JP2009258833A - Streamlining support method for supply chain - Google Patents
Streamlining support method for supply chain Download PDFInfo
- Publication number
- JP2009258833A JP2009258833A JP2008104585A JP2008104585A JP2009258833A JP 2009258833 A JP2009258833 A JP 2009258833A JP 2008104585 A JP2008104585 A JP 2008104585A JP 2008104585 A JP2008104585 A JP 2008104585A JP 2009258833 A JP2009258833 A JP 2009258833A
- Authority
- JP
- Japan
- Prior art keywords
- information
- sales
- product
- supply chain
- plan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
本発明は、製品が資材調達から生産工程を経て顧客に至るまでのサプライチェーンにおいて、販売計画に変動が生じても、販売計画に支障を生じさせることのない、且つ製品のライフサイクル終了時に生ずる製品及び資材の廃棄ロスの削減を図ることができる、製品及び資材の安全在庫数の最適化に関する。 The present invention does not interfere with the sales plan even if the sales plan fluctuates in the supply chain from the procurement of the material to the customer through the production process, and occurs at the end of the product life cycle. The present invention relates to optimization of the safety stock number of products and materials that can reduce the loss of products and materials.
製品が顧客に届くまでには、資材(以下、部品ともいう)の調達から顧客に届けるまでの複数の業務、例えば、資材調達・生産・販売といった各業務(以下、部門ともいう)が存在し、各業務における業務活動の連携を通じて一連の業務活動が行われる。 There are multiple operations from procurement of materials (hereinafter also referred to as parts) to delivery to customers, for example, operations such as material procurement, production and sales (hereinafter also referred to as departments) before the product reaches the customer. A series of business activities are performed through coordination of business activities in each business.
前記業務は、それぞれ1拠点とは限らず一般的には複数の拠点で構成されることが多い。例えば、販売部門は、複数の販売拠点で構成されることが多い。 The business is not always limited to one site, and is generally composed of a plurality of sites. For example, the sales department is often composed of a plurality of sales bases.
このような一連の業務活動の連鎖、所謂サプライチェーンを最適化(効率化)することが重要な問題として研究されている。 Optimization of such a chain of business activities, the so-called supply chain (efficiency) has been studied as an important issue.
このような複数の業務が存在するサプライチェーンの最適化に際しては、生産量及び納期等の生産情報、調達・生産・物流・販売等の形態及びそれらの拠点についての情報等、複数の観点から考慮することが必要になる。このようなことは、一般的にサプライチェーンマネジメント(SCM)と呼ばれている。 When optimizing a supply chain where there are multiple operations, consider production information such as production volume and delivery date, procurement, production, distribution, sales, etc., and information about their bases from multiple perspectives. It becomes necessary to do. Such a thing is generally called supply chain management (SCM).
このようなことからサプライチェーンの最適化のために、サプライチェーンモデルを作成しシミュレーターでシミュレーションを行いサプライチェーンの最適化を図る方法の開発が行われてきている。 For this reason, in order to optimize the supply chain, methods for creating a supply chain model and simulating with a simulator to optimize the supply chain have been developed.
また、前記サプライチェーンにおいては、そのチェーンの中に物の流れ、情報等の捕捉に弱い部分、例えば在庫数量が不明確等、があるとサプライチェーンが崩れる恐れがある。したがって、資材の調達から顧客に届けるまでの資材の調達・生産・販売といった業務活動の物と情報の流れを最適化するためには、サプライチェーン内の全ての業務で、リアルタイムで物の流れが捉えられている必要がある。そのため、企業の基幹業務を対象に、ERP(Enterprise Resource Planning)パッケージと呼ばれる情報システム・パッケージの導入が進められてきている。 In addition, in the supply chain, if there is a weak part in the chain, such as the flow of information or information, such as an unclear stock quantity, the supply chain may be broken. Therefore, in order to optimize the flow of materials and information on business activities such as procurement, production and sales of materials from the procurement of materials to delivery to customers, the flow of materials in all operations in the supply chain Need to be captured. Therefore, introduction of an information system package called an ERP (Enterprise Resource Planning) package has been promoted for the core business of a company.
前記ERPパッケージとは統合業務パッケージであり、販売・生産・物流・財務等の企業活動全般にわたる業務を全社的に統合した企業情報システムのパッケージソフトウェアである。各部門に別々に構築されていたシステムを統合し、相互に参照・利用できるようにしようというもので、財務会計や人事等のデータの一元管理、システムのバージョンアップや保守点検の容易化、他部門の作業のリアルタイムな参照等も可能になるものである。 The ERP package is an integrated business package, which is package software for an enterprise information system that integrates the entire enterprise activities such as sales, production, logistics, and finance. It is intended to integrate systems built separately in each department so that they can be referred to and used by each department. Centralized management of data such as financial accounting and personnel, system upgrades and easy maintenance inspections, etc. It is possible to refer to the work of the department in real time.
前記サプライチェーンにおいては、顧客からの注文に応じて販売・生産計画を立案し、社外や他工場(以下、サプライヤーと言う)から資材を調達し、生産工程で生産活動が行われる。 In the supply chain, sales and production plans are made according to orders from customers, materials are procured from outside and other factories (hereinafter referred to as suppliers), and production activities are performed in the production process.
図1は、サプライチェーンの一例を示す概略図である。図1において、顧客21は、製品を購入する販売拠点22に製品を発注する。販売拠点22は、顧客21からの注文及び販売拠点22での販売予測等を基に販売計画を作成し、販売部門23に発注する。ここで、販売拠点22とは、製品を生産する製造会社の販売部門の販売店、及び製造会社とは独立した、例えば特約店、代理店等の販売会社等をいう。
FIG. 1 is a schematic diagram illustrating an example of a supply chain. In FIG. 1, a
販売部門23は、複数の販売拠点22からの注文、販売部門23での在庫計画等を基に需要計画を作成し、製品を生産部門24に発注する。ここで販売部門23とは、各販売拠点からの注文、入出庫情報及び販売情報等を統括する業務を有し、製品を一時在庫する拠点倉庫42を有する。また、販売部門23は、前記製造会社の一部門であることが多い。販売部門23は、地域毎、例えば国内においては市、県毎等、国外においては州、郡毎等に複数設けられる場合もある。
The sales department 23 creates a demand plan based on orders from a plurality of
生産部門24は、販売部門23からの需要計画に基づき製品及び資材の工場在庫を考慮し、製品の出荷、工場での生産数量を決め、資材調達部門25に資材の発注を行う。資材発注部門は、複数のサプライヤー26に資材の発注を行い、資材を調達する。
The
図1において、実線の矢印は注文等の情報の流れを示し、破線の矢印は物の流れを示す。 In FIG. 1, solid arrows indicate the flow of information such as orders, and broken arrows indicate the flow of goods.
前記製品の発注に際し、一般的に製品の発注確定情報以外に、調達を円滑に行うため、調達側(発注側)より供給側に将来の製品発注見込み情報(フォーキャスト情報)が通知される。前記フォーキャスト情報は、所定期日に製品発注確定情報(確定情報)へと変更される。これにより、供給側は、将来の生産計画を立てることができ、過剰在庫や欠品の発生を抑制することが可能となる。図1の例では、販売拠点から販売部門へは販売見込み情報及び販売確定情報であり、販売部門から生産部門へは需要見込み情報及び需要確定情報である。 When placing an order for the product, in general, in addition to the order confirmation information for the product, the procurement side (ordering side) notifies future supply information (forecast information) from the procurement side (ordering side) to the supply side. The forecast information is changed to product order confirmation information (confirmation information) on a predetermined date. As a result, the supply side can make a future production plan, and it is possible to suppress the occurrence of excess inventory and shortage. In the example of FIG. 1, sales prospect information and sales confirmation information from the sales base to the sales department are demand forecast information and demand confirmation information from the sales department to the production department.
しかしながら、顧客からの注文は一定で推移するとは限らず、販売計画に変動が生じる場合がある。これにより、フォーキャスト情報から確定情報への変更時に、需要及び生産計画変動が生じる。このため、特に販売計画の増加変動に対して、資材の欠品による生産遅延及び製品在庫の不足による出荷遅延を防ぎつつ、資材及び製品の不要な在庫の発生を防ぎ、在庫費用を最小とすることが望まれる。 However, orders from customers do not always stay constant, and sales plans may vary. This causes demand and production plan fluctuations when changing from forecast information to confirmed information. For this reason, especially in response to an increase in the sales plan, it prevents production delays due to material shortages and shipment delays due to insufficient product inventory, while preventing unnecessary inventory of materials and products and minimizing inventory costs. It is desirable.
また、製品が販売開始されてから販売終了に至る、所謂製品のライフサイクルは、一般的に導入期、成長期、成熟期、衰退期の段階を経ると考えられている。前記衰退期には需要量が減少し、製品寿命が終了する時期、所謂End Of Life(エンド・オブ・ライフ、以下EOLとも略す)となる。したがって、前記EOL時点における資材、特に該当製品の専用資材及び製品の在庫は、余剰在庫として残り、廃棄され廃棄ロスを生じることがある。このため、前記廃棄ロスの削減が望まれる。 The so-called product life cycle from the start of sales to the end of sales is generally considered to go through the stages of introduction, growth, maturity, and decline. During the decline period, the amount of demand decreases and the product life ends, so-called End Of Life (hereinafter also abbreviated as EOL). Accordingly, the materials at the time of the EOL, particularly the dedicated materials for the corresponding product and the stock of the product may remain as surplus stock and be discarded to cause a disposal loss. For this reason, reduction of the waste loss is desired.
上記に対し、過去のフォーキャスト情報とこれに対応する受注実績から前記過去のフォーキャスト情報の誤差、前記誤差の平均値及び前記誤差の標準偏差を算出し、現在のフォーキャスト情報を補正することにより、発注量を算出することが開示されている。(例えば、特許文献1参照)。 In contrast to the above, calculating the error of the past forecast information, the average value of the error, and the standard deviation of the error from the past forecast information and the order received corresponding thereto, and correcting the current forecast information The calculation of the order quantity is disclosed. (For example, refer to Patent Document 1).
また、サプライチェーンモデルを評価指標に基づき評価し、最適なサプライチェーンモデルを設定してそれを基に最適なサプライチェーン構築することが開示されている(例えば、特許文献2参照)。 In addition, it is disclosed that a supply chain model is evaluated based on an evaluation index, an optimal supply chain model is set, and an optimal supply chain is constructed based on the optimal supply chain model (see, for example, Patent Document 2).
また、コンピューターが、顧客が使用する製品の製造時期または使用開始時期を含む時期情報を取得し、需要予測する期間と前記取得した時期情報とを対照し、需要予測期間に製品寿命が到来する対象製品を抽出することが、開示されている(例えば、特許文献3参照)。
特許文献1は、現在のフォーキャスト情報を補正し、発注量を算出することにより、受注側では高精度な受注予測を行うことができ、これにより、欠品の発生や過剰な在庫の発生を効果的に抑制することを図るものである。しかし、急な発注の変更等の場合に欠品の発生の有無の予測がつかず、欠品が生ずることがあった。
特許文献2は、稼働中のサプライチェーンの形態をサプライチェーンモデルとしてシミュレーションを行うことにより、稼働中のサプライチェーンの調達から消費者に届けるまでの資材や部品の調達・生産・物流・販売といった業務活動の物と情報の流れを最適化するものである。しかしながら、販売及び需要変動時の対応は考慮されていない。
特許文献3は、要求される時期にその要求量にあわせてタイミングよく、しかも経済的に生産するための、精度及び効率に優れた需要予測方法を提供するものである。しかしながら、生産部門での資材在庫の調整については言及されておらず、資材在庫が過剰になる恐れがあった。
従来、想定していた以上の急な製品の注文増が生じた場合の対応として、製品、資材の在庫数を多めに持つことが一般的に行われていた。このような在庫数を多くする方法では、製品の納期遅延を減少させることができる。しかしながら、資材調達部門では、納入リードタイムの長い資材(部品)、所謂長納期部品については、安全在庫を持つことになる。生産部門では、生産リードタイムの長い製品については、工程で仕掛品及び製品を安全在庫として持つことになる。一方、販売部門では、生産部門での資材欠品による製品納期遅れが生じた場合等の対応策として、製品を安全在庫として持つことになる。このようにサプライチェーンの部門毎にそれぞれ独自に対応した形態で安全在庫を持つこととなり、サプライチェーン全体では過剰な在庫数となる場合が多い。それにともない、在庫費用も増大し、その状態が維持される恐れがあった。 Conventionally, in order to cope with a sudden increase in orders for products more than expected, it has been generally performed to have a large number of products and materials in stock. Such a method for increasing the number of stocks can reduce the delay in delivery of products. However, the material procurement department has a safety stock for materials (parts) having a long delivery lead time, so-called long delivery parts. In the production department, for products with a long production lead time, the work-in-process and products are held as safety stock in the process. On the other hand, the sales department will have the product as a safety stock as a countermeasure when the product delivery time is delayed due to a material shortage in the production department. In this way, each department in the supply chain has a safety stock in a form corresponding to each department, and the entire supply chain often has an excessive number of inventory. Along with this, inventory costs also increased, and there was a risk that the state would be maintained.
ここで、販売拠点からの注文増が想定していた以上の場合、生産部門からの調達で対応できる程度に納期が十分にある場合は、前述の販売部門での安全在庫は想定内の安全在庫で問題がないが、一般的には通常の納期とされる場合が多い。このため、前述の販売部門での安全在庫は、生産部門からの調達における出荷リードタイム(LT)と物流リードタイム(LT)の合計と納期の差に相当する数量に加え、販売変動での増加分を考慮した数量となることが多い。 Here, if the increase in orders from the sales base is more than expected, and if the delivery date is sufficient to be able to handle the procurement from the production department, the safety stock in the sales department mentioned above is the expected safety stock. There is no problem with this, but in general there are many cases where a normal delivery date is used. For this reason, the above-mentioned safety stock in the sales department increased due to sales fluctuations in addition to the quantity corresponding to the difference between the delivery lead time (LT) and the distribution lead time (LT) in procurement from the production department and the delivery date. Often the quantity takes into account minutes.
前記出荷LTとは販売部門が生産部門に発注して、製品が生産部門より出荷されるまでの時間(日数)であり、物流LTとは製品が生産部門より出荷され販売部門(拠点倉庫)入荷するまでの時間(日数)である。また、出荷LTと物流LTの合計と納期の差に相当する数量とは、例えば出荷LTが2日、物流LTが5日、納期4日の場合は、日数差は3日であり、3日分の数量となる。これは受注と発注が同日の場合であり、異なる場合は更にその日数分が必要となることがある。 The shipping LT is the time (days) from when the sales department places an order to the production department and the product is shipped from the production department. The logistics LT is the product is shipped from the production department and received at the sales department (base warehouse). This is the time (number of days) to complete. Also, the quantity corresponding to the difference between the sum of the shipping LT and the logistics LT and the delivery date is, for example, 2 days for the shipping LT, 5 days for the logistics LT, and 4 days for the delivery date. The quantity of minutes. This is the case where the order and the order are on the same day, and if they are different, it may be necessary for the number of days.
また、前述のように製品が販売開始されてから販売終了に至る、所謂製品のライフサイクルは、一般的に導入期、成長期、成熟期、衰退期の段階を経ると考えられている。前記衰退期には需要量が減少し、製品寿命が終了する時期、所謂EOL(End Of Life)となる。 Further, as described above, the so-called product life cycle from the start of sales of products to the end of sales is generally considered to go through the stages of introduction, growth, maturity, and decline. During the decline period, the amount of demand decreases and the product life ends, so-called EOL (End Of Life).
このため、前述のように各部門で一定の安全在庫を持つと、EOL時に資材、特に当該製品の専用資材及び売れ残った製品は余剰在庫として残ってしまうことがある。前記専用資材及び製品余剰在庫は、廃棄され廃棄ロスとなることが多かった。特に、前記専用資材及び製品の余剰在庫は、顧客の需要が少ない製品のような場合、一定の安全在庫を設定すると実需要以上に生産が行われ多くなることが多い。また、前記安全在庫の変更はEOL時点で行うのでは遅くなり、前述のように余剰在庫が多くなり、廃棄ロスの増加になった。 For this reason, as described above, if each department has a certain safety stock, materials, particularly materials dedicated to the product and unsold products may remain as surplus stock during EOL. In many cases, the dedicated materials and the excess product inventory are discarded and result in disposal loss. In particular, the surplus inventory of the dedicated materials and products often increases more than the actual demand if a certain safety stock is set in the case of a product with less customer demand. Further, the change of the safety stock is delayed when it is performed at the time of EOL, and as described above, the surplus stock increases and the disposal loss increases.
前記特許文献1〜3では、このようなライフサイクルの各段階における専用資材及び製品の安全在庫については考慮されておらず、前記EOL時点での製品の余剰在庫及び廃棄ロスを減少させることは困難であった。
In
本発明は、上記状況に鑑みなされたもので、当初想定した販売変動を上回る急な販売数増加の販売計画変動が生じても資材の欠品による生産遅延及び製品在庫の不足による出荷遅延を防止でき、且つ製品寿命が終了する時点での製品及び専用資材の余剰在庫の最小化を図ることができるサプライチェーンの効率化支援方法を提供することを目的とする。 The present invention has been made in view of the above situation, and prevents delays in production due to a shortage of materials and shipment delays due to a shortage of product inventory even if a sales plan fluctuation with a sudden increase in sales exceeding the initially assumed fluctuation in sales occurs. An object of the present invention is to provide a supply chain efficiency support method capable of minimizing excess inventory of products and dedicated materials at the end of the product life.
上記目的は、下記の方法により達成される。
1.製品の販売数量の販売計画と前記製品の調達数量の需要計画とが、将来の販売及び需要見込み情報(フォーキャスト情報)から販売及び需要確定情報へと移行する、また販売及び需要変動の生じることがある販売計画及び需要計画を含む、資材調達から生産工程を経て顧客に至る複数の業務からなるサプライチェーンの効率化支援方法であって、
前記サプライチェーンをモデル化したサプライチェーンモデルをコンピューター上に設定するステップと、
前記サプライチェーンにおける単位期間の期首の販売計画及び需要計画に対し、変動を想定した変動販売計画及び変動需要計画と、該変動需要計画に基づく変動生産計画を立案し、変動情報として格納手段に格納するステップと、
前記変動販売計画及び変動需要計画を上回る拡大変動を想定した拡大変動販売計画及び拡大変動需要計画と、該拡大変動需要計画に基づく拡大変動生産計画を立案し、拡大変動情報として格納手段に入力するステップと、
製品情報、生産情報、物流ルート情報を格納したERP(Enterprise Resource Planning)パッケージから各情報を、前記格納手段から前記変動情報及び前記拡大変動情報を、取り入れ、これらの情報を基に、シミュレーションデータを作成するシミュレーションデータ作成手段で前記シミュレーションデータを作成し、前記格納手段に格納するステップと、
前記サプライチェーンモデルで、前記シミュレーションデータに基づき、シミュレーターで前記変動に対応したシミュレーションを行い、変動時に製品の欠品を起こさない、且つ製品及び資材の在庫費用が最小となる製品及び資材の安全在庫数を算出するステップと、
前記期首を起点とした製品の残りのライフサイクルでの需要予測データを策定するステップと、
前記サプライチェーンモデルで、前記シミュレーションデータ及び前記需要予測データに基づき、シミュレーターで前記拡大変動に対応したシミュレーションを行い、拡大変動時に製品の欠品を起こさない、製品及び資材の最小安全在庫数と製品及び資材の物流ルートを算出するステップと、を有し、
前記ステップでの一連の処理が、所定の単位期間毎の周期で行われることを特徴とするサプライチェーンの効率化支援方法。
2.前記複数の業務は、資材調達業務、生産業務、販売業務及び販売拠点業務を含むことを特徴とする1に記載のサプライチェーンの効率化支援方法。
3.前記資材は、前記生産業務での仕掛品を含むことを特徴とする1または2に記載のサプライチェーンの効率化支援方法。
4.前記製品情報は、製品に使用する資材とその資材の数量、製品の工程表及び構成のデータを含むことを特徴とする1乃至3の何れか1項に記載のサプライチェーンの効率化支援方法。
5.前記生産情報は、製品の生産量と納期の生産計画情報、資材の在庫情報と発注情報と納期情報と価格情報、生産及び販売での製品在庫情報を含むことを特徴とする1乃至4の何れか1項に記載のサプライチェーンの効率化支援方法。
6.前記物流ルート情報は、製品及び資材の物流ルートの、物流リードタイム及び物流費用を含むことを特徴とする1乃至5の何れか1項に記載のサプライチェーンの効率化支援方法。
7.前記シミュレーションに際し、格納手段に格納された前記サプライチェーンの拠点の情報・通信環境の状態に関する情報・通信環境情報と物流の状態に関する物流情報とを取り出し加味して、シミュレーションを行うことを特徴とする1乃至6の何れか1項に記載のサプライチェーンの効率化支援方法。
The above object is achieved by the following method.
1. The sales plan for the sales volume of the product and the demand plan for the procurement quantity of the product are shifted from the future sales and demand forecast information (forecast information) to the sales and demand confirmation information, and sales and demand fluctuations occur. A supply chain efficiency support method comprising a plurality of operations ranging from material procurement to production processes, including a sales plan and a demand plan,
Setting a supply chain model that models the supply chain on a computer;
For the sales plan and demand plan at the beginning of the unit period in the supply chain, a variable sales plan and variable demand plan that assumes fluctuations, and a variable production plan based on the variable demand plan are drawn up and stored in the storage means as fluctuation information And steps to
An expansion variable sales plan and an expansion variable demand plan assuming an expansion fluctuation exceeding the variable sales plan and the variable demand plan, and an expansion variable production plan based on the expansion variable demand plan are drawn up and input to the storage means as expansion fluctuation information Steps,
Each piece of information is taken from an ERP (Enterprise Resource Planning) package that stores product information, production information, and distribution route information, and the fluctuation information and the enlarged fluctuation information are taken from the storage means, and simulation data is obtained based on these information. Creating the simulation data in the simulation data creation means to create, and storing in the storage means;
In the supply chain model, based on the simulation data, a simulation corresponding to the fluctuation is performed by a simulator, and the stock of the product and the material that does not cause a product shortage at the time of the fluctuation and minimizes the inventory cost of the product and the material is minimized. Calculating a number;
Formulating demand forecast data for the remaining lifecycle of the product starting from the beginning;
Based on the simulation data and the demand forecast data in the supply chain model, a simulation corresponding to the expansion variation is performed by a simulator, and the minimum safe stock number of products and materials and products that do not cause a product shortage at the time of expansion variation And calculating a material distribution route,
A supply chain efficiency support method, wherein a series of processing in the steps is performed at a cycle of a predetermined unit period.
2. 2. The supply chain efficiency support method according to 1, wherein the plurality of operations include a material procurement operation, a production operation, a sales operation, and a sales base operation.
3. 3. The supply chain efficiency support method according to 1 or 2, wherein the material includes work-in-process items in the production operation.
4). 4. The supply chain efficiency support method according to any one of
5. The production information includes production plan information of product production volume and delivery date, stock information of materials, ordering information, delivery date information and price information, and product inventory information in production and sales. The supply chain efficiency support method according to
6). 6. The supply chain efficiency support method according to any one of 1 to 5, wherein the distribution route information includes distribution lead time and distribution cost of distribution routes of products and materials.
7). In the simulation, the supply chain base information stored in the storage means, information related to the communication environment status, communication environment information, and distribution information related to the distribution status are extracted and added to perform the simulation. 7. The supply chain efficiency support method according to any one of 1 to 6.
上記により、当初想定した販売変動を上回る販売変動が生じても資材の欠品による生産遅延及び製品在庫の不足による出荷遅延を防止できる。また、製品のライフサイクルの時期に応じて、製品の残りのライフサイクルでの需要を考慮した資材及び製品の在庫数の最小化を図ることができ、製品寿命が終了する時点での専用資材及び製品の廃棄ロスの削減を図ることができる。 As described above, it is possible to prevent a delay in production due to a shortage of materials and a delay in shipment due to a shortage of product inventory even if a sales fluctuation exceeding the sales fluctuation assumed at the beginning occurs. In addition, depending on the timing of the product life cycle, it is possible to minimize the number of materials and product inventory that take into account the demand in the remaining life cycle of the product. Product waste loss can be reduced.
以下、図を参照しながら本発明の実施の形態を説明するが、本発明はこれに限定されるものではない。 Hereinafter, embodiments of the present invention will be described with reference to the drawings, but the present invention is not limited thereto.
図6は、発注フォーキャスト情報(以下、フォーキャストともいう)及び発注確定情報(以下、発注確定ともいう)の推移の例を表すテーブルである。図6では、発注間隔、フォーキャスト発信間隔及び納入リードタイムを1週間とした例である。これらの間隔は、製品及び資材の種類によって適宜設定されるものであり、例えば2週間であったり、1か月であったりする。また間隔はそれぞれ異なっていてもよい。また、図6では発注確定をPO、フォーキャストをFCと記す。 FIG. 6 is a table showing an example of changes in order forecast information (hereinafter also referred to as forecast) and order confirmation information (hereinafter also referred to as order confirmation). FIG. 6 shows an example in which the order interval, the forecast transmission interval, and the delivery lead time are set to one week. These intervals are appropriately set depending on the types of products and materials, and are, for example, two weeks or one month. The intervals may be different. In FIG. 6, the order confirmation is denoted as PO and the forecast as FC.
最初の受注により立案された発注計画に従い、発注予定1週に発注確定のPO1が発注されるとともに、フォーキャストのFC1が発信される。PO1は、2週に納入される。2週には、FC1がPO2に変更され発注されるとともに、フォーキャストのFC2が発信される。PO2は、3週に納入される。以下、同様に推移する。図6は、納入が9週で完了する例である。 In accordance with the ordering plan prepared by the first order, PO1 for order confirmation is ordered in one week of the planned ordering, and a forward FC1 is transmitted. PO1 is delivered in 2 weeks. In 2 weeks, FC1 is changed to PO2 and an order is placed, and a forecast FC2 is transmitted. PO2 is delivered in 3 weeks. The same goes for the following. FIG. 6 shows an example in which delivery is completed in nine weeks.
図6の例では、前記発注は1週間毎に前記生産計画に基づいてMRP(Material Requirement Planning)等によって資材所要量計画が作成され行われる。 In the example of FIG. 6, the ordering is performed by creating a material requirement plan by MRP (Material Requirements Planning) or the like based on the production plan every week.
また、フォーキャストと発注確定の間に、更に発注情報、例えば予約情報(予約)等を設けてもよい。この場合、一例を挙げるとフォーキャストは、資材の買い取りは確約ではなく、予約は、買い取りは確約であるが時期は確約ではなく、発注確定は、買い取りも時期も確約したものとしてもよい。 Further, order information such as reservation information (reservation) may be provided between forecast and order confirmation. In this case, as an example, Forecast is not a commitment to purchase materials, and reservation is a commitment to purchase, but is not a commitment, and order confirmation may be a commitment that both purchase and timing are committed.
図2、3及び4は、製品の発注情報がフォーキャストから発注確定へと移行する、且つ販売計画変動により需要及び生産変動の起こることがある需要及び生産計画を含む、資材調達から生産工程を経て顧客(製品出荷先)に至る製品のサプライチェーンの効率化を図るサプライチェーンの効率化支援方法の一実施の形態を示すフロー図である。前記フロー図は図示の関係上、図2、3及び4に分割して示すが、図2、3及び4は一体を成すものである。また、サプライチェーン20は、図1を参照する。
Figures 2, 3 and 4 show the process from material procurement to production process, including demand and production plans where product ordering information shifts from forecast to final order and demand and production fluctuations can occur due to sales plan fluctuations. It is a flowchart which shows one Embodiment of the efficiency improvement support method of the supply chain which aims at the efficiency improvement of the supply chain of the product which goes through via a customer (product shipping destination). Although the flow diagram is divided into FIGS. 2, 3 and 4 for the purpose of illustration, FIGS. 2, 3 and 4 are integrated. For the
図3において、データベース1は、前述の各種データ及び情報を格納する格納手段であり、ERPパッケージ2のデータ、情報も中継プログラム6及びシミュレーションデータ作成手段であるデータ変換部7を介して、必要に応じ取り込まれる。また、後述の、データ変換部7で作成されたシミュレーションデータも取り込まれる。なお、ERPパッケージ2のデータ、情報の内、データ変換部7で用いないデータ、情報は、データ変換部7を介さず中継プログラム6を介して直接データベース1に取り込んでもよい。
In FIG. 3, the
ERPパッケージ2は統合業務パッケージであり、統合データベースを有し、製品情報、生産情報、物流ルート情報等が格納される。前記製品情報は製品に使用する資材とその資材の数量、製品の工程表及び構成のデータ等から、生産情報は製品の生産量、生産リードタイム、納期、資材の納入ルート、納入リードタイム、在庫、発注、納期、価格の各情報、製品在庫情報等からなる。物流ルート情報は、資材調達に使用される通常物流ルート及び臨時物流ルートにおける資材別の物流リードタイム及び物流費用を含む。
The
販売計画作成部3は、サプライチェーン20における単位期間の期首の顧客21の実需要(注文)に基づき販売計画を作成する。販売計画作成部3は、販売拠点22内の、例えば、管理部門に設けられる。前記販売計画は、需要計画作成部41に伝達される。前記単位期間とは、製品の生産・販売計画を作成する、ある所定の期間のことであり、生産・販売は単位期間の継続で行われる。例えば、1か月毎、3か月毎等、製品の種類、形態等により適宜設定される。前記単位期間は、常に一定の長さである必要はなく、例えば、製品のライフサイクルの各段階、導入期、成長期、成熟期、衰退期等で期間の長さを変えてもよい。また、実需要が、ある幅で変動する毎としてもよい。
The sales
需要計画作成部41は、前記販売計画、拠点倉庫42の製品在庫情報、入出庫情報を基に、また販売変動を考慮して需要計画を作成する。また、前記単位期間が、予め想定した製品のライフサイクルのどの段階にあるかを判別し、EOL段階情報を作成する。
The demand
拠点倉庫42は、生産部門24より納入された製品を一時保管し、販売拠点22からの出荷要請(受注)により製品を出荷する。拠点倉庫42の情報としては、製品在庫情報、入出荷情報等がある。需要計画作成部41及び拠点倉庫42は販売部門23内の、例えば調達管理部門に設けられる。前記需要計画及びEOL段階情報は、生産計画作成部5に伝達される。
The
生産計画作成部5は、前記需要計画を基に、資材調達、工場、物流の各制約条件及び生産部門24での製品在庫状況を考慮して生産計画を作成する。資材調達の制約条件は、部品生産能力、資材の納入リードタイム、サプライヤーとの間の資材発注契約等がある。前記工場の制約条件は、生産リードタイム、工程の最大生産能力、工程の生産能力切り換え条件等がある。物流の制約条件は、製品の出荷及び物流リードタイム、物流能力、倉庫在庫能力等がある。生産計画作成部5は、生産部門24内の、例えば、生産管理部門に設けられる。
Based on the demand plan, the production
前記販売計画、需要計画、EOL段階情報、拠点倉庫及び前記生産計画の各情報は、中継プログラム6及びデータ変換部7を介してデータベース1、ERPパッケージ2に入力される。これらの計画及び情報は、対象となる製品のサプライチェーン20に単位期間の期首に適用される。
The sales plan, demand plan, EOL stage information, base warehouse, and production plan information are input to the
前記需要計画に対し、需要計画作成部41で販売での変動を想定し、仮想の販売での変動情報が設定される。前記販売での変動は、最初に想定される販売変動と前記販売変動を上回る拡大販売変動とが設定される。販売変動は、販売拠点22での顧客受注変動、過去の類似製品の販売変動等を考慮して機種に応じ適宜設定される。拡大販売変動は、生産部門24が生産できる最大生産能力等を参照して、当該製品の販売見込み最大数等を考慮して適宜設定される。例えば、3倍、4倍等である。
With respect to the demand plan, the demand
次に、同じく需要計画作成部41で前記販売変動情報、拠点倉庫42の製品在庫情報、入出庫情報を基に、変動需要計画及び拡大変動需要計画が作成される。
Next, similarly, the demand
前記変動需要計画及び前記拡大変動需要計画は、生産計画作成部5に伝達される。生産計画作成部5は、前記販売変動、前記拡大変動需要計画及び前記制約条件を基に変動生産計画及び拡大変動生産計画を作成する。
The variable demand plan and the expanded variable demand plan are transmitted to the production
上記の各変動及び各計画は、中継プログラム6及びデータ変換部7を介してデータベース1、ERPパッケージ2に入力される。
Each variation and each plan is input to the
データ変換部7は、ERPパッケージ2に格納されている前記製品情報及び前記生産情報を基にシミュレーションデータを作成する。
The
データ変換部7を設け、前記データ変換部7をERPパッケージ2、販売計画作成部3、需要計画作成部41、拠点倉庫42及び生産計画作成部5と結びつけることにより、最新の情報を用いてシミュレーションデータを作成することができる。例えば、設計変更が生じてERPパッケージ2のデータが修正された場合等においても、常にERPパッケージ2の最新のデータに基づきデータ変換部7でシミュレーションデータを作成することができる。このため、実際の系に近い、且つ精度の高いシミュレーションが可能になる。また、予めシミュレーションデータを作成することにより、後述のシミュレーション実行時に、シミュレーションデータを作成する負荷を軽減することができ、迅速なシミュレーションを行うことができる。
A
モデル作成部8は、データベース1に格納されたサプライチェーンの構成等の情報を基に、サプライチェーンモデルをコンピューター上に前記シミュレーションデータに基づき設定する。前記サプライチェーンモデルは、実際のサプライチェーンを模擬的にコンピューター上に仮想サプライチェーンとして再現したものである。実際のサプライチェーンの物の流れ、各作業等をコンピューター上に模擬的に再現することができる。
The
モデル作成部8で設定されるサプライチェーンモデルは、前記販売変動に基づくシミュレーションを行うモデルで、製品及び資材の供給は通常物流ルートで設定される。以下、前記サプライチェーンモデルをモデル1とも称す。
The supply chain model set by the
ここで物流ルートは、船便、自動車便、航空便等種々挙げられるが、一般的に物流ルートは、物流リードタイムが長い、例えば船便等では物流費用は安く、物流リードタイムが短い、例えば航空便等では高くなる。このため、通常は、物流ルートとして物流リードタイムが長いが物流費用が安い、例えば船便等が通常物流ルートとして用いられることが多い。これに対し、物流リードタイムが短いが物流費用が高く、臨時的に用いられる物流ルートを臨時物流ルートと称する。 Here, there are various logistics routes such as sea mail, automobile mail, air mail, etc. Generally, the logistics route has a long logistics lead time, for example, shipping costs are low, and the logistics lead time is short, for example, air mail. And so on. For this reason, usually, a logistics lead time is long as a logistics route but a logistics cost is low. For example, a shipping service is often used as a regular logistics route. On the other hand, a logistics route that has a short logistics lead time but high logistics costs and is temporarily used is referred to as a temporary logistics route.
シミュレーション条件設定部9で、シミュレーション期間、例えば販売変動設定をしたどの期間まで、或いは、始めとする単位期間以後のどの単位期間までシミュレーションを行うか等、また期首在庫の設定、単位期間の販売量の設定等のパラメータの設定、等のシミュレーション条件の設定を行う。
In the simulation
シミュレーション部10で、前記シミュレーションデータ及び前記シミュレーション条件に基づき、シミュレーターでモデル1を用いシミュレーションが行われる。
Based on the simulation data and the simulation conditions, the
前記シミュレーションにより、販売変動時に、拠点倉庫42及び生産部門24での製品在庫及び生産部門24での資材在庫の費用が最小となり且つ欠品を起こさない、変動安全在庫数が算出される。
According to the simulation, when the sales fluctuate, the variable safety stock number is calculated so that the cost of the product stock in the
結果評価部11で、前記シミュレーションの結果(変動安全在庫数)を評価検討し、更に条件を変えてシミュレーションする必要のある場合は、再度シミュレーション条件設定部9で条件を設定してシミュレーションを行うことができる。これにより、評価の範囲を広げることが可能になる。
The
前記シミュレーション結果の情報は、変動安全在庫設定値としてフィードバックされ、データベース1に格納され、更にERPパッケージ2に転送し反映される。ERPパッケージ2に転送された前記シミュレーション結果はサプライチェーン20に取り込まれ、実際の製品の在庫計画、資材所要量計画作成、発注確定、フォーキャストに反映される。
The simulation result information is fed back as a variable safety stock set value, stored in the
次に、モデル作成部12でデータベース1に格納されたサプライチェーンの構成等の情報を基に、拡大販売変動に基づきシミュレーションを行うサプライチェーンモデルが、コンピューター上に前記シミュレーションデータに基づき設定される。モデル作成部12で設定されるサプライチェーンモデルをモデル2と称す。
Next, on the basis of the simulation data, a supply chain model for performing a simulation based on the expanded sales fluctuation is set based on information such as the supply chain configuration stored in the
モデル2は、前述のモデル1に対し、製品及び資材の物流ルートに臨時物流ルート(航空便等)が加えられ、通常物流ルート(船便等)及び臨時物流ルートで供給した場合の製品及び資材の物流リードタイム及び物流費用、更に拠点倉庫情報が加えられる。モデル2は前記物流費と製品及び資材の在庫計算機能、生産部門24の資材、製品の安全在庫及び拠点倉庫42の製品安全在庫の削減機能を有する。
更に、前述のEOL段階情報を参照して、前記単位期間の期首からEOLまでの、残りのライフサイクルでの需要予測データを策定する。前記需要予測データは、一般に提案されている既知の需要予測の手法を実現するアプリケーションプログラム(需要予測ツール)を、製品特性にあわせて取捨選択して、モデル2に加え、コンピューター上で使用し、策定される。
Furthermore, with reference to the above-mentioned EOL stage information, demand forecast data in the remaining life cycle from the beginning of the unit period to EOL is formulated. For the demand forecast data, an application program (demand forecasting tool) that realizes a known demand forecasting method that has been generally proposed is selected according to product characteristics, added to
前記資材及び前記製品安全在庫の削減機能は、生産部門24における資材、生産部門24及び拠点倉庫42における製品安全在庫数を最小にするための資材及び製品の物流リードタイムを短縮する臨時物流ルートを選定し、資材及び製品安全在庫数を算出する。
The material and product safety stock reduction function provides a temporary logistics route for shortening the material and product logistics lead time for minimizing the number of materials in the
シミュレーション条件設定部13で、シミュレーション期間、例えば拡大販売変動設定したどの期間まで、或いは、始めとする単位期間以後のどの単位期間までシミュレーションを行うか等、また期首安全在庫数の設定、単位期間の生産量の設定等のパラメータの設定、等のシミュレーション条件の設定を行う。
In the simulation
シミュレーション部14で、前記シミュレーションデータ、前記シミュレーション条件及び需要予測データに基づき、シミュレーターでモデル2を用い、シミュレーションが行われる。
In the
前記シミュレーションで、単位期間の拡大販売変動と残りのライフサイクルでの需要予測データに基づき、拠点倉庫42における製品の在庫及び生産部門24での資材の在庫を最小とする最小安全在庫数及び臨時物流ルートが算出される。前記最小安全在庫数及び臨時物流ルートの算出においては、前記製品及び資材の最小安全在庫数及び臨時物流ルートは、EOL時点での製品及び専用資材の廃棄ロスが最小となるように算出される。
In the simulation, based on the expanded sales fluctuation of the unit period and the demand forecast data in the remaining life cycle, the minimum safety stock number and the temporary logistics that minimize the product stock in the
結果評価部15で、前記シミュレーションの結果(製品及び資材の最小安全在庫数と臨時物流ルート)を評価検討し、更に条件を変えてシミュレーションする必要のある場合は、再度シミュレーション条件設定部13で条件を設定してシミュレーションを行うことができる。これにより、評価の範囲を広げることが可能になる。
The
前記シミュレーション結果の情報は、拠点倉庫42の製品の最小安全在庫数及び臨時物流ルート、生産部門24の資材の安全在庫数と調達の臨時物流ルートとしてフィードバックされ、データベース1に格納され、更にERPパッケージ2に転送し反映される。拠点倉庫42の製品の安全在庫数及び生産部門24の資材の安全在庫数はサプライチェーン20に反映される。また、臨時物流ルートは拡大生産変動が生じた場合にサプライチェーン20に適用される。また、前記シミュレーション結果の一部または全部を予めサプライチェーン20に反映させることもできる。例えば、資材によっては価格が安く、予め在庫としても、またEOL時に廃棄しても金額として問題ない場合等が挙げられる。
The information of the simulation result is fed back as the minimum safety stock number and temporary logistics route of the products in the
前述のモデル1及び2のシミュレーションに際し、データベース1より前記サプライチェーンを構成する拠点の情報・通信環境の状態に関する情報・通信環境情報と、物流の状態に関する物流情報と、を取り出し加味して、シミュレーションを行うことが好ましい。これにより、更に実際の系に近い、且つ精度の高いシミュレーションが可能になる。
In the simulation of the
更に、上述のサプライチェーン20の顧客21の実需要(注文)に応じて販売計画を作成し、販売変動、拡大販売変動を想定し、製品のライフサイクルにおける需要予測を基に、シミュレーションを行いサプライチェーン20の最適化を行う一連の最適化処理を、所定周期毎に行いサプライチェーン20に反映させる。前記所定周期は、一定の期間毎、サプライチェーン20に顧客21の実需要変動(実際の販売変動)が生じる毎、前述の製品のライフサイクルにおける導入期、成長期、成熟期、衰退期の段階毎、或いはこれらの組み合わせ等がある。前記所定周期は、製品の市場における位置、需要、特徴、製品寿命等を考慮し適宜設定することが好ましい。また、製品の衰退期、即ちEOL近くには、前記所定周期を短くすることが好ましい。
Furthermore, a sales plan is created according to the actual demand (order) of the
このように周期を短くしてシミュレーションを行うことで、製品のライフサイクルの各時点において、拠点倉庫42の製品在庫数及び専用資材在庫数を、想定以上の販売変動が生じても製品の欠品を起こすことなく、且つ最小とすることができる。これにより、製品のライフサイクルが終了した時の製品の余剰在庫の低減、及び廃棄ロスの低減を図ることができる。また、製品及び資材の臨時物流ルートの費用の算出をすることができ、サプライチェーンの効率化を図ることができる。
By performing the simulation with the cycle shortened in this way, the product inventory and the dedicated material inventory in the
図5は、図2、3及び4に示すサプライチェーンの効率化支援方法を用いてサプライチェーンの効率化を図るフロー図の一例を示す。データベース1にはERPパッケージ2から必要なデータ、情報が取り込まれているものとする。
FIG. 5 shows an example of a flow chart for improving the efficiency of the supply chain using the supply chain efficiency support method shown in FIGS. It is assumed that necessary data and information are captured from the
ステップS101で、サプライチェーン20における顧客21の実需要に応じた販売計画、需要計画、生産計画が作成される。
In step S101, a sales plan, a demand plan, and a production plan corresponding to the actual demand of the
ステップS102で、需要計画作成部41で販売変動が想定され設定される。
In step S102, a demand fluctuation is assumed and set by the demand
ステップS103で、販売変動を基に変動需要計画、変動生産計画が作成される。 In step S103, a variable demand plan and a variable production plan are created based on the sales fluctuation.
ステップS104で、データ変換部7でERPパッケージ2の製品情報及び生産情報のデータを基に、シミュレーションデータが作成される。
In step S104, the
ステップS105で、モデル作成部8でデータベース1に格納されたサプライチェーンの構成等の情報を基にコンピューター上にサプライチェーンをモデル化したサプライチェーンモデル(モデル1)が作成される。
In step S105, the
ステップS106で、シミュレーション条件設定部9でシミュレーションの条件が担当者により設定される。前記シミュレーションの条件の設定は、シミュレーション期間、期首在庫の設定、単位期間の販売量の設定等パラメータの設定、等である。
In step S106, the simulation
ステップS107で、シミュレーション部10で前記シミュレーションデータ及び前記シミュレーション条件に基づき、モデル1を用いたシミュレーションを行い、シミュレーション結果として、販売変動時に製品在庫及び資材在庫費用が最小となり、且つ欠品を起こさない、変動安全在庫数が算出される。
In step S107, the
ステップS108で、結果評価部11で前記シミュレーションの結果(変動安全在庫数)が評価検討される。更に条件を変えてシミュレーションする必要のある場合は(ステップS108;No)、ステップS106で再度条件を設定してシミュレーションを行う。再シミュレーション不要の場合は(ステップS108;Yes)、ステップS109でシミュレーションの結果をデータベース1に格納する。
In step S108, the
ステップS110で、前記シミュレーションの結果(変動安全在庫数)をデータベース1からERPパッケージ2に転送し、ERPパッケージ2のデータ、情報に反映させる。
In step S110, the simulation result (variable safety stock number) is transferred from the
ステップS111で、前記シミュレーションの結果(変動安全在庫数)をサプライチェーン20に反映させる。
In step S111, the result of the simulation (the number of variable safety stocks) is reflected in the
ステップS112で、需要計画作成部41で拡大販売変動が想定され設定される。
In step S112, the demand
ステップS113で、拡大販売変動を基に拡大変動需要計画、拡大変動生産計画が作成される。 In step S113, an expanded variation demand plan and an expanded variation production plan are created based on the expanded sales variation.
ステップS114で、モデル作成部12で、データベース1に格納されたサプライチェーンの構成等の情報を基にコンピューター上にサプライチェーンをモデル化したサプライチェーンモデル(モデル2)が作成される。モデル2は、前述のモデル1に対し、製品及び資材の物流ルートに臨時物流ルート(航空便等)が加えられ、通常物流ルート(船便等)及び臨時物流ルートで供給した場合の製品及び資材の物流リードタイム及び物流費用、更に拠点倉庫情報が加えられる。モデル2は前記物流費と製品及び資材の在庫計算機能、生産部門24の資材、製品の安全在庫及び拠点倉庫42の製品安全在庫の削減機能を有する。また、前述のEOL段階情報を参照して、前記単位期間の期首からEOLまでの、残りのライフサイクルでの需要予測データを策定する。
In step S114, the
ステップS115で、シミュレーション条件設定部13でシミュレーションの条件が担当者により設定される。前記シミュレーションの条件の設定は、シミュレーション期間、期首安全在庫数の設定、単位期間の販売量の設定等パラメータの設定、等である。
In step S115, the simulation
ステップS116で、シミュレーション部14で前記シミュレーションデータ、前記シミュレーション条件及び需要予測データに基づき、モデル2を用いたシミュレーションが行われる。前記シミュレーションにより、拡大販売変動時に拠点倉庫42における製品の在庫及び生産部門24での資材の在庫を最小とする最小安全在庫数及び臨時物流ルートが算出される。前記最小安全在庫数及び臨時物流ルートの算出においては、前記製品及び資材の最小安全在庫数及び臨時物流ルートは、EOL時点での製品及び専用資材の廃棄ロスが最小となるように算出される。
In step S116, a simulation using the
ステップS117で、結果評価部15で前記シミュレーションの結果(製品及び資材の最小安全在庫数と臨時物流ルートの選定)を評価検討する。更に条件を変えてシミュレーションする必要のある場合は(ステップS117;No)、ステップS115で再度条件を設定してシミュレーションを行う。再シミュレーション不要の場合は(ステップS117;Yes)、ステップS118でシミュレーションの結果をデータベース1に格納する。
In step S117, the
ステップS119で、前記シミュレーションの結果をデータベース1からERPパッケージ2に転送し、ERPパッケージ2のデータ、情報に反映させる。
In step S119, the simulation result is transferred from the
ステップS120で、製品及び資材の最小安全在庫数はサプライチェーン20に反映される。
In step S120, the minimum safe stock quantity of products and materials is reflected in the
1 データベース
2 ERPパッケージ
3 販売計画作成部
41 需要計画作成部
42 拠点倉庫
5 生産計画作成部
6 中継プログラム
7 データ変換部
8、12 モデル作成部
9、13 シミュレーション条件設定部
10、14 シミュレーション部
11、15 結果評価部
20 サプライチェーン
21 顧客
22 販売拠点
23 販売部門
24 生産部門
25 資材調達部門
26 サプライヤー
DESCRIPTION OF
Claims (7)
前記サプライチェーンをモデル化したサプライチェーンモデルをコンピューター上に設定するステップと、
前記サプライチェーンにおける単位期間の期首の販売計画及び需要計画に対し、変動を想定した変動販売計画及び変動需要計画と、該変動需要計画に基づく変動生産計画を立案し、変動情報として格納手段に格納するステップと、
前記変動販売計画及び変動需要計画を上回る拡大変動を想定した拡大変動販売計画及び拡大変動需要計画と、該拡大変動需要計画に基づく拡大変動生産計画を立案し、拡大変動情報として格納手段に入力するステップと、
製品情報、生産情報、物流ルート情報を格納したERP(Enterprise Resource Planning)パッケージから各情報を、前記格納手段から前記変動情報及び前記拡大変動情報を、取り入れ、これらの情報を基に、シミュレーションデータを作成するシミュレーションデータ作成手段で前記シミュレーションデータを作成し、前記格納手段に格納するステップと、
前記サプライチェーンモデルで、前記シミュレーションデータに基づき、シミュレーターで前記変動に対応したシミュレーションを行い、変動時に製品の欠品を起こさない、且つ製品及び資材の在庫費用が最小となる製品及び資材の安全在庫数を算出するステップと、
前記期首を起点とした製品の残りのライフサイクルでの需要予測データを策定するステップと、
前記サプライチェーンモデルで、前記シミュレーションデータ及び前記需要予測データに基づき、シミュレーターで前記拡大変動に対応したシミュレーションを行い、拡大変動時に製品の欠品を起こさない、製品及び資材の最小安全在庫数と製品及び資材の物流ルートを算出するステップと、を有し、
前記ステップでの一連の処理が、所定の単位期間毎の周期で行われることを特徴とするサプライチェーンの効率化支援方法。 The sales plan for the sales volume of the product and the demand plan for the procurement quantity of the product are shifted from the future sales and demand forecast information (forecast information) to the sales and demand confirmation information, and sales and demand fluctuations occur. A supply chain efficiency support method comprising a plurality of operations ranging from material procurement to production processes, including a sales plan and a demand plan,
Setting a supply chain model that models the supply chain on a computer;
For the sales plan and demand plan at the beginning of the unit period in the supply chain, a variable sales plan and variable demand plan that assumes fluctuations, and a variable production plan based on the variable demand plan are drawn up and stored in the storage means as fluctuation information And steps to
An expansion variable sales plan and an expansion variable demand plan assuming an expansion fluctuation exceeding the variable sales plan and the variable demand plan, and an expansion variable production plan based on the expansion variable demand plan are drawn up and input to the storage means as expansion fluctuation information Steps,
Each piece of information is taken from an ERP (Enterprise Resource Planning) package that stores product information, production information, and distribution route information, and the fluctuation information and the enlarged fluctuation information are taken from the storage means, and simulation data is obtained based on these information. Creating the simulation data in the simulation data creation means to create, and storing in the storage means;
In the supply chain model, based on the simulation data, a simulation corresponding to the fluctuation is performed by a simulator, and the stock of the product and the material that does not cause a product shortage at the time of the fluctuation and minimizes the inventory cost of the product and the material is minimized. Calculating a number;
Formulating demand forecast data for the remaining lifecycle of the product starting from the beginning;
Based on the simulation data and the demand forecast data in the supply chain model, a simulation corresponding to the expansion variation is performed by a simulator, and the minimum safe stock number of products and materials and products that do not cause a product shortage at the time of expansion variation And calculating a material distribution route,
A supply chain efficiency support method, wherein a series of processing in the steps is performed at a cycle of a predetermined unit period.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008104585A JP2009258833A (en) | 2008-04-14 | 2008-04-14 | Streamlining support method for supply chain |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008104585A JP2009258833A (en) | 2008-04-14 | 2008-04-14 | Streamlining support method for supply chain |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2009258833A true JP2009258833A (en) | 2009-11-05 |
Family
ID=41386195
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2008104585A Pending JP2009258833A (en) | 2008-04-14 | 2008-04-14 | Streamlining support method for supply chain |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2009258833A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5980408B2 (en) * | 2013-02-20 | 2016-08-31 | 株式会社日立製作所 | Supply rule generation device and supply rule generation program |
-
2008
- 2008-04-14 JP JP2008104585A patent/JP2009258833A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5980408B2 (en) * | 2013-02-20 | 2016-08-31 | 株式会社日立製作所 | Supply rule generation device and supply rule generation program |
JPWO2014128845A1 (en) * | 2013-02-20 | 2017-02-02 | 株式会社日立製作所 | Supply rule generation device and supply rule generation program |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2010010788A1 (en) | Supply chain optimization system and method for optimizing supply chain | |
Kapuscinski et al. | Inventory decisions in Dell's supply chain | |
US8175733B2 (en) | Modeling manufacturing processes to include defined markers | |
JP5643502B2 (en) | How to create production schedules for multiple factories | |
EP1350177A1 (en) | System and method for optimizing resource plans | |
JP2011065224A (en) | Supply chain efficiency improvement support method | |
KR102345145B1 (en) | Production and logistics ERP automation system by linking and using customer information | |
JP2009301466A (en) | Efficiency enhancement support method for supply chain | |
JP2009217573A (en) | System and method for optimizing supply chain | |
JP2010198286A (en) | Support method for efficiency-promotion in supply chain | |
JP2010055258A (en) | Method for supporting improvement in supply chain efficiency | |
JP2008171237A (en) | Efficient management support method for supply chain | |
JP2010244228A (en) | Support method for efficiency promotion of supply chain | |
JP2010176272A (en) | Efficiency support method for supply chain | |
JP2010160680A (en) | Supply chain optimization system | |
JP2009140140A (en) | Supply chain optimization system and supply chain optimization method | |
JP2008217653A (en) | Efficient management support method of material procurement-production process | |
JP2011170737A (en) | Method for supporting promotion of efficiency of supply chain | |
JP2009042810A (en) | Efficiency improvement support method for supply chain | |
JP2007265127A (en) | Supply chain optimization support method | |
JP2009258833A (en) | Streamlining support method for supply chain | |
JP2008269214A (en) | Support method for improving supply chain efficiency | |
JP2010250668A (en) | Supply chain management support system | |
JP2009140291A (en) | Method of supporting efficiency enhancement of supply chain | |
JP2010113393A (en) | Efficiency enhancement support method for supply chain |