JP2973930B2 - Production planning simulation device - Google Patents

Production planning simulation device

Info

Publication number
JP2973930B2
JP2973930B2 JP16973396A JP16973396A JP2973930B2 JP 2973930 B2 JP2973930 B2 JP 2973930B2 JP 16973396 A JP16973396 A JP 16973396A JP 16973396 A JP16973396 A JP 16973396A JP 2973930 B2 JP2973930 B2 JP 2973930B2
Authority
JP
Japan
Prior art keywords
information
item
production
plan
production plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP16973396A
Other languages
Japanese (ja)
Other versions
JPH1015786A (en
Inventor
京一 村上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
Nippon Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Electric Co Ltd filed Critical Nippon Electric Co Ltd
Priority to JP16973396A priority Critical patent/JP2973930B2/en
Publication of JPH1015786A publication Critical patent/JPH1015786A/en
Application granted granted Critical
Publication of JP2973930B2 publication Critical patent/JP2973930B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は生産計画シミュレー
ション装置に関し、特にMRP(Material R
equirements Planning,以下MR
Pという。)計算を行ない各品目の所要量を算定して手
配計画を立案する生産計画シミュレーション装置に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production planning simulation apparatus, and more particularly to an MRP (Material R).
equipments Planning, MR
It is called P. The present invention relates to a production planning simulation apparatus for calculating the required quantity of each item and drafting an arrangement plan.

【0002】[0002]

【従来の技術】従来の生産計画シミュレーション装置は
生産計画から展開された下位構成部品の在庫の時系列計
算を行い、その結果の所要情報・手配情報をそのまま用
いて実際に資材発注や製造手配を行なっている。たとえ
ば、特開平04−364573号公報による在庫シミュ
レーションシステムは、その対象とする品目を発注生産
方式のものに限り、限界在庫量,発注在庫量を設定可能
パラメータとして条件を変えながら過去の手配と所要に
基づき在庫の時系列シミュレーションを行い、その日々
の在庫量推移を表示している。
2. Description of the Related Art A conventional production planning simulation apparatus performs a time-series calculation of the inventory of lower-level components developed from a production plan, and actually performs material ordering and manufacturing arrangement using the necessary information and arrangement information as it is. I do. For example, the inventory simulation system disclosed in Japanese Patent Application Laid-Open No. 04-364573 discloses a method in which the target item is of the order production system, and the past order and required order are changed while changing the conditions of the marginal inventory amount and the order inventory amount as settable parameters. , A time-series simulation of the inventory is performed, and the daily inventory change is displayed.

【0003】[0003]

【発明が解決しようとする課題】上記のような従来の生
産計画シミュレーション装置は、MRP計算を行った結
果を評価する手段をもたないので、そのまま手配業務に
つなげてしまい、計算結果を評価する機会がない。
Since the conventional production planning simulation apparatus as described above does not have means for evaluating the result of the MRP calculation, it can be directly connected to the ordering work and the calculation result is evaluated. There is no opportunity.

【0004】また、在庫推移のシミュレーショ行いグラ
フ表示して過去の生産計画に基づく在庫推移状況の評価
を行うことはできても、生産計画の変更による影響や工
程負荷までを考慮した評価結果に基づく計画変更を行う
ことができない。さらに、ロットまとめ数量やロットま
とめ期間,発注数量,部品の切り替え等の基準情報の見
直しを行う際に、どのような変更を行うと実際の手配状
況,在庫推移,工程負荷にどのような影響があるかを瞬
時にグラフ上でいろいろなパターンを試しながら評価す
ることができない。
[0004] In addition, although inventory transitions can be simulated and displayed graphically to evaluate inventory transitions based on past production plans, the results of evaluations that take into account the effects of changes in production plans and process loads can be obtained. Inability to make plan changes based on In addition, when reviewing the standard information such as lot batch quantity, lot batch period, order quantity, and part switching, what kind of changes will affect the actual ordering situation, inventory changes, and process load? It is not possible to instantly evaluate various patterns on a graph.

【0005】またこれらのシミュレーション結果ととも
に原価情報や設計情報等のMRP計算と直接関係ない情
報を統合的に評価できる環境もない。
[0005] Further, there is no environment in which information that is not directly related to the MRP calculation, such as cost information and design information, can be integratedly evaluated together with these simulation results.

【0006】本発明の目的は、上記の欠点を改善し、生
産計画立案時に資材の調達可能性,製造工程の負荷,納
期遵守という複数の評価観点で生産計画を評価しなが
ら、生産計画,資材手配計画の調整を行ないかつ基準情
報の変更や生産計画の変更による影響をさまざまな情報
とともに評価できる生産計画シミュレーション装置を提
供することにある。
SUMMARY OF THE INVENTION It is an object of the present invention to improve the above-mentioned drawbacks, and to evaluate a production plan while evaluating the production plan from a plurality of evaluation viewpoints such as availability of materials, load on a manufacturing process, and compliance with a delivery date when drafting the production plan. It is an object of the present invention to provide a production plan simulation apparatus which can adjust an arrangement plan and can evaluate the influence of a change in reference information or a change in a production plan together with various information.

【0007】[0007]

【課題を解決するための手段】本発明の生産計画シミュ
レーション装置は、製造・調達の対象となる品目の情報
が記述されている品目情報と,品目名の親子関係が記述
されている構成情報と,対象とする品目を生産する工場
の稼働日カレンダ情報と,対象とする各品目のある時点
における在庫量が記述されている在庫情報と,すでに確
定済みの確定所要情報および確定手配情報と,立案対象
である品目の所要日および数量が記述されている生産計
画情報とを入力し、前記品目情報および構成情報を参照
して前記生産計画情報からその構成部品の所要日および
所要量を計算し、前記在庫情報の記録時点を開始点とし
て時系列に在庫量から確定所要情報および確定手配情報
を参照して前記生産計画情報から展開した新規計画所要
および新規計画手配を加減し前記在庫量が品目情報に定
義されている条件に合致すると新たに所要・手配を立て
るMRP計算手段と、生産計画情報の所要日および数量
を変更したり新たに生産計画を追加・削除する生産計画
情報登録手段と、前記生産計画情報登録手段により登録
された生産計画情報をもとにして前記MRP計算手段が
計算を行なった結果の所要・手配情報から各所要・手配
の紐づけ関係を表示する手配引当手段と、前記MRP計
算手段が計算を行った結果の所要・手配情報から処理日
において手配が間に合わないものを抽出しアラーム表示
する欠品アラーム手段と、前記所要・手配情報の1つ1
つをバーとしてグラフ表示するガントチャート表示手段
と、前記所要・手配情報と,各品目の製造工程手順情報
と,各工程毎の能力情報とからタイムバケット別の工程
負荷情報を算出する工程負荷情報算出手段と、前記工程
負荷情報を指定の条件で分類しタイムバケット別に棒グ
ラフで表示する工程負荷山積みグラフ表示手段とを含ん
で構成される。
According to the present invention, there is provided a production planning simulation apparatus comprising: item information in which information of an item to be manufactured and procured is described; and configuration information in which a parent-child relationship of an item name is described. , Working day calendar information of the factory that produces the target item, inventory information that describes the stock quantity of each target item at a certain point in time, fixed finalization required information and fixed arrangement information, and planning Enter the required date and quantity of the target item and production plan information describing the quantity, calculate the required date and required amount of the component from the production plan information with reference to the item information and the configuration information, With the recording time of the stock information as a starting point, a new planning requirement and a new planning hand developed from the production planning information with reference to the fixed requirement information and the fixed order information from the stock amount in time series. MRP calculation means for making a new requirement / arrangement when the stock quantity meets the conditions defined in the item information, and changing the required date and quantity of the production plan information and adding / deleting a new production plan Production plan information registering means, and a relation between each required / arrangement based on the required / arranged information obtained as a result of calculation by the MRP calculating means based on the production plan information registered by the production plan information registered means. A shortage alarming means for extracting an item which cannot be arranged on the processing date from the required / arranged information obtained as a result of the calculation by the MRP calculating means and displaying an alarm, and an out-of-stock alarm means for displaying the required / arranged information. One by one
Gantt chart display means for displaying a graph as a bar, process load information for calculating process load information for each time bucket from the required / arranged information, manufacturing process procedure information for each item, and capacity information for each process. It comprises a calculating means and a process load pile graph displaying means for classifying the process load information under specified conditions and displaying the process load information in a bar graph for each time bucket.

【0008】また、本発明の生産計画シミュレーション
装置は、前記ガントチャート表示手段によって表示され
たガントチャート,または工程負荷山積みグラフ表示手
段によって表示された工程負荷山積みグラフの所要・手
配情報を抽出するグラフ情報逆リンク手段と、前記グラ
フ情報逆リンク手段により抽出された所要・手配情報の
所要日・所要数等の情報を変更する生産計画調整手段と
を含む。
Further, the production planning simulation apparatus of the present invention provides a graph for extracting required / arranged information of a Gantt chart displayed by the Gantt chart display means or a process load pile graph displayed by the process load pile graph display means. An information reverse linking means, and a production plan adjusting means for changing information such as required date and required number of required / arranged information extracted by the graph information reverse linking means.

【0009】さらに、本発明の生産計画シミュレーショ
ン装置は、前記品目情報,前記構成情報,前記稼働日カ
レンダ情報,前記在庫情報,および前記確定所要・手配
情報を含む基準情報に属する生産リードタイム,ロット
まとめ数量,ロットまとめ期間,部品構成有効期間など
のなかの任意の項目を変更する基準情報変更手段を具備
する。
Further, the production planning simulation apparatus according to the present invention further comprises a production lead time, a lot belonging to reference information including the item information, the configuration information, the working day calendar information, the stock information, and the confirmed required / arranged information. There is provided reference information changing means for changing any item such as a grouping quantity, a lot grouping period, and a component configuration validity period.

【0010】さらに、本発明の生産計画シミュレーショ
ン装置は、前記手配引当手段が送出する手配引当情報を
タイムバケットごとに手配分と所要分とに区別して表示
するとともに手持ち在庫から時系列に所要・手配による
在庫推移を表示する在庫推移グラフ表示手段を具備す
る。
Further, the production planning simulation apparatus according to the present invention displays the allocation allocation information sent by the allocation allocation means separately for each time bucket as the allocation of the allocation and the required amount, and chronologically determines the allocation of the allocation from the on-hand inventory. And a stock transition graph display means for displaying the stock transition according to.

【0011】さらに、本発明の生産計画シミュレーショ
ン装置は、原価情報や設計情報等の属性情報と前記品目
情報,前記構成情報,および前記所要・手配情報とを品
目をキーとして関連づける属性情報リンク手段と、前記
属性情報リンク手段で関連づけられた任意の属性情報と
品目情報,構成情報,所要・手配情報を表示する属性情
報表示手段とを含む。
Further, the production planning simulation apparatus according to the present invention includes attribute information linking means for associating attribute information such as cost information and design information with the item information, the configuration information, and the required / arranged information by using an item as a key. And attribute information display means for displaying item information, configuration information, required / arranged information, and any attribute information associated with the attribute information link means.

【0012】さらに、本発明の生産計画シミュレーショ
ン装置は、前記MRP計算手段が送出する計画所要・手
配情報を複数種類管理する複数計画案管理手段を具備す
る。
Further, the production plan simulation apparatus of the present invention includes a plurality of plan management means for managing a plurality of types of plan requirement / arrangement information sent by the MRP calculation means.

【0013】さらに、本発明の生産計画シミュレーショ
ン装置は、前記複数計画案管理手段により管理されてい
る情報を同時に複数の作業者が調整する場合に作業者間
のデータ利用の排他処理を行うデータアクセス管理手段
を含む。
Further, the production plan simulation apparatus according to the present invention provides a data access system for performing exclusive processing of data use among workers when a plurality of workers simultaneously adjust information managed by the plurality of plan management means. Including management means.

【0014】[0014]

【発明の実施の形態】以下、本発明について図面を参照
しながら説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings.

【0015】図1は本発明の実施の一形態を示すブロッ
ク図である。同図において、本発明による生産計画シミ
ュレーション装置は、製造・調達の対象となる品目の情
報が記述されている品目情報と,品目間の親子関係が記
述されている構成情報と,対象とする品目を生産する工
場の稼働日カレンダ情報と,対象とする各品目のある時
点における在庫量が記述されている在庫情報と,すでに
確定済みの確定所要情報および確定手配情報とからなる
基準情報群aと、立案対象である品目の所要日と数量が
記述されている生産計画情報bとを入力とし、前述の生
産計画情報bから前述の品目情報および構成情報を用い
てその構成部品の所要日と所要量を計算し、前述の在庫
情報の記録時点を開始点として時系列に前述の在庫量か
ら確定手配情報および確定所要情報,生産計画から展開
した新規計画所要および新規計画手配を加減し、在庫量
が品目情報に定義されている条件に合致すると新たに所
要・手配を立てるようなMRP計算手段1を有する。
FIG. 1 is a block diagram showing an embodiment of the present invention. In the figure, a production planning simulation apparatus according to the present invention includes: item information in which information on an item to be manufactured / procured is described; configuration information in which a parent-child relationship between items is described; And a reference information group a composed of inventory information describing the operation day calendar information of the factory that produces the product, inventory information describing the stock quantity of each target item at a certain point in time, already determined final requirement information and final order information. , The required date and quantity of the item to be drafted are described as input, and the required date and required value of the component are obtained from the previously described production plan information b using the above-described item information and configuration information. Calculate the quantity, and use the above-mentioned stock information as the starting point as a starting point, and chronologically determine the fixed order information and the fixed requirement information from the above-mentioned stock quantity, and the new plan requirements and new totals developed from the production plan. And adjusting the arrangements, inventory has a MRP calculation means 1 that sets a new required-arrange the meeting the conditions defined in the item information.

【0016】また、前述の生産計画情報bの所要日およ
び数量を変更したり、新たに生産計画を追加・削除する
生産計画情報登録手段2を有する。
Further, there is provided a production plan information registering means 2 for changing the required date and quantity of the production plan information b and adding / deleting a new production plan.

【0017】さらに、生産計画情報登録手段2により登
録された生産計画情報bをもとにして、前述のMRP計
算手段1が計算を行った結果の所要・手配情報cから各
所要・手配の紐づけ関係を検索し、手配引当情報gを出
力し表示する手配引当手段3を有する。
Further, based on the production plan information b registered by the production plan information registering means 2, the required / arranged information c obtained by the calculation by the MRP calculating means 1 is used to calculate a required / arranged string. There is arrangement allocating means 3 for searching for an attachment relation and outputting and displaying arrangement allocation information g.

【0018】さらに、前述のMRP計算手段1が計算を
行った結果の所要・手配情報cから、処理日において手
配が間に合わないものを抽出し欠品アラーム情報hを出
力しアラーム表示する欠品アラーム手段4を有する。
Further, from the required / arranged information c obtained as a result of the calculation by the above-mentioned MRP calculating means 1, a missing item alarm which extracts an item which cannot be arranged on the processing date, outputs missing item alarm information h, and displays an alarm is displayed. Means 4 is provided.

【0019】さらに、前述の計算結果の所要・手配情報
cの1つ1つをバーとしてグラフ表示し、そのグラフ情
報をガントチャートを情報iとして出力するガントチャ
ート表示手段5を有する。
Further, there is provided a Gantt chart display means 5 for displaying each required / arranged information c of the above-mentioned calculation results as a bar as a graph and outputting the graph information as a Gantt chart as information i.

【0020】さらに、前述の計算結果の所要・手配情報
cと各品目の製造工程手順情報および各工程毎の能力情
報からなる工程情報群dとからタイムバケット別の工程
負荷情報eを算出する工程負荷情報算出手段6を有す
る。
Further, a step of calculating process load information e for each time bucket from the requirement / arrangement information c of the above calculation result and a process information group d including manufacturing process procedure information of each item and capability information for each process. It has load information calculation means 6.

【0021】さらに、前述の工程負荷情報eを指定の条
件で分類し、色分けしてタイムバケット別に棒グラフ
(工程負荷山積みグラフ)で表示する工程負荷山積みグ
ラフ表示手段7を有する。
Further, there is provided a process load pile graph display means 7 for classifying the above-mentioned process load information e under designated conditions, classifying the process load information e by color, and displaying the time buckets in a bar graph (process load pile graph).

【0022】さらに、前述のガントチャート表示手段5
によって表示されたガントチャート上や,工程負荷山積
みグラフ表示手段7によって表示された工程負荷山積み
グラフ上でマウス等のポインティングデバイスにより指
定された位置に対応する位置情報を取得し、その位置に
対応する所要・手配情報を抽出し、逆リンク情報fとし
て出力するグラフ情報逆リンク手段8を有する。
Further, the aforementioned Gantt chart display means 5
The position information corresponding to the position designated by a pointing device such as a mouse is acquired on the Gantt chart displayed by the above or on the process load pile graph displayed by the process load pile graph display means 7, and the position information corresponding to the position is acquired. It has a graph information reverse link means 8 for extracting required / arranged information and outputting it as reverse link information f.

【0023】さらに、前述のグラフ情報逆リンク手段8
により抽出された逆リンク情報fに含まれる所要・手配
情報の所要日・所要数などの情報を変更する生産計画調
整手段9を有する。
Further, the above-mentioned graph information reverse link means 8
And a production plan adjusting means 9 for changing information such as required date and required number of required / arranged information included in the reverse link information f extracted by (1).

【0024】図2は上記の生産計画シミュレーション装
置における生産計画情報画面または生産計画調整画面の
例を示す説明図である。同図において、生産計画情報登
録画面の場合は生産計画情報6が登録・変更の対象とな
り、生産計画調整画面の場合はグラフ情報逆リンク手段
により抽出された逆リンク情報fに含まれる計画所要・
計画手配情報が登録・変更の対象となる。同図では、品
名コードF1,オーダ番号F2,所要日F3,数量F4
の各フィールドに値の入力が可能であり、この画面で入
力された値が新たに登録される。
FIG. 2 is an explanatory diagram showing an example of a production plan information screen or a production plan adjustment screen in the above-mentioned production plan simulation apparatus. In the figure, in the case of the production plan information registration screen, the production plan information 6 is to be registered / changed, and in the case of the production plan adjustment screen, the plan requirement information included in the reverse link information f extracted by the graph information reverse link means.
Planned order information is subject to registration / change. In the figure, product name code F1, order number F2, required date F3, quantity F4
Can be entered in each of the fields, and the value entered on this screen is newly registered.

【0025】図3は上記のガントチャート表示画面の例
を示す説明図である。同図において、バーB1〜B5は
1つの品目を構成する部品1点1点に対応しており、横
軸は時間軸になっている。各バーの長さは対応する製造
・調達リードタイムを表している。また、補助線HL
1,HL2により各品目間の親子関係を示し、B1はB
2,B3から構成され、B2はさらにB4,B5から構
成されることを表している。作業者はマウス等ににより
B1〜B5のバー部分をピックすることにより、それぞ
れのバーに対応した計画所要・手配情報を選択する。図
4は上記の工程負荷山積みグラフの例を示す説明図であ
る。同図においてL1〜L10は作業者により任意に指
定された分類条件により分類された山積み負荷層を表
し、縦軸は負荷量,横軸は時間軸を表す。作業者はマウ
ス等によりL1〜L10の層部分をピックすることによ
り、それぞれの層に属する計画所要・手配情報を選択す
る。
FIG. 3 is an explanatory diagram showing an example of the Gantt chart display screen. In the figure, bars B1 to B5 correspond to individual parts constituting one item, and the horizontal axis is a time axis. The length of each bar represents the corresponding manufacturing and procurement lead time. In addition, the auxiliary line HL
1, HL2 indicates the parent-child relationship between each item, and B1 is B
2, B3, and B2 is further composed of B4, B5. The operator selects the required planning / arrangement information corresponding to each bar by picking the bar portions B1 to B5 with a mouse or the like. FIG. 4 is an explanatory diagram showing an example of the above-mentioned process load pile graph. In the figure, L1 to L10 represent piled load layers classified according to classification conditions arbitrarily specified by an operator, the vertical axis represents the load amount, and the horizontal axis represents the time axis. The operator selects the required plan / arrangement information belonging to each layer by picking the layer portions L1 to L10 with a mouse or the like.

【0026】図5は上記の生産計画シミュレーション装
置の動作を示す流れ図である。同図において、まず生産
計画情報登録手段2により、登録済みの生産計画情報b
の変更または新規登録を行う(S1)。そして、この生
産計画情報bと基準情報群aからMRP計算手段1によ
りMRP計算を行い、計画所要・手配情報cを算出する
(S2)。さらに、この算出結果の計画所要・手配情報
cと基準情報群aから手配引当手段3により手配と所要
の紐つけを行う(S3)。
FIG. 5 is a flowchart showing the operation of the above-mentioned production planning simulation apparatus. In the figure, first, the production plan information b registered by the production plan information registration means 2 is registered.
Is changed or newly registered (S1). Then, MRP calculation is performed by the MRP calculation means 1 from the production plan information b and the reference information group a to calculate the plan required / arranged information c (S2). Further, arrangement and necessary association are performed by the arrangement allocation means 3 based on the plan required / arranged information c and the reference information group a of the calculation result (S3).

【0027】上記の処理の結果を用いて作業者の指示に
より適宜、欠品アラーム手段4により欠品アラーム情報
を表示したり(S4)、ガントチャート表示手段5によ
りガントチャート図を表示したり(S5)、工程情報d
と計画所要・手配情報cとから工程負荷情報算出手段6
により工程負荷情報eを算出し(S6)、これを工程負
荷山積みグラフ表示手段7により工程負荷山積みグラフ
を表示する(S7)。
The out-of-stock alarm information is displayed by the out-of-stock alarm means 4 as appropriate by the operator using the results of the above processing (S4), and the Gantt chart is displayed by the Gantt chart display means 5 (S4). S5), process information d
Process load information calculating means 6 based on the plan required / arranged information c
To calculate the process load information e (S6), and display the process load pile graph by the process load pile graph display means 7 (S7).

【0028】これらの提示された情報を作業者が評価
し、再度S1に戻り生産計画情報を再登録して違う生産
計画でシミュレーションし直して生産計画の立案・調整
を行ったり、これらガントチャート図や工程負荷山積み
グラフ上で調整したい所要・手配をマウスなどのポイン
ティングデバイスで指定し、その情報をグラフ情報逆リ
ンク手段8で調整対象とする所要・手配を抽出してこれ
を生産計画調整手段9で調整し(S8)、再度S3に戻
りシミュレーションして納期遵守,資材調達,工程負荷
を考慮した計画調整を行う。
An operator evaluates the presented information, returns to S1, re-registers the production plan information, re-simulates the production plan with a different production plan, makes a plan / adjustment of the production plan, and executes these Gantt chart diagrams. The required / arrangement to be adjusted on the process load pile graph is designated by a pointing device such as a mouse, and the information is extracted by the graph information reverse linking means 8 to extract the required / arrangement, and this is extracted by the production plan adjusting means 9. (S8), and returns to S3 again to simulate and make a plan adjustment in consideration of delivery date compliance, material procurement, and process load.

【0029】なお、上記の生産計画シミュレーション装
置において、前記品目情報,前記構成情報,前記稼働日
カレンダ情報,前記在庫情報,および前記確定所要・手
配情報を含む基準情報aに属する生産リードタイム,ロ
ットまとめ数量,ロットまとめ期間,部品構成有効期間
などのなかの任意の項目を変更する基準情報変更手段を
設けることもできる。
In the above-described production planning simulation apparatus, the production lead time, lot belonging to the reference information a including the item information, the configuration information, the working day calendar information, the stock information, and the confirmed required / arranged information are included. It is also possible to provide a reference information changing means for changing any item such as a grouping quantity, a lot grouping period, and a component configuration validity period.

【0030】また、上記の生産計画シミュレーション装
置において、前記手配引当手段が送出する手配引当情報
gをタイムバケットごとに手配分と所要分とに区別して
表示するとともに、手持在庫から時系列に所要・手配に
よる在庫推移を表示する在庫推移グラフ表示手段を設け
ることもできる。
Further, in the above-mentioned production planning simulation apparatus, the arrangement allocation information g sent by the arrangement allocation means is displayed separately for each time bucket in order of allocation and required amount. Inventory transition graph display means for displaying inventory transition by arrangement can also be provided.

【0031】また、上記の生産計画シミュレーション装
置において、原価情報や設計情報等の属性情報と前記品
目情報,構成情報,および前記所要・手配情報とを品目
をキーとして関連づける属性情報リンク手段と、前記属
性情報リンク手段で関連づけられた任意の属性情報と品
目情報,構成情報,所要・手配情報を表示する属性情報
表示手段とを設けてもよい。
Further, in the above-mentioned production planning simulation apparatus, the attribute information linking means for associating attribute information such as cost information and design information with the item information, configuration information, and the required / arranged information using the item as a key, Arbitrary attribute information associated with the attribute information linking means may be provided with attribute information displaying means for displaying item information, configuration information, and required / arranged information.

【0032】なお、上記の生産計画シミュレーション装
置において、前記MRP計算手段が送出する計画所要・
手配情報を複数種類管理する複数計画案管理手段を設け
ることによって、複数の生産プロジェクトに対応するこ
とができる。さらに、上記の複数計画案管理手段により
管理されている情報を同時に複数の作業者が調整する場
合に、作業者間のデータ利用の排他処理を行うデータア
クセス管理手段を設けることによって、作業能率を向上
させることができる。
In the above-described production planning simulation apparatus, the schedule required by the MRP calculating means is transmitted.
By providing a plurality of plan management means for managing a plurality of types of arrangement information, a plurality of production projects can be handled. Furthermore, when a plurality of workers simultaneously adjust the information managed by the above-mentioned plurality of plan management means, a data access management means for performing an exclusive process of using data between workers is provided, thereby improving work efficiency. Can be improved.

【0033】[0033]

【発明の効果】以上、詳細に説明したように、本発明の
生産計画シミュレーション装置は、MRP計算結果から
手配の間に合わない計画を抜き出してアラーム表示した
り、MRP計算結果をガントチャートに表示したり、M
RP計算結果を工程負荷まで算出工程負荷山積みグラフ
として視覚的に表現し、MRP計算結果の評価環境を提
供するとともに、生産計画の変更・登録を行うインタフ
ェースと評価に使用するガントチャートや工程負荷山積
みグラフ上でMRP計算結果の調整を行うインタフェー
スとを提供することにより、納期遵守,資材調達,工程
負荷を考慮しながらシミュレーションを行うことができ
るという効果がある。
As described in detail above, the production plan simulation apparatus of the present invention extracts a plan that is not in time for arrangement from the MRP calculation results and displays an alarm or displays the MRP calculation results on a Gantt chart. , M
The RP calculation result is visually expressed as a process load stacking graph up to the process load, providing an evaluation environment for MRP calculation results, an interface for changing and registering production plans, and a Gantt chart and process load stacking used for evaluation. By providing an interface for adjusting the MRP calculation result on the graph, there is an effect that the simulation can be performed while taking into account delivery date, material procurement, and process load.

【0034】また、ロットまとめ数量やロットまとめ期
間,発注数量,部品の切り替え等の基準の見直しを行う
際に、どのような変更を行うと実際の手配状況,在庫推
移,工程負荷にどのような影響があるかを瞬時にグラフ
上でいろいろなパターンを試しながら評価することがで
き、これらのシミュレーション結果とともに原価情報や
設計情報等のMRP計算と直接関係ない情報を統合的に
評価できるという効果がある。
When revising the criteria such as lot lot quantity, lot lot term, order quantity, part switching, etc., what kind of change should be made to the actual arrangement situation, inventory transition, process load, etc. It is possible to evaluate whether there is an effect instantly while trying various patterns on the graph, and the effect that these simulation results and the information that is not directly related to the MRP calculation such as cost information and design information can be integrated and evaluated. is there.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の一形態を示すブロック図であ
る。
FIG. 1 is a block diagram showing an embodiment of the present invention.

【図2】本発明による生産計画情報登録画面の例を示す
説明図である。
FIG. 2 is an explanatory diagram showing an example of a production plan information registration screen according to the present invention.

【図3】本発明によるガントチャートの例を示す説明図
である。
FIG. 3 is an explanatory diagram showing an example of a Gantt chart according to the present invention.

【図4】本発明による工程負荷山積みグラフの例を示す
説明図である。
FIG. 4 is an explanatory diagram showing an example of a process load pile graph according to the present invention.

【図5】本発明の動作を示す流れ図である。FIG. 5 is a flowchart showing the operation of the present invention.

【符号の説明】[Explanation of symbols]

1 MRP計算手段 2 生産計画情報登録手段 3 手配引当手段 4 欠品アラーム手段 5 ガントチャート表示手段 6 工程負荷情報算出手段 7 工程負荷山積みグラフ表示手段 8 グラフ情報逆リンク手段 9 生産計画調整手段 DESCRIPTION OF SYMBOLS 1 MRP calculation means 2 Production plan information registration means 3 Arrangement allocation means 4 Shortage alarm means 5 Gantt chart display means 6 Process load information calculation means 7 Process load pile graph display means 8 Graph information reverse link means 9 Production plan adjustment means

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) B23Q 41/08 G06F 17/60 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 6 , DB name) B23Q 41/08 G06F 17/60

Claims (7)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 製造・調達の対象となる品目の情報が記
述されている品目情報と,品目名の親子関係が記述され
ている構成情報と,対象とする品目を生産する工場の稼
働日カレンダ情報と,対象とする各品目のある時点にお
ける在庫量が記述されている在庫情報と,すでに確定済
みの確定所要情報および確定手配情報と,立案対象であ
る品目の所要日および数量が記述されている生産計画情
報とを入力し、前記品目情報および構成情報を参照して
前記生産計画情報からその構成部品の所要日および所要
量を計算し、前記在庫情報の記録時点を開始点として時
系列に在庫量から確定所要情報および確定手配情報を参
照して前記生産計画情報から展開した新規計画所要およ
び新規計画手配を加減し前記在庫量が品目情報に定義さ
れている条件に合致すると新たに所要・手配を立てるM
RP計算手段と、 生産計画情報の所要日および数量を変更したり新たに生
産計画を追加・削除する生産計画情報登録手段と、 前記生産計画情報登録手段により登録された生産計画情
報をもとにして前記MRP計算手段が計算を行なった結
果の所要・手配情報から各所要・手配の紐づけ関係を表
示する手配引当手段と、 前記MRP計算手段が計算を行った結果の所要・手配情
報から処理日において手配が間に合わないものを抽出し
アラーム表示する欠品アラーム手段と、 前記所要・手配情報の1つ1つをバーとしてグラフ表示
するガントチャート表示手段と、 前記所要・手配情報と,各品目の製造工程手順情報と,
各工程毎の能力情報とからタイムバケット別の工程負荷
情報を算出する工程負荷情報算出手段と、 前記工程負荷情報を指定の条件で分類しタイムバケット
別に棒グラフで表示する工程負荷山積みグラフ表示手段
とを含むことを特徴とする生産計画シミュレーション装
置。
1. Item information in which information of an item to be manufactured / procured is described, configuration information in which a parent-child relationship of an item name is described, and a working day calendar of a factory that manufactures the object item Information, inventory information that describes the stock quantity of each target item at a certain point in time, confirmed finalized information and confirmed arrangement information, and the required date and quantity of the item to be planned. Input the production plan information, calculate the required date and the required amount of the component parts from the production plan information by referring to the item information and the configuration information, and time-series the recording time of the stock information as a starting point. The new plan requirements and new plan orders developed from the production plan information are adjusted by referring to the fixed requirement information and the fixed order information from the stock amount, and the stock amount matches the condition defined in the item information. Then, make a new request / arrangement M
RP calculation means, production plan information registration means for changing the required date and quantity of production plan information, and adding / deleting a new production plan, and production plan information registered by the production plan information registration means. Arrangement allocating means for displaying a linking relationship between each required / arrangement from the required / arranged information obtained as a result of calculation by the MRP calculating means, and processing from the required / arranged information obtained as a result of calculation by the MRP calculating means. Out-of-stock alarm means for extracting alarms that cannot be arranged in the day and displaying an alarm, Gantt chart display means for displaying each of the required / arranged information as a bar, graph, required / arranged information, and each item Manufacturing process procedure information,
A process load information calculating means for calculating process load information for each time bucket from the capacity information for each process; and a process load pile graph displaying means for classifying the process load information under specified conditions and displaying the time load in a bar graph for each time bucket. A production planning simulation device characterized by including:
【請求項2】 請求項1記載の生産計画シミュレーショ
ン装置において、前記ガントチャート表示手段によって
表示されたガントチャート,または工程負荷山積みグラ
フ表示手段によって表示された工程負荷山積みグラフの
所要・手配情報を抽出するグラフ情報逆リンク手段と、
前記グラフ情報逆リンク手段により抽出された所要・手
配情報の所要日・所要数等の情報を変更する生産計画調
整手段とを含むことを特徴とする生産計画シミュレーシ
ョン装置。
2. The production planning simulation apparatus according to claim 1, wherein the required / arranged information of the Gantt chart displayed by the Gantt chart display means or the process load pile graph displayed by the process load pile graph display means is extracted. Graph information reverse link means,
A production plan adjusting device for changing information such as a required date and a required number of required / arranged information extracted by the graph information reverse linking device.
【請求項3】 請求項1または2記載の生産計画シミュ
レーション装置において、前記品目情報,前記構成情
報,前記稼働日カレンダ情報,前記在庫情報,および前
記確定所要・手配情報を含む基準情報に属する生産リー
ドタイム,ロットまとめ数量,ロットまとめ期間,部品
構成有効期間などのなかの任意の項目を変更する基準情
報変更手段を具備することを特徴とする生産計画シミュ
レーション装置。
3. The production planning simulation apparatus according to claim 1, wherein the item information, the configuration information, the working day calendar information, the stock information, and the reference information including the fixed requirement / arrangement information. A production planning simulation apparatus comprising: reference information changing means for changing any item such as a lead time, a lot batching quantity, a lot batching period, and a component configuration validity period.
【請求項4】 請求項1,2,または3記載の生産計画
シミュレーション装置において、前記手配引当手段が送
出する手配引当情報をタイムバケットごとに手配分と所
要分とに区別して表示するとともに手持ち在庫から時系
列に所要・手配による在庫推移を表示する在庫推移グラ
フ表示手段を具備することを特徴とする生産計画シミュ
レーション装置。
4. The production planning simulation apparatus according to claim 1, wherein the arrangement allocation information sent by said arrangement allocation means is displayed separately for each time bucket in a manual distribution and a required amount, and the stock on hand. 1. A production planning simulation apparatus comprising: a stock transition graph displaying means for displaying a stock transition according to requirements / arrangements in chronological order.
【請求項5】 請求項1,2,3,または4記載の生産
計算シミュレーション装置において、原価情報や設計情
報等の属性情報と前記品目情報,前記構成情報,および
前記所要・手配情報とを品目をキーとして関連づける属
性情報リンク手段と、前記属性情報リンク手段で関連づ
けられた任意の属性情報と品目情報,構成情報,所要・
手配情報を表示する属性情報表示手段とを含むことを特
徴とする生産計画シミュレーション装置。
5. The production calculation simulation apparatus according to claim 1, wherein attribute information such as cost information and design information and said item information, said configuration information, and said required / arranged information are included in said item. Attribute information linking means for associating the attribute information as a key, and any attribute information and item information, configuration information, required /
A production plan simulation device comprising: attribute information display means for displaying arrangement information.
【請求項6】 請求項1,2,3,4,または5記載の
生産計画シミュレーション装置において、前記MRP計
算手段が送出する計画所要・手配情報を複数種類管理す
る複数計画案管理手段を具備することを特徴とする生産
計画シミュレーション装置。
6. The production plan simulation apparatus according to claim 1, further comprising a plurality of plan management means for managing a plurality of types of plan requirement / arrangement information sent by said MRP calculation means. A production planning simulation apparatus, characterized in that:
【請求項7】 請求項1,2,3,4,5,または6記
載の生産計画シミュレーション装置において、前記複数
計画案管理手段により管理されている情報を同時に複数
の作業者が調整する場合に作業者間のデータ利用の排他
処理を行うデータアクセス管理手段を含むことを特徴と
する生産計画シミュレーション装置。
7. The production plan simulation apparatus according to claim 1, wherein a plurality of workers simultaneously adjust information managed by said plurality of plan management means. A production plan simulation apparatus including a data access management means for performing exclusive processing of data use between workers.
JP16973396A 1996-06-28 1996-06-28 Production planning simulation device Expired - Fee Related JP2973930B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16973396A JP2973930B2 (en) 1996-06-28 1996-06-28 Production planning simulation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16973396A JP2973930B2 (en) 1996-06-28 1996-06-28 Production planning simulation device

Publications (2)

Publication Number Publication Date
JPH1015786A JPH1015786A (en) 1998-01-20
JP2973930B2 true JP2973930B2 (en) 1999-11-08

Family

ID=15891849

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16973396A Expired - Fee Related JP2973930B2 (en) 1996-06-28 1996-06-28 Production planning simulation device

Country Status (1)

Country Link
JP (1) JP2973930B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4783990B2 (en) * 2001-03-22 2011-09-28 凸版印刷株式会社 Material ordering system, server and method
JP2003044726A (en) * 2001-07-27 2003-02-14 Sumitomo Corp Device, program and method for supporting manufacturing order, terminal and server used for the device, and computer readable recording medium having the program recorded thereon
CN100341003C (en) * 2001-09-14 2007-10-03 刘汝田 Selling and managing device and method for medicinal industry
JP5023714B2 (en) * 2007-01-23 2012-09-12 富士通株式会社 Production plan information output device, production plan information output method, and production management system
JP5068845B2 (en) * 2010-06-17 2012-11-07 株式会社日立製作所 A method and system for integrated production management with full development of core management process using management process matrix table
US8644974B2 (en) 2010-10-14 2014-02-04 Honda Motor Co., Ltd. Computerized system and method for managing supply chain orders
JP6688898B2 (en) * 2016-09-27 2020-04-28 株式会社日立製作所 Order parameter generation support device and order parameter generation method
CN116979529B (en) * 2023-09-22 2023-11-24 国网山西省电力公司太原供电公司 Power load evaluation method, system, equipment and storage medium

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0478661U (en) * 1990-11-20 1992-07-09
JPH04365167A (en) * 1991-06-13 1992-12-17 Nec Corp Production control system
JPH05108656A (en) * 1991-10-15 1993-04-30 Nec Corp Production schedule planning device
JPH05143613A (en) * 1991-11-19 1993-06-11 Brother Ind Ltd Production planning system
JPH0696086A (en) * 1992-09-14 1994-04-08 Hitachi Ltd Comprehensive schedule managing device
JPH07182307A (en) * 1993-12-21 1995-07-21 Sekisui Chem Co Ltd General simulation device for molding factory

Also Published As

Publication number Publication date
JPH1015786A (en) 1998-01-20

Similar Documents

Publication Publication Date Title
US7693593B2 (en) Production planning method and production planning system
Evans et al. Dynamic Supply Chain Performance: Assessing the Impact ofInformation Systems
US8620708B2 (en) Progress status management method, program, and progress status management device
US20080103859A1 (en) Project risk management system utilizing probability distributions
US20090043643A1 (en) Managerial decision support system and method
Zülch et al. Simulation-supported change process for product customization–A case study in a garment company
US7123977B2 (en) Production planning system
KR100844467B1 (en) A simulation system and method for construction progression state with 3d
KR101245151B1 (en) Optimized digital factory production plan & confirm system by using real-time factory situation
KR20080019581A (en) Cost element managing system
CN108846645A (en) A kind of enterprise's flattened management method and system
JP2973930B2 (en) Production planning simulation device
JP2007323680A (en) Management decision support system
KR102411939B1 (en) Method and device for managing project
KR100945523B1 (en) On-line construction management method
JP2016062342A (en) Project management system and integrated process management system
US7778807B2 (en) Simulation model generator of causality phenomena and events
CN115983232A (en) Form system based on view and data integrated design
JP2002244716A (en) Line capacity evaluation system
US20040078172A1 (en) Structured system for the planning, integration, analysis and management of new product development on a real-time, enterprise-wide basis
KR102354181B1 (en) A construction information management system for visualising data and a method for controlling the same
JPH08212273A (en) Suporting device for controlling product cost
JP3695152B2 (en) Cost index calculation device
Sillince A management strategy for innovation and organizational design: the case of MRP2/JIT production management systems
Yimsri et al. Flexible applications of MRP based prototyping software for production planning and diversified raw material inventory management

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990803

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080903

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees