CN103455845B - A kind of method controlling product quality with standard - Google Patents
A kind of method controlling product quality with standard Download PDFInfo
- Publication number
- CN103455845B CN103455845B CN201310289459.3A CN201310289459A CN103455845B CN 103455845 B CN103455845 B CN 103455845B CN 201310289459 A CN201310289459 A CN 201310289459A CN 103455845 B CN103455845 B CN 103455845B
- Authority
- CN
- China
- Prior art keywords
- standard
- parts
- product
- production
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Abstract
A kind of method controlling product quality with standard, control for providing the strict standard that carries out when producing drawing for shop floor worker in the design department of enterprise, production division carries out strict production drawing prescriptive jurisdiction when producing, and quality testing department carries out product, produces the detailed comparison verification of drawing, standard content.A kind of method controlling product quality with standard that the present invention proposes, normal data management is carried out in units of parts, when standard changes, designer can be made in time to be adjusted producing drawing, change, the data accuracy producing drawing can be managed by producers when producing, guarantee that the production drawing of production line is corresponding with standard, quality inspection personnel is when carrying out quality inspection to product, can accurately obtain by standard corresponding to quality inspection product, and according to up-to-date standard, product can be carried out quality inspection, thus may insure that carrying out and implementing of standard, products quality guarantee.
Description
Technical field
The present invention relates in process of producing product, quality check process by producing drawing data verification to product
The method that quality is managed, produces in particular with the normal data followed required for product component
The method of quality management.
Background technology
Regulation in " Standardization Law of the People's Republic of China ", for relevant to industrial products the most several
Individual aspect should formulate standard,
1, the kind of industrial products, specification, quality, grade or safety, hygienic requirements.
2, industrial products design, produce, check, pack, store, transport, the method that uses or
Safety in person's production, storage, transportation, hygienic requirements.
3, about technical term, symbol, code name and the system of industrial production, engineering construction and environmental protection
Drawing method.
For industrial products, the particularly industrial products of the Large-Scale Equipment such as aircraft, automobile manufacturing,
For products quality guarantee, the industrial interchangeability of parts and simplification working condition, economize on resources, respectively
Relevant enterprise is accomplished by following according to " Standardization Law of the People's Republic of China " during design, production etc.
Principle and formulate various GBs, national military standard, rower, the relevant criterion such as enterprise's mark.
Along with the development of society, standard there is also generation, the life changing, substituting and substituted, wither away
Periodic characteristic, also will bring following problem to enterprise,
1, newly marking issue, replace old mark, which which product of enterprise can be affected by?
2, standard have changed, and the standard of renewal can be carried out and implemented in time?The departments such as design, production can
Know in time?
3, the company standard being currently in use also is quoting the standard abrogated?Product design also can mistake
Use standard of abrogating and need the standard of revision?
4, for enterprise, adopting the core work that mark is standardized management, standard is in life cycle each stage
Can embody again different states or form, and adopt target behavior and have and can produce standard and product, tissue joint
The incidence relation of point.What kind of the replacement of the most each standard, change history is?Enterprise adopts mark, draws
What is with historical situation?
If these problems can not get solve, the qualification rate of product will certainly be caused to reduce, waste material and
Operation resource, brings potential safety hazard also can under serious conditions the consumer of product.
Such as, for the enterprise of a production aircraft engine, each of which aircraft engine product is equal
Being made up of thousands of kinds of parts, every kind of parts all should observe corresponding GB or national military standard or navigation mark or enterprise
The standards such as mark, wherein, enterprise's mark may quote GB or the navigation mark of upper level, as original in certain bolt
Corresponding enterprise's mark should be observed, when the content of the GB cited in this enterprise mark has carried out part change, to this spiral shell
When the material of bolt or process technique have carried out change, if this enterprise mark can not upgrade in time, or update
After enterprise mark can not feed back to a line production division by design department's more new production drawing in time, then produce
Department carries out bolt production by still marking according to the enterprise before changing on old drawing, in this case, produces
Bolt out cannot meet acceptance requirement, thus wastes material and operation resource, if these bolts
Fit on aircraft engine is passed in client's hand accidentally, then be also possible to bring severe compromise.
Existing standardization management work, relies primarily on manpower and paper document mode manages, due to single product
Product may relate to thousands of standards, and the most simple labor management is the most inefficient, it is impossible to have
Effect solves the problems referred to above, also additionally is difficult to specifically find out some standard has use on which parts,
The most also easily cause the mistake of standard management information, careless omission, be also easy for so that enterprise design,
The link such as production use (or quoting) out-of-date discarded standard, still be designed according to old standard and
Produce, thus cause substandard product rate to rise, or make the product of enterprise can not meet wanting of client
Ask.
Chinese patent CN101436200A provides a kind of standardized information management system and standard update thereof
Method, the patent provides the data message of institute of a kind of automatically updated enterprise accepted standard and updating
Whether information is sent to the method for relative users, but obtain during design, production etc. for standard
Carry out and implement and corresponding solution is not provided.
For industrial products, the particularly industrial products of the Large-Scale Equipment such as aircraft, automobile manufacturing,
Design department provide processing drawing, technological process list etc. produce drawing, shop floor worker be typically both needed to strictly by
The production drawing provided according to design department is carried out, if it is possible to from design department at parts drawing
Design phase just can carry out standard control, that is to say, if standard can be known in time in design department
Situation of change, and carry out layout design according to the change of standard, carry out strict production in production division
Drawing data accuracy manages, and carries out product quality data at quality testing department and produces the verification of drawing data
Management, it is possible to effectively solve foregoing problems.
Summary of the invention
The technical problem to be solved in the present invention is to provide one and just carries out standard in the parts drawing design phase
Controlling, production division carries out strict production drawing data accuracy management, and quality testing department carries out product
Quality detecting data and the method verifying management producing drawing data, to be reduced or avoided noted earlier asking
Topic.
It is to say, the technical problem to be solved in the present invention is: design department can be allowed to know zero in time
The change of the standard that part is used, so that designer can be according to the change information of standard to design
Drawing is adjusted or revises, or design department is when carrying out parts layout design, designer
Parts drawing data can be compared by the design equipment that member is used with corresponding standard content data
Right, it is to avoid parts drawing data does not meets the standard content of correspondence;Production division, when producing, produces
The information of the corresponding standard producing drawing can be compared by the production equipment that personnel are used, or enters
Parts drawing data is compared by one step with corresponding standard content data, it is to avoid parts drawing number
According to the standard content not meeting correspondence, it is ensured that the production drawing of production line and components information and relevant mark
Calibration information mates, and quality testing department is when quality inspection, and the quality inspection management equipment that quality inspection personnel is used can be to life
The information of corresponding standard producing drawing is compared, or further by the quality detecting data of product with corresponding
Standard content data are compared, so that it is guaranteed that product can be carried out matter according to standard accurately during quality inspection
Inspection, Improving The Quality of Products.
Specifically, the invention provides a kind of method controlling product quality with standard, exist for enterprise
Parts drawing design phase, parts production phase and quality inspection stage carry out standard control, described mark
Standard at least includes that standard No., title, standard content, described enterprise are provided with for standard management
Standard management equipment, the design equipment for designer being connected with described standard management equipment respectively,
Production management equipment for producers and the management equipment of the quality inspection for quality inspection personnel, described
Method comprises the steps,
Step A, basic standard data collection steps, for being made product and this product of described enterprise
The drawing of parts be acquired by described standard management equipment with the information of corresponding standard, should
Step includes: for each product, gathers the product figure number of described product, name of product information, gathers
Each parts title and zero that the parts group name that described product is used, described parts group comprise
Parts figure number information, gathers described parts institute accepted standard number, title, standard content and mark
Quasi-employing temporal information, is denoted as using by its accepted standard number for described parts;
Step B, normal data management process, for after completing step A, at the product of described standard
The described product affected is managed by the life cycle give birth to, change, substitute and substituted, withered away,
This step includes:
When described parts are to when should have multiple standard No., and described standard management equipment is according to the employing of standard
Time, limit using time preceding standard No. to be denoted as or discarded, time posterior standard will be used
Number it is denoted as using,
Step C, design data management step, for providing production drawing by described design equipment
Designer is pointed out by the design phase according to the data variation in step B, and this step includes:
When described parts accepted standard changes, carry out the behaviour in step B at described standard management equipment
After work, described design equipment sends prompting,
Step D, produces management of blueprint step, and described production management equipment is according to the production figure on production line
The parts figure number of paper or parts title are in described standard management equipment query standard No., and will inquire
Standard No. compare with the standard No. on described production drawing, as result is inconsistent, send alarm.
Step E, step, the described parts of described quality inspection management equipment quality inspection as required are verified in quality inspection
The parts figure number producing drawing used or parts title are in described standard management equipment query standard
Number, and the standard No. inquired is compared with the standard No. on this production drawing, as result is inconsistent
Then send alarm.As consistent in result the most further from as described in standard management equipment transfer as described in standard No. corresponding
Standard content information, by the technological parameter in described standard content information, sized data require and quality inspection
Measurement data compares, the data demand in standard content information as described in quality inspection measurement data does not meets
Then send alarm.
Preferably, described step C farther includes following steps, when carrying out parts layout design,
Described design equipment, according to the parts figure number of this drawing, obtains described zero from described standard management equipment
Standard No. corresponding to part figure number, standard content, when the data in described parts drawing are beyond from described mark
In quasi-management equipment during the data area in the standard content of acquisition, described design equipment sends warning.
For solving above-mentioned technical problem, the present invention proposes a kind of method controlling product quality with standard,
The drawing of the parts that product and this product of enterprise are used is acquired whole with corresponding standard information
Reason, carries out normal data management in units of parts, when standard changes, sends out designer in time
Go out information, designer can be made in time to be adjusted producing drawing, change, producers
Comparing, when producing, the data accuracy producing drawing, quality inspection personnel is when carrying out quality inspection, it is possible to
Accurately obtain by standard corresponding to quality inspection parts, and according to standard content accurately, parts are carried out matter
Inspection, such that it is able to guarantee carrying out and implementing of standard from design, production, the links of quality inspection, ensures institute
The management quality of the parts produced.
Furthermore, it is understood that a kind of method controlling product quality with standard proposed by the invention, first at mark
Quasi-management equipment by the way of either automatically or manually to product, parts, the information of standard,
Such as by modes such as scanner, CD, Network Synchronization to existing product, parts, the letter of standard
Breath is acquired, and then when the standard change that parts are used, that is to say and sets in described standard management
In Bei, the use state of standard, to when should have multiple standard No., can either automatically or manually be entered by parts
Row change, and on design equipment by the mode such as pop-up, sound by the change of standard corresponding for parts
Information notifies designer, and designer just can inquire about the detailed of the standard after parts change further
Content thus be adjusted producing drawing, change, additionally, described design equipment (such as Automatic Drawing
Instrument) standard content corresponding with parts figure number can also be obtained from described standard management equipment, in design
When personnel carry out layout design, if the data in parts drawing (such as element size data) surpass
When going out data (such as sized data) scope in the standard content obtained from described standard management equipment,
Described design equipment can send audible alarm, or informs that designer's data do not meet in pop-up mode
The requirement of standard, it might even be possible to force not allow described design equipment to provide these data of printing and do not meet standard
The drawing of requirement.Thus can be implemented in the standard of parts drawing design phase to control.
In the production phase, described production management equipment (such as Digit Control Machine Tool) can according to produce drawing from
Described standard management equipment obtains the standard No. corresponding with parts figure number, when from described standard management equipment
When the standard No. obtained is inconsistent with the standard No. produced on drawing, described production management equipment can send
Sound or pop-up mode alert, and further, described production management equipment (such as Digit Control Machine Tool) is also
The standard content corresponding with parts figure number can be obtained from described standard management equipment according to producing drawing,
If the data in production drawing (such as element size data) are beyond from described standard management equipment
Obtain standard content in data (such as sized data) scope time, described production management equipment is permissible
Send audible alarm, or inform the non-compliant requirement of producers' data in pop-up mode, even
Described production management equipment can be forced to stop producing.Thus can be implemented in the parts production phase
Standard controls.
In the quality inspection stage, described quality inspection management equipment (such as read the equipment of qualimeter data, or
The equipment of person's record length measurement data) can the production drawing that used of the parts of quality inspection as required
The standard No. corresponding with parts figure number is obtained, when setting from described standard management from described standard management equipment
When the standby standard No. obtained is inconsistent with the standard No. on this production drawing, described quality inspection management equipment is permissible
Sending sound or pop-up mode alerts, further, described quality inspection management equipment can also be raw according to this
Produce drawing and obtain the standard content corresponding with parts figure number from described standard management equipment, if quality detection
The data (such as element size data) of amount are beyond in the standard obtained from described standard management equipment
During data (such as sized data) scope in appearance, described quality inspection management equipment can send audible alarm,
Or inform the non-compliant requirement of producers' data in pop-up mode.Thus can be implemented in zero
The standard in parts quality inspection stage controls, thus products quality guarantee.
Detailed description of the invention
In order to the technical characteristic of the present invention, purpose and effect are more clearly understood from, existing detailed description
The detailed description of the invention of the present invention.
The invention provides a kind of method controlling product quality with standard, be used for enterprise at part diagram
Paper design phase, parts production phase and quality inspection stage, namely the design department of enterprise provides confession
Shop floor worker use production drawing, and the shop floor worker of production division of enterprise according to produce drawing carry out
Parts produce, and the production drawing of the parts of the quality inspection personnel of enterprise's quality testing department quality inspection as required enters
Carrying out standard control during row quality inspection, described standard at least includes standard No., title, standard content,
Method with standard control design case the most provided by the present invention, for parts layout design and
When carrying out parts production, quality inspection according to drawing, by mark corresponding with these parts for parts drawing figure number
The information such as the standard No. of standard, title, standard content are compared, are managed, thus realize designing rank
The standard of section, production phase and quality inspection controls, and described enterprise is provided with the standard management for standard management
Equipment, the design equipment for designer that is connected with described standard management equipment respectively, for producing
The production management equipment of librarian use and the quality inspection for quality inspection personnel manage equipment, described standard pipe
Reason equipment can be the blade type clothes being provided with windows operating system, IIS software, oracle database
Business device or PC server, described design equipment can be the PC being provided with the softwares such as autocad, or
Person is the equipment such as autoplotter, and described production management equipment can be Digit Control Machine Tool or automatic assembly line
Controlling the equipment such as main frame, described quality inspection management equipment can be the main frame being connected to electrical measurement tools, example
As being connected to the PC of qualimeter or device for measuring length, described method comprises the steps,
Step A, basic standard data collection steps, for used the product of enterprise and this product
The drawing of parts is acquired with corresponding standard information by described standard management equipment, is arranged, should
Step includes: for each product of enterprise, gather the product figure number of described product, name of product information,
Gather the parts group name that described product used, each parts title that described parts group comprises
And parts figure number information, gather described parts institute accepted standard number, title, standard employing
Time and standard content information, be denoted as making by the use state of its accepted standard for described parts
With;
At the parts used by described standard management equipment collection arrangement enterprise product and this product
During the standard information of drawing and correspondence, 3 data can be designed in described standard management equipment
Storehouse, the standard database of a storage normal data, its storage standard No., title, standard use
Time and standard content information and the incidence relation between them, the product number of storage product data
According to storehouse, its storage name of product, product figure number, parts group, parts title and parts figure number
Information and between incidence relation, one storage standard and product between relation, the pass coefficient of state
According to storehouse, it is for storing the use status information of the standard in described standard database and described product data
The incidence relation of the standard No. in each parts title/parts figure number and described standard database in storehouse.This
Sample just can utilize the management program of the programming language level of organization data such as java easily, it is simple to after realization
The standard management logic continued, naturally it is also possible to be to be respectively provided with 3 tables of data, example in a database
As one storage normal data normal data table, one storage product data product data sheet, one
Relation between storage standard and product, the relation database table of state, store above-mentioned data respectively.
In described standard database, it is also possible to gather the issuing time of described standard further, thus
After can recording the issue of new standard easily, enterprise determines that the standard using new standard uses time and issue
The difference of time and decision process, such that it is able to know that the product of enterprise uses new standard production, manufacture
Time is delayed relative to the issuing time of new standard.
Used by the part group that enterprise's basic standard data collection steps can be used according to product is checked
Part drawing (includes part design drawing, part prose drawing etc.), thus can be artificial during checking
Gather the product figure number of described product, name of product information, gather parts group that described product used,
Each parts title that described parts group comprises and parts figure number information, and by these Data Enters
To described product database;Simultaneously by gather described parts institute accepted standard number, title,
Standard uses time and standard content Data Enter to described standard database;Simultaneously by normal data and product
The incidence relation of product data is entered into described linked database, and by standard in described linked database
Use state is denoted as using;
Certainly, gatherer process can also be automatically performed, it is, for example possible to use existing drawing is entered by scanner
Row information scanning, in the case of coordinating OCR tool to use, can simplify the information input of staff
Work.Directly the renewal optical disc information of standard management tissue can also be input to described standard by CD-ROM drive
Management equipment.Described standard management equipment even can be connected to the master of standard management tissue by network
Machine or enterprise's ERP main frame, such that it is able to automatically update situation of change and the enterprise pair of standard by network
(such as company manager's decision-making standard is in the employing of certain parts for the result of decision of parts employing standard
Time).
Thus can utilize programming language establishment management program and the administration interfaces such as java easily, such as
Use B/S framework to work out administration interface based on WEB and just can conveniently carry out follow-up normal data pipe
Science and engineering is made.
Such as, there is a model aero-engine in certain aero-engine enterprise, and its name of product is that HS1A sends out
Motivation, product figure number is HS1A, and it includes several parts groups, and one of them parts group is
HS1A.00, this parts group includes several parts, and one of them parts figure number is
HS1A00001, the entitled stopper ring of these parts, this parts accepted standard number is
GB/T702-1986, title is " rolled steel bar size, profile, weight and permission ", and standard is issued
Time is on October 1st, 1986, and standard uses the time to be January 1 nineteen ninety, by setting part
The examination of meter figure, can be by HS1A engine, HS1A, HS1A.00, HS1A00001, stopper ring
Typing product database, by GB/T702-1986, " rolled steel bar size, profile, weight and permission ",
" on October 1st, 1986 ", " January 1 nineteen ninety " and the detailed content typing criterion numeral of this standard
According to storehouse, by the incidence relation of GB/T702-1986 Yu HS1A00001/ stopper ring, and GB/T702-1986
The status information typing linked database being currently being used.Further, it is also possible in described standard database
" remarks " entry is set, the reason that uses in January 1 nineteen ninety for record standard and or enterprise determine
Plan uses the process of this standard.
So, the management program and the administration interface that utilize the programming language establishments such as java just can be inquired about at any time
The standard service condition of HS1A engine.
Step B, normal data management process, for after completing step A, at the mark of described enterprise
Accurate generation, the institute of the life cycle changing, substitute and being substituted, the wither away described enterprise on being affected
State product to be managed, when enterprise needs to determine to become standard according to higher level request or self production
More, substitute time, i.e. may utilize the data in step A and carry out normal data management, this step includes:
When described parts are to when should have multiple standard No., and described standard management equipment is according to the employing of standard
Time, limit using time preceding standard No. to be denoted as or discarded, time posterior standard will be used
Number it is denoted as using,
The use state of standard is denoted as limiting, and may be used for referring in certain special cases, such as, need
When old product is carried out part replacement, need to be used for the parts of old product according to this standard production.
The use state of standard is denoted as discarding, and may be used for referring to that these parts are in design from now on, production
In not in use by this standard, and need to use new standard.
Such as, determine that HS1A00001/ stopper ring needs to begin to use in January 1 nineteen ninety-five when enterprise
Standard GB/T702-1992, in described standard management equipment, HS1A00001/ stopper ring is for same mark
Quasi-title is just to having two different standard No. of GB/T702-1986 with GB/T702-1992, described mark
Quasi-management equipment by the standard of comparison GB/T702-1986 use January 1 nineteen ninety time and
The standard of GB/T702-1992 uses January 1 nineteen ninety-five time, will at described linked database
The use state of GB/T702-1986 is denoted as limiting or discarded, and is denoted as making by GB/T702-1992
With,
Thus can inquire the most easily from when starting the use of HS1A00001/ stopper ring
New standard GB/T702-1992.Also the standard that parts are used can the most just be inquired about the most easily
Change or situation about replacing, can also inquire about the generation of each standard the most easily simultaneously, change, disappear
Die state.
If enterprise determine parts use standard change after, the title of the standard after change with before changing
Title different, then can be in described standard management equipment, the manual use state to standard is entered
Line pipe is managed, in order to be managed standard information.
Step C, design data management step, for setting by described design the design department of enterprise
Designer is pointed out by the standby design phase providing production drawing according to the data variation in step B,
This step includes:
When described parts accepted standard changes, carry out the behaviour in step B at described standard management equipment
After work, described design equipment sends prompting to designer.
Described design equipment can be connected by network with described standard management equipment, and described information can
Showing on described design equipment in the way of by pop-up window, the content of described information can be wrapped
Include described parts title, described parts figure number, thus can the most efficiently designer be entered
Row information reminding, designer can become from described standard management equipment query accordingly according to information
The detailed content of the standard more or after replacement, is adjusted producing drawing or revises, and in new life
Become produces the standard No. after indicating used change in drawing.
Described prompting can also be to carry out pointing out or flash lamp sends sudden strain of a muscle by buzzer sound of sounding a buzzer
Optical signal is pointed out, after designer receives sound or visual cues, and can be from described standard management
Equipment carries out standards change inquiry, knows the parts that standards change is affected, and to corresponding parts
Drawing is adjusted or revises, and after newly-generated producing indicates used change in drawing
Standard No..
Such line producers can produce according to the newly-generated production drawing that design department issues and meet
The parts of the standard after change or replacement.Thus ensure that the standard of renewal can be implemented enforcement.
Step D, produces management of blueprint step, and described production management equipment is according to the production figure on production line
The parts figure number of paper or parts title are in described standard management equipment query standard No., and will inquire
Standard No. compare with the standard No. on described production drawing, as result is inconsistent, send alarm.
Further, described production management equipment (such as Digit Control Machine Tool or automatic assembly line control main frame)
The standard content corresponding with parts figure number or parts title can be obtained from described standard management equipment,
If the data in the parts drawing on production line (such as element size data) are beyond from described mark
In quasi-management equipment during data (such as sized data) scope in the standard content of acquisition, described production
Management equipment can send audible alarm, or informs that producers' data do not meet standard in pop-up mode
Requirement, it might even be possible to force described production management equipment stop produce.Thus can be implemented in zero
The standard of part production phase controls.
Described production management equipment can include a warning device.This warning device can be buzzer or
Person's flash lamp, so, when described production management equipment sends warning information, it is possible to send sound or
Person's optics alarm signal attracts producers to pay close attention to.
Step E, step, the described parts of described quality inspection management equipment quality inspection as required are verified in quality inspection
The parts figure number producing drawing used or parts title are in described standard management equipment query standard
Number, and the standard No. inquired is compared with the standard No. on this production drawing, as result is inconsistent
Then send alarm.As consistent in result the most further from as described in standard management equipment transfer as described in standard No. corresponding
Standard content information, by the technological parameter in described standard content information, sized data require and quality inspection
Measurement data compares, the data demand in standard content information as described in quality inspection measurement data does not meets
Then send alarm.
When the parts product that producers are produced by quality inspection personnel carries out quality inspection, can manually or
Person is connected to described standard management equipment by described quality inspection management equipment automatically, makes according to described product
Produce the parts figure number of drawing or parts name query standard No., and the standard No. that will inquire
Compare with the standard No. on described production drawing, as result is inconsistent, design department's root can be notified
Modify according to the data variation of step B.As consistent in result the most further from as described in standard management equipment adjust
Take the standard content information of described standard, by the technological parameter in described standard content information, sized data
Require that the quality inspection measurement data obtained with described quality inspection management equipment compares, as data symbols is measured in quality inspection
Close the data demand in described standard content information, then complete quality inspection, as quality inspection measurement data does not meets institute
State the data demand in standard content information and then can notify that production division improves.
Described quality inspection management equipment can include a warning device.This warning device can be buzzer or
Person's flash lamp, so, described quality inspection management equipment send warning information time, it is possible to send sound or
Person's optics alarm signal attracts quality inspection personnel to pay close attention to.
In a preferred embodiment, described step C farther includes following steps, is carrying out parts
During layout design, described design equipment is according to the parts figure number of this drawing, from described standard management equipment
Obtain standard No. corresponding to described parts figure number, standard content, the data in described parts drawing
When exceeding the data area in the standard content obtained from described standard management equipment, described design equipment
Send warning.
Described design equipment (such as autoplotter) can obtain and zero from described standard management equipment
The standard content that part figure number is corresponding, when designer carries out layout design, if in parts drawing
Data (such as element size data) are beyond in the standard content obtained from described standard management equipment
Data (such as sized data) scope time, described design equipment can send audible alarm, or with
Pop-up mode informs the non-compliant requirement of designer's data, it might even be possible to force do not allow described in set
Meter equipment provides the drawing printing the non-compliant requirement of these data.Thus can be implemented in parts
The standard in layout design stage controls.
In a preferred embodiment, described design equipment includes a warning device.This warning device can
To be buzzer or flash lamp, its be mainly used according to described standard management equipment issue described in relate to setting
Standby prompting sends alarm signal and pays close attention to attraction designer, or finds zero at described design equipment
The data of parts drawing and the number in the standard content of the corresponding standard obtained from described standard management equipment
According to when not being inconsistent, send sound or optics alarm signal attracts designer to pay close attention to.
In a preferred embodiment, record product batch is believed with parts batch further in step
Breath, so, in stepb, after described parts accepted standard changes, it is possible at described mark
Quasi-management equipment records product batches corresponding to the standard after change and parts batch, hereafter, in step
In rapid C, designer is producing sign parts batch information on drawing further.So can be favourable
In Product Assembly or check and accept the product of different batches and corresponding zero that different time sections produced by link
Part institute accepted standard carries out retrieving, checking.
In a preferred embodiment, in step, the adduction relationship between each standard is recorded further.
Owing to there may be adduction relationship between the standard of different stage, such as certain bolt uses enterprise's mark, but
This enterprise is designated as the GB quoted, and so when this GB changes, this enterprise mark also should do corresponding change, can
With the adduction relationship between described linked database record different stage standard, so, when be cited
When standard changes, its normative reference by impact can be known, described product can be passed through further
Database knows affected components information, such that it is able to notice design department carries out producing drawing in time
Update, ensure standard implementation.
In a preferred embodiment, in step, the production unit of described parts is recorded further
Information.So, life can be worked as in the production unit information of parts described in described product database record
Produce after drawing updates and can be communicated to corresponding production unit timely, it is ensured that line producers are according to more
Production drawing after Xin produces, and ensures that the standard updated can be implemented enforcement.
The present invention proposes a kind of method controlling product quality with standard, product and this product to enterprise
The drawing of the parts used is acquired with corresponding standard information arranging, and enters in units of parts
Column criterion data management, when standard changes, sends information to designer in time, can be timely
Make designer be adjusted producing drawing, change, producers when producing to producing drawing
Data accuracy is compared, and quality inspection personnel is when carrying out quality inspection, it is possible to accurately obtain by quality inspection parts
Corresponding standard, and parts are carried out quality inspection according to standard content accurately, such that it is able to from design,
Produce, the links of quality inspection guarantees carrying out and implementing of standard, ensures the product matter of the parts produced
Amount.
Although it will be appreciated by those skilled in the art that the present invention is to retouch according to the mode of multiple embodiments
State, but the most each embodiment only comprises an independent technical scheme.Specification so describes
For the sake of being only used to understand, specification should be understood by those skilled in the art as an entirety,
And technical scheme involved in each embodiment regarded as can be in the way of being mutually combined into different embodiment
Understand protection scope of the present invention.
The foregoing is only the schematic detailed description of the invention of the present invention, be not limited to the model of the present invention
Enclose.Any those skilled in the art, is made on the premise of without departing from the design of the present invention and principle
Equivalent variations, revise and combine, the scope of protection of the invention all should be belonged to.
Claims (6)
1. the method controlling product quality with standard, standard control is carried out in parts drawing design phase, parts production phase and quality inspection stage for enterprise, described standard at least includes standard No., title, standard content, described enterprise is provided with the standard management equipment for standard management, the design equipment for designer being connected with described standard management equipment respectively, the production management equipment for producers and the quality inspection for quality inspection personnel and manages equipment, described method comprises the steps
Step A, basic standard data collection steps, the drawing of the parts for the product of described enterprise and this product being used is acquired by described standard management equipment with the information of corresponding standard, this step includes: for each product, gather the product figure number of described product, name of product information, gather the parts group name that described product is used, each parts title that described parts group comprises and parts figure number information, gather described parts institute accepted standard number, title, standard content and standard use temporal information, it is denoted as using by its accepted standard number for described parts;
Step B, normal data management process, for after completing step A, the described product affected is managed by generation, the life cycle that changes, substitute and substituted, wither away in described standard, and this step includes:
When described parts are to when should have multiple standard No., and described standard management equipment, according to the employing time of standard, limits using time preceding standard No. to be denoted as or discarded, and uses using time posterior standard No. to be denoted as,
Step C, design data management step, for pointing out designer according to the data variation in step B in the design phase being provided production drawing by described design equipment, this step includes:
When described parts accepted standard changes, after described standard management equipment carries out the operation in step B, described design equipment sends prompting, when carrying out parts layout design, described design equipment is according to the parts figure number of this drawing, standard No. corresponding to described parts figure number, standard content is obtained from described standard management equipment, when the data in described parts drawing are beyond the data area in the standard content obtained from described standard management equipment, described design equipment sends warning
Step D, produce management of blueprint step, described production management equipment is according to producing the parts figure number of drawing or parts title in described standard management equipment query standard No. on production line, and the standard No. inquired is compared with the standard No. on described production drawing, as result is inconsistent, send alarm
Step E, step is verified in quality inspection, the parts figure number of the production drawing that the described parts of described quality inspection management equipment quality inspection as required use or parts title are in described standard management equipment query standard No., and the standard No. inquired is compared with the standard No. on this production drawing, as result is inconsistent, send alarm, as consistent in result the most further from as described in standard management equipment transfer as described in standard content information corresponding to standard No., by the technological parameter in described standard content information, sized data requires to compare with quality inspection measurement data, data demand in standard content information as described in quality inspection measurement data does not meets then sends alarm.
Method the most according to claim 1, it is characterised in that described design equipment includes a warning device.
Method the most according to claim 2, it is characterised in that described warning device is a buzzer.
Method the most according to claim 1, it is characterised in that in step, further record product batch and parts batch information.
Method the most according to claim 1, it is characterised in that in step, records the adduction relationship between each standard further.
Method the most according to claim 1, it is characterised in that in step, records the production unit information of described parts further.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310289459.3A CN103455845B (en) | 2013-07-11 | 2013-07-11 | A kind of method controlling product quality with standard |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310289459.3A CN103455845B (en) | 2013-07-11 | 2013-07-11 | A kind of method controlling product quality with standard |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103455845A CN103455845A (en) | 2013-12-18 |
CN103455845B true CN103455845B (en) | 2016-08-31 |
Family
ID=49738184
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310289459.3A Active CN103455845B (en) | 2013-07-11 | 2013-07-11 | A kind of method controlling product quality with standard |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103455845B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107025510A (en) * | 2016-02-02 | 2017-08-08 | 深圳市检验检疫科学研究院 | A kind of appraisal procedure of homogeneity of product |
CN108197310B (en) * | 2018-01-31 | 2021-06-01 | 杭州优工品科技有限公司 | Industrial part management method and device based on big data |
CN108228891B (en) * | 2018-01-31 | 2021-03-02 | 杭州优工品科技有限公司 | Data processing method and device supporting interchange substitution standard |
CN112381438A (en) * | 2020-11-24 | 2021-02-19 | 北京三维天地科技股份有限公司 | Product quality and standard matching model based on fuzzy similarity algorithm |
CN113360508A (en) * | 2021-04-28 | 2021-09-07 | 浙江宏恩网络科技有限公司 | Product quality control management method and device, storage medium and electronic equipment |
CN114935703B (en) * | 2022-07-26 | 2022-11-29 | 成都市克莱微波科技有限公司 | Automatic testing method, device and system for frequency conversion assembly |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101436200A (en) * | 2008-12-25 | 2009-05-20 | 上海汽车集团股份有限公司 | Standardized information management system and standard updating method thereof |
CN101470851A (en) * | 2007-12-26 | 2009-07-01 | 上海网环信息科技有限公司 | Method for setting inspection items and controlling inspection results in inspection standard |
CN102855590A (en) * | 2012-10-09 | 2013-01-02 | 南京市标准化研究院 | Standard self-service trusteeship system used in laboratory |
-
2013
- 2013-07-11 CN CN201310289459.3A patent/CN103455845B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101470851A (en) * | 2007-12-26 | 2009-07-01 | 上海网环信息科技有限公司 | Method for setting inspection items and controlling inspection results in inspection standard |
CN101436200A (en) * | 2008-12-25 | 2009-05-20 | 上海汽车集团股份有限公司 | Standardized information management system and standard updating method thereof |
CN102855590A (en) * | 2012-10-09 | 2013-01-02 | 南京市标准化研究院 | Standard self-service trusteeship system used in laboratory |
Also Published As
Publication number | Publication date |
---|---|
CN103455845A (en) | 2013-12-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103455845B (en) | A kind of method controlling product quality with standard | |
CN110599103B (en) | Production management subsystem based on intelligent manufacturing MES system | |
CN110580026A (en) | intelligent manufacturing MES system | |
CN106971273B (en) | Transformer substation acceptance workflow control system and control method with intelligent alarm prompt | |
CN105868373B (en) | Method and device for processing key data of power business information system | |
CN110428112A (en) | A kind of dual prevention mechanism management system of enterprise based under internet+mode | |
CN107844875B (en) | Green product management system and method | |
CN111930088A (en) | Edge management system | |
CN101770612A (en) | Device defect management module of EAM (Enterprise Asset Management) system in power plant | |
CN101763582A (en) | Scheduled overhaul management module for EAM system of power plant | |
CN101763581A (en) | EAM system of power station and report forms management module thereof | |
CN102024188A (en) | Equipment accounting management module of EAM system of power plant | |
CN111462886A (en) | Full life cycle real-time online management system for medical equipment | |
CN114021971A (en) | Comprehensive evaluation system, method and storage medium for expressway operation and maintenance management | |
CN101763580A (en) | Equipment state overhaul management module for EAM system of power plant | |
CN109344981A (en) | A kind of detection device management system based on Internet of Things | |
CN101763583A (en) | Work sheet management module for EAM system of power plant | |
CN101794106A (en) | Quality control system, quality control apparatus, and quality control method | |
CN103389698B (en) | Method for controlling production through standards | |
CN112258053A (en) | Method for producing formula food for special medical application by using manufacturing execution system | |
CN101763584A (en) | Knowledge information bank management module for EAM system of power station | |
CN109146302A (en) | Overhaul of the equipments task processing method and system | |
CN115186977A (en) | Method and system for monitoring task abnormity of automobile part research and development project | |
CN103455870B (en) | A kind of method with standard control design case | |
CN112508314A (en) | Uygur medicine manufacturing execution system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 412002 Dong Jiaduan, Zhuzhou, Hunan Patentee after: China Hangfa South Industrial Co. Ltd. Address before: 412002 Dong Jiaduan, Zhuzhou, Hunan Patentee before: China Southern Airlines Industry (Group) Co., Ltd. |