CN108564336A - The identification of power transformation installing engineering construction drawing drawing and budgetary technique and system - Google Patents
The identification of power transformation installing engineering construction drawing drawing and budgetary technique and system Download PDFInfo
- Publication number
- CN108564336A CN108564336A CN201810236960.6A CN201810236960A CN108564336A CN 108564336 A CN108564336 A CN 108564336A CN 201810236960 A CN201810236960 A CN 201810236960A CN 108564336 A CN108564336 A CN 108564336A
- Authority
- CN
- China
- Prior art keywords
- equipment
- rule
- data base
- construction
- information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S40/00—Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
- Y04S40/20—Information technology specific aspects, e.g. CAD, simulation, modelling, system security
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- Economics (AREA)
- Human Resources & Organizations (AREA)
- General Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Geometry (AREA)
- General Engineering & Computer Science (AREA)
- Data Mining & Analysis (AREA)
- Public Health (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses the identification of power transformation installing engineering construction drawing drawing and budgetary technique and systems.The present invention establishes drawing data base institutes rule, forms the framework of drawing data base;Using drawing essential information collection rule and drawing combined information collection rule, construction drawing quantities is obtained, is added in drawing data base;Using unit type and material model as matching logic, equipment and materials prices match rule is established, construction drawing equipment and material price information are added in drawing data base;The construction drawing quantities and equipment and materials price in drawing data base are combed one by one, using mechanically used quota as matching logic, quota matching rule is established, the quota data in project quota database are added to one by one under the corresponding quantities of drawing data base, completes budget compilation.The present invention can reduce working drawing budget establishment required time and manpower consumption, rapidly and accurately meet quantities establishment needs when project bid, achieve the purpose that project cost finely controls.
Description
Technical field
The invention belongs to electricity power engineering budget technical field, specifically the identification of power transformation installing engineering construction drawing drawing and
Budgetary technique and system.
Background technology
Reinforce the effective measures and important means that electricity power engineering working drawing budget management is comprehensive structure cost system, to control
Power grid construction investment processed has a very important significance, and working drawing budget is the important link of control engineering cost, valuation model
Be conducive to controlled investment, improve designing quality, realizes the lean management of electricity power engineering Project Cost.
Deepen in particular with electricity power engineering cost information degree, the mode of tradition establishment working drawing budget is in progress
It is difficult to meet the requirement of Cost Management, especially in terms of the matching with the calling for tenders of project time, and traditional approach needs designing unit
A large amount of human resources inputs, be easy to cause crew shortage.
Currently, being badly in need of a kind of power transformation installing engineering working drawing budget preparation method, to solve tradition establishment working drawing budget
The problems such as budget compilation input is high caused by mode, time-consuming.
Invention content
The technical problem to be solved by the present invention is to overcome the problems of the above-mentioned prior art, power transformation engineering construction is provided
Figure drawing identifies and budgetary technique, to reduce working drawing budget establishment required time and manpower consumption, quick and precisely meets
Quantities establishment when project bid needs, and achievees the purpose that project cost finely controls.
For this purpose, the present invention adopts the following technical scheme that:Power transformation installing engineering construction drawing drawing identifies and budget compilation side
Method comprising construction drawing drawing identifies and working drawing budget establishment, and working drawing budget establishment includes the following steps:
Step 1) navigates to catalogue file from construction drawing drawing packet, acquires respective directories information, incorporation engineering item dividing mark
Standard establishes drawing data base institutes rule, forms the framework of drawing data base;
Step 2) reads title, model, unit and the quantity of equipment and material from construction drawing drawing, according to unit type and
The letter abbreviations rule of material model translates model, establishes drawing essential information collection rule;
Step 3), positioning device cross-section diagram and facility installation drawing from construction drawing drawing packet acquire drawing information, and association, which is formed, draws
Offline, interfacility link, wire jumper and gold utensil combinatorial libraries, equipment mounting material combinatorial libraries, insulator chain combinatorial libraries, cross-line combination
Drawing combined information collection rule is established in library;
Using drawing essential information collection rule and drawing combined information collection rule, construction drawing quantities is obtained, figure is added to
In paper database;
Step 4) obtains equipment price from outside and material price forms equipment and materials information valence library, with unit type and material
Model matching logic establishes equipment and materials prices match rule, construction drawing equipment and material price information is added to drawing
In database;
Step 5) combs construction drawing quantities and equipment and materials price in drawing data base one by one, is matching with mechanically used quota
Logic establishes quota matching rule, and it is corresponding that the quota data in project quota database are added to drawing data base one by one
Under quantities, budget compilation is completed.
The present invention is when working drawing budget is worked out, no longer using the quantities of manual typing as foundation, direct basis drawing number
Rule, essential information collection rule, combined information collection rule, quota matching rule, equipment and materials price are set up according to library structure
Matching rule generates working drawing budget.
As the supplement of above-mentioned technical proposal, when the construction drawing drawing identifies, recorded according to construction drawing drawing
Electronic data sets up corresponding translation rule according to different data format and data content, completes drawing information identification and reads,
Form construction drawing drawing packet.
As the supplement of above-mentioned technical proposal, in step 3), passes through algorithm and be automatically positioned capital equipment drawing, read mark
Block, by the quantity, model and unit of equipment, Classifying Sum forming apparatus parameter list, model is translated by rule, by home block title,
Device parameter information is stored in drawing data library structure respectively under relevant device title;Pass through algorithm automatic positioning equipment cross-section diagram
And facility installation drawing, home block is read, by material quantity, model and unit, Classifying Sum is at material parameter list, and model is by rule
Translation, according to material and equipment incidence relation by the corresponding drawing data library structure of home block title, the deposit of material parameter information
Under middle relevant device title, drawing essential information is formed;For downlead, wire jumper, cross-line, interfacility link, gold utensil and insulation
Substring due to can not be directly read from drawing home block, thus obtains respective default numerical value, according to this kind of from history engineering
Material forms drawing combined information under relevant device title in equipment incidence relation deposit drawing data library structure;By drawing
Essential information and drawing combined information, Classifying Sum to construction drawing quantities form drawing data base.
The present invention also provides the identification of power transformation installing engineering construction drawing drawing and budgeting systems comprising:
Drawing data base framework forms module:Catalogue file is navigated to from construction drawing drawing packet, acquires respective directories information, knot
The engineering project criteria for classifying is closed, drawing data base institutes rule is established, forms the framework of drawing data base;
Drawing basic information module:Title, model, unit and the quantity that equipment and material are read from construction drawing drawing, according to
The letter abbreviations rule of unit type and material model translates model;
Drawing combined information module:Positioning device cross-section diagram and facility installation drawing from construction drawing drawing packet acquire drawing information,
Association formed downlead, interfacility link, wire jumper and gold utensil combinatorial libraries, equipment mounting material combinatorial libraries, insulator chain combinatorial libraries,
Cross-line combinatorial libraries;
Using drawing basic information module and drawing combined information module, construction drawing quantities is obtained, drawing data base is added to
In;
Equipment and materials pricing information module:Equipment price is obtained from outside and material price forms equipment and materials information valence library, with
Unit type and material model are matching logic, equipment and materials prices match rule are established, by construction drawing equipment and material price
Information is added in drawing data base;
Budget compilation module:The construction drawing quantities and equipment and materials price in drawing data base are combed one by one, with mechanically used quota
For matching logic, quota matching rule is established, the quota data in project quota database are added to drawing data base one by one
Under corresponding quantities, budget compilation is completed.
The electricity power engineering construction drawing drawing identification and budgeting system further include drawing identification module, the figure
Paper identification module is:According to the electronic data that construction drawing drawing is recorded, phase is set up according to different data format and data content
The translation rule answered is completed drawing information identification and is read, forms construction drawing drawing packet.
The device have the advantages that as follows:
The time required to the present invention can reduce working drawing budget establishment and manpower consumption, when rapidly and accurately meeting project bid
Quantities establishment needs, and achievees the purpose that project cost finely controls.
The present invention can not only quickly read quantities after construction drawing is provided from figure, and can apply mechanically automatically corresponding
Norm for detailed estimates completes construction budget establishment.
Description of the drawings
Fig. 1 is the flow chart of working drawing budget preparation method in the embodiment of the present invention 1;
Fig. 2 is the functional block diagram of working drawing budget workout system in the embodiment of the present invention 2.
Specific implementation mode
The invention will be further described with specific implementation mode with reference to the accompanying drawings of the specification.
Embodiment 1
The present embodiment provides the identification of power transformation installing engineering construction drawing drawing and budgetary techniques comprising construction drawing drawing identifies
It is worked out with working drawing budget.When the described construction drawing drawing identification, the electron number that is recorded according to construction drawing drawing (CAD diagram paper)
According to setting up corresponding translation rule according to different data format and data content, complete drawing information identification and read, formation is applied
Work figure drawing packet.
The working drawing budget is worked out as shown in Figure 1, it includes the following steps:
Step 1) navigates to catalogue file from construction drawing drawing packet, acquires respective directories information, incorporation engineering item dividing mark
Standard establishes drawing data base institutes rule, forms the framework of drawing data base;
Step 2) reads title, model, unit and the quantity of equipment and material from construction drawing drawing, according to unit type and
The letter abbreviations rule of material model translates model, establishes drawing essential information collection rule;
Step 3), positioning device cross-section diagram and facility installation drawing from construction drawing drawing packet acquire drawing information, and association, which is formed, draws
Offline, interfacility link, wire jumper and gold utensil combinatorial libraries, equipment mounting material combinatorial libraries, insulator chain combinatorial libraries, cross-line combination
Drawing combined information collection rule is established in library;
Using drawing essential information collection rule and drawing combined information collection rule, construction drawing quantities is obtained, figure is added to
In paper database;
Step 4) obtains equipment price from outside and material price forms equipment and materials information valence library, with unit type and material
Model matching logic establishes equipment and materials prices match rule, construction drawing equipment and material price information is added to drawing
In database;
Step 5) combs construction drawing quantities and equipment and materials price in drawing data base one by one, is matching with mechanically used quota
Logic establishes quota matching rule, and it is corresponding that the quota data in project quota database are added to drawing data base one by one
Under quantities, budget compilation is completed, construction budget file is obtained.
In step 3), by algorithm be automatically positioned capital equipment drawing, read home block, by the quantity of equipment, model and
Unit, Classifying Sum forming apparatus parameter list, model are translated by rule, and by home block title, device parameter information is stored in figure respectively
In paper database structure under relevant device title;By algorithm automatic positioning equipment cross-section diagram and facility installation drawing, mark is read
Block, by material quantity, model and unit, Classifying Sum is translated by rule at material parameter list, model, is closed according to material and equipment
Home block title, material parameter information are stored in corresponding drawing data library structure under relevant device title by connection relationship, are formed
Drawing essential information;For downlead, wire jumper, cross-line, interfacility link, gold utensil and insulator chain, due to can not be from drawing mark
Know in block and directly read, thus obtain respective default numerical value from history engineering, is deposited according to this kind of material and equipment incidence relation
Enter in drawing data library structure under relevant device title, forms drawing combined information;By drawing essential information and drawing combination letter
Breath, Classifying Sum to construction drawing quantities form drawing data base.
The present invention is after engineering construction drawing is provided, and according to drawing electronic data and translation rule, positioning volume catalogue is simultaneously
Acquisition information establishes drawing normal structure data according to project of standard development division, on the one hand, is acquired in drawing normal structure data
The attribute datas such as equipment and the model of material, quantity, title, unit and essential information is added in corresponding drawing, on the other hand,
Relevant device in drawing normal structure data recorded in the drawings such as collecting device installation, cross-section diagram is associated with mounting material
Relation data simultaneously adds related information.After drawing is read, after essential information Classifying Sum, conversion portion unit, formed
Standard device detailed list of materials, and relevant device material price in price library is added, the combination of performance valence.According to drawing normal structure
Data and project quota database matching, add corresponding quota data, realize working drawing budget establishment.
Embodiment 2
The present embodiment provides the identification of power transformation installing engineering construction drawing drawing and budgeting systems comprising drawing identification module,
Drawing data base framework forms module, drawing basic information module, drawing combined information module, equipment and materials pricing information module
With budget compilation module, as shown in Figure 2.
The drawing identification module is:According to the electronic data that construction drawing drawing (CAD diagram paper) is recorded, according to difference
Data format and data content set up corresponding translation rule, complete drawing information identification and read, form construction drawing drawing packet.
The drawing data base framework forms module:Catalogue file is navigated to from construction drawing drawing packet, acquires phase
Directory information, incorporation engineering item dividing standard is answered to establish drawing data base institutes rule, form the frame of drawing data base
Structure.
The drawing basic information module is:Title, model, the unit of equipment and material are read from construction drawing drawing
And quantity, model is translated according to the letter abbreviations rule of unit type and material model.
The drawing combined information module is:Positioning device cross-section diagram and facility installation drawing from construction drawing drawing packet,
Acquire drawing information, association formed downlead, interfacility link, wire jumper and gold utensil combinatorial libraries, equipment mounting material combinatorial libraries, absolutely
Edge substring combinatorial libraries, cross-line combinatorial libraries.
Using drawing basic information module and drawing combined information module, construction drawing quantities is obtained, is added to drawing number
According in library.
The equipment and materials pricing information module is:Equipment price is obtained from outside and material price forms equipment and materials
Equipment and materials prices match rule is established, by construction drawing equipment in information valence library using unit type and material model as matching logic
It is added in drawing data base with material price information.
The budget compilation module:The construction drawing quantities and equipment and materials price in drawing data base are combed one by one,
Using mechanically used quota as matching logic, quota matching rule is established, the quota data in project quota database are added to one by one
Under the corresponding quantities of drawing data base, budget compilation is completed.
Embodiments of the present invention above described embodiment only expresses, can not be therefore understands that for patent of invention range
Limitation, also not to the present invention structure make any form of restriction.It should be pointed out that for the common skill of this field
For art personnel, without departing from the inventive concept of the premise, several changes and improvements can also be made, these belong to this hair
Bright protection domain.
Claims (5)
1. power transformation installing engineering construction drawing drawing identifies and budgetary technique, which is characterized in that identified including construction drawing drawing
It is worked out with working drawing budget, working drawing budget establishment includes the following steps:
Step 1) navigates to catalogue file from construction drawing drawing packet, acquires respective directories information, incorporation engineering item dividing mark
Standard establishes drawing data base institutes rule, forms the framework of drawing data base;
Step 2) reads title, model, unit and the quantity of equipment and material from construction drawing drawing, according to unit type and
The letter abbreviations rule of material model translates model, establishes drawing essential information collection rule;
Step 3), positioning device cross-section diagram and facility installation drawing from construction drawing drawing packet acquire drawing information, and association, which is formed, draws
Offline, interfacility link, wire jumper and gold utensil combinatorial libraries, equipment mounting material combinatorial libraries, insulator chain combinatorial libraries, cross-line combination
Drawing combined information collection rule is established in library;
Using drawing essential information collection rule and drawing combined information collection rule, construction drawing quantities is obtained, figure is added to
In paper database;
Step 4) obtains equipment price from outside and material price forms equipment and materials information valence library, with unit type and material
Model matching logic establishes equipment and materials prices match rule, construction drawing equipment and material price information is added to drawing
In database;
Step 5) combs construction drawing quantities and equipment and materials price in drawing data base one by one, is matching with mechanically used quota
Logic establishes quota matching rule, and it is corresponding that the quota data in project quota database are added to drawing data base one by one
Under quantities, budget compilation is completed.
2. electricity power engineering construction drawing drawing identification according to claim 1 and budgetary technique, which is characterized in that described
Construction drawing drawing identification when, according to the electronic data that construction drawing drawing is recorded, according to different data format and data content
Corresponding translation rule is set up, drawing information identification is completed and is read, construction drawing drawing packet is formed.
3. electricity power engineering construction drawing drawing identification according to claim 1 or 2 and budgetary technique, which is characterized in that
In step 3), capital equipment drawing is automatically positioned by algorithm, reads home block, by the quantity, model and unit of equipment, classification
It is aggregated into device parameter list, model is translated by rule, and by home block title, device parameter information is stored in drawing data base knot respectively
In structure under relevant device title;By algorithm automatic positioning equipment cross-section diagram and facility installation drawing, home block is read, by material number
Amount, model and unit, Classifying Sum are translated at material parameter list, model by rule, will be marked according to material and equipment incidence relation
Know in block title, the corresponding drawing data library structure of material parameter information deposit under relevant device title, formation drawing is believed substantially
Breath;For downlead, wire jumper, cross-line, interfacility link, gold utensil and insulator chain, due to can not be from drawing home block directly
It reads, thus obtains respective default numerical value from history engineering, drawing data is stored according to this kind of material and equipment incidence relation
In library structure under relevant device title, drawing combined information is formed;By drawing essential information and drawing combined information, Classifying Sum
To construction drawing quantities, drawing data base is formed.
4. power transformation installing engineering construction drawing drawing identifies and budgeting system, which is characterized in that including:
Drawing data base framework forms module:Catalogue file is navigated to from construction drawing drawing packet, acquires respective directories information, knot
The engineering project criteria for classifying is closed, drawing data base institutes rule is established, forms the framework of drawing data base;
Drawing basic information module:Title, model, unit and the quantity that equipment and material are read from construction drawing drawing, according to
The letter abbreviations rule of unit type and material model translates model;
Drawing combined information module:Positioning device cross-section diagram and facility installation drawing from construction drawing drawing packet acquire drawing information,
Association formed downlead, interfacility link, wire jumper and gold utensil combinatorial libraries, equipment mounting material combinatorial libraries, insulator chain combinatorial libraries,
Cross-line combinatorial libraries;
Using drawing basic information module and drawing combined information module, construction drawing quantities is obtained, drawing data base is added to
In;
Equipment and materials pricing information module:Equipment price is obtained from outside and material price forms equipment and materials information valence library, with
Unit type and material model are matching logic, equipment and materials prices match rule are established, by construction drawing equipment and material price
Information is added in drawing data base;
Budget compilation module:The construction drawing quantities and equipment and materials price in drawing data base are combed one by one, with mechanically used quota
For matching logic, quota matching rule is established, the quota data in project quota database are added to drawing data base one by one
Under corresponding quantities, budget compilation is completed.
5. electricity power engineering construction drawing drawing identification according to claim 4 and budgeting system, which is characterized in that also wrap
Drawing identification module is included, the drawing identification module is:According to the electronic data that construction drawing drawing is recorded, according to different numbers
Corresponding translation rule is set up according to format and data content, complete drawing information identification and is read, construction drawing drawing packet is formed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810236960.6A CN108564336B (en) | 2018-03-21 | 2018-03-21 | Substation installation project construction drawing identification and budgeting method and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810236960.6A CN108564336B (en) | 2018-03-21 | 2018-03-21 | Substation installation project construction drawing identification and budgeting method and system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108564336A true CN108564336A (en) | 2018-09-21 |
CN108564336B CN108564336B (en) | 2021-11-26 |
Family
ID=63533041
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810236960.6A Active CN108564336B (en) | 2018-03-21 | 2018-03-21 | Substation installation project construction drawing identification and budgeting method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108564336B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109800470A (en) * | 2018-12-25 | 2019-05-24 | 山东爱普电气设备有限公司 | A kind of fixed low-voltage complete switch equipment unified bus calculation method and system |
CN110009302A (en) * | 2019-03-21 | 2019-07-12 | 广州翔实工程咨询有限公司 | Automatic cross rate method, system and storage medium based on BIM and database |
CN110795809A (en) * | 2019-11-07 | 2020-02-14 | 国网河北省电力有限公司电力科学研究院 | Method, system and medium for transformer substation electrical secondary circuit connection relation based on CAD graph automatic pickup |
CN110992600A (en) * | 2019-12-06 | 2020-04-10 | 万翼科技有限公司 | Building material dispensing and receiving method and related equipment |
CN111260413A (en) * | 2020-01-22 | 2020-06-09 | 国网浙江省电力有限公司经济技术研究院 | Vector graph-based rapid calculation method for construction cost of power main network engineering |
CN111476855A (en) * | 2020-04-03 | 2020-07-31 | 兰剑智能科技股份有限公司 | Scheme drawing method and device, electronic equipment and computer readable medium |
CN113095296A (en) * | 2021-05-10 | 2021-07-09 | 温州广信工程管理有限公司 | Civil engineering material calculation system and method based on Internet of things |
CN113469744A (en) * | 2021-07-05 | 2021-10-01 | 四川明星电力股份有限公司 | Modular budget method and system based on typical design of distribution network |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1136919A2 (en) * | 2000-03-24 | 2001-09-26 | Original Engineering Consultants Co., Ltd. | A constructional actual cost calculation system |
CN101030194A (en) * | 2007-02-12 | 2007-09-05 | 谢红安 | Engineering-amount computer system and method |
US20110145027A1 (en) * | 2009-12-12 | 2011-06-16 | Nicusor Mihai | System for visually processing and presenting cost estimates |
CN103617243A (en) * | 2013-11-28 | 2014-03-05 | 国家电网公司 | System and method for automatically generating project amount and drawing CAD chart |
CN103699963A (en) * | 2013-12-14 | 2014-04-02 | 中广核工程有限公司 | Mounting work amount calculation method and system for nuclear power project |
CN105373864A (en) * | 2015-12-09 | 2016-03-02 | 国网四川省电力公司遂宁供电公司 | Rural power grid design method |
-
2018
- 2018-03-21 CN CN201810236960.6A patent/CN108564336B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1136919A2 (en) * | 2000-03-24 | 2001-09-26 | Original Engineering Consultants Co., Ltd. | A constructional actual cost calculation system |
CN101030194A (en) * | 2007-02-12 | 2007-09-05 | 谢红安 | Engineering-amount computer system and method |
US20110145027A1 (en) * | 2009-12-12 | 2011-06-16 | Nicusor Mihai | System for visually processing and presenting cost estimates |
CN103617243A (en) * | 2013-11-28 | 2014-03-05 | 国家电网公司 | System and method for automatically generating project amount and drawing CAD chart |
CN103699963A (en) * | 2013-12-14 | 2014-04-02 | 中广核工程有限公司 | Mounting work amount calculation method and system for nuclear power project |
CN105373864A (en) * | 2015-12-09 | 2016-03-02 | 国网四川省电力公司遂宁供电公司 | Rural power grid design method |
Non-Patent Citations (2)
Title |
---|
PARK, HEE-WON: "Estimating on The Construction Costs for Public Kindergarten Buildings", 《THE JOURNAL OF SUSTAINABLE DESIGN AND EDUCATIONAL ENVIRONMENT RESEARCH》 * |
洪建武: "CAD环境中工程预算关键技术研究", 《中国优秀博硕士学位论文全文数据库 (硕士)》 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109800470A (en) * | 2018-12-25 | 2019-05-24 | 山东爱普电气设备有限公司 | A kind of fixed low-voltage complete switch equipment unified bus calculation method and system |
CN110009302A (en) * | 2019-03-21 | 2019-07-12 | 广州翔实工程咨询有限公司 | Automatic cross rate method, system and storage medium based on BIM and database |
CN110795809A (en) * | 2019-11-07 | 2020-02-14 | 国网河北省电力有限公司电力科学研究院 | Method, system and medium for transformer substation electrical secondary circuit connection relation based on CAD graph automatic pickup |
CN110795809B (en) * | 2019-11-07 | 2023-08-29 | 国网河北省电力有限公司电力科学研究院 | Method, system and medium for automatically picking up connection relation of electric secondary circuit of transformer substation based on CAD (computer aided design) drawing |
CN110992600A (en) * | 2019-12-06 | 2020-04-10 | 万翼科技有限公司 | Building material dispensing and receiving method and related equipment |
CN111260413A (en) * | 2020-01-22 | 2020-06-09 | 国网浙江省电力有限公司经济技术研究院 | Vector graph-based rapid calculation method for construction cost of power main network engineering |
CN111260413B (en) * | 2020-01-22 | 2023-09-12 | 国网浙江省电力有限公司经济技术研究院 | Vector graph-based electric power main network engineering construction diagram cost quick calculation method |
CN111476855A (en) * | 2020-04-03 | 2020-07-31 | 兰剑智能科技股份有限公司 | Scheme drawing method and device, electronic equipment and computer readable medium |
CN111476855B (en) * | 2020-04-03 | 2024-01-26 | 兰剑智能科技股份有限公司 | Scheme drawing method, device, electronic equipment and computer readable medium |
CN113095296A (en) * | 2021-05-10 | 2021-07-09 | 温州广信工程管理有限公司 | Civil engineering material calculation system and method based on Internet of things |
CN113469744A (en) * | 2021-07-05 | 2021-10-01 | 四川明星电力股份有限公司 | Modular budget method and system based on typical design of distribution network |
CN113469744B (en) * | 2021-07-05 | 2023-06-16 | 四川明星电力股份有限公司 | Modular budget method and system based on distribution network typical design |
Also Published As
Publication number | Publication date |
---|---|
CN108564336B (en) | 2021-11-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108564336A (en) | The identification of power transformation installing engineering construction drawing drawing and budgetary technique and system | |
CN108971807B (en) | Intelligent management control method and management system for field welding construction process | |
CN107368967A (en) | Engineering safety quality inspection intelligent management based on internet | |
CN102411540B (en) | Automatic management system of workflow-based common software testing process | |
CN109472642A (en) | The editing of electricity power engineering cost and inventory application system based on working drawing budget management | |
CN106447197A (en) | Construction cost data management system | |
CN105608254A (en) | Automated design method and platform oriented to intelligent hardware system development | |
CN108876019A (en) | A kind of electro-load forecast method and system based on big data | |
CN109300001A (en) | Tailoring technique analysis method, device, electronic equipment and storage medium | |
CN111260413A (en) | Vector graph-based rapid calculation method for construction cost of power main network engineering | |
CN109978495A (en) | A kind of nuclear power station debugging test Report workout method and system | |
CN104298705B (en) | A kind of conversion method of relational data and unstructured data | |
CN105630734A (en) | Configuration method and device for ex-factory parameters of power equipment terminal | |
CN104537131A (en) | Data collection method for satellite final assembly process | |
CN113722311A (en) | Power distribution network power failure range positioning method, system, equipment and medium | |
CN106126522A (en) | A kind of processing system of accounting statement | |
CN109726513A (en) | Project big data analysis system based on BIM | |
CN108229816A (en) | Management method is matched by the battalion of Internet of Things networking based on distributed management | |
CN110110950A (en) | Generate the method, apparatus and computer readable storage medium in dispatching road area | |
CN106254174A (en) | A kind of consumption information processing system | |
Chen et al. | The influence of green technology cognition in adoption behavior: On the consideration of green innovation policy perception’s moderating effect | |
CN101777052A (en) | Marketing and distribution platform region information management system | |
CN105633970B (en) | Distribution back scheduling control system building method based on major network scheduling system | |
CN110674235B (en) | Synchronous management system and method for marketing and distribution topology files | |
CN104317704A (en) | Measuring software integration method for production line automatic test system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |