WO2024034058A1 - Work management system and work management method - Google Patents

Work management system and work management method Download PDF

Info

Publication number
WO2024034058A1
WO2024034058A1 PCT/JP2022/030577 JP2022030577W WO2024034058A1 WO 2024034058 A1 WO2024034058 A1 WO 2024034058A1 JP 2022030577 W JP2022030577 W JP 2022030577W WO 2024034058 A1 WO2024034058 A1 WO 2024034058A1
Authority
WO
WIPO (PCT)
Prior art keywords
information
load state
charge
work
construction
Prior art date
Application number
PCT/JP2022/030577
Other languages
French (fr)
Japanese (ja)
Inventor
一生 冨澤
研一 佐藤
Original Assignee
三菱電機ビルソリューションズ株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三菱電機ビルソリューションズ株式会社 filed Critical 三菱電機ビルソリューションズ株式会社
Priority to PCT/JP2022/030577 priority Critical patent/WO2024034058A1/en
Publication of WO2024034058A1 publication Critical patent/WO2024034058A1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management

Definitions

  • the present disclosure relates to a construction management system and a construction management method.
  • a construction manager who manages construction needs to understand the work load status of each worker and the progress status of multiple jobs being performed simultaneously. On top of that, the construction manager needs to take measures to ensure that all work is completed safely and by the deadline while maintaining the quality of the work.
  • the construction manager grasps the workload of the workers by holding morning meetings, interviewing the person in charge of work, checking daily work reports, etc., and also monitors the progress of the work by visiting the work site and checking visually and checking site photos. I understand the situation. Based on the situation ascertained in this way, the construction manager increases or replaces workers, reviews the work process, etc.
  • the present disclosure has been made to solve such problems, and the purpose of the present disclosure is to provide a construction management system and a construction management method that allow even inexperienced construction managers to efficiently manage construction.
  • the goal is to provide the following.
  • the construction management system of the present disclosure is a system that manages the construction of a construction project consisting of multiple steps handled by multiple personnel.
  • the construction management system includes a control unit that generates a construction schedule, and a display unit that displays the schedule.
  • the control unit determines a load state indicating the workload of the plurality of persons in charge based on information including schedule information of the plurality of persons in charge.
  • the display unit displays schedule information and load status in association with the processes each of the plurality of persons in charge is in charge of.
  • the construction management method of the present disclosure is a method for managing the construction of construction work consisting of multiple steps handled by multiple personnel.
  • the construction management method includes a step of generating a construction schedule and a step of displaying the schedule.
  • the generating step includes determining a load state indicating the workload of the plurality of persons in charge based on information including schedule information of the plurality of persons in charge.
  • the step of displaying includes a step of displaying schedule information and load status in association with the processes each of the plurality of persons in charge is in charge of.
  • FIG. 1 is a diagram showing a hardware configuration of a construction management system according to a first embodiment. It is a figure showing a functional block diagram in a construction management system. It is a flowchart of main processing. It is a flowchart of display information generation processing. It is a figure showing an example of a process chart. It is a figure showing an example of a process chart. It is a figure showing a functional block diagram in a construction management system concerning a 2nd embodiment. It is a flowchart of main processing. It is a figure showing an example of a process chart.
  • FIG. 3 is a diagram for explaining a learning data set.
  • FIG. 3 is a diagram for explaining a learning data set. It is a flowchart of learning processing. It is a flowchart of route display processing concerning a modification. It is a figure showing an example of a process chart concerning a modification.
  • FIG. 1 is a diagram showing the hardware configuration of a construction management system 1 according to the first embodiment.
  • the construction management system 1 is a system that manages the construction of a construction project consisting of a plurality of steps. A plurality of persons in charge (also referred to as "workers”) are in charge of these plurality of steps.
  • FIG. 5 shows a process chart showing a plurality of steps in new air conditioning equipment construction work to install new air conditioning equipment in Building X.
  • companies A to F personnel in charge of companies A to F are in charge of each process.
  • person in charge may refer to each person in charge of the companies (Companies A to F) that undertake each process as described above, or may refer to each person in charge of the companies that undertake each process (Companies A to F). It may also indicate the company itself.
  • the number of persons in charge (workers) in charge of one process may be one or more.
  • the construction management system 1 includes a server 100 and a plurality of terminals 200.
  • the server 100 performs processes such as generating a process chart.
  • the plurality of terminals 200 are composed of a terminal used by a construction manager (also simply referred to as a "manager") who manages construction, and a plurality of terminals used by a plurality of persons in charge of a plurality of construction steps. Ru.
  • the construction manager manages the site so that the construction work is completed by the deadline, while keeping track of the workload of each person in charge of each step of the construction work and the progress of each work.
  • a terminal 200 used by a construction manager, a terminal 200 used by worker K1, and a terminal 200 used by worker K2 are shown.
  • the construction management system 1 is configured to be connectable to the schedule management system 400.
  • the schedule management system 400 is a system that manages the schedules of a plurality of people in charge.
  • Each person in charge accesses the schedule management system 400 from the terminal 200 that he/she uses, and manages his/her own schedule using the schedule management software provided by the schedule management system 400.
  • the schedule management software may be used by starting software installed on the terminal 200 in advance, or may be used via a browser started on the terminal 200.
  • Each person in charge specifies the date and time and registers their own schedule in the schedule management system 400 using schedule management software. Users who are permitted to view (for example, users within the company) can access the schedule management system 400 and view the registered schedules.
  • the server 100 is configured to be able to access the schedule management system 400 and obtain registered schedules.
  • the schedule information includes schedules unrelated to the construction work managed by the construction manager.
  • the server 100 can access the schedule management system 400 and obtain the schedules registered by the workers (persons in charge) of companies A to F.
  • This schedule includes schedules unrelated to the construction of new air conditioning equipment in Building X.
  • it may be construction schedule information for Building Y, which is different from Building X, or it may be a schedule for an internal meeting, or it may be any schedule.
  • companies A to F are not limited to using the same schedule management system (schedule management system 400), but each company may use a different schedule management system. In this case, it is assumed that the server 100 can access these multiple schedule management systems and acquire schedule information.
  • the server 100 includes a control section 111, a storage section 112, and a communication section 113. These are communicably connected to each other via a bus.
  • the control unit 111 is, for example, a CPU (Central Processing Unit).
  • the storage unit 112 includes a ROM (Read Only Memory), a RAM (Random Access Memory), and a nonvolatile storage device (for example, a HDD (Hard Disk Drive) or an SSD (Solid State Drive)).
  • the storage unit 112 stores a learning data set 160, a learned model 163, a learning data set 170, and a learned model 173, which will be described later.
  • the control unit 111 loads programs stored in the ROM into the RAM and executes them to realize various functions of the server 100.
  • the control unit 111 performs processing such as generating a work schedule.
  • the ROM stores a program in which processing procedures of the server 100 are written.
  • the RAM serves as a work area when the control unit 111 executes a program, and temporarily stores programs and data used when executing the program.
  • the server 100 can be connected to the terminal 200 and the schedule management system 400 wirelessly or by wire via the communication unit 113.
  • the terminal 200 may be, for example, a mobile terminal such as a smartphone or a tablet, or a personal computer such as a notebook computer or a desktop computer.
  • the terminal 200 includes a control unit (CPU) 211, a storage unit 212, a communication unit 213, an input unit 220, and a display unit 221. These are communicably connected to each other via a bus.
  • the storage unit 212 may be configured to include a ROM, a RAM, and a nonvolatile storage device such as an HDD or an SSD.
  • the control unit 211 loads programs stored in the ROM into the RAM and executes them to realize various functions of the terminal 200.
  • the ROM stores a program in which processing procedures for the terminal 200 are written.
  • the terminal 200 is connectable to the server 100 and the schedule management system 400 via the communication unit 213.
  • the input unit 220 receives input from the user.
  • the input unit 220 is, for example, a touch panel, but may also be a keyboard or a mouse.
  • the display unit 221 displays various information.
  • the display unit 221 is, for example, a liquid crystal display or a display.
  • the display unit 221 can display the process chart generated by the control unit 111. Note that the process chart may be configured to be viewable only on the terminal 200 used by the administrator, or may be configured to be viewable on the terminal 200 used by each worker.
  • the construction management system 1 may be a device that integrates a server 100 and a terminal 200 used by an administrator.
  • the display unit (display) included in the apparatus is configured to display the process chart generated by the control unit (CPU) included in the apparatus.
  • the construction management system 1 may be configured to include the schedule management system 400, or may be configured to include only the server 100 and the terminal 200 used by the administrator.
  • FIG. 2 is a diagram showing a functional block diagram of the construction management system 1.
  • the control unit 111 of the server 100 can execute the processing executed by the second estimation unit 121 and the generation unit 123.
  • the second estimation unit 121 acquires schedule information of a plurality of people in charge of construction from the schedule management system 400.
  • the second estimation unit 121 acquires second input information, which will be described later, from the storage unit 112.
  • the second estimation unit 121 determines the load state indicating the workload of the plurality of persons in charge based on the schedule information of the plurality of persons in charge and the second input information.
  • the load state includes a high load state.
  • a "high load state” is a state in which work delays are expected in the target process.
  • the second input information is information necessary to determine the load state. The second input information and the process of determining the load state will be explained in detail using FIGS. 10 and 12.
  • the generation unit 123 acquires process information, which will be described later, from the storage unit 112.
  • the generation unit 123 generates display information including a process chart based on process information, load status, and the like.
  • the display unit 221 of the terminal 200 displays display information including the generated process chart.
  • FIG. 3 is a flowchart of main processing.
  • the processing shown in this flowchart may be activated based on a display request from the terminal 200, for example.
  • the server 100 acquires schedule information from the schedule management system 400 in S101.
  • the server 100 acquires the second input information from the storage unit 112 in S102.
  • the server 100 inputs the schedule information and the second input information to the learned model 163 (FIG. 10), and acquires the load state output from the learned model 163.
  • the server 100 acquires process information from the storage unit 112 in S104.
  • the process information is various information set regarding multiple processes in the target construction. For example, in the example shown in Figure 5, the construction name (new construction of air conditioning equipment in building This is the information necessary to generate a process chart, such as 1 day to 2 days).
  • the server 100 executes display information generation processing (FIG. 4) to generate display information (work schedule, etc.).
  • the server 100 outputs display information (work schedule, etc.) to the display unit 221, and ends the main processing.
  • main processing is executed in response to a display request from the terminal 200, and display information generated as a result is acquired by the terminal 200 via the communication unit 213 and displayed on the display unit 221.
  • Examples of the process chart displayed on the display unit 221 are shown in FIGS. 5 and 6.
  • FIGS. 5 and 6 the flowchart of the display information generation process will be explained using FIG. 4, and the process charts shown in FIGS. 5 and 6 will be explained.
  • FIG. 4 is a flowchart of display information generation processing.
  • the server 100 acquires schedule information, load information, process information, etc. in S201.
  • a process chart is generated based on this information.
  • FIG. 5 is a diagram showing an example of a process chart. As shown in FIG. 5, the construction name is displayed at the top of the process chart 91 (hereinafter also simply referred to as "process chart"). In this example, it is shown that construction is being carried out to install new air conditioning equipment in building X.
  • the process chart is a bar chart process chart that displays a plurality of bar charts corresponding to a plurality of processes.
  • the process chart for the period from April 1st to April 24th, 2022 is shown as a bar chart.
  • a vertical line indicating that today is April 9, 2022 is displayed.
  • the process chart shows the item name, company name, progress rate, and bar chart for each process.
  • the item name column shows the work name (work type) of each process.
  • the company name column shows the name of the company in charge of the work.
  • the progress rate column shows the progress rate of the work as a percentage.
  • Company A is in charge of equipment delivery work on the second floor
  • Company B is in charge of equipment installation work on the second floor
  • Company C is in charge of piping work on the second floor
  • Displayed are wiring work on the second floor handled by Company D
  • insulation work on the second floor handled by Company E and test run on the second floor handled by Company F.
  • Company A is in charge of equipment delivery work on the 3rd floor
  • Company B is in charge of equipment installation work on the 3rd floor
  • Company C is in charge of piping on the 3rd floor. Displayed are construction work, wiring work on the third floor handled by Company D, insulation work on the third floor handled by Company E, and test run on the third floor handled by Company F.
  • equipment on the second floor (Company A), installation on the second floor (Company B), and equipment on the third floor (Company A) are scheduled to be brought in from April 1st to April 2nd. There is. Next, from April 3rd to April 8th (in this embodiment, work will not be carried out on Saturdays and Sundays), the plumbing work on the second floor (Company C) will be carried out, and from April 3rd to April 4th, the plumbing work will be carried out on the third floor.
  • Equipment installation (Company B) is planned. Today is April 9th, and all of the above steps have been completed as planned, so the bar chart is displayed in "blue" to indicate completed work. Further, the progress rate of these tasks is displayed as "100%".
  • the server 100 extracts the first step and the second step from the step information.
  • the plurality of steps include a first step and a second step that is a step after the first step.
  • the second process is a process that is affected by the delay if the work in the first process is delayed.
  • the server 100 In S203, the server 100 generates an image that connects the bar chart corresponding to the first step and the bar chart corresponding to the second step. As a result, when displaying the process chart on the display unit 221, an image connecting the first bar chart corresponding to the first process and the second bar chart corresponding to the second process is displayed. By doing so, when a delay occurs in a certain process (first process), it is possible to intuitively understand which process (second process) is affected by the delay.
  • Company B is in charge of equipment installation on the second floor from April 1st to April 2nd, and equipment installation on the third floor from April 3rd to April 4th. , it is necessary to install the equipment on the third floor the day after the equipment installation on the second floor is completed.
  • the third floor equipment installation may not be able to begin, and the third floor equipment installation may also be delayed. In this way, if a certain process (first process) is delayed and there is a possibility that the next process (second process) will be affected, a line is drawn between these two processes as "related work”. (here, an image of an arrow pointing from the first step to the second step) is displayed.
  • Company C is scheduled to carry out piping work on the third floor from April 9th to April 12th.
  • these two steps are also shown to be "related operations.”
  • Company D will conduct wiring work on the third floor from April 15th to April 16th after wiring work on the second floor from April 9th to April 10th. In this example, it is determined that there is a two-day margin between the two processes, which may affect the next process, so these processes are also shown to be "related work.” Finally, a trial run by Company F is scheduled for April 23rd to April 24th on the second and third floors.
  • the server 100 sets the bar chart image corresponding to the process in the high load state to red. At this time, the entire bar chart image may be displayed in red, or only the period (day) in a high load state may be displayed in red. In S205, the server 100 sets the bar chart corresponding to the second process to pink when the load state of the first process is a high load state.
  • the display unit 221 displays the first bar chart in a first mode (red) when the load state of the first process is a high load state, which is different from when the load state of the first process is not a high load state. is displayed. By doing so, the construction manager can intuitively grasp the load status of the person in charge.
  • the display unit 221 displays the first bar chart in the first mode (red) and displays the second bar chart in the second mode. It is displayed in pink color.
  • the load state is determined to be a high load state during the wiring work on the second floor (first step) on April 10th.
  • the bar chart for the second floor wiring work (first process) on April 10th is displayed in red. Note that the entire bar chart of this step may be displayed in red.
  • the bar chart for the insulation work on the second floor (second process) and the bar chart for the wiring work on the third floor (second process), which are set to be "related work" to this process are highlighted in pink. Display in color.
  • the bar chart for the insulation work on the second floor on April 15th is displayed in red. Note that the entire bar chart for the insulation work on the second floor may be displayed in red. Then, a bar chart of the third floor insulation work, which is set as "work related" to this process, is displayed in pink.
  • processes that are being performed or scheduled to be performed today are displayed as "scheduled work" on the bar chart in light blue.
  • the wiring work on the second floor is currently being carried out (progress rate is 50%), so it is displayed in light blue.
  • the plumbing work on the third floor is currently being carried out (progress rate is 25%), so it is displayed in light blue.
  • Processes scheduled after April 10th have not yet been started, so that fact is displayed in the progress rate column.
  • the bar chart for the second and third floor test runs scheduled for April 23rd to April 24th is displayed in light blue.
  • the server 100 associates schedule information of the person in charge with each bar chart.
  • the server 100 generates display information (work schedule, etc.) in S207, and ends the display information generation process.
  • display information work schedule, etc.
  • a process chart 91 is displayed on the display section 221 as display information.
  • FIG. 6 shows an example of displaying schedule information (see S206) of the person in charge associated with each bar chart.
  • the schedule information can be switched between display and non-display according to the user's specifications, and FIG. 5 shows an example in which the schedule information is set to be hidden, and FIG. 6 shows an example in which the schedule information is set to be displayed. .
  • FIG. 6 is a diagram showing an example of a process chart.
  • Company D will carry out wiring work on the second floor from April 9th to April 10th.
  • the schedule for April 10th of the person in charge of Company D doing the wiring work on the second floor is ⁇ 8:00-17:00 X building wiring "Construction”, "18:00-20:00 Y Building Estimate Creation”, and "20:00-22:00 Z Building Drawing Creation” are registered.
  • the display unit 221 displays schedule information in association with bar charts corresponding to the processes each of the plurality of persons in charge is responsible for.
  • the above schedule information is displayed in association with a bar chart corresponding to the wiring work on the second floor.
  • the schedule information is displayed in correspondence with the area of April 10th on the bar chart so that it can be seen that the schedule is for April 10th.
  • the name of the person in charge may also be displayed.
  • the display unit 221 displays the load status in association with the process that each of the plurality of persons in charge is in charge of.
  • the display unit 221 can also display schedule information in association with the processes each of the plurality of persons in charge is in charge of.
  • the construction manager can check the load status of the person in charge without having to interview the person in charge, check the daily work report that records the daily work contents, or check the site situation. Can be grasped accurately and intuitively.
  • the schedule information includes schedules that are unrelated to the target construction work. In this example, it is possible to grasp the load situation including schedules for Building Y and Building Z other than Building X managed by the construction manager. Information about other construction projects may come up in small talk, but it is usually difficult to grasp. In this embodiment, even such information is displayed on the process chart and can also be used for determining the load state. The construction manager can store such load status and schedule information in one place without having to create separate materials or reconstruct the information in his or her head, or without having to switch screens or systems.
  • FIG. 7 is a diagram showing the hardware configuration of the construction management system 1 according to the second embodiment.
  • the control unit 111 is configured to be able to execute the processes executed by the second estimation unit 121 and the generation unit 123.
  • the control unit 111 is further capable of executing the processing executed by the first estimation unit 122 and the notification unit 124.
  • descriptions of parts common to the first embodiment may be omitted.
  • the second estimation unit 121 acquires schedule information from the schedule management system 400.
  • the second estimation unit 121 acquires second input information from the storage unit 112.
  • the second estimation unit 121 determines the load state based on the second input information and schedule information.
  • the notification unit 124 When the load state of the first process is high, the notification unit 124 notifies the manager who manages the construction, the person in charge of the first process, and the person in charge of the second process to Notify information including status.
  • Such notification may be performed, for example, by sending an email to the email address of the administrator and the person in charge who have been registered in advance. By doing so, it is possible to quickly grasp the status of construction delays, and it is also possible to smoothly prepare for coordination between the parties involved to eliminate the delay.
  • the first estimation unit 122 acquires first input information, which will be described later, from the storage unit 112.
  • the first estimation unit 122 determines countermeasure information, which will be described later, based on the load state and the first input information.
  • the countermeasure information is information on a plurality of countermeasure plans indicating what countermeasures should be taken (extension of work period, increase in personnel, etc.) when a high load state occurs.
  • the generation unit 123 acquires process information, which will be described later, from the storage unit 112.
  • the generation unit 123 generates a process chart based on process information, countermeasure information, and load status.
  • the display unit 221 of the terminal 200 displays the generated process chart.
  • FIG. 8 is a flowchart of the main processing. The processing shown in this flowchart may be activated based on a request from the terminal 200.
  • the server 100 acquires schedule information from the schedule management system 400 in S301.
  • the server 100 acquires the second input information from the storage unit 112 in S302.
  • the server 100 inputs the schedule information and the second input information to the learned model 163, and acquires the load state output from the learned model 163.
  • the server 100 acquires the first input information from the storage unit 112 in S304. In S305, the server 100 inputs the load state and the first input information to the learned model 173, and acquires countermeasure information output from the learned model 173.
  • the server 100 acquires process information from the storage unit 112 in S306. In S307, the server 100 executes display information generation processing and generates display information (work schedule, etc.).
  • FIG. 9 is a diagram showing an example of a process chart.
  • the process chart 93 in FIG. 9 displays associated countermeasure information.
  • the load state is high during the wiring work on the second floor (first step).
  • heat insulation work on the second floor and heat insulation work on the third floor are set as the second process.
  • Countermeasure Information is displayed that is associated with the wiring work on the second floor that is under high load. Specifically, as the countermeasure information, "Countermeasure Plan 1" is “Extend the schedule of Company D” and “Increase in the number of personnel at Company E,” and “Countermeasure Plan 2" is “Increase in the number of personnel at Company D.”
  • Measure plan 2 assumes a case where it is not possible to increase the number of workers working on the insulation work on the second floor of Company E. In this case, Company D must complete the wiring work on the second floor by April 10 as scheduled. For this reason, the second plan for countermeasures is to recommend an increase in the number of employees at Company D.
  • the construction manager will coordinate the work with Company D and Company E based on the above countermeasure information. Then, as a result of the adjustment, it is determined which of countermeasure plan 1 and countermeasure plan 2 to adopt.
  • the server 100 outputs display information (process chart, etc.) to the display unit 221 in S309. As a result, a process chart 93 as shown in FIG. 9 is displayed on the display section 221.
  • the notification unit 124 of the server 100 notifies the administrator, the process in the high load state (the first process), and the related process (the second process) when the load state of the first process is the high load state.
  • the person in charge of the process) is notified of the load status, and the main process ends.
  • a learned model that has been subjected to machine learning is used to determine whether or not the load is high and to determine countermeasure information (multiple countermeasure plans) when the load is high. It will be done. Note that these are not limited to those that are determined or judged using a trained model, but may be determined or judged using other estimation models, or determined or judged based on some kind of rules. Good too. The learning process performed in this embodiment will be described below with reference to FIGS. 10 to 12.
  • FIG. 10 is a diagram for explaining the learning data set 160. There is a certain correlation between the above schedule information and second input information (input data) and the load state (output data).
  • the "load state” is determined using AI (Artificial Intelligence).
  • AI Artificial Intelligence
  • a learned model that infers output Y from input X is generated based on learning data consisting of a combination of input data and output data.
  • learning can be performed using supervised learning using a neural network.
  • deep learning which learns how to extract the feature amount itself, can also be used.
  • the storage unit 112 stores a learning data set 160 and a learned model 163.
  • the control unit 111 inputs the schedule information and the second input information to the second learned model (learned model 163), and outputs the load state and the like as an estimation result from the learned model 163.
  • the learned model 163 is a model that has been subjected to machine learning processing using teacher data so that when the schedule information and the second input information are input, the load state and the like are output as estimation results.
  • the second input information includes information indicating the schedule priority of each of the plurality of persons in charge, information on the company to which each of the plurality of persons in charge belongs, and information on each of the plurality of processes.
  • the learning process is performed using the above-mentioned input/output data set (learning data set 160). Then, using the obtained trained model, an estimation process is performed in which the schedule information and the second input information are input data, and the load state and the like are output data (estimated results). A set of input/output data is accumulated on a daily basis in the storage unit 112 of the server 100 as historical information on past construction work.
  • input data 161 includes schedule information and second input information.
  • Output data 162 includes the load status and adjustment results.
  • the learning data set 160 As the learning data set 160, a combination of input data 161 and output data 162 is prepared. Here, the output data 162 becomes the correct data. Examples of combinations of input data 161 and output data 162 will be described below.
  • the input data includes schedule priority, company information (company in charge, etc.), process information (work content, implementation period, schedule information of the person in charge during the implementation period, implementation timing, etc.), and the output data includes adjustments.
  • Results additional personnel, extended work days
  • load status etc.
  • the schedule priority is the priority of each schedule registered by the person in charge (high, medium, or low can be set), and this priority can be set in advance in the schedule management system 400.
  • the schedule priority is "Work A: High Priority”
  • the company in charge is “Company D”
  • the work content is “Wiring work”
  • the implementation period is “March 1st”
  • the schedule information of the person in charge during the implementation period is "March 1st”.
  • implementation time "March” output data is "0 additional personnel”
  • number of work extension days “1 day”
  • load status "High load "state”.
  • the data administrator shall set the load state to "high load state” or "normal state” after confirming the above input/output data.
  • the load state may be set to "high load state” when work with a high priority other than the target construction work is registered in the schedule for a predetermined time (predetermined ratio) or more.
  • information other than the schedule may also be taken into consideration. For example, if there is one or more additional personnel, or if there is one or more days of work extension, the load state may be set to "high load state” regardless of the schedule registration status. Further, the load state may be automatically set using the above rules.
  • the schedule priority "Work B: Low priority” the work content "thermal insulation work”
  • the implementation period "February 3rd” the company in charge "Company E”
  • implementation time is "February”
  • output data is "0 additional personnel”
  • number of work extension days is "0 days”
  • load status Assume that it is in a "normal state”.
  • the load state can be estimated with high accuracy by using the obtained learned model.
  • the construction manager can make adjustments such as adjusting schedules and adding personnel for processes that are under high load, so that the construction can be completed by the deadline. In this way, even a construction manager with little experience can manage construction efficiently.
  • FIG. 11 is a diagram for explaining the learning data set. There is a certain correlation between the above-mentioned load state and first input information (input data) and countermeasure information (output data).
  • the storage unit 112 stores a learning data set 170 and a learned model 173.
  • the control unit 111 outputs countermeasure information from the learned model 173 as an estimation result by inputting the load state and the first input information to the first learned model (learned model 173).
  • the learned model 173 is a model that has been subjected to machine learning processing using teacher data so that countermeasure information is output as an estimation result when the load state and first input information are input.
  • the first input information includes information on the company to which each of the plurality of persons in charge belongs, and information on each of the plurality of processes.
  • the countermeasure information is information indicating a countermeasure method for the first process and the second process when a high load state occurs.
  • Countermeasures include a method of extending the working period of either or both of the first process and the second process, and a method of increasing the number of workers in either or both of the first process and the second process. including.
  • learning processing is performed using the above-mentioned input/output data set. Then, using the obtained trained model, an estimation process is performed in which the load state and the first input information are input data, and the countermeasure information is output data (estimation result).
  • the input data 171 includes the load state and first input information.
  • the output data 172 includes countermeasure information.
  • a combination of input data 171 and output data 172 is prepared as a learning data set 170.
  • the output data 172 becomes the correct data. Examples of combinations of input data 171 and output data 172 will be described below.
  • the input data is the company in charge of the first process, the load condition, the work content, the implementation time, the company in charge of the second process, the work content, and the implementation time
  • the output data is countermeasure information
  • the company in charge is “Company D”
  • the load state is “high load state”
  • the work content is “wiring work”
  • the implementation period is "March”
  • the company in charge is "Company E”
  • the work content is "thermal insulation work” and the implementation period is "March”
  • the output data includes countermeasure information such as an extension of the first process "1 day”, an increase in the number of people for the first process "0 people”, and the second process Assume that the extension of the process was ⁇ 0 days'' and the number of people added to the second process was ⁇ 1 person.''
  • Company D is unable to increase its staff because March is a busy season
  • Company E was able to increase its staff because March is not a busy season.
  • Company D which has a heavy workload, has to extend its work by one day
  • Company E which has extra personnel, increases its staff and completes the insulation work in one day shorter than planned.
  • Company D has a small number of employees, it will be difficult to increase the number of employees, whereas if Company E has a large number of employees, it will be easier to increase the number of employees.
  • input data and output data can be used to determine whether to increase the number of people in the first process or the second process, or to extend or shorten the period. There is a certain correlation.
  • one countermeasure may be output, or multiple countermeasures may be output in descending order of probability, such as countermeasure 1, countermeasure 2, etc. You may also do so.
  • the optimal countermeasure can be determined by using the obtained learned model.
  • the construction manager can make adjustments such as adjusting schedules and adding personnel for processes that are under high load, so that the construction can be completed by the deadline. In this way, even a construction manager with little experience can manage construction efficiently.
  • FIG. 12 is a flowchart of the learning process.
  • the “step” will also be simply referred to as "S”.
  • processing for learning the trained model 163 will be described.
  • the server 100 selects learning data from the learning data set 160 in S401, and advances the process to S402.
  • the server 100 inputs the selected learning data to the estimation model, and advances the process to S403.
  • the server 100 executes the estimation process, outputs the estimation result, and advances the process to S404.
  • the server 100 updates the parameters of the estimation model based on the error between the estimation result and the correct data corresponding to the learning data, and advances the process to S405.
  • the server 100 determines whether learning has been performed based on all learning data. If the server 100 determines that learning has been performed based on all the learning data (YES in S405), the process proceeds to S406. If the server 100 does not determine that learning has been performed based on all the learning data (NO in S405), the process returns to S401. In S406, the server 100 stores the learned estimation model as the learned model 163, and ends the learning process.
  • the learning process for the learned model 173 is also performed using the learning data set 170 in the same manner as above.
  • FIG. 13 is a flowchart of route display processing according to a modification.
  • FIG. 14 is a diagram showing an example of a process chart according to a modification. The process chart in FIG. 14 is illustrated more simply than the process chart described using FIGS. 5 and 6.
  • the server 100 classifies the route from the start of the construction work to the end of the work into a plurality of routes in S501.
  • FIG. 14 a bar chart of multiple companies (multiple people in charge) in charge of construction work and the processes each person in charge is in charge of is shown.
  • FIG. 14 when there is a process that can be started on the condition that a certain process is completed, the former process and the latter process are connected by a line and displayed.
  • Company C's process can start. After Company B's process is completed, Company C's process can begin. After Company C's process is completed, Company F's process can begin. After Company F's process is completed, Company G's process can begin.
  • Company E's process can start.
  • Company F's process can begin.
  • the order of the processes is as follows: a route that follows Company A, Company C, Company F, and Company G (referred to as "route 1"), and a route that follows Company B, Company C, Company F, and Company G in that order (referred to as “route 1"). (referred to as "Route 2”), followed by a route (referred to as "Route 3") in which Company D, Company E, Company F, and Company G proceed in this order.
  • the server 100 selects the route with the maximum number of required days from the number of required days for each route.
  • Route 1 is the route that takes the maximum number of days from the start to the end of the construction work. For example, if Company A's process on Route 1 is delayed, Company C's process that starts immediately thereafter will be delayed. On the other hand, in the case of route 2, even if there is a delay in Company B's process, there is plenty of time before Company C's process starts next, so the delay is less likely to occur.
  • the server 100 changes the color and size of the bar chart included in the route with the maximum number of required days, and ends the route display process.
  • the route that takes the maximum number of days from the start to the end of the construction work is displayed in a different manner from the other routes.
  • the bar chart for each process in route 1 which takes the maximum number of days from the start to the end of construction, is displayed as a red image with a large vertical width, and the line connecting these processes is displayed. Displayed as a solid line.
  • a bar chart for each process of routes 2 and 3 is displayed as a white image with a vertical width smaller than that of route 1, and a line connecting these processes is displayed as a broken line.
  • those included in route 1 are displayed using the display method according to route 1 (a red image with a large vertical width). By doing this, it is easy to intuitively understand routes that are likely to be affected by delays, and it is possible to draw attention to such routes.
  • This modification is applicable to the first embodiment or the second embodiment.
  • the process of company A in the first route corresponds to the first process
  • the process of company C corresponds to the second process.
  • the process of Company C in the first route corresponds to the first process
  • the process of Company F corresponds to the second process.
  • the process of Company F in the first route corresponds to the first process
  • the process of Company G corresponds to the second process.
  • the schedule may be a network schedule.
  • schedule information may be displayed in association with each process.
  • the process first process
  • the process that may be affected by this process second process
  • the path 1 in the modified example corresponds to a critical path.
  • 1 Construction management system 91-94 Schedule, 100 Server, 111, 211 Control unit, 112, 212 Storage unit, 113, 213 Communication unit, 121 Second estimation unit, 122 First estimation unit, 123 Generation unit, 124 Notification Section, 161, 171 Input data, 162, 172 Output data, 163, 173 Learned model, 200 Terminal, 220 Input section, 221 Display section, 400 Schedule management system.

Abstract

A work management system (1) comprises a control unit (111) that generates a process schedule for construction, and a display unit (221) that displays the process schedule. The control unit (111) determines a load state indicating a task load of a plurality of managers on the basis of information including schedule information for the plurality of managers. The display unit (221) displays schedule information and the load state in association with the processes that each of the plurality of managers is responsible for.

Description

施工管理システムおよび施工管理方法Construction management system and construction management method
 本開示は、施工管理システムおよび施工管理方法に関する。 The present disclosure relates to a construction management system and a construction management method.
 ビル等の建設現場での工事において、工事を担当する複数の作業者(担当者)が複数の作業を並行して行うことが多い。施工を管理する施工管理者(現場代理人)は、各作業者の作業の負荷状況と、同時進行で行われる複数の作業の進捗状況とを把握する必要がある。その上で、施工管理者は、作業の品質を維持しつつ安全に全ての作業が期日までに完了するよう対策を講じる必要がある。 During construction work at construction sites such as buildings, multiple workers (persons in charge) often perform multiple tasks in parallel. A construction manager (on-site agent) who manages construction needs to understand the work load status of each worker and the progress status of multiple jobs being performed simultaneously. On top of that, the construction manager needs to take measures to ensure that all work is completed safely and by the deadline while maintaining the quality of the work.
 施工管理者は、朝礼の実施、作業責任者へのヒヤリング、作業日報の確認等より作業者の負荷状況を把握するとともに、作業現場を巡回して目視確認、現場写真の確認等により作業の進捗状況を把握している。施工管理者は、このようにして把握した状況に基づき、作業者の増員あるいは入れ替え、作業工程の見直し等を実施している。 The construction manager grasps the workload of the workers by holding morning meetings, interviewing the person in charge of work, checking daily work reports, etc., and also monitors the progress of the work by visiting the work site and checking visually and checking site photos. I understand the situation. Based on the situation ascertained in this way, the construction manager increases or replaces workers, reviews the work process, etc.
特開2020-135098号公報Japanese Patent Application Publication No. 2020-135098
 施工管理者が把握した状況に基づき、作業者の増員あるいは入れ替え、作業工程の見直し等の実施が必要かどうかを適切に判断できるようになるためには、現場でのある程度の実績と経験が必要となる。建設業界の労働人口の減少が進んでいる現状においては、このような適切な判断を行うことができる施工管理者を育成する必要がある一方、経験が乏しい施工管理者であっても効率よく施工管理を行えるような施工管理システムが求められている。 In order for construction managers to be able to appropriately judge whether it is necessary to increase or replace workers, review work processes, etc. based on the situation ascertained, a certain level of track record and experience in the field is required. becomes. In the current situation where the working population in the construction industry is decreasing, there is a need to develop construction managers who can make such appropriate decisions. There is a need for a construction management system that can perform management.
 本開示は、かかる問題を解決するためになされたものであり、本開示の目的は、経験が乏しい施工管理者であっても、効率よく施工管理を行うことができる施工管理システムおよび施工管理方法を提供することである。 The present disclosure has been made to solve such problems, and the purpose of the present disclosure is to provide a construction management system and a construction management method that allow even inexperienced construction managers to efficiently manage construction. The goal is to provide the following.
 本開示の施工管理システムは、複数の担当者が担当する複数の工程から成る工事の施工を管理するシステムである。施工管理システムは、工事の工程表を生成する制御部と、工程表を表示する表示部とを備える。制御部は、複数の担当者のスケジュール情報を含む情報に基づき、複数の担当者の作業負荷を示す負荷状態を決定する。表示部は、複数の担当者の各々が担当する工程に対応付けてスケジュール情報および負荷状態を表示する。 The construction management system of the present disclosure is a system that manages the construction of a construction project consisting of multiple steps handled by multiple personnel. The construction management system includes a control unit that generates a construction schedule, and a display unit that displays the schedule. The control unit determines a load state indicating the workload of the plurality of persons in charge based on information including schedule information of the plurality of persons in charge. The display unit displays schedule information and load status in association with the processes each of the plurality of persons in charge is in charge of.
 また、本開示の施工管理方法は、複数の担当者が担当する複数の工程から成る工事の施工を管理する方法である。施工管理方法は、工事の工程表を生成するステップと、工程表を表示するステップとを備える。生成するステップは、複数の担当者のスケジュール情報を含む情報に基づき、複数の担当者の作業負荷を示す負荷状態を決定するステップを含む。表示するステップは、複数の担当者の各々が担当する工程に対応付けてスケジュール情報および負荷状態を表示するステップを含む。 Furthermore, the construction management method of the present disclosure is a method for managing the construction of construction work consisting of multiple steps handled by multiple personnel. The construction management method includes a step of generating a construction schedule and a step of displaying the schedule. The generating step includes determining a load state indicating the workload of the plurality of persons in charge based on information including schedule information of the plurality of persons in charge. The step of displaying includes a step of displaying schedule information and load status in association with the processes each of the plurality of persons in charge is in charge of.
 本開示によれば、経験が乏しい施工管理者であっても、効率よく施工管理を行うことができる。 According to the present disclosure, even a construction manager with little experience can efficiently manage construction.
第1実施形態に係る施工管理システムのハードウェア構成を示す図である。FIG. 1 is a diagram showing a hardware configuration of a construction management system according to a first embodiment. 施工管理システムにおける機能ブロック図を示す図である。It is a figure showing a functional block diagram in a construction management system. メイン処理のフローチャートである。It is a flowchart of main processing. 表示情報生成処理のフローチャートである。It is a flowchart of display information generation processing. 工程表の一例を示す図である。It is a figure showing an example of a process chart. 工程表の一例を示す図である。It is a figure showing an example of a process chart. 第2実施形態に係る施工管理システムにおける機能ブロック図を示す図である。It is a figure showing a functional block diagram in a construction management system concerning a 2nd embodiment. メイン処理のフローチャートである。It is a flowchart of main processing. 工程表の一例を示す図である。It is a figure showing an example of a process chart. 学習用データセットを説明するための図である。FIG. 3 is a diagram for explaining a learning data set. 学習用データセットを説明するための図である。FIG. 3 is a diagram for explaining a learning data set. 学習処理のフローチャートである。It is a flowchart of learning processing. 変形例に係る経路表示処理のフローチャートである。It is a flowchart of route display processing concerning a modification. 変形例に係る工程表の一例を示す図である。It is a figure showing an example of a process chart concerning a modification.
 以下、本開示の実施の形態について、図面を参照しながら詳細に説明する。以下では、複数の実施の形態について説明するが、各実施の形態で説明された構成を適宜組合わせることは出願当初から予定されている。なお、図中同一又は相当部分には同一符号を付してその説明は繰り返さない。 Hereinafter, embodiments of the present disclosure will be described in detail with reference to the drawings. Although a plurality of embodiments will be described below, it has been planned from the beginning of the application to appropriately combine the configurations described in each embodiment. In addition, the same reference numerals are attached to the same or corresponding parts in the drawings, and the description thereof will not be repeated.
 <第1実施形態>
 図1は、第1実施形態に係る施工管理システム1のハードウェア構成を示す図である。施工管理システム1は、複数の工程から成る工事の施工を管理するシステムである。これら複数の工程は、複数の担当者(「作業者」とも称する)が担当する。
<First embodiment>
FIG. 1 is a diagram showing the hardware configuration of a construction management system 1 according to the first embodiment. The construction management system 1 is a system that manages the construction of a construction project consisting of a plurality of steps. A plurality of persons in charge (also referred to as "workers") are in charge of these plurality of steps.
 たとえば、後述する図5の例では、Xビルにおいて空調設備を新設する空調設備新設工事における複数の工程を示した工程表を示している。この例では、A社~F社(A社~F社の各担当者)が各工程の作業を担当している。 For example, the example of FIG. 5, which will be described later, shows a process chart showing a plurality of steps in new air conditioning equipment construction work to install new air conditioning equipment in Building X. In this example, companies A to F (persons in charge of companies A to F) are in charge of each process.
 ここでは、4月1日~2日において、A社の担当者(作業者)が2階の機器搬入の作業(工程)を担当している。そして、最終的には、4月23日~24日のF社の担当者が2階および3階の試運転を担当しており、これらの作業が完了することで、本工事の施工が完了する。 Here, from April 1st to April 2nd, the person in charge (worker) from Company A is in charge of the work (process) of bringing in equipment to the second floor. Finally, from April 23rd to 24th, personnel from Company F were in charge of trial runs on the 2nd and 3rd floors, and once these tasks are completed, the main construction work will be completed. .
 ここで、「担当者」とは、上記のように各工程を請け負う業者(A社~F社)の各担当者を指し示すものであってもよいし、各工程を請け負う業者(A社~F社)そのものを指し示すものであってもよい。1つの工程を担当する担当者(作業者)は、1人であってもよいし、複数であってもよい。 Here, "person in charge" may refer to each person in charge of the companies (Companies A to F) that undertake each process as described above, or may refer to each person in charge of the companies that undertake each process (Companies A to F). It may also indicate the company itself. The number of persons in charge (workers) in charge of one process may be one or more.
 図1に戻り、施工管理システム1は、サーバ100と、複数の端末200とを備える。サーバ100は、工程表を生成する処理等を行う。複数の端末200は、施工を管理する施工管理者(単に「管理者」とも称する)が使用する端末と、工事の複数の工程を担当する複数の担当者が使用する複数の端末とで構成される。 Returning to FIG. 1, the construction management system 1 includes a server 100 and a plurality of terminals 200. The server 100 performs processes such as generating a process chart. The plurality of terminals 200 are composed of a terminal used by a construction manager (also simply referred to as a "manager") who manages construction, and a plurality of terminals used by a plurality of persons in charge of a plurality of construction steps. Ru.
 施工管理者は、担当する工事の各工程における各担当者の負荷状況や各作業の進捗状況を把握しつつ、期日までに工事が完了するように現場を管理する。図1の例では、施工管理者が使用する端末200、作業者K1が使用する端末200および作業者K2が使用する端末200が示されている。 The construction manager manages the site so that the construction work is completed by the deadline, while keeping track of the workload of each person in charge of each step of the construction work and the progress of each work. In the example of FIG. 1, a terminal 200 used by a construction manager, a terminal 200 used by worker K1, and a terminal 200 used by worker K2 are shown.
 施工管理システム1は、スケジュール管理システム400と接続可能に構成されている。スケジュール管理システム400は、複数の担当者のスケジュールを管理するシステムである。 The construction management system 1 is configured to be connectable to the schedule management system 400. The schedule management system 400 is a system that manages the schedules of a plurality of people in charge.
 各担当者は、各自が使用する端末200からスケジュール管理システム400にアクセスし、スケジュール管理システム400が提供するスケジュール管理ソフトを用いて各自のスケジュールを管理する。スケジュール管理ソフトは、あらかじめ端末200にインストールされたソフトウェアを起動して使用するものであってもよいし、端末200上で起動するブラウザを介して使用するものであってもよい。 Each person in charge accesses the schedule management system 400 from the terminal 200 that he/she uses, and manages his/her own schedule using the schedule management software provided by the schedule management system 400. The schedule management software may be used by starting software installed on the terminal 200 in advance, or may be used via a browser started on the terminal 200.
 各担当者は、日付および時刻を指定して、自身のスケジュールをスケジュール管理ソフトを用いてスケジュール管理システム400に登録する。閲覧が許可されたユーザ(たとえば、社内のユーザ)は、スケジュール管理システム400にアクセスして登録されたスケジュールを閲覧可能である。 Each person in charge specifies the date and time and registers their own schedule in the schedule management system 400 using schedule management software. Users who are permitted to view (for example, users within the company) can access the schedule management system 400 and view the registered schedules.
 本実施の形態では、サーバ100は、スケジュール管理システム400にアクセスして、登録されたスケジュールを取得することが可能に構成されている。スケジュール情報には、施工管理者が管理する工事と関係のないスケジュールが含まれる。 In this embodiment, the server 100 is configured to be able to access the schedule management system 400 and obtain registered schedules. The schedule information includes schedules unrelated to the construction work managed by the construction manager.
 図5の例では、Xビルの空調設備新設工事を行う各社(A社~F社)は、スケジュール管理システム400によってスケジュールを管理しているものとする。サーバ100は、スケジュール管理システム400にアクセスして、A社~F社の作業者(担当者)が登録したスケジュールを取得することができる。 In the example of FIG. 5, it is assumed that the companies (Companies A to F) that are constructing new air conditioning equipment in building X manage their schedules using the schedule management system 400. The server 100 can access the schedule management system 400 and obtain the schedules registered by the workers (persons in charge) of companies A to F.
 このスケジュールには、Xビルの空調設備新設工事とは無関係なスケジュールが含まれる。たとえば、Xビルとは異なるYビルの工事スケジュール情報であってもよいし、社内会議のスケジュールであってもよいし、どのようなスケジュールであってもよい。 This schedule includes schedules unrelated to the construction of new air conditioning equipment in Building X. For example, it may be construction schedule information for Building Y, which is different from Building X, or it may be a schedule for an internal meeting, or it may be any schedule.
 また、A社~F社は同一のスケジュール管理システム(スケジュール管理システム400)を使用するものに限らず、各社で異なるスケジュール管理システムを使用するものであってもよい。この場合、サーバ100は、これら複数のスケジュール管理システムにアクセスしてスケジュール情報を取得可能であるものとする。 Further, companies A to F are not limited to using the same schedule management system (schedule management system 400), but each company may use a different schedule management system. In this case, it is assumed that the server 100 can access these multiple schedule management systems and acquire schedule information.
 図1に戻り、サーバ100は、制御部111と、記憶部112と、通信部113とを備える。これらは、バスを介して相互に通信可能に接続されている。 Returning to FIG. 1, the server 100 includes a control section 111, a storage section 112, and a communication section 113. These are communicably connected to each other via a bus.
 制御部111は、たとえば、CPU(Central Processing Unit)である。記憶部112は、ROM(Read Only Memory)と、RAM(Random Access Memory)と、不揮発性の記憶装置(たとえば、HDD(Hard Disk Drive)あるいはSSD(Solid State Drive)等)とを備える。記憶部112は、後述する学習用データセット160と、学習済モデル163と、学習用データセット170と、学習済モデル173とを記憶する。 The control unit 111 is, for example, a CPU (Central Processing Unit). The storage unit 112 includes a ROM (Read Only Memory), a RAM (Random Access Memory), and a nonvolatile storage device (for example, a HDD (Hard Disk Drive) or an SSD (Solid State Drive)). The storage unit 112 stores a learning data set 160, a learned model 163, a learning data set 170, and a learned model 173, which will be described later.
 制御部111は、ROMに保存されているプログラムをRAMに読み込んで実行し、サーバ100の各種機能を実現する。制御部111は、工事の工程表を生成する処理等を行う。ROMは、サーバ100の処理手順が記されたプログラムを格納する。RAMは、制御部111がプログラムを実行する際の作業領域となるものであり、プログラムやプログラムを実行する際のデータ等を一時的に記憶する。サーバ100は、通信部113を介して、端末200およびスケジュール管理システム400と無線または有線で接続可能である。 The control unit 111 loads programs stored in the ROM into the RAM and executes them to realize various functions of the server 100. The control unit 111 performs processing such as generating a work schedule. The ROM stores a program in which processing procedures of the server 100 are written. The RAM serves as a work area when the control unit 111 executes a program, and temporarily stores programs and data used when executing the program. The server 100 can be connected to the terminal 200 and the schedule management system 400 wirelessly or by wire via the communication unit 113.
 端末200は、たとえば、スマートフォン、タブレット等のモバイル端末であってもよいし、ノートパソコン、デスクトップコンピュータ等のパーソナルコンピュータ等であってもよい。 The terminal 200 may be, for example, a mobile terminal such as a smartphone or a tablet, or a personal computer such as a notebook computer or a desktop computer.
 端末200は、制御部(CPU)211と、記憶部212と、通信部213と、入力部220と、表示部221とを備える。これらは、バスを介して相互に通信可能に接続されている。記憶部212も同様に、ROMと、RAMと、HDDあるいはSSD等の不揮発性の記憶装置とを備えるように構成してもよい。 The terminal 200 includes a control unit (CPU) 211, a storage unit 212, a communication unit 213, an input unit 220, and a display unit 221. These are communicably connected to each other via a bus. Similarly, the storage unit 212 may be configured to include a ROM, a RAM, and a nonvolatile storage device such as an HDD or an SSD.
 制御部211は、ROMに保存されているプログラムをRAMに読み込んで実行し、端末200の各種機能を実現する。ROMは、端末200の処理手順が記されたプログラムを格納する。端末200は、通信部213を介して、サーバ100およびスケジュール管理システム400と接続可能である。 The control unit 211 loads programs stored in the ROM into the RAM and executes them to realize various functions of the terminal 200. The ROM stores a program in which processing procedures for the terminal 200 are written. The terminal 200 is connectable to the server 100 and the schedule management system 400 via the communication unit 213.
 入力部220は、ユーザからの入力を受け付ける。入力部220は、たとえば、タッチパネルであるが、キーボード、マウスであってもよい。表示部221は、各種情報の表示を行う。表示部221は、たとえば、液晶表示器、ディスプレイである。表示部221は、制御部111が生成した工程表を表示することができる。なお、工程表は、管理者が使用する端末200でのみ閲覧可能に構成してもよいし、各作業者が使用する端末200においても閲覧可能に構成してもよい。 The input unit 220 receives input from the user. The input unit 220 is, for example, a touch panel, but may also be a keyboard or a mouse. The display unit 221 displays various information. The display unit 221 is, for example, a liquid crystal display or a display. The display unit 221 can display the process chart generated by the control unit 111. Note that the process chart may be configured to be viewable only on the terminal 200 used by the administrator, or may be configured to be viewable on the terminal 200 used by each worker.
 なお、施工管理システム1は、サーバ100と管理者が使用する端末200とを一体として構成する装置であってもよい。この場合、本装置が備える制御部(CPU)が生成した工程表を本装置が備える表示部(ディスプレイ)が表示するように構成する。また、施工管理システム1は、スケジュール管理システム400も含めて構成してよいし、サーバ100および管理者が使用する端末200のみで構成してもよい。 Note that the construction management system 1 may be a device that integrates a server 100 and a terminal 200 used by an administrator. In this case, the display unit (display) included in the apparatus is configured to display the process chart generated by the control unit (CPU) included in the apparatus. Moreover, the construction management system 1 may be configured to include the schedule management system 400, or may be configured to include only the server 100 and the terminal 200 used by the administrator.
 図2は、施工管理システム1における機能ブロック図を示す図である。サーバ100の制御部111は、第2推定部121と、生成部123とが実行する処理を実行可能である。 FIG. 2 is a diagram showing a functional block diagram of the construction management system 1. The control unit 111 of the server 100 can execute the processing executed by the second estimation unit 121 and the generation unit 123.
 第2推定部121は、スケジュール管理システム400から、工事における複数の担当者のスケジュール情報を取得する。第2推定部121は、記憶部112から後述する第2入力情報を取得する。 The second estimation unit 121 acquires schedule information of a plurality of people in charge of construction from the schedule management system 400. The second estimation unit 121 acquires second input information, which will be described later, from the storage unit 112.
 第2推定部121は、複数の担当者のスケジュール情報と、第2入力情報とに基づき、複数の担当者の作業負荷を示す負荷状態を決定する。負荷状態は、高負荷状態を含む。「高負荷状態」とは、対象となる工程において作業の遅延が予測される状態である。第2入力情報は、負荷状態を判断するために必要な情報である。第2入力情報と、負荷状態を決定する処理とについては、図10,図12を用いて詳細に説明する。 The second estimation unit 121 determines the load state indicating the workload of the plurality of persons in charge based on the schedule information of the plurality of persons in charge and the second input information. The load state includes a high load state. A "high load state" is a state in which work delays are expected in the target process. The second input information is information necessary to determine the load state. The second input information and the process of determining the load state will be explained in detail using FIGS. 10 and 12.
 生成部123は、記憶部112から後述する工程情報を取得する。生成部123は、工程情報および負荷状態等に基づき工程表を含む表示情報を生成する。端末200の表示部221は、生成した工程表を含む表示情報を表示する。 The generation unit 123 acquires process information, which will be described later, from the storage unit 112. The generation unit 123 generates display information including a process chart based on process information, load status, and the like. The display unit 221 of the terminal 200 displays display information including the generated process chart.
 以下、フローチャートを用いて具体的に説明する。図3は、メイン処理のフローチャートである。このフローチャートに示される処理は、たとえば、端末200からの表示要求に基づき起動するようにすればよい。 A detailed explanation will be given below using a flowchart. FIG. 3 is a flowchart of main processing. The processing shown in this flowchart may be activated based on a display request from the terminal 200, for example.
 メイン処理が開始すると、サーバ100は、S101において、スケジュール管理システム400からスケジュール情報を取得する。サーバ100は、S102において、記憶部112から第2入力情報を取得する。サーバ100は、S103において、スケジュール情報および第2入力情報を学習済モデル163(図10)に入力し、学習済モデル163から出力される負荷状態を取得する。 When the main process starts, the server 100 acquires schedule information from the schedule management system 400 in S101. The server 100 acquires the second input information from the storage unit 112 in S102. In S103, the server 100 inputs the schedule information and the second input information to the learned model 163 (FIG. 10), and acquires the load state output from the learned model 163.
 サーバ100は、S104において、記憶部112から工程情報を取得する。工程情報は、対象となる工事における複数の工程に関して設定された各種情報である。たとえば、図5の例においては、工事名称(Xビル空調設備新設工事)、各工程の項目名(2階の機器搬入等)、会社名(A社)、工事予定日(2022年4月1日~2日)等、工程表を生成するために必要な情報である。 The server 100 acquires process information from the storage unit 112 in S104. The process information is various information set regarding multiple processes in the target construction. For example, in the example shown in Figure 5, the construction name (new construction of air conditioning equipment in building This is the information necessary to generate a process chart, such as 1 day to 2 days).
 サーバ100は、S105において、表示情報生成処理(図4)を実行し、表示情報(工程表等)を生成する。サーバ100は、S106において、表示情報(工程表等)を表示部221に対して出力し、メイン処理を終了する。 In S105, the server 100 executes display information generation processing (FIG. 4) to generate display information (work schedule, etc.). In S106, the server 100 outputs display information (work schedule, etc.) to the display unit 221, and ends the main processing.
 具体的には、端末200からの表示要求によりメイン処理が実行され、その結果生成された表示情報は、通信部213を介して端末200に取得されて、表示部221で表示される。表示部221に表示される工程表の例は、図5,図6において示される。以下、図4を用いて、表示情報生成処理のフローチャートを説明しつつ、図5,図6に示される工程表について説明する。 Specifically, main processing is executed in response to a display request from the terminal 200, and display information generated as a result is acquired by the terminal 200 via the communication unit 213 and displayed on the display unit 221. Examples of the process chart displayed on the display unit 221 are shown in FIGS. 5 and 6. Hereinafter, the flowchart of the display information generation process will be explained using FIG. 4, and the process charts shown in FIGS. 5 and 6 will be explained.
 図4は、表示情報生成処理のフローチャートである。表示情報生成処理が開始すると、サーバ100は、S201において、スケジュール情報、負荷情報、工程情報等を取得する。工程表は、これらの情報に基づき生成される。 FIG. 4 is a flowchart of display information generation processing. When the display information generation process starts, the server 100 acquires schedule information, load information, process information, etc. in S201. A process chart is generated based on this information.
 図5は、工程表の一例を示す図である。図5に示すように、工程表91(以下、単に「工程表」とも称する)の上部には、工事名称が表示されている。本例では、Xビルの空調設備新設工事であることが示されている。本実施の形態においては、工程表は、複数の工程に対応する複数のバーチャートを表示するバーチャート工程表である。 FIG. 5 is a diagram showing an example of a process chart. As shown in FIG. 5, the construction name is displayed at the top of the process chart 91 (hereinafter also simply referred to as "process chart"). In this example, it is shown that construction is being carried out to install new air conditioning equipment in building X. In this embodiment, the process chart is a bar chart process chart that displays a plurality of bar charts corresponding to a plurality of processes.
 本例では、2022年4月1日~4月24日の期間の工程表がバーチャートで示されている。工程表においては、本日が2022年4月9日である旨を示す縦のラインが表示されている。 In this example, the process chart for the period from April 1st to April 24th, 2022 is shown as a bar chart. In the process chart, a vertical line indicating that today is April 9, 2022 is displayed.
 工程表には、各工程の、項目名、会社名、進捗率およびバーチャートが示されている。項目名の欄には、各工程の作業名(作業の種類)が示される。会社名の欄には、作業を担当する会社名が示される。進捗率の欄には、作業の進捗率がパーセンテージで示される。 The process chart shows the item name, company name, progress rate, and bar chart for each process. The item name column shows the work name (work type) of each process. The company name column shows the name of the company in charge of the work. The progress rate column shows the progress rate of the work as a percentage.
 Xビルの空調設備新設工事においては、複数の工程として、A社が担当する2階の機器搬入作業、B社が担当する2階の機器据付作業、C社が担当する2階の配管工事、D社が担当する2階の配線工事、E社が担当する2階の保温工事、F社が担当する2階の試運転が表示されている。 In the construction of new air conditioning equipment in Building X, there are multiple steps: Company A is in charge of equipment delivery work on the second floor, Company B is in charge of equipment installation work on the second floor, Company C is in charge of piping work on the second floor, Displayed are wiring work on the second floor handled by Company D, insulation work on the second floor handled by Company E, and test run on the second floor handled by Company F.
 さらに、Xビルの空調設備新設工事においては、複数の工程として、A社が担当する3階の機器搬入作業、B社が担当する3階の機器据付作業、C社が担当する3階の配管工事、D社が担当する3階の配線工事、E社が担当する3階の保温工事、F社が担当する3階の試運転が表示されている。 Furthermore, in the construction of new air conditioning equipment in Building X, there are multiple steps: Company A is in charge of equipment delivery work on the 3rd floor, Company B is in charge of equipment installation work on the 3rd floor, and Company C is in charge of piping on the 3rd floor. Displayed are construction work, wiring work on the third floor handled by Company D, insulation work on the third floor handled by Company E, and test run on the third floor handled by Company F.
 本工程表によれば、4月1日~4月2日に2階の機器搬入(A社)、2階の機器据付(B社)、3階の機器搬入(A社)が計画されている。次に、4月3日~4月8日(本実施の形態においては、土日は作業を実施しない)に2階の配管工事(C社)、4月3日~4月4日に3階の機器据付(B社)が計画されている。本日は、4月9日であり、上記全ての工程は計画通り作業が終了したため、バーチャートは、終了した作業を示す「青色」で表示されている。また、これらの作業は、進捗率=「100%」と表示されている。 According to this schedule, equipment on the second floor (Company A), installation on the second floor (Company B), and equipment on the third floor (Company A) are scheduled to be brought in from April 1st to April 2nd. There is. Next, from April 3rd to April 8th (in this embodiment, work will not be carried out on Saturdays and Sundays), the plumbing work on the second floor (Company C) will be carried out, and from April 3rd to April 4th, the plumbing work will be carried out on the third floor. Equipment installation (Company B) is planned. Today is April 9th, and all of the above steps have been completed as planned, so the bar chart is displayed in "blue" to indicate completed work. Further, the progress rate of these tasks is displayed as "100%".
 図4に戻り、サーバ100は、S202において、工程情報から、第1の工程および第2の工程を抽出する。本実施の形態において、複数の工程は、第1の工程と、第1の工程の後の工程である第2の工程とを含む。第2の工程は、第1の工程の作業が遅延した場合に、当該遅延による影響が生じる工程である。これらの関係は、予め工程情報として設定されている。 Returning to FIG. 4, in S202, the server 100 extracts the first step and the second step from the step information. In this embodiment, the plurality of steps include a first step and a second step that is a step after the first step. The second process is a process that is affected by the delay if the work in the first process is delayed. These relationships are set in advance as process information.
 サーバ100は、S203において、第1の工程に対応するバーチャートと、第2の工程に対応するバーチャートとを繋ぐ画像を生成する。その結果、表示部221において工程表を表示する際に、第1の工程に対応する第1のバーチャートと、第2の工程に対応する第2のバーチャートとを繋ぐ画像が表示される。このようにすることで、ある工程(第1の工程)において遅延が発生したときに、遅延により影響を及ぼす工程(第2の工程)を直感的に把握することができる。 In S203, the server 100 generates an image that connects the bar chart corresponding to the first step and the bar chart corresponding to the second step. As a result, when displaying the process chart on the display unit 221, an image connecting the first bar chart corresponding to the first process and the second bar chart corresponding to the second process is displayed. By doing so, when a delay occurs in a certain process (first process), it is possible to intuitively understand which process (second process) is affected by the delay.
 図5の例では、4月1日~4月2日の2階の機器据付、および、4月3日~4月4日の3階の機器据付は、いずれもB社が担当しており、2階の機器据付が終了した翌日に3階の機器据付を行う必要がある。 In the example in Figure 5, Company B is in charge of equipment installation on the second floor from April 1st to April 2nd, and equipment installation on the third floor from April 3rd to April 4th. , it is necessary to install the equipment on the third floor the day after the equipment installation on the second floor is completed.
 2階の機器据付(第1の工程)が遅延した場合、3階の機器据付(第2の工程)に着手できず、3階の機器据付も遅延してしまう可能性がある。このように、ある工程(第1の工程)が遅延した場合、次の工程(第2の工程)に影響を及ぼす可能性のある場合、「関連する作業」として、この2つの工程間を線で繋ぐ画像(ここでは、第1の工程から第2の工程に向けての矢印の画像)を表示している。 If the second floor equipment installation (first process) is delayed, the third floor equipment installation (second process) may not be able to begin, and the third floor equipment installation may also be delayed. In this way, if a certain process (first process) is delayed and there is a possibility that the next process (second process) will be affected, a line is drawn between these two processes as "related work". (here, an image of an arrow pointing from the first step to the second step) is displayed.
 さらに、C社は、4月3日~4月8日の2階の配管工事の終了後、4月9日~4月12日に3階の配管工事が予定されている。この場合も、2階の配管工事が遅延した場合、3階の配管工事に着手できない可能性がある。この場合も、この2つの工程も「関連する作業」であることが示されている。 Furthermore, after completing the piping work on the second floor from April 3rd to April 8th, Company C is scheduled to carry out piping work on the third floor from April 9th to April 12th. In this case as well, if the piping work on the second floor is delayed, there is a possibility that the piping work on the third floor cannot be started. In this case, these two steps are also shown to be "related operations."
 一方、2階の機器据付(B社)の作業が遅延したとしても、2階の配管工事(C社)は予定通り4月3日から着手可能である。このため、この2つの工程は「関連する作業」として設定されていない。 On the other hand, even if the equipment installation work on the second floor (Company B) is delayed, the plumbing work on the second floor (Company C) can be started on April 3rd as scheduled. Therefore, these two processes are not set as "related works".
 次に、4月9日~4月10日に2階の配線工事(D社)、4月11日~4月16日に2階の保温工事(E社)、4月17日~4月22日に3階の保温工事(E社)が予定されている。本工事においては、2階の配線工事が終了しないと2階の保温工事に着手できない。このため、これらの工程も「関連する作業」であることが示されている。また、E社は、2階の保温工事が終了した翌日から3階の保温工事に着手する必要があるため、これらの工程も「関連する作業」であることが示されている。 Next, from April 9th to April 10th, wiring work on the second floor (Company D), insulation work on the second floor (Company E) from April 11th to April 16th, and from April 17th to April 10th. Thermal insulation work (Company E) is scheduled for the 3rd floor on the 22nd. During this construction work, insulation work on the second floor cannot begin until the wiring work on the second floor is completed. For this reason, these steps are also shown to be "related work." Furthermore, since Company E needs to start insulation work on the third floor the day after the insulation work on the second floor is completed, these processes are also shown to be "related work."
 また、D社は、4月9日~4月10日の2階の配線工事の後、4月15日~4月16日に3階の配線工事を行う。間に2日の余裕があるもの、この例では、次の工程に影響を及ぼす可能性があると判断されているため、これらの工程も「関連する作業」であることが示されている。最後に、4月23日~4月24日に2階および3階でF社による試運転が予定されている。 In addition, Company D will conduct wiring work on the third floor from April 15th to April 16th after wiring work on the second floor from April 9th to April 10th. In this example, it is determined that there is a two-day margin between the two processes, which may affect the next process, so these processes are also shown to be "related work." Finally, a trial run by Company F is scheduled for April 23rd to April 24th on the second and third floors.
 図4に戻り、サーバ100は、S204において、高負荷状態である工程に対応するバーチャート画像を赤色に設定する。その際、バーチャート画像全体を赤色に表示してもよいし、高負荷状態である期間(日)のみを赤色にして表示してもよい。サーバ100は、S205において、第1の工程の負荷状態が高負荷状態であるときに、第2の工程に対応するバーチャートをピンク色に設定する。 Returning to FIG. 4, in S204, the server 100 sets the bar chart image corresponding to the process in the high load state to red. At this time, the entire bar chart image may be displayed in red, or only the period (day) in a high load state may be displayed in red. In S205, the server 100 sets the bar chart corresponding to the second process to pink when the load state of the first process is a high load state.
 表示部221は、第1の工程の負荷状態が高負荷状態であるときは、第1の工程の負荷状態が高負荷状態でないときとは異なる第1の態様(赤色)で第1のバーチャートを表示するようにしている。このようにすることで、施工管理者は、直感的に担当者の負荷状態を把握することができる。 The display unit 221 displays the first bar chart in a first mode (red) when the load state of the first process is a high load state, which is different from when the load state of the first process is not a high load state. is displayed. By doing so, the construction manager can intuitively grasp the load status of the person in charge.
 そして、表示部221は、第1の工程の負荷状態が高負荷状態であるときに、第1のバーチャートを第1の態様(赤色)で表示するとともに、第2のバーチャートを第2の態様(ピンク色)で表示するようにしている。このようにすることで、施工管理者は、高負荷状況によって遅延が発生しそうな工程と、この工程に影響を受けて遅延が発生し得る工程とを直感的に把握することができる。これにより、これらの工程のスケジュールの見直し、負荷調整等の検討を素早く行うことができる。 Then, when the load state of the first step is a high load state, the display unit 221 displays the first bar chart in the first mode (red) and displays the second bar chart in the second mode. It is displayed in pink color. By doing so, the construction manager can intuitively grasp which processes are likely to be delayed due to high load conditions and which processes are likely to be delayed due to the influence of these processes. This makes it possible to quickly review the schedules of these processes and consider load adjustments.
 図5の例においては、4月10日の2階の配線工事(第1の工程)において負荷状態が高負荷状態であると判断されているとする。この場合、4月10日の2階の配線工事(第1の工程)のバーチャートを赤色で表示する。なお、この工程のバーチャート全体を赤色で表示してもよい。そして、この工程に「関連する作業」であると設定されている、2階の保温工事(第2の工程)のバーチャートおよび3階の配線工事(第2の工程)のバーチャートをそれぞれピンク色で表示する。 In the example of FIG. 5, it is assumed that the load state is determined to be a high load state during the wiring work on the second floor (first step) on April 10th. In this case, the bar chart for the second floor wiring work (first process) on April 10th is displayed in red. Note that the entire bar chart of this step may be displayed in red. Then, the bar chart for the insulation work on the second floor (second process) and the bar chart for the wiring work on the third floor (second process), which are set to be "related work" to this process, are highlighted in pink. Display in color.
 また、4月15日の2階の保温工事において負荷状態が高負荷状態であると判断されているとする。この場合、4月15日の2階の保温工事のバーチャートを赤色で表示する。なお、2階の保温工事のバーチャート全体を赤色で表示してもよい。そして、この工程に「関連する作業」であると設定されている3階の保温工事のバーチャートをピンク色で表示する。 Also, assume that the load state is determined to be high during the insulation work on the second floor on April 15th. In this case, the bar chart for the insulation work on the second floor on April 15th is displayed in red. Note that the entire bar chart for the insulation work on the second floor may be displayed in red. Then, a bar chart of the third floor insulation work, which is set as "work related" to this process, is displayed in pink.
 本日(4月9日)において実施中あるいは実施が予定されている工程は、原則として、「予定作業」として、バーチャートが水色で表示される。2階の配線工事は、実施中(進捗率は50%)であるため、水色で表示される。ただし、上記のように赤色またはピンク色で表示される場合には、これらの色の表示が優先される。また、3階の配管工事も、実施中(進捗率は25%)であるため、水色で表示されている。4月10日以降に予定されている工程については、未着手であるため、進捗率の欄にはその旨が表示される。4月23日~4月24日に予定されている2階および3階の試運転は、バーチャートが水色で表示されている。 As a general rule, processes that are being performed or scheduled to be performed today (April 9th) are displayed as "scheduled work" on the bar chart in light blue. The wiring work on the second floor is currently being carried out (progress rate is 50%), so it is displayed in light blue. However, when displayed in red or pink as described above, display in these colors takes priority. Additionally, the plumbing work on the third floor is currently being carried out (progress rate is 25%), so it is displayed in light blue. Processes scheduled after April 10th have not yet been started, so that fact is displayed in the progress rate column. The bar chart for the second and third floor test runs scheduled for April 23rd to April 24th is displayed in light blue.
 図4に戻り、サーバ100は、S206において、各バーチャートに、担当者のスケジュール情報を対応付ける。サーバ100は、S207において、表示情報(工程表等)を生成し、表示情報生成処理を終了する。図5の例では、表示情報として工程表91が表示部221に表示される。 Returning to FIG. 4, in S206, the server 100 associates schedule information of the person in charge with each bar chart. The server 100 generates display information (work schedule, etc.) in S207, and ends the display information generation process. In the example of FIG. 5, a process chart 91 is displayed on the display section 221 as display information.
 次に、図6を用いて、各バーチャートに対応付けられた担当者のスケジュール情報(S206参照)を表示する例を説明する。スケジュール情報は、ユーザの指定により表示または非表示を切り替え可能とし、図5はスケジュール情報を非表示に設定された例であり、図6はスケジュール情報を表示に設定された例であるものとする。 Next, an example of displaying schedule information (see S206) of the person in charge associated with each bar chart will be described using FIG. 6. The schedule information can be switched between display and non-display according to the user's specifications, and FIG. 5 shows an example in which the schedule information is set to be hidden, and FIG. 6 shows an example in which the schedule information is set to be displayed. .
 図6は、工程表の一例を示す図である。上述のように、D社は4月9日~4月10日に2階の配線工事を実施する。たとえば、2階の配線工事を行うD社の担当者(この例では、1人で作業を行うものとする)の4月10日のスケジュールには、「8:00-17:00 Xビル 配線工事」、「18:00-20:00 Yビル 見積書作成」、「20:00-22:00 Zビル 図面作成」が登録されている。 FIG. 6 is a diagram showing an example of a process chart. As mentioned above, Company D will carry out wiring work on the second floor from April 9th to April 10th. For example, the schedule for April 10th of the person in charge of Company D doing the wiring work on the second floor (in this example, one person is working alone) is ``8:00-17:00 X building wiring "Construction", "18:00-20:00 Y Building Estimate Creation", and "20:00-22:00 Z Building Drawing Creation" are registered.
 表示部221は、複数の担当者の各々が担当する工程に対応するバーチャートに対応付けてスケジュール情報を表示している。本例では、2階の配線工事に対応するバーチャートに、上記のスケジュール情報を対応付けて表示している。その際、4月10日のスケジュールであることが分かるように、バーチャートの4月10日の領域に対応させて、スケジュール情報を表示している。なお、その際、併せて担当者名を表示するようにしてもよい。 The display unit 221 displays schedule information in association with bar charts corresponding to the processes each of the plurality of persons in charge is responsible for. In this example, the above schedule information is displayed in association with a bar chart corresponding to the wiring work on the second floor. At this time, the schedule information is displayed in correspondence with the area of April 10th on the bar chart so that it can be seen that the schedule is for April 10th. Note that at this time, the name of the person in charge may also be displayed.
 これにより施工管理者は、担当者の負荷状況を一目で把握することができる。D社の担当者は、4月10日の8時~17時に本ビル(Xビル)において2階の配線工事を行った後、オフィスに戻って、さらに、18時~22時に他のビル(Yビル、Zビル)の見積書および図面の作成作業を行う必要がある。 This allows the construction manager to understand the load status of the person in charge at a glance. After completing the wiring work on the second floor of the main building (Building It is necessary to prepare estimates and drawings for Building Y and Building Z.
 このように、D社の担当者は、Xビルの作業以外にも、4月10日には22時まで作業を行う必要がある。仮に、Xビルでの作業が遅延した場合、18時からY,Zビルに関する作業が予定されているため、Xビルでの作業終了時刻を延長することができず、次の日に作業を持ち越してしまう(作業が遅延する)可能性が考えられる。 In this way, in addition to working on Building X, the person in charge at Company D needs to work until 10pm on April 10th. If the work at Building X is delayed, work on Buildings Y and Z is scheduled to start from 6:00 pm, so the end time of the work at Building X cannot be extended, and the work will be carried over to the next day. There is a possibility that the work will be delayed (work will be delayed).
 このような場合、4月10日において、2階の配線工事の負荷状態が高負荷状態となると判断して、バーチャートが赤色で表示されている。さらに、図5において説明したように、影響が生じ得る工程のバーチャートがピンク色で表示されている。なお、図6の例では、図示を省略しているが、その他の工程においても、スケジュール情報を対応付けて表示される。高負荷状態となるか否かの判断等の詳細については、図10~図12を用いて後述する。 In such a case, on April 10th, it was determined that the load state of the wiring work on the second floor would be a high load state, and the bar chart was displayed in red. Furthermore, as explained in FIG. 5, the bar chart of processes that may be affected is displayed in pink. Although not shown in the example of FIG. 6, schedule information is displayed in association with other processes as well. Details of the determination of whether or not a high load state will occur will be described later using FIGS. 10 to 12.
 このように、表示部221は、複数の担当者の各々が担当する工程に対応付けて負荷状態を表示している。加えて、表示部221は、複数の担当者の各々が担当する工程に対応付けてスケジュール情報も表示可能である。 In this way, the display unit 221 displays the load status in association with the process that each of the plurality of persons in charge is in charge of. In addition, the display unit 221 can also display schedule information in association with the processes each of the plurality of persons in charge is in charge of.
 このようにすることで、施工管理者は、担当者にヒヤリングを行ったり、日々の作業内容を記録する作業日報を確認したり、現場の状況を確認しなくても、担当者の負荷状態を正確かつ直感的に把握することができる。また、スケジュール情報には、対象となる工事と関係のないスケジュールが含まれる。本例においては、施工管理者が管理するXビル以外のYビルおよびZビルに関するスケジュールも含めた負荷状況を把握することができる。他の工事の情報は、雑談程度で話に出ることがあるが、通常は把握しにくい情報である。本実施の形態においては、このような情報であっても、工程表に表示されるとともに、負荷状態の判定にも用いることができる。施工管理者は、このような負荷状態およびスケジュール情報を、施工管理者が別途資料を作成したり、頭の中で情報を再構築する必要なく、また、画面やシステムを切り替えることなく、1つの画面上で容易に把握することができる。さらに、これらの情報に基づき、作業時間の延長の可否、高負荷状態の工程が後の工程に与える影響など、従来把握できなかった情報から工程全体への影響を推定することができるようになる。その結果、施工管理者は、作業の品質を維持しつつ安全に全ての作業が期日までに完了するよう対策を講じること可能である。これにより、経験が乏しい施工管理者であっても、効率よく施工管理を行うことができる。 By doing this, the construction manager can check the load status of the person in charge without having to interview the person in charge, check the daily work report that records the daily work contents, or check the site situation. Can be grasped accurately and intuitively. Furthermore, the schedule information includes schedules that are unrelated to the target construction work. In this example, it is possible to grasp the load situation including schedules for Building Y and Building Z other than Building X managed by the construction manager. Information about other construction projects may come up in small talk, but it is usually difficult to grasp. In this embodiment, even such information is displayed on the process chart and can also be used for determining the load state. The construction manager can store such load status and schedule information in one place without having to create separate materials or reconstruct the information in his or her head, or without having to switch screens or systems. It can be easily understood on the screen. Furthermore, based on this information, it will be possible to estimate the impact on the entire process from information that was previously impossible to grasp, such as whether or not work time can be extended, and the impact of a high-load process on subsequent processes. . As a result, the construction manager can take measures to ensure that all work is completed safely and by the deadline while maintaining the quality of the work. This allows even an inexperienced construction manager to efficiently manage construction.
 <第2実施形態>
 図7は、第2実施形態に係る施工管理システム1のハードウェア構成を示す図である。第1実施形態において、制御部111は、第2推定部121と、生成部123とが実行する処理を実行可能に構成されている。第2実施形態においては、さらに、制御部111は、第1推定部122と、通知部124とが実行する処理を実行可能である。以下、第1実施形態と共通する部分は、説明を省略することがある。
<Second embodiment>
FIG. 7 is a diagram showing the hardware configuration of the construction management system 1 according to the second embodiment. In the first embodiment, the control unit 111 is configured to be able to execute the processes executed by the second estimation unit 121 and the generation unit 123. In the second embodiment, the control unit 111 is further capable of executing the processing executed by the first estimation unit 122 and the notification unit 124. Hereinafter, descriptions of parts common to the first embodiment may be omitted.
 第2推定部121は、スケジュール管理システム400からスケジュール情報を取得する。第2推定部121は、記憶部112から第2入力情報を取得する。第2推定部121は、第2入力情報とスケジュール情報とに基づき負荷状態を決定する。 The second estimation unit 121 acquires schedule information from the schedule management system 400. The second estimation unit 121 acquires second input information from the storage unit 112. The second estimation unit 121 determines the load state based on the second input information and schedule information.
 通知部124は、第1の工程の負荷状態が高負荷状態であるときに、工事を管理する管理者、第1の工程を担当する担当者および第2の工程を担当する担当者に、負荷状態を含めた情報を通知する。このような通知は、たとえば、事前に登録された管理者および担当者のメールアドレス宛てにメールを送信することで行えばよい。このようにすることで、工事の遅延状況を素早く把握することができるとともに、遅延解消のために必要な当事者間での調整の準備をスムーズに行うことができる。 When the load state of the first process is high, the notification unit 124 notifies the manager who manages the construction, the person in charge of the first process, and the person in charge of the second process to Notify information including status. Such notification may be performed, for example, by sending an email to the email address of the administrator and the person in charge who have been registered in advance. By doing so, it is possible to quickly grasp the status of construction delays, and it is also possible to smoothly prepare for coordination between the parties involved to eliminate the delay.
 第1推定部122は、記憶部112から後述する第1入力情報を取得する。第1推定部122は、負荷状態と第1入力情報に基づき後述する対策情報を決定する。対策情報は、高負荷状態が発生したときに、どのように対策すべきか(作業期間延長、人員増強等)を示す複数の対策案の情報である。 The first estimation unit 122 acquires first input information, which will be described later, from the storage unit 112. The first estimation unit 122 determines countermeasure information, which will be described later, based on the load state and the first input information. The countermeasure information is information on a plurality of countermeasure plans indicating what countermeasures should be taken (extension of work period, increase in personnel, etc.) when a high load state occurs.
 生成部123は、記憶部112から後述する工程情報を取得する。生成部123は、工程情報と対策情報と負荷状態に基づき工程表を生成する。端末200の表示部221は、生成した工程表を表示する。 The generation unit 123 acquires process information, which will be described later, from the storage unit 112. The generation unit 123 generates a process chart based on process information, countermeasure information, and load status. The display unit 221 of the terminal 200 displays the generated process chart.
 以下、フローチャートを用いて具体的に説明する。図8は、メイン処理のフローチャートである。このフローチャートに示される処理は、端末200からの要求に基づき起動するようにすればよい。 A detailed explanation will be given below using a flowchart. FIG. 8 is a flowchart of the main processing. The processing shown in this flowchart may be activated based on a request from the terminal 200.
 メイン処理が開始すると、サーバ100は、S301において、スケジュール管理システム400からスケジュール情報を取得する。サーバ100は、S302において、記憶部112から第2入力情報を取得する。サーバ100は、S303において、スケジュール情報および第2入力情報を学習済モデル163に入力し、学習済モデル163から出力される負荷状態を取得する。 When the main process starts, the server 100 acquires schedule information from the schedule management system 400 in S301. The server 100 acquires the second input information from the storage unit 112 in S302. In S303, the server 100 inputs the schedule information and the second input information to the learned model 163, and acquires the load state output from the learned model 163.
 サーバ100は、S304において、記憶部112から第1入力情報を取得する。サーバ100は、S305において、負荷状態および第1入力情報を学習済モデル173に入力し、学習済モデル173から出力される対策情報を取得する。 The server 100 acquires the first input information from the storage unit 112 in S304. In S305, the server 100 inputs the load state and the first input information to the learned model 173, and acquires countermeasure information output from the learned model 173.
 サーバ100は、S306において、記憶部112から工程情報を取得する。サーバ100は、S307において、表示情報生成処理を実行し、表示情報(工程表等)を生成する。 The server 100 acquires process information from the storage unit 112 in S306. In S307, the server 100 executes display information generation processing and generates display information (work schedule, etc.).
 サーバ100は、S308において、表示情報に対策情報を対応付ける。図9は、工程表の一例を示す図である。図9の工程表93には、対応付けられた対策情報が表示されている。 In S308, the server 100 associates countermeasure information with display information. FIG. 9 is a diagram showing an example of a process chart. The process chart 93 in FIG. 9 displays associated countermeasure information.
 図9の例では、2階の配線工事(第1の工程)において負荷状態が高負荷状態となっている。また、2階の保温工事および3階の保温工事が第2の工程として設定されている。 In the example of FIG. 9, the load state is high during the wiring work on the second floor (first step). In addition, heat insulation work on the second floor and heat insulation work on the third floor are set as the second process.
 上述のように、2階の配線工事を行うD社の担当者の4月10日のスケジュールとして、「8:00-17:00 Xビル 配線工事」、「18:00-20:00 Yビル 見積書作成」、「20:00-22:00 Zビル 図面作成」が表示されている。 As mentioned above, the schedule for April 10th of the person in charge of Company D, who will be conducting wiring work on the second floor, is "8:00-17:00 Wiring work in Building X" and "18:00-20:00 Building Y" ``Create quotation'' and ``20:00-22:00 Z building drawing creation'' are displayed.
 本例では、高負荷状態となった2階の配線工事に対応付けられた対策情報が表示されている。具体的には、対策情報として、「対策案1」が「D社のスケジュールを延長」および「E社の人員増加」であり、「対策案2」が「D社の人員増加」である。 In this example, countermeasure information is displayed that is associated with the wiring work on the second floor that is under high load. Specifically, as the countermeasure information, "Countermeasure Plan 1" is "Extend the schedule of Company D" and "Increase in the number of personnel at Company E," and "Countermeasure Plan 2" is "Increase in the number of personnel at Company D."
 対策案1では、D社の担当者のスケジュールが逼迫しているため、予定通り4月10日までに2階の配線工事を完了することができないと推測している。また、この時期、D社には人員に余裕がない。このため、D社のスケジュールを4月11日以降に延長することを推奨しており、これによってE社の2階の保温工事の開始が遅れることになる。また、この時期、E社には人員に余裕がある。このため、対策案1では、さらに、E社の2階の保温工事の作業人数を増加させることで、予定通り2階の保温工事を完了させようとしている。 In plan 1, it is estimated that due to the tight schedule of the person in charge at Company D, it will not be possible to complete the wiring work on the second floor by April 10 as planned. Also, during this period, Company D does not have enough personnel. For this reason, we are recommending that Company D's schedule be extended beyond April 11th, which will delay Company E's start of insulation work on the second floor. Also, during this period, Company E has plenty of personnel. Therefore, in Countermeasure Plan 1, the number of people working on the second floor insulation work at Company E is increased in order to complete the second floor insulation work as scheduled.
 対策案2では、E社の2階の保温工事の作業人数を増やすことができなかったケースを想定している。この場合、D社は、予定通り4月10日までに2階の配線工事を完了しなければならない。このため、対策案2では、第2の案として、D社の人員増加を推奨している。 Measure plan 2 assumes a case where it is not possible to increase the number of workers working on the insulation work on the second floor of Company E. In this case, Company D must complete the wiring work on the second floor by April 10 as scheduled. For this reason, the second plan for countermeasures is to recommend an increase in the number of employees at Company D.
 施工管理者は、上記対策情報に基づき、D社およびE社と作業の調整を行う。そして、調整した結果として、対策案1および対策案2のいずれを採用するかを決定する。 The construction manager will coordinate the work with Company D and Company E based on the above countermeasure information. Then, as a result of the adjustment, it is determined which of countermeasure plan 1 and countermeasure plan 2 to adopt.
 図8に戻り、サーバ100は、S309において、表示情報(工程表等)を表示部221に対して出力する。これにより、表示部221において、図9で示したような工程表93が表示される。 Returning to FIG. 8, the server 100 outputs display information (process chart, etc.) to the display unit 221 in S309. As a result, a process chart 93 as shown in FIG. 9 is displayed on the display section 221.
 サーバ100は、S310において、通知部124は、第1の工程の負荷状態が高負荷状態であるときに、管理者、高負荷状態である工程(第1の工程)および関連する工程(第2の工程)の担当者に負荷状態を通知し、メイン処理を終了する。 In S310, the notification unit 124 of the server 100 notifies the administrator, the process in the high load state (the first process), and the related process (the second process) when the load state of the first process is the high load state. The person in charge of the process) is notified of the load status, and the main process ends.
 上記例においては、管理者と、高負荷状態である2階の配線工事の担当者(D社)と、関連する工程である2階の保温工事の担当者(E社)および3階の配線工事の担当者(D社)とに対して、その旨が通知される。これにより、工事の遅延状況を素早く把握することができるとともに、遅延解消のために必要な当事者間での調整の準備をスムーズに行うことができる。 In the above example, the administrator, the person in charge of the wiring work on the second floor (Company D), which is under high load, the person in charge of the insulation work on the second floor (Company E), which is a related process, and the person in charge of the wiring work on the third floor. The person in charge of construction (Company D) will be notified of this. This makes it possible to quickly grasp the status of construction delays and smoothly prepare for coordination between the parties involved to eliminate delays.
 本実施の形態において、高負荷状態であるか否かの判断、および、高負荷状態であるときの対策情報(複数の対策案)の決定は、機械学習が施された学習済モデルを用いて行われる。なお、学習済モデルを用いてこれらを決定または判断するものに限らず、その他の推定モデルを用いて決定または判断するものであってもよいし、何らかのルールに基づき決定または判断するものであってもよい。以下、図10~図12を用いて、本実施の形態で行われる学習処理について説明する。 In this embodiment, a learned model that has been subjected to machine learning is used to determine whether or not the load is high and to determine countermeasure information (multiple countermeasure plans) when the load is high. It will be done. Note that these are not limited to those that are determined or judged using a trained model, but may be determined or judged using other estimation models, or determined or judged based on some kind of rules. Good too. The learning process performed in this embodiment will be described below with reference to FIGS. 10 to 12.
 図10は、学習用データセット160を説明するための図である。上記の、スケジュール情報および第2入力情報(入力データ)と、負荷状態(出力データ)との間には、一定の相関関係がある。 FIG. 10 is a diagram for explaining the learning data set 160. There is a certain correlation between the above schedule information and second input information (input data) and the load state (output data).
 このため、本実施の形態においては、AI(Artificial Intelligence)を用いた「負荷状態」の決定を行う。たとえば、入力データおよび出力データの組合せからなる学習用データに基づいて、入力Xから出力Yを推論する学習済モデルを生成する。たとえば、ニューラルネットワークを用いた教師あり学習を用いて、学習を行うことができる。モデル生成に用いられる学習アルゴリズムとしては、特徴量そのものの抽出を学習する、深層学習(Deep Learning)を用いることもできる。 Therefore, in this embodiment, the "load state" is determined using AI (Artificial Intelligence). For example, a learned model that infers output Y from input X is generated based on learning data consisting of a combination of input data and output data. For example, learning can be performed using supervised learning using a neural network. As a learning algorithm used for model generation, deep learning, which learns how to extract the feature amount itself, can also be used.
 本実施の形態では、記憶部112は、学習用データセット160および学習済モデル163を記憶する。制御部111は、スケジュール情報および第2入力情報を第2学習済モデル(学習済モデル163)に入力することで、学習済モデル163から負荷状態等を推定結果として出力する。 In this embodiment, the storage unit 112 stores a learning data set 160 and a learned model 163. The control unit 111 inputs the schedule information and the second input information to the second learned model (learned model 163), and outputs the load state and the like as an estimation result from the learned model 163.
 学習済モデル163は、スケジュール情報および第2入力情報が入力された際に、負荷状態等を推定結果として出力するように、教師データを用いた機械学習処理が施されたモデルである。第2入力情報は、複数の担当者の各々のスケジュールの優先度を示す情報と、複数の担当者の各々が所属する会社の情報と、複数の工程の各々の情報とを含む。 The learned model 163 is a model that has been subjected to machine learning processing using teacher data so that when the schedule information and the second input information are input, the load state and the like are output as estimation results. The second input information includes information indicating the schedule priority of each of the plurality of persons in charge, information on the company to which each of the plurality of persons in charge belongs, and information on each of the plurality of processes.
 具体的には、上述した入出力データのセット(学習用データセット160)を用いて、学習処理を行う。そして、得られた学習済モデルを用いて、スケジュール情報および第2入力情報を入力データし、負荷状態等を出力データ(推定結果)とする推定処理を行う。入出力データのセットは、過去に工事を行った際の履歴情報として、サーバ100の記憶部112に日々蓄積されている。 Specifically, the learning process is performed using the above-mentioned input/output data set (learning data set 160). Then, using the obtained trained model, an estimation process is performed in which the schedule information and the second input information are input data, and the load state and the like are output data (estimated results). A set of input/output data is accumulated on a daily basis in the storage unit 112 of the server 100 as historical information on past construction work.
 上記の「入力データ」および「出力データ」は、図10に示す通りである。図10に示すように、入力データ161は、スケジュール情報および第2入力情報とを含む。出力データ162は、負荷状態と調整結果とを含む。 The above "input data" and "output data" are as shown in FIG. As shown in FIG. 10, input data 161 includes schedule information and second input information. Output data 162 includes the load status and adjustment results.
 学習用データセット160としては、入力データ161に対する出力データ162の組合せを用意する。ここで、出力データ162が正解データとなる。以下、入力データ161に対する出力データ162の組合せの例について説明する。 As the learning data set 160, a combination of input data 161 and output data 162 is prepared. Here, the output data 162 becomes the correct data. Examples of combinations of input data 161 and output data 162 will be described below.
 たとえば、入力データは、スケジュールの優先度、会社情報(担当会社等)、工程情報(作業内容、実施期間、実施期間における担当者のスケジュール情報、実施時期等)等であり、出力データは、調整結果(追加人員、作業延長日数)、負荷状態等である。スケジュールの優先度は、担当者が登録している各スケジュールの優先度(高、中、低を設定可能)であり、この優先度は、スケジュール管理システム400において事前に設定できるものとする。 For example, the input data includes schedule priority, company information (company in charge, etc.), process information (work content, implementation period, schedule information of the person in charge during the implementation period, implementation timing, etc.), and the output data includes adjustments. Results (additional personnel, extended work days), load status, etc. The schedule priority is the priority of each schedule registered by the person in charge (high, medium, or low can be set), and this priority can be set in advance in the schedule management system 400.
 たとえば、スケジュールの優先度「作業A:優先度高」、担当会社「D社」、作業内容「配線工事」、実施期間「3月1日」、実施期間における担当者のスケジュール情報「3月1日:8~17時 配線工事、18~22時 作業A」、実施時期「3月」であり、出力データは、追加人員「0人」、作業延長日数「1日」、負荷状態「高負荷状態」である。なお、工事の担当者が複数人いる場合は、複数人のスケジュール情報が取得される。 For example, the schedule priority is "Work A: High Priority", the company in charge is "Company D", the work content is "Wiring work", the implementation period is "March 1st", and the schedule information of the person in charge during the implementation period is "March 1st". Sunday: 8:00 to 17:00 Wiring work, 18:00 to 22:00 Work A", implementation time "March", output data is "0 additional personnel", number of work extension days "1 day", load status "High load "state". Note that if there are multiple people in charge of the construction work, schedule information for the multiple people is acquired.
 上記において、配線工事の実施期間において、D社の担当者は、8~17時の配線工事の後に、優先度の高い作業Aが予定されている。この場合、配線工事の作業が思いがけず遅れたとしても、その後に予定されている優先度の作業Aを行わなければならないため、当日中に予定の作業を完了させることができない。このため、結果として、翌日まで配線工事が長引き、作業延長日数は「1日」となったとする。また、3月は、D社の繁忙期であるため、追加人員を出すことができなかったとする。 In the above, during the wiring work implementation period, the person in charge of company D is scheduled to perform high priority work A after wiring work from 8:00 to 17:00. In this case, even if the wiring work is unexpectedly delayed, the scheduled work A cannot be completed on the same day because the scheduled priority work A must be performed afterwards. As a result, it is assumed that the wiring work is prolonged until the next day, and the number of extended work days is "1 day". Also, suppose that March is a busy season for Company D, so it is not possible to hire additional personnel.
 ここで、本実施の形態においては、データ管理者が、上記入出力データを確認した上で、負荷状態を「高負荷状態」または「通常状態」に設定するものとする。たとえば、対象となる工事以外に優先度の高い作業が所定時間(所定比率)以上スケジュール登録されている場合に、負荷状態を「高負荷状態」に設定してもよい。さらに、スケジュール以外の情報も加味してもよい。たとえば、追加人員が1人以上ある場合、あるいは、作業延長日数が1日以上ある場合は、スケジュールの登録状況とは無関係に負荷状態を「高負荷状態」に設定するようにしてもよい。また、上記ルールを用いて、自動的に負荷状態が設定されるようにしてもよい。 Here, in this embodiment, the data administrator shall set the load state to "high load state" or "normal state" after confirming the above input/output data. For example, the load state may be set to "high load state" when work with a high priority other than the target construction work is registered in the schedule for a predetermined time (predetermined ratio) or more. Furthermore, information other than the schedule may also be taken into consideration. For example, if there is one or more additional personnel, or if there is one or more days of work extension, the load state may be set to "high load state" regardless of the schedule registration status. Further, the load state may be automatically set using the above rules.
 別の例として、スケジュールの優先度「作業B:優先度低」、作業内容「保温工事」、実施期間「2月3日」、担当会社「E社」、実施期間における担当者のスケジュール情報「2月3日:8~17時 保温工事、18~22時 作業B」、実施時期「2月」であり、出力データは、追加人員「0人」、作業延長日数「0日」、負荷状態「通常状態」であったとする。 As another example, the schedule priority "Work B: Low priority", the work content "thermal insulation work", the implementation period "February 3rd", the company in charge "Company E", the schedule information of the person in charge during the implementation period " February 3rd: 8:00 to 17:00 Heat insulation work, 18:00 to 22:00 Work B", implementation time is "February", output data is "0 additional personnel", number of work extension days "0 days", load status Assume that it is in a "normal state".
 上記において、保温工事の実施期間において、E社の担当者は、8~17時の保温工事の後に、優先度の低い作業Bが予定されている。この場合、保温工事の作業が思いがけず遅れたとしても、優先度の低い作業Bを翌日にまわすことで、当日中に保温工事を完了させることができる。また、2月は、E社の繁忙期でないため、作業が遅れそうな場合は、人員を追加することもできる。 In the above, during the period for carrying out the insulation work, the person in charge of Company E is scheduled to perform work B, which has a low priority, after the insulation work from 8:00 to 17:00. In this case, even if the heat insulation work is unexpectedly delayed, the heat insulation work can be completed on the same day by moving work B, which has a lower priority, to the next day. Furthermore, since February is not a busy season for Company E, additional personnel can be added if the work is likely to be delayed.
 以上説明したように、担当者のスケジュールに優先度の高い作業が多く登録されていれば、高負荷状態となり、作業の遅延または人員の追加が発生する可能性が高くなる。このように、担当者のスケジュールと負荷状態とは一定の相関関係がある。また、特定の会社(たとえば、規模の小さい会社)、特定の種類の工程(機材トラブルが発生しやすい工程)、実施時期(たとえば、繁忙期)によっては、作業の遅延が発生やすい(高負荷状態になりやすい)可能性がある。このため、これらの情報と負荷状態とも一定の相関関係があると言える。 As explained above, if many high-priority tasks are registered in the schedule of the person in charge, the workload will be high, and there is a high possibility that work will be delayed or additional personnel will be added. In this way, there is a certain correlation between the schedule of the person in charge and the load status. Furthermore, depending on the specific company (for example, a small company), the specific type of process (process where equipment troubles are likely to occur), or the implementation period (for example, during a busy season), work delays may occur (high load conditions). likely to occur). Therefore, it can be said that there is a certain correlation between this information and the load state.
 以上のことから、上述のような入出力データのセットを用いて学習処理を行った場合、得られた学習済モデルを用いることで、精度よく負荷状態を推測することができる。施工管理者は、高負荷状態である工程について、日程調整、人員追加等の調整を行うことができるため、期日までに工事を完了させることができる。このようにすることで、経験が乏しい施工管理者であっても、効率よく施工管理を行うことができる。 From the above, when learning processing is performed using the above-mentioned input/output data set, the load state can be estimated with high accuracy by using the obtained learned model. The construction manager can make adjustments such as adjusting schedules and adding personnel for processes that are under high load, so that the construction can be completed by the deadline. In this way, even a construction manager with little experience can manage construction efficiently.
 図11は、学習用データセットを説明するための図である。上記の、負荷状態および第1入力情報(入力データ)と、対策情報(出力データ)との間には、一定の相関関係がある。 FIG. 11 is a diagram for explaining the learning data set. There is a certain correlation between the above-mentioned load state and first input information (input data) and countermeasure information (output data).
 本実施の形態では、記憶部112は、学習用データセット170および学習済モデル173を記憶する。制御部111は、負荷状態および第1入力情報を第1学習済モデル(学習済モデル173)に入力することで、学習済モデル173から対策情報を推定結果として出力する。学習済モデル173は、負荷状態および第1入力情報が入力された際に、対策情報を推定結果として出力するように、教師データを用いた機械学習処理が施されたモデルである。 In this embodiment, the storage unit 112 stores a learning data set 170 and a learned model 173. The control unit 111 outputs countermeasure information from the learned model 173 as an estimation result by inputting the load state and the first input information to the first learned model (learned model 173). The learned model 173 is a model that has been subjected to machine learning processing using teacher data so that countermeasure information is output as an estimation result when the load state and first input information are input.
 第1入力情報は、複数の担当者の各々が所属する会社の情報と、複数の工程の各々の情報とを含む。対策情報は、高負荷状態が発生したときに、第1の工程および第2の工程に対する対策方法を示す情報である。 The first input information includes information on the company to which each of the plurality of persons in charge belongs, and information on each of the plurality of processes. The countermeasure information is information indicating a countermeasure method for the first process and the second process when a high load state occurs.
 対策方法は、第1の工程および第2の工程のいずれか一方または両方の作業期間を延長する方法と、第1の工程および第2の工程のいずれか一方または両方の作業人数を増やす方法とを含む。 Countermeasures include a method of extending the working period of either or both of the first process and the second process, and a method of increasing the number of workers in either or both of the first process and the second process. including.
 具体的には、上述した入出力データのセットを用いて、学習処理を行う。そして、得られた学習済モデルを用いて、負荷状態および第1入力情報を入力データし、対策情報を出力データ(推定結果)とする推定処理を行う。 Specifically, learning processing is performed using the above-mentioned input/output data set. Then, using the obtained trained model, an estimation process is performed in which the load state and the first input information are input data, and the countermeasure information is output data (estimation result).
 上記図9を用いて示した例では、高負荷状態である2階の配線工事(第1の工程)の対策方法として、「対策案1」が「D社(第1の工程)のスケジュールを延長」および「E社(第2の工程)の人員増加」であり、「対策案2」が「D社(第1の工程)の人員増加」である。 In the example shown in Figure 9 above, "Measure plan 1" is a countermeasure for wiring work on the second floor (first process), which is under high load. ``extension'' and ``increase in personnel at Company E (second process),'' and ``Countermeasure 2'' is ``increase in personnel at Company D (first process).''
 上記の「入力データ」および「出力データ」は、図11に示す通りである。図11に示すように、入力データ171は、負荷状態および第1入力情報を含む。出力データ172は、対策情報を含む。 The above "input data" and "output data" are as shown in FIG. 11. As shown in FIG. 11, the input data 171 includes the load state and first input information. The output data 172 includes countermeasure information.
 学習用データセット170として、入力データ171に対する出力データ172の組合せを用意する。ここで、出力データ172が正解データとなる。以下、入力データ171に対する出力データ172の組合せの例について説明する。 A combination of input data 171 and output data 172 is prepared as a learning data set 170. Here, the output data 172 becomes the correct data. Examples of combinations of input data 171 and output data 172 will be described below.
 たとえば、入力データは、第1の工程の担当会社、負荷状態、作業内容、実施時期、第2の工程の担当会社、作業内容、実施時期であり、出力データは、対策情報である。 For example, the input data is the company in charge of the first process, the load condition, the work content, the implementation time, the company in charge of the second process, the work content, and the implementation time, and the output data is countermeasure information.
 たとえば、第1の工程において、担当会社「D社」、負荷状態「高負荷状態」、作業内容「配線工事」、実施時期「3月」、第2の工程において、担当会社「E社」、作業内容「保温工事」、実施時期「3月」であり、出力データは、対策情報として、第1の工程の延長「1日」、第1の工程の増員「0人」、第2の工程の延長「0日」、第2の工程の増員「1人」であったとする。 For example, in the first process, the company in charge is "Company D", the load state is "high load state", the work content is "wiring work", the implementation period is "March", in the second process, the company in charge is "Company E", The work content is "thermal insulation work" and the implementation period is "March", and the output data includes countermeasure information such as an extension of the first process "1 day", an increase in the number of people for the first process "0 people", and the second process Assume that the extension of the process was ``0 days'' and the number of people added to the second process was ``1 person.''
 上記において、D社は3月が繁忙期であるため増員することができず、E社は3月が繁忙期でないため増員可能であったとする。このため、結果として、負荷が高いD社の作業を1日延長し、人員に余裕のあるE社は増員して予定より1日短い期間で保温工事を完了させたとする。あるいは、D社の従業員数が少ない場合は増員が難しくなるし、E社の従業員数が多い場合は増員しやすくなる。このように、担当会社および実施時期と、対策方法との間には一定の相関関係がある。また、1人でしか作業できないために増員することができない工程もあるため、工程の種類と対策方法とも一定の相関関係があると言える。 In the above, assume that Company D is unable to increase its staff because March is a busy season, and Company E was able to increase its staff because March is not a busy season. As a result, Company D, which has a heavy workload, has to extend its work by one day, and Company E, which has extra personnel, increases its staff and completes the insulation work in one day shorter than planned. Alternatively, if Company D has a small number of employees, it will be difficult to increase the number of employees, whereas if Company E has a large number of employees, it will be easier to increase the number of employees. In this way, there is a certain correlation between the company in charge, the implementation period, and the countermeasure method. In addition, there are some processes where only one person can work on the process and therefore it is not possible to increase the number of workers, so it can be said that there is a certain correlation between the type of process and the countermeasure method.
 このように負荷が高く調整が必要となる状況において、第1の工程と第2の工程とのうちいずれにおいて増員すべきかあるいは期間延長または期間短縮すべきかの判断に関し、入力データと出力データとで一定の相関関係がある。学習済モデル173を用いて対策方法を出力させる場合は、対策方法を1つ出力させるようにしてもよいし、可能性の高い順に、対策案1、対策案2・・・のように複数出力させるようにしてもよい。 In such a situation where the load is high and adjustments are required, input data and output data can be used to determine whether to increase the number of people in the first process or the second process, or to extend or shorten the period. There is a certain correlation. When outputting countermeasures using the trained model 173, one countermeasure may be output, or multiple countermeasures may be output in descending order of probability, such as countermeasure 1, countermeasure 2, etc. You may also do so.
 以上のことから、上述のような入出力データのセットを用いて学習処理を行った場合、得られた学習済モデルを用いることで、最適な対策案を決定することができる。施工管理者は、高負荷状態である工程について、日程調整、人員追加等の調整を行うことができるため、期日までに工事を完了させることができる。このようにすることで、経験が乏しい施工管理者であっても、効率よく施工管理を行うことができる。 From the above, when learning processing is performed using the input/output data set described above, the optimal countermeasure can be determined by using the obtained learned model. The construction manager can make adjustments such as adjusting schedules and adding personnel for processes that are under high load, so that the construction can be completed by the deadline. In this way, even a construction manager with little experience can manage construction efficiently.
 特に、入出力データセットが蓄積されればされるほど、AIによる学習が進み、より適切な対策方法を提示し、作業遅れなどをより的確に予測することができる。また、建設業界の労働人口の減少が進んでいることを鑑みると、作業者の増員あるいは入れ替え、工程の見直し等の判断ができる施工管理者を短期間で育成したいというニーズがある。本実施の形態による方法を活用することで、一定レベルの施工管理者を早期に育成することも可能である。 In particular, the more input/output data sets are accumulated, the more the AI learns, the more appropriate countermeasures can be presented, and work delays can be more accurately predicted. In addition, in view of the continuing decline in the working population in the construction industry, there is a need to quickly train construction managers who can make decisions such as increasing or replacing workers and reviewing processes. By utilizing the method according to this embodiment, it is also possible to quickly train construction managers at a certain level.
 図12は、学習処理のフローチャートである。以下、「ステップ」を単に「S」とも称する。ここでは、学習済モデル163を学習する処理について説明する。図12に示すように、学習処理が開始すると、サーバ100は、S401において、学習用データセット160の中から学習用データを選択し、処理をS402に進める。 FIG. 12 is a flowchart of the learning process. Hereinafter, the "step" will also be simply referred to as "S". Here, processing for learning the trained model 163 will be described. As shown in FIG. 12, when the learning process starts, the server 100 selects learning data from the learning data set 160 in S401, and advances the process to S402.
 サーバ100は、S402において、選択した学習用データを推定モデルに入力し、処理をS403に進める。サーバ100は、S403において、推定処理を実行し推定結果を出力し、処理をS404に進める。サーバ100は、S404において、推定結果と学習用データに対応する正解データとの誤差に基づき推定モデルのパラメータを更新し、処理をS405に進める。 In S402, the server 100 inputs the selected learning data to the estimation model, and advances the process to S403. In S403, the server 100 executes the estimation process, outputs the estimation result, and advances the process to S404. In S404, the server 100 updates the parameters of the estimation model based on the error between the estimation result and the correct data corresponding to the learning data, and advances the process to S405.
 サーバ100は、S405において、全ての学習用データに基づき学習したか否かを判定する。サーバ100は、全ての学習用データに基づき学習したと判定した場合(S405でYES)、処理をS406に進める。サーバ100は、全ての学習用データに基づき学習したと判定しなかった場合(S405でNO)、処理をS401に戻す。サーバ100は、S406において、学習済みの推定モデルを学習済モデル163として記憶し、学習処理を終了する。 In S405, the server 100 determines whether learning has been performed based on all learning data. If the server 100 determines that learning has been performed based on all the learning data (YES in S405), the process proceeds to S406. If the server 100 does not determine that learning has been performed based on all the learning data (NO in S405), the process returns to S401. In S406, the server 100 stores the learned estimation model as the learned model 163, and ends the learning process.
 学習済モデル173についても、学習用データセット170を用いて、上記同様の手順で学習処理が行われる。 The learning process for the learned model 173 is also performed using the learning data set 170 in the same manner as above.
 [変形例]
 第1実施形態においては、図5,図6に示した工程表が表示され、第2実施形態においては、図9に示した工程表が表示されるようにした。しかし、これに限らず、以下に説明するような工程表が表示されるようにしてもよい。
[Modified example]
In the first embodiment, the process chart shown in FIGS. 5 and 6 is displayed, and in the second embodiment, the process chart shown in FIG. 9 is displayed. However, the present invention is not limited to this, and a process chart as described below may be displayed.
 図13は、変形例に係る経路表示処理のフローチャートである。図14は、変形例に係る工程表の一例を示す図である。図14の工程表においては、図5,図6を用いて説明した工程表よりも簡略化して図示している。 FIG. 13 is a flowchart of route display processing according to a modification. FIG. 14 is a diagram showing an example of a process chart according to a modification. The process chart in FIG. 14 is illustrated more simply than the process chart described using FIGS. 5 and 6.
 図13に示すように、経路表示処理が開始すると、サーバ100は、S501において、工事開始から終了までの経路を複数の経路に分類する。 As shown in FIG. 13, when the route display process starts, the server 100 classifies the route from the start of the construction work to the end of the work into a plurality of routes in S501.
 図14の例では、工事を担当する複数の会社(複数の担当者)と、各担当者が担当する工程のバーチャートが示されている。図14においては、ある工程が終了したことを条件に開始可能となる工程がある場合、前者の工程と後者の工程とを線で繋いで表示している。 In the example of FIG. 14, a bar chart of multiple companies (multiple people in charge) in charge of construction work and the processes each person in charge is in charge of is shown. In FIG. 14, when there is a process that can be started on the condition that a certain process is completed, the former process and the latter process are connected by a line and displayed.
 本例においては、A社の工程が完了した後に、C社の工程が開始可能となる。B社の工程が完了した後に、C社の工程が開始可能となる。C社の工程が完了した後に、F社の工程が開始可能となる。F社の工程が完了した後に、G社の工程が開始可能となる。 In this example, after Company A's process is completed, Company C's process can start. After Company B's process is completed, Company C's process can begin. After Company C's process is completed, Company F's process can begin. After Company F's process is completed, Company G's process can begin.
 また、D社の工程が完了した後に、E社の工程が開始可能となる。E社の工程が完了した後に、F社の工程が開始可能となる。 Furthermore, after Company D's process is completed, Company E's process can start. After Company E's process is completed, Company F's process can begin.
 このように、工程の順序としては、A社、C社、F社、G社の順に進める経路(「経路1」と称する)、B社、C社、F社、G社の順に進める経路(「経路2」と称する)、D社、E社、F社、G社の順に進める経路(「経路3」と称する)に分類される。 In this way, the order of the processes is as follows: a route that follows Company A, Company C, Company F, and Company G (referred to as "route 1"), and a route that follows Company B, Company C, Company F, and Company G in that order (referred to as "route 1"). (referred to as "Route 2"), followed by a route (referred to as "Route 3") in which Company D, Company E, Company F, and Company G proceed in this order.
 図13に戻り、サーバ100は、S502において、各経路における所要日数から、所要日数が最大となる経路を選択する。 Returning to FIG. 13, in S502, the server 100 selects the route with the maximum number of required days from the number of required days for each route.
 経路1は、工事が開始してから終了するまでに所要する日数が最大となる経路である。たとえば、経路1のA社の工程が遅延した場合、その後すぐに開始されるC社の工程が遅延する。一方、経路2の場合、B社の工程に遅延が生じても、次に開始されるC社の工程までに時間の余裕があるため、遅延が生じにくい。 Route 1 is the route that takes the maximum number of days from the start to the end of the construction work. For example, if Company A's process on Route 1 is delayed, Company C's process that starts immediately thereafter will be delayed. On the other hand, in the case of route 2, even if there is a delay in Company B's process, there is plenty of time before Company C's process starts next, so the delay is less likely to occur.
 また、経路1のC社の工程が遅延した場合、その後すぐに開始されるF社の工程が遅延する。一方、経路3の場合、E社の工程に遅延が生じても、次に開始されるF社の工程までに時間の余裕があるため、遅延が生じにくい。 Furthermore, if Company C's process on route 1 is delayed, Company F's process that starts immediately thereafter will be delayed. On the other hand, in the case of route 3, even if there is a delay in Company E's process, there is plenty of time before Company F's process starts next, so the delay is less likely to occur.
 このように、工事が開始してから終了するまでに所要する日数が最大となる経路1においては、遅延が生じやすいと言える。 In this way, it can be said that delays are likely to occur on route 1, where the number of days required from the start to the end of construction is the largest.
 図13に戻り、サーバ100は、S503において、所要日数が最大になる経路中に含まれるバーチャートの色およびサイズを変更し、経路表示処理を終了する。本変形例においては、複数の工程における複数の経路のうち、工事が開始してから終了するまでに所要する日数が最大となる経路をその他の経路とは異なる態様で表示する。 Returning to FIG. 13, in S503, the server 100 changes the color and size of the bar chart included in the route with the maximum number of required days, and ends the route display process. In this modification, among a plurality of routes in a plurality of processes, the route that takes the maximum number of days from the start to the end of the construction work is displayed in a different manner from the other routes.
 具体的には、工事が開始してから終了するまでに所要する日数が最大となる経路1の各工程のバーチャートを上下幅が大きい赤色の画像で表示するとともに、これらの工程を繋ぐ線を実線で表示する。経路2,3の各工程のバーチャートを経路1よりも上下幅が小さい白色の画像で表示するとともに、これらの工程を繋ぐ線を破線で表示する。ただし、経路2,3のバーチャートであっても、経路1に含まれるものは、経路1による表示方法(上下幅が大きい赤色の画像)で表示する。このようにすることで、遅延による影響が発生しやすい経路を直感的に把握しやすく、このような経路に注意を集めることができる。 Specifically, the bar chart for each process in route 1, which takes the maximum number of days from the start to the end of construction, is displayed as a red image with a large vertical width, and the line connecting these processes is displayed. Displayed as a solid line. A bar chart for each process of routes 2 and 3 is displayed as a white image with a vertical width smaller than that of route 1, and a line connecting these processes is displayed as a broken line. However, even in the bar charts for routes 2 and 3, those included in route 1 are displayed using the display method according to route 1 (a red image with a large vertical width). By doing this, it is easy to intuitively understand routes that are likely to be affected by delays, and it is possible to draw attention to such routes.
 本変形例は、第1実施形態または第2実施形態に適用可能である。図14に示した例では、第1経路中のA社の工程が第1の工程に相当し、C社の工程が第2の工程に相当する。第1経路中のC社の工程が第1の工程に相当し、F社の工程が第2の工程に相当する。第1経路中のF社の工程が第1の工程に相当し、G社の工程が第2の工程に相当する。 This modification is applicable to the first embodiment or the second embodiment. In the example shown in FIG. 14, the process of company A in the first route corresponds to the first process, and the process of company C corresponds to the second process. The process of Company C in the first route corresponds to the first process, and the process of Company F corresponds to the second process. The process of Company F in the first route corresponds to the first process, and the process of Company G corresponds to the second process.
 本実施の形態および変形例においては、工程表として、バーチャート工程表を適用した例を例示して説明したが、これに限らず、どのような工程表を適用してもよい。たとえば、工程表は、ネットワーク工程表であってもよい。この場合、各工程を示す表示において、スケジュール情報を対応付けて表示すればよい。また、工程が高負荷状態であれば、当該工程(第1の工程)の表示を赤色で表示し、この工程により影響を受けて遅延が発生し得る工程(第2の工程)の表示をピンク色で表示すればよい。また、変形例における経路1は、クリティカルパスに相当する。 In the present embodiment and the modified examples, an example in which a bar chart process chart is applied as the process chart has been exemplified and explained, but the present invention is not limited to this, and any process chart may be applied. For example, the schedule may be a network schedule. In this case, schedule information may be displayed in association with each process. Additionally, if a process is under high load, the process (first process) will be displayed in red, and the process that may be affected by this process (second process) will be displayed in pink. It can be displayed in color. Further, the path 1 in the modified example corresponds to a critical path.
 今回開示された各実施の形態は、技術的に矛盾しない範囲で適宜組合わせて実施することも予定されている。そして、今回開示された実施の形態は、全ての点で例示であって制限的なものではないと考えられるべきである。本開示により示される技術的範囲は、上記した実施の形態の説明ではなくて請求の範囲によって示され、請求の範囲と均等の意味及び範囲内での全ての変更が含まれることが意図される。 It is also planned that the embodiments disclosed herein will be implemented in appropriate combinations within a technically consistent range. The embodiments disclosed this time should be considered to be illustrative in all respects and not restrictive. The technical scope indicated by the present disclosure is indicated by the claims rather than the description of the embodiments described above, and it is intended that all changes within the scope and meanings equivalent to the claims are included. .
 1 施工管理システム、91~94 工程表、100 サーバ、111,211 制御部、112,212 記憶部、113,213 通信部、121 第2推定部、122 第1推定部、123 生成部、124 通知部、161,171 入力データ、162,172 出力データ、163,173 学習済モデル、200 端末、220 入力部、221 表示部、400 スケジュール管理システム。 1 Construction management system, 91-94 Schedule, 100 Server, 111, 211 Control unit, 112, 212 Storage unit, 113, 213 Communication unit, 121 Second estimation unit, 122 First estimation unit, 123 Generation unit, 124 Notification Section, 161, 171 Input data, 162, 172 Output data, 163, 173 Learned model, 200 Terminal, 220 Input section, 221 Display section, 400 Schedule management system.

Claims (10)

  1.  複数の担当者が担当する複数の工程から成る工事の施工を管理する施工管理システムであって、
     前記工事の工程表を生成する制御部と、
     前記工程表を表示する表示部とを備え、
     前記制御部は、前記複数の担当者のスケジュール情報を含む情報に基づき、前記複数の担当者の作業負荷を示す負荷状態を決定し、
     前記表示部は、前記複数の担当者の各々が担当する工程に対応付けて前記スケジュール情報および前記負荷状態を表示する、施工管理システム。
    A construction management system that manages construction work consisting of multiple processes handled by multiple personnel,
    a control unit that generates a work schedule for the construction;
    and a display section that displays the process chart,
    The control unit determines a load state indicating the workload of the plurality of persons in charge based on information including schedule information of the plurality of persons in charge,
    The display unit is a construction management system that displays the schedule information and the load state in association with a process that each of the plurality of persons in charge is in charge of.
  2.  前記施工管理システムは、前記複数の担当者のスケジュールを管理するスケジュール管理システムと接続可能に構成されており、
     前記制御部は、前記スケジュール管理システムから前記スケジュール情報を取得し、
     前記スケジュール情報には、前記工事と関係のないスケジュールが含まれる、請求項1に記載の施工管理システム。
    The construction management system is configured to be connectable to a schedule management system that manages schedules of the plurality of personnel,
    The control unit acquires the schedule information from the schedule management system,
    The construction management system according to claim 1, wherein the schedule information includes a schedule unrelated to the construction.
  3.  前記工程表は、前記複数の工程に対応する複数のバーチャートを表示するバーチャート工程表であり、
     前記複数の工程は、第1の工程と、前記第1の工程の後の工程である第2の工程とを含み、
     前記第2の工程は、前記第1の工程の作業が遅延した場合に、当該遅延による影響が生じる工程であり、
     前記表示部は、前記第1の工程に対応する第1のバーチャートと、前記第2の工程に対応する第2のバーチャートとを繋ぐ画像を表示する、請求項1または請求項2に記載の施工管理システム。
    The process chart is a bar chart process chart that displays a plurality of bar charts corresponding to the plurality of processes,
    The plurality of steps include a first step and a second step that is a step after the first step,
    The second step is a step that is affected by the delay if the work in the first step is delayed,
    3. The display unit displays an image connecting a first bar chart corresponding to the first step and a second bar chart corresponding to the second step. construction management system.
  4.  前記負荷状態は、前記第1の工程の作業の遅延が予測される高負荷状態を含み、
     前記表示部は、
      前記複数の担当者の各々が担当する工程に対応するバーチャートに対応付けて前記スケジュール情報を表示し、
      前記第1の工程の前記負荷状態が前記高負荷状態であるときは、前記第1の工程の前記負荷状態が前記高負荷状態でないときとは異なる第1の態様で前記第1のバーチャートを表示する、請求項3に記載の施工管理システム。
    The load state includes a high load state in which a delay in work in the first step is expected,
    The display section is
    displaying the schedule information in association with a bar chart corresponding to a process each of the plurality of persons in charge is in charge of;
    When the load state of the first step is the high load state, the first bar chart is displayed in a first manner different from when the load state of the first step is not the high load state. The construction management system according to claim 3, which displays the construction management system.
  5.  前記表示部は、前記第1の工程の前記負荷状態が前記高負荷状態であるときに、前記第1のバーチャートを前記第1の態様で表示するとともに、前記第2のバーチャートを第2の態様で表示する、請求項4に記載の施工管理システム。 The display section displays the first bar chart in the first mode and displays the second bar chart in the second mode when the load state of the first step is the high load state. 5. The construction management system according to claim 4, wherein the construction management system is displayed in the following manner.
  6.  前記制御部は、前記第1の工程の前記負荷状態が前記高負荷状態であるときに、前記工事を管理する管理者、前記第1の工程を担当する担当者および前記第2の工程を担当する担当者に、前記負荷状態を通知する、請求項5に記載の施工管理システム。 When the load state of the first step is the high load state, the control unit includes a manager who manages the construction, a person in charge of the first step, and a person in charge of the second step. The construction management system according to claim 5, wherein the construction management system notifies the person in charge of the load state.
  7.  前記複数の工程における複数の経路のうち、前記工事が開始してから終了するまでに所要する日数が最大となる経路をその他の経路とは異なる態様で表示する、請求項4~請求項6のいずれか1項に記載の施工管理システム。 Claims 4 to 6, wherein among the plurality of routes in the plurality of steps, the route that takes the maximum number of days from the start to the end of the construction work is displayed in a different manner from the other routes. The construction management system according to any one of the items.
  8.  前記制御部は、前記負荷状態および第1入力情報を第1学習済モデルに入力することで、前記第1学習済モデルから対策情報を推定結果として出力し、
     前記第1学習済モデルは、前記負荷状態および前記第1入力情報が入力された際に、前記対策情報を前記推定結果として出力するように、教師データを用いた機械学習処理が施されたモデルであり、
     前記第1入力情報は、前記複数の担当者の各々が所属する会社の情報と、前記複数の工程の各々の情報とを含み、
     前記対策情報は、前記高負荷状態が発生したときに、前記第1の工程および前記第2の工程に対する対策方法を示す情報であり、
     前記対策方法は、前記第1の工程および前記第2の工程のいずれか一方または両方の作業期間を延長する方法と、前記第1の工程および前記第2の工程のいずれか一方または両方の作業人数を増やす方法とを含む、請求項4~請求項7のいずれか1項に記載の施工管理システム。
    The control unit outputs countermeasure information as an estimation result from the first learned model by inputting the load state and the first input information to the first learned model,
    The first trained model is a model that has been subjected to machine learning processing using teacher data so that when the load state and the first input information are input, the countermeasure information is output as the estimation result. and
    The first input information includes information on a company to which each of the plurality of persons in charge belongs, and information on each of the plurality of processes,
    The countermeasure information is information indicating a countermeasure method for the first step and the second step when the high load state occurs,
    The countermeasure methods include a method of extending the work period of either or both of the first step and the second step, and a method of extending the work period of either or both of the first step and the second step. The construction management system according to any one of claims 4 to 7, comprising a method of increasing the number of people.
  9.  前記制御部は、前記スケジュール情報および第2入力情報を第2学習済モデルに入力することで、前記第2学習済モデルから前記負荷状態を推定結果として出力し、
     前記第2学習済モデルは、前記スケジュール情報および前記第2入力情報が入力された際に、前記負荷状態を前記推定結果として出力するように、教師データを用いた機械学習処理が施されたモデルであり、
     前記第2入力情報は、前記複数の担当者の各々のスケジュールの優先度を示す情報と、前記複数の担当者の各々が所属する会社の情報と、前記複数の工程の各々の情報とを含む、請求項1~請求項8のいずれか1項に記載の施工管理システム。
    The control unit outputs the load state as an estimation result from the second learned model by inputting the schedule information and second input information to the second learned model,
    The second learned model is a model that has been subjected to machine learning processing using teacher data so that the load state is output as the estimation result when the schedule information and the second input information are input. and
    The second input information includes information indicating the schedule priority of each of the plurality of persons in charge, information on the company to which each of the plurality of persons in charge belongs, and information on each of the plurality of processes. , the construction management system according to any one of claims 1 to 8.
  10.  複数の担当者が担当する複数の工程から成る工事の施工を管理する施工管理方法であって、
     前記工事の工程表を生成するステップと、
     前記工程表を表示するステップとを備え、
     前記生成するステップは、前記複数の担当者のスケジュール情報を含む情報に基づき、前記複数の担当者の作業負荷を示す負荷状態を決定するステップを含み、
     前記表示するステップは、前記複数の担当者の各々が担当する工程に対応付けて前記スケジュール情報および前記負荷状態を表示するステップを含む、施工管理方法。
    A construction management method for managing construction work consisting of multiple processes handled by multiple personnel,
    a step of generating a work schedule for the construction;
    and a step of displaying the process chart,
    The generating step includes determining a load state indicating the workload of the plurality of persons in charge based on information including schedule information of the plurality of persons in charge,
    The construction management method, wherein the displaying step includes displaying the schedule information and the load state in association with a process that each of the plurality of personnel is in charge of.
PCT/JP2022/030577 2022-08-10 2022-08-10 Work management system and work management method WO2024034058A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/JP2022/030577 WO2024034058A1 (en) 2022-08-10 2022-08-10 Work management system and work management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2022/030577 WO2024034058A1 (en) 2022-08-10 2022-08-10 Work management system and work management method

Publications (1)

Publication Number Publication Date
WO2024034058A1 true WO2024034058A1 (en) 2024-02-15

Family

ID=89851195

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2022/030577 WO2024034058A1 (en) 2022-08-10 2022-08-10 Work management system and work management method

Country Status (1)

Country Link
WO (1) WO2024034058A1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1196222A (en) * 1997-09-17 1999-04-09 Hitachi Ltd Method for managing process progress and its device
JP2011170496A (en) * 2010-02-17 2011-09-01 Mitsubishi Heavy Ind Ltd Device and method for supporting plant construction plan
JP2015075868A (en) * 2013-10-08 2015-04-20 株式会社神戸製鋼所 Schedule display device, method and program

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1196222A (en) * 1997-09-17 1999-04-09 Hitachi Ltd Method for managing process progress and its device
JP2011170496A (en) * 2010-02-17 2011-09-01 Mitsubishi Heavy Ind Ltd Device and method for supporting plant construction plan
JP2015075868A (en) * 2013-10-08 2015-04-20 株式会社神戸製鋼所 Schedule display device, method and program

Similar Documents

Publication Publication Date Title
Gordon et al. Measuring safety culture in a research and development centre: A comparison of two methods in the Air Traffic Management domain
US6954737B2 (en) Method and apparatus for work management for facility maintenance
CN106185507B (en) Maintenance work auxiliary device, system and the method for elevator
US8275797B2 (en) Academy for the knowledge management system
GB2469741A (en) Knowledge management system display
GB2469744A (en) System for resolving incidents
Jain et al. A project management framework for global software development
US20220310214A1 (en) Methods and apparatus for data-driven monitoring
St Germain et al. Guidelines for implementation of an advanced outage control center to improve outage coordination, problem resolution, and outage risk management
Gerbec et al. Design of procedures for rare, new or complex processes: Part 1–An iterative risk-based approach and case study
de Souza et al. Modelling the work-as-done in the building maintenance using a layered FRAM: A case study on HVAC maintenance
WO2024034058A1 (en) Work management system and work management method
JP2008527500A (en) Automated project office and system and method for automated risk assessment and reporting
US20190266544A1 (en) Techniques for managing process-flows across an enterprise
US20080109291A1 (en) Executing and Tracking Strategic Plans
Adeyekun An Assessment of Poor Communication between the Contractor and Subcontractor
Power Metrics for understanding flow
Ainsworth Task analysis
WO2024034059A1 (en) Work management system and work management method
Germain et al. Status report on the development of micro-scheduling software for the advanced outage control center project
Stengl et al. SAP R/3 Plant Maintenance: making it work for your business
WO2024034060A1 (en) Construction management system and construction management method
Darrow Exploring the factors that drive organizational resilience: Lessons from healthcare
Ortner et al. Virtualization of organizations: consequences for workflow modeling
JP2018060272A (en) Budget management system, budget management method and budget management

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22954975

Country of ref document: EP

Kind code of ref document: A1