekannt, bel denen meist eine Bohrspülung und ein verlaufsgesteuerter Bohrkopf eingesetzt werden und die mit ausreichender Richtungsgenauigkeit das Bohren entsprechender Bohrlöcher längs einem durch die Planvorgabe vorbestimmten Leitungsverlauf erlauben.

   Das eigentliche Verlegen der aus einzelnen Rohrschüssen zusammengesetzten   Rohrlei-   tungen erfolgt dann durch das Einziehen des sich   schussweise   auf Grund des zugfesten   Anemanderrelhens   der Rohrschüsse verlängernden Rohrstranges in die Bodenbohrung, wobei auch schon vorgeschlagen wurde, zur Erleichterung dieses Rohreinzuges eine Stützflüssigkeit In das Bohrloch zu pumpen, um einerseits während des Einziehens die   Reibungs- und Bewegungsverhältnisse beeinflussen   zu können und anderseits nach dem Rohrleitungseinzug durch das Erhärten der Stützflüssigkeit gleich eine den Rmgraum zwischen Rohrleitung und Bohrlochwandung ausfüllende Bettung der Rohrleitung zu erhalten.

   Da es für die Rohrverlegung notwendig ist, die Bodenbohrung mit einem Übermass gegenüber der Rohrleitung herzustel-   len,   welches Übermass sich nach den geologischen Gegebenheiten, nach der   Steuerungsgenau) gke) t   des Bohrkopfes, nach dem Rohrmatenal, nach der Art der   Rohrschussverbindungen   u. dgl. richtet, Ist bisher auch bel ausreichend genauem Bodenbohrungsverlauf die Lage der Rohrleitung innerhalb des Bohrloches mit beträchtlichen Toleranzen verbunden, was sich vor allem bel Rohrleitungen mit einem einzuhaltenden Mindestgefälle sehr ungünstig auswirkt, da die zu berücksichtigenden Neigungstoleranzen vor allem bei längeren   Leitungsstrecken   zu erheblichen   unvorherbestimmbaren   Niveauunterschieden und Im Falle gerin- 
 EMI1.2 
 



   Der Erfindung liegt daher die Aufgabe zugrunde, diese Mängel zu beseitigen und ein Verfahren der eingangs geschilderten Art anzugehen, das ein rationelles Verlegen von Rohrleitungen auch unter Einhaltung geringer Gefälle Innerhalb engster Toleranzen erlaubt. Darüber hinaus soll eine zweckmässige Vorrichtung zum einfachen Durchführen dieses Verfahrens geschaffen werden. 



   Die Erfindung löst diese Aufgabe dadurch, dass vorzugsweise die spezifischen Gewichte der Rohrleitung bzw. der Rohrschüsse und der Stützflüssigkeit aneinander angeglichen werden und dass die Rohrleitung nach dem Einziehen beiderends positionsrichtig lagegesichert und dann zum Streckrichten innendruckbeaufschlag wird. Durch die Angleichung der spezifischen Gewichte von Rohrleitung und Stützflüssigkeit lässt sich ein schwebender Schwimmzustand der Rohrleitung innerhalb der   Stützflüssigkeit   erreichen, weicher schwebende Zustand nicht nur das Einziehen der Rohrschüsse in die Bödenbohrung erleichtert, sondern darüber hinaus auch eine radiale Querbewegung der Rohrleitung gegenüber der Bodenbohrung begünstigt. 



  Wird nun nach dem Einzug der Rohrleitung In das Bohrloch die Rohrleitung innendruckbeaufschlagt, wozu selbstverständlich die Rohrleitungsenden verschlossen sein müssen, bewirkt diese Innendruckbeaufschlagung eine axiale Zugbelastung und damit ein Streckrichten der Rohrleitung, so dass bei entsprechender Lagejustierung der Rohrenden sich über die gesamte Rohrleitungslänge ein gleichmässiges Gefälle ausbildet. Die Rohrleitung nimmt dadurch nicht mehr den beim Einziehen sich ergebenden toleranzbehafteten polygonalen Verlauf Innerhalb der Bodenbohrung ein, sondern streckt sich zu einem der Höhe nach konstant geneigten Verlauf und gewährleistet so eine Rohrverlegung mit engsten   Lage- und Gefälletoleran-   zen.

   Die   Stützflüssigkeit   wird in ihren Aushärteigenschaften auf dieses Streckrichten abgestimmt und erlaubt dann durch ihr Erhärten nach dem Streckrichten das bleibende Einbetten der genchteten Rohrleitung Innerhalb der Bodenbohrung. An sich spielt es keine Rolle, ob die Rohrleitung hinsichtlich des Gefälles aufwärts oder abwärts in die Bodenbohrung eingezogen wird, es muss nur darauf geachtet werden, dass das Bohrloch entsprechend abgedichtet ist, um die Stützflüssigkeitsfüllung der Bodenbohrung zum Streckrichten und zum Einbetten der Rohrleitung nicht zu gefährden. 



   Wird die Innendruckbeaufschlagung der Rohrleitung aufrecht erhalten, bis die Stützflüssigkeit erhärtet ist. kann die ausgerichtete Lage der Rohrleitung nachträglich nicht mehr gestört und der exakte Leitungsverlauf bleibend sichergestellt werden. 



   Wird die Rohrleitung an einem oder beiden Enden In neigungsrichtiger Lage axial beweglich abgestützt, können die beim Streckrichten auftretenden Längenänderungen gut aufgenommen und ausgeglichen werden, wodurch die Lagegenauigkeit weiter zu verbessern ist. 



   Um die spezifischen Gewichte von Rohrleitung und Stützflüssigkeit aufeinander abstimmen zu können, werden die Rohrschüsse zur Gewichtsangleichung mit wasserbefüllbaren Ballastbehältern belastet oder mit 
 EMI1.3 
 

 <Desc/Clms Page number 2> 

 
 EMI2.1 
 misch verwendet, wobei Bentonit mit Hochofenschlacke, kaustischem Soda und Natriumkarbonat und Wasser oder mit Natriumkarbonat und Polymeren und anderen Additiven und Wasser gemischt werden kann, um In Abhängigkeit von den jeweiligen geologischen, ökologischen und gesundheitlichen Bedingungen die gewünschten Erstarrungseigenschaften zu erbnngen. 



   Eine andere   Möglichkeit   zur   Rohrleitungseinbettung   ergibt sich erfindungsgemäss dadurch, dass die Stützflüssigkeit während der Innendruckbeaufschlagung der Rohrleitung durch eine Bettungsmasse ausgetauscht wird, so dass einerseits die Stützflüssigkeit auf das Einziehen und Ausrichten und anderseits die Bettungsmasse auf das Einbetten der ausgerichteten Rohrleitung speziell abgestimmt werden können und beste Verlegebedingungen herrschen. Als Bettungsmasse eignet sich beispielsweise ein Bentonit-ZementSand-Wassergemisch, wobei es vorteilhaft ist, wenn beim Austausch die Bettungsmasse vom tieferen Bodenbohrungsende eingepresst wird, von wo aus sie die Stützflüssigkeit ansteigend verdrängt, die am höheren Bohrungsende abgesaugt und entsorgt wird. 



   Zum Durchführen dieses Verfahrens lassen sich durchaus bekannte Vomchtungen zum Rohreinziehen verwenden, die einen über eine Zugkupplung und einen Räumer an einem durch die Bodenbohrung verlaufenden Zuggestänge hängenden, eine Halterung für den ersten Rohrschuss der Rohrleitung aufweisenden Ziehkopf besitzen, wobei der Räumer an eine Flüssigkeitszuleitung des   Zuggestänges angeschlossene     Verteilerdüse   zum   Einbnngen   der   Stützflüssigkeit   bildet.

   Diese   Vomchtung   ist nun lediglich dahingehend zu ergänzen, dass der Ziehkopf einen äusseren, an den Bohrlochdurchmesser angepassten Dichtkörper trägt, der axiale, mit Rückschlagklappen versehene Durchströmkanäle für die   Stützflüssigkeit   besitzt, dass vorzugsweise in die Rohrschüsse zugfest miteinander verbindbare Behälter zur   Wasser- oder Gasbefüllung   einschiebbar sind, dass das   einziehseittge   Bohrlochende mit einer Rohrschleuse zum dichten Einführen der zugfest zusammensetzbaren Rohrschüsse ausgestattet ist und dass für das ziehkopfabgewandte   Rohr ! ei-   tungsende ein   Verschlussdeckel   mit einer Einrichtung zum Innendruckbeaufschlagen der Rohrleitung vorgesehen ist.

   So ist es ohne Schwierigkeiten möglich, mit Hilfe des Zuggestänges die Rohrleitung in das Bohrloch einzuziehen und gleichzeitig im Masse dieses Einzuges Stutzflüssigkeit in den Ringraum zwischen Rohrleitung und Bodenbohrung einzufüllen.   Die Stützflüssigkeit   wird durch die Flüssigkeitsleitung des Zuggestänges und die   Verteilerdüsen   des Räumers in die Bodenbohrung eingebracht und dringt dann durch die Durchströmkanäle des Dichtkörpers in den Aussenbereich der einzuziehenden Rohrleitung ein.

   Die Rückschlagklappen verhindern dabei ein Rückströmen der   Stützflüssigkeit,   was vor allem am Ende des Einziehvorganges wichtig ist, da dann der Dichtkörper den Abschluss der Bodenbohrung nach aussen hin mit sich bringen muss, wenn bereits der Räumer aus dem Bohrloch herausgezogen ist und keine   Stützf) üss) gkeit   mehr nachgepumpt wird. Die Rohrschteuse am einziehseitigen Bohrlochende ergibt hier den Abschluss des Bohrloches und verhindert ein Ausfliessen der   Stützflüssigkeit,   wobei das Einführen der Rohrschüsse zum Aufbau der Rohrleitung während des Einzugvorganges problemlos   möglich   bleibt.

   Dazu ist auch das Gewicht der Rohrschüsse durch eine zusätzliche Be- oder Entlastung mittels der   wasser- oder gasbefüllten   Behälter an einen Schwebezustand in der Stützflüssigkeit abgestimmt und erleichtert so die Rohrbewegung. Ist das ziehkopfabgewandte Rohrleitungsende mit einem Verschlussdeckel versehen, entsteht zusammen mit dem Ziehkopf am anderen Leitungsende ein abgeschlossener Rohrinnenraum, der für die Innendruckbeaufschlagung notwendig ist. Diese Druckbeaufschlagung kann vorzugsweise mit   Pressluft,   aber durchaus auch mit einem Hydraulikmittel od. dgl. vorgenommen werden, wobei entsprechende Sicherheits- und Messeinrichtungen Verwendung finden. 



   Ist der Rohrschleuse eine Justiereinrichtung zur Lagesicherung der Rohrleitung zugeordnet, kann die Positionierung des Rohrleitungsendes gleich im Bereich der Rohrschleuse durchgeführt werden, wobei die Schleuse von sich aus bereits eine Vorzentrierung ergibt. Die Justiereinrichtung selbst kann dann mit einer Führungseinnchtung zur axial beweglichen Halterung der Rohrleitung kombiniert sein, so dass ein einwandfreier Längenausgleich der Rohrleitung beim Streckrichten unabhängig vom Reibungsschluss am ziehkopfseitigen Ende zwischen Dichtkörper und Bohrloch möglich ist, welcher Dichtkörper selbst ja für die Abdichtung und Lagejustierung des schleusenabgewandten Bohrlochendes bzw. Rohrleitungsendes sorgen soll. 



   In der Zeichnung ist der Erfindungsgegenstand rein schematisch veranschaulicht und zwar zeigen
Fig. 1 eine erfindungsgemässe Vorrichtung zum neigungsgenauen Verlegen unterirdischer Rohrleitun- gen an Hand eines Anlagenschemas sowie
Fig. 2 den Ziehkopf dieser Vorrichtung im Axialschnitt grösseren Massstabes und
Fig. 3 die Rohrschleuse dieser Vorrichtung ebenfalls im Axialschnitt grösseren Massstabes. 



   Um eine Rohrleitung 1 möglichst neigungsgenau im Untertageverfahren verlegen zu können, wird zuerst entlang dem durch die Planvorgabe bestimmten Leitungsverlauf eine Bodenbohrung 2 hergestellt, 

 <Desc/Clms Page number 3> 

 
 EMI3.1 
 

 <Desc/Clms Page number 4> 

 können. 



   Ist die Rohrleitung 1 eingezogen und durch die Innendruckbeaufschlagung streckgenchtet. nimmt sie 
 EMI4.1 
 
Bett zur Aufnahme der Rohrleitung 1 bildet, womit auch der exakte   Rohrleitungsverlauf langfnst ! g abgest-   chert ist. Nach dem Erstarren der   Stützflüssigkeit   10 werden Ziehkopf 5 und Rohrschleuse 18 abmontiert und   die Verlegungsarbeltung   können   üblicherweise   beendet werden. 



   

   <Desc / Clms Page number 1>
 



   The invention relates to a method for the inclination-accurate laying of underground pipelines, first of all by making a bottom hole along the predetermined line course and
 EMI1.1
 



   Various drilling methods, so-called horizontal drilling methods, are already known for producing boreholes for the underground laying of pipelines or the like, mostly using a drilling fluid and a progressively controlled drilling head and which, with sufficient directional accuracy, permit the drilling of corresponding boreholes along a line course predetermined by the plan .

   The actual laying of the pipe lines composed of individual pipe sections is then carried out by pulling the pipe string lengthening in sections due to the tensile strength of the pipe sections into the bottom bore, whereby it has also already been proposed to pump a supporting liquid into the borehole to facilitate this pipe pulling in, in order to be able to influence the friction and movement conditions while pulling in and on the other hand to obtain a bedding of the pipeline filling the space between the pipeline and the borehole wall after hardening of the supporting liquid.

   Since it is necessary for the pipe laying to make the floor borehole with an oversize compared to the pipeline, which oversize depends on the geological conditions, on the control accuracy of the drill head, on the pipe material, on the type of pipe socket connections and the like. Like., Is the position of the pipeline within the borehole associated with considerable tolerances, even with a sufficiently precise course of the bottom bore, which has a particularly unfavorable effect especially for pipelines with a minimum gradient to be observed, since the inclination tolerances to be taken into account, especially with longer pipeline routes, lead to considerable, unpredictable Level differences and in the case of low
 EMI1.2
 



   The invention is therefore based on the object of eliminating these deficiencies and of tackling a method of the type described at the outset which permits rational laying of pipelines, even with a slight gradient, within the narrowest tolerances. In addition, an expedient device for simple implementation of this method is to be created.



   The invention solves this problem in that the specific weights of the pipeline or the pipe sections and the supporting liquid are preferably matched to one another and in that the pipeline is secured in the correct position after pulling in at both ends and is then subjected to internal pressure for stretching. By aligning the specific weights of the pipeline and the supporting fluid, a floating floating state of the pipeline within the supporting fluid can be achieved, the softer floating state not only facilitates the drawing of the pipe sections into the bottom hole, but also favors a radial transverse movement of the pipeline relative to the bottom hole.



  If the pipeline is then pressurized into the borehole after the pipeline has been drawn in, for which purpose the pipeline ends must of course be closed, this internal pressurization causes an axial tensile load and thus a straightening of the pipeline, so that if the pipe ends are adjusted accordingly, a uniform gradient over the entire pipeline length trains. As a result, the pipeline no longer adopts the tolerance-prone polygonal course within the floor bore when it is drawn in, but instead stretches to a course that is constantly inclined in height, thus ensuring pipe laying with the narrowest tolerances in terms of position and gradient.

   The hardening properties of the supporting liquid are matched to this stretch leveling and then, by hardening after stretch leveling, allows the non-sealed pipeline to be permanently embedded within the bottom hole. As such, it does not matter whether the pipeline is drawn into the bottom hole upwards or downwards, it is only necessary to ensure that the borehole is sealed appropriately so that the support fluid filling of the bottom hole is not used to straighten and embed the pipeline endanger.



   The internal pressurization of the pipeline is maintained until the supporting fluid has hardened. the aligned position of the pipeline can no longer be disturbed and the exact line routing can be permanently ensured.



   If the pipeline is axially movably supported at one or both ends in the correct inclination position, the changes in length occurring during stretch straightening can be well absorbed and compensated, which further improves the positional accuracy.



   In order to be able to match the specific weights of the pipeline and the supporting fluid to one another, the pipe sections are loaded with ballast containers that can be filled with water or with
 EMI1.3
 

 <Desc / Clms Page number 2>

 
 EMI2.1
 mixed used, whereby bentonite can be mixed with blast furnace slag, caustic soda and sodium carbonate and water or with sodium carbonate and polymers and other additives and water, in order to inherit the desired solidification properties depending on the respective geological, ecological and health conditions.



   Another possibility for embedding the pipeline results according to the invention in that the supporting fluid is replaced by a bedding compound during the internal pressurization of the pipeline, so that on the one hand the supporting liquid can be specially adapted to the drawing in and aligning and on the other hand the bedding compound can be specially adapted to the embedding of the aligned pipeline Laying conditions prevail. A bentonite-cement-sand-water mixture, for example, is suitable as bedding compound, whereby it is advantageous if, during replacement, the bedding compound is pressed in from the lower end of the borehole, from where it displaces the supporting fluid, which is suctioned off and disposed of at the higher end of the borehole.



   To carry out this method, well-known devices for pulling in the pipe can be used, which have a pulling head that hangs over a pull coupling and a scraper on a pull rod that runs through the bottom bore and has a holder for the first pipe section of the pipeline, the clearer being connected to a liquid supply line for the pull rod connected distributor nozzle for trapping the supporting liquid.

   This requirement can now only be supplemented to the extent that the drawing head has an outer sealing body which is adapted to the borehole diameter and has axial flow channels for the supporting liquid which are provided with non-return flaps, so that containers for water or gas filling, which can be connected to one another in a tensile manner, can be inserted that the end of the hole on the pull-in side is equipped with a pipe lock for the tight insertion of the pipe sections that can be assembled with tensile strength and that for the pipe facing away from the drawing head! at the end of the line, a cover with a device for pressurizing the pipeline is provided.

   It is therefore possible without difficulty to pull the pipeline into the borehole with the aid of the pulling rod and, at the same time, pour filler liquid into the annular space between the pipeline and the bottom hole in the mass of this draw-in. The support fluid is introduced into the bottom bore through the fluid line of the pulling rod and the distributor nozzles of the reamer and then penetrates through the flow channels of the sealing body into the outer region of the pipeline to be drawn in.

   The non-return flaps prevent the support fluid from flowing back, which is particularly important at the end of the pull-in process, since the sealing body must then bring the bottom hole outwards when the reamer is already pulled out of the drill hole and no support feet) pumped more. The pipe lock at the pull-in end of the borehole here results in the completion of the borehole and prevents the supporting liquid from flowing out, the insertion of the pipe sections to build up the pipeline remaining easily possible during the pulling-in process.

   For this purpose, the weight of the pipe sections is matched to a floating state in the supporting liquid by means of an additional loading or unloading by means of the water- or gas-filled containers, and thus facilitates the pipe movement. If the end of the pipe facing away from the drawing head is provided with a sealing cover, a closed pipe interior is created together with the drawing head at the other end of the pipe, which is necessary for the internal pressurization. This pressurization can preferably be carried out with compressed air, but definitely also with a hydraulic medium or the like, appropriate safety and measuring devices being used.



   If an adjustment device for securing the position of the pipeline is assigned to the pipe lock, the positioning of the pipe end can be carried out immediately in the area of the pipe lock, the lock already resulting in a pre-centering. The adjustment device itself can then be combined with a guide device for axially movable mounting of the pipeline, so that a perfect length compensation of the pipeline during stretch straightening is possible regardless of the frictional connection at the end of the drawing head between the sealing body and the borehole, which sealing body itself is used for sealing and adjusting the position of the lock away End of the borehole or the end of the pipeline.



   In the drawing, the subject matter of the invention is illustrated purely schematically and shows
1 shows a device according to the invention for the inclination-accurate laying of underground pipelines using a system diagram and
Fig. 2 the drawing head of this device in axial section on a larger scale and
Fig. 3, the tube lock of this device also in axial section on a larger scale.



   In order to be able to lay a pipeline 1 as precisely as possible in the underground method, a bottom hole 2 is first made along the line course determined by the plan,

 <Desc / Clms Page number 3>

 
 EMI3.1
 

 <Desc / Clms Page number 4>

 can.



   Is the pipeline 1 retracted and stretched by the internal pressure. she takes
 EMI4.1
 
Forms bed for receiving pipeline 1, which means that the exact pipeline run is long! g is flawed. After the supporting liquid 10 has solidified, the drawing head 5 and the tube lock 18 are removed and the laying process can usually be ended.



   
    

Claims (8)

Patentansprüche 1. Verfahren zum neigungsgenauen Verlegen untenrdischer Rohrleitungen, bel dem zuerst entlang dem vorbestimmten Leitungsverlauf eine Bodenbohrung hergestellt und gegebenenfalls das Bohrloch aufge- weitet und dann die aus einzelnen Rohrschüssen zusammensetzbare Rohrleitung unter gleichzeitigem Hinterfüllen einer aushärtenden Stützflüssigkeit In die Bodenbohrung eingezogen wird, dadurch gekennzeichnet, dass vorzugsweise die spezifischen Gewichte der Rohrleitung bzw. der Rohrschüsse und der Stützflüssigkeit aneinander angeglichen werden und dass die Rohrleitung nach dem Einziehen beiderends positionsrichtig lagegesichert und dann zum Strecknchten Innendruckbeaufschlagt wird.Claims 1. Method for the incline-accurate laying of underground pipelines, first of all, a floor borehole is made along the predetermined pipe run and the borehole is widened if necessary, and then the pipeline, which can be assembled from individual pipe sections, is drawn into the floor borehole with simultaneous backfilling of a hardening support liquid, characterized in that preferably the specific weights of the pipeline or of the pipe sections and the supporting fluid are adjusted to one another and that the pipeline is secured in the correct position after pulling in at both ends and then subjected to internal pressure for extension. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass die Innendruckbeaufschlagung der Rohr- leitung aufrechterhalten wird, bis die Stützflüssigkeit erhärtet. 2. The method according to claim 1, characterized in that the internal pressure on the pipeline is maintained until the supporting liquid hardens. 3. Verfahren nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass die Rohrleitung an einem oder belden Enden In neigungsncht ! ger Lage axialbeweglich abgestützt wird. 3. The method according to claim 1 or 2, characterized in that the pipeline at one or belden ends In inclinationsncht! ger position is supported axially movable. 4. Verfahren nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass die Rohrschüsse zur Gewichtsangleichung mit wasserbefüllbaren Ballastbehältern belastet oder mit gasbefüllbaren Auftriebs- behältern entlastet werden. 4. The method according to any one of claims 1 to 3, characterized in that the pipe sections for Weight adjustment can be loaded with water-filled ballast containers or relieved with gas-filled buoyancy containers. 5. Verfahren nach einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, dass als Stützflüssigkeit ein Bentonitgemisch verwendet wird. 5. The method according to any one of claims 1 to 4, characterized in that as a supporting liquid Bentonite mixture is used. 6. Verfahren nach einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, dass die Stützflüssigkeit während der Innendruckbeaufschlagung der Rohrleitung durch eine Bettungsmasse ausgetauscht wird. 6. The method according to any one of claims 1 to 4, characterized in that the supporting liquid is exchanged during the internal pressurization of the pipeline by a bedding compound. 7. Vorrichtung zum Durchführung des Verfahrens nach einem der Ansprüche 1 bis 6, mit einem über eine Zugkupplung und einen Räumer an einem durch die Bodenbohrung verlaufenden Zuggestänge hängenden, eine Halterung für den ersten Rohrschuss der Rohrleitung aufweisenden Ziehkopf, wobei der Räumer an eine Flüssigkeitszuleitung des Zuggestänges angeschlossene Verteilerdüsen zum Einbringen der Stützflüssigkeit bildet, dadurch gekennzeichnet, dass der Ziehkopf (5) einen äusseren, an den Bohrlochdurchmesser angepassten Dichtkörper (14) trägt, der axiale, mit Rückschlagklappen (17) versehene Durchströmkanäle (15) für die Stützflüssigkeit (10) besitzt, dass vorzugsweise in die Rohrschüsse (4) zugfest miteinander verbindbare Behälter (29) zur Wasser- oder Gasbefüllung ein- schiebbar sind, 7. Device for carrying out the method according to one of claims 1 to 6, with one over Train coupling and a scraper on a pulling rod hanging through the bottom bore and holding a holder for the first pipe section of the pipeline, the scraper connected to a liquid supply line of the pulling rod for distribution nozzles Introducing the support fluid, characterized in that the drawing head (5) carries an outer sealing body (14) which is adapted to the borehole diameter and which has axial flow channels (15) for the support fluid (10) provided with non-return flaps (17), that preferably in the Pipe sections (4), containers (29) which can be connected to one another for tensile strength, can be inserted for water or gas filling, dass das einziehseitige Bohrlochende (21) mit einer Rohrschleuse (18) zum dichten Einführen der zugfest zusammensetzbaren Rohrschüsse (4) ausgestattet ist und dass für das ziehkopf- abgewandte Rohrleitungsende (25) ein Verschlussdeckel (26) mit einer Einrichtung (27) zum Innendruck- beaufschlagen der Rohrleitung (1) vorgesehen ist.  that the pull-in borehole end (21) with a tube lock (18) for sealing Insertion of the pipe sections (4) which can be assembled in a tensile manner and that a closure cover (26) with a device (27) for applying internal pressure to the pipe (1) is provided for the end of the pipe (25) facing away from the drawing head. 8. Vomchtung nach Anspruch 7, dadurch gekennzeichnet, dass der Rohrschleuse (18) eine Positionier- einrichtung (24) für die Rohrleitung (1) zugeordnet ist. 8. arrangement according to claim 7, characterized in that the tube lock (18) is associated with a positioning device (24) for the pipeline (1).
AT183595A 1995-11-08 1995-11-08 Method and apparatus for laying underground pipelines at an accurate gradient AT402546B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AT183595A AT402546B (en) 1995-11-08 1995-11-08 Method and apparatus for laying underground pipelines at an accurate gradient

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT183595A AT402546B (en) 1995-11-08 1995-11-08 Method and apparatus for laying underground pipelines at an accurate gradient

Publications (2)

Publication Number Publication Date
ATA183595A ATA183595A (en) 1996-10-15
AT402546B true AT402546B (en) 1997-06-25

Family

ID=3522048

Family Applications (1)

Application Number Title Priority Date Filing Date
AT183595A AT402546B (en) 1995-11-08 1995-11-08 Method and apparatus for laying underground pipelines at an accurate gradient

Country Status (1)

Country Link
AT (1) AT402546B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113915408B (en) * 2021-09-08 2023-05-09 湖南尚桦景观工程有限公司 Be used for afforestation engineering pipeline laying device

Also Published As

Publication number Publication date
ATA183595A (en) 1996-10-15

Similar Documents

Publication Publication Date Title
DE2523988C2 (en) Method for anchoring a protective wall or the like. with the ground and grouting anchors to carry out the procedure
DE2118815A1 (en) Cementing device for casing strings of boreholes
DE1634626B1 (en) Method and device for producing an anchorage in the ground or rock
EP1974124B1 (en) Fluid recovery
DE3014027B1 (en) Method and device for introducing an extension into wells, in particular a watertight extension into wells to be sunk by water-bearing mountains
DE1409904A1 (en) Method for creating excavations in water-bearing soil by means of a jacking shield
AT402546B (en) Method and apparatus for laying underground pipelines at an accurate gradient
WO2012056011A1 (en) Method for the underground placement of a pipeline
DE588407C (en) Method for pressing a detergent into damaged structures, stone or the like.
DE3818998C3 (en) Procedure for laying supply lines
DE3335487A1 (en) Device for high-pressure injection into masonry bores
DE102007016682B3 (en) Method for installing geothermal probe into borehole, involves carrying out construction of geothermal probe before high pressure application
DE3545084A1 (en) TUNNEL CONSTRUCTION
DE3633350C1 (en) Method of supplying compressed air to the working chamber and the personnel and materials lock of a manhole cylinder and device for carrying out the method
DE1634626C (en) Method and device for Her provide an anchorage in the ground or rock
DE3925097C1 (en)
DE102018125947A1 (en) Method and device for dismantling geothermal probes
DE3408558C2 (en) Device for introducing injection compound into injection zones located under the earth&#39;s surface or on the surface of a building
DE3543059A1 (en) Method of stabilising soil sections
EP4339378A1 (en) Handling device and method for gripping and inserting a pipe pile into a borehole
DE19617196C1 (en) Sealing-solidifying agent injection system in ground or rock, e.g. two-ingredient fast-reacting agent, esp. polyurethane
DE2410212A1 (en) Sealing device for rock consolidating plastics grouting - includes tensioner arm, bored probe, and foam plastics recessed end plug
WO2024056237A1 (en) Method for forming a foundation pile in the ground
DE2108878C3 (en) Method for producing a deep foundation skörpe rs
DE19849668C1 (en) Renewal method for old underground fresh water or sewage pipes, using liners and folded bubbles fitted through bores into gap and filled with hardening material to align inner pipe

Legal Events

Date Code Title Description
ELJ Ceased due to non-payment of the annual fee