CN108197802A - It is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control - Google Patents
It is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control Download PDFInfo
- Publication number
- CN108197802A CN108197802A CN201711480910.4A CN201711480910A CN108197802A CN 108197802 A CN108197802 A CN 108197802A CN 201711480910 A CN201711480910 A CN 201711480910A CN 108197802 A CN108197802 A CN 108197802A
- Authority
- CN
- China
- Prior art keywords
- bim
- construction
- concrete structure
- node
- quality
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 82
- 238000000034 method Methods 0.000 title claims abstract description 28
- 238000005516 engineering process Methods 0.000 title claims abstract description 18
- 239000000463 material Substances 0.000 claims abstract description 7
- 238000003908 quality control method Methods 0.000 claims description 11
- 230000000694 effects Effects 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims description 3
- 238000012795 verification Methods 0.000 abstract description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000012790 confirmation Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 238000003384 imaging method Methods 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q10/06395—Quality analysis or management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Operations Research (AREA)
- Data Mining & Analysis (AREA)
- Game Theory and Decision Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention discloses a kind of method and system based on BIM technology to concrete structure construction quality management and control, includes the following steps:BIM threedimensional models are established according to arrangement and method for construction;Setting critical construction checks and accepts node in the three-dimensional model;Examination image information, which is acquired, using image documentation equipment is uploaded to BIM threedimensional models;The live material information of verification is uploaded to BIM threedimensional models;Upload information is matched with BIM three-dimensional model informations;Next construction node is carried out if successful match to check and accept;If it fails to match, rectified and improved, checked and accepted until successful match carries out next construction node again.It is of the present invention to be based on BIM construction quality managing and control systems, by BIM threedimensional models, the substep control of construction site and BIM model informations are realized, high degree reduces construction quality problem and the nonstandard problem of onsite acceptance.
Description
Technical field
The present invention relates to it is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control, especially relate to
And large-sized concrete structure, quality control require the method and system of high construction site quality management and control.
Background technology
In heavy construction construction field, construction quality management is the key that one ring of field control.In the prior art, due to item
The mesh duration is tight, blindly pursues speed and the engineering project of economic benefit emerges in an endless stream, final construction quality is caused to be difficult to be protected
Card.Quality management is caused to disconnect due to excessively pursuing progress control and cost management, once key node control is not in place,
And in order to pursue speed blindly overwork, it will cause great security risk, and bring economic loss difficult to the appraisal.
Meanwhile compared to external construction quality management level, the existing construction quality management level in China also relatively lags behind,
The quality information acquisition of traditional mode is copied repeatedly mostly using papery data, and information is lengthy and jumbled to cause many unnecessary labour,
Slow down the duration.Shared difficulty is big simultaneously, stays mostly in paper form, and it is extremely serious to practise fraud, and is hardly formed effective letter
Breathization.And key message missing is easily caused, brings great security risk.
Invention content
The technical problem to be solved in the present invention is to provide a kind of by BIM technology model and concrete structure construction quality management
It is combined, realizes that the quality management of concrete structure site operation is qualified, ensure the method and system of project quality, while can be real
It is now generated to checking and accepting the synchronous of data, greatly reduces unnecessary manual labor, to accelerate engineering construction.
For solution more than technical problem, the present invention uses following scheme:One kind is based on BIM technology to concrete structure construction
The method and system of quality management and control, include the following steps:
Step 1:It identifies project arrangement and method for construction, and arrangement and method for construction is imported into BIM systems, establish BIM threedimensional models, and
The critical construction of concrete structure is set to check and accept node in BIM threedimensional models;
Step 2:Live Quality Inspector is believed critical construction node image using the technical equipment such as digital camera, panoramic scanning
Breath acquires and uploads to BIM threedimensional models;
Step 3:Live Quality Inspector acquires corresponding construction node material requested, and quantity, position, which is put, waits construction inspection rules
Require information, and upload to BIM threedimensional models;
Step 4:Collected information and the arrangement and method for construction in BIM models are matched, if successful match, carried out
The construction of next step;If it fails to match, it will rectify and improve rapidly, after reaching quality requirement, BIM models could carry out next step
Operation;Step 5:According to《Concrete structure engineering construction quality accident specification》Each construction node identified project, and to each
Node construct according to above-mentioned requirements control;
Step 6:After a node examination of constructing passes through, data will be checked and accepted by BIM threedimensional models and exported, and by phase
It closes responsible party and represents signature confirmation.
Further, in step 1, pass through the foundation to threedimensional model and examination node, you can institute is checked and accepted in export
The key messages such as each part dimension structure needed, material property, convenient for the matching work of step 4.
Further, in step 4, to ensure that concealment part sets up examination node before pouring for concealed work,
Ensure the inspection of quality before pouring.
Further, by the operational mode of preceding step, once there is construction quality problem, you can pass through model text
Part clears the responsibility of the main at the first time.
Compared with prior art, the present invention has following benefit:
1 present invention based on BIM technology to the method and system of concrete structure construction quality management and control by BIM technology with
The combination of construction site ensure that the stringent supervision of quality information, information-based, effectively prevent the generation that information is played tricks.
Information timely and effectively can be transmitted to management side and Party A by 2 quality control systems from construction party, be reduced
Cumbersome copies process, improves work efficiency.
3 quality control systems, it is ensured that the accuracy that information is transmitted, by with no paper office, with generation
The transmission of the forms such as table or document, reduces the information error copied privately and brought.
4 quality control systems by three-dimensional modeling, break away from the abstract of word, can be more intuitively by quality feelings
Condition shows Construction Party, and the intuitive mode of intelligence transmission substantially increases reading efficiency.
Description of the drawings
Fig. 1 is a kind of based on operation of the BIM technology to the method and system of concrete structure construction quality management and control for the present invention
Flow chart.
Specific embodiment
Illustrate the specific embodiment of the invention below by way of specific particular instance, those skilled in the art can be by this theory
Content described in bright book understands feature and effect of the present invention.The present invention can also be subject to reality by way of a different and different embodiment
It applies or applies, the details of this specification can also be based on different viewpoints and application, under the premise of the spirit without departing from the present invention
It is modified.
As shown in fig.1, a kind of for the present invention to the method for concrete structure construction quality management and control and be based on BIM technology
System operational flowchart.As shown in Figure 1, the present invention it is a kind of based on BIM technology to the method for concrete structure construction quality management and control and
System mainly includes the following steps:
Step 1:BIM threedimensional models are established according to arrangement and method for construction;
Step 2:Setting critical construction checks and accepts node in the three-dimensional model;
Step 3:Examination image information, which is acquired, using image documentation equipment is uploaded to BIM threedimensional models;
Step 4:The live material information of verification is uploaded to BIM threedimensional models;
Step 5:Upload information is matched with BIM three-dimensional model informations;
Step 6:Next construction node is carried out if successful match to check and accept;If it fails to match, rectified and improved,
It is checked and accepted until successful match carries out next construction node again;
(BIM models type software, and same type can be used by taking the AutodeskRevit softwares in BIM technology as an example below
Other classes BIM softwares, the present invention is not to using software to be particularly limited to), to further illustrate the present invention, to concrete knot
The concrete scheme of the method and system of structure construction quality management and control is as follows:
In step 1:According to the arrangement and method for construction for having designed completion, engineering is established using AutodeskRevit softwares
Threedimensional model and structure three-dimensional model are arranged in construction main flat face.The Chinese of AutodeskRevit is architectural design and construction
Software, major function is constructs Building Information Model.BIM is to design, construct to whole operation and the structure based on information
The model system built.In the present invention, using the modeling function of AutodeskRevit softwares, it is three-dimensional to establish construction main flat face arrangement
Arrangement and method for construction is imported into BIM systems by model and structure three-dimensional model.
In step 2:According to the arrangement and method for construction worked out and《Concrete structure engineering construction quality accident specification》Choosing
Examination node during rounding concrete structure construction, and these nodes are carried out in the threedimensional model having had built up
Setting.Each construction node is inserted into block mold using AutodeskRevit softwares.
In step 3:The equipment such as digital photographing, video camera, panoramic scanning, which can be used, in Quality Inspector at the scene needs scene
The situation of construction node is checked and accepted by taking a picture, imaging the progress physical record in the form of image.It will by AutodeskRevit softwares
Photograph, video are uploaded in established threedimensional model.
In step 4:Quality Inspector's basis at the scene《Concrete structure engineering construction quality accident specification》In specifically will
It asks, each scantling at acquisition construction node, position, model, the key messages such as quantity.It will by AutodeskRevit softwares
Collected information is uploaded in established threedimensional model.
In step 5:Using AutodeskRevit softwares by the information of upload with establishing in the threedimensional model completed
Information is matched.Critical control point and non-key control point are divided into according to node setting in matching process, ensure crucial control
Point highly consistent and non-key control point it is unanimous on the whole.
In step 6:If successful match in step 5, next construction is then entered in AutodeskRevit softwares
Node is checked and accepted, and generates acceptance report simultaneously with document form.If it fails to match, the content according to software unsuccessfully
It is rectified and improved, and information upload is resurveyed after rectification, until by checking and accepting, proceeded to next construction node and check and accept.
The present invention it is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control, further include:For
The examination problem of concealed work can in advance set before concealed work pours and check and accept node, to ensure to test concealed work
It is retracted into reminding effect.Generation for engineering accident can at the first time be cleared the responsibility of the main by the information uploaded in software,
And it calls to account.It separately needs to illustrate, the structure shown in the drawings of this specification, size, ratio etc., is all used for aiding in illustrating specification
Particular content, so that skilled addressee is read, be not the present invention qualifications.Any rational adjustment, is repaiied
Decorations are under the premise of without prejudice to original intention of the present invention, in technical scope of the present invention.Meanwhile this specification is applied
Such as " on ", " under ", "left", "right" term also the non-limiting present invention can practical range, in the premise without essence change technology
Under, also it is regarded as implementation scope of the invention.
Above-described invention example not does formal limitation to the present invention, and those skilled in the art can be to corresponding
Technology contents are modified or are adjusted, as long as without departing from the content of technical solution of the present invention, still fall within technical solution of the present invention
In the range of.
Claims (8)
1. it is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control, which is characterized in that including following
Step:
Step 1:It identifies project arrangement and method for construction, and arrangement and method for construction is imported into BIM systems, establish BIM threedimensional models, and in BIM
The critical construction of concrete structure is set to check and accept node in threedimensional model
Step 2:Live Quality Inspector is acquired critical construction node image information simultaneously using the technologies such as digital camera, panoramic scanning
Upload to BIM threedimensional models
Step 3:Live Quality Inspector acquires the material information of corresponding construction node and uploads to BIM threedimensional models
Step 4:Collected information and the arrangement and method for construction in BIM models are matched, if successful match, carried out next
The construction of step;If it fails to match, it will rectify and improve rapidly, after reaching quality requirement, BIM models could carry out the operation of next step
Step 5:According to《Concrete structure engineering construction quality accident specification》Each construction node identified project, and to each
Node construct according to above-mentioned requirements control
Step 6:After a node examination of constructing passes through, data will be checked and accepted by BIM threedimensional models and exported, and by construction party,
Management side and Party A, which sign, to be confirmed
Further, in step 1, pass through the foundation to threedimensional model and examination node, you can export is checked and accepted required
The key messages such as each scantling, material property, convenient for the matching work of step 4
Further, in step 4, to ensure that concealment part sets up examination node before pouring for concealed work, ensure
Inspection of quality before pouring
Further, by the operational mode of preceding step, once there is construction quality problem, you can it is carried by BIM models
The relevant information of confession clears the responsibility of the main at the first time.
2. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It is described
BIM models can set up the construction node of examination in advance according to arrangement and method for construction.
3. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It will apply
Work quality in site information is combined by recording equipment with BIM models.
4. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It is described
BIM threedimensional models carry out stringent control to construction speed, only by quality matches, could carry out next step construction.
5. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It is described
The combination of BIM models and concrete construction acceptance specification highlights the characteristics of concrete structure quality is checked and accepted.
6. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It is described
It checks and accepts material to export by BIM threedimensional models, a large amount of numerous and diverse meaningless copy can be reduced.
7. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It is described
The BIM of the setting in advance model nodes of concealed work are checked and accepted, reminding effect is played to acceptance of concealed work.
8. the concrete structure construction quality control system according to claim 1 based on BIM, it is characterised in that:It is described
To the stringent control of each link, once there is quality accident, can information be recorded according to model at the first time and divide responsibility.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711480910.4A CN108197802A (en) | 2017-12-29 | 2017-12-29 | It is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711480910.4A CN108197802A (en) | 2017-12-29 | 2017-12-29 | It is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108197802A true CN108197802A (en) | 2018-06-22 |
Family
ID=62586789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711480910.4A Pending CN108197802A (en) | 2017-12-29 | 2017-12-29 | It is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108197802A (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108802677A (en) * | 2018-07-05 | 2018-11-13 | 国网福建省电力有限公司 | Substation project based on RFID checks and accepts Intelligent auxiliary equipment localization method |
CN109779261A (en) * | 2018-12-20 | 2019-05-21 | 上海建工集团股份有限公司 | The method and system of concreting dynamic control based on BIM technology |
CN109784758A (en) * | 2019-01-30 | 2019-05-21 | 北京筑业志远软件开发有限公司 | Construction quality supervision early warning system and method based on BIM model |
CN109886573A (en) * | 2019-02-18 | 2019-06-14 | 重庆工商职业学院 | Building intelligence build guality, safety management system and method |
CN110400075A (en) * | 2019-07-24 | 2019-11-01 | 中煤地建设工程有限公司 | A kind of wisdom building site quality safety management system |
WO2020006984A1 (en) * | 2018-07-04 | 2020-01-09 | 成都希盟泰克科技发展有限公司 | Bim technology-based comprehensive aid decision-making method for engineering construction organization scheme |
CN111080491A (en) * | 2019-12-12 | 2020-04-28 | 成都阳帆网络科技有限公司 | Construction site inspection system and method based on video identification |
CN111521162A (en) * | 2020-04-15 | 2020-08-11 | 广东博智林机器人有限公司 | Method and device for determining station measurement, electronic equipment and storage medium |
CN111861160A (en) * | 2020-07-04 | 2020-10-30 | 广东粤源工程咨询有限公司 | Construction engineering quality information management method and system |
CN112365151A (en) * | 2020-11-09 | 2021-02-12 | 重庆智慧之源科技有限公司 | Intelligent detection system for building concealed engineering |
CN112488879A (en) * | 2020-12-02 | 2021-03-12 | 滨州学院 | Intelligent construction site management system based on BIM model |
CN112733239A (en) * | 2021-01-15 | 2021-04-30 | 广州市新誉工程咨询有限公司 | Building engineering quality monitoring method and system based on BIM model |
WO2021116093A1 (en) * | 2019-12-10 | 2021-06-17 | Peri Gmbh | Computer-assisted method and device for testing the quality of exposed concrete |
CN112990844A (en) * | 2020-12-26 | 2021-06-18 | 上海建科工程咨询有限公司 | Construction method and management system based on BIM |
CN114169058A (en) * | 2021-12-13 | 2022-03-11 | 金螳螂家装电子商务(苏州)有限公司 | Construction node quality inspection management method based on home decoration industry |
CN116090907A (en) * | 2023-03-07 | 2023-05-09 | 中建四局第五建筑工程有限公司 | Building construction quality traceability management method and system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104978696A (en) * | 2015-06-09 | 2015-10-14 | 广州市水电设备安装有限公司 | Electronic acceptance and handover method based on BIM technology |
CN105303308A (en) * | 2015-10-22 | 2016-02-03 | 张玉英 | Management system and method for whole steel bar engineering process based on 3D figure information platform |
CN106055839A (en) * | 2016-06-30 | 2016-10-26 | 上海宝冶集团有限公司 | Application method of three-dimensional scanning technology in building engineering based on BIM |
CN106096851A (en) * | 2016-06-21 | 2016-11-09 | 浙江精工钢结构集团有限公司 | A kind of structural steelwork based on BIM technology visualization acceptance method |
CN107229777A (en) * | 2017-05-12 | 2017-10-03 | 中国建筑局(集团)有限公司 | A kind of acceptance of concealed work method based on mixed reality technology |
-
2017
- 2017-12-29 CN CN201711480910.4A patent/CN108197802A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104978696A (en) * | 2015-06-09 | 2015-10-14 | 广州市水电设备安装有限公司 | Electronic acceptance and handover method based on BIM technology |
CN105303308A (en) * | 2015-10-22 | 2016-02-03 | 张玉英 | Management system and method for whole steel bar engineering process based on 3D figure information platform |
CN106096851A (en) * | 2016-06-21 | 2016-11-09 | 浙江精工钢结构集团有限公司 | A kind of structural steelwork based on BIM technology visualization acceptance method |
CN106055839A (en) * | 2016-06-30 | 2016-10-26 | 上海宝冶集团有限公司 | Application method of three-dimensional scanning technology in building engineering based on BIM |
CN107229777A (en) * | 2017-05-12 | 2017-10-03 | 中国建筑局(集团)有限公司 | A kind of acceptance of concealed work method based on mixed reality technology |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020006984A1 (en) * | 2018-07-04 | 2020-01-09 | 成都希盟泰克科技发展有限公司 | Bim technology-based comprehensive aid decision-making method for engineering construction organization scheme |
CN108802677A (en) * | 2018-07-05 | 2018-11-13 | 国网福建省电力有限公司 | Substation project based on RFID checks and accepts Intelligent auxiliary equipment localization method |
CN109779261A (en) * | 2018-12-20 | 2019-05-21 | 上海建工集团股份有限公司 | The method and system of concreting dynamic control based on BIM technology |
CN109779261B (en) * | 2018-12-20 | 2023-06-23 | 上海建工集团股份有限公司 | BIM technology-based concrete pouring dynamic control method and system |
CN109784758A (en) * | 2019-01-30 | 2019-05-21 | 北京筑业志远软件开发有限公司 | Construction quality supervision early warning system and method based on BIM model |
CN109886573A (en) * | 2019-02-18 | 2019-06-14 | 重庆工商职业学院 | Building intelligence build guality, safety management system and method |
CN110400075A (en) * | 2019-07-24 | 2019-11-01 | 中煤地建设工程有限公司 | A kind of wisdom building site quality safety management system |
WO2021116093A1 (en) * | 2019-12-10 | 2021-06-17 | Peri Gmbh | Computer-assisted method and device for testing the quality of exposed concrete |
CN111080491A (en) * | 2019-12-12 | 2020-04-28 | 成都阳帆网络科技有限公司 | Construction site inspection system and method based on video identification |
CN111521162A (en) * | 2020-04-15 | 2020-08-11 | 广东博智林机器人有限公司 | Method and device for determining station measurement, electronic equipment and storage medium |
CN111861160A (en) * | 2020-07-04 | 2020-10-30 | 广东粤源工程咨询有限公司 | Construction engineering quality information management method and system |
CN112365151A (en) * | 2020-11-09 | 2021-02-12 | 重庆智慧之源科技有限公司 | Intelligent detection system for building concealed engineering |
CN112365151B (en) * | 2020-11-09 | 2024-05-17 | 重庆智慧之源科技有限公司 | Intelligent detection system for building concealed engineering |
CN112488879A (en) * | 2020-12-02 | 2021-03-12 | 滨州学院 | Intelligent construction site management system based on BIM model |
CN112990844A (en) * | 2020-12-26 | 2021-06-18 | 上海建科工程咨询有限公司 | Construction method and management system based on BIM |
CN112733239A (en) * | 2021-01-15 | 2021-04-30 | 广州市新誉工程咨询有限公司 | Building engineering quality monitoring method and system based on BIM model |
CN114169058A (en) * | 2021-12-13 | 2022-03-11 | 金螳螂家装电子商务(苏州)有限公司 | Construction node quality inspection management method based on home decoration industry |
CN116090907A (en) * | 2023-03-07 | 2023-05-09 | 中建四局第五建筑工程有限公司 | Building construction quality traceability management method and system |
CN116090907B (en) * | 2023-03-07 | 2023-06-20 | 中建四局第五建筑工程有限公司 | Building construction quality traceability management method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108197802A (en) | It is a kind of based on BIM technology to the method and system of concrete structure construction quality management and control | |
CN106652049A (en) | Full-professional design delivery method for building based on augmented reality technology of mobile terminal | |
WO2018121333A1 (en) | Real-time generation method for 360-degree vr panoramic graphic image and video | |
CN108665527A (en) | A kind of technical annotation in construction method based on panoramic technique and BIM models | |
CN108388711A (en) | A kind of engineering design based on BIM and management system | |
CN108510406A (en) | Construction based on Building Information Model and panoramic technique is told somebody what one's real intentions are method and system | |
DE112015007134T5 (en) | Method and device for synchronous image display | |
CN104680320A (en) | BIM-based project management system and method | |
CN203352678U (en) | Panoramic image hardware imaging device with six camera heads | |
JP2017167969A (en) | Damage extraction system | |
CN109462736B (en) | Road and bridge engineering construction video conference management method and system based on BIM + GIS modeling | |
CN107451737A (en) | A kind of big data O2O check of drawings cloud platform management systems examined for engineering construction figure | |
CN106201201A (en) | View method of adjustment and system | |
CN105965894A (en) | Automatic control system for 3D printing monitoring based on image processing | |
CN115760021A (en) | GIS-based engineering progress three-dimensional monitoring system | |
CN105551069B (en) | A kind of real-time generation method and system of thumbnail | |
CN101807289B (en) | Modeling method for distributed image processing system | |
CN113474784A (en) | Dynamic two-dimensional code evaluation method, dynamic two-dimensional code evaluation system, and dynamic two-dimensional code evaluation program | |
CN114666133B (en) | Remote inquiry evidence obtaining system and method based on original handwriting signature | |
CN106203967A (en) | Teleconference information exchange method based on BIM and system | |
CN108765574A (en) | 3D scenes intend true method and system and computer readable storage medium | |
CN108769612A (en) | A kind of VR Visualization Platforms | |
CN109191578B (en) | Method, system and device for generating conference bottoms of engineering site and readable storage medium | |
US20170070705A1 (en) | System and method for collating digital content from a plurality of devices into a single media file | |
CN115797584B (en) | Method for constructing live-action model in no-fly zone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180622 |