CN107517468A - Wireless base station expansion method, dilatation control signal sending method, apparatus and system - Google Patents

Wireless base station expansion method, dilatation control signal sending method, apparatus and system Download PDF

Info

Publication number
CN107517468A
CN107517468A CN201610423681.1A CN201610423681A CN107517468A CN 107517468 A CN107517468 A CN 107517468A CN 201610423681 A CN201610423681 A CN 201610423681A CN 107517468 A CN107517468 A CN 107517468A
Authority
CN
China
Prior art keywords
veneer
master control
stand
dilatation
base station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610423681.1A
Other languages
Chinese (zh)
Inventor
相龙锋
马广宇
廖俊锋
付庆
段晶晶
钟小武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZTE Corp
Original Assignee
ZTE Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZTE Corp filed Critical ZTE Corp
Priority to CN201610423681.1A priority Critical patent/CN107517468A/en
Publication of CN107517468A publication Critical patent/CN107517468A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W24/00Supervisory, monitoring or testing arrangements
    • H04W24/02Arrangements for optimising operational condition
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D30/00Reducing energy consumption in communication networks
    • Y02D30/70Reducing energy consumption in communication networks in wireless communication networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The present invention relates to communication technical field, more particularly to a kind of wireless base station expansion method, dilatation control signal sending method, apparatus and system.The wireless base station expansion method includes:The master control veneer of normal operation obtains the dilatation configuration data that webmaster side is sent on base station, and is powered according to the dilatation configuration data controlig power board to stand-by resource veneer;Stand-by resource veneer after power supply obtains newest version and data, load operating to the master control veneer of the normal operation.Above-mentioned technical proposal is powered off stand-by and subsequently enabled by the master control veneer of normal operation to the master control veneer or/and base band veneer of ready mode, realize the long-range dilatation in wireless base station, reduce the lower station number in existing base station dilation process, so as to reduce the dilatation cost of wireless base station and improve dilatation efficiency.

Description

Wireless base station expansion method, dilatation control signal sending method, apparatus and system
Technical field
The invention belongs to communication technical field, and particularly a kind of wireless base station expansion method, dilatation control signal are sent out Delivery method, apparatus and system.
Background technology
With the Large scale construction of LTE (Long Term Evolution, Long Term Evolution) network, 2G (gener Ation), 3G, 4G network Long Coexistence, single base station will need progressively to support with the change of user situation over a period to come More wireless standards and more Large Copacity.
It is usually at present to be stood under arrangement personnel in the new wireless standard of original opening base station or dilatation, the method for use, Then it is new to insert veneer and then open new standard on newly plug in veneer or enter as needed in the slot of station spare Row dilatation.This method is got up relatively easily for some site operations in city, but for positioned at from far-off regions, even high Base station on mountain, island, the cost for operation of arriving at a station is very high, and the cost such as manpower, traffic to a secondary has been even more than base station In new insertion veneer cost.
Therefore the cost consideration with dilatation is opened based on wireless base station, it is desirable to reduce lower station number, reduce dilatation (original Another new standard is opened in the wireless standard of base station, can also as a kind of dilatation behavior of original base station, below for This operation common name " dilatation ") maintenance cost.
The content of the invention
The invention reside in a kind of wireless base station expansion method, dilatation control signal sending method, apparatus and system is provided, use In reducing the lower station number in existing base station dilation process, the dilatation cost and lifting dilatation efficiency of wireless base station are reduced.
According to an aspect of the invention, there is provided a kind of wireless base station expansion method, including,
The master control veneer of normal operation obtains the dilatation configuration data that webmaster side is sent on base station, and is matched somebody with somebody according to the dilatation Data controlig power board is put to be powered to stand-by resource veneer;
Stand-by resource veneer after power supply obtains newest version and data, loading to the master control veneer of the normal operation Operation.
Further, before the master control veneer of normal operation obtains the dilatation configuration data that webmaster side is sent on base station, Including:
The master control veneer of normal operation reads the configuration data of master control veneer after upper electricity, and controls power supply according to configuration data Plate is powered off stand-by stand-by resource veneer is configured to.
Further, the stand-by resource veneer is master control veneer or/and base band veneer.
Further, it is configured to described before stand-by stand-by master control veneer powered off, including:
When being opened for the first time in base station, by webmaster side configuration data by opening instrument first master control veneer on base station Burning configuration data is configured as enabling mode in flash;
By webmaster side configuration data by opening instrument burning configuration data in the flash of the second master control veneer on base station It is configured as ready mode;
Power panel is powered to first master control veneer and second master control veneer on base station;
Two pieces of master control veneers after the power supply start simultaneously at loading running software, configuration feelings of the software in flash Condition, first master control veneer is controlled to provide clock using the master control veneer as normal operation.
Further, configuration data of the first master control veneer reading and saving in flash, if it find that described first When master control veneer and second master control veneer are each configured to the abnormal data for ready mode, without power operation.
Further, it is configured to described before stand-by stand-by base band veneer powered off, including:
Base station when opening for the first time, by webmaster side configuration data by opening the master control of instrument normal operation on base station Burning configuration data in the flash of veneer, the base band veneer not enabled temporarily is configured to ready mode.
According to another aspect of the present invention, a kind of wireless base station dilatation control signal sending method is additionally provided, including:
Stand-by resource veneer configuration data is revised as enabling mode by webmaster lateral root according to dilatation demand, and the dilatation is configured Data syn-chronization is on the master control veneer of base station normal operation.
According to a further aspect of the invention, a kind of wireless base station flash chamber is additionally provided, including:It is arranged at base band frame The master control veneer of middle normal operation, stand-by resource veneer, power panel;
The master control veneer of the normal operation is used for the dilatation configuration data for obtaining the transmission of webmaster side, and according to the dilatation Configuration data controls the power panel to be powered to the stand-by resource veneer;
Stand-by resource veneer after power supply is used to obtain newest version and data to the master control veneer of the normal operation, Load operating.
Further, the master control veneer of normal operation includes:Signal receiving module, power control module;
The signal receiving module is used for the dilatation configuration data for obtaining the transmission of webmaster side;
The power control module is used to control the power panel to give the stand-by resource according to the dilatation configuration data Veneer is powered, and is additionally operable to read the configuration data of master control veneer, and will be configured to treat according to configuration data controlig power board Stand-by resource veneer is powered off.
According to a further aspect of the invention, a kind of wireless base station dilatation control signal dispensing device is additionally provided, is set Configuration module, control signal sending module in webmaster side;
The configuration module is used to stand-by resource veneer configuration data is revised as into enabling mode according to dilatation demand;
The control signal sending module is used for the master control veneer that the dilatation configuration data is synchronized to normal operation.
According to a further aspect of the invention, a kind of wireless base station capacity-enlarging system is additionally provided, including:
It is arranged at configuration module, the control signal sending module of webmaster side;
It is arranged at the master control veneer of normal operation in base band frame, stand-by resource veneer, power panel;
The configuration module is used to stand-by resource veneer configuration data is revised as into enabling mode according to dilatation demand;
The control signal sending module is used for the master control veneer that the dilatation configuration data is synchronized to normal operation;
The master control veneer of the normal operation is used for the dilatation configuration data for obtaining the transmission of webmaster side, and according to the dilatation Configuration data controls the power panel to be powered to the stand-by resource veneer;
Stand-by resource veneer after power supply is used to obtain newest version and data to the master control veneer of the normal operation, Load operating.
Above-mentioned technical proposal is powered off stand-by by the master control veneer of normal operation to stand-by master control veneer or/and base band veneer And follow-up dilatation enables, and realizes the long-range dilatation in wireless base station.Reduce the lower station number in existing base station dilation process, so as to drop The low dilatation cost of wireless base station and improve dilatation efficiency.
Brief description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, forms the part of the present invention, this hair Bright schematic description and description is used to explain the present invention, does not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is stand-by in base station baseband frame provided by the invention and enables veneer distributed architecture schematic diagram;
Fig. 2 is a kind of wireless base station expansion method flow chart that the embodiment of the present invention one provides;
Fig. 3 is a kind of wireless base station expansion method flow chart that the embodiment of the present invention two provides;
Fig. 4 is the method flow diagram handled when base station provided by the invention is opened first master control veneer;
Fig. 5 is that the first master control veneer provided by the invention using normal operation controls the second stand-by master control veneer and treated Base band veneer powers off stand-by and upper electricity and enables method flow schematic diagram;
Fig. 6 is a kind of wireless base station flash chamber structural representation provided in an embodiment of the present invention;
Fig. 7 is a kind of wireless base station dilatation control signal dispensing device structural representation provided in an embodiment of the present invention;
Fig. 8 is a kind of wireless base station capacity-enlarging system structural representation that the embodiment of the present invention three provides.
Embodiment
In order that technical problems, technical solutions and advantages to be solved are clearer, clear, tie below Drawings and examples are closed, the present invention will be described in further detail.It should be appreciated that specific embodiment described herein is only To explain the present invention, it is not intended to limit the present invention.
At present, for the ease of the new wireless standard of opening base station and expansion capacity, some slots are reserved in base band frame. When the new wireless standard of original opening base station or dilatation, usually stood under arrangement personnel, then as needed in station spare Slot in, it is new to insert veneer and then new standard is opened on newly plug in veneer or carries out dilatation.
It is stand-by and to enable veneer distribution as shown in Figure 1 in the base band frame of base station.Including being inserted in power panel, base band frame slot Master control veneer, stand-by master control veneer, the base band veneer enabled, stand-by base band veneer and the fan knot for radiating enabled Structure.
In order to reduce the lower station number in existing base station dilation process, dilatation cost and the lifting dilatation of wireless base station are reduced Efficiency.The invention provides a kind of wireless base station expansion method.
As shown in Fig. 2 be a kind of embodiment one of wireless base station expansion method provided by the invention, including:
S1, the master control veneer of normal operation obtain the dilatation configuration data that webmaster side is sent, and are configured according to the dilatation Data controlig power board is powered to stand-by resource veneer;
Stand-by resource veneer after S2, power supply obtains newest version and data to the master control veneer of the normal operation, Load operating.
Before to wireless base station dilatation, when base station is opened first, as needed, by not having to temporarily in base band frame, groove position is pre- Some resource veneers are plugged, these resource veneers generally comprise master control veneer, base band veneer and master control borad and base band veneer Combination, but these veneers are configured to ready mode, the master control list of normal operation by webmaster side configuration data by opening instrument Plate is configured to stand-by veneer to these according to the configuration data controlig power board of webmaster side and carries out power operation, it is ensured that these are standby The normal operation for enabling veneer and consumption electric energy is not interfered with before dilatation enables with veneer resource.
Specifically, as the embodiment of the present invention two, as shown in figure 3, the master control veneer of normal operation obtains net on base station Before the dilatation configuration data that pipe side is sent, in addition to:
The master control veneer of normal operation reads the configuration data of master control veneer after S11, upper electricity, and is controlled according to configuration data Power panel is powered off stand-by stand-by resource veneer is configured to.
The other steps of this method are identical with embodiment one, are not repeated.In this method, the master control veneer of normal operation according to The configuration data of itself or the configuration data of stand-by master control veneer are configured to described stand-by stand-by resource veneer and powered off, When stand-by resource veneer is base band veneer, the master control veneer of normal operation is according to the configuration data of itself by the stand-by base band Veneer is powered off;When stand-by resource veneer is master control veneer, the master control veneer of normal operation is according to stand-by master control veneer Configuration data is powered off the stand-by master control veneer;Ensure that these standby board resources do not interfere with before dilatation enables The normal operation for enabling veneer and consumption electric energy.
The configuration data derives from webmaster side, but when opening first, webmaster side does not set up wireless connection, net also with base station Pipe side is carried to the configuration data of base station by opening instrument (for example, USB flash disk), master control veneer to normal operation in base band and is treated Master control veneer carries out data write-in.
When being built a station in wireless base station, by stand-by resource veneer insertion base band frame slot, stand-by resource veneer, it is divided into Two kinds:Master control veneer or/and base band veneer, it will describe to handle strategy, stand-by base band for stand-by master control veneer below respectively The processing strategy of veneer, and processing strategy when stand-by master control veneer and stand-by base band veneer insert simultaneously.
As shown in figure 4, the method that the master control veneer and stand-by master control veneer to normal operation are handled is as follows, will It is described to be configured to before stand-by master control veneer powered off, including:
S41, base station for the first time open when, by webmaster side configuration data by opening instrument in the first master control veneer Burning configuration data is configured as enabling mode in flash;
S42, webmaster side configuration data matched somebody with somebody by opening instrument burning configuration data in the flash of the second master control veneer It is set to as ready mode;
S43, power panel are powered to first master control veneer and second master control veneer;
Two pieces of master control veneers after S44, the power supply start simultaneously at loading running software, software matching somebody with somebody in flash Situation is put, controls first master control veneer to provide clock using the master control veneer as normal operation.
It is above-mentioned for base station for the first time open when, what master control veneer and stand-by master control veneer to normal operation were handled Method, to realize that the determination of the master control veneer of normal operation and the data of normal operation master control veneer and stand-by master control veneer are matched somebody with somebody Put.The master control veneer of subsequent normal operation can power off according to configuration to stand-by master control veneer.
During above-mentioned configuration data burning, it is possible to make a mistake, in order to ensure also will not in burning data exception There is the situation at station.Then during configuration data of the first master control veneer reading and saving in flash, if it find that described When one master control veneer and second master control veneer are each configured to the abnormal data for ready mode, without power operation.
The processing mode of the stand-by base band veneer base band veneer different, stand-by with the processing mode of stand-by master control veneer Configuration data pass through to configure the master control veneer of normal operation and realize.It is specific as follows:
When being opened for the first time in base station, by webmaster side configuration data by opening instrument in the flash of master control veneer Burning configuration data, the base band veneer not enabled temporarily is configured to ready mode.
Above-mentioned technical proposal powers off stand-by and follow-up expansion to stand-by mode resource veneer by the master control veneer of normal operation Appearance enables, and realizes the long-range dilatation in wireless base station.Reduce the lower station number in existing base station dilation process, it is wireless so as to reduce The dilatation cost of base station and improve dilatation efficiency.
Present invention also offers a kind of wireless base station dilatation control signal sending method, including:
Stand-by resource veneer configuration data is revised as enabling mode by webmaster lateral root according to dilatation demand, and the dilatation is configured Data syn-chronization is on the master control veneer of base station normal operation.
The above method realizes the generation and transmission of webmaster side dilatation signal, is easy to base station side to realize long-range dilatation.
In addition, webmaster side can also be as needed, the configuration data of the resource veneer after reactivating is revised as stand-by Pattern, the master control veneer of normal operation can also enter resource veneer again according to the amended configuration data controlig power board Row power-off, to realize the remote control to these resource veneers.Such case occurs less, is only moved back gradually in a kind of standard Go out, when the base station covering area is fewer and fewer using the mobile terminal of the standard, in order to avoid unnecessary resource veneer wastes electricity Source, the master control veneer of remote controlled normal operation are powered off to save power supply to these resource veneers.
For the ease of understanding that the master control veneer of normal operation controls stand-by master control veneer and the power-off of stand-by base band veneer The procedure that stand-by and upper electricity enables.As the embodiment of the present invention, as shown in figure 5, the first master control veneer for normal operation The second stand-by master control veneer and stand-by base band veneer is controlled to power off stand-by and upper electricity and enable schematic flow sheet.
The master control veneer of normal operation controls stand-by master control veneer to be dormant to the whole workflow that upper electricity enables from power-off Journey is as follows:
(1), webmaster side configuration data is matched somebody with somebody by opening instrument burning configuration data in the flash of the first master control veneer It is set to as enabling mode;Webmaster side configuration data is configured into number by opening instrument burning in the flash of the second master control veneer According to ready mode is configured as, such as the T1 steps in Fig. 5;
(2), power panel is powered to first master control veneer and second master control veneer, such as the T2 steps in Fig. 5 Suddenly;
(3), two pieces of master control veneers after the power supply start simultaneously at loading running software, software matching somebody with somebody in flash Situation is put, controls first master control veneer to provide clock using the master control veneer as normal operation, such as the T3 steps in Fig. 5;
(4), when the offer clock master control veneer running software to power control module when, power control module can be read Go bail for the configuration data existed in flash, then give power panel to send control command according to configuration data, another is stand-by Master control veneer power-off, the master control veneer then normally enabled continues to run with, and completes after cell the flow such as establishes, master control veneer fortune Row is normal, such as the T4 steps in Fig. 5;
(5) master control veneer of lower electricity, is enabled if desired according to planning below, then by stand-by master control on webmaster Veneer is revised as normally enabling.Then by data syn-chronization to base station, after the master control veneer of base station normal operation receives data, the master The power control module controlled in veneer is powered according to newest configuration data, controlig power board to original stand-by master control veneer, Such as the T5 steps in Fig. 5;
(6) after the master control veneer power supply, newly enabled, software is loaded, is then obtained to the master control veneer of normal operation Newest version and data, after newest version is arrived in renewal, carry out board resetting and then proceed to run, load correct data, Until working properly, such as the T6 steps in Fig. 5.
In above-mentioned process flow steps (4), when master control veneer carries out power operation to another master control veneer, if It was found that two master control veneers have all been configured to stand-by abnormal data, at this moment then without any power operation, it is ensured that in data It is also not in the situation for falling station when abnormal.
The master control veneer of normal operation controls stand-by base band veneer to be dormant to the whole workflow that upper electricity enables from power-off Journey is as follows:
(1) when, being opened for the first time in base station, by webmaster side configuration data by opening instrument in master control veneer Burning configuration data in flash, the base band veneer not enabled temporarily is configured to ready mode;
(2), on master control veneer after electricity, power control module reads configuration data, if it find that this base band veneer is to treat With pattern, then controlig power board powers off to this base band veneer;
(3) when, needing to carry out dilatation according to planning, by this stand-by base band veneer configuration modification to open on webmaster With then by data syn-chronization to base station, after base station initiated master control veneer receives new configuration data, controlig power board is to newly opening Base band veneer is powered, such as the T5 steps in Fig. 5;
(4), after the power supply of base band veneer, newest version is obtained to the master control veneer enabled, is normally added after getting version Carrying row, until normal work, such as the T6 steps in Fig. 5.
Stand-by master control veneer and stand-by base band veneer are as follows from strategy is handled while being dormant to and enable:
When stand-by base band veneer and master control veneer are simultaneously preset, respective independent flow is each walked, detailed description realizes stream Journey refers to stand-by base band veneer and stand-by master control veneer handling process.
Above-mentioned technical proposal is broken by the master control veneer of normal operation to the master control veneer or/and base band veneer of ready mode Electricity is stand-by and subsequently enables.Realize the long-range dilatation in wireless base station.Reduce the lower station number in existing base station dilation process, so as to Reduce the dilatation cost of wireless base station and improve dilatation efficiency.
Present invention also offers a kind of wireless base station flash chamber, as shown in fig. 6, including:
It is arranged at the master control veneer 21, stand-by resource veneer 22, power panel 23 of normal operation in base band frame;
The master control veneer 21 of the normal operation is used for the dilatation configuration data for obtaining the transmission of webmaster side, and according to the expansion Holding configuration data controls the power panel 23 to be powered to the stand-by resource veneer 22;
Stand-by resource veneer 22 after power supply be used for the master control veneer 21 of the normal operation obtain newest version and Data, load operating.
In said apparatus, the master control veneer of normal operation includes:Signal receiving module 211, power control module 212;
The signal receiving module 211 is used for the dilatation configuration data for obtaining the transmission of webmaster side;
The power control module 212 is used to control the power panel 23 to described stand-by according to the dilatation configuration data Resource veneer 22 is powered, and is additionally operable to read the configuration data of master control veneer, and will according to configuration data controlig power board 23 Stand-by stand-by resource veneer 22 is configured to be powered off.
Above-mentioned technical proposal carries out dilatation by the master control veneer of normal operation to stand-by master control veneer or/and base band veneer Enable, realize the long-range dilatation in wireless base station.Reduce the lower station number in existing base station dilation process, so as to reduce wireless base The dilatation cost stood and improve dilatation efficiency.
Present invention also offers a kind of wireless base station dilatation control signal dispensing device, as shown in fig. 7, comprises:
It is arranged at the configuration module 11 of webmaster side, control signal sending module 12;
The configuration module 11 is used to stand-by resource veneer configuration data is revised as into enabling mode according to dilatation demand;
The control signal sending module 12 is used for the master control veneer that the dilatation configuration data is synchronized to normal operation.
Said apparatus realizes the generation and transmission of webmaster side dilatation signal, is easy to base station side to realize long-range dilatation.
Present invention also offers a kind of wireless base station capacity-enlarging system, as the embodiment of the present invention three, as shown in figure 8, including: The configuration module 11 of webmaster side, control signal sending module 12;Base station side is arranged at the master control veneer of normal operation in base band frame 21, stand-by resource veneer 22, power panel 23;The configuration module 11 is used for the stand-by resource veneer 22 according to dilatation demand Configuration data is revised as enabling mode;The control signal sending module 12 be used for by the dilatation configuration data be synchronized to it is described just On the master control veneer 21 often run;The master control veneer 21 of the normal operation is used for the dilatation configuration number for obtaining the transmission of webmaster side According to, and control the power panel 23 to be powered to the stand-by resource veneer 22 according to the dilatation configuration data;After power supply Stand-by resource veneer 22 be used to obtain newest version and data, load operating to the master control veneer 21 of the normal operation.
Before to wireless base station dilatation, when base station is opened first, as needed, by not having to temporarily in base band frame, groove position is pre- Some resource veneers are plugged, these resource veneers generally comprise master control veneer, base band veneer and master control borad and base band veneer Combination, but these veneers are configured to ready mode by webmaster side configuration data by opening instrument, it is configured to ready mode These veneers are configured to stand-by by the master control veneer of normal operation according to the configuration data controlig power board of webmaster side to these Veneer carries out power operation, it is ensured that these standby board resources do not interfere with the normal operation for enabling veneer before dilatation enables And consumption electric energy.
Specifically, as the embodiment of the present invention four, the master control veneer of the normal operation includes:Signal receiving module 211, Power control module 212;The signal receiving module is used for the dilatation configuration data for obtaining the transmission of webmaster side;The power supply control Module 212 is used to control the power panel 23 to be powered to the stand-by resource veneer 22 according to the dilatation configuration data, It is additionally operable to read the configuration data of master control veneer, and stand-by stand-by resource will be configured to according to configuration data controlig power board 23 Veneer 22 is powered off.
The system other structures are identical with embodiment three, are not repeated.In the system, the master control veneer of normal operation according to The configuration data of itself is configured to described stand-by stand-by resource veneer and powered off.
The configuration data derives from webmaster side, but when opening first, webmaster side does not set up wireless connection, net also with base station Pipe side is carried to the configuration data of base station by opening instrument (for example, USB flash disk), master control veneer to normal operation in base band and is treated Master control veneer carries out data write-in.
When being built a station in wireless base station, by stand-by resource veneer insertion base band frame slot, stand-by resource veneer, it is divided into Two kinds:Master control veneer or/and base band veneer.
The system also includes:First burning module, the second burning module, clock veneer determining module;
When first burning module is used to open for the first time in base station, by webmaster side configuration data by opening instrument in base station Burning configuration data is configured as enabling mode in the flash of upper first master control veneer;
Second burning module is used for webmaster side configuration data by opening instrument second master control veneer on base station Burning configuration data is configured as ready mode in flash;
Power panel is powered to first master control veneer and second master control veneer on base station;
Two pieces of master control veneers after the power supply start simultaneously at loading running software, and clock veneer determining module is used for basis Configuring condition in flash, first master control veneer is controlled to provide clock using the master control veneer as normal operation.
It is above-mentioned for base station for the first time open when, what master control veneer and stand-by master control veneer to normal operation were handled Mode, to realize that the determination of the master control veneer of normal operation and the data of normal operation master control veneer and stand-by master control veneer are matched somebody with somebody Put.The master control veneer of subsequent normal operation can power off according to configuration to stand-by master control veneer.
During above-mentioned configuration data burning, it is possible to make a mistake, in order to ensure also will not in burning data exception There is the situation at station.Configuration data of the power control module reading and saving in flash in first master control veneer, such as When fruit finds that first master control veneer and second master control veneer are each configured to the abnormal data for ready mode, without Power operation.
The processing mode of the stand-by base band veneer base band veneer different, stand-by with the processing mode of stand-by master control veneer Configuration data pass through to configure the master control veneer of normal operation and realize.The system also includes:3rd burning module, in base Stand for the first time when opening, by webmaster side configuration data by opening instrument on base station burning configures in the flash of master control veneer Data, the base band veneer not enabled temporarily is configured to ready mode.
Said system powers off stand-by and follow-up dilatation to stand-by mode resource veneer by the master control veneer of normal operation and opened With realizing the long-range dilatation in wireless base station.Reduce the lower station number in existing base station dilation process, so as to reduce wireless base station Dilatation cost and improve dilatation efficiency.
The preferred embodiments of the present invention have shown and described in described above, but as previously described, it should be understood that the present invention is not Form disclosed herein is confined to, is not to be taken as the exclusion to other embodiment, and available for various other combinations, modification And environment, and can be carried out in the scope of the invention is set forth herein by the technology or knowledge of above-mentioned teaching or association area Change., then all should be in institute of the present invention and the change and change that those skilled in the art are carried out do not depart from the spirit and scope of the present invention In attached scope of the claims.

Claims (11)

1. a kind of wireless base station expansion method, wherein, including:
The master control veneer of normal operation obtains the dilatation configuration data that webmaster side is sent on base station, and configures number according to the dilatation It is powered according to controlig power board to stand-by resource veneer;
Stand-by resource veneer after power supply obtains newest version and data, loading fortune to the master control veneer of the normal operation OK.
2. the method according to claim 11, wherein,
Before the master control veneer of normal operation obtains the dilatation configuration data that webmaster side is sent on base station, including:
The master control veneer of normal operation after upper electricity reads the configuration data of master control veneer, and according to configuration data controlig power board The stand-by resource veneer for being configured to stand-by is powered off.
3. the method according to claim 11, wherein,
The stand-by resource veneer is master control veneer or/and base band veneer.
4. the method according to claim 11, wherein,
It is configured to described before stand-by stand-by master control veneer powered off, including:
When being opened for the first time in base station, by webmaster side configuration data by opening instrument first master control veneer on base station Burning configuration data is configured as enabling mode in flash;
By webmaster side configuration data by opening instrument burning configuration data configuration in the flash of the second master control veneer on base station As ready mode;
Power panel is powered to first master control veneer and second master control veneer on base station;
Two pieces of master control veneers after the power supply start simultaneously at loading running software, configuring condition of the software in flash, control Make first master control veneer and provide clock using the master control veneer as normal operation.
5. the method according to claim 11, wherein, configuration number of the first master control veneer reading and saving in flash According to, if it find that when first master control veneer and second master control veneer are each configured to the abnormal data for ready mode, Without power operation.
6. according to the method for claim 3, wherein, it is configured to stand-by stand-by base band veneer by described and carries out powering off it Before, including:
Base station when opening for the first time, by webmaster side configuration data by opening the master control veneer of instrument normal operation on base station Flash in burning configuration data, the base band veneer not enabled temporarily is configured to ready mode.
7. a kind of wireless base station dilatation control signal sending method, wherein, including:
Stand-by resource veneer configuration data is revised as enabling mode by webmaster lateral root according to dilatation demand, and by the dilatation configuration data It is synchronized on the master control veneer of base station normal operation.
8. a kind of wireless base station flash chamber, wherein, including:It is arranged at the master control veneer of normal operation in base band frame, stand-by money Source veneer, power panel;
The master control veneer of the normal operation is used for the dilatation configuration data for obtaining the transmission of webmaster side, and is configured according to the dilatation Data control the power panel to be powered to the stand-by resource veneer;
Stand-by resource veneer after power supply is used to obtain newest version and data, loading to the master control veneer of the normal operation Operation.
9. device according to claim 8, wherein, the master control veneer of normal operation includes:Signal receiving module, power supply control Molding block;
The signal receiving module is used for the dilatation configuration data for obtaining the transmission of webmaster side;
The power control module is used to control the power panel to give the stand-by resource veneer according to the dilatation configuration data It is powered, is additionally operable to read the configuration data of master control veneer, and will be configured to according to configuration data controlig power board stand-by Stand-by resource veneer is powered off.
10. a kind of wireless base station dilatation control signal dispensing device, wherein, including:
It is arranged at configuration module, the control signal sending module of webmaster side;
The configuration module is used to stand-by resource veneer configuration data is revised as into enabling mode according to dilatation demand;
The control signal sending module is used for the master control veneer that the dilatation configuration data is synchronized to normal operation.
11. a kind of wireless base station capacity-enlarging system, wherein, including:
It is arranged at configuration module, the control signal sending module of webmaster side;
It is arranged at the master control veneer of normal operation in base band frame, stand-by resource veneer, power panel;
The configuration module is used to stand-by resource veneer configuration data is revised as into enabling mode according to dilatation demand;
The control signal sending module is used for the master control veneer that the dilatation configuration data is synchronized to normal operation;
The master control veneer of the normal operation is used for the dilatation configuration data for obtaining the transmission of webmaster side, and is configured according to the dilatation Data control the power panel to be powered to the stand-by resource veneer;
Stand-by resource veneer after power supply is used to obtain newest version and data, loading to the master control veneer of the normal operation Operation.
CN201610423681.1A 2016-06-15 2016-06-15 Wireless base station expansion method, dilatation control signal sending method, apparatus and system Pending CN107517468A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610423681.1A CN107517468A (en) 2016-06-15 2016-06-15 Wireless base station expansion method, dilatation control signal sending method, apparatus and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610423681.1A CN107517468A (en) 2016-06-15 2016-06-15 Wireless base station expansion method, dilatation control signal sending method, apparatus and system

Publications (1)

Publication Number Publication Date
CN107517468A true CN107517468A (en) 2017-12-26

Family

ID=60719964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610423681.1A Pending CN107517468A (en) 2016-06-15 2016-06-15 Wireless base station expansion method, dilatation control signal sending method, apparatus and system

Country Status (1)

Country Link
CN (1) CN107517468A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012134567A1 (en) * 2011-04-01 2012-10-04 Intel Corporation Opportunistic carrier aggregation using short range extension carriers
CN103297985A (en) * 2013-05-31 2013-09-11 华为技术有限公司 Base station configuration method and system
US20130265917A1 (en) * 2012-04-09 2013-10-10 Huawei Technologies Co., Ltd. Communication method and system, access network device, and application server
EP2753111A1 (en) * 2011-11-22 2014-07-09 Huawei Technologies Co., Ltd. Method and device for implementing lte baseband resource pool
CN104768182A (en) * 2015-03-23 2015-07-08 大唐移动通信设备有限公司 Double-mode RRU upgrading method and device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012134567A1 (en) * 2011-04-01 2012-10-04 Intel Corporation Opportunistic carrier aggregation using short range extension carriers
EP2753111A1 (en) * 2011-11-22 2014-07-09 Huawei Technologies Co., Ltd. Method and device for implementing lte baseband resource pool
US20130265917A1 (en) * 2012-04-09 2013-10-10 Huawei Technologies Co., Ltd. Communication method and system, access network device, and application server
CN103297985A (en) * 2013-05-31 2013-09-11 华为技术有限公司 Base station configuration method and system
CN104768182A (en) * 2015-03-23 2015-07-08 大唐移动通信设备有限公司 Double-mode RRU upgrading method and device

Similar Documents

Publication Publication Date Title
CN102421134B (en) Wireless access point equipment and method for controlling same
CN109360564B (en) Method and device for selecting language identification mode and household appliance
US20080254841A1 (en) Communication terminal and computer-readable storage medium
CN103384157A (en) Low-power-consumption embedded type WIFI module
CN104517086B (en) ID card information read method
CN106662908A (en) Technologies for collaborative hardware and software scenario-based power management
CN103200655A (en) Method and device for energy conservation of remote radio frequency system
CN110417871A (en) A kind of smart machine upgrade method
CN103379528A (en) Board self-adaptation parameter configuration method, BBU, base station and base station subsystem (BSS)
CN112105041A (en) Control method and device for environment adjusting equipment powered by battery and terminal
CN105611409A (en) Advertisement machine control system, control method thereof and advertisement machine
CN101944314A (en) Pattern generator, pattern data updating system and pattern data updating method
CN107517468A (en) Wireless base station expansion method, dilatation control signal sending method, apparatus and system
CN108605289A (en) Low-power cellular modem system architecture
CN105474732A (en) Device control method, device and system under centralized baseband pool architecture
CN104424142A (en) Method and device for accessing shared resource in multi-core processor system
CN103685764A (en) Power-saving method for mobile terminal and device
CN103986588A (en) Computer system and far-end remote control method of computer device
CN106484074B (en) Nonvolatile memory device, nonvolatile memory method, computer system, and method for implementing standby or hibernation
CN105828421A (en) Terminal and terminal power saving method
CN206148602U (en) Antenna is divided to integration room
WO2012088846A1 (en) Method, device and base station for powering on base station in single station mode
CN111698297B (en) Upgradable electronic table board control method
CN104661284A (en) WIFI (wireless fidelity) management system of mobile terminal and management method of WIFI management system
CN110177346A (en) Wireless electron display device based on eMTC

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171226