CN108154244A - The O&M methods, devices and systems of real estate power equipment - Google Patents

The O&M methods, devices and systems of real estate power equipment Download PDF

Info

Publication number
CN108154244A
CN108154244A CN201810072387.XA CN201810072387A CN108154244A CN 108154244 A CN108154244 A CN 108154244A CN 201810072387 A CN201810072387 A CN 201810072387A CN 108154244 A CN108154244 A CN 108154244A
Authority
CN
China
Prior art keywords
power equipment
decision
maintenance
repair
tree model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810072387.XA
Other languages
Chinese (zh)
Inventor
殷晓磊
马如明
杨毅
马锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING TIANSU AUTOMATION CONTROL SYSTEM CO Ltd
Original Assignee
NANJING TIANSU AUTOMATION CONTROL SYSTEM CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING TIANSU AUTOMATION CONTROL SYSTEM CO Ltd filed Critical NANJING TIANSU AUTOMATION CONTROL SYSTEM CO Ltd
Priority to CN201810072387.XA priority Critical patent/CN108154244A/en
Publication of CN108154244A publication Critical patent/CN108154244A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/16Real estate
    • G06Q50/163Real estate management

Landscapes

  • Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of O&M methods, devices and systems of real estate power equipment;Wherein, this method includes:Obtain the fault message sent from electric power equipment management platform;By the decision-tree model pre-established, classify to fault message, obtain the corresponding maintenance program of classification results;Decision-tree model is established by exercising supervision study to history operation/maintenance data;According to maintenance program, corresponding repair work order is generated, so that operation maintenance personnel repairs power equipment according to maintenance program.The present invention can improve the intelligence degree of power equipment O&M, provide accurate maintenance program to operation maintenance personnel, the breakdown maintenance time is reduced, so as to reduce power equipment O&M cost.

Description

The O&M methods, devices and systems of real estate power equipment
Technical field
The present invention relates to equipment O&M technical field, more particularly, to a kind of O&M method, apparatus of real estate power equipment And system.
Background technology
As commercial real estate in the development of one, tier 2 cities serious saturation occurs, reducing O&M cost becomes real estate A kind of mode of operation upgrading transformation.With operation platform on line centralized management can be carried out to the power equipment in real estate, Overall control commercial real estate ammeter situation reduces human input, to achieve the purpose that reduce O&M cost.
In terms of commercial real estate, existing intelligent electric meter management platform has accessed big electrometer, and also has every year very More newly added equipment accesses;Platform daily about thousands of or more ammeter questionnaire generate;Questionnaire is sent to pair by platform The Corporate Asset Management platform answered generates work order;After operation maintenance personnel completes repair, work order is filled in, Corporate Asset Management platform is again By work order storage to database.However, the O&M side that this intelligent electric meter management platform and Corporate Asset Management platform are combined Formula intelligence degree is relatively low, and there are larger limitations, it is difficult to obtain accurate fault message, still need operation maintenance personnel Service experience repair, cause maintenance efficiency relatively low, cost is higher.
Invention content
In view of this, the purpose of the present invention is to provide a kind of O&M methods, devices and systems of real estate power equipment, with The intelligence degree of power equipment O&M is improved, accurate maintenance program is provided to operation maintenance personnel, when reducing breakdown maintenance Between, so as to reduce power equipment O&M cost.
In a first aspect, an embodiment of the present invention provides a kind of O&M method of real estate power equipment, method includes:It obtains and The fault message sent from electric power equipment management platform;By the decision-tree model pre-established, classify to fault message, Obtain the corresponding maintenance program of classification results;Decision-tree model is established by exercising supervision study to history operation/maintenance data;Root According to maintenance program, corresponding repair work order is generated, so that operation maintenance personnel repairs power equipment according to maintenance program.
With reference to first aspect, an embodiment of the present invention provides the first possible embodiment of first aspect, wherein, on Decision-tree model is stated to establish by following manner:Obtain the history operation/maintenance data of power equipment;History operation/maintenance data includes at least Identification information, attribute information, fault message and the repair feedback information of power equipment;By the way of keyword search, to going through History operation/maintenance data carries out classification learning, obtains the decision point of setting quantity and corresponding O&M scheme, generates decision-tree model.
With reference to first aspect, an embodiment of the present invention provides second of possible embodiment of first aspect, wherein, on The method of stating further includes:Receive the repair feedback information that operation maintenance personnel is sent;According to repair feedback information update decision-tree model.
Second of possible embodiment with reference to first aspect, an embodiment of the present invention provides the third of first aspect Possible embodiment, wherein, above-mentioned the step of decision-tree model is updated according to repair feedback information, including:Repair is fed back Information saves as history operation/maintenance data, searches again for the keyword in history operation/maintenance data;It calculates and searches going out for the keyword that element goes out Existing frequency;The frequency of occurrences is met to the keyword of given threshold, as updated decision point.
The third possible embodiment with reference to first aspect, an embodiment of the present invention provides the 4th kind of first aspect Possible embodiment, wherein, the above method further includes:The frequency of occurrences is met to the keyword of given threshold, according to appearance frequency The sequence of rate from high to low is ranked up;According to ranking results, the keyword of quantity will be set as final decision point.
With reference to first aspect, an embodiment of the present invention provides the 5th kind of possible embodiment of first aspect, wherein, on The step of stating according to maintenance program, generating corresponding repair work order, including:Maintenance program is pushed to Corporate Asset Management to put down Platform, so that Corporate Asset Management platform generates corresponding repair work order.
Second aspect, an embodiment of the present invention provides a kind of O&M device of real estate power equipment, device includes:Failure is believed Acquisition module is ceased, for obtaining the fault message sent from electric power equipment management system;Sort module is built in advance for passing through Vertical decision-tree model, classifies to fault message, obtains the corresponding maintenance program of classification results;It is right that decision-tree model passes through History operation/maintenance data, which exercises supervision, to be learnt and establishes;Work order generation module is repaired, for according to maintenance program, generating corresponding dimension Work order is repaiied, so that operation maintenance personnel repairs power equipment according to maintenance program.
With reference to second aspect, an embodiment of the present invention provides the first possible embodiment of second aspect, wherein, on Decision-tree model is stated to establish by following manner:Obtain the history operation/maintenance data of power equipment;History operation/maintenance data includes at least Identification information, attribute information, fault message and the repair feedback information of power equipment;By the way of keyword search, to going through History operation/maintenance data carries out classification learning, obtains the decision point of setting quantity and corresponding O&M scheme, generates decision-tree model.
With reference to second aspect, an embodiment of the present invention provides second of possible embodiment of second aspect, wherein, on Device is stated to further include:Feedback information receiving module, for receiving the repair feedback information of operation maintenance personnel transmission;Model modification mould Block, for according to repair feedback information update decision-tree model.
The third aspect, an embodiment of the present invention provides a kind of operational system of real estate power equipment, system includes public clothes Business device, the first cloud server and the second cloud server;Public servicer is provided with the O&M dress of above-mentioned real estate power equipment It puts;First cloud server is provided with electric power equipment management platform;Second cloud server is provided with Corporate Asset Management platform.
The embodiment of the present invention brings following advantageous effect:
A kind of O&M methods, devices and systems of real estate power equipment provided in an embodiment of the present invention are got from electricity After the fault message that power device management platform is sent, by the decision-tree model pre-established, classify to the fault message, Obtain the corresponding maintenance program of classification results;Further according to the maintenance program, corresponding repair work order is generated, so that operation maintenance personnel root Power equipment is repaired according to maintenance program.Which improves the intelligence degree of power equipment O&M, can be carried to operation maintenance personnel For accurate maintenance program, reduce the breakdown maintenance time, so as to reduce power equipment O&M cost.
Other features and advantages of the present invention will illustrate in the following description, also, partly become from specification It obtains it is clear that being understood by implementing the present invention.The purpose of the present invention and other advantages are in specification, claims And specifically noted structure is realized and is obtained in attached drawing.
For the above objects, features and advantages of the present invention is enable to be clearer and more comprehensible, preferred embodiment cited below particularly, and coordinate Appended attached drawing, is described in detail below.
Description of the drawings
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution of the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, in being described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, can also be obtained according to these attached drawings other attached drawings.
Fig. 1 is a kind of application environment schematic diagram of the O&M method of real estate power equipment provided in an embodiment of the present invention;
Fig. 2 is a kind of flow chart of the O&M method of real estate power equipment provided in an embodiment of the present invention;
Fig. 3 is the flow chart of the O&M method of another real estate power equipment provided in an embodiment of the present invention;
Fig. 4 is the flow chart provided in an embodiment of the present invention classified by decision-tree model to fault message;
When Fig. 5 is update decision-tree model provided in an embodiment of the present invention, the schematic diagram of new decision point is generated;
Fig. 6 is in the O&M method of real estate power equipment provided in an embodiment of the present invention, according to repair feedback information update The step flow chart of decision-tree model;
Fig. 7 is the flow chart of the O&M method of another real estate power equipment provided in an embodiment of the present invention;
Fig. 8 leads to the problem of list schematic diagram for CSMMS platforms provided in an embodiment of the present invention;
Fig. 9 is the flow chart of EAM platform processes work order provided in an embodiment of the present invention;
Figure 10 is work order list schematic diagram in EAM platforms provided in an embodiment of the present invention;
Figure 11 is the specific schematic diagram of work order in EAM platforms provided in an embodiment of the present invention;
Figure 12 is a kind of structure diagram of the O&M device of real estate power equipment provided in an embodiment of the present invention;
Figure 13 is a kind of structure diagram of the operational system of real estate power equipment provided in an embodiment of the present invention.
Specific embodiment
Purpose, technical scheme and advantage to make the embodiment of the present invention are clearer, below in conjunction with attached drawing to the present invention Technical solution be clearly and completely described, it is clear that described embodiment be part of the embodiment of the present invention rather than Whole embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creative work premise Lower all other embodiments obtained, shall fall within the protection scope of the present invention.
For ease of understanding the present embodiment, first to a kind of real estate power equipment disclosed in the embodiment of the present invention The application environment of O&M method describes in detail;Application environment is as shown in Figure 1, electric power equipment management platform is generally accessible The power equipment of multiple real estates, building, for managing these power equipments, and whether monitoring device breaks down;With intelligent electricity For table, which is specifically as follows CSMMS (Commercial Smart Meter Management System, intelligent electric meter management platform) platform;When intelligent electric meter breaks down, platform can generate questionnaire, which can To show the ammeter position broken down and failure Risk factor (for example, ammeter's reading meter failure) etc..
CSMMS platforms will singly be sent to EAM (Enterprise Asset Management, enterprise assets the problem of generation Management platform) platform, EAM platforms generate corresponding work order, and operation maintenance personnel is assigned to repair;Operation maintenance personnel repair finishes Afterwards, specific fault message, maintenance program etc. are filled in work order, is stored the work order to database by EAM platforms.
It can be seen from the above, the O&M mode of existing real estate power equipment is usually mutually tied by CSMMS platforms with EAM platforms It closes and realizes, but this O&M mode intelligence degree is relatively low, there are larger limitation, for example, CSMMS platforms can detect Ammeter breaks down, but the concrete reason of failure is difficult to obtain automatically, and fault cues accuracy is not high, needs operation maintenance personnel to now Field, which is checked, just to be known;For example, the situation of ammeter's reading meter failure, the prompting that system usually provides is ammeter response timeout, needs to examine Device talk situation is looked into, is had responded to however, actual conditions are ammeters, has been stuck in concentrator link, is that concentrator is not received and copied Table information.
In addition, EAM platforms save a large amount of work order data, containing every operation maintenance personnel in these work order data enriches O&M experience, but due to lacking to the recycling processes of these data, these experiences are difficult to induction and conclusion and come out, and cause every time During repair, maintenance program also needs largely to rely on the personal experience of operation maintenance personnel, is unfavorable for the promotion of ammeter equipment O&M efficiency.
For these reasons, an embodiment of the present invention provides a kind of O&M methods, devices and systems of real estate power equipment; The technology can be applied in business, housing real estate, building in the O&M of power equipment;It is particularly applicable to commercial real estate In the management of intelligent electric meter, O&M;Relevant software or hardware realization may be used in the technology, is retouched below by embodiment It states.
A kind of flow chart of the O&M method of real estate power equipment shown in Figure 2;This method comprises the following steps:
Step S202 obtains the fault message sent from electric power equipment management platform;The fault message can be with problem Single form is sent, and typically includes the contents such as location information, identification information and the problem description for the equipment that breaks down.
Step S204 by the decision-tree model pre-established, classifies to fault message, obtains classification results correspondence Maintenance program;The decision-tree model is established by exercising supervision study to history operation/maintenance data;
The maintenance program that the fault message comprising power equipment and operation maintenance personnel are filled in historical failure data;To history Operation/maintenance data exercises supervision during study, the fault message of various power equipments can be classified, and to various types of The fault message of type is corresponded with corresponding maintenance program, so as to generate above-mentioned decision-tree model.When getting new failure During information, which can be input in the decision-tree model, handle, can obtain corresponding by the classification of model Maintenance program.
Step S206 according to maintenance program, generates corresponding repair work order, so that operation maintenance personnel is repaired according to maintenance program Power equipment.The maintenance program can include it is one or more, be shown in the repair work order of generation, for maintenance personal join It examines.
A kind of O&M method of real estate power equipment provided in an embodiment of the present invention, gets and is put down from electric power equipment management After the fault message that platform is sent, by the decision-tree model pre-established, classify to the fault message, obtain classification results Corresponding maintenance program;Further according to the maintenance program, corresponding repair work order is generated, so that operation maintenance personnel is tieed up according to maintenance program Repair power equipment.Which improves the intelligence degree of power equipment O&M, can be provided to operation maintenance personnel accurate Maintenance program reduces the breakdown maintenance time, so as to reduce power equipment O&M cost.
The flow chart of the O&M method of another real estate power equipment shown in Figure 3;This method shown side in fig. 2 It is realized on the basis of method;In this method, the decision-tree model is established by history operation/maintenance data first;This method specifically includes as follows Step:
Step S302 obtains the history operation/maintenance data of power equipment;The history operation/maintenance data includes at least power equipment Identification information, attribute information, fault message and repair feedback information;
By the way of keyword search, classification learning is carried out to history operation/maintenance data, obtains setting quantity by step S304 Decision point and corresponding O&M scheme, generate decision-tree model.
Specifically, in above-mentioned steps S204, ID3 (Iterative may be used in generation decision-tree model Dichotomiser 3,3 generation of iteration binary tree) decision making algorithm realization;In the ID3 decision making algorithms, decision tree is by decision point, branch It is formed with leaf.Uppermost node is root node in decision tree, and each branch is a new decision point.Each decision point generation One decision of table, corresponding to the processing scheme of problem.Each leafy node represents a kind of possible classification results.Along decision tree During traversing from top to bottom, a test, the different tests to problem on each node can be encountered in each node Output leads to different branches, can finally reach a leafy node, this process is exactly the mistake classified using decision tree Journey generates last scheme using several decision points.
As described in Table 1, during the O&M of power equipment, the decision point that may relate to includes at least equipment ID, square ID, brand ID, concentrator ID, on-line time, whether went out problem, wiring etc. before.
Table 1
Step S306 obtains the fault message sent from electric power equipment management platform;
Step S308 by the decision-tree model pre-established, classifies to fault message, obtains classification results correspondence Maintenance program;
The flow chart classified by decision-tree model to fault message shown in Figure 4;Fault message is inputted To decision-tree model, usually first determine whether that belonging to no before the equipment the problem of usual (i.e. same fault message) occurred, such as Fruit is, the problem of before lookup, and obtains corresponding maintenance program;If it is not, then check other equipment with the presence or absence of identical Whether whether problem judge whether it is brand problem, be square problem, be concentrator problem etc. successively, until according to corresponding Problem provides solution (i.e. maintenance program).
Maintenance program is pushed to Corporate Asset Management platform by step S310, so that the generation pair of Corporate Asset Management platform The repair work order answered, operation maintenance personnel repair power equipment according to maintenance program.
Step S312 receives the repair feedback information that operation maintenance personnel is sent;According to repair feedback information update decision tree Model.
In order to ensure the practicability of decision-tree model, the repair feedback information dynamic sent according to operation maintenance personnel is needed more Newly, new decision point is generated in time, so that the maintenance program of decision-tree model output is more accurate.Update shown in Figure 5 During decision-tree model, the schematic diagram of new decision point is generated;Decision point is typically derived from commercial real estate model and a large amount of O&Ms Work order experience;When there is new repair feedback information, system can use keyword search side in the work order filled in Formula after meeting certain number, becomes into new decision point.For example, the problem of ammeter generally existing wiring, operation maintenance personnel is in work In the repair feedback information filled in list if including " wiring " keyword, and volumes of searches is more than 1000 times, then, " wiring " New decision point can then be become.
Specifically, in the O&M method of real estate power equipment shown in Figure 6, according to repair feedback information update decision The flow chart of the step of tree-model, includes the following steps:
Repair feedback information is saved as history operation/maintenance data, searches again for the pass in history operation/maintenance data by step S602 Key word;
Step S604 calculates the frequency of occurrences for searching the keyword that element goes out;The frequency of occurrences is met to the keyword of given threshold, As updated decision point.
The frequency of occurrences is met the keyword of given threshold by step S606, according to the sequence of the frequency of occurrences from high to low into Row sequence;
Step S608 according to ranking results, will set the keyword of quantity as final decision point.That is, if there is The total quantity that frequency meets the keyword of given threshold is more than above-mentioned setting quantity N, according to the sequence of the frequency of occurrences from high to low After being ranked up, interception top n keyword is as final decision point.
Situation is actually used in view of system, the work order quantity generated daily is more, according to dynamic generation decision point Scheme has a large amount of keyword and meets the requirements, and becomes new decision point, can influence the efficiency of decision making algorithm in this way;If it is System could support up 20 decision points, if the keyword that the above-mentioned frequency of occurrences meets given threshold is less than or equal to 20, Each decision point can use;If greater than 20, then can only be taken using the number that each decision point occurs as basis for estimation Preceding 20 uses.
The flow chart of the O&M method of another real estate power equipment shown in Figure 7;This method specifically includes as follows Step:
Step (1), CSMMS platforms generate questionnaire, and provide problem clew information (being equivalent to above-mentioned fault message), and It is sent to EAM platforms;It is illustrated in figure 8 CSMMS platforms and leads to the problem of list schematic diagram.
Step (2), EAM platforms generate work order after receiving questionnaire, are illustrated in figure 9 the flow of EAM platform processes work orders Figure;It after operation maintenance personnel receives work order, that is, rushes towards device context and starts to repair, after the completion of repair, it is anti-that operation maintenance personnel fills in repair Feedforward information is preserved by EAM platforms.If Figure 10 is work order list schematic diagram in EAM platforms, Figure 11 is work order in EAM platforms Specific schematic diagram.
Step (3), above-mentioned decision-tree model export maintenance program, which are filled in into work order;Meanwhile the dimension The scheme of repairing can also be pushed to CSMMS platforms, and user can check in CSMMS platforms.
Aforesaid way can provide the higher troubleshooting scheme of accuracy, reduce questionnaire processing time, so as to subtract Few O&M input, achievees the purpose that reduce O&M cost.
Corresponding to above method embodiment, a kind of structure of the O&M device of real estate power equipment shown in Figure 12 is shown It is intended to;The device includes:
Fault message acquisition module 120, for obtaining the fault message sent from electric power equipment management system;
Sort module 121 for passing through the decision-tree model pre-established, classifies to fault message, is classified As a result corresponding maintenance program;Decision-tree model is established by exercising supervision study to history operation/maintenance data;
Work order generation module 122 is repaired, for according to maintenance program, corresponding repair work order being generated, so that operation maintenance personnel Power equipment is repaired according to maintenance program.
Above-mentioned decision-tree model is established by following manner:Obtain the history operation/maintenance data of power equipment;History O&M number According to including at least the identification information of power equipment, attribute information, fault message and repair feedback information;Using keyword search Mode carries out classification learning to history operation/maintenance data, obtains the decision point of setting quantity and corresponding O&M scheme, generates decision Tree-model.
Above device further includes:Feedback information receiving module, for receiving the repair feedback information of operation maintenance personnel transmission;Mould Type update module, for according to repair feedback information update decision-tree model.
A kind of O&M device of real estate power equipment provided in an embodiment of the present invention, gets and is put down from electric power equipment management After the fault message that platform is sent, by the decision-tree model pre-established, classify to the fault message, obtain classification results Corresponding maintenance program;Further according to the maintenance program, corresponding repair work order is generated, so that operation maintenance personnel is tieed up according to maintenance program Repair power equipment.Which improves the intelligence degree of power equipment O&M, can be provided to operation maintenance personnel accurate Maintenance program reduces the breakdown maintenance time, so as to reduce power equipment O&M cost.
A kind of structure diagram of the operational system of real estate power equipment shown in Figure 13;The system includes public clothes Business device 130, the first cloud server 131 and the second cloud server 132;
Public servicer 130 is provided with the O&M device of above-mentioned real estate power equipment;First cloud server 131 is provided with Electric power equipment management platform;Second cloud server 132 is provided with Corporate Asset Management platform.
The operational system of real estate power equipment provided in an embodiment of the present invention, the real estate electric power provided with above-described embodiment are set Standby O&M method and apparatus have identical technical characteristic, so can also solve the technical issues of identical, reach identical skill Art effect.
The O&M methods, devices and systems of real estate power equipment provided in an embodiment of the present invention, providing to plant can incite somebody to action greatly Amount work order data O&M scheme is obtained by decision making algorithm, can apply to commercial real estate carry out processing maintenance, prevention Platform.Specifically, by sorting out to work order, decision-tree model is established, is existed using ID3 decision making algorithms to work order data According to prediction of the condition judgment of decision point for result in decision-tree model, the higher solution of accuracy is proposed.
The computer program production of the O&M methods, devices and systems for the real estate power equipment that the embodiment of the present invention is provided Product, the computer readable storage medium including storing program code, the instruction that said program code includes can be used for before performing Method described in the embodiment of the method for face, specific implementation can be found in embodiment of the method, and details are not described herein.
If the function is realized in the form of SFU software functional unit and is independent product sale or in use, can be with It is stored in a computer read/write memory medium.Based on such understanding, technical scheme of the present invention is substantially in other words The part contribute to the prior art or the part of the technical solution can be embodied in the form of software product, the meter Calculation machine software product is stored in a storage medium, is used including some instructions so that a computer equipment (can be People's computer, server or network equipment etc.) perform all or part of the steps of the method according to each embodiment of the present invention. And aforementioned storage medium includes:USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited The various media that can store program code such as reservoir (RAM, Random Access Memory), magnetic disc or CD.
Finally it should be noted that:Embodiment described above, only specific embodiment of the invention, to illustrate the present invention Technical solution, rather than its limitations, protection scope of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair It is bright to be described in detail, it will be understood by those of ordinary skill in the art that:Any one skilled in the art In the technical scope disclosed by the present invention, it can still modify to the technical solution recorded in previous embodiment or can be light It is readily conceivable that variation or equivalent replacement is carried out to which part technical characteristic;And these modifications, variation or replacement, do not make The essence of corresponding technical solution is detached from the spirit and scope of technical solution of the embodiment of the present invention, should all cover the protection in the present invention Within the scope of.Therefore, protection scope of the present invention described should be subject to the protection scope in claims.

Claims (10)

  1. A kind of 1. O&M method of real estate power equipment, which is characterized in that the method includes:
    Obtain the fault message sent from electric power equipment management platform;
    By the decision-tree model pre-established, classify to the fault message, obtain the corresponding repair side of classification results Case;The decision-tree model is established by exercising supervision study to history operation/maintenance data;
    According to the maintenance program, corresponding repair work order is generated, so that operation maintenance personnel is according to repairing the maintenance program Power equipment.
  2. 2. according to the method described in claim 1, it is characterized in that, the decision-tree model is established by following manner:
    Obtain the history operation/maintenance data of power equipment;The mark that the history operation/maintenance data includes at least the power equipment is believed Breath, attribute information, fault message and repair feedback information;
    By the way of keyword search, classification learning is carried out to the history operation/maintenance data, obtains the decision point of setting quantity With corresponding O&M scheme, decision-tree model is generated.
  3. 3. according to the method described in claim 1, it is characterized in that, the method further includes:
    Receive the repair feedback information that the operation maintenance personnel is sent;The decision tree mould is updated according to the repair feedback information Type.
  4. 4. according to the method described in claim 3, it is characterized in that, described update the decision according to the repair feedback information The step of tree-model, including:
    The repair feedback information is saved as into history operation/maintenance data, searches again for the keyword in the history operation/maintenance data;
    Calculate the frequency of occurrences for searching the keyword that element goes out;The frequency of occurrences is met to the keyword of given threshold, as update Decision point afterwards.
  5. 5. according to the method described in claim 4, it is characterized in that, the method further includes:
    The frequency of occurrences is met to the keyword of given threshold, is arranged according to the sequence of the frequency of occurrences from high to low Sequence;
    According to ranking results, the keyword of quantity will be set as final decision point.
  6. 6. according to the method described in claim 1, it is characterized in that, described according to the maintenance program, corresponding repair is generated The step of work order, including:
    The maintenance program is pushed into Corporate Asset Management platform, so that the Corporate Asset Management platform generates corresponding dimension Repair work order.
  7. 7. a kind of O&M device of real estate power equipment, which is characterized in that described device includes:
    Fault message acquisition module, for obtaining the fault message sent from electric power equipment management system;
    Sort module for passing through the decision-tree model pre-established, classifies to the fault message, obtains classification results Corresponding maintenance program;The decision-tree model is established by exercising supervision study to history operation/maintenance data;
    Repair work order generation module, for according to the maintenance program, generating corresponding repair work order so that operation maintenance personnel according to The maintenance program repairs the power equipment.
  8. 8. device according to claim 7, which is characterized in that the decision-tree model is established by following manner:
    Obtain the history operation/maintenance data of power equipment;The mark that the history operation/maintenance data includes at least the power equipment is believed Breath, attribute information, fault message and repair feedback information;
    By the way of keyword search, classification learning is carried out to the history operation/maintenance data, obtains the decision point of setting quantity With corresponding O&M scheme, decision-tree model is generated.
  9. 9. device according to claim 7, which is characterized in that described device further includes:
    Feedback information receiving module, for receiving the repair feedback information that the operation maintenance personnel is sent;
    Model modification module, for updating the decision-tree model according to the repair feedback information.
  10. 10. a kind of operational system of real estate power equipment, which is characterized in that the system comprises public servicer, the first high in the clouds Server and the second cloud server;
    The public servicer is provided with the O&M device of claim 7-9 any one of them real estate power equipments;Described One cloud server is provided with electric power equipment management platform;Second cloud server is provided with Corporate Asset Management platform.
CN201810072387.XA 2018-01-24 2018-01-24 The O&M methods, devices and systems of real estate power equipment Pending CN108154244A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810072387.XA CN108154244A (en) 2018-01-24 2018-01-24 The O&M methods, devices and systems of real estate power equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810072387.XA CN108154244A (en) 2018-01-24 2018-01-24 The O&M methods, devices and systems of real estate power equipment

Publications (1)

Publication Number Publication Date
CN108154244A true CN108154244A (en) 2018-06-12

Family

ID=62459121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810072387.XA Pending CN108154244A (en) 2018-01-24 2018-01-24 The O&M methods, devices and systems of real estate power equipment

Country Status (1)

Country Link
CN (1) CN108154244A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109447287A (en) * 2018-11-02 2019-03-08 国网河北省电力有限公司雄安新区供电公司 Multiple-energy-source operational system method for building up and terminal device
CN109617229A (en) * 2018-11-29 2019-04-12 国网安徽省电力有限公司检修分公司 A kind of smart substation equipment void loop state appraisal procedure and assessment system
CN109767081A (en) * 2018-12-25 2019-05-17 云南电网有限责任公司信息中心 Electric power work order table generating method and device
CN111242328A (en) * 2020-02-27 2020-06-05 贵州智诚科技有限公司 Method for improving operation and maintenance quality and efficiency of equipment
CN111340256A (en) * 2020-03-06 2020-06-26 广东美的制冷设备有限公司 Household appliance fault maintenance method, household appliance fault maintenance terminal and storage medium
CN111445073A (en) * 2020-03-26 2020-07-24 珠海格力电器股份有限公司 Equipment operation and maintenance management method and device, storage medium and terminal
CN111882081A (en) * 2020-07-08 2020-11-03 上海嘉实(集团)有限公司 BIM model-based operation and maintenance management method, medium, terminal and system
CN111898776A (en) * 2020-08-03 2020-11-06 贵州电网有限责任公司 Transformer substation equipment abnormity and accident handling method
CN112328875A (en) * 2020-10-30 2021-02-05 北京精密机电控制设备研究所 Intelligent equipment maintenance scheme recommendation method based on big data
CN112348707A (en) * 2020-10-24 2021-02-09 广东冠雄建设集团有限公司 Holographic intelligent building energy-saving operation and maintenance management system based on BIM model
CN112666879A (en) * 2020-12-18 2021-04-16 山东盛帆蓝海电气有限公司 Metering device fault positioning and diagnosing system and method based on building management robot
CN112686568A (en) * 2021-01-11 2021-04-20 南方电网数字电网研究院有限公司 Operation and maintenance strategy generation processing method, device, system, equipment and storage medium
CN113343651A (en) * 2021-05-06 2021-09-03 广东核电合营有限公司 Nuclear power station notice generation method and device, computer equipment and storage medium
CN114091700A (en) * 2021-11-22 2022-02-25 珠海优特电力科技股份有限公司 Operation and maintenance method and device for power equipment, operation and maintenance management equipment and operation and maintenance robot
CN117278383A (en) * 2023-11-21 2023-12-22 航天科工广信智能技术有限公司 Internet of things fault investigation scheme generation system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102195813A (en) * 2011-05-04 2011-09-21 成都勤智数码科技有限公司 Method and device for intelligently creating operation and maintenance worksheet
CN103714348A (en) * 2014-01-09 2014-04-09 北京泰乐德信息技术有限公司 Rail transit fault diagnosis method and system based on decision-making tree
CN106054857A (en) * 2016-05-27 2016-10-26 大连楼兰科技股份有限公司 Maintenance decision tree/word vector-based fault remote diagnosis platform
CN106790538A (en) * 2016-12-22 2017-05-31 逯帅 Power system is set up and fault solution method for pushing with O&M fault database
CN107589735A (en) * 2017-08-31 2018-01-16 远景能源(江苏)有限公司 Photovoltaic O&M robot system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102195813A (en) * 2011-05-04 2011-09-21 成都勤智数码科技有限公司 Method and device for intelligently creating operation and maintenance worksheet
CN103714348A (en) * 2014-01-09 2014-04-09 北京泰乐德信息技术有限公司 Rail transit fault diagnosis method and system based on decision-making tree
CN106054857A (en) * 2016-05-27 2016-10-26 大连楼兰科技股份有限公司 Maintenance decision tree/word vector-based fault remote diagnosis platform
CN106790538A (en) * 2016-12-22 2017-05-31 逯帅 Power system is set up and fault solution method for pushing with O&M fault database
CN107589735A (en) * 2017-08-31 2018-01-16 远景能源(江苏)有限公司 Photovoltaic O&M robot system

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109447287A (en) * 2018-11-02 2019-03-08 国网河北省电力有限公司雄安新区供电公司 Multiple-energy-source operational system method for building up and terminal device
CN109617229A (en) * 2018-11-29 2019-04-12 国网安徽省电力有限公司检修分公司 A kind of smart substation equipment void loop state appraisal procedure and assessment system
CN109767081A (en) * 2018-12-25 2019-05-17 云南电网有限责任公司信息中心 Electric power work order table generating method and device
CN109767081B (en) * 2018-12-25 2023-08-25 云南电网有限责任公司信息中心 Method and device for generating power worksheet
CN111242328A (en) * 2020-02-27 2020-06-05 贵州智诚科技有限公司 Method for improving operation and maintenance quality and efficiency of equipment
CN111340256A (en) * 2020-03-06 2020-06-26 广东美的制冷设备有限公司 Household appliance fault maintenance method, household appliance fault maintenance terminal and storage medium
CN111445073B (en) * 2020-03-26 2022-05-17 珠海格力电器股份有限公司 Equipment operation and maintenance management method and device, storage medium and terminal
CN111445073A (en) * 2020-03-26 2020-07-24 珠海格力电器股份有限公司 Equipment operation and maintenance management method and device, storage medium and terminal
CN111882081A (en) * 2020-07-08 2020-11-03 上海嘉实(集团)有限公司 BIM model-based operation and maintenance management method, medium, terminal and system
CN111898776A (en) * 2020-08-03 2020-11-06 贵州电网有限责任公司 Transformer substation equipment abnormity and accident handling method
CN112348707A (en) * 2020-10-24 2021-02-09 广东冠雄建设集团有限公司 Holographic intelligent building energy-saving operation and maintenance management system based on BIM model
CN112348707B (en) * 2020-10-24 2024-04-05 广东冠雄建设集团有限公司 BIM model-based holographic intelligent building energy-saving operation and maintenance management system
CN112328875A (en) * 2020-10-30 2021-02-05 北京精密机电控制设备研究所 Intelligent equipment maintenance scheme recommendation method based on big data
CN112666879A (en) * 2020-12-18 2021-04-16 山东盛帆蓝海电气有限公司 Metering device fault positioning and diagnosing system and method based on building management robot
CN112686568A (en) * 2021-01-11 2021-04-20 南方电网数字电网研究院有限公司 Operation and maintenance strategy generation processing method, device, system, equipment and storage medium
CN113343651A (en) * 2021-05-06 2021-09-03 广东核电合营有限公司 Nuclear power station notice generation method and device, computer equipment and storage medium
CN114091700A (en) * 2021-11-22 2022-02-25 珠海优特电力科技股份有限公司 Operation and maintenance method and device for power equipment, operation and maintenance management equipment and operation and maintenance robot
CN117278383A (en) * 2023-11-21 2023-12-22 航天科工广信智能技术有限公司 Internet of things fault investigation scheme generation system and method
CN117278383B (en) * 2023-11-21 2024-02-20 航天科工广信智能技术有限公司 Internet of things fault investigation scheme generation system and method

Similar Documents

Publication Publication Date Title
CN108154244A (en) The O&M methods, devices and systems of real estate power equipment
CN106570778B (en) A kind of method that data integration based on big data is calculated with line loss analyzing
CN102509178B (en) Distribution network device status evaluating system
Jabbarzadeh et al. Designing a Supply Chain Network under the Risk of Disruptions.
CN110493025B (en) Fault root cause diagnosis method and device based on multilayer digraphs
CN108197131A (en) A kind of construction method and device of electric power asset portrait
CN112217207B (en) Transient voltage stability margin prediction method and device
CN105894177A (en) Decision-making-tree-algorithm-based analysis and evaluation method for operation risk of power equipment
CN113343593B (en) Home decoration wiring planning management method, system and storage medium based on neural network
CN109905885A (en) A kind of method and inspection device of determining inspection station list
López et al. New online load forecasting system for the Spanish Transport System Operator
CN116681187B (en) Enterprise carbon quota prediction method based on enterprise operation data
CN107357730A (en) A kind of system fault diagnosis restorative procedure and device
CN106447209A (en) Determination method and device for evaluation factor of power distribution network project
CN105471647A (en) Power communication network fault positioning method
CN113095524A (en) Intelligent generation method, system and storage medium for maintenance work document of power equipment
CN115860694A (en) Business expansion process management and control method and system based on instant message technology
CN111709597B (en) Power grid production domain operation monitoring system
CN117319452A (en) Safety inspection method and system applied to barium sulfate preparation
CN112000708A (en) Abnormal data processing method and system based on regulation and control adapted data fusion
CN107590747A (en) Power grid asset turnover rate computational methods based on the analysis of comprehensive energy big data
CN116562596A (en) Retired battery processing method and device, retired battery storage vertical warehouse and medium
CN114912854B (en) Subway train operation adjusting method and device, electronic equipment and storage medium
CN116739408A (en) Power grid dispatching safety monitoring method and system based on data tag and electronic equipment
CN115983714A (en) Static security assessment method and system for edge graph neural network power system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180612

RJ01 Rejection of invention patent application after publication