WO2023082119A1 - Waste gas tower - Google Patents

Waste gas tower Download PDF

Info

Publication number
WO2023082119A1
WO2023082119A1 PCT/CN2021/129952 CN2021129952W WO2023082119A1 WO 2023082119 A1 WO2023082119 A1 WO 2023082119A1 CN 2021129952 W CN2021129952 W CN 2021129952W WO 2023082119 A1 WO2023082119 A1 WO 2023082119A1
Authority
WO
WIPO (PCT)
Prior art keywords
tower body
water tank
support plate
tower
water
Prior art date
Application number
PCT/CN2021/129952
Other languages
French (fr)
Chinese (zh)
Inventor
匡优新
Original Assignee
无锡星亿智能环保装备股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 无锡星亿智能环保装备股份有限公司 filed Critical 无锡星亿智能环保装备股份有限公司
Priority to PCT/CN2021/129952 priority Critical patent/WO2023082119A1/en
Priority to CN202180004063.2A priority patent/CN114206475A/en
Publication of WO2023082119A1 publication Critical patent/WO2023082119A1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/34Chemical or biological purification of waste gases
    • B01D53/74General processes for purification of waste gases; Apparatus or devices specially adapted therefor
    • B01D53/77Liquid phase processes
    • B01D53/79Injecting reactants

Definitions

  • the present application relates to the technical field of environmental protection equipment, for example, to an exhaust gas tower.
  • the waste gas tower can process the waste gas emitted by some industrial production, remove the harmful substances in the gas and the substances that will cause environmental pollution, and avoid pollution to the human living environment and the atmosphere.
  • Exhaust gas towers are used in a wide range of applications. Exhaust gas towers are widely used in chemical enterprises. Because chemical production will produce a large amount of harmful chemical gases, these gases will be discharged into the air without treatment, which will cause great harm to the environment and human health. big damage.
  • Some light industries also use exhaust gas towers, and some printing and dyeing factories, pharmaceutical factories, steel plants and power plants all need to use exhaust gas towers.
  • the exhaust gas tower adopts gas-liquid countercurrent operation, and the exhaust gas to be treated enters the interior from the inlet of the exhaust gas tower, is pressed into the air inlet section through the fan, then passes through the packing layer, and finally exits the exhaust gas tower.
  • the agent absorbed by the waste gas tower passes through the spraying device at the top of the waste gas tower, sprays evenly to the middle packing layer, and flows down along the surface of the packing layer to the bottom of the waste gas tower, and then is discharged out of the waste gas tower through the pipeline, and is pumped by the circulating water pump to The spraying device at the top of the tower is recycled.
  • a general waste gas tower will be provided with a water tank at the bottom of the tower body, which is set to store liquid.
  • the water tank and the tower body are made in one piece (the side plate of the water tank and the side plate of the tower body Adopt the whole board to make or weld as a whole), but this structure will have the following problems.
  • the tower body and the tower body are connected by flanges. If a water tank is shared between the multi-section tower bodies, since the tower body and the water tank are made integrally, the tower body The meaning of segmentation is lost.
  • the application provides an exhaust gas tower, which can make the water tank and the tower body separable, facilitate transportation and installation, and avoid air and water leakage from the exhaust gas tower.
  • An exhaust gas tower including a tower body and a water tank, the bottom of the tower body is surrounded by a first support plate in the vertical direction, the tower body is supported and overlapped with the water tank by the first support plate, and the first support plate will
  • the water tank is divided into a water storage chamber and a medicine dosing chamber, and the first support plate is provided with a communication port connecting the water storage chamber and the medicine dosing chamber.
  • Fig. 1 is the sectional view of the waste gas tower that the application provides;
  • Fig. 2 is the structural representation of the tower body that the application provides;
  • Fig. 3 is the structural representation of the tower body that the application provides
  • Fig. 4 is a schematic diagram of the relationship between the number of tower body sections and the number of water tanks provided by the present application.
  • the terms “center”, “upper”, “lower”, “left”, “right”, “vertical”, “horizontal”, “inner”, “outer”, etc. indicate orientation or position The relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, therefore It should not be construed as a limitation of the application.
  • the terms “first” and “second” are used for descriptive purposes only, and should not be construed as indicating or implying relative importance.
  • first position and second position are two different positions, and "above”, “above” and “above” the first feature on the second feature include that the first feature is on the second feature. Directly above and obliquely above, or simply means that the first feature level is higher than the second feature. "Below”, “beneath” and “under” the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.
  • connection should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; It can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components.
  • installation can be a fixed connection, a detachable connection, or an integral connection; It can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components.
  • connection should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; It can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components.
  • connection should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; It can be a mechanical connection or
  • the tower body of the waste gas tower is made in sections.
  • the water tank and the tower body are made in one piece.
  • the towers are actually inseparable; if a separate water tank is installed for each section of the tower, in order to avoid water leakage at the connection between the tower and the tower, the water tank is often set longer to ensure that the tower and the tower The connection is placed above the water tank. This setting also makes the tower body inseparable from each other, and loses the meaning of segmented production.
  • the tower body and the tower body are connected by flanges. If a water tank is shared between the multi-section tower bodies, the division between the tower bodies will be lost due to the integrated production of the tower body and the water tank.
  • the significance of the section if the water tank is also segmented, and there is a water tank under each section of the tower body, then when the length of the water tank is less than or equal to the length of the tower body, there is no water tank below the flange connection between the tower body and the tower body , if the flange connection leaks, the liquid will leak out of the exhaust gas tower. If the length of the water tank is longer than the length of the tower body, so that there is a water tank under the flange connection between the tower body and the tower body, the tower body will also lose its segmental function. significance.
  • an exhaust gas tower is provided.
  • the tower body 100 is supported and overlapped with the water tank 200 through the first support plate 300, the first support plate 300 divides the water tank 200 into a water storage chamber 210 and a dosing chamber 220, and the first support plate 300
  • a communication port 310 connecting the water storage chamber 210 and the medicine feeding chamber 220 is provided.
  • the waste gas tower includes a tower body 100 and a water tank 200 , wherein a circle of first support plates 300 is vertically arranged at the bottom of the tower body 100 , and the first support plates 300 are lapped on the water tank 200 Among them, the bottom of the water tank 200 supports the first support plate 300.
  • the first support plate 300 divides the water tank 200 into two parts: the water storage chamber 210 and the dosing chamber 220. The part surrounded by the first support plate 300 is the storage chamber.
  • the water chamber 210 the rest is the dosing chamber 220
  • the first support plate 300 is provided with a communication port 310
  • the water storage chamber 210 and the dosing chamber 220 are communicated through the communication port 310
  • the medicine is added through the dosing chamber 220
  • the communication port 310 the water in the water storage chamber 210 contains medicament, and the medicament is configured to absorb harmful gas.
  • the tower body 100 and the water tank 200 can be separated.
  • the water tank 200 is divided into storage tanks by the first support plate 300
  • the water chamber 210 and the dosing chamber 220 simplify the processing procedure of the water tank 200, improve production efficiency and reduce production cost.
  • the harmful gas when the above-mentioned waste gas tower is working, the harmful gas is pressed or sucked into the air inlet section through the centrifugal fan, and then flows to the packing layer, where it contacts and reacts with the spray liquid.
  • the spray system uses clear water as the circulating absorption liquid, and the circulating water is sprayed from the water distributor on the upper part of the tower body 100 to the packing layer, wetting the packing surface to form a flowing liquid film, and in the packing layer, the gas and liquid phases are countercurrent Flow and contact, using the certain solubility of harmful gas in the absorbent, the meltable part is continuously integrated into the absorption liquid to achieve the purpose of degrading the content of harmful components in the gas.
  • the harmful gas is continuously absorbed or removed by chemical reactions. During the flow process, it will gradually decrease, and it will be discharged out of the waste gas tower after reaching the absorption requirement.
  • the water source of the water distributor on the upper part of the tower body 100 comes from the water tank 200, and the water in the water tank 200 is pumped to the upper part of the tower body 100 through the circulating water pump, then enters the water distributor to spray and react with harmful gases, and then falls back to the water tank 200 for recycling , when the water quality in the water tank 200 deteriorates and needs to be replaced, they will be replaced uniformly.
  • some mesh holes 110 can be set at the bottom of the tower body 100 , and the water sprayed by the water distributor flows back to the bottom of the tower body 100 and flows into the water tank 200 through the mesh holes 110 .
  • the tower body 100 is provided with a mesh 110 connecting the water storage chamber 210 with the tower body 100 .
  • a mesh 110 can be opened in the area surrounded by the first support plate 300, so that the mesh 110 can communicate with the interior of the tower body 100 and the water storage chamber 210, so as to ensure that the water in the water tank 200 is recycled.
  • the number and size of 110 should be able to meet the water circulation requirements of the waste gas tower, and avoid affecting the water flow velocity due to fewer or smaller meshes 110, thereby affecting the water circulation speed of the waste gas tower and reducing the working efficiency of the waste gas tower.
  • the second support plate 120 can be set at the bottom edge of the tower body 100, and the third support plate 230 is correspondingly set at the edge of the water tank 200, and the second support plate 120 is overlapped on the third support plate 230 to increase the contact area between the tower body 100 and the water tank 200 , thereby improving the stability of the connection between the tower body 100 and the water tank 200 .
  • the second support plate 120 and the third support plate 230 can be arranged along the horizontal direction, the second support plate 120 and the third support plate 230 are two flat plates, the second support plate 120 and the third support plate 230 The plane positions of the two butt against each other, and the third support plate 230 supports the second support plate 120.
  • a detachable connection structure can be provided, such as bolt connection, snap connection, etc.; in another embodiment, the second support plate 120 can be a flat plate, and the third support plate 230 can be an L-shaped plate.
  • the vertical surface of the L-shaped plate can play a role in radial positioning of the second support plate 120, avoiding the displacement of the tower body 100 relative to the water tank 200 due to vibration during the operation of the waste gas tower , thereby affecting the performance of the exhaust gas tower.
  • the second support plate 120 can be arranged on both sides of the tower body 100, and the third support plate 230 is arranged on the position opposite to the second support plate 120 on the water tank 200, and the second support plate 230 is used to support the second support plate 230.
  • Support plate 120 and then stabilize the connection between tower body 100 and water tank 200;
  • the third supporting board 230 is arranged to support the second supporting board 120 .
  • the second supporting plate 120 can be arranged continuously along the circumferential direction of the tower body 100, and can also be arranged at intervals along the circumferential direction of the tower body 100. It can be produced according to actual needs.
  • the third supporting plate 230 can also be continuously arranged on the edge of the water tank 200 or The spaced arrangement only needs to ensure that the third support plate 230 can stably support the second support plate 120 .
  • the second support plate 120 can be connected to the tower body 100 by welding; in other embodiments, the second support plate 120 can also be connected to the tower body 100 by bolt connection.
  • the third support plate 230 can be connected with the water tank 200 by welding; in another embodiment, the third support plate 230 can be made integrally with the wall plate of the water tank 200; in other implementations In an example, the third support plate 230 may also be connected with the water tank 200 through bolt connection.
  • the height of the first support plate 300 can be greater than or equal to the depth of the water tank 200, which can prevent the tower body 100 from immersing in the water tank 200, and can ensure that the water tank 200 supports the tower body by overlapping the bottom of the water tank 200 and the first support plate 300 100, and the tower body 100 is supported by the overlapping of the third support plate 230 and the second support plate 120.
  • the double support structure can stabilize the connection between the tower body 100 and the water tank 200, and avoid the vibration and collision caused by the waste gas tower when it is working.
  • the displacement of the tower body 100 relative to the water tank 200 affects the working performance of the waste gas tower.
  • the first support plate 300 can be connected to the tower body 100 by welding; in other embodiments, the first support plate The plate 300 can also be made integrally with the side plate of the tower body 100, and the connection between the first support plate 300 and the tower body 100 must be sealed so as not to leak air or water.
  • a communication port 310 can be provided on the first support plate 300, through which the liquid in the water storage chamber 210 and the dosing chamber 220 can be connected, the medicine can be added through the dosing chamber 220, and through the communication
  • the port 310 makes the water in the water storage chamber 210 also be filled with medicament, and the structure of the communication port 310 enables the staff to finish adding the medicament outside the tower body 100 .
  • the communication port 310 can be arranged at the bottom of the first support plate 300, through the communication port 310, the liquid level in the water tank 200 is the same as the liquid level in the area surrounded by the first support plate 300, and the water in the water tank 200 can be kept at Lift to the upper part of the tower body 100 and then flow back to the water tank 200 by spraying, because the liquid level in the water tank 200 is generally only 150mm-200mm downward from the lower edge of the water tank 200 (the liquid level cannot reach the upper edge of the water tank 200 , otherwise it may overflow from the dosing chamber 220 at any time), the gas inside the tower body may leak from the mesh to the water tank in the related art, and then overflow from the liquid surface of the water tank through the dosing port, causing the waste gas tower to leak air, and this
  • the exhaust gas tower provided by the application, through the structure of the first support plate 300 can ensure that whether it is liquid flow or air flow leaking from the tower body 100, it is only in the area surrounded by the first support plate 300, and
  • the 310 is arranged at the bottom of the first support plate 300 so that the gas or liquid flow in the tower body 100 will not leak from the connection between the first support plate 300 and the tower body 100 .
  • the air flow passes through the inside of the tower body 100. If it leaks from the mesh 110, the liquid in the area surrounded by the first support plate 300 will form a liquid seal to prevent the air flow from escaping. At the same time, the liquid seal can also prevent the external air flow from adding medicine. into cavity 220.
  • Multiple communication ports 310 can be provided. Continue to refer to FIG. 2 .
  • multiple communication ports 310 can be arranged at intervals on the bottom of the first support plate 300, which can speed up the flow of liquid and ensure that the water storage chamber 210 and the dosing chamber The liquid level in 220 remains at the same level.
  • the first support plate 300 can be installed on one side of the water tank 200, at this time, the dosing chamber 220 is on one side of the water tank 200; the first support plate 300 can also be installed in the water tank 200 , not in contact with the side wall of the water tank 200 , at this time the dosing chamber 220 is located on both sides or surroundings of the water storage chamber 210 .
  • a cover plate 240 can be provided above the dosing chamber 220 to prevent impurities in the external environment from entering the dosing chamber 220 and affecting the water quality in the water tank 200 .
  • the cover plate 240 and the medicine feeding chamber 220 may be connected in a rotational manner, which is convenient for the staff to open and close the cover plate 240 .
  • the cover plate 240 can be connected to the dosing chamber 220 through a hinge, and the cover plate 240 can rotate relative to the dosing chamber 220 around the hinge shaft of the hinge, and retaining rings can also be provided at both ends of the hinge shaft, and the retaining rings can prevent the hinge shaft from loosening , slipping occurs, the cover 240 and the dosing chamber 220 are connected by hinges, which is convenient for opening and closing the cover 240 .
  • a handle can be arranged on the cover plate 240 , and the staff can open and close the cover plate 240 through the handle.
  • the handle and the cover plate 240 can be fixedly connected by welding; in other embodiments, the cover plate 240 can also be connected with the handle by bolt connection.
  • a drain can be set on the water tank 200, and the drain can be connected to the pipeline.
  • the water quality in the water tank 200 is poor enough to purify harmful gases, the water in the water tank 200 can be drained away through the drain.
  • the tower body 100 is divided into multiple sections, and the multi-section tower body 100 shares a water tank 200; or, the tower body 100 is divided into multiple sections, and the multi-section tower body 100 shares a plurality of water tanks 200, and the connection between two adjacent sections of the tower body 100 is arranged in the water tank Above 200.
  • the tower body 100 is divided into multiple sections, each section of the tower body 100 is provided with a water tank 200, and the junction of two adjacent sections of the tower body 100 is set above the water tank 200 (the water tank 200 directly below the section of the tower body).
  • the relationship between the number of tower body sections and the number of water tanks is shown, wherein the number of tower body sections can be M sections, and the number of water tanks can be N.
  • the number of tower body sections is M
  • the number of tower body sections is M sections, 2 ⁇ N ⁇ M, at this time, when there is no water tank under the tower body 100 of a section, the mesh 110 is not opened on the inner bottom plate of the tower body 100 of this section, and the inside of the tower body 100 of this section The liquid flows to the adjacent tower body 100 through the slope, and then flows into the water tank 200 below the adjacent tower body 100 through the mesh 110 on the bottom plate of the adjacent tower body 100 .
  • the number of tower body sections is M sections
  • Fig. 4 exemplarily illustrates the relationship between the number of tower body sections and the number of water tanks.
  • the tower body 100 and the water tank 200 can also be arranged in other ways, which are not limited in this application.
  • the above embodiment needs to ensure that the connection of the segmented tower body must be above the water tank, so that it can be ensured that even if the connection leaks, it will only leak into the water tank and not outside the water tank.
  • the waste gas tower is composed of multi-section tower bodies 100.
  • all tower bodies 100 share a water tank 200, and the water tank 200 covers the joints of all tower bodies 100 to avoid air and water leakage in the waste gas tower and ensure that the multi-section tower bodies 100
  • the multi-section tower body 100 can share multiple water tanks 200.
  • the multi-section tower body 100 can share two water tanks 200, or the multi-section tower body 100 can share three water tanks 200, etc., while To ensure that the connection between the tower body 100 and the tower body 100 is placed above the water tank 200, the liquid in the waste gas tower can be prevented from leaking into the external environment from the connection between the tower body 100 and the tower body 100; in other embodiments, each section The tower body 100 is provided with a water tank 200 alone, but the length of the water tank 200 is to ensure that the connection between the tower body 100 and the tower body 100 is placed above the water tank 200, so as to avoid the connection of the liquid in the waste gas tower from the tower body 100 to the tower body 100 leakage into the external environment.
  • the tower body 100 can be separated from the water tank 200 by vertically enclosing the first support plate 300 at the bottom of the tower body 100 and overlapping the first support plate 300 in the water tank 200, which is convenient for transportation.
  • divide the water tank 200 into the water storage chamber 210 and the dosing chamber 220 through the first support plate 300 which can simplify the processing procedure of the water tank 200, improve production efficiency, and reduce costs; at the same time, the first support
  • the liquid seal in the area surrounded by the plate 300 prevents the gas flow and liquid flow in the exhaust gas tower from leaking from the connection between the first support plate 300 and the tower body 100, avoiding air and water leakage from the exhaust gas tower, and at the same time, the external gas will not leak from the exhaust gas tower.
  • the dosing chamber 220 enters the tower body 100 .
  • the water tank is integrated with the tower body of the waste gas tower in the related art.
  • the tower body made in sections shares a water tank, the water tank cannot be segmented, so that the tower body cannot be segmented.
  • the waste gas tower above can be disassembled and assembled at any time by enclosing the first support plate in the vertical direction at the bottom of the tower body and lapping the first support plate on the water tank , easy to transport.
  • each section of the tower body When each section of the tower body is provided with a separate water tank, the water tank often covers the joint of the tower body. If the water tank is covered with the tower body joint and made integrally with the tower body, this structure also makes the tower body connected together and cannot be segmented. Good for transportation.
  • the above-mentioned waste gas tower encloses the first support plate in the vertical direction at the bottom of the tower body, and overlaps the first support plate on the water tank, and by setting the length of the water tank, the connection of the tower body can be made above the water tank. It can not only avoid water leakage at the joint of the tower body, but also ensure that the tower body made in sections can be disassembled and assembled at any time.

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Biomedical Technology (AREA)
  • Analytical Chemistry (AREA)
  • General Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Gas Separation By Absorption (AREA)
  • Treating Waste Gases (AREA)

Abstract

Provided in the present application is a waste gas tower, comprising a tower body and a water tank, wherein a first support plate is vertically arranged at the bottom of the tower body in a surrounding manner; the tower body is supported and connected to the water tank in an overlapping manner by means of the first support plate; the first support plate divides the water tank into a water storage chamber and a dosing chamber; and the first support plate is provided with communication ports by which the water storage cavity is in communication with the dosing chamber.

Description

废气塔exhaust tower 技术领域technical field
本申请涉及环保设备技术领域,例如涉及一种废气塔。The present application relates to the technical field of environmental protection equipment, for example, to an exhaust gas tower.
背景技术Background technique
废气塔能够把一些工业生产时所排放出来的废气进行处理,把气体当中的有害物质以及会造成环境污染的物质都清除掉,避免对人类生活的环境以及大气层造成污染。废气塔的使用范围较广,在化工类企业中废气塔应用较多,由于化工生产会产生大量的有害化学气体,这些气体没有经过处理就排放到空气中,会对环境以及人体的健康造成很大的伤害。有些轻工业也使用废气塔,还有一些印染厂、医药厂、钢铁厂以及发电厂等都需要用到废气塔。The waste gas tower can process the waste gas emitted by some industrial production, remove the harmful substances in the gas and the substances that will cause environmental pollution, and avoid pollution to the human living environment and the atmosphere. Exhaust gas towers are used in a wide range of applications. Exhaust gas towers are widely used in chemical enterprises. Because chemical production will produce a large amount of harmful chemical gases, these gases will be discharged into the air without treatment, which will cause great harm to the environment and human health. big damage. Some light industries also use exhaust gas towers, and some printing and dyeing factories, pharmaceutical factories, steel plants and power plants all need to use exhaust gas towers.
废气塔采用气液逆流运行,待处理的废气由废气塔进口进入内部,通过通风机压入进风段,然后穿过填料层,最后排出废气塔。废气塔吸收的药剂通过废气塔顶部的喷淋装置,均匀地喷淋到中间填料层,并沿着填料层表面向下流动直到废气塔底部,再通过管道排出废气塔外,通过循环水泵抽至塔顶的喷淋装置循环使用。The exhaust gas tower adopts gas-liquid countercurrent operation, and the exhaust gas to be treated enters the interior from the inlet of the exhaust gas tower, is pressed into the air inlet section through the fan, then passes through the packing layer, and finally exits the exhaust gas tower. The agent absorbed by the waste gas tower passes through the spraying device at the top of the waste gas tower, sprays evenly to the middle packing layer, and flows down along the surface of the packing layer to the bottom of the waste gas tower, and then is discharged out of the waste gas tower through the pipeline, and is pumped by the circulating water pump to The spraying device at the top of the tower is recycled.
一般的废气塔都会在塔体底部设置一个水箱,设置为储存液体,相关技术中为避免废气塔的塔体渗漏,水箱大多数与塔体采用一体式制作(水箱侧板与塔体侧板采用整板一体制作或焊接为一体),但是这种结构会存在以下问题。A general waste gas tower will be provided with a water tank at the bottom of the tower body, which is set to store liquid. In the related art, in order to avoid leakage of the tower body of the waste gas tower, most of the water tank and the tower body are made in one piece (the side plate of the water tank and the side plate of the tower body Adopt the whole board to make or weld as a whole), but this structure will have the following problems.
(1)造成塔体体积增加,不利于运输安装。(1) The volume of the tower body increases, which is not conducive to transportation and installation.
(2)对于分段制作的卧式废气塔来说,塔体与塔体之间采用法兰连接,若多段塔体之间共用一个水箱,则由于塔体与水箱一体制作,塔体之间失去了分段的意义。(2) For the horizontal exhaust gas tower manufactured in sections, the tower body and the tower body are connected by flanges. If a water tank is shared between the multi-section tower bodies, since the tower body and the water tank are made integrally, the tower body The meaning of segmentation is lost.
发明内容Contents of the invention
本申请提供一种废气塔,能够使水箱和塔体可分离,能够便于运输与安装,避免废气塔漏风和漏水。The application provides an exhaust gas tower, which can make the water tank and the tower body separable, facilitate transportation and installation, and avoid air and water leakage from the exhaust gas tower.
提供一种废气塔,包括塔体和水箱,上述塔体底部沿竖直方向围设有第一支撑板,上述塔体通过上述第一支撑板支撑搭接于上述水箱,上述第一支撑板将上述水箱分隔成蓄水腔和加药腔,且上述第一支撑板上设有连通上述蓄水腔和上述加药腔的连通口。An exhaust gas tower is provided, including a tower body and a water tank, the bottom of the tower body is surrounded by a first support plate in the vertical direction, the tower body is supported and overlapped with the water tank by the first support plate, and the first support plate will The water tank is divided into a water storage chamber and a medicine dosing chamber, and the first support plate is provided with a communication port connecting the water storage chamber and the medicine dosing chamber.
附图说明Description of drawings
图1为本申请提供的废气塔的剖视图;Fig. 1 is the sectional view of the waste gas tower that the application provides;
图2为本申请提供的塔体的结构示意图;Fig. 2 is the structural representation of the tower body that the application provides;
图3为本申请提供的塔体的结构示意图;Fig. 3 is the structural representation of the tower body that the application provides;
图4为本申请提供的塔体段数与水箱个数的关系示意图。Fig. 4 is a schematic diagram of the relationship between the number of tower body sections and the number of water tanks provided by the present application.
图中:In the picture:
100、塔体;110、网孔;120、第二支撑板;200、水箱;210、蓄水腔;220、加药腔;230、第三支撑板;240、盖板;300、第一支撑板;310、连通口。100, tower body; 110, mesh; 120, second support plate; 200, water tank; 210, water storage chamber; 220, dosing chamber; 230, third support plate; 240, cover plate; 300, first support plate; 310, a communication port.
具体实施方式Detailed ways
下面将结合附图对本申请的技术方案进行描述,所描述的实施例是本申请一部分实施例,而不是全部的实施例。The technical solutions of the present application will be described below in conjunction with the accompanying drawings, and the described embodiments are part of the embodiments of the present application, but not all of the embodiments.
在本申请的描述中,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。此外,术语“第一”、“第二”、仅用于描述目的,而不能理解为指示或暗示相对重要性。其中,术语“第一位置”和“第二位置”为两个不同的位置,而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。In the description of this application, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate orientation or position The relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, therefore It should not be construed as a limitation of the application. In addition, the terms "first" and "second" are used for descriptive purposes only, and should not be construed as indicating or implying relative importance. Wherein, the terms "first position" and "second position" are two different positions, and "above", "above" and "above" the first feature on the second feature include that the first feature is on the second feature. Directly above and obliquely above, or simply means that the first feature level is higher than the second feature. "Below", "beneath" and "under" the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.
在本申请的描述中,除非另有规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。可以根据实际情况理解上述术语在本申请中的含义。In the description of this application, unless otherwise specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; It can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components. The meanings of the above terms in this application can be understood according to the actual situation.
下面描述本申请的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,仅用于解释本申请,而不能理解为对本申请的限制。Embodiments of the present application are described below, examples of which are shown in the drawings, wherein the same or similar reference numerals designate the same or similar elements or elements having the same or similar functions throughout. The embodiments described below by referring to the figures are exemplary, and are only for explaining the present application, and should not be construed as limiting the present application.
为了方便运输,废气塔的塔体会分段制作,对于分段制作的卧式废气塔, 大多数情况下水箱与塔体采用一体式制作,若多段塔体共用一个水箱,则由于塔体和水箱为一体,则实际上塔体之间不可分离;若每段塔体单独设置一个水箱,则为了避免塔体与塔体的连接处漏水,水箱往往被设置的较长,保证塔体与塔体的连接处置于水箱的上方,这种设置也使得塔体与塔体之间不可拆分,失去了分段制作的意义。For the convenience of transportation, the tower body of the waste gas tower is made in sections. For the horizontal waste gas tower made in sections, in most cases, the water tank and the tower body are made in one piece. As a whole, the towers are actually inseparable; if a separate water tank is installed for each section of the tower, in order to avoid water leakage at the connection between the tower and the tower, the water tank is often set longer to ensure that the tower and the tower The connection is placed above the water tank. This setting also makes the tower body inseparable from each other, and loses the meaning of segmented production.
对于分段制作的卧式废气塔来说,塔体与塔体之间采用法兰连接,若多段塔体之间共用一个水箱,则由于塔体与水箱一体制作,塔体之间失去了分段的意义;若水箱也采用分段式,每段塔体的下方都设有水箱,则当水箱的长度小于或等于塔体的长度时,塔体与塔体的法兰连接处下方没有水箱,若法兰连接处渗漏,液体会漏出废气塔,若水箱的长度比塔体的长度长,使得塔体与塔体的法兰连接处下方有水箱,则塔体同样失去了分段的意义。For the horizontal waste gas tower manufactured in sections, the tower body and the tower body are connected by flanges. If a water tank is shared between the multi-section tower bodies, the division between the tower bodies will be lost due to the integrated production of the tower body and the water tank. The significance of the section; if the water tank is also segmented, and there is a water tank under each section of the tower body, then when the length of the water tank is less than or equal to the length of the tower body, there is no water tank below the flange connection between the tower body and the tower body , if the flange connection leaks, the liquid will leak out of the exhaust gas tower. If the length of the water tank is longer than the length of the tower body, so that there is a water tank under the flange connection between the tower body and the tower body, the tower body will also lose its segmental function. significance.
针对上述问题,在本申请的一个实施例中,提供了一种废气塔,如图1所示,该废气塔包括塔体100和水箱200,其中,塔体100的底部沿竖直方向围设有第一支撑板300,塔体100通过第一支撑板300支撑搭接于水箱200,第一支撑板300将水箱200分隔成蓄水腔210和加药腔220,且第一支撑板300上设有连通蓄水腔210和加药腔220的连通口310。如图1所示,该废气塔包括塔体100和水箱200,其中,在塔体100的底部沿竖直方向上围设一圈第一支撑板300,第一支撑板300搭接在水箱200中,水箱200的底部对第一支撑板300起到支撑的作用,第一支撑板300将水箱200分成蓄水腔210和加药腔220两部分,第一支撑板300围设的部分为蓄水腔210,其余部分为加药腔220,在第一支撑板300上设有连通口310,通过连通口310将蓄水腔210和加药腔220连通,通过加药腔220添加药剂,并通过连通口310使得蓄水腔210中的水中含有药剂,药剂设置为吸收有害气体。In view of the above problems, in one embodiment of the present application, an exhaust gas tower is provided. As shown in FIG. There is a first support plate 300, the tower body 100 is supported and overlapped with the water tank 200 through the first support plate 300, the first support plate 300 divides the water tank 200 into a water storage chamber 210 and a dosing chamber 220, and the first support plate 300 A communication port 310 connecting the water storage chamber 210 and the medicine feeding chamber 220 is provided. As shown in FIG. 1 , the waste gas tower includes a tower body 100 and a water tank 200 , wherein a circle of first support plates 300 is vertically arranged at the bottom of the tower body 100 , and the first support plates 300 are lapped on the water tank 200 Among them, the bottom of the water tank 200 supports the first support plate 300. The first support plate 300 divides the water tank 200 into two parts: the water storage chamber 210 and the dosing chamber 220. The part surrounded by the first support plate 300 is the storage chamber. The water chamber 210, the rest is the dosing chamber 220, the first support plate 300 is provided with a communication port 310, the water storage chamber 210 and the dosing chamber 220 are communicated through the communication port 310, the medicine is added through the dosing chamber 220, and Through the communication port 310, the water in the water storage chamber 210 contains medicament, and the medicament is configured to absorb harmful gas.
通过在塔体100的底部沿竖直方向上围设第一支撑板300,并将第一支撑板300支撑搭接在水箱200中,实现了塔体100和水箱200可分离,对于分段制作的卧式废气塔来说,能够保证分段的塔体100可以随时拆分和装配,保证了塔体100分段制作的意义,便于安装和运输,通过第一支撑板300将水箱200分成蓄水腔210和加药腔220,简化了水箱200的加工工序,提高生产效率,降低生产成本。By enclosing the first support plate 300 in the vertical direction at the bottom of the tower body 100, and supporting the first support plate 300 in the water tank 200, the tower body 100 and the water tank 200 can be separated. For the horizontal exhaust gas tower, it can ensure that the segmented tower body 100 can be disassembled and assembled at any time, which ensures the significance of the tower body 100 segmented production, and is convenient for installation and transportation. The water tank 200 is divided into storage tanks by the first support plate 300 The water chamber 210 and the dosing chamber 220 simplify the processing procedure of the water tank 200, improve production efficiency and reduce production cost.
继续参见图1,上述废气塔工作时,有害气体通过离心通风机压入或吸入进风段,再流动至填料层,与喷淋液接触反应。喷淋系统利用清水作为循环吸收液,循环水从塔体100的上部的布水器喷淋至填料层,润湿填料表面形成流动的液膜,在填料层内,气、液两相呈逆流流动并接触,利用有害气体在吸收剂中的一定溶解度,可融的部分不断融入吸收液中,达到降解气体中有害组分含 量的目的,有害气体不断被吸收或被化学反应去除掉,浓度在流动过程中逐渐降低,达到吸收要求后排出废气塔。塔体100的上部的布水器的水源来自水箱200,水箱200中的水通过循环水泵抽至塔体100的上部,然后进布水器喷淋与有害气体反应后又落回水箱200循环使用,等水箱200中的水质变差需要更换时,统一更换。因此,可以在塔体100的底部设置一些网孔110,经布水器喷淋后的水回流至塔体100的底部,并通过网孔110流入水箱200中。例如,塔体100上设有连通蓄水腔210与塔体100的网孔110。在一个实施例中,可以在第一支撑板300围设的区域内开设网孔110,使网孔110连通塔体100内部和蓄水腔210,保证水箱200中的水被循环使用,网孔110的数量以及大小应能满足废气塔的水循环的要求,避免因网孔110较少或较小而影响水流速度,进而影响废气塔的水循环速度,降低废气塔的工作效率。Continuing to refer to Fig. 1, when the above-mentioned waste gas tower is working, the harmful gas is pressed or sucked into the air inlet section through the centrifugal fan, and then flows to the packing layer, where it contacts and reacts with the spray liquid. The spray system uses clear water as the circulating absorption liquid, and the circulating water is sprayed from the water distributor on the upper part of the tower body 100 to the packing layer, wetting the packing surface to form a flowing liquid film, and in the packing layer, the gas and liquid phases are countercurrent Flow and contact, using the certain solubility of harmful gas in the absorbent, the meltable part is continuously integrated into the absorption liquid to achieve the purpose of degrading the content of harmful components in the gas. The harmful gas is continuously absorbed or removed by chemical reactions. During the flow process, it will gradually decrease, and it will be discharged out of the waste gas tower after reaching the absorption requirement. The water source of the water distributor on the upper part of the tower body 100 comes from the water tank 200, and the water in the water tank 200 is pumped to the upper part of the tower body 100 through the circulating water pump, then enters the water distributor to spray and react with harmful gases, and then falls back to the water tank 200 for recycling , when the water quality in the water tank 200 deteriorates and needs to be replaced, they will be replaced uniformly. Therefore, some mesh holes 110 can be set at the bottom of the tower body 100 , and the water sprayed by the water distributor flows back to the bottom of the tower body 100 and flows into the water tank 200 through the mesh holes 110 . For example, the tower body 100 is provided with a mesh 110 connecting the water storage chamber 210 with the tower body 100 . In one embodiment, a mesh 110 can be opened in the area surrounded by the first support plate 300, so that the mesh 110 can communicate with the interior of the tower body 100 and the water storage chamber 210, so as to ensure that the water in the water tank 200 is recycled. The number and size of 110 should be able to meet the water circulation requirements of the waste gas tower, and avoid affecting the water flow velocity due to fewer or smaller meshes 110, thereby affecting the water circulation speed of the waste gas tower and reducing the working efficiency of the waste gas tower.
考虑到塔体100与水箱200之间支撑的稳定性,可以在塔体100的底部边缘设置第二支撑板120,相对应的在水箱200的边缘设置第三支撑板230,将第二支撑板120搭接在第三支撑板230上,以增加塔体100与水箱200的接触面积,进而提高塔体100与水箱200连接的稳定性。Considering the stability of the support between the tower body 100 and the water tank 200, the second support plate 120 can be set at the bottom edge of the tower body 100, and the third support plate 230 is correspondingly set at the edge of the water tank 200, and the second support plate 120 is overlapped on the third support plate 230 to increase the contact area between the tower body 100 and the water tank 200 , thereby improving the stability of the connection between the tower body 100 and the water tank 200 .
在一个实施例中,第二支撑板120和第三支撑板230可以沿水平方向设置,第二支撑板120和第三支撑板230为两个平板,第二支撑板120和第三支撑板230的平面位置相互抵接,第三支撑板230对第二支撑板120起到支撑的作用,为了提高塔体100与水箱200的连接稳定性,第二支撑板120和第三支撑板230之间可以设置可拆卸连接的结构,如螺栓连接、卡扣连接等;在另一个实施例中,第二支撑板120可以为平板,第三支撑板230可以为L型板,将第二支撑板120搭接在L型板的水平面,L型板的竖直面可以对第二支撑板120起到径向定位的作用,避免在废气塔工作过程中由于震动而导致塔体100相对水箱200产生位移,从而影响废气塔的性能。In one embodiment, the second support plate 120 and the third support plate 230 can be arranged along the horizontal direction, the second support plate 120 and the third support plate 230 are two flat plates, the second support plate 120 and the third support plate 230 The plane positions of the two butt against each other, and the third support plate 230 supports the second support plate 120. In order to improve the connection stability between the tower body 100 and the water tank 200, between the second support plate 120 and the third support plate 230 A detachable connection structure can be provided, such as bolt connection, snap connection, etc.; in another embodiment, the second support plate 120 can be a flat plate, and the third support plate 230 can be an L-shaped plate. Lap on the horizontal surface of the L-shaped plate, the vertical surface of the L-shaped plate can play a role in radial positioning of the second support plate 120, avoiding the displacement of the tower body 100 relative to the water tank 200 due to vibration during the operation of the waste gas tower , thereby affecting the performance of the exhaust gas tower.
在一个实施例中,第二支撑板120可以设置在塔体100的两侧,第三支撑板230设置在水箱200上与第二支撑板120相对的位置,通过第三支撑板230支撑第二支撑板120,进而稳定塔体100与水箱200的连接;在其他实施例中,第二支撑架也可以沿塔体100的底部周向设置,第三支撑板230也可以沿水箱200的边缘周向设置,第三支撑板230设置为支撑第二支撑板120。第二支撑板120可以沿塔体100的周向连续设置,也可以沿塔体100的周向间隔设置,根据实际需要生产即可,第三支撑板230也可以在水箱200的边缘连续设置或间隔设置,只要保证第三支撑板230能够稳定支撑第二支撑板120即可。In one embodiment, the second support plate 120 can be arranged on both sides of the tower body 100, and the third support plate 230 is arranged on the position opposite to the second support plate 120 on the water tank 200, and the second support plate 230 is used to support the second support plate 230. Support plate 120, and then stabilize the connection between tower body 100 and water tank 200; The third supporting board 230 is arranged to support the second supporting board 120 . The second supporting plate 120 can be arranged continuously along the circumferential direction of the tower body 100, and can also be arranged at intervals along the circumferential direction of the tower body 100. It can be produced according to actual needs. The third supporting plate 230 can also be continuously arranged on the edge of the water tank 200 or The spaced arrangement only needs to ensure that the third support plate 230 can stably support the second support plate 120 .
在一个实施例中,第二支撑板120可以通过焊接的方式与塔体100相连;在其他实施例中,第二支撑板120也可以通过螺栓连接的方式与塔体100相连。In one embodiment, the second support plate 120 can be connected to the tower body 100 by welding; in other embodiments, the second support plate 120 can also be connected to the tower body 100 by bolt connection.
可选地,在一个实施例中,第三支撑板230可以通过焊接的方式与水箱200相连;在另一个实施例中,第三支撑板230可以与水箱200的壁板一体制作;在其他实施例中,第三支撑板230也可以通过螺栓连接的方式与水箱200相连。Optionally, in one embodiment, the third support plate 230 can be connected with the water tank 200 by welding; in another embodiment, the third support plate 230 can be made integrally with the wall plate of the water tank 200; in other implementations In an example, the third support plate 230 may also be connected with the water tank 200 through bolt connection.
第一支撑板300的高度可以大于或等于水箱200的深度,这样能够避免塔体100浸入水箱200,同时可以保证水箱200既通过水箱200的底部与第一支撑板300的搭接而支撑塔体100,又通过第三支撑板230与第二支撑板120的搭接而支撑塔体100,双重支撑结构能够稳定塔体100与水箱200的连接,避免因废气塔工作时的震动和碰撞而导致塔体100相对水箱200发生位移,进而影响废气塔的工作性能。The height of the first support plate 300 can be greater than or equal to the depth of the water tank 200, which can prevent the tower body 100 from immersing in the water tank 200, and can ensure that the water tank 200 supports the tower body by overlapping the bottom of the water tank 200 and the first support plate 300 100, and the tower body 100 is supported by the overlapping of the third support plate 230 and the second support plate 120. The double support structure can stabilize the connection between the tower body 100 and the water tank 200, and avoid the vibration and collision caused by the waste gas tower when it is working. The displacement of the tower body 100 relative to the water tank 200 affects the working performance of the waste gas tower.
考虑到塔体100与第一支撑板300之间连接的稳定性,在一个实施例中,可以通过焊接的方式将第一支撑板300与塔体100相连;在其他实施例中,第一支撑板300也可以与塔体100侧板采用整板一体制作,第一支撑板300与塔体100之间的连接处一定要保证密封,不能漏风或漏水。Considering the stability of the connection between the tower body 100 and the first support plate 300, in one embodiment, the first support plate 300 can be connected to the tower body 100 by welding; in other embodiments, the first support plate The plate 300 can also be made integrally with the side plate of the tower body 100, and the connection between the first support plate 300 and the tower body 100 must be sealed so as not to leak air or water.
如图2所示,可以在第一支撑板300上设置连通口310,通过连通口310将蓄水腔210和加药腔220中的液体相连通,通过加药腔220添加药剂,并通过连通口310使得蓄水腔210中的水也充满药剂,连通口310的结构能够使工作人员在塔体100外部完成加药。As shown in Figure 2, a communication port 310 can be provided on the first support plate 300, through which the liquid in the water storage chamber 210 and the dosing chamber 220 can be connected, the medicine can be added through the dosing chamber 220, and through the communication The port 310 makes the water in the water storage chamber 210 also be filled with medicament, and the structure of the communication port 310 enables the staff to finish adding the medicament outside the tower body 100 .
可以将连通口310设置在第一支撑板300的底部,通过连通口310使得水箱200内液面高度与第一支撑板300围设的区域内液面高度相同,水箱200中的水可以一直处于提升至塔体100的上部然后通过喷淋回流至水箱200的状态中,由于水箱200中液面高度一般仅为水箱200下沿向下150mm-200mm(液面高度不可能漫至水箱200上沿,否则随时可能从加药腔220处溢出),相关技术中塔体内部的气体可能从网孔处漏出至水箱,再从水箱液面上方,通过加药口溢出,导致废气塔漏风,而本申请提供的废气塔,通过第一支撑板300的结构,能够保证从塔体100内漏出的无论是液流还是气流,均只在第一支撑板300围设的区域内,并通过将连通口310设置在第一支撑板300的底部,使得塔体100内的气流或液流不会从第一支撑板300与塔体100的连接处漏出。气流从塔体100内部通过,如从网孔110中漏出,第一支撑板300围设区域内的液体则会形成液封,阻止气流逸出,同时,液封也可以阻止外部气流从加药腔220中逸入。The communication port 310 can be arranged at the bottom of the first support plate 300, through the communication port 310, the liquid level in the water tank 200 is the same as the liquid level in the area surrounded by the first support plate 300, and the water in the water tank 200 can be kept at Lift to the upper part of the tower body 100 and then flow back to the water tank 200 by spraying, because the liquid level in the water tank 200 is generally only 150mm-200mm downward from the lower edge of the water tank 200 (the liquid level cannot reach the upper edge of the water tank 200 , otherwise it may overflow from the dosing chamber 220 at any time), the gas inside the tower body may leak from the mesh to the water tank in the related art, and then overflow from the liquid surface of the water tank through the dosing port, causing the waste gas tower to leak air, and this The exhaust gas tower provided by the application, through the structure of the first support plate 300, can ensure that whether it is liquid flow or air flow leaking from the tower body 100, it is only in the area surrounded by the first support plate 300, and passes through the connecting port. 310 is arranged at the bottom of the first support plate 300 so that the gas or liquid flow in the tower body 100 will not leak from the connection between the first support plate 300 and the tower body 100 . The air flow passes through the inside of the tower body 100. If it leaks from the mesh 110, the liquid in the area surrounded by the first support plate 300 will form a liquid seal to prevent the air flow from escaping. At the same time, the liquid seal can also prevent the external air flow from adding medicine. into cavity 220.
连通口310可以设置多个,继续参见图2,在一个实施例中,可以在第一支撑板300的底部间隔设置多个连通口310,能够加快液体流动,保证蓄水腔210和加药腔220内的液面高度保持在同一水平面。 Multiple communication ports 310 can be provided. Continue to refer to FIG. 2 . In one embodiment, multiple communication ports 310 can be arranged at intervals on the bottom of the first support plate 300, which can speed up the flow of liquid and ensure that the water storage chamber 210 and the dosing chamber The liquid level in 220 remains at the same level.
可选地,考虑到操作习惯,可以将第一支撑板300安装在水箱200的一侧, 此时加药腔220处于水箱200的一侧;也可以将第一支撑板300安装在水箱200内,不与水箱200的侧壁接触,此时加药腔220处于蓄水腔210的两侧或四周。Optionally, considering the operating habits, the first support plate 300 can be installed on one side of the water tank 200, at this time, the dosing chamber 220 is on one side of the water tank 200; the first support plate 300 can also be installed in the water tank 200 , not in contact with the side wall of the water tank 200 , at this time the dosing chamber 220 is located on both sides or surroundings of the water storage chamber 210 .
加药腔220除了具有加药的作用外,工作人员还会通过加药腔220来观察水箱200中的水质,当水质被污染到一定程度时,需要及时给水箱200换水,以保证废气塔对废气的净化性能,因此,可以在加药腔220的上方设置一个盖板240,避免外部环境中的杂质进入加药腔220中,影响水箱200中的水质。In addition to the function of adding medicine to the dosing chamber 220, the staff will also observe the water quality in the water tank 200 through the dosing chamber 220. When the water quality is polluted to a certain extent, it is necessary to change the water in the water tank 200 in time to ensure that the waste gas tower For exhaust gas purification performance, therefore, a cover plate 240 can be provided above the dosing chamber 220 to prevent impurities in the external environment from entering the dosing chamber 220 and affecting the water quality in the water tank 200 .
在一个实施例中,盖板240与加药腔220可以采用转动连接的方式进行连接,方便工作人员开、关盖板240。In one embodiment, the cover plate 240 and the medicine feeding chamber 220 may be connected in a rotational manner, which is convenient for the staff to open and close the cover plate 240 .
盖板240可以通过铰链和加药腔220相连,并且,盖板240可以绕铰链的铰轴相对加药腔220转动,铰轴的两端还可以设置挡圈,挡圈可以防止铰轴出现松动、滑落的情况发生,通过铰链连接盖板240和加药腔220,便于开、关盖板240。The cover plate 240 can be connected to the dosing chamber 220 through a hinge, and the cover plate 240 can rotate relative to the dosing chamber 220 around the hinge shaft of the hinge, and retaining rings can also be provided at both ends of the hinge shaft, and the retaining rings can prevent the hinge shaft from loosening , slipping occurs, the cover 240 and the dosing chamber 220 are connected by hinges, which is convenient for opening and closing the cover 240 .
可以在盖板240上设置一个把手,工作人员通过把手来开、关盖板240。在一个实施例中,把手与盖板240可以通过焊接的方式固定连接;在其他实施例中,盖板240还可以通过螺栓连接的方式与把手相连。A handle can be arranged on the cover plate 240 , and the staff can open and close the cover plate 240 through the handle. In one embodiment, the handle and the cover plate 240 can be fixedly connected by welding; in other embodiments, the cover plate 240 can also be connected with the handle by bolt connection.
可以在水箱200上开设一个排水口,排水口可以连通管道,当水箱200中的水质较差,不足以用于净化有害气体时,通过排水口将水箱200中的水集中排走。A drain can be set on the water tank 200, and the drain can be connected to the pipeline. When the water quality in the water tank 200 is poor enough to purify harmful gases, the water in the water tank 200 can be drained away through the drain.
示例性的,塔体100分设多段,多段塔体100共用一个水箱200;或,塔体100分设多段,多段塔体100共用多个水箱200,相邻两段塔体100的连接处设置在水箱200的上方。示例性的,塔体100分设多段,每段塔体100设有一个水箱200,相邻两段塔体100的连接处设置在水箱200(该段塔体正下方的水箱200)的上方。Exemplarily, the tower body 100 is divided into multiple sections, and the multi-section tower body 100 shares a water tank 200; or, the tower body 100 is divided into multiple sections, and the multi-section tower body 100 shares a plurality of water tanks 200, and the connection between two adjacent sections of the tower body 100 is arranged in the water tank Above 200. Exemplarily, the tower body 100 is divided into multiple sections, each section of the tower body 100 is provided with a water tank 200, and the junction of two adjacent sections of the tower body 100 is set above the water tank 200 (the water tank 200 directly below the section of the tower body).
如图4所示,示出了塔体段数与水箱个数之间的关系,其中塔体段数可为M段,水箱个数可为N个。当塔体段数为M段,水箱个数可为N=1,即塔体100共用一个水箱200。还可以是当塔体段数为M段时,2≤N<M,此时当一段塔体100下方无水箱时,该段塔体100内部底板上不开网孔110,该段塔体100内的液体通过坡度流到相邻塔体100,再通过相邻塔体100底板上的网孔110,流入相邻塔体100下方的水箱200。还可以是当塔体段数为M段时,水箱个数N=M,即一段塔体100对应一个水箱200。图4示例性的说明了塔体段数与水箱个数的关系,塔体100与水箱200的设置还可以为其他方式,本申请不作限制。上述实施例需要保证,分段塔体的连接处,必须处于水箱的上方,这样可以确保,即使连接处漏水,也只会漏入水箱内,而不会漏到水箱外。As shown in Figure 4, the relationship between the number of tower body sections and the number of water tanks is shown, wherein the number of tower body sections can be M sections, and the number of water tanks can be N. When the number of tower body sections is M, the number of water tanks can be N=1, that is, the tower body 100 shares one water tank 200 . It can also be that when the number of tower body sections is M sections, 2≤N<M, at this time, when there is no water tank under the tower body 100 of a section, the mesh 110 is not opened on the inner bottom plate of the tower body 100 of this section, and the inside of the tower body 100 of this section The liquid flows to the adjacent tower body 100 through the slope, and then flows into the water tank 200 below the adjacent tower body 100 through the mesh 110 on the bottom plate of the adjacent tower body 100 . It can also be that when the number of tower body sections is M sections, the number of water tanks is N=M, that is, one section of tower body 100 corresponds to one water tank 200 . Fig. 4 exemplarily illustrates the relationship between the number of tower body sections and the number of water tanks. The tower body 100 and the water tank 200 can also be arranged in other ways, which are not limited in this application. The above embodiment needs to ensure that the connection of the segmented tower body must be above the water tank, so that it can be ensured that even if the connection leaks, it will only leak into the water tank and not outside the water tank.
废气塔由多段塔体100组成,在一个实施例中,所有塔体100共用一个水箱200,水箱200覆盖所有塔体100的连接处,避免废气塔漏风和漏水,能够保证多段塔体100之间可分离;在另一个实施例中,多段塔体100可以共用多个水箱200,示例性地,多段塔体100可以共用两个水箱200,或多段塔体100可以共用三个水箱200等,同时要保证塔体100与塔体100的连接处置于水箱200的上方,能够避免废气塔中的液体从塔体100与塔体100的连接处漏出到外部环境中;在其他实施例中,每段塔体100单独设置一个水箱200,但是设置的水箱200的长度要保证塔体100与塔体100的连接处置于水箱200的上方,避免废气塔中的液体从塔体100与塔体100的连接处漏出到外部环境中。本申请通过在塔体100的底部沿竖直方向围设第一支撑板300,并将第一支撑板300支撑搭接在水箱200内,能够实现塔体100与水箱200可分离,便于运输,避免塔体100失去分段的意义;通过第一支撑板300将水箱200分成蓄水腔210和加药腔220,可以简化水箱200的加工工序,提高生产效率,降低成本;同时,第一支撑板300围设区域内的液封使得废气塔中的气流和液流不会从第一支撑板300和塔体100的连接处漏出,避免废气塔漏风和漏水,同时外部的气体也不会从加药腔220进入塔体100。The waste gas tower is composed of multi-section tower bodies 100. In one embodiment, all tower bodies 100 share a water tank 200, and the water tank 200 covers the joints of all tower bodies 100 to avoid air and water leakage in the waste gas tower and ensure that the multi-section tower bodies 100 In another embodiment, the multi-section tower body 100 can share multiple water tanks 200. Exemplarily, the multi-section tower body 100 can share two water tanks 200, or the multi-section tower body 100 can share three water tanks 200, etc., while To ensure that the connection between the tower body 100 and the tower body 100 is placed above the water tank 200, the liquid in the waste gas tower can be prevented from leaking into the external environment from the connection between the tower body 100 and the tower body 100; in other embodiments, each section The tower body 100 is provided with a water tank 200 alone, but the length of the water tank 200 is to ensure that the connection between the tower body 100 and the tower body 100 is placed above the water tank 200, so as to avoid the connection of the liquid in the waste gas tower from the tower body 100 to the tower body 100 leakage into the external environment. In this application, the tower body 100 can be separated from the water tank 200 by vertically enclosing the first support plate 300 at the bottom of the tower body 100 and overlapping the first support plate 300 in the water tank 200, which is convenient for transportation. To prevent the tower body 100 from losing the meaning of segmentation; divide the water tank 200 into the water storage chamber 210 and the dosing chamber 220 through the first support plate 300, which can simplify the processing procedure of the water tank 200, improve production efficiency, and reduce costs; at the same time, the first support The liquid seal in the area surrounded by the plate 300 prevents the gas flow and liquid flow in the exhaust gas tower from leaking from the connection between the first support plate 300 and the tower body 100, avoiding air and water leakage from the exhaust gas tower, and at the same time, the external gas will not leak from the exhaust gas tower. The dosing chamber 220 enters the tower body 100 .
对于塔体分段制作的卧式废气塔,相关技术中将水箱与废气塔的塔体一体制作,当分段制作的塔体共用一个水箱时,水箱不能分段,进而使得塔体无法分段制作、运输和安装,上述废气塔通过在塔体底部沿竖直方向上围设第一支撑板,并将第一支撑板搭接在水箱上,可以随时对废气塔和水箱进行拆分以及装配,便于运输。For the horizontal waste gas tower manufactured in sections, the water tank is integrated with the tower body of the waste gas tower in the related art. When the tower body made in sections shares a water tank, the water tank cannot be segmented, so that the tower body cannot be segmented. Production, transportation and installation, the waste gas tower above can be disassembled and assembled at any time by enclosing the first support plate in the vertical direction at the bottom of the tower body and lapping the first support plate on the water tank , easy to transport.
当每段塔体单独设置水箱时,水箱往往覆盖塔体的连接处,如将水箱覆盖塔体连接处且与塔体一体制作,则这种结构也使得塔体连接在一起无法分段,不利于运输。上述废气塔通过在塔体底部沿竖直方向上围设第一支撑板,并将第一支撑板搭接在水箱上,并通过设置水箱的长度能够使塔体的连接处在水箱的上方,既可以避免塔体的连接处漏水,还可以保证分段制作的塔体可以随时拆分和装配。When each section of the tower body is provided with a separate water tank, the water tank often covers the joint of the tower body. If the water tank is covered with the tower body joint and made integrally with the tower body, this structure also makes the tower body connected together and cannot be segmented. Good for transportation. The above-mentioned waste gas tower encloses the first support plate in the vertical direction at the bottom of the tower body, and overlaps the first support plate on the water tank, and by setting the length of the water tank, the connection of the tower body can be made above the water tank. It can not only avoid water leakage at the joint of the tower body, but also ensure that the tower body made in sections can be disassembled and assembled at any time.

Claims (10)

  1. 一种废气塔,包括塔体(100)和水箱(200),其中,An exhaust gas tower, comprising a tower body (100) and a water tank (200), wherein,
    所述塔体(100)的底部沿竖直方向围设有第一支撑板(300),所述塔体(100)通过所述第一支撑板(300)支撑搭接于所述水箱(200),所述第一支撑板(300)将所述水箱(200)分隔成蓄水腔(210)和加药腔(220),且所述第一支撑板(300)上设有连通所述蓄水腔(210)和所述加药腔(220)的连通口(310)。The bottom of the tower body (100) is surrounded by a first support plate (300) in the vertical direction, and the tower body (100) is supported and overlapped with the water tank (200) by the first support plate (300). ), the first support plate (300) divides the water tank (200) into a water storage chamber (210) and a dosing chamber (220), and the first support plate (300) is provided with the A communication port (310) between the water storage chamber (210) and the medicine feeding chamber (220).
  2. 根据权利要求1所述的废气塔,其中,所述塔体(100)的底部边缘设有第二支撑板,所述水箱(200)的边缘设有第三支撑板,所述第二支撑板搭接于所述第三支撑板上。The exhaust gas tower according to claim 1, wherein the bottom edge of the tower body (100) is provided with a second support plate, the edge of the water tank (200) is provided with a third support plate, and the second support plate lapped on the third support plate.
  3. 根据权利要求2所述的废气塔,其中,所述第二支撑板和所述第三支撑板沿水平方向设置。The exhaust gas tower according to claim 2, wherein the second support plate and the third support plate are arranged along a horizontal direction.
  4. 根据权利要求1所述的废气塔,其中,所述连通口(310)设置在所述第一支撑板(300)的底部。The exhaust gas tower according to claim 1, wherein the communication port (310) is arranged at the bottom of the first support plate (300).
  5. 根据权利要求4所述的废气塔,其中,所述连通口(310)设有多个,多个连通口(310)间隔设置。The exhaust gas tower according to claim 4, wherein there are multiple communication ports (310), and the plurality of communication ports (310) are arranged at intervals.
  6. 根据权利要求1所述的废气塔,其中,所述塔体(100)上设有连通所述蓄水腔(210)与所述塔体(100)的网孔(110)。The exhaust gas tower according to claim 1, wherein, the tower body (100) is provided with a mesh (110) connecting the water storage chamber (210) and the tower body (100).
  7. 根据权利要求1所述的废气塔,其中,所述第一支撑板(300)的高度大于或等于所述水箱(200)的深度。The exhaust gas tower according to claim 1, wherein the height of the first support plate (300) is greater than or equal to the depth of the water tank (200).
  8. 根据权利要求1所述的废气塔,其中,所述加药腔(220)上方设有盖板。The exhaust gas tower according to claim 1, wherein a cover plate is provided above the dosing chamber (220).
  9. 根据权利要求1-8中任一项所述的废气塔,其中,所述塔体(100)分设多段,多段塔体(100)共用一个水箱(200);The exhaust gas tower according to any one of claims 1-8, wherein the tower body (100) is divided into multiple sections, and the multi-section tower body (100) shares a water tank (200);
    或,所述塔体(100)分设多段,多段塔体(100)共使用多个水箱(200),相邻两段塔体(100)的连接处设置在所述水箱(200)的上方。Or, the tower body (100) is divided into multiple sections, and the multi-section tower body (100) uses a plurality of water tanks (200) in total, and the connection between two adjacent sections of the tower body (100) is arranged above the water tank (200).
  10. 根据权利要求1-8中任一项所述的废气塔,其中,所述塔体(100)分设多段,每段塔体(100)设有一个水箱(200),相邻两段塔体(100)的连接处设置在所述水箱(200)的上方。The exhaust gas tower according to any one of claims 1-8, wherein the tower body (100) is divided into multiple sections, each section of the tower body (100) is provided with a water tank (200), and two adjacent sections of the tower body ( 100) is arranged above the water tank (200).
PCT/CN2021/129952 2021-11-11 2021-11-11 Waste gas tower WO2023082119A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
PCT/CN2021/129952 WO2023082119A1 (en) 2021-11-11 2021-11-11 Waste gas tower
CN202180004063.2A CN114206475A (en) 2021-11-11 2021-11-11 Waste gas tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2021/129952 WO2023082119A1 (en) 2021-11-11 2021-11-11 Waste gas tower

Publications (1)

Publication Number Publication Date
WO2023082119A1 true WO2023082119A1 (en) 2023-05-19

Family

ID=80659084

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/129952 WO2023082119A1 (en) 2021-11-11 2021-11-11 Waste gas tower

Country Status (2)

Country Link
CN (1) CN114206475A (en)
WO (1) WO2023082119A1 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB365657A (en) * 1930-10-24 1932-01-25 James Arthur Reavell Improvements in bubble towers and the like fractionating columns
US20130055937A1 (en) * 2010-05-18 2013-03-07 Babcock-Hitachi Kabushiki Kaisha Flue gas desulfurization device, combustion system and combustion method
CN106178905A (en) * 2016-09-12 2016-12-07 山东泰北环保设备股份有限公司 There is the desulfurizing tower held one's breath with aerator
CN109173608A (en) * 2018-09-27 2019-01-11 无锡星亿智能环保装备股份有限公司 A kind of Horizental showering type absorption purification tower
CN208553653U (en) * 2019-01-23 2019-03-01 烟台盛泽环保科技有限公司 A kind of Horizental showering tower for pickling exhaust-gas treatment
CN209138018U (en) * 2018-09-17 2019-07-23 晋州市吉象新能源有限公司 A kind of furfural production primary distillation tower tower bottom waste water automatic draining device
CN214552458U (en) * 2020-10-30 2021-11-02 新昌县新宏力铝业有限公司 Waste gas treatment spray tower

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205127659U (en) * 2015-10-20 2016-04-06 福建省三净环保科技有限公司 Purifying column is washed to components of a whole that can function independently water tank formula multilayer
CN107051067A (en) * 2017-06-12 2017-08-18 广州薪光合环保技术有限公司 Integrated waste gas treatment equipment
CN209475978U (en) * 2018-12-27 2019-10-11 上海超惠通风环保设备有限公司 Bilayer cleans deacidification washing tower (for removing CO2)
CN212417483U (en) * 2020-04-20 2021-01-29 苏州绿通环保科技有限公司 Tower body and water tank split type washing tower device
CN214075889U (en) * 2020-11-10 2021-08-31 太原市润民环保节能有限公司 Biochemical double-acting deodorization equipment

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB365657A (en) * 1930-10-24 1932-01-25 James Arthur Reavell Improvements in bubble towers and the like fractionating columns
US20130055937A1 (en) * 2010-05-18 2013-03-07 Babcock-Hitachi Kabushiki Kaisha Flue gas desulfurization device, combustion system and combustion method
CN106178905A (en) * 2016-09-12 2016-12-07 山东泰北环保设备股份有限公司 There is the desulfurizing tower held one's breath with aerator
CN209138018U (en) * 2018-09-17 2019-07-23 晋州市吉象新能源有限公司 A kind of furfural production primary distillation tower tower bottom waste water automatic draining device
CN109173608A (en) * 2018-09-27 2019-01-11 无锡星亿智能环保装备股份有限公司 A kind of Horizental showering type absorption purification tower
CN208553653U (en) * 2019-01-23 2019-03-01 烟台盛泽环保科技有限公司 A kind of Horizental showering tower for pickling exhaust-gas treatment
CN214552458U (en) * 2020-10-30 2021-11-02 新昌县新宏力铝业有限公司 Waste gas treatment spray tower

Also Published As

Publication number Publication date
CN114206475A (en) 2022-03-18

Similar Documents

Publication Publication Date Title
CN208066110U (en) A kind of activated carbon adsorber
CN207755921U (en) A kind of infant industry exhaust-gas treatment tank
WO2023082119A1 (en) Waste gas tower
CN212091664U (en) Malodorous gas treatment device
CN215654839U (en) Rotary gas distribution device for low-concentration gas and catalytic oxidation combustion device
CN209797534U (en) tower tray for ammonia still
CN107875813A (en) A kind of gas absorbing device applied to chemical laboratory
CN210114973U (en) Waste gas treatment device for environmental protection equipment
CN211677152U (en) Spray tower convenient to maintenance
CN213433730U (en) Atomizing interception waste gas treatment device
CN212355109U (en) Oil field oil tank safety device
KR20120004201A (en) Drain oil tank for ship
CN112058029A (en) Detachable waste gas treatment device for chemical production
CN206746265U (en) A kind of steam purifier for waste gas purification
CN218901289U (en) Waste gas purifying treatment device
CN213965910U (en) Aluminum trichloride packing tail gas absorption tower
CN215311154U (en) Waste gas purification&#39;s spray column
CN219815792U (en) Treatment device for chemical industry waste gas
CN214715595U (en) Industrial waste gas treatment equipment
CN217367815U (en) Spray tower for industrial VOC waste gas treatment
CN219128834U (en) Acid waste gas treatment device
CN212687863U (en) Deodorizing device for sludge treatment
CN220294667U (en) Liquid hazardous chemical leakage inhibition volatilization treatment device
CN212426151U (en) Self-flowing type control groove body sealing device
JP2018079834A (en) Liquid leakage prevention device for set tank of vessel

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21963574

Country of ref document: EP

Kind code of ref document: A1