CN109711645A - A kind of pipeline construction data management system and method based on two dimensional code - Google Patents

A kind of pipeline construction data management system and method based on two dimensional code Download PDF

Info

Publication number
CN109711645A
CN109711645A CN201711008326.9A CN201711008326A CN109711645A CN 109711645 A CN109711645 A CN 109711645A CN 201711008326 A CN201711008326 A CN 201711008326A CN 109711645 A CN109711645 A CN 109711645A
Authority
CN
China
Prior art keywords
data
pipeline
dimensional code
information
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711008326.9A
Other languages
Chinese (zh)
Other versions
CN109711645B (en
Inventor
牟观良
何宏华
郑孝苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhongying Anxin Technical Service Co Ltd
Original Assignee
Beijing Zhongying Anxin Technical Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Zhongying Anxin Technical Service Co Ltd filed Critical Beijing Zhongying Anxin Technical Service Co Ltd
Priority to CN201711008326.9A priority Critical patent/CN109711645B/en
Publication of CN109711645A publication Critical patent/CN109711645A/en
Application granted granted Critical
Publication of CN109711645B publication Critical patent/CN109711645B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pipeline Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the present invention provides pipeline construction data management system and method based on two dimensional code.The described method includes: obtaining the information that the two dimensional code carries by the two dimensional code on scanning pipeline;Based on the information that the two dimensional code obtained carries, pipe operations data are obtained, the pipe operations data include at least pipeline welding data, pipeline laying data, Pipe installing data and adjunct data, and are verified.Method and system provided in an embodiment of the present invention reduce data and make a report on the probability that mistake occurs, ensure that the relevance of data between each process, while improving the working efficiency of real-time data acquisition using two dimensional code as the carrier of key message.

Description

A kind of pipeline construction data management system and method based on two dimensional code
Technical field
The present embodiments relate to petroleum gas technical fields, and in particular to a kind of pipeline construction number based on two dimensional code According to management system and method.
Background technique
There is construction period length, covering area extensively, on surrounding enviroment to influence big, management business complexity etc. for pipeline engineering construction Feature, oil-gas pipeline are continuous thousands of miles, cross over mountain after mountain, and environment is complicated on the way, frequently pass through urban population compact district, river, Highway, railway, security risk control difficulty is big, once accident occurs, easily causes great casualties, polluted source and nature Environment generates biggish society's negative effect.
With the development of the technologies such as computer technology, geographical information technology, database technology and country, enterprise, the common people Concern to pipe safety, pipeline integrity management are increasingly becoming the new model of pipe safety management, and have obtained government and public affairs Many approvals, meet the requirement of government and the public to pipe safety management.And to realize pipeline integrity management, effective number It will be the necessary basis for carrying out pipeline integrity according to support.
Therefore, carrying out the acquisition of data from pipe design, construction, operation each stage is exactly an essential work Make.The data acquisition of especially pipeline construction will provide abundant, true, accurate data for pipeline operation management, this is both pipe The needs and construction process control of road Integrity Management and the needs of management.Meanwhile in the construction process, some data It is very poor to acquire almost irreversible or invertibity, so having higher requirement to data acquisition target and precision.It is constructing Phase acquisition has retrospective data, can pipeline data be inquired and be analyzed during in-pipe inspection robot operation, can Situation is controlled to trace the quality of work progress, is conducive to the maintenance and operation of pipeline.
Currently, in pipeline engineering process of construction, construction data, construction data acquisition be all often by each unit of taking part in building according to Respective data collecting standard carries out making a report on for data using Paper Formwork, the number of related data is then carried out further according to demand Wordization processing.Such mode acquires many problems of bring to pipeline construction data, is also unfavorable for the pipe-line maintenance of operation phase, It specifically includes that
(1) data standard disunity, each unit of taking part in building cannot carry out construction data acquisition according to unified standard, cause to receive The data information of collection can not be shared.
(2) information-based metadata acquisition tool is not made a report on easily using the live hand filling of Paper Formwork progress The loss of mistake and data.
(3) construction site information interaction approach is limited, can not supervise site operation situation in time;
(4) technological means limits, and management means not yet breaks space limitation, can not accomplish real-time monitoring whenever and wherever possible and examine Batch;
(5) validity is poor, the low problem of data correlation matcher degree between process for data acquisition;
(6) missing of data is that effective supervision of project management process brings very big hidden danger.
(7) data are made a report on not high with the own service level of auditor, lead to that many common-sense mistakes occur, and can not It was found that.Such as repaired mouth quantity is more than weld bond quantity, length of steel pipe is more than 12m etc..
Therefore, how to reduce data acquisition and make a report on the probability that mistake occurs, guarantee the relevance of data between each process, As urgent problem to be solved.
Summary of the invention
For the defects in the prior art, the embodiment of the invention provides a kind of pipeline construction data pipe based on two dimensional code Manage system and method.
In a first aspect, the embodiment of the present invention provides a kind of pipeline construction data management system based on two dimensional code, at least wrap Mobile data acquisition terminal is included, for being acquired based on two dimensional code to pipeline construction data, and is managed;The wherein shifting Dynamic data collection station includes at least scan module, construction data acquisition module and examination of materials module;Wherein,
The scan module is used to scan the two dimensional code on pipeline, and gets the information of two dimensional code carrying, includes at least Number, material and the specification of pipeline;
The construction data acquisition module is used for the information carried based on the two dimensional code obtained, obtains pipeline behaviour Make data, the pipe operations data include at least pipeline welding data, pipeline laying data, Pipe installing data and adjunct Data, and be sent to the examination of materials module after storing and verified;
The examination of materials module is for testing to the pipe operations data got.
Second aspect, the embodiment of the present invention provide a kind of pipeline construction data managing method based on two dimensional code, comprising:
By the two dimensional code on scanning pipeline, the information that the two dimensional code carries is obtained;
Based on the information that the two dimensional code obtained carries, pipe operations data, the pipe operations data are obtained Including at least pipeline welding data, pipeline laying data, Pipe installing data and adjunct data, and verified.
Pipeline construction data management system and method provided in an embodiment of the present invention based on two dimensional code is to close with two dimensional code The carrier of key information, change it is traditional with Paper Formwork carry out site operation data make a report on, then carry out at data in the industry again The mode of reason reduces data and makes a report on the probability that mistake occurs, ensure that the relevance of data between each process, with engineering construction Real-time data acquisition improves work efficiency.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is this hair Bright some embodiments for those of ordinary skill in the art without creative efforts, can be with root Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the structural schematic diagram of the pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code;
Fig. 2 is that weld bond information provided in an embodiment of the present invention records interface;
Fig. 3 is pipeline corrosion protection inspection provided in an embodiment of the present invention and information record sheet;
Fig. 4 is the operation interface of electronic map provided in an embodiment of the present invention;
Fig. 5 is the administration interface of RTK provided in an embodiment of the present invention management;
Fig. 6 is steel pipe information management provided in an embodiment of the present invention interface;
Fig. 7 is weld bond information record management interface provided in an embodiment of the present invention;
Fig. 8 is pipeline projects administration interface provided in an embodiment of the present invention;
Fig. 9 is the administration interface of construction welding unit provided in an embodiment of the present invention;
Figure 10 is data statistics interface in the industry provided in an embodiment of the present invention;
Figure 11 is the structural framing figure of system provided in an embodiment of the present invention;
Figure 12 is the flow diagram of the pipeline construction data managing method provided in an embodiment of the present invention based on two dimensional code.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without creative efforts, shall fall within the protection scope of the present invention.
Fig. 1 is the structural schematic diagram of the pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code, As shown in Figure 1, the system includes at least Mobile data acquisition terminal, for being adopted based on two dimensional code to pipeline construction data Collection, and be managed;Wherein the Mobile data acquisition terminal includes at least scan module 10,20 and of construction data acquisition module Examination of materials module 30;Wherein,
The scan module 10 is used to scan the two dimensional code on pipeline, and gets the information of two dimensional code carrying, at least wraps Include the number, material and specification of pipeline;
Specifically, the pipeline construction data management system based on two dimensional code includes at least Mobile data acquisition terminal, For being acquired based on two dimensional code to pipeline construction data, and storage management is carried out, wherein the Mobile data acquisition terminal Including at least scan module 10, construction data acquisition module 20 and examination of materials module 30, specifically, the scan module 10, Staff is swept using the two dimensional code posted in advance in 10 align with tube of scan module on Mobile data acquisition terminal It retouches, while having got the information of two dimensional code carrying, including at least information such as the numbers, material and specification of pipeline, wherein two dimension The generation of code is to input steel pipe, the number of pipe fitting, material using the data collection system on Mobile data acquisition terminal in advance And the parameters such as specification, click generate button, system according to the information made a report on be automatically every steel pipe, every root canal part generate uniquely Two dimensional code prints the two dimensional code of generation, and is pasted on corresponding steel pipe and pipe fitting, subsequent to the steel pipe and pipe fitting When the operation such as being welded, laid, two dimensional code is scanned with the scan module on Mobile data acquisition terminal, so that it may obtain Get the information of two dimensional code carrying.By scanning function, realize to steel pipe two-dimensional code scanning, and obtain the main information of steel pipe, The difficulty of making a report on for mitigating construction data collector, ensures the accuracy and timeliness of data acquisition.
For example, constructing ready-made to steel-pipe welding, lossless inspection in the construction data acquisition core process based on two dimensional code The work such as survey, measurement carry out digitlization improvement, using two dimensional code as carrier, through the information achievement of each profession, avoid multi-specialized The problem of data caused by cooperation are discontinuous, topological correlation is lost.
By information inputs such as steel pipe, the number of pipe fitting, material, specifications into Mobile data acquisition terminal, two dimensional code is produced, Generate respective two dimensional code for a steel pipe or pipe fitting, and be pasted onto corresponding steel pipe or key, it is subsequent to steel pipe or When pipe fitting is operated, for example, being welded to steel pipe, is then scanned the two-dimensional code, got with Mobile data acquisition terminal The essential information that two dimensional code carries, and the operation data of welding is also recorded in Mobile data acquisition terminal, a part of data It can be automatically generated by Mobile data acquisition terminal, for example, welding seam No etc., a part of data needs are manually inputted, Such as welder's name etc., by all data records it is complete after save, it is convenient to be used in subsequent operation.
Above-mentioned operation is also executed in processes such as non-destructive testing, repaired mouth, weld bond measurements, the data of each step are all recorded simultaneously It saves, facilitates subsequent check.
It should be noted that can choose the new two dimensional code of generation after operation data each time saves and re-paste It on steel pipe, can also be recorded only in the system of Mobile data acquisition terminal, in subsequent each operation, to two-dimensional code scanning During, the corresponding all information of two dimensional code can be got.
The construction data acquisition module 20 is used for the information carried based on the two dimensional code obtained, obtains pipeline Operation data, the pipe operations data include at least pipeline welding data, pipeline laying data, Pipe installing data and attached Object data, and be sent to the examination of materials module after storing and verified;
The main information that pipeline entrained by two dimensional code is got based on scan module 10 is executing subsequent operation to pipeline During, it needs all to record each data of the operation to pipeline.Two dimensional code is carried out using scan module 10 Scanning, the information of two dimensional code corresponding can be filled into the corresponding position of the system of Mobile data acquisition terminal, other data It can be system to be automatically generated according to the operation of staff, be also possible to staff and be manually entered.The construction data is adopted Collection includes pipeline welding data collecting, the acquisition of pipeline laying data, the acquisition of pipe fitting installation data, the acquisition of adjunct data, map The modules such as inquiry.For example, the record interface of such as weld bond information record is as shown in Fig. 2, Fig. 2 provides for the embodiment of the present invention Weld bond information record interface.In addition, newly-increased, inquiry can also be arranged in this system, Orientation on map, picture upload, delete Etc. functions, help unit in charge of construction by mobile terminal at the construction field (site) quickly, accurately acquire construction data.
The examination of materials module 30 is for testing to the pipe operations data got.
The pipe operations data obtained after different operation are carried out for the main information of pipeline got and to pipeline, The data are verified, and also storage is into material correction verification module simultaneously by the result after verification, in order to pipeline Checking information and pipe fitting checking information are managed, and that realizes various information the functions such as makes a report on, checks, deleting, modifying, and Support the functions such as batch input and the batch removal of data.Fig. 3 is pipeline corrosion protection inspection provided in an embodiment of the present invention and information Record sheet, as shown in Figure 3.
Pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, the Mobile data acquisition terminal further include: store keeping module, for the two dimension got The information that code carries carries out the management of pipeline material, and is managed to the pipeline of cutting.
On the basis of the above embodiments, the Mobile data acquisition terminal further includes store keeping module, the material Management module, to steel pipe, the bend pipe, valve, threeway, insulating joint, potentiostat, concentric reducer, closure in pipeline engineering construction The relevant information of the materials such as object, receiving ball tube is stored in Mobile data acquisition terminal, and carries out pipe to the relevant information of material Reason, can carry out typing to material information, the operation such as check, inquire, modify and delete, and support steel pipe cutting message tube Reason.
Pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, the Mobile data acquisition terminal further includes data mode module, for checking logging and offline Data, and do not submit to off-line data or successful data to be submitted to server admin end.
On the basis of the above embodiments, the Mobile data acquisition terminal further includes data mode module, using described Data mode module, can logging to construction personnel and off-line data check, and support to treat the work handled It is handled, realize off-line data or the manual submission of successful data or a key is not submitted to report and submitted.
Pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, the Mobile data acquisition terminal further includes electric map module, for by weld bond, special construction, Pipe protection, backfilling of pipe canal are screened in Mobile data acquisition terminal, and the result of screening is shown.
On the basis of the above embodiments, the Mobile data acquisition terminal further includes electric map module, the electronics Map includes the functions such as map inquiry, map operation, using electric map module, can be protected by weld bond, special construction, pipeline Electronic map interface of the information such as shield, backfilling of pipe canal in mobile terminal inquires screening, realizes that pipe-line construction Various types of data is based on two dimension The displaying of map, Fig. 4 are the operation interface of electronic map provided in an embodiment of the present invention, as shown in Figure 4.
Pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, the Mobile data acquisition terminal further includes Beidou positioning device management module, to be detected for obtaining The coordinate information of pipeline.
On the basis of the above embodiments, the Mobile data acquisition terminal further includes Beidou positioning device management module, Mobile terminal integrates Beidou positioning device and uses carrier phase difference technology (Real-time kinematic, RTK), high-precision GPS measurement must use carrier phase observation data, and RTK location technology is namely based on the real-time dynamic positioning of carrier phase observation data Technology, it can provide three-dimensional localization of the survey station point in specified coordinate system as a result, and reaching a centimetre class precision in real time.? Under RTK work pattern, base station sends its observation and survey station coordinate information to rover station by data-link together.Rover station The data from base station are not only received by data-link, also to acquire GPS observation data, and form difference observation in system Value is handled in real time, while providing centimeter-level positioning as a result, lasting less than one second.Rover station can be at stationary state, It can be at motion state;It can first be initialized on fixed point and enter back into dynamic job afterwards, it can also in a dynamic condition directly Booting, and the search finding of integer ambiguity is completed in a dynamic environment.After the several solution of complete cycle knowing not is fixed, it can carry out The real-time processing of each epoch, if be able to maintain four or more Satellite Phase observations tracking and necessary geometric figure, Rover station can provide centimeter-level positioning result at any time.
The embodiment of the present invention obtains target X, Y, Z coordinate by RTK data-interface, such as, it is desirable to obtain some weld seam Geographical location, so that it may the accurate geographical position coordinates that weld seam is obtained by RTK data-interface facilitate work order digit According to collector's quick obtaining coordinates of targets information, Fig. 5 is the administration interface of RTK provided in an embodiment of the present invention management, such as Fig. 5 It is shown.
Pipeline construction data management system provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, the system also includes server admin end, the server admin end includes at least construction information pipe Module and data check module are managed, the server admin end passes through with the Mobile data acquisition terminal wirelessly to be communicated, Wherein:
The construction information management module is used to receive the data that the Mobile data acquisition terminal uploads, and the data are extremely It less include material information, material verification, pipeline welding, pipeline laying, pipe fitting, adjunct and construction operation information recording attachment;
The data check module is used to carry out data check to the data in the construction information management module.
On the basis of the above embodiments, the system also includes server admin end, the server admin end and institutes It states Mobile data acquisition terminal to be communicated by wireless signal, such as GPRS, 4G, WIFI etc., Mobile data acquisition terminal will The data of acquisition are sent to server admin end by wireless signal, and the data of collection in worksite are tieed up at server admin end Shield, verification, audit and statistical analysis, and Mobile data acquisition terminal is sent by audit opinion.
The server admin end further includes construction information management module and data check module, the construction information management Module is managed the data of the relevant operation of pipeline and construction, and construction information management mainly includes material information, material school It tests, the modules such as pipeline welding, pipeline laying, pipe fitting, adjunct, construction operation information recording attachment upload, realizes and mobile number It is synchronous according to the data of acquisition terminal, while supporting increase data newly, modify, deleting, inquiring, uploading the functions such as attachment, Fig. 6 For steel pipe information management provided in an embodiment of the present invention interface, as shown in Figure 6.
The data check module, essential information and pipe operations data to the pipeline of acquisition are verified, are usually adopted With the basis verification being built in system, there are the verification rule such as verification, logic verify, GIS verification, completeness check, logarithms According to accuracy, integrality verified.Such as judge weld bond information, weld bond measurement, non-destructive testing, corrosion-resistanting interpolating port data whether Completely, by weld bond position and design route distance multilevel iudge weld bond whether offset design middle line etc., Fig. 7 is that the present invention is implemented The weld bond information record management interface that example provides, as shown in Figure 7.
Wherein: basis verification is verified for the master data to pipeline, and whether verification occurs during input Mistake;
In the presence of verification for the data to pipeline typing whether should the position of typing or typing mistake has occurred;
Logic verify is for verifying the logicality of pipe operations data entirety;
GIS is verified for being verified based on data of the geographical location information technology to pipeline;
Completeness check is for all verifying all data of storage, if has the either building of input error defeated Enter.
User can completely judge the related data of pipeline according to above-mentioned verification rule, convenient in subsequent behaviour Make the mistake that data occur for process.
Optionally, the server admin end further include: project information management module, basic data management module and data Statistical analysis module, in which:
The project information management module is for being managed the engineering project of pipe-line construction phase;
The basic data management module is used for the basic data that record management system operates normally;
The data statistic analysis module is for analyzing and counting the data of the engineering project got.
On the basis of the above embodiments, the server admin end further include: project information management module, basic data Management module and data statistics analysis module.Wherein:
The project information management module, is managed the engineering project of pipe-line construction phase, with engineering construction bid section Specific division unit is foundation, is safeguarded using hierarchical tree to information management.User can be according to actual demand pair Engineering project newly such as is increased, is modified, being deleted, being inquired at the operation, and Fig. 8 is pipeline projects management field provided in an embodiment of the present invention Face, as shown in Figure 8.
The basic data management module, for the indispensable basic data that management system operates normally, bonding machine of such as constructing Group management, crew's management, welder's information registration form.It realizes to the increasing newly of basic data, modify, check, inquire, export etc. Function, Fig. 9 are the administration interface of construction welding unit provided in an embodiment of the present invention, as shown in Figure 9.
The data statistic analysis module, for by different dimensions, in conjunction with modes such as line chart, histogram, lists The information such as the displaying engineering material service condition of visual pattern, construction speed statistics, Figure 10 are industry provided in an embodiment of the present invention Interior data statistics interface, as shown in Figure 10.
On the basis of the above embodiments, the server admin end further includes authority management module, the rights management Module includes user management, Role Management, information department management, authority distribution etc. for providing complete rights management function Function.
On the basis of above-mentioned each embodiment, Figure 11 is the structural framing figure of system provided in an embodiment of the present invention, such as Shown in Figure 11, the pipeline construction data management system based on two dimensional code is acquired for the data that pipeline engineering process of construction faces The business problems such as difficulty, data are inaccurate, data are imperfect, sufficiently merge WEB technology, mobile communication technology, geography information skill Art combines M/S (Server/Model) pattern architecture using B/S (browser/Server mode), constructs pipeline construction data Acquisition system carries out data acquisition with engineering construction is synchronous, realizes the information system management of pipeline construction data acquisition, change Traditional Paper Formwork makes a report on mode, and general frame figure is as follows: the system comprises the Mobile data acquisition terminal with it is described Detailed discussion has been done in server admin end, the operation that each module executes in front, and details are not described herein.
Pipeline construction data management system provided by the invention based on two dimensional code, Mobile data acquisition terminal realize scene Construction data is made a report on and is submitted in real time, change it is traditional the acquisition of site operation data is first carried out with Paper Formwork, then again into The mode of row data processing.The use of Mobile data acquisition terminal makes to construct and does not have the time difference between managing, breaks Real-time monitoring whenever and wherever possible and examination & approval are accomplished in time and space limitation, avoid the delay of duration.
Be that every steel pipe, each pipe fitting generate unique two dimensional code using current advanced planar bar code technology, based on this two Code is tieed up as unique identification, the data acquisition of every procedure in pipeline engineering process of construction is carried out, guarantees construction data acquisition Validity, the relevance of data between process, is realized based on two dimensional code, carries out data to pipeline body for Various types of data is unified Alignment.Each unit of taking part in building carries out construction data acquisition according to unified standard, ensure the data uniformity of acquisition, integrality and Sharing provides data supporting for operation phase pipeline integrity management.
Figure 12 is the flow diagram of the pipeline construction data managing method provided in an embodiment of the present invention based on two dimensional code, As shown in figure 12, which comprises
S101, by the two dimensional code on scanning pipeline, obtain the information that the two dimensional code carries;
S102, the information carried based on the two dimensional code obtained, obtain pipe operations data, the pipe operations Data include at least pipeline welding data, pipeline laying data, Pipe installing data and adjunct data, and are verified.
Pipeline construction data managing method provided in an embodiment of the present invention based on two dimensional code is based on described based on two dimension Code pipeline construction data management system, first have to be acquired pipeline data, the embodiment of the present invention be using two dimensional code as Information carrier first loads the information such as steel pipe, the number of pipe fitting, material, specification in pipeline construction data collection system, system It automatically will be every steel pipe, the unique two dimensional code of every root canal part generation according to the information made a report on;To need on site segmentation steel pipe, By scanning original steel pipe two dimensional code, segmentation length is determined, system carries out information update, and generates new two dimensional code;It will give birth to At two dimensional code printed and affixed on steel pipe and pipe fitting.
Second step obtains the key message of steel pipe and pipe fitting by scanning the two-dimensional code, passes through shifting according to pipeline construction process Dynamic data collection station realizes the material information of construction site, the examination of materials, construction data (including pipeline weld information, pipeline Laying information, pipe fitting mount message) etc. data be acquired, meanwhile, the data of collection in worksite utilize cordless communication network submission To server, realize mobile terminal it is synchronous with the data of management end with it is shared.
Third step, the administrative staff of PC management end are by the interactions of the data with server end, to the data of collection in worksite It safeguarded, verified, being audited and being statisticallyd analyze, and audit opinion is fed back into server end, and pushing to mobile data acquisition Terminal.On-site data gathering personnel carry out data collection task adjustment and deployment according to audit opinion.
Pipeline construction data managing method provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, it the method also includes being measured by parameter of the Beidou orientation management system to pipeline, gets The geographic coordinate information of pipeline to be measured.
On the basis of the above embodiments, Beidou RTK, the acquisition when measuring can be used during data acquire High-precision geographic coordinate information, and the connection with Mobile data acquisition terminal is completed by bluetooth approach.
Pipeline construction data managing method provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.
Optionally, the two dimensional code by scanning pipeline, obtains the information that the two dimensional code carries, further include to point The pipeline cut determines segmentation length, the two dimensional code of the pipeline after regenerating segmentation by scanning original pipeline two dimensional code.
On the basis of the above embodiments, in some cases, it is desirable to be split to steel pipe, to need on site segmentation Steel pipe determines segmentation length, system carries out information update, and generates new two dimensional code by scanning original steel pipe two dimensional code; The two dimensional code of generation is printed and affixed on steel pipe and pipe fitting.
Pipeline construction data managing method provided in an embodiment of the present invention based on two dimensional code, by using two dimensional code as information Carrier, and run through the information achievement collection process of each profession, data data errors caused by multi-specialized cooperation are avoided, data are not The problems such as coherent, topological correlation is lost.Pipeline construction collecting method based on two dimensional code changes traditional with papery mould Plate carries out site operation data and makes a report on, and then carries out the mode of data processing again.Using two dimensional code as the load of key message Body reduces data and makes a report on the probability that mistake occurs, ensure that the relevance of data between each process, counts in real time with engineering construction It is improved work efficiency according to acquisition.
In pipeline engineering process of construction, to working procedures such as store keeping, steel-pipe welding, non-destructive testing, repaired mouth, measurements Data acquisition modes carry out digitlization improvement, using intelligent mobile terminal as pipeline construction data collection system mounting platform, with Two dimensional code is the key messages carriers such as steel pipe, pipe fitting, and runs through the information achievement collection process of each profession, avoids multi-specialized association The problems such as data data errors, data caused by work are discontinuous, topological correlation is lost.
Those of ordinary skill in the art will appreciate that: realize that all or part of the steps of above method embodiment can pass through The relevant hardware of program instruction is completed, and program above-mentioned can be stored in a computer readable storage medium, the program When being executed, step including the steps of the foregoing method embodiments is executed;And storage medium above-mentioned includes: ROM, RAM, magnetic disk or light The various media that can store program code such as disk.
Through the above description of the embodiments, those skilled in the art can be understood that each embodiment can It realizes by means of software and necessary general hardware platform, naturally it is also possible to pass through hardware.Based on this understanding, on Stating technical solution, substantially the part that contributes to existing technology can be embodied in the form of software products in other words, should Computer software product may be stored in a computer readable storage medium, such as ROM/RAM, magnetic disk, CD, including several fingers It enables and using so that a computer equipment (can be personal computer, server or the network equipment etc.) executes each implementation Method described in certain parts of example or embodiment.
Device and system embodiment described above is only schematical, wherein described be used as separate part description Unit may or may not be physically separated, component shown as a unit may or may not be Physical unit, it can it is in one place, or may be distributed over multiple network units.It can be according to the actual needs Some or all of the modules therein is selected to achieve the purpose of the solution of this embodiment.Those of ordinary skill in the art are not paying In the case where creative labor, it can understand and implement.

Claims (10)

1. a kind of pipeline construction data management system based on two dimensional code, which is characterized in that include at least mobile data acquisition eventually End for being acquired based on two dimensional code to pipeline construction data, and is managed;Wherein the Mobile data acquisition terminal is extremely It less include scan module, construction data acquisition module and examination of materials module;Wherein,
The scan module is used to scan the two dimensional code on pipeline, and gets the information of two dimensional code carrying, includes at least pipeline Number, material and specification;
The construction data acquisition module is used for the information carried based on the two dimensional code obtained, obtains pipe operations number According to the pipe operations data include at least pipeline welding data, pipeline laying data, Pipe installing data and adjunct number According to, and be sent to the examination of materials module after storing and verified;
The examination of materials module is for testing to the pipe operations data got.
2. system according to claim 1, which is characterized in that the Mobile data acquisition terminal further include: store keeping Module, the information for carrying to the two dimensional code got carries out the management of pipeline material, and carries out to the pipeline of cutting Management.
3. system according to claim 1, which is characterized in that the Mobile data acquisition terminal further includes data mode mould Block for checking logging and off-line data, and does not submit to off-line data or successful data to be submitted to server admin end.
4. system according to claim 1, which is characterized in that the Mobile data acquisition terminal further includes electronically artwork Block, for being screened by weld bond, special construction, pipe protection, backfilling of pipe canal in Mobile data acquisition terminal, by screening As a result it is shown.
5. system according to claim 1, which is characterized in that the Mobile data acquisition terminal further includes that Beidou positioning is set Standby management, for obtaining the coordinate information of pipeline to be detected.
6. system according to claim 1, which is characterized in that the system also includes server admin end, the service For device management end with the Mobile data acquisition terminal by wirelessly being communicated, the server admin end includes at least construction letter Cease management module and data check module, in which:
The construction information management module is used to receive the data that the Mobile data acquisition terminal uploads, and the data are at least wrapped Include material information, material verification, pipeline welding, pipeline laying, pipe fitting, adjunct and construction operation information recording attachment;
The data check module is used to carry out data check to the data in the construction information management module.
7. system according to claim 1, which is characterized in that the server admin end further include: project information management Module, basic data management and data statistics analysis module, in which:
The project information management module is for being managed the engineering project of pipe-line construction phase;
The basic data management module is used for the basic data that record management system operates normally;
The data statistic analysis module is for analyzing and counting the data of the engineering project got.
8. a kind of pipeline construction data managing method based on two dimensional code, which is characterized in that
By the two dimensional code on scanning pipeline, the information that the two dimensional code carries is obtained;
Based on the information that the two dimensional code obtained carries, pipe operations data are obtained, the pipe operations data are at least Including pipeline welding data, pipeline laying data, Pipe installing data and adjunct data, and verified.
9. according to the method described in claim 8, it is characterized in that, the method also includes passing through Beidou orientation management system pair The parameter of pipeline measures, and gets the geographic coordinate information of pipeline to be measured.
10. according to the method described in claim 8, it is characterized in that, the two dimensional code by scanning pipeline, described in acquisition The information that two dimensional code carries, further includes the pipeline to segmentation, by scanning original pipeline two dimensional code, determines segmentation length, weight The two dimensional code of pipeline after newly-generated segmentation.
CN201711008326.9A 2017-10-25 2017-10-25 Pipeline construction data management system and method based on two-dimensional code Active CN109711645B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711008326.9A CN109711645B (en) 2017-10-25 2017-10-25 Pipeline construction data management system and method based on two-dimensional code

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711008326.9A CN109711645B (en) 2017-10-25 2017-10-25 Pipeline construction data management system and method based on two-dimensional code

Publications (2)

Publication Number Publication Date
CN109711645A true CN109711645A (en) 2019-05-03
CN109711645B CN109711645B (en) 2021-07-20

Family

ID=66252061

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711008326.9A Active CN109711645B (en) 2017-10-25 2017-10-25 Pipeline construction data management system and method based on two-dimensional code

Country Status (1)

Country Link
CN (1) CN109711645B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110815827A (en) * 2019-10-11 2020-02-21 西安塑龙熔接设备有限公司 High-precision positioning system and method for welding data cloud of polyethylene pipeline
CN112241841A (en) * 2020-10-17 2021-01-19 范玲珍 Building engineering quality safety tracing management system based on big data
CN112257828A (en) * 2020-10-22 2021-01-22 广州文冲船厂有限责任公司 Steel pipe scanning method, device and system
CN112561017A (en) * 2020-12-25 2021-03-26 东方电气集团科学技术研究院有限公司 Snake-shaped pipe weld joint mark tracing system
CN113159248A (en) * 2021-04-28 2021-07-23 温州开晨科技有限公司 Pile foundation construction management method and system based on two-dimensional code
CN114754810A (en) * 2021-01-08 2022-07-15 中国石油天然气集团有限公司 System for acquiring anti-corrosion joint coating data
CN115860429A (en) * 2023-01-06 2023-03-28 三峡高科信息技术有限责任公司 Pipe network construction management method and system based on label two-dimensional code

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793789A (en) * 2014-01-28 2014-05-14 上海市政建设有限公司 Pipe-jacking construction information management system and method based on two-dimensional bar codes
CN104636873A (en) * 2015-02-11 2015-05-20 上海公路投资建设发展有限公司 Bridge precast concrete member monitoring system based on two-dimensional code and control method thereof
CN106779386A (en) * 2016-12-07 2017-05-31 哈尔滨工程大学 Build management system and method in cruise cabin based on Quick Response Code
CN107067223A (en) * 2016-12-16 2017-08-18 上海建工集团股份有限公司 Construction information collection processing method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793789A (en) * 2014-01-28 2014-05-14 上海市政建设有限公司 Pipe-jacking construction information management system and method based on two-dimensional bar codes
CN104636873A (en) * 2015-02-11 2015-05-20 上海公路投资建设发展有限公司 Bridge precast concrete member monitoring system based on two-dimensional code and control method thereof
CN106779386A (en) * 2016-12-07 2017-05-31 哈尔滨工程大学 Build management system and method in cruise cabin based on Quick Response Code
CN107067223A (en) * 2016-12-16 2017-08-18 上海建工集团股份有限公司 Construction information collection processing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
庞保华 等: ""管道建设中钢管的数据化管理"", 《中国石油石化》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110815827A (en) * 2019-10-11 2020-02-21 西安塑龙熔接设备有限公司 High-precision positioning system and method for welding data cloud of polyethylene pipeline
CN112241841A (en) * 2020-10-17 2021-01-19 范玲珍 Building engineering quality safety tracing management system based on big data
CN112241841B (en) * 2020-10-17 2021-06-15 龙元明筑科技有限责任公司 Building engineering quality safety tracing management system based on big data
CN112257828A (en) * 2020-10-22 2021-01-22 广州文冲船厂有限责任公司 Steel pipe scanning method, device and system
CN112561017A (en) * 2020-12-25 2021-03-26 东方电气集团科学技术研究院有限公司 Snake-shaped pipe weld joint mark tracing system
CN114754810A (en) * 2021-01-08 2022-07-15 中国石油天然气集团有限公司 System for acquiring anti-corrosion joint coating data
CN113159248A (en) * 2021-04-28 2021-07-23 温州开晨科技有限公司 Pile foundation construction management method and system based on two-dimensional code
CN115860429A (en) * 2023-01-06 2023-03-28 三峡高科信息技术有限责任公司 Pipe network construction management method and system based on label two-dimensional code

Also Published As

Publication number Publication date
CN109711645B (en) 2021-07-20

Similar Documents

Publication Publication Date Title
CN109711645A (en) A kind of pipeline construction data management system and method based on two dimensional code
CN110782154A (en) Construction plan management system based on BIM + GIS
Navon et al. Field experiments in automated monitoring of road construction
CN109344218A (en) Lightguide cable link method for inspecting and its system
CN108320515B (en) Automatic matching and checking method and system for road network of traffic accident site
CN104499714A (en) Mechanical and electrical installation engineering construction method based on BIM platform and measuring robot
CN104732607A (en) Intelligent pipe network patrolling method and system
CN111551147A (en) Arch dam surface deformation monitoring system based on GNSS and measuring robot fusion
CN107272534A (en) A kind of intelligence compacting monitoring system
KR101000949B1 (en) Web-based realtime surveying managing system
CN110489896B (en) Temporary construction project site selection and design method based on multi-source data fusion technology
CN111274683B (en) Data alignment management method for oil and gas pipeline
CN112989532A (en) BIM-based construction method for changing municipal pipeline of subway station
CN111582729A (en) System and method for acquiring field data of soil mass and geological survey
CN112050092A (en) Water supply pipe network leakage information management system, building method and application
Kivimäki et al. Infra BIM based real-time quality control of infrastructure construction projects
CN111299893A (en) System for be used for gas pipeline crater quality analysis and trace back
CN111460623B (en) Real-time acquisition and processing method and system for mapping operation data
Guo et al. Implementation of CIM-related technologies within transportation projects
CN106758698B (en) Road roller control method and device
CN114646321A (en) Automatic generation method and system of high-precision map data and map data cloud platform
CN109889526B (en) Gas pipeline data acquisition method and gas pipeline data acquisition device based on position coordinates
CN115375864B (en) Unmanned aerial vehicle-based high-speed railway completion acceptance method
CN116205399A (en) Cable channel resource management system
CN110610244A (en) Water supply pipeline hidden danger troubleshooting integrated operation method, computer readable storage medium and terminal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant