CN113570332A CN202110808111.5A CN202110808111A CN113570332A CN 113570332 A CN113570332 A CN 113570332A CN 202110808111 A CN202110808111 A CN 202110808111A CN 113570332 A CN113570332 A CN 113570332A
Authority
CN
China
Prior art keywords
data
module
project
audit
link
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110808111.5A
Other languages
Chinese (zh)
Inventor
华远鹏
白宏坤
王圆圆
常安
韩丁
卜飞飞
闫利
时昱
贾一博
王涵
王世谦
杨萌
李文峰
李虎军
尹硕
刘军会
邓方钊
赵文杰
杨钦臣
柴喆
邓振立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Jiuyu Tenglong Information Engineering Co ltd
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Original Assignee
Henan Jiuyu Tenglong Information Engineering Co ltd
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Jiuyu Tenglong Information Engineering Co ltd, State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd filed Critical Henan Jiuyu Tenglong Information Engineering Co ltd
Priority to CN202110808111.5A priority Critical patent/CN113570332A/en
Publication of CN113570332A publication Critical patent/CN113570332A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Data Mining & Analysis (AREA)
  • Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)

Abstract

A charging facility project reward fund approval system belongs to the field of project approval. The system comprises a project data entry module, a data attribute check module, a data summarization module, an audit conclusion entry module and a data circulation module, wherein the data attribute check module is used for checking whether the project data entry module is consistent with the entry content attribute, the data summarization module is used for classifying and summarizing project data, the audit conclusion entry module is used for entering an audit conclusion, and the data circulation module is used for transmitting the project data and the audit conclusion to the next level. The method can enhance the quality of the joint approval and improve the efficiency of the joint approval.

Description

Charging facility project reward fund examination and approval system
Technical Field
The invention relates to the field of project approval, in particular to a charging facility project reward fund approval system.
Background
The electric automobile facility project examination and approval relates to four departments of development and reform Commission, industry and trust department, science and technology department and financial department. At present, charging facility construction enterprises and operation enterprises submit project materials mostly made of paper materials, the phenomena of disordered contents and error leakage are prone to occurring, and a large amount of manpower and material resources are wasted in the links of paying and reviewing replacement materials. In the examination and approval link, the paper materials are gradually transferred from the lower level to the upper level, and the examination and approval modes reported step by step lack sufficient fairness and permeability, so that the examination and approval process of the project is not easily monitored. In addition, the mode of reporting step by step also causes long approval period and wastes a great deal of time of workers; the storage of paper materials also requires space and is not conducive to data query. Therefore, how to enhance the quality of the joint approval and improve the efficiency of the joint approval is a problem to be solved.
Disclosure of Invention
The invention aims to provide a charging facility project reward and fund approval system, which is used for enhancing the joint approval quality of projects and improving the joint approval efficiency.
The technical scheme of the invention is as follows:
a charging facility project reward fund approval system comprises a project data entry module, a data attribute check module, a data summarization module, an audit conclusion entry module and a data circulation module, wherein the data attribute check module is used for checking whether the project data entry module is consistent with the entry content attribute, the data summarization module is used for classifying and summarizing project data, the audit conclusion entry module is used for entering an audit conclusion, and the data circulation module is used for transmitting project data and the audit conclusion to the next level.
Preferably, the data summarization module is used for summarizing project data according to the application project, summarizing project data according to the auditing department, and summarizing the conclusion according to the auditing conclusion.
Preferably, the data transfer module comprises a project data input link, a field acceptance link, an expert review link and a combined review link, wherein the project data input link is used for inputting project data of an application project, the field acceptance link is used for reviewing the project data and uploading a field acceptance report of the application project, the expert review link is used for reviewing the project data according to the application project and receiving correction data, and the combined review link is used for each review department to respectively review corresponding project data.
Furthermore, in the expert auditing link, the data summarizing module is used for summarizing data according to the application items.
Furthermore, in the joint auditing link, the data summarizing module is used for respectively summarizing project data according to the auditing departments.
Further, after the joint review link, the data summarization module is used for summarizing the conclusion according to the review conclusion.
Furthermore, in the expert declaration link, when the content of the project data does not meet the standard, the correction data is recorded into the project data recording module again.
The invention has the beneficial effects that:
1. the data attribute checking module can preliminarily check the entry errors of the project data so as to improve the auditing efficiency. The data transfer module is internally provided with a data transfer process, and after the data summarization module summarizes project data in a classified manner, the joint approval quality can be enhanced and the joint approval efficiency can be improved.
2. In the field acceptance link and the expert auditing link, the project data are accepted according to the application project, and the data summarizing module is used for summarizing the project data according to the application project, so that the acceptance efficiency can be improved. In the joint audit link, each audit department respectively audits corresponding project data to realize joint audit, and the data summarization module summarizes the project data according to the audit headquarters, so that the acceptance efficiency can be improved. After the acceptance is finished, the data gathering module gathers the conclusion according to the examination conclusion, so that the visibility of the examination and approval result can be improved.
Drawings
Fig. 1 is a flow chart of the usage of a charging facility item reward fund approval system.
Detailed Description
The present invention is described below in terms of embodiments in conjunction with the accompanying drawings to assist those skilled in the art in understanding and implementing the present invention. Unless otherwise indicated, the following embodiments and technical terms therein should not be understood to depart from the background of the technical knowledge in the technical field.
Example 1: a charging facility project reward fund approval system comprises a project data entry module, a data attribute check module, a data summarization module, an audit conclusion entry module and a data circulation module, wherein the data attribute check module is used for checking whether the project data entry module is consistent with the entry content attribute, the data summarization module is used for classifying and summarizing project data, the audit conclusion entry module is used for entering an audit conclusion, and the data circulation module is used for transmitting project data and the audit conclusion to the next level.
Preferably, the data summarization module is used for summarizing project data according to the application project, summarizing project data according to the auditing department, and summarizing the conclusion according to the auditing conclusion.
Preferably, the data transfer module comprises a project data entry link, a field acceptance link, an expert review link and a combined review link, the project data entry link is used for entering project data of an application project, the field acceptance link is used for reviewing the project data and uploading a field acceptance report of the application project, the expert review link is used for reviewing the project data and receiving correction data according to the application project, and each review department reviews corresponding project data respectively.
Furthermore, in the expert auditing link, the data summarizing module is used for summarizing data according to the application items.
Further, in the joint review link, the data summarization module is used for summarizing project data according to the review department.
Further, after the joint review link, the data summarization module is used for summarizing the conclusion according to the review conclusion.
Furthermore, in the expert declaration link, when the content of the project data does not meet the standard, the correction data is recorded into the project data recording module again.
Example 2: a method for using a charging facility item reward fund approval system, referring to fig. 1, comprising the following steps:
(1) the operator builds a subsidy application. The operator can initiate a construction subsidy application on the platform, and can complete account registration, complete data access and fill in the station building data to perform the subsidy application. When applying for subsidy, the subsidy data including site information, investment information, reward information, equipment information, invoice information, etc. need to be uploaded. At the data upload module, the system has intelligent data verification, can accurately identify junk information and junk data, ensures the correctness and authenticity of uploaded data, and avoids the time waste of later-stage auditors on meaningless data.
(2) And (5) committing and auditing the market-level issue. After receiving the construction subsidy application submitted by the operator, the market-level delivery and modification committee can check the application data in batches according to the requirement, check the data, check and accept the data on site after the check is correct, upload a site check and accept report, greatly save the time consumed by the check, and then flow to the next step for continuous check.
(3) And initiating a joint audit. And submitting subsidy materials after the prefecture review is finished to provincial development and reform committee, rapidly summarizing the subsidy materials by using a joint review system, and initiating subsidy joint review according to the prefecture and the time.
(4) And (5) auditing by an expert group. After the issue and reform committee initiates the joint audit, the expert group conducts subsidy data audit according to the joint audit work order, application data of each site are checked and audited in the system, data which do not meet the standard are returned in the system, a material subsidy time limit is set, an audit state is displayed in time on an operator account interface, and an operator is reminded of modification. After all work orders are audited, the expert group collects the joint audit work orders, and the system collects all data and then submits the work orders to the four halls for audit.
(5) And committing and checking in the four halls. And the four halls commission logs in the summary work orders initiated by the account auditing expert group respectively, checks the summary information and the detail data and audits. The material is totally transparent, and the four halls commission must pass all the way to be considered as a pass subsidy application.
The invention is described in detail above with reference to the figures and examples. It should be understood that in practice the description of all possible embodiments is not exhaustive and that the inventive concepts are described herein as far as possible by way of illustration. Without departing from the inventive concept of the present invention and without any creative work, a person skilled in the art should, in all of the embodiments, make optional combinations of technical features and experimental changes of specific parameters, or make a routine replacement of the disclosed technical means by using the prior art in the technical field to form specific embodiments, which belong to the content implicitly disclosed by the present invention.

Claims (7)

1. The system is characterized by comprising a project data entry module, a data attribute check module, a data summarization module, an audit conclusion entry module and a data circulation module, wherein the data attribute check module is used for checking whether the project data entry module is consistent with the entry content attribute, the data summarization module is used for classifying and summarizing project data, the audit conclusion entry module is used for entering an audit conclusion, and the data circulation module is used for transmitting the project data and the audit conclusion to the next level.
2. The system of claim 1, wherein the data summarization module is configured to summarize project data according to application projects, summarize project data according to review departments, and summarize conclusions according to review conclusions.
3. The system of claim 1, wherein the data transfer module includes a project data entry link, a field acceptance link, an expert audit link, and a joint audit link, the project data entry link is configured to enter project data of an application project, the field acceptance link is configured to audit the project data and upload a field acceptance report of the application project, the expert audit link is configured to receive the compensation data according to the application project audit project data, and the joint audit link is configured to respectively audit corresponding project data by each audit department.
4. The system of claim 3, wherein the data summarization module is configured to summarize data according to an applied item in an expert audit process.
5. The system of claim 3, wherein in the joint review step, the data summarization module is configured to summarize the project data according to the review department.
6. The system of claim 3, wherein the data summarization module is configured to summarize the findings according to the review findings after the joint review procedure.
7. The system of claim 3, wherein in the expert declaration section, the contents of the project data do not meet the standard, and the correction data are recorded again in the project data recording module.
CN202110808111.5A 2021-07-16 2021-07-16 Charging facility project reward fund examination and approval system Pending CN113570332A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110808111.5A CN113570332A (en) 2021-07-16 2021-07-16 Charging facility project reward fund examination and approval system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110808111.5A CN113570332A (en) 2021-07-16 2021-07-16 Charging facility project reward fund examination and approval system

Publications (1)

Publication Number Publication Date
CN113570332A true CN113570332A (en) 2021-10-29

Family

ID=78165241

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110808111.5A Pending CN113570332A (en) 2021-07-16 2021-07-16 Charging facility project reward fund examination and approval system

Country Status (1)

Country Link
CN (1) CN113570332A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101082970A (en) * 2007-07-05 2007-12-05 山东浪潮齐鲁软件产业股份有限公司 Method for realizing government affairs examination and approval workflow engines system
CN101702212A (en) * 2009-11-12 2010-05-05 上海众恒信息产业有限公司 Approval system and method
CN108345991A (en) * 2018-01-31 2018-07-31 国网山东省电力公司经济技术研究院 A kind of the feasibility study review system and reviewing method of fusion power grid multi-source information
CN108388996A (en) * 2018-03-08 2018-08-10 青岛东方深蓝信息科技股份有限公司 A kind of scientific research service integration management system
CN109272295A (en) * 2018-09-12 2019-01-25 张连祥 Project of inviting outside investment audits statistical method and system
CN109377178A (en) * 2018-10-23 2019-02-22 国网江苏省电力有限公司经济技术研究院 Power grid technological transformation major repair project electronization review system and reviewing method
CN109829683A (en) * 2018-12-25 2019-05-31 航天信息股份有限公司 A kind of measures and procedures for the examination and approval and system in parallel based on traffic control stream
CN109858751A (en) * 2018-12-26 2019-06-07 中国大唐集团科学技术研究院有限公司 Power engineering Evaluating Projects System
CN109961266A (en) * 2017-12-26 2019-07-02 广东电网有限责任公司电力调度控制中心 A kind of production project contractor management system and method
CN110400126A (en) * 2019-07-26 2019-11-01 天津紫藤科技股份有限公司 Smart items approval system and project examination method
CN111861366A (en) * 2020-06-08 2020-10-30 远光软件股份有限公司 Project-ground intelligent auditing system and computer
CN112163957A (en) * 2020-08-28 2021-01-01 生态环境部华南环境科学研究所 Capital approval and distribution system of environment-friendly fund
CN112330303A (en) * 2020-11-27 2021-02-05 同济大学建筑设计研究院(集团)有限公司 Intelligent project evaluation cooperative management system
CN112686560A (en) * 2021-01-06 2021-04-20 罗兰 One-stop innovative entrepreneurship incubation platform

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101082970A (en) * 2007-07-05 2007-12-05 山东浪潮齐鲁软件产业股份有限公司 Method for realizing government affairs examination and approval workflow engines system
CN101702212A (en) * 2009-11-12 2010-05-05 上海众恒信息产业有限公司 Approval system and method
CN109961266A (en) * 2017-12-26 2019-07-02 广东电网有限责任公司电力调度控制中心 A kind of production project contractor management system and method
CN108345991A (en) * 2018-01-31 2018-07-31 国网山东省电力公司经济技术研究院 A kind of the feasibility study review system and reviewing method of fusion power grid multi-source information
CN108388996A (en) * 2018-03-08 2018-08-10 青岛东方深蓝信息科技股份有限公司 A kind of scientific research service integration management system
CN109272295A (en) * 2018-09-12 2019-01-25 张连祥 Project of inviting outside investment audits statistical method and system
CN109377178A (en) * 2018-10-23 2019-02-22 国网江苏省电力有限公司经济技术研究院 Power grid technological transformation major repair project electronization review system and reviewing method
CN109829683A (en) * 2018-12-25 2019-05-31 航天信息股份有限公司 A kind of measures and procedures for the examination and approval and system in parallel based on traffic control stream
CN109858751A (en) * 2018-12-26 2019-06-07 中国大唐集团科学技术研究院有限公司 Power engineering Evaluating Projects System
CN110400126A (en) * 2019-07-26 2019-11-01 天津紫藤科技股份有限公司 Smart items approval system and project examination method
CN111861366A (en) * 2020-06-08 2020-10-30 远光软件股份有限公司 Project-ground intelligent auditing system and computer
CN112163957A (en) * 2020-08-28 2021-01-01 生态环境部华南环境科学研究所 Capital approval and distribution system of environment-friendly fund
CN112330303A (en) * 2020-11-27 2021-02-05 同济大学建筑设计研究院(集团)有限公司 Intelligent project evaluation cooperative management system
CN112686560A (en) * 2021-01-06 2021-04-20 罗兰 One-stop innovative entrepreneurship incubation platform

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘斌斌: "湖北省电力公司电网建设工程投资审计操作手册", 31 July 2007, 武汉:崇文书局, pages: 194 - 198 *
张轶;季民;翟雪奎;刘允鹏;: "城乡建设用地增减挂钩项目审核审批系统开发", 测绘与空间地理信息, no. 10, pages 179 - 184 *

Similar Documents

Publication Publication Date Title
CN106650971A (en) LIMS-based laboratory management system
CN105205682A (en) Product design Internet platform and application method thereof
CN113656505B (en) Digitization of distributed project management system and method for synchronizing data thereof
CN107918836A (en) A kind of intelligence clearance system and method
TW201432588A (en) Order management system and order management method thereof
CN110517125A (en) A kind of automatic method that keeps accounts of travel reimbursement
CN107194627A (en) Expense report checking method and device
CN116542790A (en) Mobile intelligent general account reporting system, control method, equipment and terminal
CN104252664A (en) Ocean environment monitoring data reporting verification realization method and device
CN113570332A (en) Charging facility project reward fund examination and approval system
CN114123504B (en) Online monitoring method for transformer substation information
CN111950976A (en) Engineering project review system and method
CN116245410A (en) Inspection and detection reporting system and method for oil and gas storage and transportation equipment
CN114429299A (en) Engineering quality safety management method
CN111339079A (en) Airworthiness certification process and data management method and architecture for complex electronic hardware
CN114399275A (en) Environmental impact evaluation and environmental detection collaborative management and control platform
CN116644915A (en) Engineering project management flow system and method
Ding et al. New hybrid simulation model for urban construction waste management: an empirical study
CN117876055A (en) Intelligent solution for invoice arrangement and auditing in trade financing
CN114612206A (en) Financial budget integration-based automatic settlement report generation algorithm and system
TWM641297U (en) Settlement and final accounts report integration system
Ting Data center engineering project risk assessment based on risk matrix model
Li et al. Research on Energy Efficiency Improvement of Science And Technology Discovery Based on Empirical Method
Cai et al. The Research of Wind Power Project Company’s Engineering Management System
CN115099789A (en) Mobile terminal intelligent contract platform and operation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination