WO2023120489A1 - 水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム - Google Patents

水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム Download PDF

Info

Publication number
WO2023120489A1
WO2023120489A1 PCT/JP2022/046724 JP2022046724W WO2023120489A1 WO 2023120489 A1 WO2023120489 A1 WO 2023120489A1 JP 2022046724 W JP2022046724 W JP 2022046724W WO 2023120489 A1 WO2023120489 A1 WO 2023120489A1
Authority
WO
WIPO (PCT)
Prior art keywords
water pipe
related information
pipe construction
construction
process plan
Prior art date
Application number
PCT/JP2022/046724
Other languages
English (en)
French (fr)
Inventor
聡 打越
早人 景山
一也 伊東
Original Assignee
株式会社クボタ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社クボタ filed Critical 株式会社クボタ
Publication of WO2023120489A1 publication Critical patent/WO2023120489A1/ja

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Definitions

  • the present invention relates to a process plan creation system for creating a process plan for water pipe construction, a process plan creation method, and a program for creating a process plan.
  • a process plan is created, and work proceeds according to the created process plan.
  • a construction process creation system for example, as disclosed in Patent Document 1, the amount of construction work for a construction object for each of a plurality of construction sections, and the number of man-hours for the construction amounts in the plurality of construction sections and the plurality of construction operations a man-hour coefficient representing the ratio of, a difficulty coefficient, and a modularization ratio representing the ratio of the number of assembly locations in a module pre-assembled in a location other than the construction section to the total number of assembly locations in the construction section is known, which includes a calculation unit that calculates the construction period of each of the plurality of construction works for each of the plurality of construction sections.
  • the construction time is calculated based on the construction volume of the construction target, the man-hour coefficient, the difficulty coefficient, and the modularization rate.
  • modularization is difficult, and after excavating the ground at the site, it is necessary to connect the water pipes one by one in the ground and backfill them. Therefore, in water pipe construction, the process varies greatly depending on the diameter, length, type, number and arrangement of individual water pipes.
  • the purpose of the present invention is to realize a process plan creation system that can easily create a process plan for water pipe construction.
  • a process plan creation system for water pipe work creates a process plan for water pipe work.
  • the process plan creation system includes an information acquisition unit that acquires water pipe-related information related to at least one of the diameter, length, type, number, and arrangement of water pipes used in water pipe construction; Based on the acquired water pipe-related information, a process time calculation unit that calculates the process time including the work time of each process of water pipe construction, and the process time of each process calculated by the process time calculation unit and a process plan creation unit that creates a process plan for at least part of the water pipe construction (first configuration).
  • the process plan includes at least one of a daily process plan and an overall process plan.
  • the overall process plan means a process plan from start to finish of water pipe construction, and includes, for example, a weekly process plan, a monthly process plan, and an annual process plan.
  • the information acquisition unit also acquires water pipe construction related information related to water pipe construction in addition to the water pipe related information.
  • the process time calculation unit calculates the process time using the water pipe related information and the water pipe construction related information acquired by the information acquisition unit (second configuration).
  • the water pipe construction related information includes ground related information including information related to the ground where the water pipe is laid, and information related to the ground where the water pipe is laid.
  • the ground-related information includes ground-surrounding-related information related to the ground surroundings of the location where the water pipe is laid, and road-condition-related information related to the road conditions of the location where the water pipe is buried. , (fourth configuration).
  • the underground related information includes information related to at least one of underground obstacles, road structures, soil properties, and groundwater (fifth configuration).
  • the process time calculation unit calculates a preliminary time for each process of water pipe work based on the water pipe related information and the water pipe work related information. Calculate.
  • the process plan creation unit creates a process plan for at least a part of the water pipe construction, taking into consideration not only the process time of each process but also the preliminary time (sixth configuration).
  • the process time calculation unit has a preliminary time correction unit that corrects the preliminary time in each process of water pipe construction based on past performance (seventh configuration).
  • the reserve time for each process of water pipe construction can be determined with high accuracy based on past performance. For example, since parameters related to water pipe construction differ for each work site, past results can be reflected in the preliminary time by correcting the preliminary time according to the parameter. Further, by correcting the preliminary time based on past weather data and the like in the period of water pipe construction, the preliminary time can be obtained with higher accuracy.
  • the information acquisition unit acquires, as the water pipe work related information, construction suspension related information related to dates and times when water pipe work is not performed.
  • the process plan creation unit prepares a process plan for at least a part of the water pipe construction using the construction suspension related information acquired by the information acquisition unit and the process time of each process calculated by the process time calculation unit. create (eighth configuration).
  • a progress-related information acquisition unit for acquiring progress-related information related to the progress of water pipe construction, and acquired by the progress-related information acquisition unit and a process plan correction unit that corrects the process plan created by the process plan creation unit using the progress related information thus obtained (ninth configuration).
  • a method for creating a process plan for water pipe construction is a method for creating a process plan for water pipe construction.
  • the process plan creation method includes an information acquisition step of acquiring water pipe-related information related to at least one of the diameter, length, type, number, and arrangement of water pipes used in water pipe construction, and the information acquisition step.
  • a process time calculation step of calculating a process time including the work time of each process of water pipe construction based on the acquired water pipe related information, and a process time of each process calculated in the process time calculation step.
  • a program for creating a process plan for water pipe construction is a program for creating a process plan for water pipe construction.
  • This program causes a computer to acquire water pipe related information related to at least one of the diameter, length, type, number and arrangement of water pipes used for water pipe construction, and based on the acquired water pipe related information to calculate the process time including the work time of each process of the water pipe construction, and to create a process plan for at least a part of the water pipe construction using the calculated process time of each process (tenth configuration) .
  • a process plan creation system for water pipe construction is based on water pipe-related information related to at least one of the diameter, length, type, number, and arrangement of water pipes used for water pipe construction. Then, the process time including the work time of each process of the water pipe construction is calculated, and a process plan for at least a part of the water pipe construction is created using the calculated process time of each process.
  • FIG. 1 is a functional block diagram showing a schematic configuration of a process plan creation system according to Embodiment 1.
  • FIG. 2 is a diagram showing an example of a daily process plan for water pipe construction.
  • FIG. 3 is a diagram showing an example of a monthly process plan for water pipe construction.
  • FIG. 4 is a diagram schematically showing how the work machine is used to excavate the ground.
  • FIG. 5 is a diagram schematically showing how water pipes are arranged in trenches formed by excavation.
  • FIG. 6 is a diagram schematically showing how water pipes are joined together.
  • FIG. 7 is a diagram schematically showing how a work machine is used to fill a water pipe.
  • FIG. 8 is a diagram showing a state in which the side surface of the ditch is anchored by sheet piles.
  • FIG. 9 is a diagram schematically showing the schematic configuration of a road.
  • FIG. 10 is a diagram schematically showing an example of the result of calculating the work time for each process of water pipe construction.
  • FIG. 11 is a flow chart showing an outline of the process plan creation method.
  • FIG. 12 is a flow chart showing an outline of a method for acquiring water pipe-related information and water pipe work-related information in the process plan creation method.
  • 13 is a functional block diagram showing a schematic configuration of a process plan creation system according to a modification of the first embodiment;
  • FIG. 14 is a functional block diagram showing a schematic configuration of a process plan creation system according to the second embodiment.
  • FIG. 15 shows a flow chart of a process plan creation method executed by the process plan creation system according to the second embodiment.
  • FIG. 1 is a functional block diagram showing a schematic configuration of a process planning system 1 according to Embodiment 1 of the present invention.
  • the process plan creation system 1 creates and outputs daily or monthly process plans for water pipe construction as shown in FIGS.
  • the process plan creation system 1 may be composed of, for example, a computer device, or may have a mobile terminal capable of exchanging data with the computer device and the computer device via a communication device.
  • the above water pipe work means the work of burying the water pipe W underground.
  • the water pipe work includes not only the work of newly burying the water pipe W in the ground, but also the work of renewing the water pipe W buried in the ground.
  • the construction work for newly burying the water pipe W in the ground includes a water pipe laying process.
  • the water pipe laying process includes a daily process and a monthly process.
  • the daily process includes an excavation process, a piping process, and a backfilling process.
  • the monthly process includes the daily process for the number of process days.
  • the monthly process may include a lane marking process of drawing lane markings on the surface of the road.
  • the construction work to renew the water pipe W includes an excavation process, a pipe removal process, a piping process, and a backfilling process in the daily processes.
  • FIG. 4 is a diagram schematically showing how the work machine M is used to excavate the ground.
  • FIG. 5 is a diagram schematically showing how water pipes W are arranged in grooves L formed by excavation.
  • FIG. 6 is a diagram schematically showing how the water pipes W are joined together.
  • FIG. 7 is a diagram schematically showing how the work machine M is used to fill the water pipe W. As shown in FIG.
  • an excavation process is performed to excavate the ground using a work machine M.
  • the surface of the ground is paved with asphalt. Therefore, in the excavation step, the work machine M excavates the ground after excavating the asphalt. In the excavation step, the ground is excavated so that a groove L in which the water pipe W can be arranged is formed.
  • the water pipe W is placed in the trench L formed by excavation.
  • the water pipe W is carried into the groove L using a working machine M, for example.
  • the water pipes W carried into the groove L are joined together as shown in FIG.
  • the process of carrying the water pipes W into the grooves L and joining them together is the piping process.
  • FIG. 9 is a diagram schematically showing the schematic configuration of the road R.
  • the road R has, in order from the top, a surface layer R1, an upper roadbed R2, a lower roadbed R3, and a roadbed R4.
  • the groove L is backfilled in the order of the roadbed R4, the lower roadbed R3, the upper roadbed R2, and the surface layer R1 so that the road has the configuration shown in FIG.
  • an earth retaining process as shown in Fig. 8 may be performed after the excavation process.
  • the sheet pile P is used to reinforce the side surface of the groove L excavated in the excavating step.
  • the entire side surface of the groove L may be reinforced, or only a portion of the side surface of the groove L may be reinforced.
  • the process plan creation system 1 has an information acquisition unit 11, a plan control unit 15, a process time calculation unit 21, and a process plan creation unit 31.
  • the information acquisition unit 11 acquires water pipe related information and water pipe construction related information.
  • the water pipe-related information includes information related to at least one of the diameter, length, type (straight pipe, deformed pipe, T-shaped pipe, cut pipe, etc.), number, and arrangement of water pipes used in water pipe construction. include.
  • the water pipe-related information is, for example, information obtained from a pipe diagram of a water pipe. That is, the water pipe-related information may be automatically obtained, for example, from the device that generates the pipe diagram.
  • the water pipe-related information may be obtained by an input, or may be obtained from a result calculated by a calculation device.
  • the water pipe construction related information includes information related to water pipe construction.
  • the water pipe construction related information includes information related to site conditions.
  • Information related to the site conditions includes workable time, workable personnel, type and number of working machines to be used, whether parallel work is possible, whether working machines can be used in parallel, transport time for earth and sand or water pipes, etc., test drilling It includes at least one of information regarding the presence or absence of the device.
  • the water pipe construction related information includes ground related information and underground related information.
  • the ground-related information includes information related to the ground where the water pipe is buried.
  • the ground related information includes ground surroundings related information and road condition related information.
  • the ground surroundings related information includes information on the environment (facilities facing the construction site (houses, shops, parking lots, etc.), the construction site in the city or in the suburbs, etc.) in the vicinity of the site where the water pipe construction is performed.
  • the road condition-related information includes at least one of traffic information at the place where water pipe work is to be performed, and information on the width and number of lanes of the road when the place where water pipe work is to be done is a road.
  • the underground related information includes information related to the underground of the location where the water pipe is buried. Specifically, the underground related information includes information related to at least one of underground obstacles (underground structures such as crossing pipes, other underground buried objects, etc.), road structures, soil properties, and groundwater. .
  • underground obstacles underground structures such as crossing pipes, other underground buried objects, etc.
  • road structures such as crossing pipes, other underground buried objects, etc.
  • soil properties such as gravel, etc.
  • the underground-related information may include information about the types, sizes, positions, and the like of underground obstacles.
  • the subsurface related information may include information related to road structure such as pavement and roadbed thicknesses, characteristics, and the like.
  • the underground-related information may include information about the soil quality (sand, silt, clay, etc.) of the excavation position.
  • the underground-related information may include information regarding the location and amount of groundwater.
  • the underground related information includes the necessity of earth retaining, the type of earth retaining (aluminum sheet pile, wooden sheet pile, lightweight steel sheet pile, H-steel horizontal sheet pile, etc.), earth retaining method (elevating, driving, etc.), earth retaining position. and range information.
  • the information acquisition unit 11 also acquires information related to the construction period and workable dates as water pipe construction related information.
  • the information on the construction period and workable date acquired by the information acquisition unit 11 is used when the process plan creation unit 31 creates a process plan.
  • the information acquisition unit 11 may acquire construction suspension related information related to dates and times when water pipe construction is not performed as water pipe construction related information.
  • the process plan creation unit 31 uses the construction suspension related information acquired by the information acquisition unit 11 and the process time of each process calculated by the process time calculation unit 21, which will be described later, to perform at least a part of the water pipe construction. Create a process plan for
  • the plan control unit 15 selects information that cannot be obtained by the information acquisition unit 11 to create a process plan for water pipe construction. Determine necessary construction conditions. Specifically, the plan control unit 15 selects, for example, a work range to be calculated by the process time calculation unit 21, which will be described later, as well as conditions related to earth retaining work (necessary or unnecessary, applicable range, etc.) and conditions related to test excavation (necessary or unnecessary , number of test pits, etc.). The work range selected by the plan control unit 15, and the conditions for earth retaining work and the conditions for test excavation determined by the plan control unit 15 are output to the process time calculation unit 21 as part of the water pipe work related information. be done.
  • the process time calculation unit 21 calculates the process time including the work time for each process of water pipe construction.
  • the process time calculation unit 21 calculates the work time required for burying one water pipe, for example, based on the water pipe related information and the water pipe work related information.
  • FIG. 10 is a diagram schematically showing an example of the result of calculating the work time for each process of water pipe construction. In FIG. 10, for the sake of explanation, the working time of each process is displayed along with the pipeline of the water pipe. As shown in FIG. 10, the process plan creation system 1 may display the work time of each process together with the water pipe line, or may display only the work time of each process in a list form.
  • the process time calculation unit 21 outputs the work time calculated in each process as process time data to the process plan creation unit 31, which will be described later.
  • the process time calculation unit 21 uses the work time corresponding to the water pipe related information and the work time corresponding to the water pipe construction related information to determine the work time required to bury one water pipe. It may be calculated, or it is necessary to bury one water pipe in consideration of the coefficient according to the water pipe related information and the coefficient according to the water pipe construction related information with respect to the standard work time working hours may be calculated.
  • the process time calculation unit 21 may calculate the preliminary time in each process of water pipe construction based on the water pipe related information and the water pipe construction related information.
  • the preliminary time may be included in the water pipe work-related information, and the process time calculation unit 21 calculates the process time of each process based on the water pipe-related information and the water pipe work-related information. Calculations may be performed in consideration of delay factors.
  • the process time calculation unit 21 may calculate the reserve time for the excavation and piping process time from the probability of existence of an underground obstacle or the like in the underground related information. That is, the process time calculation unit 21 may calculate the spare time by considering the probability of occurrence of an event in each process.
  • the process plan creation unit 31 uses the process time for each process calculated by the process time calculation unit 21 to create a process plan for at least a part of the water pipe construction.
  • the process plan creating unit 31 creates a process plan as shown in FIG. 2, for example, using the input conditions such as the construction period and workable days, and the process time of each process.
  • the process plan creation unit 31 may create the process plan by considering not only the process time of each process but also the spare time.
  • the process plan creation unit 31 may determine the order of construction locations in the pipeline where water pipe construction is to be performed. For example, the process plan creation unit 31 may determine the order of construction locations according to the degree of difficulty of construction.
  • the process plan creation system 1 for water pipe construction creates a daily process plan for water pipe construction.
  • the process plan creation system 1 includes an information acquisition unit 11 that acquires water pipe-related information related to at least one of the diameter, length, type, number, and arrangement of water pipes W used in water pipe construction, and an information acquisition unit.
  • the daily process time for each process of water pipe construction is calculated based on the water pipe-related information, and the calculated process time is used to create at least a part of the daily process plan for the water pipe construction. be able to. Therefore, daily process plans for water pipe construction can be automatically and easily created.
  • the water pipe work process plan creation system 1 may create a monthly process plan for water pipe work as shown in FIG. 3 based on the created daily process plan for water pipe work. Specifically, the process plan creation system 1 for water pipe construction creates a monthly process plan for water pipe work as shown in FIG. You may
  • the water pipe work process plan creation system 1 may create only a daily process plan for water pipe work, or may create only a monthly process plan for water pipe work. Further, the process plan creation system 1 for water pipe construction may create an overall process plan including a weekly process plan, a monthly process plan, an annual process plan, and the like.
  • the method of calculating the process time for each process in the process plan for water pipe work other than daily is the same as the method for calculating the process time for each process in the above-described daily process plan for water pipe work.
  • the information acquisition unit 11 also acquires water pipe construction related information related to water pipe construction in addition to the water pipe related information.
  • the process time calculation unit 21 calculates the process time using the water pipe related information and the water pipe construction related information acquired by the information acquisition unit 11 .
  • the water pipe work related information includes ground related information including information related to the ground where the water pipe W is laid, and ground related information including information related to the ground where the water pipe W is laid. related information;
  • the ground related information includes ground periphery related information related to the ground periphery of the location where the water pipe W is buried, and road condition related information related to the road condition of the location where the water pipe W is buried. include.
  • the underground related information includes information related to at least one of underground obstacles, road structures, soil properties, and groundwater.
  • the process time calculation unit 21 may calculate the preliminary time in each process of water pipe construction based on the water pipe related information and the water pipe construction related information.
  • the process plan creation unit 31 may create a process plan for at least a part of the water pipe construction, taking into consideration not only the process time of each process but also the preliminary time.
  • the information acquisition unit 11 may acquire, as the water pipe work related information, construction suspension related information related to dates and times when water pipe work is not performed.
  • the process plan creation unit 31 uses the construction suspension related information acquired by the information acquisition unit 11 and the process time of each process calculated by the process time calculation unit 21 to create a process plan for at least a part of the water pipe construction. may be created.
  • FIG. 11 is a flow chart showing an outline of the process plan creation method.
  • FIG. 12 is a flow chart showing an outline of a method for acquiring water pipe-related information and water pipe work-related information in the process plan creation method.
  • the information acquisition unit 11 of the process plan creation system 1 acquires the construction period and workable dates (step S1).
  • the construction period and workable days may be input to the process planning system 1, or the process planning system 1 may acquire information from another system or storage device.
  • step S2 the information acquisition unit 11 acquires water pipe related information and water pipe construction related information. Specifically, the information acquisition unit 11 acquires the water pipe related information and the water pipe construction related information as shown in the flowchart shown in FIG. 12 .
  • step SA1 the information acquisition unit 11 reads design data for water pipes.
  • the information acquisition unit 11 reads the design data from, for example, another system or storage device.
  • the design data is, for example, data relating to at least one of the size (diameter, length), type, number, and arrangement of water pipes, which is obtained by designing water pipes. That is, the information acquisition unit 11 acquires the water pipe-related information.
  • the design data may include ground-related information around the pipeline of the water pipe.
  • step SA2 the plan control unit 15 selects the work range, which is the input range of the construction conditions in step SA3.
  • the work range selected by the plan control unit 15 is input to the information acquisition unit 11 .
  • the selection of the work range may be performed by an input to the information acquisition unit 11, or may be performed using a work range set in another system or storage device.
  • the work range may be the range of the entire pipeline for which water pipe construction is to be performed, or it may be the range of only a part of the pipeline.
  • the information acquisition unit 11 may select the work range by selecting the start point and the end point of the pipeline.
  • the information acquisition unit 11 acquires the construction conditions for the water pipe in the work range selected in step SA2.
  • the construction conditions include water pipe construction related information. That is, the construction conditions include information related to site conditions, ground related information and underground related information.
  • the information related to the site conditions includes workable time, number of workable workers, type and number of work machines to be used, availability of parallel work, availability of parallel use of work machines, transportation time for earth and sand or water pipes, etc. contains information on at least one of
  • ground-related information includes traffic information at the place where water pipe work is performed, width and number of lanes of the road when the place where water pipe work is performed, environment (houses, shops) near the place where water pipe work is performed etc.).
  • the underground related information includes information related to at least one of underground obstacles (underground structures such as crossing pipes, other underground buried objects, etc.), road structure, soil quality, and groundwater.
  • the underground-related information may include information about types, sizes, positions, and the like of underground obstacles.
  • the subsurface related information may include information related to road structure such as pavement and roadbed thicknesses, characteristics, and the like.
  • the underground-related information may include information about the soil quality (sand, silt, clay, etc.) of the excavation position.
  • the underground-related information may include information regarding the location and amount of groundwater.
  • the underground-related information may include information on the necessity of earth retaining, earth retaining method (sheet pile, strut, etc.), earth retaining construction method (elevating, driving, etc.), and earth retaining range.
  • step SA4 the plan control unit 15 determines the presence or absence of earth retaining and the range of earth retaining from the underground related information acquired by the information acquisition unit 11 and the like. Specifically, the plan control unit 15 determines the presence or absence of earth retaining and the range of earth retaining, based on information such as the soil quality and groundwater in the ground, for example. The information on earth retaining determined by the plan control unit 15 is input to the information acquisition unit 11 as water pipe construction related information.
  • the plan control unit 15 determines the presence or absence of test excavation and the test excavation location from the underground related information acquired by the information acquisition unit 11 and the like. Specifically, the plan control unit 15 determines the presence or absence of test digging and the test digging locations based on information such as underground obstacles. The information about the trial drilling determined by the plan control unit 15 is input to the information acquisition unit 11 as water pipe work related information. After that, the process plan creation system 1 returns to the flowchart shown in FIG. 11 and performs the process of step S3.
  • step SA4 does not have to be performed in the process plan creation method.
  • step SA5 does not have to be performed in the process plan creation method.
  • step S3 of the flowchart shown in FIG. 11 the process time calculation unit 21 calculates the process time in each process of water pipe construction based on the water pipe related information and water pipe construction related information acquired in step S2. Specifically, the process time calculation unit 21 calculates the work time required for burying one water pipe based on the water pipe related information and the water pipe construction related information, for example. Any method may be used for the process time calculation unit 21 to calculate the work time.
  • the process plan creation unit 31 uses the process time of each process calculated by the process time calculation unit 21 and the information such as the construction period and workable days acquired by the information acquisition unit 11 in step S1. , create daily and monthly schedules. Specifically, the process plan creation unit 31 sets the process time so that the daily process is completed in one day, and the work is performed on the workable day within the work period to complete the entire water pipe construction. Create a process plan in combination. At this time, the process plan creation unit 31 creates a process plan so that the work proceeds efficiently according to the presence or absence of parallel work, the number of working machines, the transportation time, and the like.
  • step S2 corresponds to the information acquisition step
  • step S3 corresponds to the process time calculation step
  • step S4 corresponds to the process plan creation step.
  • the method for creating a process plan for water pipe construction is a method for creating a process plan for water pipe construction.
  • the process plan creation method includes an information acquisition step of acquiring water pipe-related information related to at least one of the diameter, length, type, number, and arrangement of water pipes used in water pipe construction, and the information acquisition step.
  • a process time calculation step of calculating a process time including the work time of each process of water pipe construction based on the acquired water pipe related information, and a process time of each process calculated in the process time calculation step.
  • the program in the embodiment of the present invention may be any program that causes the computer constituting the process plan creation system 1 to execute steps S1 to S4 shown in FIG. By executing this program by the computer of the process plan creation system 1, the process plan creation system 1 and the process plan creation method in this embodiment can be realized.
  • the computer that constitutes the process plan creation system 1 may be a general-purpose computer or a dedicated computer.
  • a computer is equipped with, for example, a CPU, and performs arithmetic processing by means of the CPU (Central Processing Unit).
  • the data acquired by the process plan creation system 1 and the results of computations are stored in a storage device (not shown).
  • the process planning system 1 reads the data and performs calculation processing.
  • the storage device is configured by a storage medium including a storage device such as a memory and a hard disk.
  • a program for creating a process plan for water pipe construction is a program for creating a process plan for water pipe construction.
  • This program causes a computer to acquire water pipe-related information related to at least one of the diameter, length, type, number, and arrangement of water pipes W used in water pipe construction, and stores the acquired water pipe-related information in Based on this, the process time including the work time of each process of the water pipe work is calculated, and the process plan of at least a part of the water pipe work is created using the calculated process time of each process.
  • FIG. 13 is a functional block diagram showing a schematic configuration of a process plan creation system 100 according to this modification.
  • the configuration of the process plan creation system 100 according to this modification differs from the configuration of the process plan creation system 1 of the first embodiment in that the process time calculator 121 has a preliminary time corrector 122 . Therefore, in the following description, the same reference numerals are assigned to the same configurations as in the first embodiment, and only the portions different from the first embodiment will be described.
  • the process time calculation unit 121 calculates the spare time in each process of water pipe work, and corrects the spare time according to the past performance of water pipe work. Specifically, the process time calculator 121 has a preliminary time corrector 122 .
  • the spare time correction unit 122 corrects the spare time according to the past performance of water pipe work. Specifically, the preliminary time correction unit 122 corrects the preliminary time for the water pipe work to be scheduled using the actual values of the parameters of the water pipe work-related information that differ for each construction site of the water pipe work. In addition, the reserve time correction unit 122 corrects the reserve time in consideration of a case where water pipe construction cannot be performed due to seasonal weather such as the rainy season or the snowfall season. In this way, the preliminary time correcting unit 122 corrects the preliminary time based on the information about the past results including the situation of the construction site of the water pipe construction and the weather during the past construction period. Thereby, the calculation accuracy of the spare time can be improved.
  • the process time calculation unit 121 has a preliminary time correction unit 122 that corrects the preliminary time in each process of water pipe construction based on past performance.
  • the reserve time for each process of water pipe construction can be determined with high accuracy based on past performance. For example, since parameters related to water pipe construction differ for each work site, past results can be reflected in the preliminary time by correcting the preliminary time according to the parameter. Further, by correcting the preliminary time based on past weather data and the like in the period of water pipe construction, the preliminary time can be obtained with higher accuracy.
  • FIG. 14 is a functional block diagram showing a schematic configuration of a process plan creation system 200 according to the second embodiment.
  • the process plan creation system 200 according to the second embodiment differs from the process plan creation systems 1 and 100 of the first embodiment in that the process plan is corrected according to the progress of water pipe construction. Therefore, in the following description, the same reference numerals are given to the same configurations as in the first embodiment, and the description thereof is omitted, and only the portions different from the first embodiment will be described.
  • the process plan creation system 200 includes an information acquisition unit 11, a plan control unit 15, a process time calculation unit 21, a process plan creation unit 31, a progress related information acquisition unit 241, and a process plan correction unit 242. .
  • the progress-related information acquisition unit 241 acquires progress-related information for water pipe construction.
  • the progress-related information is information related to the progress of water pipe construction, such as construction performance data, process data, and construction management data.
  • the progress-related information acquisition unit 241 may acquire the progress-related information from, for example, a construction information system (not shown) that manages construction information, or may acquire the progress-related information by input.
  • the process plan correction unit 242 corrects the process plan created by the process plan creation unit 31 based on the progress related information acquired by the progress related information acquisition unit 241 .
  • the process plan correction unit 242 outputs the corrected process plan data.
  • FIG. 15 shows a flowchart of the process plan creation method executed by the process plan creation system 200 having the configuration described above.
  • steps S1 to S4 of the process plan creation method executed by the process plan creation system 200 are similar to steps S1 to S4 of the process plan creation method executed by the process plan creation system 1 of the first embodiment. are the same. Therefore, description of steps S1 to S4 is omitted.
  • the progress related information acquisition unit 241 acquires progress related information in step S101.
  • the process plan correction unit 242 corrects the process plan based on the progress related information. Thereafter, the process plan correction unit 242 outputs the corrected process plan.
  • the process plan creation system 200 includes a progress related information acquisition unit 241 that acquires progress related information related to the progress of water pipe construction, and the progress related information acquired by the progress related information acquisition unit 241. and a process plan correction unit 242 that corrects the process plan created by the process plan creation unit 31 using the situation-related information.
  • the process plan creation system 1 has the plan control unit 15. However, even if the process plan creating system does not have a plan control unit and obtains by inputting the construction conditions necessary for creating a process plan for water pipe work out of the information that cannot be obtained by the information acquisition unit 11, Alternatively, it may be obtained from data pre-stored in a storage device or the like.
  • the water pipe construction related information includes information related to site conditions, ground related information, and underground related information.
  • the plumbing related information may not include information related to site conditions.
  • the plumbing related information may not include ground related information.
  • the water pipe work related information may not include underground related information.
  • ground related information includes ground surroundings related information and road condition related information.
  • ground related information may not include ground surrounding related information.
  • Ground related information may not include road condition related information.
  • the process time calculation unit 21 calculates the process time including the work time for each process of water pipe construction based on the water pipe related information and the water pipe construction related information.
  • the process time calculation unit may calculate the process time including the working time of each process of the water pipe construction based on the water pipe related information.
  • the process time calculation unit may calculate the process time including the working time of each process of the water pipe work based on the water pipe work related information.
  • the process time calculation unit 21 calculates the preliminary time for each process of water pipe construction based on the water pipe related information and the water pipe construction related information.
  • the process time calculation unit may calculate the preliminary time in each process of the water pipe construction based on the water pipe related information.
  • the process time calculation unit may calculate the preliminary time in each process of the water pipe work based on the water pipe work related information.
  • the process plan creation system 1, 100, 200 creates and outputs a process plan for underground water pipe construction.
  • the process plan creating system may create a process plan for water pipe construction including not only the burying of water pipes but also the burying of parallel pipes arranged in parallel with the water pipes.
  • the process plan creation system 1, 100, 200 creates a process plan for water pipe construction.
  • the process plan creation system may create materials to be submitted to the water utility, including construction management plans, etc., in addition to the process plan.
  • the process plan creation system may visualize data to be managed during construction, such as work charts, construction management charts, and inventory management charts.
  • the process plan creation system may automatically create a process chart and a daily construction report.
  • the process plan creation system may automatically create documents such as an implementation process chart after completion of construction.
  • the process plan creation system 1, 100, 200 creates a process plan for water pipe construction using an open-cut construction method that excavates the ground.
  • the process plan creation system may create a process plan for water pipe construction using a non-open-cut construction method used for laying water pipes in tunnels.
  • the process plan creation system creates a process plan based on the process suitable for water pipe construction by the excavation method.
  • the process plan creation system 200 corrects the process plan for water pipe construction according to the actual progress of the water pipe construction.
  • the process planning system may recommend the personnel or work machines needed to meet the target schedule. Such recommendations may be made by the process planning system of the first embodiment.
  • the present invention can be used in a process plan creation system that creates a process plan for water pipe construction.
  • Process plan creation system 11 Information acquisition unit 15 Plan control unit 21 Process time calculation unit 31 Process plan creation unit 121 Process time calculation unit 122 Preliminary time correction unit 241 Progress related information acquisition unit 242 Process plan correction unit W Water pipe L Ditch M Work machine P Sheet pile R Road R1 Surface layer R2 Upper roadbed R3 Lower roadbed R4 Subgrade

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

水道管工事の工程計画を容易に作成可能な工程計画作成システムを実現する。工程計画作成システム1は、水道管工事に用いる水道管Wの径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得部11と、情報取得部11によって取得した水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算部21と、工程時間演算部21によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成部31と、を有する。

Description

水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム
 本発明は、水道管工事の工程計画を作成する工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラムに関する。
 一般的に、工事では、工程計画が作成され、作成された工程計画に沿って作業が進められる。工事の工程作成システムとしては、例えば特許文献1に開示されるように、複数の工事区画毎の工事対象物の工事物量と、前記複数の工事区画および前記複数の工事作業での工事物量に対する工数の割合を表す工数係数と、難易度係数と、前記工事区画と別の場所で事前に組み立てるモジュール内の組み立て箇所の個数の当該工事区間内での組み立て箇所の総数に対する割合を表すモジュール化率とに基づいて、前記複数の工事区画毎の前記複数の工事作業それぞれの工事期間を算出する算出部を具備する工事工程作成システムが知られている。
特許第5665759号公報
 上述の特許文献1の工事工程作成システムでは、工事対象物の工事物量と、工数係数と、難易度係数と、モジュール化率とに基づいて工事時間を算出している。これに対し、水道管工事の場合には、モジュール化が難しく、現場で地面を掘削した後、水道管を1本ずつ地中で接続して埋め戻す必要がある。そのため、水道管工事では、個々の水道管の径、長さ、種類、数及び配置等によって、工程が大きく変わる。
 よって、水道管工事では、単純な工程計算が難しく、熟練の作業者の経験と知識によって手作業で工程を作成していた。したがって、水道管工事の工程作成は、熟練の作業者が時間をかけて作成する必要があり、容易に作成できなかった。
 本発明の目的は、水道管工事の工程計画を容易に作成可能な工程計画作成システムを実現することにある。
 本発明の一実施形態に係る水道管工事の工程計画作成システムは、水道管工事の工程計画を作成する。前記工程計画作成システムは、水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得部と、前記情報取得部によって取得した前記水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算部と、前記工程時間演算部によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成部と、を有する(第1の構成)。
 上述の構成により、水道管関連情報に基づいて水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて水道管工事の少なくとも一部の工程計画を作成することができる。よって、水道管工事の工程計画を自動で容易に作成することができる。なお、前記工程計画は、日毎の工程計画及び全体の工程計画の少なくとも一方を含む。前記全体の工程計画は、水道管工事の開始から終了までの工程計画を意味していて、例えば、週間の工程計画、月間の工程計画、年間の工程計画などを含む。
 前記第1の構成において、前記情報取得部は、前記水道管関連情報に加えて、水道管工事に関連する水道管工事関連情報も取得する。前記工程時間演算部は、前記情報取得部によって取得された前記水道管関連情報及び前記水道管工事関連情報を用いて、前記工程時間を演算する(第2の構成)。
 これにより、水道管関連情報に加えて、水道管工事に関連する水道管工事関連情報を用いて、水道管工事の工程計画を作成することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 前記第2の構成において、前記水道管工事関連情報は、前記水道管を埋設する場所の地上に関連する情報を含む地上関連情報と、前記水道管を埋設する場所の地中に関連する情報を含む地中関連情報と、を含む(第3の構成)。
 これにより、水道管工事に大きな影響を与える地上関連情報及び地中関連情報を考慮して、水道管工事の各工程の工程時間を演算することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 前記第3の構成において、前記地上関連情報は、前記水道管を埋設する場所の地上周辺に関連する地上周辺関連情報と、前記水道管を埋設する場所の道路状況に関連する道路状況関連情報と、を含む(第4の構成)。
 これにより、水道管工事に大きな影響を与える地上関連情報のうち、地上周辺関連情報及び道路状況関連情報を考慮して、水道管工事の各工程の工程時間を演算することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 前記第3または第4の構成において、前記地中関連情報は、地中障害物、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を含む(第5の構成)。
 これにより、水道管工事に大きな影響を与える地中障害物、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を考慮して、水道管工事の各工程の工程時間を演算することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 前記第2から第5の構成のうちいずれか一つの構成において、前記工程時間演算部は、前記水道管関連情報及び前記水道管工事関連情報に基づいて、水道管工事の各工程における予備時間を演算する。前記工程計画作成部は、各工程の工程時間だけでなく前記予備時間も考慮して、水道管工事の少なくとも一部の工程計画を作成する(第6の構成)。
 これにより、地中内の予想外の埋設物によって工程が変更になる場合、または、地上の状況(駐車場または店舗の出入り口で工事ができない時間帯がある等)によって工程が変更になる場合などでも、そのリスクを考慮して、水道管工事の工程計画を作成することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 前記第6の構成において、前記工程時間演算部は、水道管工事の各工程における前記予備時間を、過去の実績に基づいて補正する予備時間補正部を有する(第7の構成)。
 これにより、水道管工事の各工程における予備時間を、過去の実績に基づいて精度良く求めることができる。例えば、水道管工事に関連するパラメータは作業現場ごとに異なるため、前記パラメータに応じて前記予備時間を補正することにより、過去の実績を前記予備時間に反映させることができる。また、水道管工事の時期における過去の天候データ等に基づいて、前記予備時間を補正することにより、前記予備時間をより精度良く求めることができる。
 したがって、補正された予備時間を用いて、水道管工事の工程計画をより精度良く作成することができる。
 前記第2から第7の構成のうちいずれか一つの構成において、前記情報取得部は、前記水道管工事関連情報として、水道管工事を行わない日時に関連する工事休止関連情報を取得する。前記工程計画作成部は、前記情報取得部によって取得した前記工事休止関連情報及び前記工程時間演算部によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する(第8の構成)。
 これにより、水道管工事が休止している期間または時間帯を除いて、水道管工事の工程を作成することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 前記第1から第8の構成のうちいずれか一つの構成において、水道管工事の進捗状況に関連する進捗状況関連情報を取得する進捗状況関連情報取得部と、前記進捗状況関連情報取得部によって取得された前記進捗状況関連情報を用いて、前記工程計画作成部によって作成された工程計画を修正する工程計画修正部と、をさらに有する(第9の構成)。
 これにより、水道管工事の実際の進捗状況に応じて、水道管工事の工程計画を修正することができる。よって、水道管工事の工程計画を、実情に合わせてより精度良く作成することができる。
 本発明の一実施形態に係る水道管工事の工程計画作成方法は、水道管工事の工程計画を作成する方法である。前記工程計画作成方法は、水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得ステップと、前記情報取得ステップで取得された前記水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算ステップと、前記工程時間演算ステップで演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成ステップと、を有する(第1の方法)。
 上述の方法により、水道管関連情報に基づいて水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて水道管工事の少なくとも一部の工程計画を作成することができる。よって、水道管工事の工程計画を自動で容易に作成することができる。
 本発明の一実施形態に係る水道管工事の工程計画を作成するためのプログラムは、水道管工事の工程計画を作成するためのプログラムである。このプログラムは、コンピュータに、水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得させ、前記取得した水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算させ、前記演算した各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成させる(第10の構成)。
 上述の構成により、水道管関連情報に基づいて水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて水道管工事の少なくとも一部の工程計画を作成することができる。よって、水道管工事の工程計画を自動で容易に作成することができる。
 本発明の一実施形態に係る水道管工事の工程計画作成システムは、水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算し、演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する。
 これにより、水道管関連情報に基づいて水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて水道管工事の少なくとも一部の工程計画を作成することができる。よって、水道管工事の工程計画を自動で容易に作成することができる。
図1は、実施形態1に係る工程計画作成システムの概略構成を示す機能ブロック図である。 図2は、水道管工事における日毎の工程計画の一例を示す図である。 図3は、水道管工事における月毎の工程計画の一例を示す図である。 図4は、作業機械を用いて地面を掘削する様子を模式的に示す図である。 図5は、掘削によって形成された溝内に水道管を配置する様子を模式的に示す図である。 図6は、水道管同士を接合する様子を模式的に示す図である。 図7は、作業機械を用いて、水道管を埋める様子を模式的に示す図である。 図8は、溝の側面が矢板によって土留めされている状態を示す図である。 図9は、道路の概略構成を模式的に示す図である。 図10は、水道管工事の各工程の作業時間を演算した結果の一例を模式的に示す図である。 図11は、工程計画作成方法の概略を示すフローチャートである。 図12は、工程計画作成方法のうち水道管関連情報及び水道管工事関連情報を取得する方法の概略を示すフローチャートである。 図13は、実施形態1の変形例に係る工程計画作成システムの概略構成を示す機能ブロック図である。 図14は、実施形態2に係る工程計画作成システムの概略構成を示す機能ブロック図である。 図15は、実施形態2に係る工程計画作成システムによって実行される工程計画作成方法のフローチャートを示す。
 以下で、各実施形態について、図面を参照しながら説明する。各図において、同一部分には同一の符号を付して、その同一部分の説明は繰り返さない。なお、各図中の構成部材の寸法は、実際の構成部材の寸法及び各構成部材の寸法比率等を忠実に表したものではない。
 また、以下の説明において、“固定”、“接続”及び“取り付ける”等(以下、固定等)の表現は、部材同士が直接、固定等されている場合だけでなく、他の部材を介して固定等されている場合も含む。すなわち、以下の説明において、固定等の表現には、部材同士の直接的及び間接的な固定等の意味が含まれる。
[実施形態1]
 (水道管工事の工程計画作成システム)
 図1は、本発明の実施形態1に係る工程計画作成システム1の概略構成を示す機能ブロック図である。工程計画作成システム1は、図2及び図3に示すような水道管工事の日毎または月毎の工程計画を作成して出力する。工程計画作成システム1は、例えば、コンピュータ装置によって構成されていてもよいし、コンピュータ装置及び該コンピュータ装置と通信装置を介してデータを授受可能な携帯端末を有していてもよい。
 前記水道管工事は、水道管Wを地中に埋設する工事を意味する。前記水道管工事は、水道管Wを地中に新規に埋設する工事だけでなく、地中に埋設されている水道管Wを更新する工事も含む。前記水道管工事のうち水道管Wを地中に新規に埋設する工事は、水道管敷設工程を含む。前記水道管敷設工程は、日毎の工程と、月毎の工程とを含む。前記日毎の工程は、掘削工程と、配管工程と、埋め戻し工程とを含む。前記月毎の工程は、前記日毎の工程を、工程日数分含む。前記月毎の工程は、道路の表面に区画線等を描く区画線工程等を含んでいてもよい。以下では、前記水道管工事として、水道管Wを地中に新規に埋設する工事を説明する。
 なお、前記水道管工事のうち水道管Wを更新する工事は、日毎の工程の中に、掘削工程と、配管取り外し工程と、配管工程と、埋め戻し工程とを含む。
 前記日毎の水道管工事の各工程を、図4から図7を用いて簡単に説明する。図4は、作業機械Mを用いて地面を掘削する様子を模式的に示す図である。図5は、掘削によって形成された溝L内に水道管Wを配置する様子を模式的に示す図である。図6は、水道管W同士を接合する様子を模式的に示す図である。図7は、作業機械Mを用いて、水道管Wを埋める様子を模式的に示す図である。
 水道管工事では、まず、図4に示すように、作業機械Mを用いて地面を掘削する掘削工程が行われる。図4には特に図示しないが、地面の表面はアスファルトによって舗装されている。よって、前記掘削工程では、作業機械Mは、アスファルトを掘削した後、地面を掘削する。前記掘削工程は、水道管Wを配置可能な溝Lが形成されるように地面を掘削する。
 次に、図5に示すように、掘削によって形成された溝L内に水道管Wを配置する。水道管Wは、例えば作業機械Mを用いて、溝L内に搬入される。溝L内に搬入された水道管Wは、図6に示すように、互いに接合される。このように、溝L内に水道管Wを搬入して互いに接合する工程が、配管工程である。
 その後、水道管工事では、図7に示すように、作業機械Mを用いて、接合した水道管Wを溝L内で埋め戻す埋め戻し工程が行われる。図9は、道路Rの概略構成を模式的に示す図である。道路Rは、上から順に、表層R1、上層路盤R2、下層路盤R3及び路床R4を有する。溝L内で水道管Wを埋め戻す場合には、道路の構成が図9に示す構成になるように、路床R4、下層路盤R3、上層路盤R2及び表層R1の順に溝Lを埋め戻す。
 なお、水道管工事では、掘削工程の後に、図8に示すような土留め工程を行ってもよい。この土留め工程では、矢板Pを用いて、掘削工程で掘削した溝Lの側面を補強する。土留め工程では、溝Lの側面全体を補強してもよいし、溝Lの側面の一部のみを補強してもよい。
 図1に示すように、工程計画作成システム1は、情報取得部11と、計画制御部15と、工程時間演算部21と、工程計画作成部31とを有する。
 情報取得部11は、水道管関連情報及び水道管工事関連情報を取得する。前記水道管関連情報は、水道管工事に用いる水道管の径、長さ、種類(直管、異形管、T字管、切管など)、数及び配置のうち少なくとも一つに関連する情報を含む。前記水道管関連情報は、例えば、水道管の管路図等から得られる情報である。すなわち、前記水道管関連情報は、例えば、前記管路図を生成する装置から自動的に得られてもよい。前記水道管関連情報は、入力によって得られてもよいし、演算装置によって演算された結果から得られてもよい。
 前記水道管工事関連情報は、水道管工事に関連する情報を含む。具体的には、前記水道管工事関連情報は、現場条件に関連する情報を含む。前記現場条件に関連する情報は、作業可能時間、作業可能人員、使用する作業機械の種類及び数、並行作業の可否、作業機械の並行使用の可否、土砂または水道管等の運搬時間、試掘の有無などに関する情報のうち少なくとも一つの情報を含む。
 また、前記水道管工事関連情報は、地上関連情報と、地中関連情報とを含む。前記地上関連情報は、水道管を埋設する場所の地上に関連する情報を含む。具体的には、前記地上関連情報は、地上周辺関連情報と、道路状況関連情報とを含む。前記地上周辺関連情報は、水道管工事を行う場所の付近の環境(工事場所が面している施設(住宅、店舗、駐車場など)、工事場所が街中または郊外など)に関する情報を含む。前記道路状況関連情報は、水道管工事を行う場所における交通情報、及び、水道管工事を行う場所が道路の場合にはその道路の幅及び車線数のうち少なくとも一つの情報を含む。
 前記地中関連情報は、前記水道管を埋設する場所の地中に関連する情報を含む。詳しくは、前記地中関連情報は、地中障害物(横断管などの地中構造物、その他の地中埋設物など)、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を含む。
 すなわち、前記地中関連情報は、地中障害物の種類、大きさ、位置などに関する情報を含んでいてもよい。前記地中関連情報は、舗装及び路盤の厚み、特性などの道路構造に関連する情報を含んでいてもよい。前記地中関連情報は、掘削する位置の土質(砂系、シルト系、粘土系など)に関する情報を含んでいてもよい。前記地中関連情報は、地下水の位置及び量などに関する情報を含んでいてもよい。前記地中関連情報は、土留めの要不要、土留めの種類(アルミ矢板、木矢板、軽量鋼矢板、H鋼横矢板など)、土留め工法(建て込み、打ち込みなど)、土留めの位置及び範囲に関する情報を含んでいてもよい。
 情報取得部11は、工期及び工事可能日等に関する情報も、水道管工事関連情報として取得する。情報取得部11が取得した工期及び工事可能日に関する情報は、工程計画作成部31によって工程計画を作成する際に、用いられる。
 情報取得部11は、水道管工事を行わない日時に関連する工事休止関連情報を、水道管工事関連情報として取得してもよい。この場合、工程計画作成部31は、情報取得部11によって取得した前記工事休止関連情報及び後述する工程時間演算部21によって演算された各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する。
 計画制御部15は、情報取得部11によって取得された水道管関連情報及び水道管工事関連情報に基づいて、情報取得部11では得られない情報のうち水道管工事の工程計画を作成するために必要な工事条件を決める。具体的には、計画制御部15は、例えば、後述する工程時間演算部21で演算する作業範囲を選択するとともに、土留め工事に関する条件(要不要、適用範囲など)及び試掘に関する条件(要不要、試掘箇所数など)を決定する。計画制御部15によって選択された作業範囲、及び、計画制御部15によって決定された土留め工事に関する条件及び試掘に関する条件は、前記水道管工事関連情報の一部として、工程時間演算部21に出力される。
 工程時間演算部21は、情報取得部11によって取得した前記水道管関連情報及び前記水道管工事関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する。工程時間演算部21は、例えば、前記水道管関連情報及び前記水道管工事関連情報に基づいて、1本の水道管を埋設するために必要な作業時間を演算する。図10は、水道管工事の各工程の作業時間を演算した結果の一例を模式的に示す図である。図10では、説明のために、水道管の管路とともに各工程の作業時間を表示している。工程計画作成システム1は、図10に示すように水道管の管路とともに各工程の作業時間を表示してもよいし、各工程の作業時間のみをリストで表示してもよい。
 工程時間演算部21は、各工程において演算した作業時間を、工程時間データとして、後述する工程計画作成部31に出力する。
 なお、工程時間演算部21は、前記水道管関連情報に応じた作業時間及び前記水道管工事関連情報に応じた作業時間を用いて、1本の水道管を埋設するために必要な作業時間を演算してもよいし、基準作業時間に対して、前記水道管関連情報に応じた係数及び前記水道管工事関連情報に応じた係数を考慮して、1本の水道管を埋設するために必要な作業時間を演算してもよい。
 工程時間演算部21は、前記水道管関連情報及び前記水道管工事関連情報に基づいて、水道管工事の各工程における予備時間を演算してもよい。前記予備時間は、前記水道管工事関連情報に含まれていてもよいし、工程時間演算部21が、前記水道管関連情報及び前記水道管工事関連情報に基づいて、前記各工程の工程時間が遅れる要因を考慮して演算してもよい。例えば、工程時間演算部21は、前記地中関連情報における地中障害物などの存在可能性の確率等から、掘削及び配管の工程時間に対する予備時間を演算してもよい。すなわち、工程時間演算部21は、各工程において事象が発生する確率等を考慮して前記予備時間を演算してもよい。
 工程計画作成部31は、工程時間演算部21によって演算された各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する。工程計画作成部31は、入力された工期及び作業可能日などの条件と、前記各工程の工程時間とを用いて、例えば図2に示すような工程計画を作成する。
 工程計画作成部31は、工程時間演算部21が前記予備時間を演算した場合には、各工程の工程時間だけでなく前記予備時間も考慮して、前記工程計画を作成してもよい。
 工程計画作成部31は、水道管工事を行う管路において、工事箇所の順番を決めてもよい。例えば、工程計画作成部31は、工事の難易度に応じて、工事箇所の順番を決めてもよい。
 以上より、本実施形態に係る水道管工事の工程計画作成システム1は、日毎の水道管工事の工程計画を作成する。工程計画作成システム1は、水道管工事に用いる水道管Wの径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得部11と、情報取得部11によって取得した水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算部21と、工程時間演算部21によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成部31と、を有する。
 上述の構成により、水道管関連情報に基づいて日毎の水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて日毎の水道管工事の少なくとも一部の工程計画を作成することができる。よって、日毎の水道管工事の工程計画を自動で容易に作成することができる。
 さらに、水道管工事の工程計画作成システム1は、作成した日毎の水道管工事の工程計画に基づき、図3に示すような月毎の水道管工事の工程計画を作成してもよい。具体的には、水道管工事の工程計画作成システム1は、作成した日毎の水道管工事の工程計画を日数分積算することにより、図3に示すような月毎の水道管工事の工程を作成してもよい。
 なお、水道管工事の工程計画作成システム1は、日毎の水道管工事の工程計画のみを作成してもよいし、月毎の水道管工事の工程計画のみを作成してもよい。また、水道管工事の工程計画作成システム1は、週間の工程計画、月間の工程計画及び年間の工程計画などを含む全体の工程計画を作成してもよい。日毎以外の水道管工事の工程計画における各工程の工程時間の演算方法は、上述した日毎の水道管工事の工程計画における各工程の工程時間の演算方法と同様である。
 本実施形態では、情報取得部11は、前記水道管関連情報に加えて、水道管工事に関連する水道管工事関連情報も取得する。工程時間演算部21は、情報取得部11によって取得された前記水道管関連情報及び前記水道管工事関連情報を用いて、前記工程時間を演算する。
 これにより、水道管関連情報に加えて、水道管工事に関連する水道管工事関連情報を用いて、水道管工事の工程計画を作成することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 本実施形態では、前記水道管工事関連情報は、水道管Wを埋設する場所の地上に関連する情報を含む地上関連情報と、水道管Wを埋設する場所の地中に関連する情報を含む地中関連情報と、を含む。
 これにより、水道管工事に大きな影響を与える地上関連情報及び地中関連情報を考慮して、水道管工事の各工程の工程時間を演算することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 本実施形態では、前記地上関連情報は、水道管Wを埋設する場所の地上周辺に関連する地上周辺関連情報と、水道管Wを埋設する場所の道路状況に関連する道路状況関連情報と、を含む。
 これにより、水道管工事に大きな影響を与える地上関連情報のうち、地上周辺関連情報及び道路状況関連情報を考慮して、水道管工事の各工程の工程時間を演算することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 本実施形態では、前記地中関連情報は、地中障害物、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を含む。
 これにより、水道管工事に大きな影響を与える地中障害物、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を考慮して、水道管工事の各工程の工程時間を演算することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 本実施形態では、工程時間演算部21は、前記水道管関連情報及び前記水道管工事関連情報に基づいて、水道管工事の各工程における予備時間を演算してもよい。工程計画作成部31は、各工程の工程時間だけでなく前記予備時間も考慮して、水道管工事の少なくとも一部の工程計画を作成してもよい。
 これにより、地中内の予想外の埋設物によって工程が変更になる場合、または、地上の状況(駐車場または店舗の出入り口で工事ができない時間帯がある等)によって工程が変更になる場合などでも、そのリスクを考慮して、水道管工事の工程計画を作成することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 本実施形態では、情報取得部11は、前記水道管工事関連情報として、水道管工事を行わない日時に関連する工事休止関連情報を取得してもよい。工程計画作成部31は、情報取得部11によって取得した前記工事休止関連情報及び工程時間演算部21によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成してもよい。
 これにより、水道管工事が休止している期間または時間帯を除いて、水道管工事の工程を作成することができる。よって、水道管工事の工程計画をより精度良く作成することができる。
 (工程計画作成方法)
 次に、上述のような構成を有する工程計画作成システム1によって実行される工程計画作成方法について、図11及び図12を用いて説明する。図11は、工程計画作成方法の概略を示すフローチャートである。図12は、工程計画作成方法のうち水道管関連情報及び水道管工事関連情報を取得する方法の概略を示すフローチャートである。
 図11に示すように、まず、工程計画作成システム1の情報取得部11は、工期及び作業可能日を取得する(ステップS1)。前記工期及び作業可能日は、例えば、工程計画作成システム1に入力されてもよいし、工程計画作成システム1が他のシステムまたは記憶装置などから情報を取得してもよい。
 次にステップS2において、情報取得部11は、水道管関連情報及び水道管工事関連情報を取得する。具体的には、情報取得部11は、図12に示すフローチャートのように、水道管関連情報及び水道管工事関連情報を取得する。
 まず、ステップSA1では、情報取得部11は、水道管の配管の設計データを読み込む。情報取得部11は、例えば、他のシステムまたは記憶装置などから、前記設計データを読み込む。前記設計データは、例えば、水道管の管路設計によって得られる、水道管のサイズ(径、長さ)、種類、数及び配置のうち少なくとも一つに関連するデータである。すなわち、情報取得部11は、水道管関連情報を取得する。なお、前記設計データは、水道管の管路の周辺における地上関連情報を含んでいてもよい。
 次に、ステップSA2では、計画制御部15は、ステップSA3における工事条件の入力範囲である作業範囲を選択する。計画制御部15によって選択された作業範囲は、情報取得部11に入力される。前記作業範囲の選択は、情報取得部11に対する入力によって行われてもよいし、他のシステムまたは記憶装置で設定されている作業範囲を用いて行われてもよい。
 前記作業範囲は、水道管工事を行う管路全体の範囲であってもよいし、前記管路のうち一部の範囲のみであってもよい。なお、情報取得部11は、前記作業範囲を、前記管路における始点及び終点を選択することによって選択してもよい。
 続くステップSA3では、情報取得部11は、ステップSA2で選択した作業範囲における水道管の工事条件を取得する。前記工事条件は、水道管工事関連情報を含む。すなわち、前記工事条件は、現場条件に関連する情報、地上関連情報及び地中関連情報を含む。
 前記現場条件に関連する情報は、作業可能時間、作業可能人員、使用する作業機械の種類及び数、並行作業の可否、作業機械の並行使用の可否、土砂または水道管等の運搬時間などに関する情報のうち少なくとも一つの情報を含む。
 前記地上関連情報は、水道管工事を行う場所における交通情報、水道管工事を行う場所が道路の場合にはその道路の幅及び車線数、水道管工事を行う場所の付近の環境(住宅、店舗など)に関する情報のうち少なくとも一つの情報を含む。
 前記地中関連情報は、地中障害物(横断管などの地中構造物、その他の地中埋設物など)、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を含む。前記地中関連情報は、地中障害物の種類、大きさ、位置などに関する情報を含んでいてもよい。前記地中関連情報は、舗装及び路盤の厚み、特性などの道路構造に関連する情報を含んでいてもよい。前記地中関連情報は、掘削する位置の土質(砂系、シルト系、粘土系など)に関する情報を含んでいてもよい。前記地中関連情報は、地下水の位置及び量などに関する情報を含んでいてもよい。前記地中関連情報は、土留めの要不要、土留めの方法(矢板、切梁など)、土留め工法(建て込み、打ち込みなど)、土留めの範囲に関する情報を含んでいてもよい。
 ステップSA4では、計画制御部15は、情報取得部11が取得した地中関連情報等から、土留めの有無及び土留めを実施する範囲を決定する。詳しくは、計画制御部15は、例えば、地中の土質及び地下水などの情報に基づいて、土留めの有無及び土留めを実施する範囲を決定する。計画制御部15によって決定された土留めに関する情報は、水道管工事関連情報として情報取得部11に入力される。
 続くステップSA5では、計画制御部15は、情報取得部11が取得した地中関連情報等から、試掘の有無及び試掘箇所を決定する。詳しくは、計画制御部15は、例えば、地中障害物などの情報に基づいて、試掘の有無及び試掘箇所を決定する。計画制御部15によって決定された試掘に関する情報は、水道管工事関連情報として情報取得部11に入力される。その後、工程計画作成システム1は、図11に示すフローチャートに戻って、ステップS3の処理を行う。
 なお、ステップSA4は、工程計画作成方法で行われなくてもよい。また、ステップSA5は、工程計画作成方法で行われなくてもよい。
 図11に示すフローチャートのステップS3では、工程時間演算部21は、ステップS2で取得した水道管関連情報及び水道管工事関連情報に基づいて、水道管工事の各工程における工程時間を演算する。具体的には、工程時間演算部21は、例えば、前記水道管関連情報及び前記水道管工事関連情報に基づいて、1本の水道管を埋設するために必要な作業時間を演算する。工程時間演算部21が前記作業時間を演算する方法は、どのような方法であってもよい。
 続くステップS4では、工程計画作成部31は、工程時間演算部21によって演算された各工程の工程時間と、ステップS1で情報取得部11が取得した工期及び作業可能日等の情報とを用いて、日毎及び月毎の工程計画を作成する。具体的には、工程計画作成部31は、1日で日毎の工程が完了するとともに、前記工期内で前記作業可能日に作業を行って水道管工事全体が完了するように、前記工程時間を組み合わせて工程計画を作成する。この際、工程計画作成部31は、並行作業の有無、作業機械の台数及び運搬時間などに応じて、効率良く作業が進むように工程計画を作成する。
 ここで、ステップS2が情報取得ステップに対応し、ステップS3が工程時間演算ステップに対応し、ステップS4が工程計画作成ステップに対応する。
 本実施形態に係る水道管工事の工程計画作成方法は、水道管工事の工程計画を作成する方法である。前記工程計画作成方法は、水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得ステップと、前記情報取得ステップで取得された前記水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算ステップと、前記工程時間演算ステップで演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成ステップと、を有する。
 上述の方法により、水道管関連情報に基づいて水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて水道管工事の少なくとも一部の工程計画を作成することができる。よって、水道管工事の工程計画を自動で容易に作成することができる。
 (水道管工事の工程計画を作成するためのプログラム)
 本発明の実施形態におけるプログラムは、工程計画作成システム1を構成するコンピュータに、図11に示すステップS1からS4を実行させるプログラムであれば良い。このプログラムを工程計画作成システム1のコンピュータによって実行することにより、本実施形態における工程計画作成システム1と工程計画作成方法とを実現することができる。この場合、工程計画作成システム1を構成するコンピュータは、汎用のコンピュータまたは専用のコンピュータであってもよい。コンピュータは、例えばCPUを搭載し、該CPU(Central Processing Unit)によって演算処理を行う。
 また、本実施形態では、工程計画作成システム1が取得したデータ及び演算した演算結果は、図示しない記憶装置に記憶される。工程計画作成システム1は、前記記憶装置に記憶されたデータを用いて演算を行う場合には、前記データを読み込んで演算処理を行う。前記記憶装置は、メモリ、ハードディスク等の記憶装置を含む記憶媒体によって構成される。
 本実施形態に係る水道管工事の工程計画を作成するためのプログラムは、水道管工事の工程計画を作成するためのプログラムである。このプログラムは、コンピュータに、水道管工事に用いる水道管Wの径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得させ、前記取得した水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算させ、前記演算した各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成させる。
 上述の構成により、水道管関連情報に基づいて水道管工事の各工程の工程時間を演算し、該演算した工程時間を用いて水道管工事の少なくとも一部の工程計画を作成することができる。よって、水道管工事の工程計画を自動で容易に作成することができる。
 (変形例)
 次に、図13を用いて、上述の構成を有する工程計画作成システム1の変形例について説明する。図13は、本変形例に係る工程計画作成システム100の概略構成を示す機能ブロック図である。本変形例に係る工程計画作成システム100の構成は、工程時間演算部121が予備時間補正部122を有する点で、実施形態1の工程計画作成システム1の構成と異なる。よって、以下の説明では、実施形態1と同様の構成については同一の符号を付して、実施形態1と異なる部分についてのみ説明する。
 工程時間演算部121は、水道管工事の各工程における予備時間を演算するとともに、前記予備時間を水道管工事の過去の実績に応じて補正する。具体的には、工程時間演算部121は、予備時間補正部122を有する。
 予備時間補正部122は、前記予備時間を、水道管工事の過去の実績に応じて補正する。具体的には、予備時間補正部122は、水道管工事の工事現場ごとに異なる、水道管工事関連情報のパラメータの実績値を用いて、工程計画を行う水道管工事の予備時間を補正する。また、予備時間補正部122は、梅雨時期または降雪時期などの季節の天候によって水道管工事ができない場合を考慮して、前記予備時間を補正する。このように、予備時間補正部122は、水道管工事の工事現場の状況及び過去の工事時期の天候などを含む過去の実績に関する情報に基づいて、前記予備時間を補正する。これにより、前記予備時間の計算精度を高めることができる。
 以上のように、本変形例では、工程時間演算部121は、水道管工事の各工程における予備時間を、過去の実績に基づいて補正する予備時間補正部122を有する。
 これにより、水道管工事の各工程における予備時間を、過去の実績に基づいて精度良く求めることができる。例えば、水道管工事に関連するパラメータは作業現場ごとに異なるため、前記パラメータに応じて前記予備時間を補正することにより、過去の実績を前記予備時間に反映させることができる。また、水道管工事の時期における過去の天候データ等に基づいて、前記予備時間を補正することにより、前記予備時間をより精度良く求めることができる。
 したがって、補正された予備時間を用いて、水道管工事の工程計画をより精度良く作成することができる。
[実施形態2]
 図14は、実施形態2に係る工程計画作成システム200の概略構成を示す機能ブロック図である。実施形態2に係る工程計画作成システム200は、水道管工事の進捗状況に応じて工程計画を修正する点で、実施形態1の工程計画作成システム1,100とは異なる。よって、以下の説明では、実施形態1と同様の構成には同一の符号を付して説明を省略し、実施形態1と異なる部分についてのみ説明する。
 工程計画作成システム200は、情報取得部11と、計画制御部15と、工程時間演算部21と、工程計画作成部31と、進捗状況関連情報取得部241と、工程計画修正部242とを有する。
 進捗状況関連情報取得部241は、水道管工事の進捗状況関連情報を取得する。前記進捗状況関連情報は、工事実績データ、工程データ、施工管理データなどのように、水道管工事の進捗状況に関連する情報である。進捗状況関連情報取得部241は、例えば施工情報を管理する図示しない施工情報システムから前記進捗状況関連情報を取得してもよいし、入力によって前記進捗状況関連情報を取得してもよい。
 工程計画修正部242は、工程計画作成部31によって作成された工程計画を、進捗状況関連情報取得部241によって取得した進捗状況関連情報に基づいて修正する。工程計画修正部242は、修正した工程計画データを出力する。
 図15は、上述のような構成を有する工程計画作成システム200によって実行される工程計画作成方法のフローチャートを示す。図15に示すように、工程計画作成システム200によって実行される工程計画作成方法のステップS1~S4は、実施形態1の工程計画作成システム1によって実行される工程計画作成方法のステップS1~S4と同じである。よって、ステップS1~S4までの説明は省略する。
 ステップS4で工程計画作成部31が工程計画を作成した後、ステップS101では、進捗状況関連情報取得部241が進捗状況関連情報を取得する。続くステップS102では、工程計画修正部242が、前記工程計画を、前記進捗状況関連情報に基づいて修正する。その後、工程計画修正部242は、修正した工程計画を出力する。
 本実施形態では、工程計画作成システム200は、水道管工事の進捗状況に関連する進捗状況関連情報を取得する進捗状況関連情報取得部241と、進捗状況関連情報取得部241によって取得された前記進捗状況関連情報を用いて、工程計画作成部31によって作成された工程計画を修正する工程計画修正部242と、を有する。
 これにより、水道管工事の実際の進捗状況に応じて、水道管工事の工程計画を修正することができる。本実施形態の工程計画作成システム200の構成によって、例えば、雨等の天候の影響により水道管工事を行えない場合に、工事の遅れを取り戻すための工程計画の修正を行うことができる。よって、水道管工事の工程計画を、実情に合わせてより精度良く作成することができる。
 (その他の実施形態)
 以上、本発明の実施の形態を説明したが、上述した実施の形態は本発明を実施するための例示に過ぎない。よって、上述した実施の形態に限定されることなく、その趣旨を逸脱しない範囲内で上述した実施の形態を適宜変形して実施することが可能である。
 前記各実施形態では、工程計画作成システム1は、計画制御部15を有する。しかしながら、工程計画作成システムは、計画制御部を有さずに、情報取得部11では得られない情報のうち水道管工事の工程計画を作成するために必要な工事条件を、入力によって得てもよいし、記憶装置等に予め記憶されているデータから得てもよい。
 前記各実施形態では、水道管工事関連情報は、現場条件に関連する情報と、地上関連情報と、地中関連情報とを含む。しかしながら、水道管工事関連情報は、現場条件に関連する情報を含んでいなくてもよい。水道管工事関連情報は、地上関連情報を含んでいなくてもよい。水道管工事関連情報は、地中関連情報を含んでいなくてもよい。
 前記各実施形態では、地上関連情報は、地上周辺関連情報と、道路状況関連情報とを含む。しかしながら、地上関連情報は、地上周辺関連情報を含んでいなくてもよい。地上関連情報は、道路状況関連情報を含んでいなくてもよい。
 前記各実施形態では、工程時間演算部21は、水道管関連情報及び水道管工事関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する。しかしながら、工程時間演算部は、水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算してもよい。工程時間演算部は、水道管工事関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算してもよい。
 前記各実施形態では、工程時間演算部21は、水道管関連情報及び水道管工事関連情報に基づいて、水道管工事の各工程における予備時間を演算する。しかしながら、工程時間演算部は、水道管関連情報に基づいて、水道管工事の各工程における予備時間を演算してもよい。工程時間演算部は、水道管工事関連情報に基づいて、水道管工事の各工程における予備時間を演算してもよい。
 前記各実施形態では、工程計画作成システム1,100,200は、水道管を地中に埋設する水道管工事の工程計画を作成して出力する。しかしながら、工程計画作成システムは、水道管の埋設だけでなく、水道管に対して並行に配置された並行管の埋設も含めた水道管工事の工程計画を作成してもよい。
 前記各実施形態では、工程計画作成システム1,100,200は、水道管工事の工程計画を作成する。しかしながら、工程計画作成システムは、工程計画以外にも、施工管理計画などを含む水道事業体への提出資料を作成してもよい。また、工程計画作成システムは、作業表、施工管理表及び在庫管理表などの工事中に管理したいデータを可視化してもよい。また、工程計画作成システムは、工程表、工事日報を自動作成してもよい。また、工程計画作成システムは、実施工程表などの工事完了後の書類を自動作成してもよい。
 前記各実施形態では、工程計画作成システム1,100,200は、地面を掘削する開削工法によって水道管工事を行う場合の工程計画を作成する。しかしながら、工程計画作成システムは、トンネル内に水道管を配管する場合などに用いられる非開削工法によって水道管工事を行う場合の工程計画を作成してもよい。この場合には、工程計画作成システムは、前記非開削工法の水道管工事に適した工程に基づいて、工程計画を作成する。
 前記実施形態2では、工程計画作成システム200は、水道管工事の実際の進捗状況に応じて、水道管工事の工程計画を修正する。しかしながら、工程計画作成システムは、目標工期を守るために必要な人員または作業機械をリコメンドしてもよい。このようなリコメンドを、実施形態1の工程計画作成システムが行ってもよい。
 本発明は、水道管工事の工程計画を作成する工程計画作成システムに利用可能である。
1、100、200 工程計画作成システム
11 情報取得部
15 計画制御部
21 工程時間演算部
31 工程計画作成部
121 工程時間演算部
122 予備時間補正部
241 進捗状況関連情報取得部
242 工程計画修正部
W 水道管
L 溝
M 作業機械
P 矢板
R 道路
R1 表層
R2 上層路盤
R3 下層路盤
R4 路床

Claims (11)

  1.  水道管工事の工程計画を作成する工程計画作成システムであって、
     水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得部と、
     前記情報取得部によって取得した前記水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算部と、
     前記工程時間演算部によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成部と、
    を有する、
    水道管工事の工程計画作成システム。
  2.  請求項1に記載の水道管工事の工程計画作成システムにおいて、
     前記情報取得部は、前記水道管関連情報に加えて、水道管工事に関連する水道管工事関連情報も取得し、
     前記工程時間演算部は、前記情報取得部によって取得された前記水道管関連情報及び前記水道管工事関連情報を用いて、前記工程時間を演算する、
    水道管工事の工程計画作成システム。
  3.  請求項2に記載の水道管工事の工程計画作成システムにおいて、
     前記水道管工事関連情報は、
     前記水道管を埋設する場所の地上に関連する情報を含む地上関連情報と、
     前記水道管を埋設する場所の地中に関連する情報を含む地中関連情報と、
    を含む、
    水道管工事の工程計画作成システム。
  4.  請求項3に記載の水道管工事の工程計画作成システムにおいて、
     前記地上関連情報は、
     前記水道管を埋設する場所の地上周辺に関連する地上周辺関連情報と、
     前記水道管を埋設する場所の道路状況に関連する道路状況関連情報と、
    を含む、
    水道管工事の工程計画作成システム。
  5.  請求項3または4に記載の水道管工事の工程計画作成システムにおいて、
     前記地中関連情報は、地中障害物、道路構造、土質及び地下水のうち少なくとも一つに関連する情報を含む、
    水道管工事の工程計画作成システム。
  6.  請求項2から5のいずれか一つに記載の水道管工事の工程計画作成システムにおいて、
     前記工程時間演算部は、前記水道管関連情報及び前記水道管工事関連情報に基づいて、水道管工事の各工程における予備時間を演算し、
     前記工程計画作成部は、各工程の工程時間だけでなく前記予備時間も考慮して、水道管工事の少なくとも一部の工程計画を作成する、
    水道管工事の工程計画作成システム。
  7.  請求項6に記載の水道管工事の工程計画作成システムにおいて、
     前記工程時間演算部は、水道管工事の各工程における前記予備時間を、過去の実績に基づいて補正する予備時間補正部を有する、
    水道管工事の工程計画作成システム。
  8.  請求項2から7のいずれか一つに記載の水道管工事の工程計画作成システムにおいて、
     前記情報取得部は、前記水道管工事関連情報として、水道管工事を行わない日時に関連する工事休止関連情報を取得し、
     前記工程計画作成部は、前記情報取得部によって取得した前記工事休止関連情報及び前記工程時間演算部によって演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する、
    水道管工事の工程計画作成システム。
  9.  請求項1から8のいずれか一つに記載の水道管工事の工程計画作成システムにおいて、
     水道管工事の進捗状況に関連する進捗状況関連情報を取得する進捗状況関連情報取得部と、
     前記進捗状況関連情報取得部によって取得された前記進捗状況関連情報を用いて、前記工程計画作成部によって作成された工程計画を修正する工程計画修正部と、
    をさらに有する、
    水道管工事の工程計画作成システム。
  10.  水道管工事の工程計画を作成する工程計画作成方法であって、
     水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得する情報取得ステップと、
     前記情報取得ステップで取得された前記水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算する工程時間演算ステップと、
     前記工程時間演算ステップで演算された前記各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成する工程計画作成ステップと、
    を有する、
    水道管工事の工程計画作成方法。
  11.  水道管工事の工程計画を作成するためのプログラムであって、
     コンピュータに、
     水道管工事に用いる水道管の径、長さ、種類、数及び配置のうち少なくとも一つに関連する水道管関連情報を取得させ、
     前記取得した水道管関連情報に基づいて、水道管工事の各工程の作業時間を含む工程時間を演算させ、
     前記演算した各工程の工程時間を用いて、水道管工事の少なくとも一部の工程計画を作成させる、
    水道管工事の工程計画を作成するためのプログラム。 
PCT/JP2022/046724 2021-12-24 2022-12-19 水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム WO2023120489A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2021-210631 2021-12-24
JP2021210631A JP2023094996A (ja) 2021-12-24 2021-12-24 水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム

Publications (1)

Publication Number Publication Date
WO2023120489A1 true WO2023120489A1 (ja) 2023-06-29

Family

ID=86902477

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2022/046724 WO2023120489A1 (ja) 2021-12-24 2022-12-19 水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム

Country Status (3)

Country Link
JP (1) JP2023094996A (ja)
TW (1) TW202331631A (ja)
WO (1) WO2023120489A1 (ja)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003176693A (ja) * 2001-12-10 2003-06-27 Osaka Gas Co Ltd 道路使用工事の計画方法およびシステム
JP2009139996A (ja) * 2007-12-03 2009-06-25 Riraito:Kk 建築管理システム
JP5665759B2 (ja) 2009-11-12 2015-02-04 株式会社東芝 工事工程作成システムおよび工事工程作成方法
JP2021096563A (ja) * 2019-12-16 2021-06-24 株式会社日立製作所 生産計画立案支援システム及び生産計画立案支援方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003176693A (ja) * 2001-12-10 2003-06-27 Osaka Gas Co Ltd 道路使用工事の計画方法およびシステム
JP2009139996A (ja) * 2007-12-03 2009-06-25 Riraito:Kk 建築管理システム
JP5665759B2 (ja) 2009-11-12 2015-02-04 株式会社東芝 工事工程作成システムおよび工事工程作成方法
JP2021096563A (ja) * 2019-12-16 2021-06-24 株式会社日立製作所 生産計画立案支援システム及び生産計画立案支援方法

Also Published As

Publication number Publication date
JP2023094996A (ja) 2023-07-06
TW202331631A (zh) 2023-08-01

Similar Documents

Publication Publication Date Title
Ghorbani et al. Geotechnical, structural and geodetic measurements for conventional tunnelling hazards in urban areas–The case of Niayesh road tunnel project
Yasitli Numerical modeling of surface settlements at the transition zone excavated by New Austrian Tunneling Method and Umbrella Arch Method in weak rock
JP5114528B2 (ja) 埋設管工事・土木工事の設計・管理支援システム
Berdigylyjov et al. The implementation and role of geotechnical data in BIM process
WO2023120489A1 (ja) 水道管工事の工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム
Hassanein Planning and scheduling highway construction using GIS and dynamic programming
Glass et al. Application of the observational method at the Limehouse Link
US9990449B2 (en) Pipeline design and installation systems and methods
Han et al. Productivity evaluation of the conventional and GPS-based earthmoving systems using construction simulation
Azar et al. Effectiveness of automated machine guidence technology in productivity improvement: Case study
AECOM Spon's Civil Engineering and Highway Works Price Book 2019
Hastak et al. Decision Tool for Selecting the Most Appropriate Technology for Underground Conduit Construction
KR100961512B1 (ko) 지하 매설물을 용이하게 설치하기 위한 건설공사ve의 일환으로 l형측구 선시공이 적용된 부지 조성 공법
Hamad et al. Construction Cost for Soil Excavation (Cut and Fill) on-Site: Computer Based Program Analysis
JP4565494B2 (ja) 埋設管工事・土木工事の設計・管理支援システム
JP2003176693A (ja) 道路使用工事の計画方法およびシステム
White Three-dimensional modelling at Clays Lake
Hutson et al. Big Pipe—Tight Quarters: Lessons Learned from Large Diameter Urban Pipelines
Kakoto et al. Engineering decision support of automated shield tunneling
Moselhi et al. Data acquisition and analysis for highway construction using geographic information systems
Fuentez Feasibility of Utilizing Autonomous, Trenchless Tunneling Technology
Flaten Predicting production rates in the wisconsin highway construction industry using computer tools
Hutson Big Pipe-Tight Quarters: Lessons Learned from Large Diameter Urban Pipelines By Alan C. Hutson, PE, Russell L. Gibson, PE 2, Jared Barber, PE 3
Horst et al. CAED Support Shop Concrete Slab
Kaur Effectiveness of project based learning (PBL) for undergraduate-bachelor’s civil engineering education

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application