CN106771873A - A kind of distribution network failure quick positioning system - Google Patents
A kind of distribution network failure quick positioning system Download PDFInfo
- Publication number
- CN106771873A CN106771873A CN201611256722.9A CN201611256722A CN106771873A CN 106771873 A CN106771873 A CN 106771873A CN 201611256722 A CN201611256722 A CN 201611256722A CN 106771873 A CN106771873 A CN 106771873A
- Authority
- CN
- China
- Prior art keywords
- distribution network
- quick positioning
- positioning system
- layer
- network failure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/08—Locating faults in cables, transmission lines, or networks
- G01R31/081—Locating faults in cables, transmission lines, or networks according to type of conductors
- G01R31/086—Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution networks, i.e. with interconnected conductors
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
- Y04S10/52—Outage or fault management, e.g. fault detection or location
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
A kind of distribution network failure quick positioning system, category monitoring field.It is in power distribution network, one or more current sensors are installed in interdependent node, the analog signal digital that Current Transformer Secondary side is sensed, and the backstage main website installed in control centre is sent to by GPRS/GSM wireless networks, backstage main station system combination PMS platforms area figure information, it is possible to be accurately positioned to trouble point.Its testing result according to the current transformer for being arranged on bar change crane case outgoing line side, it is accurately positioned trouble point, breakdown repair flow can be greatly simplified, dispatcher can directly arrange power network operation maintenance personnel to go to trouble point handling failure, the waste of unnecessary manpower and materials is reduced, power supply reliability is improve.Can be widely used for operation maintenance and the operational management field of distribution system.
Description
Technical field
Determine method the invention belongs to the field of monitoring, more particularly to a kind of abort situation for low-voltage network.
Background technology
During annual summer peak meeting, residential electricity consumption load drastically abruptly increase, from 95598 Customer Service Centers (also known as electric power visitor
Family servicing call center system or 95598 customer service hotlines) the breakdown repair list for coming is transmitted through mainly with power distribution station low tension switch
Tripping operation, the molten knife fusing of feeder pillar, bar become based on the fusing of crane case stereotype, and the normal electricity consumption to low pressure resident causes very big shadow
Ring.When power supply reliability has turned into one critical services index of Utilities Electric Co., how quick fault point, eliminate failure,
Fast quick-recovery resident powers, and reduces resident's power off time, and this is related to Utilities Electric Co. to the promise of society and to value view
Practicing.
At this stage, low pressure resident breakdown repair basic procedure is as follows:
After family has a power failure, resident can contact residential property first, if trouble point does not belong to property and managed, resident will dial
95598 customer service hotlines are made a call to, 95598 Customer Service Centers can give each electric company according to address job order where residential households
Hold inquiry, hold the project to outsource team ask and can be dispatched to nearby according to the single specific address of repairing, after construction brigade makes house calls if it find that
Trouble point does not belong to it and is managed, and repairing can singly be replied to and hold inquiry by he, and propose to need scheduling assisted treatment, and holding inquiry again will repairing list
Control centre is given to, dispatcher arranges O&M maintainer to go to in-situ processing failure again.
Be can be seen that in the case of some failures from above-mentioned breakdown repair flow, residential property, project to outsource team do not have
Solve resident to have a power failure this problem, the role of they simply eliminate the possible position in trouble point, if one can be developed
Set is directed to the failure fast positioning method or system of low-voltage network, the localization of faults within the most short time, it is possible to will be small
Area's property, the emergency repair time of these engineering noises of project to outsource team are omitted, and power network operation maintenance personnel goes directly to according to dispatcher's instruction
Trouble point handling failure, fast quick-recovery power transmission, improves rapidly power supply reliability.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of distribution network failure quick positioning system.It is in interdependent node
One or more voltages or current sensor are installed, the detection knot of the current transformer by becoming crane case outgoing line side installed in bar
Really, trouble point can be accurately positioned, breakdown repair flow can be greatly simplified, before dispatcher can directly arrange power network operation maintenance personnel
Toward trouble point handling failure.
The technical scheme is that:A kind of distribution network failure quick positioning system is provided, it is characterized in that:
In power distribution network, one or more current sensors are installed in interdependent node, by the sensing of Current Transformer Secondary side
Analog signal digital, and the backstage main website installed in control centre, backstage master are sent to by GPRS/GSM wireless networks
System of standing combination PMS platforms area figure information, it is possible to be accurately positioned to trouble point;
Described quick positioning system, by data collection station layer, base station layer and expert analyzing system layer come quick fixed
The failure of position power distribution network;
Described data collection station layer is made up of current sensor, main processor unit, communication module and power supply unit,
It is responsible for gathering sensing data from interdependent node, carries out analog-to-digital conversion, is sent to by GPRS/GSM wireless networks
Backstage main station system on Internet;
Wireless telecommunications and data between the responsible data collection station layer of described base station layer and expert analyzing system layer are passed
It is defeated;
Described expert analyzing system layer receives the current signal that data collection station layer is measured for long-range, and signal is entered
Row fault section diagnosis, and remote control is carried out to system, it is ensured that system stable operation;
Stelliform connection topology configuration is used between described data collection station layer and base station layer.
Wherein, for final electricity consumption user, described interdependent node becomes the outgoing line side of crane case for bar;Described electric current is passed
Sensor is arranged on the outgoing line side that bar becomes crane case.
Wherein, for the miscellaneous equipment in power distribution network, described interdependent node is that low tension switch or low pressure melt going out for knife
Line side, described current sensor is threephase current transformer;Described threephase current transformer be arranged on low tension switch or
The outgoing line side of the molten knife of low pressure.
Further, described miscellaneous equipment includes European-type box change, American Unit Substation or low pressure feeder pillar.
Specifically, when a user does not have electricity, if the threephase current transformer installed in outgoing line side can be in secondary side
Sense related data, it is determined that bar becomes high voltage fuse, low pressure crane case plug-in strip normal operation;
When many users do not have electricity, if A phase current mutual inductor secondary sides sensed data is 0, infer that trouble point belongs to
Electric industry equipment;
Described distribution network failure quick positioning system, is judged by this decision logic, to simplify breakdown repair flow.
Compared with the prior art, it is an advantage of the invention that:
When electric power facility breaks down, can quick lock in abort situation, reduce the breakdown repair time, optimization failure rob
Handling process is repaiied, the waste of unnecessary manpower and materials is reduced, power supply reliability is improved.
Brief description of the drawings
Fig. 1 is the structural representation of distribution network failure quick positioning system of the present invention.
Specific embodiment
With reference to embodiment, the present invention will be further described.
In Fig. 1, technical solution of the present invention carrys out the quick event for positioning power distribution network according to distribution network failure quick positioning system
Barrier, the distribution network failure quick positioning system described in it physically can be divided into three-decker according to deployed position, respectively count
According to acquisition terminal layer, base station layer, expert analyzing system layer.
As seen from the figure, its base station layer includes front end monitoring terminal and backstage main station system.
Front end monitoring terminal is arranged on relevant device node, mainly by current sensor, main processor unit, communication mould
Block and power supply unit are constituted.Front end monitoring terminal collection sensing data, is sent to by GPRS/GSM wireless networks
Backstage main station system on Internet.
Stelliform connection topology configuration is used between base station and data acquisition equipment.
Expert analyzing system is the current signal measured for long-range reception system, and fault section diagnosis are carried out to signal,
And remote control is carried out to system, it is ensured that system stable operation.
The mechanism that the data acquisition equipment of bottom is uploaded using data timing, after it upload the data to main website, by base
Stand and Treatment Analysis are carried out to data according to the algorithm on backstage, and be stored in the database specified, after the standard for meeting agreement,
Data in the database can also meet the demand of each service application, be supported for other special information systems provide data.
Collecting device is the information bottom of power information acquisition system, is responsible for collecting and providing the original electricity consumption of whole system
Information, including current sensor, central data acquisition process unit, lithium battery power supply system, by these simulation monitoring equipment
The high speed precise acquisition of signal is completed, and ensures the continued power of whole system.
Wherein, wireless communication system is the tie of base station and collecting device, for the information exchange of base station and terminal provides chain
Roadbed plinth.In the technical program, the main remote radio communication that main website and bottom collecting device are realized using GPRS wireless public networks.
After center of the centralized monitor receives various alarm signals, corresponding responsibility is notified by the way that management software is manual or automatic
People, and result is tracked and collects simultaneously, detection terminal can will measure energy value timing and be sent in management
The heart, administrative center will compare to number of actually checking meter according to this.
The major function of analysis expert software is that the data that system for field is collected are analyzed, and by fault message reality
When show.
Analysis expert Software for Design is write using MFC, MFC (Microsoft Foundation Classes, Microsoft
MFC) with pressing close to bottom, performance is good, and reliable and stable, compatibility is strong, simple to operate, efficiency high, and user interface is warm,
The features such as optional component is more.
Login feature is added in analysis expert software, user needs just be operated system interface after logging in.
Interface mainly includes equipment mount message and device fault information two parts after login, in view of distribution network failure is quick
The uniformity and ease for use of alignment system, the background data base of selection is Access databases, and it has simple and convenient, it is easy on
The advantages such as hand, maintenance.
The analysis expert software current data that meeting periodic detection is collected in actual motion, when a certain phase current of discovery is
Fault warning information is sent when 0 and is shown in device fault information, can pointed out again after pending fault reparation.
In summary, technical scheme, there is provided a kind of distribution network failure quick positioning system, its inventive point exists
In:In power distribution network, one or more current sensors are installed in interdependent node, the simulation that Current Transformer Secondary side is sensed
Signal is digitized, and is sent to the backstage main website installed in control centre, backstage main station system by GPRS/GSM wireless networks
With reference to PMS platforms area figure information, it is possible to be accurately positioned to trouble point.
In the technical program, for final electricity consumption user, described interdependent node becomes the outgoing line side of crane case for bar;Institute
The current sensor stated is arranged on the outgoing line side that bar becomes crane case.
In the technical program, for the miscellaneous equipment in power distribution network, described interdependent node is low tension switch or low
The outgoing line side of the molten knife of pressure, described current sensor is threephase current transformer;Described threephase current transformer is arranged on low
Compress switch or the molten knife of low pressure outgoing line side.
Further, described miscellaneous equipment includes European-type box change, American Unit Substation or low pressure feeder pillar.
Specifically, the quick positioning system, by data collection station layer, base station layer and expert analyzing system layer come fast
The failure of speed positioning power distribution network.
Data collection station layer described in it is by current sensor, main processor unit, communication module and power supply unit structure
Into, it is responsible for gathering sensing data from interdependent node, analog-to-digital conversion is carried out, it is sent to by GPRS/GSM wireless networks
Backstage main station system on Internet.
Wireless telecommunications between base station layer responsible data collection station layer and expert analyzing system layer and data described in it
Transmission.
Expert analyzing system layer described in it receives the current signal that data collection station layer is measured for long-range, to signal
Fault section diagnosis are carried out, and remote control is carried out to system, it is ensured that system stable operation..
Specifically, using stelliform connection topology configuration between described data collection station layer and base station layer.
In actual moving process, when a user does not have electricity, if installed in the equal energy of threephase current transformer of outgoing line side
Related data is sensed in secondary side, it is determined that bar becomes high voltage fuse, low pressure crane case plug-in strip normal operation;
When many users do not have electricity, if A phase current mutual inductor secondary sides sensed data is 0, infer that trouble point belongs to
Electric industry equipment;
Described distribution network failure quick positioning system, is judged by this decision logic, to simplify breakdown repair flow.
Because the present invention is accurately positioned by the testing result of the current transformer installed in bar change crane case outgoing line side
Trouble point, can greatly simplify breakdown repair flow, and dispatcher can directly arrange power network operation maintenance personnel to go to trouble point to process
Failure, and remote control is carried out to system, it is ensured that the safe and stable operation of distribution system.
The method can be widely used in operation maintenance and the operational management field of distribution system.
Claims (5)
1. a kind of distribution network failure quick positioning system, it is characterized in that:
In power distribution network, one or more current sensors are installed in interdependent node, the mould that Current Transformer Secondary side is sensed
Intend signal digitlization, and the backstage main website installed in control centre, backstage system of main website are sent to by GPRS/GSM wireless networks
System combines PMS platforms area figure information, it is possible to be accurately positioned to trouble point;
Described quick positioning system, is matched somebody with somebody by data collection station layer, base station layer and expert analyzing system layer come quick positioning
The failure of power network;
Described data collection station layer is made up of current sensor, main processor unit, communication module and power supply unit, is responsible for
Sensing data is gathered from interdependent node, analog-to-digital conversion is carried out, is sent on internet by GPRS/GSM wireless networks
Backstage main station system;
Wireless telecommunications and data transfer between the responsible data collection station layer of described base station layer and expert analyzing system layer;
Described expert analyzing system layer receives the current signal that data collection station layer is measured for long-range, and event is carried out to signal
Barrier level diagnosis, and remote control is carried out to system, it is ensured that system stable operation;
Stelliform connection topology configuration is used between described data collection station layer and base station layer.
2. according to the distribution network failure quick positioning system described in claim 1, it is characterized in that for final electricity consumption user, it is described
Interdependent node for bar become crane case outgoing line side;Described current sensor is arranged on the outgoing line side that bar becomes crane case.
3. according to the distribution network failure quick positioning system described in claim 1, it is characterized in that being set for other in power distribution network
Standby, described interdependent node is low tension switch or the outgoing line side of the molten knife of low pressure, and described current sensor is that three-phase current is mutual
Sensor;Described threephase current transformer is arranged on the outgoing line side of low tension switch or the molten knife of low pressure.
4. according to the distribution network failure quick positioning system described in claim 3, it is characterized in that described miscellaneous equipment includes Europe
The change of formula case, American Unit Substation or low pressure feeder pillar.
5. according to the distribution network failure quick positioning system described in claim 1, it is characterized in that when a user does not have electricity, if
Threephase current transformer installed in outgoing line side can sense related data in secondary side, it is determined that bar becomes high voltage fuse, low
Pressure crane case plug-in strip normal operation;
When many users do not have electricity, if A phase current mutual inductor secondary sides sensed data is 0, infer that trouble point belongs to electric industry
Equipment;
Described distribution network failure quick positioning system, is judged by this decision logic, to simplify breakdown repair flow.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611256722.9A CN106771873A (en) | 2016-12-30 | 2016-12-30 | A kind of distribution network failure quick positioning system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611256722.9A CN106771873A (en) | 2016-12-30 | 2016-12-30 | A kind of distribution network failure quick positioning system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106771873A true CN106771873A (en) | 2017-05-31 |
Family
ID=58953500
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611256722.9A Pending CN106771873A (en) | 2016-12-30 | 2016-12-30 | A kind of distribution network failure quick positioning system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106771873A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110852627A (en) * | 2019-11-13 | 2020-02-28 | 国电南瑞科技股份有限公司 | Decision method and device for post-disaster first-aid repair of power distribution network |
CN111579917A (en) * | 2020-04-08 | 2020-08-25 | 广西电网有限责任公司北海供电局 | Low-voltage distribution network fault positioning system and method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201408236Y (en) * | 2009-05-07 | 2010-02-17 | 思源电气股份有限公司 | Power distribution network failure locating device |
CN203224591U (en) * | 2013-01-29 | 2013-10-02 | 重庆市电力公司万州供电局 | Distribution network fault positioning device based on wireless synchronization technology and zero-sequence current detection |
CN203870191U (en) * | 2014-05-05 | 2014-10-08 | 国电南瑞科技股份有限公司 | Low-voltage line fault locating terminal of power distribution area |
US20140300210A1 (en) * | 2011-11-03 | 2014-10-09 | Marcos Valadão Abi-Ackel | System for controlling, measuring and monitoring the secondary electric power distribution grid |
CN204177912U (en) * | 2014-11-25 | 2015-02-25 | 国家电网公司 | Based on Distribution Network Failure early warning and the positioning system of GIS application |
CN204408024U (en) * | 2015-03-13 | 2015-06-17 | 刘明慧 | A kind of 10kV circuit operation information acquisition system |
CN204559234U (en) * | 2015-03-04 | 2015-08-12 | 国家电网公司 | A kind of panorama integral intelligent distribution network failure monitoring system |
CN106054027A (en) * | 2016-07-30 | 2016-10-26 | 孙文兵 | Distribution network grounding fault location system |
-
2016
- 2016-12-30 CN CN201611256722.9A patent/CN106771873A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201408236Y (en) * | 2009-05-07 | 2010-02-17 | 思源电气股份有限公司 | Power distribution network failure locating device |
US20140300210A1 (en) * | 2011-11-03 | 2014-10-09 | Marcos Valadão Abi-Ackel | System for controlling, measuring and monitoring the secondary electric power distribution grid |
CN203224591U (en) * | 2013-01-29 | 2013-10-02 | 重庆市电力公司万州供电局 | Distribution network fault positioning device based on wireless synchronization technology and zero-sequence current detection |
CN203870191U (en) * | 2014-05-05 | 2014-10-08 | 国电南瑞科技股份有限公司 | Low-voltage line fault locating terminal of power distribution area |
CN204177912U (en) * | 2014-11-25 | 2015-02-25 | 国家电网公司 | Based on Distribution Network Failure early warning and the positioning system of GIS application |
CN204559234U (en) * | 2015-03-04 | 2015-08-12 | 国家电网公司 | A kind of panorama integral intelligent distribution network failure monitoring system |
CN204408024U (en) * | 2015-03-13 | 2015-06-17 | 刘明慧 | A kind of 10kV circuit operation information acquisition system |
CN106054027A (en) * | 2016-07-30 | 2016-10-26 | 孙文兵 | Distribution network grounding fault location system |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110852627A (en) * | 2019-11-13 | 2020-02-28 | 国电南瑞科技股份有限公司 | Decision method and device for post-disaster first-aid repair of power distribution network |
CN111579917A (en) * | 2020-04-08 | 2020-08-25 | 广西电网有限责任公司北海供电局 | Low-voltage distribution network fault positioning system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2602289C (en) | Using a fixed network wireless data collection system to improve utility responsiveness to power outages | |
CN106990328B (en) | Distribution network emergency repair abnormal data analysis and fault positioning system and method | |
US10128664B1 (en) | Monitoring voltage levels on power lines and recloser operation | |
CN106980071B (en) | Visual first-aid repair system based on power grid GIS and working method thereof | |
JP5249950B2 (en) | Method and system for utility network outage detection | |
CN100466416C (en) | Intelligent decision support system for urban power grid accidents | |
CN102928809B (en) | Electric energy metering device remote monitoring diagnostic system and working method thereof | |
CN106872856B (en) | Power distribution network fault active first-aid repair system and method based on multi-element fault collection | |
CN102255393B (en) | Ground wire hanging anti-error blocking system and method thereof | |
CN107167704B (en) | Power distribution network fault diagnosis system and method based on CIM model | |
CN103852744A (en) | Distributed online monitoring system and method for electric energy metering device | |
CN102436226A (en) | Online monitoring and condition maintenance management system | |
CN201314942Y (en) | Monitoring system for detecting the fault of distribution network trolly wires | |
CN106814286B (en) | Power distribution network fault positioning system, method and server based on multi-element fault acquisition | |
CN101446618A (en) | Real-time monitoring system of faults of overhead lines of distribution network | |
CN103915898A (en) | Operation and maintenance method for intelligent substation network | |
CN112001686A (en) | Overhead line power failure studying and judging system | |
CN112583117A (en) | Data assembly service system based on intelligent edge terminal | |
CN112165398A (en) | System based on 5G wisdom lamp pole is measurement along separate routes | |
CN115775080A (en) | Energy perception studying and judging system for client side | |
JP4358121B2 (en) | Power system monitoring control system, method, program, and management server | |
CN106771873A (en) | A kind of distribution network failure quick positioning system | |
CN110108970A (en) | Transformers for Rural Networks temperature monitoring cloud service system based on Internet of Things | |
CN104614699A (en) | Higher-efficiency remote monitoring and diagnosis method of electric energy metering device | |
CN106814285A (en) | A kind of method for rapidly positioning of distribution network failure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170531 |