CN108848337A - Long-range auditing method, device, terminal and the computer storage medium of line project - Google Patents

Long-range auditing method, device, terminal and the computer storage medium of line project Download PDF

Info

Publication number
CN108848337A
CN108848337A CN201810600189.6A CN201810600189A CN108848337A CN 108848337 A CN108848337 A CN 108848337A CN 201810600189 A CN201810600189 A CN 201810600189A CN 108848337 A CN108848337 A CN 108848337A
Authority
CN
China
Prior art keywords
line project
line
information
latitude
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810600189.6A
Other languages
Chinese (zh)
Inventor
张育红
龙永明
童贞理
霍明德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China United Network Communications Group Co Ltd
Original Assignee
China United Network Communications Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China United Network Communications Group Co Ltd filed Critical China United Network Communications Group Co Ltd
Priority to CN201810600189.6A priority Critical patent/CN108848337A/en
Publication of CN108848337A publication Critical patent/CN108848337A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • H04N7/181Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast for receiving images from a plurality of remote sources
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Educational Administration (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Multimedia (AREA)
  • Signal Processing (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention provides long-range auditing method, device, terminal and the computer storage medium of a kind of line project, method includes:Obtain the multiple images information of line project;It is verified according to authenticity of the image information to line project, and determines the latitude and longitude information of line project;The line project after verifying is carried out checking processing according to image information and latitude and longitude information.The present invention carries out authenticity verification to line project according to image information, and determine the latitude and longitude information of line project, further line project is carried out to check processing according to image information and latitude and longitude information, on-site verification is carried out without staff, effectively overcome a large amount of man power and material of needs existing in the prior art, and time upper serious lag, the problem of influencing treatment effeciency, the accuracy that the line length of fragmentary line project is checked is greatly improved, reduce engineering circuit project amount and engineered material material clearing amount, obtain economic benefit and social benefit bumper harvests.

Description

Long-range auditing method, device, terminal and the computer storage medium of line project
Technical field
The present invention relates to the long-range auditing method of field of communication technology more particularly to a kind of line project, device, terminal and Computer storage medium.
Background technique
The fragmentary engineering in general of route refers to that project amount is smaller or the lower transmission line engineering project of cost, mainly includes day Normal line maintenance engineering, breakdown repair and transmission line Optimizing Reconstruction engineering.This kind of engineering project wide variety, single cost Low, distribution is fragmentary, and construction point is more, wire length, wide, and management difficulty is big;Engineering construction is pressed for time, and ostentatious project is more, extensive management, Loophole is big;Meanwhile engineering project does not have regular Specialty Design, construction is random stronger, and cost is difficult to control.How to manage The fragmentary engineering of route, the especially auditing management website of line length, control engineering cost allow limited fund to play maximum effect, Achieve the purpose that " getting more done on less money ", is highly pay close attention to the problem of.
The construction work clearing of fragmentary line project, line length is key, and line length is related to fragmentary engineering construction Material therefor quantity, engineering cost clearing number just with line length it is closely related, so checking for line length just becomes The key factor of fragmentary line project Engineering Settlement is settled accounts closely related with settlement amounts in fragmentary line project.
In daily transmission line maintenance process, transmission line is since construction is disconnected by artificial digging, mouse bites broken or other Failure needs maintenance personnel to repair to scene.After fault restoration, when carrying out line material clearing, due to lacking line Road length remotely checks that means, the line length that maintenance personnel provides often differ larger with actually required length, and as fortune If battalion quotient verifies the line length of the fragmentary engineering in everywhere to scene one by one, especially some routes are remote It is not only time-consuming and laborious on high mountain, and verify without so human resources, cause to settle accounts line length and actually make There is very big waste with optical cable.
From the point of view of the situation in current actual production process, processing problems are manufactured almost exclusively by the construction at the scene of participation Or maintenance personnel oneself makes a report on the mode of line material work order to operator, operator person in charge audits.Auditor Member is often in the fragmentary engineering construction of route, and step may be checked all to scene one by one under normal circumstances, in addition transmission line passes through The environment crossed is extremely complex, some routes will also be by various environment such as remote mountain streams, and auditor is even if sampling observation Each on-site verification line length can not be arrived one by one, therefore, be merely able to verify by the declaration data of construction personnel, this Sample, often time-consuming, laborious, accuracy is not high, and time span is big, and checks low efficiency, and accuracy is not high.
Summary of the invention
The embodiment of the invention provides the storages of a kind of long-range auditing method of line project, device, terminal and computer to be situated between Matter, to solve it is existing in the prior art be merely able to verify by construction personnel, in this way, often time-consuming, laborious, accurately Property it is not high, time span is big, and check get up low efficiency, the not high problem of accuracy.
First aspect of the embodiment of the present invention provides a kind of long-range auditing method of line project, including:
Obtain the multiple images information of line project;
It is verified according to authenticity of the described image information to the line project, and determines the warp of the line project Latitude information;
The line project after verifying is carried out checking processing according to described image information and the latitude and longitude information.
Method as described above is verified according to authenticity of the described image information to the line project, and is determined The latitude and longitude information of the line project, including:
According to the image latitude and longitude information at described image acquisition of information line project place on map;
Obtain the default latitude and longitude information of the line project;
If described image latitude and longitude information matches with the default latitude and longitude information, it is determined that the line project it is true Real storage exists, and described image latitude and longitude information is determined as to the latitude and longitude information of the line project.
Method as described above, according to described image information and the latitude and longitude information to the line project after verifying It carries out checking processing, including:
Obtain the shooting time of described image information;
Described image information is arranged based on the shooting time;
According to after arrangement image information and the latitude and longitude information line project is carried out to check processing.
Method as described above, according to after arrangement image information and the latitude and longitude information to the line project carry out Check processing, including:
It is sequentially marked, is obtained multiple on map according to the latitude and longitude information and the image information after arrangement Mark point;
Multiple mark point positions on map are attached by the construction line based on the line project obtained in advance, are obtained Map line information;
Determine that the route of the line project calculates length according to length of the map line information on map;
The line project is carried out to check processing based on route measuring and calculating length.
Method as described above carries out the line project to check processing based on route measuring and calculating length, including:
Obtain the preset length of the line project;
If the error between the route measuring and calculating length and the preset length is less than or equal to preset threshold value, by institute State the total length that route measuring and calculating length is determined as the line project;Alternatively,
If the error between the route measuring and calculating length and the preset length is greater than preset threshold value, by the route Feedback is marked in engineering.
Method as described above, the multiple images information for obtaining line project, including:
Obtain multiple critical construction points in the line project;
Each critical construction point is shot, obtains multiple images information, wherein in captured image information background Including preset landmark.
What second aspect of the embodiment of the present invention provided a kind of line project remotely checks device, including:
Module is obtained, for obtaining the multiple images information of line project;
Authentication module for verifying according to authenticity of the described image information to the line project, and determines institute State the latitude and longitude information of line project;
Processing module, for according to described image information and the latitude and longitude information to the line project after verifying into Row checks processing.
Device as described above, the authentication module, is used for:
According to the image latitude and longitude information at described image acquisition of information line project place on map;
Obtain the default latitude and longitude information of the line project;
If described image latitude and longitude information matches with the default latitude and longitude information, it is determined that the line project it is true Real storage exists, and described image latitude and longitude information is determined as to the latitude and longitude information of the line project.
Device as described above, the processing module, is used for:
Obtain the shooting time of described image information;
Described image information is arranged based on the shooting time;
According to after arrangement image information and the latitude and longitude information line project is carried out to check processing.
Device as described above, the processing module, is used for:
It is sequentially marked, is obtained multiple on map according to the latitude and longitude information and the image information after arrangement Mark point;
Multiple mark point positions on map are attached by the construction line based on the line project obtained in advance, are obtained Map line information;
Determine that the route of the line project calculates length according to length of the map line information on map;
The line project is carried out to check processing based on route measuring and calculating length.
Device as described above, the processing module, is used for:
Obtain the preset length of the line project;
If the error between the route measuring and calculating length and the preset length is less than or equal to preset threshold value, by institute State the total length that route measuring and calculating length is determined as the line project;Alternatively,
If the error between the route measuring and calculating length and the preset length is greater than preset threshold value, by the route Feedback is marked in engineering.
Device as described above, the acquisition module, is used for:
Obtain multiple critical construction points in the line project;
Each critical construction point is shot, obtains multiple images information, wherein in captured image information background Including preset landmark.
What the third aspect of the embodiment of the present invention provided a kind of line project remotely checks terminal, including:
Memory;
Processor;And
Computer program;
Wherein, the computer program stores in the memory, and is configured as being executed by the processor with reality A kind of long-range auditing method of line project described in existing above-mentioned first aspect.
Fourth aspect of the embodiment of the present invention provides a kind of computer storage medium, and the computer storage medium is computer Readable storage medium storing program for executing is stored thereon with computer program;
The computer program is executed by processor to realize a kind of the long-range of line project described in above-mentioned first aspect Auditing method.
Long-range auditing method, device, terminal and the computer storage medium of line project provided in an embodiment of the present invention are led to The multiple images information for obtaining line project is crossed, is verified according to authenticity of the image information to line project, and determines line The latitude and longitude information of road engineering further checks the line project after verifying according to image information and latitude and longitude information Core processing carries out on-site verification without staff, effectively overcomes and existing in the prior art generally require a large amount of people Power and material resources, and time upper serious the technical issues of lagging, influencing treatment effeciency, in addition, this method is practical, judge standard Exactness is high, and to the technical of less demanding of operator, easy to operate, can increase substantially the line of fragmentary line project The accuracy that road length is checked reduces engineering circuit project amount and engineered material material clearing amount, obtains economic benefit and society Benefit bumper harvests, are conducive to the popularization and application in market.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of the long-range auditing method of line project provided in an embodiment of the present invention;
Fig. 2 is provided in an embodiment of the present invention to be tested according to authenticity of the described image information to the line project Card, and determine the flow diagram of the latitude and longitude information of the line project;
Fig. 3 be it is provided in an embodiment of the present invention according to described image information and the latitude and longitude information to after verifying Line project check the flow diagram of processing;
Fig. 4 is the image information provided in an embodiment of the present invention according to after arrangement and the latitude and longitude information to the route Engineering check the flow diagram of processing;
Fig. 5 is that the route measuring and calculating length provided in an embodiment of the present invention that is based on carries out the line project to check processing Flow diagram;
Fig. 6 is the flow diagram of the multiple images information provided in an embodiment of the present invention for obtaining line project;
Fig. 7 is a kind of flow diagram of the long-range auditing method for line project that Application Example of the present invention provides;
Fig. 8 is a kind of structural schematic diagram for remotely checking device of line project provided in an embodiment of the present invention;
Fig. 9 is a kind of structural schematic diagram for remotely checking terminal of line project provided in an embodiment of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The term " includes " of description and claims of this specification and " having " and their any deformation, it is intended that Be to cover it is non-exclusive include, for example, the device of the process or structure that contain series of steps is not necessarily limited to clearly arrange Those of out structure or step but may include other steps being not clearly listed or intrinsic for these processes or device Rapid or structure.
The technical solution of the application in order to facilitate understanding, the below status to the fragmentary engineering of route and there are the problem of progress Explanation:
One, the fragmentary engineering of existing route has the following problems:
1) supervision difficulty is big, firstly, fragmentary line project, because of the amount of money and small scale, typically no design, engineering technology and Administrative staff lack, and are difficult deeply in face of the large number of fragmentary engineering project supervision and check of route.Secondly, fragmentary linemen's Journey, due to the rigid mission requirements for being limited by time, natural conditions and being completed as early as possible, engineering material especially line material, such as Optical cable and piecing devices equal loss, supervision are affected to a certain extent.Third is ready since construction cost is relatively high Often scale is smaller for the unit in charge of construction of catcher, is lacking in terms of technology, management and prestige, and using inferior materials and turning out substandard goods and exaggerating material makes With being very universal phenomenon, supervision difficulty is larger.
2) arbitrarily construction and management, lacks necessary research and demonstration fragmentary line project early period, to the work of concrete engineering Sequence or technique lack research, time-consuming, cause to waste.In addition, lacking perspective and relevant policies research equally can also make At waste or even even more serious.For another example default " dragging-on construction project " (some units in charge of construction cause hidden dangers in project using technology) In the presence of forming maintenance engineering in the future.
3) follow-up work is short of, managerial confusion, in fragmentary line project it is many be all repairing failure, engineering optimization transformation and Maintenance work is repaired, the fragmentary line project both sides in part might not sign formal contract, only with a paper agreement or leader The oral commitment of people just fixs task, has followed traditional Items Management Mode, fragmentary line project construction personnel is often It is both builder and documenter as more duties, thus the data keeping of fragmentary line project is not often scattered complete with filing, gives Follow-up work brings management risk.Often resulting in have mended also needs to mend, and is broken the vicious circle in cycles changed again again, temporary solution is not It effects a permanent cure, does not tackle the problem at its root.
4) without design scheme and construction drawing, to increase project cost, provide concocting various pretexts, the chance practised fraud and Premise.On the one hand, certain units be strictly the insufficient institute of administrative skill strength extremely;On the other hand and main aspect, certain people recognize For small engineering, it is not necessary that be designed and budget, it is believed that this will increase cost.In practice, most of fragmentary line projects It requires.Therefore the new-added item in engineering or change item with regard to more, also very at will.Often engineering construction side is mentioned with various reasons or excuse New-added item out changes item requirement, and unit management personnel only agree to that this is just concocting various pretexts, practising fraud creates chance.
Two, fragmentary engineering is checked difficult with following fundamental cause:
1) management system is unsound, and from the trick of engineering, bid, to final acceptance of construction, just macroscopic view aspect says that country is to fragmentary line For road engineering without specific restrictive very strong regulatory documents, some is guiding standard data and technological standards;With regard to micro- It sees aspect and says that most unit roots originally throw the management system or measure about fragmentary line project.In short, fragmentary engineering Management is in disordered state.
2) management profrssion degree is low, and technical strength is insufficient, since fragmentary line project is generally formal engineering project Supplement need, or due to repairing line fault need, or due to repair and optimize route routing needs, construction list Position leader and related administrative staff couple《Bid method》,《Contract law》Learn inadequate, understanding etc. the law in relation to engineering construction, regulation It is not deep, bid and tender for construction project activity and specification contract behavior cannot be carried out fully according to relevant law, rules and regulations, or even occur by Individual interest driving, the specified contractor unit in inside, causes bidding black-box operation.
3) fragmentary Construction Audit strength is insufficient, and fragmentary line project project " valence is low, amount is more, point is scattered ", this is engineering constraint The bottleneck that project auditing work is carried out.Works settlement audit is related to many aspects such as norm for detailed estimates, engineering technology, audit and engineering The related professional knowledge of cost, it is more demanding to the professional qualities of auditor.And the current audit personnel structure of knowledge is not Rationally, the professional comprehensively in terms of grasp Engineering Project Audit is few.
4) fixed several mini engineerings construction is all used for a long time in person-to-person emotion and advantage factors, some units Unit, the cooperative relationship of both sides form " underlying rule " of default.Between unit relevant functional departments or leader, with unit in charge of construction Relationship, there is an a kind of multiple interests of mutual reciprocity and mutual benefit and the relationship on emotion basis, both sides in emotion and using above reaching certain tacit agreement, Though the single fragmentary work route journey amount of money is small, everlasting, the number to accumulate over a long period is not but small.
5) it can not provide and effectively check required foundation data, since the fragmentary project site of transmission line disperses, add Upper engineering construction needs, and the routing trend of route may be varied compared with original, can not provide objective track data and make To check foundation, therefore the line length of fragmentary engineering is checked and is difficult to.
For above situation, carry out checking processing in the prior art frequently with following means:
(1) currently, in the practice of known Practical Project, aspect is checked for the line length data of fragmentary line project The problem of, there are no enough attention are caused, do not carry out particular study.In general, the person in charge of the project is exactly required to arrive Construction site carries out site operation state and surveys, and carries out linear measure longimetry using necessary measuring tool, and make a record.
(2) if person in charge of the project personnel check less than construction site, judge by rule of thumb with common sense.Construction team is by fragmentary route After engineering construction finishes, table is made a report on according to the material of condition of construction, the person in charge of the project according to the reported data of construction team, according to Whether oneself micro-judgment is reasonable, if it is considered to then passing through audit within zone of reasonableness.
(3) the line length data sensory difference that the person in charge of the project reports construction team personnel is larger, if excessively going against accepted conventions It may cause attention.For the data that these excessively go against accepted conventions, person in charge may address inquires to construction team, if construction team Explanation it is fair and sensible, then person in charge may just will be considered that these data are reasonable.If the explanation of construction team is unreasonable, Person in charge is likely to go to survey to scene and proofread, and to arrive scene must have a premise, that is, construction site environment phase To relatively close, if construction environment is remote and mountain area, it is likely to person in charge and wants to go to also be less likely.
But reality is, and after often many fragmentary line project constructions finish, data and reality that construction team makes a report on Border discrepancy is very big, even many times of actual measurement data.And the person in charge of the project can not arrive each construction site and obtain the True line length data on the other hand, this data for resulting in construction team to report and submit and real data discrepancy difference are huge, cause to apply Work route, such as the huge waste of lightguide cable link material, also, fragmentary line project quantity is more, wide and small scale, if each If fragmentary line project must all go on-site examination and survey, it will a large amount of human and material resources are wasted, not only low efficiency, but also Effect is also bad.
In order to solve the above-mentioned problems in the prior art, with reference to attached drawing 1 it is found that present embodiments providing a kind of route The long-range auditing method of engineering, this method remotely can carry out line project based on acquired image information checking processing, Specifically, this method includes:
S101:Obtain the multiple images information of line project;
Wherein, without limitation for the specific number of image information, those skilled in the art can be according to specific route Engineering is arranged different image information numbers, and under normal circumstances, line project is longer, and image information is more, and image information It is more, it carries out checking that the accuracy of processing is higher;In addition, the image information in the present embodiment, which can use filming apparatus, (to be had The terminal of shooting function, camera, video camera etc.) acquisition obtains, specific acquisition mode can taking human as collection in worksite, alternatively, Remote control acquisition, such as:Long-range shooting, collecting etc. is carried out using unmanned plane;Acquired image information is based on practical line Road engineering is acquired, of course, those skilled in the art can also using other modes come Huqiu image information, as long as It can guarantee the real reliability of image information, details are not described herein.
S102:It is verified according to authenticity of the image information to line project, and determines the longitude and latitude letter of line project Breath;
After getting image information, it can be verified based on authenticity of the image information to line project, specifically , it can be matched according to the object information for including in image information with practical object, for example, can will be in image information Background information is matched with the background in kind on map, to reach the verifying whether true effect of line project, if background is believed Breath matches with the background in kind on map, then can determine line project necessary being, may further be according to image information Determine the latitude and longitude information of line project, wherein can wrap in image information containing latitude and longitude information, by image information Analysis handles the latitude and longitude information to determine line project.
And when the background in kind in background information and map mismatches, then illustrate that the authenticity of line project exists and doubts It asks, at this point it is possible to which the line project is marked, and feeds back to related personnel and verify, to be effectively guaranteed pair The accurate reliability that line project is checked.
S103:The line project after verifying is carried out checking processing according to image information and latitude and longitude information.
After getting image information and latitude and longitude information, can to by verifying after line project length carry out It estimates, and line project is carried out according to the length estimated to check processing, with the reported line project data of acquisition and really The difference degree of data checks treatment process to line project to realize.
The long-range auditing method of line project provided in this embodiment, by obtaining the multiple images information of line project, It is verified according to authenticity of the image information to line project, and determines the latitude and longitude information of line project, further basis Image information and latitude and longitude information carry out checking processing to the line project after verifying, carry out live core without staff Look into, effectively overcome it is existing in the prior art generally require a large amount of man power and material, and time upper serious lag, shadow The technical issues of ringing treatment effeciency, in addition, this method is practical, accuracy of judgement degree is high, and to the technical of operator It is of less demanding, it is easy to operate, the accuracy that the line length of fragmentary line project is checked can be increased substantially, engineering line is reduced Road project amount and engineered material material clearing amount obtain economic benefit and social benefit bumper harvests, be conducive to the popularization in market with Using.
On the basis of the above embodiments, with continued reference to attached drawing 2 it is found that the present embodiment for according to image information to route The authenticity of engineering is verified, and the specific implementation process of the latitude and longitude information of determining line project is without limitation, this field Technical staff can be configured according to specific design requirement, more preferably, in the present embodiment according to image information pair The authenticity of line project is verified, and the latitude and longitude information of determining line project may include:
S1021:According to the image latitude and longitude information at image information acquisition line project place on map;
It may include latitude and longitude information in image information, image longitude and latitude determined by the analysis processing to image information Information;Specifically, can be matched by the object in GIS map with the subject in image information, in GIS map On object and image information in subject when matching, the latitude and longitude information of the object in GIS map can be determined For image latitude and longitude information.Of course, those skilled in the art can also obtain image longitude and latitude letter using other modes Breath.
S1022:Obtain the default latitude and longitude information of line project;
The latitude and longitude information for the line project that default latitude and longitude information is reported by construction personnel.
S1023:If image latitude and longitude information matches with default latitude and longitude information, it is determined that line project is really deposited , and image latitude and longitude information is determined as to the latitude and longitude information of line project.
Wherein, matching can refer to that image latitude and longitude information is identical with default latitude and longitude information, alternatively, can also be with Refer to that the matching degree of image latitude and longitude information and default latitude and longitude information is greater than or equal to preset threshold value, in order to improve warp The accurate reliability that latitude information obtains more preferably can be by of image latitude and longitude information and default latitude and longitude information It is determined as image latitude and longitude information when being greater than or equal to preset threshold value with degree to match with default latitude and longitude information.
It is understood that the above process can also include:
S1024:If image latitude and longitude information and default latitude and longitude information mismatch, exist to the authenticity of line project Feedback is marked in line project by query.
The authenticity of line project is verified through the above way, and determines the latitude and longitude information of line project, is had It ensure that effect the accuracy that latitude and longitude information determines, improve the reliability that this method uses.
On the basis of the above embodiments, with continued reference to attached drawing 3-5 it is found that the present embodiment is for according to image information and warp Latitude information check the specific implementation process of processing without limitation to the line project after verifying, those skilled in the art Member can be configured according to specific design requirement, more preferably, in the present embodiment according to image information and longitude and latitude Information carries out checking that processing may include to the line project after verifying:
S1031:Obtain the shooting time of image information;
When taking pictures using filming apparatus to line project, the photo opporunity taken pictures a little will record, the photo opporunity The as shooting time of image information.
S1032:Image information is arranged based on shooting time;
Image information can be arranged according to the sequencing of time based on shooting time.
S1033:According to after arrangement image information and latitude and longitude information line project is carried out to check processing.
Wherein, according to after arrangement image information and latitude and longitude information line project is carried out to check that processing may include:
S10331:It is sequentially marked, is obtained on map according to latitude and longitude information and the image information after arrangement Multiple mark points;
S10332:Construction line based on the line project obtained in advance connects multiple mark point positions on map It connects, obtains map line information;
S10333:Length of the line information on map determines the route measuring and calculating length of line project according to the map;
S10334:Line project is carried out to check processing based on route measuring and calculating length.
Specifically, carrying out checking that processing may include to line project based on route measuring and calculating length:
S103341:Obtain the preset length of line project;
The length of included line project when wherein preset length is construction personnel's reported data.
S103342:If route, which calculates the error between length and preset length, is less than or equal to preset threshold value, by line Drive test calculates the total length that length is determined as line project;Alternatively,
S103343:If route, which calculates the error between length and preset length, is greater than preset threshold value, by line project Feedback is marked.
In the present embodiment, by by the preset length that calculated route calculates length and construction personnel reports divide Analysis is compared, specifically, if above-mentioned error is in the error range of permission, then it is assumed that construction team's reported data is reasonable, Ke Yizhi It connects and carries out Engineering Settlement as construction line length using the data (preset length) of construction team;Conversely, then construction team is allowed to provide It explains, and calls to take pictures and carry out inquiry verification;Due to thering is pictorial information and latitude and longitude information to compare as evidence, line construction The case where length has a comparison evidence well, and the previous no evidence of very good solution can be compared and be verified, also, should Method automatic running, be not necessarily to manual intervention, whole-process high-efficiency is fast, so effectively improve this method use it is convenient and reliable Property.
On the basis of the above embodiments, with continued reference to attached drawing 6 it is found that the present embodiment is for obtaining the multiple of line project Without limitation, those skilled in the art can be configured the specific implementation process of image information according to specific design requirement, More preferred, the multiple images information of the acquisition line project in the present embodiment may include:
S1011:Obtain multiple critical construction points in line project;
Wherein, critical construction point may include at least one of:Corner, bridge, tunnel, man-hand hole, optical fiber fusion welding point etc. Deng being preset or pre-selected for user, the specific number of critical construction point can be according to the property of line project It determines, under normal circumstances, the length of line project is longer, the number of critical construction point is more.
S1012:Each critical construction point is shot, obtains multiple images information, wherein captured image information It include preset landmark in background.
Wherein, when taking pictures to critical construction point, the background taken pictures can include landmark, such as bridge as far as possible Beam, tunnel, building etc., so that the image information (photo) with landmark can be got, in this way convenient in GIS The accordance comparison that coordinate and building are carried out on figure, further improves the service efficiency of the auditing method.
When concrete application, with reference to attached drawing 7 it is found that this application embodiment, which provides, provides a kind of remotely checking based on GIS Method, have can accurate judgement line length, consult engineering construction validity, and it is time saving and energy saving, inexpensive, efficient Effect, specifically, can use filming apparatus obtains critical construction point (such as corner, bridge, tunnel, man-hand hole, optical fiber fusion welding point) It takes pictures, and the latitude and longitude information that will acquire and sends back, distance is carried out according to the longitude and latitude of photo institute band automatically by system Calculating, then the line length of fragmentary line project can be calculated automatically, meanwhile, the longitude and latitude taken pictures can from Dynamic and GIS map is combined, and is allowed the person in charge of the project that can not only check line length, can also be supervised entire engineering construction Journey checks check and correction using this method progress line length.The method of this automation based on the clearing of transmission line project amount, Maintenance personnel's site operation or speedily carry out rescue work while, need to only carry out upload of taking pictures to actual conditions, the automatic audit analysis processing in backstage, Whether engineering can should be settled accounts, the progress automatic management, the remote upload and transfer resource in later period such as much are measured in clearing Management brings very big convenience, revolutionizes over and makes a report on data by construction personnel, auditor checks verification without any The way of means efficiently solves the problems, such as that fragmentary engineered transmission line road length is remotely checked in time.
Specifically, this method may include steps of:
1, background storage server is established and tool of taking pictures, firstly, it is necessary to establish one according to the needs of the technical solution Platform storage server checks the storage of required initial data and photo of taking pictures for storing remote link.
Still further aspect needs to develop one and simply checks shooting tool, which can be mobile phone, runs on In Android or IOS system, the major function of the tool is taken pictures to construction site, is left and is taken pictures a little while taking pictures Latitude and longitude information and photo opporunity.The most basic information that these essential informations will be checked as remote link length.
2, it is taken pictures to critical construction point with mobile phone photograph tool, in fragmentary line project construction site, with mobile phone photograph work Tool takes pictures to construction site.Background of taking pictures is preferably selected the background with some landmark buildings, such as bridge, tunnel, iron Tower or other buildings etc. can be compared when in order to be got ready in GIS map.
After taking pictures, photo is required within (10 minutes, 15 minutes or 20 minutes etc.) within a preset time period Background server is uploaded in time to be stored.As shooting places wireless signal is bad, it has not been convenient to upload pictures, it can also be subsequent It goes home upload pictures again.Timely upload pictures, in the good place of satellite-signal, photo longitude and latitude precision is higher, is more conducive to It is accurately positioned.
3, job location critical state information is obtained, verifying construction scene and longitude and latitude precision, background server is according to applying Work scene is taken pictures the photo of upload, is on map by invocation map according to the latitude and longitude information obtained from photo It is existing.The photo that backstage personnel are above presented according to the map, photo scene can be shown by clicking photo, according to the background and ground in photo Background in kind on figure is matched, and reaches whether verifying job location is true, and whether is the latitude and longitude information obtained from photo Accurately and effectively purpose.
4, calculate fragmentary line project line length, verified to essential informations such as construction site place and longitudes and latitudes Later, it is arranged sequentially in time in GIS map taking pictures, and is identified sequentially in time.
5, fragmentary line project length calibration, if the system-computed result and construction team's reported data allow model in error In enclosing, then it is assumed that construction team's reported data is reasonable, and construction team's data can be directly used as construction line length and carry out engineering Clearing;Conversely, then construction team is allowed to give an explaination, and calls to take pictures and carry out inquiry verification.
In the following, the further details of technical solution for illustrating the application:
1) establishing checks datum number storage according to library
Fragmentary engineering to be checked, it is necessary to have the foundation checked, this just needs to establish one and checks according to number According to storing data library, the initial data for checking foundation is saved.Due to not high to requirement of real-time, the storing data library Can use an independent server can complete, and complete the original storage for checking data using database, according to not It is in the database of code storage in the server with fragmentary engineering project, project code will become the pass of retrieval and data auditing Key index word.
2) it takes pictures according to sequence of construction to construction key point
The mobile phone photograph uploading tools for developing a background storage server database of taking pictures and can upload to, will own The fragmentary engineering of construction of approving and initiate a project is pushed to and is taken pictures in uploading tools by backstage.When site operation, by construction personnel elder generation Project code and project manager are selected, then can start to take pictures to the crucial place of construction site.
In order to which backstage personnel check convenient for identification and remotely, when using mobile phone photograph, centainly it is however emphasized that interval of taking pictures With the reasonable selection for background of taking pictures.
The distance interval taken pictures:It preferably buries with the scale of line construction and requires identical, interval can suitably reduce.In order to It is accurate to calculate line length, it is desirable that must to take pictures for corner and man-hand hole, aerial, direct-burried and handover etc..
The Foreground selection taken pictures:The background taken pictures, as far as possible by landmark, such as bridge, tunnel, building frame are into photograph In piece, it is primarily to facilitate the accordance comparison that coordinate and building are carried out in GIS map.
3) construction takes pictures and uploads background data base
Site operation personnel open tool of taking pictures before construction starts, and pass through the menu selection project coding that gets off, entry name Claim and project manager's Auto-matching comes out, then just taken pictures to construction starting point and clicks directly on upload.For certain The bad place of remote mountain areas wireless signal, first can take pictures and then go home upload can also be with terminal to be onstructed must also take pictures And click completion of taking pictures, it is meant that construction terminates.
4) construction site airworthiness compliance
After one fragmentary line project construction terminates, all photos are successfully uploaded and are saved in background server database Later, backstage personnel load all photos of the project by project code, and present in GIS map automatically.Pass through click Background compares on the photo and GIS map, can verify whether the photo meets with construction site.
5) the construction actual track length of fragmentary line project is calculated
It, can be direct by following two mode after the airworthiness compliance of construction starting and terminal point, all photos is completed Calculate the construction line length of the fragmentary line project:
(1) land used icon ruler mark is calculated
It, will with the scale that map carries according to construction line and photograph time sequencing according to checking and correction result It takes pictures and is a little connected on map, become a broken line.After connection finishes, the total length of this broken line will be automatically on ground It is shown on figure.So the transmission line length of practice of construction will add and subtract an error amount on the broken line length.
(2) it is calculated automatically with longitude and latitude
Under the premise of taking pictures in strict accordance with construction direction, according to photo opporunity sequence, successively calculates and calculated on map Then the distance of two points is added the total length that will automatically derive all construction lines.
According to two o'clock longitude and latitude on the earth, the distance between two o'clock is calculated, calculation method is as follows:
If point A, longitude and latitude is respectively (LonA, LatA);Another point be B, longitude and latitude be respectively (LonB, LatB), the earth is the spheroid of an intimate standard, its equatorial radius is 6378.140 kms, polar radius 6356.755 Km, 6371.004 km of mean radius.If we assume that the earth is a perfect sphere, then its radius is exactly ground The mean radius of ball, is denoted as R.If on the basis of 0 degree of warp, according to the longitude and latitude of earth surface any two points Calculate this point-to-point transmission surface distance (ignore here earth surface landform to calculate bring error, it is only theoretic Estimated value).According to the benchmark of 0 degree of warp, the positive value (Longitude) of east longitude degree of learning from else's experience, west longitude degree of learning from else's experience negative value (- Longitude), north latitude takes 90- latitude value (90-Latitude), and south latitude takes 90+ latitude value (90+Latitude), then by upper It states the two o'clock after processing and is counted as (MLonA, MLatA) and (MLonB, MLatB).So derived according to triangle formula, it can be with Obtain calculating the following formula of two o'clock distance:
C=sin (MLatA) * sin (MLatB) * cos (MLonA-MLonB)+cos (MLatA) * cos (MLatB);
Distance=R*arccos (C) * Pi/180;
Here, R and Distance unit is identical, if it is 6371.004 kms of use as radius, then, Distance is exactly km unit.
If only making positive and negative processing to longitude, without making 90-Latitude to latitude, (assuming that being all the Northern Hemisphere, south is partly Ball only have Australia have application value) processing, then formula is:
C=sin (LatA) * sin (LatB)+cos (LatA) * cos (LatB) * cos (MLonA-MLonB);
Distance=R*arccos (C) * Pi/180;
6) data are carried out to compare and check
The line length data that the data M calculated according to step 5 and construction team report is compared n.In order to compare Error threshold is preferably 20% first according to data over the years and industry rule by as a result objective and fair, i.e., enters and leaves with real data In 20% range, then it is assumed that belong to reasonable error range.
(1) if M≤(1+20%) n, M are the fragmentary line project length value.
(2) if M >=(1+20%) n, asks construction team to give an explaination, if explaining rationally, M is the fragmentary line project length Value.If explanation is unreasonable, according to circumstances selection must arrive field verification and sampling observation, adjust Engineering Settlement route according to Examined Length value.
7) construction team's credit file is established
According to Examined, construction team's credit file is established, unit higher for credibility gives the reward in engineering. It gives the poor unit of credibility and gives and punish, job specfication management is promoted with this.
It is to carry out the case information that fragmentary line project is remotely checked using the method in the application below:
Check background:Because being inconvenient to on-site examination due to remote areas, fragmentary line project line length is remotely checked Problem, certain branch company's remoteness mountain area need since transmission line optimizes, need to the convergence loop wire by a certain small towns Carry out track remodelling.Construction team is according to requiring to construction site to have carried out construction and require with having carried out critical construction according to office side The simultaneously upload server of taking pictures of point.
After construction terminates, construction team reports line length to carry out Engineering Settlement, the construction line length reported It is 3000 meters.The person in charge of the project has invoked backstage photo and the program when auditing the report of construction team.
It is compared by the terrestrial reference on photo background and map, it is determined that job location and construction site.Then along photo It clicks scale to be attached, finally completed the line chart of construction site, calculating construction line length according to line chart is 452.51 rice.
It checks 3000 meters that result and construction team report by this to compare, difference is at as many as 6 times.Scheme is being checked in face of this Check as a result, construction team it will be recognized that reported data there are problems, line length is finally modified to 500 meters, the data It closes the account data as Engineering Settlement expense and material.
By it is above-mentioned check data can be seen that the person in charge of the project do not use construction site can be by the long-range side of checking Case remotely checks construction site, is compared by the landmark building on photo background and map with confirming construction site Point has finally reached site operation information being directly fed back to backstage, people from backstage by longitude and latitude by critical construction point location Member does not have to reach the live audit that can be completed to construction site, to the purpose that construction length and material are checked, thus Reached time saving, saved worry, convenient and be efficiently completed fragmentary line project remotely checks problem, and saved largely for company Operating expenses and engineered material Master Cost.
The technical program uploads failure and disposition picture concerned by fault in-situ, is calculated by background support, puts down Platform can be directly realized by the calculating and audit of correlation engineering amount, and branch company maintenance personnel is without going fault in-situ that audit work can be completed To make, is the resource management of optical cable, fibre core, transmission line resource optimization, engineering cost clearing provide conveniently system and support, The critical datas such as the line length of fragmentary line project are remotely checked using this method, it is fast and easy, high-efficient, and It is not required to the person in charge of the project and reaches construction site in person manually to check from the background, not only check line length, can also check Core construction site and construction quality are not only advantageous to improve construction quality, and facilitate standardized administration line material, transparent knot The engineering project for calculating line construction, accomplishes time saving and energy saving and efficient purpose.
Fig. 8 is a kind of structural schematic diagram for remotely checking device of line project provided in an embodiment of the present invention, and reference is attached Fig. 8 it is found that the another aspect of the present embodiment provide a kind of line project remotely check device, which can execute above-mentioned Auditing method, specifically, the apparatus may include:
Module 1 is obtained, for obtaining the multiple images information of line project;
Authentication module 2 for verifying according to authenticity of the image information to line project, and determines line project Latitude and longitude information;
Processing module 3, for being checked according to image information and latitude and longitude information to the line project after verifying Processing.
The present embodiment is for obtaining the concrete shape structure of module 1, authentication module 2 and processing module 3 without limitation, ability Field technique personnel can carry out any setting to it according to its function realized, details are not described herein;In addition, the present embodiment It is middle obtain module 1, the specific implementation process for the operating procedure that authentication module 2 and processing module 3 are realized and realize effect with The specific implementation process of step S101-S103 and realization effect are identical in above-described embodiment, specifically refer in above statement Hold, details are not described herein.
Further, the present embodiment verifies authentication module 2 according to authenticity of the image information to line project, And the specific implementation process of the latitude and longitude information of determining line project is without limitation, those skilled in the art can be according to specific Design requirement is configured, and more preferably, is tested in authentication module 2 according to authenticity of the image information to line project Card, and when the latitude and longitude information of determining line project, which can execute following steps:
According to the image latitude and longitude information at image information acquisition line project place on map;Obtain the pre- of line project If latitude and longitude information;If image latitude and longitude information matches with default latitude and longitude information, it is determined that the necessary being of line project, And image latitude and longitude information is determined as to the latitude and longitude information of line project.
Further, the present embodiment for processing module 3 according to image information and latitude and longitude information to after verifying Line project check the specific implementation process of processing without limitation, and those skilled in the art can be according to specific design need It asks and is configured, more preferably, in processing module 3 according to image information and latitude and longitude information to the linemen's after verifying When Cheng Jinhang checks processing, which can be used for executing following steps:
Obtain the shooting time of image information;Image information is arranged based on shooting time;According to the figure after arrangement As information and latitude and longitude information carry out line project to check processing.
Wherein, processing module 3 according to after arrangement image information and latitude and longitude information to line project carry out auditing department When reason, which is specifically used for executing:It is carried out on map according to latitude and longitude information and the image information after arrangement It sequentially marks, obtains multiple mark points;Construction line based on the line project obtained in advance is by multiple mark points on map Position is attached, and obtains map line information;Length of the line information on map determines the line of line project according to the map Drive test calculates length;Line project is carried out to check processing based on route measuring and calculating length.
Specifically, when processing module 3 carries out checking processing based on route measuring and calculating length to line project, the processing module 3 are specifically used for:Obtain the preset length of line project;If the error between route measuring and calculating length and preset length is less than or equal to Route measuring and calculating length is then determined as the total length of line project by preset threshold value;Alternatively, if route measuring and calculating length and default length Error between degree is greater than preset threshold value, then feedback is marked in line project.
Further, the specific implementation that the present embodiment obtains the multiple images information of line project for obtaining module 1 Without limitation, those skilled in the art can be configured journey according to specific design requirement, more preferably, obtain module When the multiple images information of 1 acquisition line project, which can be used for executing:Obtain multiple passes in line project Key construction point;Each critical construction point is shot, obtains multiple images information, wherein captured image information background In include preset landmark.
Line project provided in this embodiment remotely checks that device can be used in executing corresponding to Fig. 2-Fig. 7 embodiment Method, specific executive mode is similar with beneficial effect, repeats no more herein.
What the another aspect of the present embodiment provided a kind of line project remotely checks terminal, including:
Memory;
Processor;And
Computer program;
Wherein, computer program stores in memory, and is configured as being executed by processor to realize such as above-mentioned one The long-range auditing method of kind line project.
Specifically, Fig. 9 is a kind of structural schematic diagram for remotely checking terminal of line project provided in an embodiment of the present invention.
As shown in figure 9, checking that terminal 800 may include following one or more components:Processing component 802, memory 804, power supply module 806, multimedia component 808, audio component 810, input/output (I/O) interface 812, sensor module 814 and communication component 816.
The integrated operation of terminal 800 is checked in the usually control of processing component 802, and such as with display, call, data are logical Letter, camera operation and record operate associated operation.Processing component 802 may include one or more processors 820 to hold Row instruction, to perform all or part of the steps of the methods described above.In addition, processing component 802 may include one or more moulds Block, convenient for the interaction between processing component 802 and other assemblies.For example, processing component 802 may include multi-media module, with Facilitate the interaction between multimedia component 808 and processing component 802.
Memory 804 is configured as storing various types of data to support in the operation for checking terminal 800.These data Example include any application or method for being operated on checking terminal 800 instruction, contact data, telephone directory Data, message, picture, video etc..Memory 804 can by any kind of volatibility or non-volatile memory device or it Combination realize, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM) is erasable Except programmable read only memory (EPROM), programmable read only memory (PROM), read-only memory (ROM), magnetic memory, fastly Flash memory, disk or CD.
Power supply module 806 is checks that the various assemblies of terminal 800 provide electric power.Power supply module 806 may include power supply pipe Reason system, one or more power supplys and other with to check that terminal 800 generates, managees, and distributes the associated component of electric power.
Multimedia component 808 includes in the screen for checking one output interface of offer between terminal 800 and user.One In a little embodiments, screen may include liquid crystal display (LCD) and touch panel (TP).If screen includes touch panel, screen Curtain may be implemented as touch screen, to receive input signal from the user.Touch panel includes one or more touch sensings Device is to sense the gesture on touch, slide, and touch panel.Touch sensor can not only sense the side of touch or sliding action Boundary, but also detect duration and pressure relevant to touch or slide.
Audio component 810 is configured as output and/or input audio signal.For example, audio component 810 includes a Mike Wind (MIC), when checking that terminal 800 is in operation mode, when such as call mode, recording mode, and voice recognition mode, microphone It is configured as receiving external audio signal.The received audio signal can be further stored in memory 804 or via logical Believe that component 816 is sent.In some embodiments, audio component 810 further includes a loudspeaker, is used for output audio signal.
I/O interface 812 provides interface between processing component 802 and peripheral interface module, and above-mentioned peripheral interface module can To be keyboard, click wheel, button etc..These buttons may include, but are not limited to:Home button, volume button, start button and lock Determine button.
Sensor module 814 includes one or more sensors, for check that terminal 800 provides the state of various aspects Assessment.For example, sensor module 814 can detecte the state that opens/closes for checking terminal 800, the relative positioning of component, example If component is the display and keypad for checking terminal 800, sensor module 814, which can also detect, to be checked terminal 800 or checks The position change of 800 1 components of terminal, 800 orientation of terminal is checked in user and the existence or non-existence for checking that terminal 800 contacts Or acceleration/deceleration and check the temperature change of terminal 800.Sensor module 814 may include proximity sensor, be configured to It detects the presence of nearby objects without any physical contact.Sensor module 814 can also include CCD camera assembly, take the photograph As head can be used such as CMOS or ccd image sensor, for being used in imaging applications.In some embodiments, the sensor Component 814 can also include acceleration transducer, gyro sensor, Magnetic Sensor, pressure sensor or temperature sensor.
Communication component 816 is configured to facilitate the communication for checking wired or wireless way between terminal 800 and other equipment. The wireless network based on communication standard, such as WiFi can be accessed by checking terminal 800,2G or 3G or their combination.Show at one In example property embodiment, communication component 816 receives broadcast singal or broadcast from external broadcasting management system via broadcast channel Relevant information.In one exemplary embodiment, communication component 816 further includes near-field communication (NFC) module, to promote short distance logical Letter.For example, radio frequency identification (RFID) technology, Infrared Data Association (IrDA) technology, ultra wide band (UWB) can be based in NFC module Technology, bluetooth (BT) technology and other technologies are realized.
In the exemplary embodiment, check that terminal 800 can be by one or more application specific integrated circuit (ASIC), number Word signal processor (DSP), digital signal processing appts (DSPD), programmable logic device (PLD), field programmable gate array (FPGA), controller, microcontroller, microprocessor or other electronic components are realized, for executing the above method.
On the other hand the embodiment of the present invention provides a kind of computer storage medium, wherein computer storage medium is meter Calculation machine readable storage medium storing program for executing, is stored thereon with computer program;Computer program is executed by processor to realize above-mentioned one kind The long-range auditing method of line project.
Finally, it should be noted that those of ordinary skill in the art will appreciate that whole in above-described embodiment method or Part process is that relevant hardware can be instructed to complete by computer program, and the program can be stored in a computer In readable storage medium storing program for executing, the program is when being executed, it may include such as the process of the embodiment of above-mentioned each method.Wherein, described to deposit Storage media can be disk, CD, read-only memory (ROM) or random access memory (RAM) etc..
Each functional unit in the embodiment of the present invention can integrate in a processing module, be also possible to each unit It is individually physically present, can also be integrated in two or more units in a module.Above-mentioned integrated module both can be with Using formal implementation of hardware, can also be realized in the form of software function module.If the integrated module is with software The form of functional module realizes, and when sold or used as an independent product, also can store and computer-readable deposits at one In storage media.Storage medium mentioned above can be read-only memory, disk or CD etc..
The above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;Although referring to aforementioned each reality Applying example, invention is explained in detail, those skilled in the art should understand that:It still can be to aforementioned each Technical solution documented by embodiment is modified, or equivalent substitution of some or all of the technical features;And These are modified or replaceed, the range for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution.

Claims (14)

1. a kind of long-range auditing method of line project, which is characterized in that including:
Obtain the multiple images information of line project;
It is verified according to authenticity of the described image information to the line project, and determines the longitude and latitude of the line project Information;
The line project after verifying is carried out checking processing according to described image information and the latitude and longitude information.
2. the method according to claim 1, wherein according to described image information to the true of the line project Property verified, and determine the latitude and longitude information of the line project, including:
According to the image latitude and longitude information at described image acquisition of information line project place on map;
Obtain the default latitude and longitude information of the line project;
If described image latitude and longitude information matches with the default latitude and longitude information, it is determined that the line project is really deposited , and described image latitude and longitude information is determined as to the latitude and longitude information of the line project.
3. the method according to claim 1, wherein according to described image information and the latitude and longitude information to warp Line project after crossing verifying carries out checking processing, including:
Obtain the shooting time of described image information;
Described image information is arranged based on the shooting time;
According to after arrangement image information and the latitude and longitude information line project is carried out to check processing.
4. according to the method described in claim 3, it is characterized in that, according to the image information and the latitude and longitude information after arrangement The line project is carried out to check processing, including:
It is sequentially marked on map according to the latitude and longitude information and the image information after arrangement, obtains multiple labels Point;
Multiple mark point positions on map are attached by the construction line based on the line project obtained in advance, obtain map Line information;
Determine that the route of the line project calculates length according to length of the map line information on map;
The line project is carried out to check processing based on route measuring and calculating length.
5. according to the method described in claim 4, it is characterized in that, based on the route measuring and calculating length to the line project into Row checks processing, including:
Obtain the preset length of the line project;
If the error between the route measuring and calculating length and the preset length is less than or equal to preset threshold value, by the line Drive test calculates the total length that length is determined as the line project;Alternatively,
If the error between the route measuring and calculating length and the preset length is greater than preset threshold value, by the line project Feedback is marked.
6. method described in any one of -5 according to claim 1, which is characterized in that the multiple figures for obtaining line project As information, including:
Obtain multiple critical construction points in the line project;
Each critical construction point is shot, obtains multiple images information, wherein include in captured image information background Preset landmark.
7. a kind of line project remotely checks device, which is characterized in that including:
Module is obtained, for obtaining the multiple images information of line project;
Authentication module for verifying according to authenticity of the described image information to the line project, and determines the line The latitude and longitude information of road engineering;
Processing module, for being checked according to described image information and the latitude and longitude information to the line project after verifying Core processing.
8. device according to claim 7, which is characterized in that the authentication module is used for:
According to the image latitude and longitude information at described image acquisition of information line project place on map;
Obtain the default latitude and longitude information of the line project;
If described image latitude and longitude information matches with the default latitude and longitude information, it is determined that the line project is really deposited , and described image latitude and longitude information is determined as to the latitude and longitude information of the line project.
9. device according to claim 7, which is characterized in that the processing module is used for:
Obtain the shooting time of described image information;
Described image information is arranged based on the shooting time;
According to after arrangement image information and the latitude and longitude information line project is carried out to check processing.
10. device according to claim 9, which is characterized in that the processing module is used for:
It is sequentially marked on map according to the latitude and longitude information and the image information after arrangement, obtains multiple labels Point;
Multiple mark point positions on map are attached by the construction line based on the line project obtained in advance, obtain map Line information;
Determine that the route of the line project calculates length according to length of the map line information on map;
The line project is carried out to check processing based on route measuring and calculating length.
11. device according to claim 10, which is characterized in that the processing module is used for:
Obtain the preset length of the line project;
If the error between the route measuring and calculating length and the preset length is less than or equal to preset threshold value, by the line Drive test calculates the total length that length is determined as the line project;Alternatively,
If the error between the route measuring and calculating length and the preset length is greater than preset threshold value, by the line project Feedback is marked.
12. the device according to any one of claim 7-11, which is characterized in that the acquisition module is used for:
Obtain multiple critical construction points in the line project;
Each critical construction point is shot, obtains multiple images information, wherein include in captured image information background Preset landmark.
13. a kind of line project remotely checks terminal, which is characterized in that including:
Memory;
Processor;And
Computer program;
Wherein, the computer program stores in the memory, and is configured as being executed by the processor to realize such as A kind of long-range auditing method of line project described in any one of claim 1-6.
14. a kind of computer storage medium, which is characterized in that the computer storage medium is computer readable storage medium, It is stored thereon with computer program;
The computer program is executed by processor to realize a kind of line project as described in any one of claim 1-6 Long-range auditing method.
CN201810600189.6A 2018-06-12 2018-06-12 Long-range auditing method, device, terminal and the computer storage medium of line project Pending CN108848337A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810600189.6A CN108848337A (en) 2018-06-12 2018-06-12 Long-range auditing method, device, terminal and the computer storage medium of line project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810600189.6A CN108848337A (en) 2018-06-12 2018-06-12 Long-range auditing method, device, terminal and the computer storage medium of line project

Publications (1)

Publication Number Publication Date
CN108848337A true CN108848337A (en) 2018-11-20

Family

ID=64211724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810600189.6A Pending CN108848337A (en) 2018-06-12 2018-06-12 Long-range auditing method, device, terminal and the computer storage medium of line project

Country Status (1)

Country Link
CN (1) CN108848337A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109902974A (en) * 2019-04-11 2019-06-18 北京拓疆者智能科技有限公司 A kind of generation method and device of arrangement and method for construction
CN110298454A (en) * 2019-05-22 2019-10-01 深圳壹账通智能科技有限公司 Checking method, device, computer equipment and the storage medium of operation image
CN110335003A (en) * 2019-04-30 2019-10-15 中国联合网络通信集团有限公司 A kind of port resource management method and device
CN110348739A (en) * 2019-07-12 2019-10-18 武汉新江城环境事务咨询有限责任公司 Completion of project environmental protection inspection and acceptance appraisal procedure, system and storage medium
CN111552388A (en) * 2020-05-06 2020-08-18 重庆中宏建设监理有限公司 Engineering cost progress management system
CN117093548A (en) * 2023-10-20 2023-11-21 公诚管理咨询有限公司 Bidding management auditing system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002016956A (en) * 2000-06-30 2002-01-18 Toshiba Corp System and method for acquiring positional information
CN103729712A (en) * 2013-10-25 2014-04-16 国家电网公司 Intelligent security control method of electric power field operating personnel
CN104463469A (en) * 2014-12-09 2015-03-25 国家电网公司 Grid infrastructural project digital photo management method and device
CN105184519A (en) * 2015-10-23 2015-12-23 国家电网公司 Standardized safety operation tracing management system
CN106067101A (en) * 2016-08-02 2016-11-02 杭州凯达电力建设有限公司 A kind of distribution power engineering acceptance method and system
CN106096820A (en) * 2016-05-31 2016-11-09 中交第航务工程局有限公司 Engineering project management system for monitoring based on GIS
CN107063284A (en) * 2017-04-24 2017-08-18 北京视据科技有限公司 A kind of guidance path measurement of length method and device based on electronic map
CN107563635A (en) * 2017-08-29 2018-01-09 国网福建省电力有限公司 The long-range audit system of distribution line engineering construction quality and method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002016956A (en) * 2000-06-30 2002-01-18 Toshiba Corp System and method for acquiring positional information
CN103729712A (en) * 2013-10-25 2014-04-16 国家电网公司 Intelligent security control method of electric power field operating personnel
CN104463469A (en) * 2014-12-09 2015-03-25 国家电网公司 Grid infrastructural project digital photo management method and device
CN105184519A (en) * 2015-10-23 2015-12-23 国家电网公司 Standardized safety operation tracing management system
CN106096820A (en) * 2016-05-31 2016-11-09 中交第航务工程局有限公司 Engineering project management system for monitoring based on GIS
CN106067101A (en) * 2016-08-02 2016-11-02 杭州凯达电力建设有限公司 A kind of distribution power engineering acceptance method and system
CN107063284A (en) * 2017-04-24 2017-08-18 北京视据科技有限公司 A kind of guidance path measurement of length method and device based on electronic map
CN107563635A (en) * 2017-08-29 2018-01-09 国网福建省电力有限公司 The long-range audit system of distribution line engineering construction quality and method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109902974A (en) * 2019-04-11 2019-06-18 北京拓疆者智能科技有限公司 A kind of generation method and device of arrangement and method for construction
CN110335003A (en) * 2019-04-30 2019-10-15 中国联合网络通信集团有限公司 A kind of port resource management method and device
CN110298454A (en) * 2019-05-22 2019-10-01 深圳壹账通智能科技有限公司 Checking method, device, computer equipment and the storage medium of operation image
CN110348739A (en) * 2019-07-12 2019-10-18 武汉新江城环境事务咨询有限责任公司 Completion of project environmental protection inspection and acceptance appraisal procedure, system and storage medium
CN110348739B (en) * 2019-07-12 2023-04-07 武汉新江城环境事务咨询有限责任公司 Construction project completion environment-friendly acceptance assessment method and system and storage medium
CN111552388A (en) * 2020-05-06 2020-08-18 重庆中宏建设监理有限公司 Engineering cost progress management system
CN117093548A (en) * 2023-10-20 2023-11-21 公诚管理咨询有限公司 Bidding management auditing system
CN117093548B (en) * 2023-10-20 2024-01-26 公诚管理咨询有限公司 Bidding management auditing system

Similar Documents

Publication Publication Date Title
CN108848337A (en) Long-range auditing method, device, terminal and the computer storage medium of line project
CN111598379B (en) Project management method, platform, device, computer equipment and storage medium
US8977558B2 (en) Methods, apparatus and systems for facilitating generation and assessment of engineering plans
US8731999B2 (en) Management system, and associated methods and apparatus, for providing improved visibility, quality control and audit capability for underground facility locate and/or marking operations
CN112232761B (en) Infrastructure application system and method
CN103927860A (en) GPS (Global Position System)-positioned meter reading smart handheld machine and meter reading system
KR102038269B1 (en) Method for providing professional visiting service and apparatus thereof
CN102074107A (en) Positioning navigation meter reading handheld terminal
US20150227893A1 (en) Estimate method and generator
CN112053124A (en) Online on-line payment method and device, electronic equipment and medium
CN109840701A (en) A kind of engineering construction quality control system
CN111582729A (en) System and method for acquiring field data of soil mass and geological survey
WO2017141225A2 (en) Method for diagnosing/managing new renewable energy facility using mobile terminal and system therefor
CN109636312A (en) Land control engineering online monitoring and management system
US20140229204A1 (en) Estimate method and generator
CN109784840A (en) A kind of construction survey automatic data collection processing method being associated with engineering structure task
CN109582702A (en) A kind of off-line data processing system and method based on Spacecraft TT&C
CN111797946A (en) Water quality sample collection management method and related equipment and storage device thereof
WO2009158017A2 (en) Methods and apparatus for quality assessment of a field service operation
CN114511296A (en) High-standard farmland construction project management platform
CN113010987A (en) Real-time judgment method for construction progress of overhead line based on Internet of things
US20200311741A1 (en) Methods and systems for validating order request
US11216782B2 (en) Insurance system
CN110891080A (en) Supervision on-site intelligent application platform system
Vacanas The risk of delay in Cyprus construction industry: causes, effects and control

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181120