WO2023029782A1 - Anti-seepage embankment and construction process - Google Patents

Anti-seepage embankment and construction process Download PDF

Info

Publication number
WO2023029782A1
WO2023029782A1 PCT/CN2022/106400 CN2022106400W WO2023029782A1 WO 2023029782 A1 WO2023029782 A1 WO 2023029782A1 CN 2022106400 W CN2022106400 W CN 2022106400W WO 2023029782 A1 WO2023029782 A1 WO 2023029782A1
Authority
WO
WIPO (PCT)
Prior art keywords
seepage
layer
seepage body
construction
filling layer
Prior art date
Application number
PCT/CN2022/106400
Other languages
French (fr)
Chinese (zh)
Inventor
潘伟
陈富
张乃受
武洋
Original Assignee
中交第一航务工程局有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中交第一航务工程局有限公司 filed Critical 中交第一航务工程局有限公司
Priority to PCT/CN2022/106400 priority Critical patent/WO2023029782A1/en
Publication of WO2023029782A1 publication Critical patent/WO2023029782A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/06Methods or arrangements for protecting foundations from destructive influences of moisture, frost or vibration
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil

Definitions

  • the application belongs to the field of building construction, and relates to an anti-seepage embankment and a construction process.
  • the main difference is that firstly, a certain thickness of sand cushion must be filled as the water outlet backfill to provide a working surface for the subsequent inserting operations.
  • the mechanical self-weight of the inserting plate of the slab is relatively large, and the load of the outlet backfill and the mechanical load of the inserting plate are superimposed on the soft clay foundation.
  • the shear strength of the soft clay foundation has not been improved during the construction of the insert plate, and the possibility of instability of the soft clay foundation is extremely high under the joint action of the backfill load of the effluent and the mechanical load of the insert plate.
  • the application provides an anti-seepage embankment and construction technology.
  • the anti-seepage embankment has good flexibility and anti-seepage performance, and can adapt to subsidence foundation.
  • the first aspect of the present application provides an anti-seepage embankment, which includes: a sand cushion and a filling layer, wherein,
  • the sand cushion layer is located on the soft soil layer; the plastic drainage board extends from the soft soil layer to the sand cushion layer to drain the soft soil layer;
  • the filling layer is located on the sand cushion, which is provided with a first anti-seepage body at the bottom and a second anti-seepage body at the top; the first anti-seepage body is a rigid or semi-rigid anti-seepage body, and the second anti-seepage body The second anti-seepage body connected with the first anti-seepage body is a flexible anti-seepage body.
  • the first anti-seepage body is a semi-rigid anti-seepage body; it can be hardened by cement slurry.
  • the anti-seepage embankment further includes a third anti-seepage body formed later than the first anti-seepage body, extending from the soft soil layer to the filling layer and connecting with the first anti-seepage body.
  • the third anti-seepage body is a semi-rigid anti-seepage body; it can be hardened by cement slurry.
  • the filling layer is filled with sand and gravel or clay; the first anti-seepage body is formed by hardening cement slurry in the filling layer without contacting the sand cushion; the second anti-seepage The body is at least one layer of anti-seepage geotextile, and the joint of the second anti-seepage body is located in the first anti-seepage body; the second anti-seepage body is bent.
  • the soft soil layer and the sand cushion layer are located below the water surface, the filling layer and the first anti-seepage body located in the filling layer both extend from below the water surface to the water surface, and the second anti-seepage body is located on the water surface.
  • the soft soil layer is provided with a geotextile layer
  • the geotextile layer is provided with a geogrid
  • the sand cushion is laid on the geogrid.
  • the second aspect of the present application provides a kind of anti-seepage embankment, which comprises:
  • Sand cushion and filling layer wherein, the sand cushion is located on the soft soil layer; the plastic drainage board extends from the soft soil layer to the sand cushion to drain the soft soil layer; the filling layer is located on the sand cushion On the layer, the first anti-seepage body is arranged in it;
  • It also includes a third anti-seepage body formed later than the first anti-seepage body, extending from the soft soil layer to the filling layer and connecting with the first anti-seepage body.
  • the third anti-seepage body is a semi-rigid anti-seepage body; it can be hardened by cement slurry.
  • the first anti-seepage body at the lower part and the second anti-seepage body at the upper part are provided in the filling layer;
  • the first anti-seepage body is a rigid or semi-rigid anti-seepage body, and the first anti-seepage body
  • the second anti-seepage body connected with the seepage body is a flexible anti-seepage body.
  • the third aspect of the present application provides a construction technique for an anti-seepage embankment, which includes:
  • Sand cushion construction lay a sand cushion on the surface of the soft soil layer
  • Construction of plastic drainage boards Drive multiple plastic drainage boards into the soft soil layer, so that one end of each plastic drainage board is located on the sand cushion to drain water;
  • the construction of the filling layer and its anti-seepage body fill the first filling layer on the sand cushion layer; build a rigid or semi-rigid first anti-seepage body in the first filling layer; place the flexible second anti-seepage body One end of the anti-seepage body overlaps with the first anti-seepage body; on the first filling layer, a plurality of sub-filling layers with slopes are sequentially filled on both sides of the second anti-seepage body, and the second anti-seepage body is along the The slope is laid.
  • the construction process of the anti-seepage embankment also includes the construction of the third anti-seepage body: after the settlement of the soft soil layer is stable, the third anti-seepage body is constructed in the sand cushion layer, extending from the soft soil layer to the first anti-seepage body. In the filling layer, it is in contact with the first anti-seepage body.
  • the construction process of the anti-seepage embankment includes:
  • Sand cushion construction Lay geotextiles, geogrids and sand cushions in sequence on the surface of the soft soil layer;
  • Construction of plastic drainage boards Drive multiple plastic drainage boards into the soft soil layer, so that one end of each plastic drainage board is located on the sand cushion to drain water;
  • Construction of the filling layer and its anti-seepage body Backfill sand and gravel or clay on the sand cushion layer to form the first filling layer; spray cement slurry into the first filling layer, and form the first anti-seepage body after the cement slurry hardens; Embed one end of the second anti-seepage body into the first anti-seepage body to form an overlap before the cement slurry hardens; on the first filling layer, fill sand and gravel or clay in sequence on both sides of the second anti-seepage body, A plurality of sub-filling layers with a slope are formed, and the second anti-seepage body is laid along the slope in a Z-shaped direction; the two sub-filling layers of the uppermost layer are approximately flush, and further construction can be carried out on it to form a road surface; The second anti-seepage body adopts one or more layers of anti-seepage geotextiles.
  • the construction process of the anti-seepage embankment includes:
  • Sand cushion construction Lay geotextiles and geogrids sequentially on the surface of the soft soil layer under the water surface; lay sand cushions on the geogrid;
  • Construction of plastic drainage boards use ships to insert boards on the water, drive multiple plastic drainage boards into the soft soil layer, and make one end of each plastic drainage board located in the sand cushion;
  • Construction of the filling layer and its anti-seepage body Backfill sand and gravel or clay out of the water surface on the sand cushion layer to form the first filling layer; spray cement slurry into the first filling layer, and form the first anti-seepage layer after the cement slurry hardens.
  • the second anti-seepage body adopts one or more layers of anti-seepage geotextiles; on the first filling layer, sand and gravel or clay are alternately filled on both sides of the second anti-seepage body to form A plurality of sub-filling layers with a slope; the second anti-seepage body is laid along the slope, in a bent shape; the uppermost sub-filling layer is roughly flush, and can be further constructed to form a road surface;
  • Construction of the third anti-seepage body After the construction of the filling layer is completed and the settlement of the soft soil layer is stable, cement slurry is sprayed into the sand cushion layer, and the third anti-seepage body is formed after the cement slurry hardens; the lower part of the third anti-seepage body is located in the soft soil layer. In the soil layer, the third anti-seepage body is also in contact with the first anti-seepage body;
  • Pavement construction Carry out pavement and auxiliary structure construction on the filling layer to form an embankment.
  • the fourth aspect of the present application provides an anti-seepage embankment, which is obtained by using the construction process of the anti-seepage embankment described in any of the above technical solutions.
  • the fifth aspect of the present application provides an application of an anti-seepage embankment, which is applied to a subsidence foundation.
  • the anti-seepage embankment provided by at least one embodiment of the present application adopts a flexible embankment structure, and adopts a water-sliding board technology to prevent foundation instability when backfilling sand and gravel materials backfill out of the water surface.
  • the problem of the construction and subsequent operation of seawalls with flexible structures or rigid structures in the prior art is solved.
  • the anti-seepage embankment provided by at least one embodiment of the present application adopts the combination of cement slurry and anti-seepage geotextile, which is convenient for construction and has good anti-seepage reliability.
  • the anti-seepage geotextile is inside the embankment and has good aging resistance. Compared with rigid concrete walls, the foundation has strong adaptability to deformation, will not fall and crack, etc., and has low construction and maintenance costs.
  • Fig. 1 is a schematic diagram of sand cushion construction of an embodiment
  • Fig. 2 is a construction schematic diagram of a plastic drainage board in an embodiment
  • Fig. 3 is a construction schematic diagram of the first filling layer of an embodiment
  • Fig. 4 is a construction schematic diagram of the first anti-seepage body of an embodiment
  • 5A-5D are construction schematic diagrams of a filling layer and a second anti-seepage body in an embodiment
  • Fig. 6 is a construction schematic diagram of a third anti-seepage body in an embodiment
  • Fig. 7 is a schematic diagram of an embodiment of an anti-seepage embankment
  • first and second are used for description purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly indicating the quantity of indicated technical features. Thus, a feature defined as “first” and “second” may explicitly or implicitly include one or more of these features.
  • connection and “connected” should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated Ground connection; it can be directly connected, or indirectly connected through an intermediary, and can be internally connected between two components.
  • connection should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated Ground connection; it can be directly connected, or indirectly connected through an intermediary, and can be internally connected between two components.
  • the soft soil layer in the present embodiment mainly refers to the water-containing soil layer prone to subsidence, such as soft clay foundation etc.;
  • the embankment can be a river embankment, a lake embankment, a sea embankment, etc.
  • the first embodiment of the present application provides an anti-seepage embankment, which can be adapted to subsidence foundations, including:
  • a geotextile layer 1 and a geogrid wherein the geotextile layer 1 is located on the soft soil layer 100 , and the geogrid is located on the geotextile layer 1 .
  • the geotextile layer 1 mainly plays an isolation role, which can prevent the soft soil layer 100 from polluting the sand cushion layer 2 .
  • the geogrid has a relatively high strength, which can share the load, make the settlement uniform, and avoid the rupture of the geotextile.
  • the sand cushion layer 2 is located on the geotextile layer 1 and the geogrid, 200 below the water surface; the thickness can be 800-1200mm, such as 900mm, 1000mm, 1100mm, etc.
  • the filling layer 3 is located on the sand cushion layer 2; road surfaces such as roads can be laid on the top of the filling layer 3.
  • the filling layer 3 can be filled with sand and gravel or clay, and a first anti-seepage body 41 and a second anti-seepage body 42 are provided therein.
  • the first anti-seepage body 41 is a rigid or semi-rigid anti-seepage body; said rigidity means that the strength is relatively high, for example, the first anti-seepage body is a concrete structure, etc.; said semi-rigidity means that the working characteristics are between rigidity and
  • flexibility such as cement-soil mixing piles or high-pressure rotary grouting piles, etc., are conventional terms in the field; for example, it can be formed by injecting cement slurry into the filling layer 3 and stirring and hardening sand and gravel materials or clay; extending from the water surface 200 to On the water surface 200; connected with the second anti-seepage body 42.
  • the second anti-seepage body 42 is a flexible anti-seepage body (deformable), located on the water surface 200 .
  • the second anti-seepage body 42 is formed by construction of at least one layer of anti-seepage geotextile, for example, two cloths and one membrane can be used, and its joint is located in the first anti-seepage body 41, and can be connected with the first anti-seepage body 41. Form a seamless connection and increase the anti-seepage performance.
  • the second anti-seepage body 42 is in a bent shape in the filling layer 3 , such as the zigzag shape shown in FIG. 7 , and is arranged obliquely along with the stepwise filling process of the filling layer 3 .
  • This embodiment adopts semi-rigid/rigid and flexible anti-seepage body, which can undergo adaptive deformation without cracking, so the adaptability is better. If all are rigid anti-seepage body up and down in the filling layer 3, its rigidity is too high, can make anti-seepage body produce crack and leak when the ground subsidence takes place probably.
  • the bending direction of the second anti-seepage body 42 on the one hand, conforms to the filling direction of the filling layer 3 to facilitate filling, and on the other hand, it is more adaptable to the deformability of the embankment.
  • the anti-seepage embankment also has a third anti-seepage body 43 constructed later than the first anti-seepage body 41 and the second anti-seepage body 42 .
  • it is preferably a semi-rigid anti-seepage body, for example, it can be formed by injecting cement slurry and stirring and hardening.
  • the third anti-seepage body 43 extends from the soft soil layer 100 to the filling layer 3, and connects with the first anti-seepage body 41; it cuts off the function of the horizontal permeable channel of the sand cushion layer 2, thereby closing the anti-seepage embankment under the water surface 200 Divided into two parts to prevent river, sea or lake water entering from one side from entering the other side. For example, in Fig. 7, if sea water hits from the right side, it can be prevented from entering the left side due to the existence of each anti-seepage body.
  • a plurality of plastic drainage boards 5 are drilled in the soft soil layer 100, which extend from the soft soil layer 100 to the sand cushion layer 2, so that the soft soil layer 100 can be pre-treated. Pressure drain. Further, the bottom of the first anti-seepage body 41 does not reach the sand cushion layer 2, so that the corresponding plastic drainage board 5 at the bottom will not be damaged; the third anti-seepage body 43 is formed after the drainage of the plastic drainage board 5 is completed .
  • Such a method can provide sufficient drainage space and drainage time for the plastic drainage boards 5, so that the water discharged from each plastic drainage board 5 may be discharged to the left and right directions, so that the drainage consolidation of the soft soil layer 100 is more sufficient and effective. .
  • the second embodiment of the present application provides a construction process for an anti-seepage embankment, comprising the following steps:
  • a geotextile 1 and a geogrid are sequentially laid on the surface of the soft soil layer 100 under the water surface 200 .
  • a medium-coarse sand cushion 2 with a thickness of about 1000mm is laid on the geogrid.
  • the medium-coarse refers to sand with a fineness modulus of 1.6-3.7, and the sand cushion 2 mainly provides drainage channels for the subsequent drainage of the plastic drainage board 5 .
  • the operation of inserting plastic drainage boards above water can be referred to as water boards for short.
  • Use a special ship to insert the board on the water drive the plastic drainage board 5 into the soft soil layer 100, and make one end of each plastic drainage board 5 be located in the sand cushion 2.
  • the plastic drainage board 5 mainly forms a drainage channel in the soft soil layer 100 , and under the ballast action of the subsequent filling layer 3 , the water in the soft soil layer 100 is discharged to the sand cushion 2 along the plastic drainage board 5 .
  • Water flaps are relatively mature construction operations, and are widely used in the construction of riprap breakwaters in muddy ports such as Tianjin Port, Huanghua Port, and Lianyungang Port in China.
  • CCCC has a complete set of laying and plastic drainage boards for laying special ships on water.
  • the plastic drainage board 5 needs to be driven into the bearing layer under the soft soil layer 100 needs to be determined according to the reinforcement thickness.
  • the setting depth of the plastic drainage board 5 can also be determined according to the thickness of the soft soil layer 100. For example, if the thickness of the soft soil layer is too deep, it may not be necessary to extend to the bearing layer.
  • the first filling layer 31 is formed by backfilling the sand cushion layer 2 with sand and gravel or clay about 0.5 m out of the water surface.
  • cement slurry is sprayed into the first filling layer 31 , and the first anti-seepage body 41 is formed after the cement slurry hardens. Since the first filling layer 31 is generally filled with sand and gravel or clay, conventional high-pressure jet grouting piles or cement mixing piles can be used for construction to form the first anti-seepage body 41 .
  • the first anti-seepage body 41 formed by cement slurry is a semi-rigid anti-seepage body. It is also possible to choose to pour concrete in the first filling layer 31 to form a rigid anti-seepage body.
  • one end of the second anti-seepage body 42 is embedded in the cement slurry of the first anti-seepage body 41 for more than 0.3m, preferably more than 0.5m, to form a complete lap joint with the first anti-seepage body 41. Seep.
  • the second anti-seepage body is a flexible anti-seepage body, for example, one or more layers of anti-seepage geotextiles can be used.
  • the second anti-seepage body 42 On the first filling layer 31, located on the second side (the left side in the figure) of the second anti-seepage body 42, continue to fill sand and gravel or clay to form a layer higher than the second filling layer. 32 and a third filling layer 33 with a second slope.
  • the second anti-seepage body 42 is laid from the first slope to the second slope, as shown in FIG. 5C .
  • the number of filling layers in this application is not limited to the first to fourth filling layers, and the number of filling layers can be increased or decreased according to actual needs.
  • the sand cushion 2 needs to discharge the water discharged from the plastic drainage board 5 to the left and right sides, it is generally not recommended to place the first anti-seepage body 41 in it, so the first anti-seepage body 41 preferably does not touch Sand cushion 2.
  • the plastic drainage board 5 in the middle of the figure where the first anti-seepage body 41 is located will be damaged and unable to drain water; in addition, due to the first anti-seepage Due to the blocking effect of the body 41, the drainage direction of the left and right sides is limited, the left side can only drain to the left, and the right side can only drain to the right, thereby causing the problem of poor drainage.
  • the flexible anti-seepage geotextile is gradually raised along the half-width slope in a "Z" shape.
  • the flexible anti-seepage geotextile is gradually raised along the half-width slope in a "Z" shape.
  • the filling layer 3 the lower part adopts a semi-rigid or rigid structure, and the upper part adopts a flexible structure, which can be adaptively deformed.
  • it plays the role of fixing the second anti-seepage body 42, and on the other hand, it plays the role of adapting to flexible deformation. Therefore, The overall adaptability is better.
  • the third anti-seepage body 43 (being a semi-rigid anti-seepage structure) is formed after the cement slurry is hardened. body).
  • the third anti-seepage body 43 can also be formed by using conventional high-pressure rotary grouting piles.
  • the lower part of the third anti-seepage body 43 is located in the soft soil layer 100 , and the third anti-seepage body 43 is also in contact with the first anti-seepage body 41 ; thus it can be seen as extending from the soft soil layer 100 to the first filling layer 31 .
  • the third anti-seepage body 43, the first anti-seepage body 41 and the second anti-seepage body 42 form an integrally connected anti-seepage body from bottom to top, which divides the embankment from the inside into two parts separated from each other on the left and right to prevent moisture from flowing from one side to the other. Infiltrate the other side.
  • the filling layer 3 and its anti-seepage body (the first anti-seepage body 41 and the second anti-seepage body 42 ) is completed, it is necessary to wait for the soil to settle.
  • the plastic drainage board 5 located in the soft soil layer 100 is in a draining state.
  • the soft soil layer is measured. The amount of deformation is small, indicating that the drainage is basically over.
  • the construction of the third anti-seepage body 43 can be started at this time; therefore, the construction of the third anti-seepage body 43 is later than that of the first anti-seepage body 41 .
  • the upper road pavement and auxiliary structures are constructed on the filling layer 3 to form an embankment.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The present application provides an anti-seepage embankment, comprising a sand cushion layer and a filling layer. The sand cushion layer is located on a soft soil layer. A plastic drainage plate extends into the sand cushion layer from the soft soil layer to drain water for the soft soil layer. The filling layer is located on the sand cushion layer, and a first anti-seepage body located on the lower portion and a second anti-seepage body located on the upper portion are arranged in the filling layer. The first anti-seepage body is a rigid or semi-rigid anti-seepage body, and the second anti-seepage body connected to the first anti-seepage body is a flexible anti-seepage body.

Description

防渗路堤及施工工艺Anti-seepage Embankment and Construction Technology 技术领域technical field
本申请属于建筑施工领域,涉及一种防渗路堤及施工工艺。The application belongs to the field of building construction, and relates to an anti-seepage embankment and a construction process.
背景技术Background technique
随着海平面升高或者沿海城市过量抽取地下水引起地基不断下沉,近年来海水倒灌严重影响生产生活,部分场地已永久性水淹,因此需要在海边修筑挡水海墙。现在技术中有砂石料路堤的柔性结构方案和混凝土海墙的刚性结构方案,但两者均存在建造和后期运行的问题,具体地,As the sea level rises or the excessive pumping of groundwater in coastal cities causes the foundation to sink continuously, seawater intrusion has seriously affected production and life in recent years, and some sites have been permanently flooded, so it is necessary to build water-retaining sea walls near the sea. Currently, there are flexible structural schemes for sand and gravel embankments and rigid structural schemes for concrete sea walls, but both of them have problems in construction and later operation. Specifically,
在砂石料路堤的柔性结构方案中,由于海边场地基本已经被水淹没,无法进行常规的陆上施工,只能先回填一定厚度的砂石料出水面再进行施工。但由于该场地地基主要为深厚软黏土,表层土体承载力较弱,标贯击数小于3击。因此如何在水下而且深厚软黏土地基上修筑填方路堤是修筑海堤面临的主要难题。In the flexible structure scheme of sand and gravel embankment, since the seaside site is basically submerged by water, conventional land construction cannot be carried out, so it can only be backfilled with a certain thickness of sand and gravel to get out of the water before construction. However, because the foundation of the site is mainly deep and soft clay, the bearing capacity of the surface soil is weak, and the number of standard penetration hits is less than 3. Therefore, how to build a fill embankment under water and on a deep soft clay foundation is a major problem in building a sea embankment.
与普通陆地上的软土路堤填筑的工程相比,主要差别是首先要填筑一定厚度的砂垫层作为出水回填料出水面为后续的插板作业提供作业面,同时由于超深塑料排水板的插板机械自重较大,出水回填料荷载和插板机械荷载叠加作用于软黏土地基上。在插板施工时地基软黏土的抗剪强度没有得到任何提高,在出水回填料荷载和插板机械荷载联合作用下软黏土地基失稳可能性极大。Compared with the soft soil embankment filling project on ordinary land, the main difference is that firstly, a certain thickness of sand cushion must be filled as the water outlet backfill to provide a working surface for the subsequent inserting operations. At the same time, due to the ultra-deep plastic drainage The mechanical self-weight of the inserting plate of the slab is relatively large, and the load of the outlet backfill and the mechanical load of the inserting plate are superimposed on the soft clay foundation. The shear strength of the soft clay foundation has not been improved during the construction of the insert plate, and the possibility of instability of the soft clay foundation is extremely high under the joint action of the backfill load of the effluent and the mechanical load of the insert plate.
在混凝土海墙的刚性结构方案中,由于软土地基沉降尚未结束,海墙还要随着地基一起沉降变形,由于变形不均匀,可能引起海墙的倾倒或者开裂。 上述现象在印尼雅加达的现有的混凝土结构的海墙中得到体现;麻拉巴鲁地区十多年前建造的混凝土海墙的墙体已经开裂,海水顺裂缝流向街道。混凝土海墙的主要缺点为建墙成本高昂;海墙建成后开裂或者倾倒,挡水效果不佳。In the rigid structure scheme of the concrete sea wall, since the settlement of the soft soil foundation has not yet ended, the sea wall will also settle and deform along with the foundation, and the uneven deformation may cause the sea wall to topple or crack. The above phenomenon is reflected in the existing concrete sea wall in Jakarta, Indonesia; the wall of the concrete sea wall built more than ten years ago in the Mala Baru area has cracked, and seawater flows along the cracks to the streets. The main disadvantage of the concrete sea wall is the high cost of building the wall; the sea wall cracks or topples after completion, and the water retaining effect is not good.
发明内容Contents of the invention
针对现有技术中存在的一些问题,本申请提供了一种防渗路堤及施工工艺,该防渗路堤的柔性和防渗性较好,可适应沉降地基。Aiming at some problems existing in the prior art, the application provides an anti-seepage embankment and construction technology. The anti-seepage embankment has good flexibility and anti-seepage performance, and can adapt to subsidence foundation.
本申请第一方面提供了一种防渗路堤,其包括:砂垫层和填筑层,其中,The first aspect of the present application provides an anti-seepage embankment, which includes: a sand cushion and a filling layer, wherein,
所述砂垫层位于软土层上;塑料排水板从软土层中延伸至砂垫层中,为软土层排水;The sand cushion layer is located on the soft soil layer; the plastic drainage board extends from the soft soil layer to the sand cushion layer to drain the soft soil layer;
所述填筑层位于砂垫层上,其中设有位于下部的第一防渗体和位于上部的第二防渗体;所述第一防渗体为刚性或半刚性防渗体,与第一防渗体相连的第二防渗体为柔性防渗体。The filling layer is located on the sand cushion, which is provided with a first anti-seepage body at the bottom and a second anti-seepage body at the top; the first anti-seepage body is a rigid or semi-rigid anti-seepage body, and the second anti-seepage body The second anti-seepage body connected with the first anti-seepage body is a flexible anti-seepage body.
优选所述第一防渗体为半刚性防渗体;可采用水泥浆硬化而成。Preferably, the first anti-seepage body is a semi-rigid anti-seepage body; it can be hardened by cement slurry.
可选地,所述防渗路堤还包括形成晚于第一防渗体的第三防渗体,从软土层延伸至填筑层并与第一防渗体相接。Optionally, the anti-seepage embankment further includes a third anti-seepage body formed later than the first anti-seepage body, extending from the soft soil layer to the filling layer and connecting with the first anti-seepage body.
可选地,所述第三防渗体为半刚性防渗体;可采用水泥浆硬化而成。Optionally, the third anti-seepage body is a semi-rigid anti-seepage body; it can be hardened by cement slurry.
可选地,所述填筑层采用砂石料或黏土填筑而成;所述第一防渗体采用水泥浆在填筑层中硬化而成,未接触砂垫层;所述第二防渗体为至少一层防渗土工布,第二防渗体的接头位于第一防渗体中;所述第二防渗体呈弯折形。Optionally, the filling layer is filled with sand and gravel or clay; the first anti-seepage body is formed by hardening cement slurry in the filling layer without contacting the sand cushion; the second anti-seepage The body is at least one layer of anti-seepage geotextile, and the joint of the second anti-seepage body is located in the first anti-seepage body; the second anti-seepage body is bent.
可选地,所述软土层和砂垫层位于水面下,填筑层和位于填筑层中的第一防渗体均从水面下延伸至水面上,第二防渗体位于水面上。Optionally, the soft soil layer and the sand cushion layer are located below the water surface, the filling layer and the first anti-seepage body located in the filling layer both extend from below the water surface to the water surface, and the second anti-seepage body is located on the water surface.
可选地,所述软土层上设有土工布层,土工布层上设有土工格栅,土工 格栅上铺设所述砂垫层。Optionally, the soft soil layer is provided with a geotextile layer, the geotextile layer is provided with a geogrid, and the sand cushion is laid on the geogrid.
本申请第二方面提供了一种防渗路堤,其包括:The second aspect of the present application provides a kind of anti-seepage embankment, which comprises:
砂垫层和填筑层;其中,所述砂垫层位于软土层上;塑料排水板从软土层中延伸至砂垫层中,为软土层排水;所述填筑层位于砂垫层上,其中设有第一防渗体;Sand cushion and filling layer; wherein, the sand cushion is located on the soft soil layer; the plastic drainage board extends from the soft soil layer to the sand cushion to drain the soft soil layer; the filling layer is located on the sand cushion On the layer, the first anti-seepage body is arranged in it;
还包括形成晚于第一防渗体的第三防渗体,从软土层延伸至填筑层并与第一防渗体相接。It also includes a third anti-seepage body formed later than the first anti-seepage body, extending from the soft soil layer to the filling layer and connecting with the first anti-seepage body.
可选地,所述第三防渗体为半刚性防渗体;可采用水泥浆硬化而成。Optionally, the third anti-seepage body is a semi-rigid anti-seepage body; it can be hardened by cement slurry.
可选地,所述填筑层中设有位于下部的第一防渗体和位于上部的第二防渗体;所述第一防渗体为刚性或半刚性防渗体,与第一防渗体相连的第二防渗体为柔性防渗体。Optionally, the first anti-seepage body at the lower part and the second anti-seepage body at the upper part are provided in the filling layer; the first anti-seepage body is a rigid or semi-rigid anti-seepage body, and the first anti-seepage body The second anti-seepage body connected with the seepage body is a flexible anti-seepage body.
第二方面提供的防渗路堤的其他技术方案可与第一方面提供的防渗路堤的技术方案相同或相似,此处不再赘述。Other technical solutions of the anti-seepage embankment provided by the second aspect may be the same as or similar to the technical solutions of the anti-seepage embankment provided by the first aspect, and will not be repeated here.
本申请第三方面提供了一种防渗路堤的施工工艺,其包括:The third aspect of the present application provides a construction technique for an anti-seepage embankment, which includes:
砂垫层施工:在软土层表面铺设砂垫层;Sand cushion construction: lay a sand cushion on the surface of the soft soil layer;
塑料排水板施工:将多个塑料排水板打入软土层中,使各个塑料排水板的一端位于砂垫层,以排水;Construction of plastic drainage boards: Drive multiple plastic drainage boards into the soft soil layer, so that one end of each plastic drainage board is located on the sand cushion to drain water;
填筑层及其防渗体施工:在砂垫层上填筑第一填筑层;在第一填筑层中构建刚性或半刚性的第一防渗体;将柔性的第二防渗体的一端与第一防渗体搭接;在第一填筑层上,在第二防渗体的两侧依次填筑多个具有坡度的子填筑层,所述第二防渗体沿着所述坡度铺设。The construction of the filling layer and its anti-seepage body: fill the first filling layer on the sand cushion layer; build a rigid or semi-rigid first anti-seepage body in the first filling layer; place the flexible second anti-seepage body One end of the anti-seepage body overlaps with the first anti-seepage body; on the first filling layer, a plurality of sub-filling layers with slopes are sequentially filled on both sides of the second anti-seepage body, and the second anti-seepage body is along the The slope is laid.
可选地,所述防渗路堤的施工工艺,还包括第三防渗体施工:待软土层沉降稳定后,在砂垫层中构建第三防渗体,由软土层延伸至第一填筑层中, 与第一防渗体相接。Optionally, the construction process of the anti-seepage embankment also includes the construction of the third anti-seepage body: after the settlement of the soft soil layer is stable, the third anti-seepage body is constructed in the sand cushion layer, extending from the soft soil layer to the first anti-seepage body. In the filling layer, it is in contact with the first anti-seepage body.
可选地,所述防渗路堤的施工工艺,更具体地,包括:Optionally, the construction process of the anti-seepage embankment, more specifically, includes:
砂垫层施工:在软土层表面依次铺设土工布、土工格栅和砂垫层;Sand cushion construction: Lay geotextiles, geogrids and sand cushions in sequence on the surface of the soft soil layer;
塑料排水板施工:将多个塑料排水板打入软土层中,使各个塑料排水板的一端位于砂垫层,以排水;Construction of plastic drainage boards: Drive multiple plastic drainage boards into the soft soil layer, so that one end of each plastic drainage board is located on the sand cushion to drain water;
填筑层及其防渗体施工:在砂垫层上回填砂石料或黏土形成第一填筑层;在第一填筑层中喷入水泥浆,待水泥浆硬化后形成第一防渗体;在水泥浆硬化前将第二防渗体的一端埋入第一防渗体中形成搭接;在第一填筑层上,在第二防渗体的两侧依次填筑砂石料或黏土,形成多个具有坡度的子填筑层,所述第二防渗体沿着所述坡度铺设,呈Z字走向;最上层的两个子填筑层大致齐平,其上能够进一步施工形成路面;第二防渗体采用一层或多层防渗土工布。Construction of the filling layer and its anti-seepage body: Backfill sand and gravel or clay on the sand cushion layer to form the first filling layer; spray cement slurry into the first filling layer, and form the first anti-seepage body after the cement slurry hardens; Embed one end of the second anti-seepage body into the first anti-seepage body to form an overlap before the cement slurry hardens; on the first filling layer, fill sand and gravel or clay in sequence on both sides of the second anti-seepage body, A plurality of sub-filling layers with a slope are formed, and the second anti-seepage body is laid along the slope in a Z-shaped direction; the two sub-filling layers of the uppermost layer are approximately flush, and further construction can be carried out on it to form a road surface; The second anti-seepage body adopts one or more layers of anti-seepage geotextiles.
可选地,所述防渗路堤的施工工艺,更具体地,包括:Optionally, the construction process of the anti-seepage embankment, more specifically, includes:
砂垫层施工:在位于水面下的软土层表面依次铺设土工布和土工格栅;在土工格栅上铺设砂垫层;Sand cushion construction: Lay geotextiles and geogrids sequentially on the surface of the soft soil layer under the water surface; lay sand cushions on the geogrid;
塑料排水板施工:采用船舶进行水上插板,将多个塑料排水板打入软土层中,并使各个塑料排水板的一端位于砂垫层中;Construction of plastic drainage boards: use ships to insert boards on the water, drive multiple plastic drainage boards into the soft soil layer, and make one end of each plastic drainage board located in the sand cushion;
填筑层及其防渗体施工:在砂垫层上回填砂石料或黏土出水面,形成第一填筑层;在第一填筑层中喷入水泥浆,待水泥浆硬化后形成第一防渗体;第一防渗体不接触砂垫层;在水泥浆未硬化前将柔性的第二防渗体的一端埋入第一防渗体的水泥浆内0.3m以上,与第一防渗体形成完全搭接防渗;第二防渗体采用一层或多层防渗土工布;在第一填筑层上,在第二防渗体的两侧轮流填筑砂石料或黏土,形成具有坡度的多个子填筑层;第二防渗体沿着所 述坡度铺设,呈弯折形;最上层的子填筑层大致齐平,其上能够进一步施工形成路面;Construction of the filling layer and its anti-seepage body: Backfill sand and gravel or clay out of the water surface on the sand cushion layer to form the first filling layer; spray cement slurry into the first filling layer, and form the first anti-seepage layer after the cement slurry hardens. seepage body; the first anti-seepage body does not contact the sand cushion; before the cement slurry is hardened, one end of the flexible second anti-seepage body is buried in the cement slurry of the first anti-seepage body for more than 0.3m, and the first anti-seepage body The second anti-seepage body adopts one or more layers of anti-seepage geotextiles; on the first filling layer, sand and gravel or clay are alternately filled on both sides of the second anti-seepage body to form A plurality of sub-filling layers with a slope; the second anti-seepage body is laid along the slope, in a bent shape; the uppermost sub-filling layer is roughly flush, and can be further constructed to form a road surface;
第三防渗体施工:待填筑层施工完毕、软土层沉降稳定后,在砂垫层中喷入水泥浆,待水泥浆硬化后形成第三防渗体;第三防渗体下部位于软土层中,第三防渗体还与第一防渗体相接;Construction of the third anti-seepage body: After the construction of the filling layer is completed and the settlement of the soft soil layer is stable, cement slurry is sprayed into the sand cushion layer, and the third anti-seepage body is formed after the cement slurry hardens; the lower part of the third anti-seepage body is located in the soft soil layer. In the soil layer, the third anti-seepage body is also in contact with the first anti-seepage body;
路面施工:在填筑层上进行路面及附属结构施工,形成路堤。Pavement construction: Carry out pavement and auxiliary structure construction on the filling layer to form an embankment.
本申请第四方面提供了一种防渗路堤,其采用前文任一技术方案所述的防渗路堤的施工工艺得到。The fourth aspect of the present application provides an anti-seepage embankment, which is obtained by using the construction process of the anti-seepage embankment described in any of the above technical solutions.
本申请第五方面提供了一种防渗路堤的应用,其应用于沉降地基。The fifth aspect of the present application provides an application of an anti-seepage embankment, which is applied to a subsidence foundation.
与现有技术相比,本申请的有益效果为:Compared with the prior art, the beneficial effects of the present application are:
本申请至少一种实施方式提供的防渗路堤采用柔性路堤结构,采用水上插板工艺,防止回填砂石料回填出水面时的地基失稳问题。解决了现有技术中柔性结构或刚性结构的海堤的建造及后续运行的难题。The anti-seepage embankment provided by at least one embodiment of the present application adopts a flexible embankment structure, and adopts a water-sliding board technology to prevent foundation instability when backfilling sand and gravel materials backfill out of the water surface. The problem of the construction and subsequent operation of seawalls with flexible structures or rigid structures in the prior art is solved.
本申请至少一种实施方式提供的防渗路堤,采用水泥浆和防渗土工布组合的方式,施工方便,防渗可靠性好,防渗土工布在路堤内部,抗老化好。与刚性混凝土墙相比,地基变形适用能力强,不会倾倒开裂等,建造和维护成本低。The anti-seepage embankment provided by at least one embodiment of the present application adopts the combination of cement slurry and anti-seepage geotextile, which is convenient for construction and has good anti-seepage reliability. The anti-seepage geotextile is inside the embankment and has good aging resistance. Compared with rigid concrete walls, the foundation has strong adaptability to deformation, will not fall and crack, etc., and has low construction and maintenance costs.
附图说明Description of drawings
图1是一种实施方式的砂垫层施工示意图;Fig. 1 is a schematic diagram of sand cushion construction of an embodiment;
图2是一种实施方式的塑料排水板施工示意图;Fig. 2 is a construction schematic diagram of a plastic drainage board in an embodiment;
图3是一种实施方式的第一填筑层施工示意图;Fig. 3 is a construction schematic diagram of the first filling layer of an embodiment;
图4是一种实施方式的第一防渗体施工示意图;Fig. 4 is a construction schematic diagram of the first anti-seepage body of an embodiment;
图5A-5D是一种实施方式的填筑层和第二防渗体施工示意图;5A-5D are construction schematic diagrams of a filling layer and a second anti-seepage body in an embodiment;
图6是一种实施方式的第三防渗体施工示意图;Fig. 6 is a construction schematic diagram of a third anti-seepage body in an embodiment;
图7是一种实施方式的防渗路堤示意图;Fig. 7 is a schematic diagram of an embodiment of an anti-seepage embankment;
图中编号:1土工布层;2砂垫层;3填筑层,31第一填筑层,32第二填筑层,33第三填筑层,34第四填筑层;41第一防渗体,42第二防渗体,43第三防渗体;5塑料排水板;100软土层,200水面。Numbers in the figure: 1 geotextile layer; 2 sand cushion layer; 3 filling layer, 31 first filling layer, 32 second filling layer, 33 third filling layer, 34 fourth filling layer; 41 first filling layer Anti-seepage body, 42 second anti-seepage body, 43 third anti-seepage body; 5 plastic drainage board; 100 soft soil layer, 200 water surface.
具体实施方式Detailed ways
以下结合具体实施方式对本申请的技术方案进行详实的阐述,然而应当理解,在没有进一步叙述的情况下,一个实施方式中的元件、结构和特征也可以有益地结合到其他实施方式中。The technical solutions of the present application will be described in detail below in conjunction with specific embodiments. However, it should be understood that without further description, elements, structures and features in one embodiment can also be beneficially combined in other embodiments.
在本申请的描述中,需要理解的是,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。In the description of the present application, it should be understood that the terms "first" and "second" are used for description purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly indicating the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features.
在本申请的描述中,需要理解的是,术语“上”、“下”、“底”、“内”等指示的方位或位置关系为基于附图1所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。In the description of the present application, it should be understood that the orientations or positional relationships indicated by the terms "upper", "lower", "bottom", "inside" and the like are based on the orientation or positional relationships shown in Figure 1, and are only In order to facilitate the description of the present application and simplify the description, it does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present application.
在本申请的描述中,需要说明的是,除非另有明确的规定和限定,术语“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本申请中的具体含义。In the description of this application, it should be noted that, unless otherwise clearly stipulated and limited, the terms "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated Ground connection; it can be directly connected, or indirectly connected through an intermediary, and can be internally connected between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in this application in specific situations.
本实施方式中的软土层主要是指含水的易发生沉降的土层,如软黏土地 基等;所述的路堤可以是河堤,湖堤,海堤等。The soft soil layer in the present embodiment mainly refers to the water-containing soil layer prone to subsidence, such as soft clay foundation etc.; the embankment can be a river embankment, a lake embankment, a sea embankment, etc.
如图7所示,本申请第一种实施方式提供了一种防渗路堤,可适应于沉降地基,包括:As shown in Figure 7, the first embodiment of the present application provides an anti-seepage embankment, which can be adapted to subsidence foundations, including:
土工布层1和土工格栅,其中,土工布层1位于软土层100上,土工格栅位于土工布层1上。其中,土工布层1主要起隔离作用,可防止软土层100污染砂垫层2。所述土工格栅强度较大,可以起到分担载荷的作用,使沉降均匀,避免土工布破裂。A geotextile layer 1 and a geogrid, wherein the geotextile layer 1 is located on the soft soil layer 100 , and the geogrid is located on the geotextile layer 1 . Among them, the geotextile layer 1 mainly plays an isolation role, which can prevent the soft soil layer 100 from polluting the sand cushion layer 2 . The geogrid has a relatively high strength, which can share the load, make the settlement uniform, and avoid the rupture of the geotextile.
砂垫层2,其位于土工布层1和土工格栅上,水面200下;厚度可为800-1200mm,例如可为900mm,1000mm,1100mm等。The sand cushion layer 2 is located on the geotextile layer 1 and the geogrid, 200 below the water surface; the thickness can be 800-1200mm, such as 900mm, 1000mm, 1100mm, etc.
填筑层3,其位于砂垫层2上;填筑层3顶部可铺设公路等路面。The filling layer 3 is located on the sand cushion layer 2; road surfaces such as roads can be laid on the top of the filling layer 3.
其中,所述填筑层3可采用砂石料或黏土等填筑而成,其中设有第一防渗体41和第二防渗体42。其中,第一防渗体41为刚性或半刚性防渗体;所述的刚性是指强度较高,例如第一防渗体为混凝土结构等;所述半刚性是指工作特性介于刚性和柔性之间,例如水泥土搅拌桩或者高压旋喷桩等,为本领域常规术语;例如可采用在填筑层3中注入水泥浆与砂石料或黏土搅拌硬化而成;从水面200下延伸至水面200上;与第二防渗体42相连。第二防渗体42为柔性防渗体(可变形),位于水面200上。可选地,第二防渗体42采用至少一层防渗土工布施工形成,例如可采用两布一膜,其接头位于第一防渗体41中,可与第一防渗体41之间形成无缝连接,增加防渗性能。所述第二防渗体42在填筑层3中呈弯折形,例如图7中所示的之字形,随着填筑层3的分段填筑过程倾斜设置。Wherein, the filling layer 3 can be filled with sand and gravel or clay, and a first anti-seepage body 41 and a second anti-seepage body 42 are provided therein. Wherein, the first anti-seepage body 41 is a rigid or semi-rigid anti-seepage body; said rigidity means that the strength is relatively high, for example, the first anti-seepage body is a concrete structure, etc.; said semi-rigidity means that the working characteristics are between rigidity and Between flexibility, such as cement-soil mixing piles or high-pressure rotary grouting piles, etc., are conventional terms in the field; for example, it can be formed by injecting cement slurry into the filling layer 3 and stirring and hardening sand and gravel materials or clay; extending from the water surface 200 to On the water surface 200; connected with the second anti-seepage body 42. The second anti-seepage body 42 is a flexible anti-seepage body (deformable), located on the water surface 200 . Optionally, the second anti-seepage body 42 is formed by construction of at least one layer of anti-seepage geotextile, for example, two cloths and one membrane can be used, and its joint is located in the first anti-seepage body 41, and can be connected with the first anti-seepage body 41. Form a seamless connection and increase the anti-seepage performance. The second anti-seepage body 42 is in a bent shape in the filling layer 3 , such as the zigzag shape shown in FIG. 7 , and is arranged obliquely along with the stepwise filling process of the filling layer 3 .
本实施方式采用半刚性/刚性与柔性结合的防渗体,能够发生适应性变形而不开裂,因此适应性更好。如果填筑层3中上下全部为刚性防渗体,其刚 度太高,很可能当地基发生沉降时会使得防渗体产生裂缝而漏水。此外,第二防渗体42的弯折走向,一方面顺应填筑层3的填筑走向方便填料,另一方面适应路堤变形性更强。This embodiment adopts semi-rigid/rigid and flexible anti-seepage body, which can undergo adaptive deformation without cracking, so the adaptability is better. If all are rigid anti-seepage body up and down in the filling layer 3, its rigidity is too high, can make anti-seepage body produce crack and leak when the ground subsidence takes place probably. In addition, the bending direction of the second anti-seepage body 42, on the one hand, conforms to the filling direction of the filling layer 3 to facilitate filling, and on the other hand, it is more adaptable to the deformability of the embankment.
所述防渗路堤还具有施工晚于第一防渗体41和第二防渗体42的第三防渗体43。为了施工方便,优选为半刚性防渗体,例如可采用注入水泥浆搅拌硬化而成。第三防渗体43从软土层100延伸至填筑层3,并与第一防渗体41相接;隔断了砂垫层2的水平透水通道作用,从而在水面200下将防渗路堤分为两部分,防止从一侧进入的河水、海水或者湖水进入另一侧。例如,在图7中,如果海水从右侧袭来,由于各个防渗体的存在,可防止其进入左侧。The anti-seepage embankment also has a third anti-seepage body 43 constructed later than the first anti-seepage body 41 and the second anti-seepage body 42 . For the convenience of construction, it is preferably a semi-rigid anti-seepage body, for example, it can be formed by injecting cement slurry and stirring and hardening. The third anti-seepage body 43 extends from the soft soil layer 100 to the filling layer 3, and connects with the first anti-seepage body 41; it cuts off the function of the horizontal permeable channel of the sand cushion layer 2, thereby closing the anti-seepage embankment under the water surface 200 Divided into two parts to prevent river, sea or lake water entering from one side from entering the other side. For example, in Fig. 7, if sea water hits from the right side, it can be prevented from entering the left side due to the existence of each anti-seepage body.
作为一种可选的实施方式,所述软土层100中打设有多个塑料排水板5,其从软土层100中延伸至砂垫层2,从而可实现对软土层100的预压排水。进一步地,所述第一防渗体41的底部未到达砂垫层2,从而不会破坏其底部对应的塑料排水板5;所述第三防渗体43形成于塑料排水板5排水完成后。这样的方式能够给塑料排水板5提供足够的排水空间和排水时间,使得各塑料排水板5排出的水均可能实现向左右两个方向的排出,使得软土层100的排水固结更充分有效。As an optional embodiment, a plurality of plastic drainage boards 5 are drilled in the soft soil layer 100, which extend from the soft soil layer 100 to the sand cushion layer 2, so that the soft soil layer 100 can be pre-treated. Pressure drain. Further, the bottom of the first anti-seepage body 41 does not reach the sand cushion layer 2, so that the corresponding plastic drainage board 5 at the bottom will not be damaged; the third anti-seepage body 43 is formed after the drainage of the plastic drainage board 5 is completed . Such a method can provide sufficient drainage space and drainage time for the plastic drainage boards 5, so that the water discharged from each plastic drainage board 5 may be discharged to the left and right directions, so that the drainage consolidation of the soft soil layer 100 is more sufficient and effective. .
本申请第二种实施方式提供了一种防渗路堤的施工工艺,包括以下步骤:The second embodiment of the present application provides a construction process for an anti-seepage embankment, comprising the following steps:
砂垫层施工:Sand cushion construction:
如图1所示,在位于水面200下的软土层100表面依次铺设土工布1和土工格栅。在土工格栅上铺设厚度约为1000mm的中粗砂垫层2。所述中粗是指细度模数在1.6-3.7的砂,该砂垫层2主要为后续的塑料排水板5排水提供排水通道。As shown in FIG. 1 , a geotextile 1 and a geogrid are sequentially laid on the surface of the soft soil layer 100 under the water surface 200 . A medium-coarse sand cushion 2 with a thickness of about 1000mm is laid on the geogrid. The medium-coarse refers to sand with a fineness modulus of 1.6-3.7, and the sand cushion 2 mainly provides drainage channels for the subsequent drainage of the plastic drainage board 5 .
塑料排水板施工:Plastic drainage board construction:
如图2所示,进行水上插设塑料排水板作业,可简称为水上插板。采用专用船舶进行水上插板,将塑料排水板5打入软土层100中,并使各个塑料排水板5的一端位于砂垫层2中。塑料排水板5主要为软土层100内形成排水通道,在后续填筑层3的压载作用下,软土层100内的水沿着塑料排水板5排至砂垫层2上。As shown in Figure 2, the operation of inserting plastic drainage boards above water can be referred to as water boards for short. Use a special ship to insert the board on the water, drive the plastic drainage board 5 into the soft soil layer 100, and make one end of each plastic drainage board 5 be located in the sand cushion 2. The plastic drainage board 5 mainly forms a drainage channel in the soft soil layer 100 , and under the ballast action of the subsequent filling layer 3 , the water in the soft soil layer 100 is discharged to the sand cushion 2 along the plastic drainage board 5 .
水上插板是比较成熟的施工作业,在中国天津港、黄骅港、连云港等淤泥质港口的抛石防波堤建造中广泛采用。例如中交集团具有成套的铺排和塑料排水板水上打设专用船舶。Water flaps are relatively mature construction operations, and are widely used in the construction of riprap breakwaters in muddy ports such as Tianjin Port, Huanghua Port, and Lianyungang Port in China. For example, CCCC has a complete set of laying and plastic drainage boards for laying special ships on water.
此外,塑料排水板5是否需要打入位于软土层100下的持力层中是需要根据加固厚度而确定的。也可以根据软土层100的厚度确定塑料排水板5的打设深度,例如软土层厚度太深,可能就不需要延伸至持力层。In addition, whether the plastic drainage board 5 needs to be driven into the bearing layer under the soft soil layer 100 needs to be determined according to the reinforcement thickness. The setting depth of the plastic drainage board 5 can also be determined according to the thickness of the soft soil layer 100. For example, if the thickness of the soft soil layer is too deep, it may not be necessary to extend to the bearing layer.
填筑层3及其防渗体施工:Construction of filling layer 3 and its anti-seepage body:
如图3所示,在砂垫层2上回填砂石料或黏土出水面约0.5m,形成第一填筑层31。As shown in FIG. 3 , the first filling layer 31 is formed by backfilling the sand cushion layer 2 with sand and gravel or clay about 0.5 m out of the water surface.
如图4所示,在第一填筑层31中喷入水泥浆,待水泥浆硬化后形成第一防渗体41。由于第一填筑层31一般为砂石料或黏土填筑,可采用常规的高压旋喷桩或者水泥搅拌桩施工以形成第一防渗体41。采用水泥浆形成的第一防渗体41为半刚性防渗体。还可以选择在第一填筑层31中浇筑混凝土形成刚性防渗体。As shown in FIG. 4 , cement slurry is sprayed into the first filling layer 31 , and the first anti-seepage body 41 is formed after the cement slurry hardens. Since the first filling layer 31 is generally filled with sand and gravel or clay, conventional high-pressure jet grouting piles or cement mixing piles can be used for construction to form the first anti-seepage body 41 . The first anti-seepage body 41 formed by cement slurry is a semi-rigid anti-seepage body. It is also possible to choose to pour concrete in the first filling layer 31 to form a rigid anti-seepage body.
在水泥浆或混凝土未硬化前将第二防渗体42的一端埋入第一防渗体41的水泥浆内0.3m以上,优选0.5m以上,与第一防渗体41形成完全搭接防渗。所述第二防渗体为柔性防渗体,例如可采用防渗的一层或多层土工布。Before the cement slurry or concrete is hardened, one end of the second anti-seepage body 42 is embedded in the cement slurry of the first anti-seepage body 41 for more than 0.3m, preferably more than 0.5m, to form a complete lap joint with the first anti-seepage body 41. Seep. The second anti-seepage body is a flexible anti-seepage body, for example, one or more layers of anti-seepage geotextiles can be used.
如图5A所示,在第一填筑层31上,位于第二防渗体42的第一侧(图 中为右侧),继续填筑砂石料或黏土,形成具有第一坡度的第二填筑层32。第二防渗体42沿着该第一坡度铺设。As shown in Figure 5A, on the first filling layer 31, on the first side (the right side in the figure) of the second anti-seepage body 42, continue to fill sand and gravel or clay to form a second slope with a first slope. Fill layer 32. The second anti-seepage body 42 is laid along the first slope.
如图5B所示,在第一填筑层31上,位于第二防渗体42的第二侧(图中为左侧),继续填筑砂石料或黏土,形成高于第二填筑层32并具有第二坡度的第三填筑层33。第二防渗体42从第一坡度转至第二坡度铺设,如图5C所示。As shown in Figure 5B, on the first filling layer 31, located on the second side (the left side in the figure) of the second anti-seepage body 42, continue to fill sand and gravel or clay to form a layer higher than the second filling layer. 32 and a third filling layer 33 with a second slope. The second anti-seepage body 42 is laid from the first slope to the second slope, as shown in FIG. 5C .
如图5D所示,在第二填筑层32上,位于第二防渗体42的第一侧(图中为右侧),继续填筑砂石料或黏土,形成与第三填筑层33等高(大致齐平)的第四填筑层34,从而完成填筑层3的施工。As shown in Figure 5D, on the second filling layer 32, on the first side (the right side in the figure) of the second anti-seepage body 42, continue to fill sand and gravel or clay to form the third filling layer 33 The fourth filling layer 34 of equal height (approximately flush), thereby completing the construction of the filling layer 3 .
值得理解的是,本申请中的填筑层数量不仅限于第一至第四填筑层,可以根据实际的需要增加或减少填筑层的数量。It should be understood that the number of filling layers in this application is not limited to the first to fourth filling layers, and the number of filling layers can be increased or decreased according to actual needs.
在上述施工过程中,因为砂垫层2需要将塑料排水板5排出的水向左右两侧排出,一般不建议在其中打第一防渗体41,因此第一防渗体41优选地不接触砂垫层2。相反地,如果第一防渗体41延伸至砂垫层2,会使得第一防渗体41所在的图中大致中间部位的塑料排水板5被损坏而无法排水;此外,由于第一防渗体41的阻挡作用,左右两侧的排水方向受限,左侧只能向左侧排水,右侧只能向右侧排水,从而出现排水不畅的问题。In the above construction process, because the sand cushion 2 needs to discharge the water discharged from the plastic drainage board 5 to the left and right sides, it is generally not recommended to place the first anti-seepage body 41 in it, so the first anti-seepage body 41 preferably does not touch Sand cushion 2. Conversely, if the first anti-seepage body 41 extends to the sand cushion 2, the plastic drainage board 5 in the middle of the figure where the first anti-seepage body 41 is located will be damaged and unable to drain water; in addition, due to the first anti-seepage Due to the blocking effect of the body 41, the drainage direction of the left and right sides is limited, the left side can only drain to the left, and the right side can only drain to the right, thereby causing the problem of poor drainage.
在上述施工过程中,按照半幅先后填筑的方式进行,并将柔性的防渗土工布按照“Z”字形的方式沿着半幅坡面逐次升高,一方面顺应土体方便填料,另一方面适应路堤变形性更强。而且在填筑层3中,下部采用半刚性或刚性结构,上部采用柔性结构,能够适应性地变形,一方面起固定第二防渗体42作用,另一方面起适应柔性变形的作用,因此整体的可适应性更好。In the above-mentioned construction process, it is carried out according to the method of half-width successive filling, and the flexible anti-seepage geotextile is gradually raised along the half-width slope in a "Z" shape. On the one hand, it conforms to the soil body to facilitate filling; It is more adaptable to embankment deformation. Moreover, in the filling layer 3, the lower part adopts a semi-rigid or rigid structure, and the upper part adopts a flexible structure, which can be adaptively deformed. On the one hand, it plays the role of fixing the second anti-seepage body 42, and on the other hand, it plays the role of adapting to flexible deformation. Therefore, The overall adaptability is better.
第三防渗体施工:Construction of the third anti-seepage body:
如图6所示,待填筑层3施工完毕、软土层100沉降稳定后,在砂垫层2中喷入水泥浆,待水泥浆硬化后形成第三防渗体43(为半刚性防渗体)。也可采用常规的高压旋喷桩施工以形成第三防渗体43。第三防渗体43下部位于软土层100中,第三防渗体43还与第一防渗体41相接;从而可看做由软土层100延伸至第一填筑层31中。第三防渗体43,第一防渗体41和第二防渗体42形成从下至上的整体衔接的防渗体,将路堤从内部分为左右相互隔离的两部分,防止水分从一侧渗入另一侧。As shown in Figure 6, after the construction of the filling layer 3 is completed and the settlement of the soft soil layer 100 is stable, cement slurry is sprayed into the sand cushion layer 2, and the third anti-seepage body 43 (being a semi-rigid anti-seepage structure) is formed after the cement slurry is hardened. body). The third anti-seepage body 43 can also be formed by using conventional high-pressure rotary grouting piles. The lower part of the third anti-seepage body 43 is located in the soft soil layer 100 , and the third anti-seepage body 43 is also in contact with the first anti-seepage body 41 ; thus it can be seen as extending from the soft soil layer 100 to the first filling layer 31 . The third anti-seepage body 43, the first anti-seepage body 41 and the second anti-seepage body 42 form an integrally connected anti-seepage body from bottom to top, which divides the embankment from the inside into two parts separated from each other on the left and right to prevent moisture from flowing from one side to the other. Infiltrate the other side.
在填筑层3及其防渗体(第一防渗体41和第二防渗体42)施工完成后,需要等待土体沉降。在这过程中,在填筑层3的载荷作用下,位于软土层100中的塑料排水板5处于排水状态,待软土层100排水基本结束,例如排水3个月后测量,软土层的变形量较小,则说明排水基本结束。那么此时便可开始第三防渗体43的施工;因此,第三防渗体43的施工晚于第一防渗体41。After the construction of the filling layer 3 and its anti-seepage body (the first anti-seepage body 41 and the second anti-seepage body 42 ) is completed, it is necessary to wait for the soil to settle. In this process, under the load of the filling layer 3, the plastic drainage board 5 located in the soft soil layer 100 is in a draining state. After the drainage of the soft soil layer 100 is basically completed, for example, after 3 months of drainage, the soft soil layer is measured. The amount of deformation is small, indicating that the drainage is basically over. Then the construction of the third anti-seepage body 43 can be started at this time; therefore, the construction of the third anti-seepage body 43 is later than that of the first anti-seepage body 41 .
路面施工:Road construction:
如图7所示,在填筑层3上进行上部公路路面及附属结构施工,形成路堤。As shown in Fig. 7, the upper road pavement and auxiliary structures are constructed on the filling layer 3 to form an embankment.
所述的实施方式仅仅是对本申请的优选实施方式进行描述,并非对本申请的范围进行限定,在不脱离本申请设计精神的前提下,本领域普通技术人员对本申请的技术方案作出的各种变形和改进,均应落入本申请权利要求书确定的保护范围内。The described embodiment is only a description of the preferred embodiment of the application, and is not intended to limit the scope of the application. Without departing from the design spirit of the application, those skilled in the art may make various modifications to the technical solution of the application. and improvements, all should fall within the scope of protection determined by the claims of the present application.

Claims (11)

  1. 一种防渗路堤,包括砂垫层和填筑层,其特征在于,An anti-seepage embankment, comprising a sand cushion and a filling layer, is characterized in that,
    所述砂垫层位于软土层上;塑料排水板从软土层中延伸至砂垫层中,为软土层排水;The sand cushion layer is located on the soft soil layer; the plastic drainage board extends from the soft soil layer to the sand cushion layer to drain the soft soil layer;
    所述填筑层位于砂垫层上,其中设有位于下部的第一防渗体和位于上部的第二防渗体;所述第一防渗体为刚性或半刚性防渗体,与第一防渗体相连的第二防渗体为柔性防渗体。The filling layer is located on the sand cushion, which is provided with a first anti-seepage body at the bottom and a second anti-seepage body at the top; the first anti-seepage body is a rigid or semi-rigid anti-seepage body, and the second anti-seepage body The second anti-seepage body connected with the first anti-seepage body is a flexible anti-seepage body.
  2. 根据权利要求1所述的防渗路堤,其特征在于,还包括形成晚于第一防渗体的第三防渗体,从软土层延伸至填筑层并与第一防渗体相接。The anti-seepage embankment according to claim 1, further comprising a third anti-seepage body formed later than the first anti-seepage body, extending from the soft soil layer to the filling layer and connecting with the first anti-seepage body .
  3. 根据权利要求2所述的防渗路堤,其特征在于,所述第一防渗体和所述第三防渗体均为半刚性防渗体。The anti-seepage embankment according to claim 2, characterized in that, the first anti-seepage body and the third anti-seepage body are both semi-rigid anti-seepage bodies.
  4. 根据权利要求1-3任一项所述的防渗路堤,其特征在于,所述填筑层采用砂石料或黏土填筑而成;所述第一防渗体采用水泥浆在填筑层中硬化而成,未接触砂垫层;所述第二防渗体为至少一层防渗土工布,第二防渗体的接头位于第一防渗体中;所述第二防渗体呈弯折形。According to the anti-seepage embankment according to any one of claims 1-3, it is characterized in that the filling layer is filled with sand and gravel or clay; the first anti-seepage body is filled with cement slurry in the filling layer It is hardened and does not contact the sand cushion; the second anti-seepage body is at least one layer of anti-seepage geotextile, and the joint of the second anti-seepage body is located in the first anti-seepage body; the second anti-seepage body is curved folding shape.
  5. 根据权利要求1-3任一项所述的防渗路堤,其特征在于,所述软土层和砂垫层位于水面下,填筑层和位于填筑层中的第一防渗体均从水面下延伸至水面上,第二防渗体位于水面上。According to the anti-seepage embankment according to any one of claims 1-3, it is characterized in that, the soft soil layer and the sand cushion are located under the water surface, and the filling layer and the first anti-seepage body positioned in the filling layer are all from The water surface extends to the water surface, and the second anti-seepage body is located on the water surface.
  6. 根据权利要求1-3任一项所述的防渗路堤,其特征在于,所述软土层上设有土工布层,土工布层上设有土工格栅,土工格栅上铺设所述砂垫层。According to the anti-seepage embankment described in any one of claims 1-3, it is characterized in that a geotextile layer is arranged on the soft soil layer, a geogrid is arranged on the geotextile layer, and the sand is laid on the geogrid. Cushion.
  7. 一种防渗路堤的施工工艺,其特征在于,包括:A construction technique for an anti-seepage embankment, characterized in that it comprises:
    砂垫层施工:在软土层表面铺设砂垫层;Sand cushion construction: lay a sand cushion on the surface of the soft soil layer;
    塑料排水板施工:将多个塑料排水板打入软土层中,使各个塑料排水板 的一端位于砂垫层,以排水;Plastic drainage board construction: drive multiple plastic drainage boards into the soft soil layer, so that one end of each plastic drainage board is located on the sand cushion to drain water;
    填筑层及其防渗体施工:在砂垫层上填筑第一填筑层;在第一填筑层中构建刚性或半刚性的第一防渗体;将柔性的第二防渗体的一端与第一防渗体搭接;在第一填筑层上,在第二防渗体的两侧依次填筑多个具有坡度的子填筑层,所述第二防渗体沿着所述坡度铺设。The construction of the filling layer and its anti-seepage body: fill the first filling layer on the sand cushion layer; build a rigid or semi-rigid first anti-seepage body in the first filling layer; place the flexible second anti-seepage body One end of the anti-seepage body overlaps with the first anti-seepage body; on the first filling layer, a plurality of sub-filling layers with slopes are sequentially filled on both sides of the second anti-seepage body, and the second anti-seepage body is along the The slope is laid.
  8. 根据权利要求7所述的防渗路堤的施工工艺,其特征在于,还包括第三防渗体施工:待软土层沉降稳定后,在砂垫层中构建第三防渗体,由软土层延伸至第一填筑层中,与第一防渗体相接。The construction technique of the anti-seepage embankment according to claim 7, is characterized in that, also comprises the construction of the third anti-seepage body: after the settlement of the soft soil layer is stable, the third anti-seepage body is constructed in the sand cushion layer, made of soft soil The layer extends into the first filling layer and is in contact with the first anti-seepage body.
  9. 根据权利要求7所述的防渗路堤的施工工艺,其特征在于,更具体地,包括:The construction technology of anti-seepage embankment according to claim 7, is characterized in that, more specifically, comprises:
    砂垫层施工:在软土层表面依次铺设土工布、土工格栅和砂垫层;Sand cushion construction: Lay geotextiles, geogrids and sand cushions in sequence on the surface of the soft soil layer;
    塑料排水板施工:将多个塑料排水板打入软土层中,使各个塑料排水板的一端位于砂垫层,以排水;Construction of plastic drainage boards: Drive multiple plastic drainage boards into the soft soil layer, so that one end of each plastic drainage board is located on the sand cushion to drain water;
    填筑层及其防渗体施工:在砂垫层上回填砂石料或黏土形成第一填筑层;在第一填筑层中喷入水泥浆,待水泥浆硬化后形成第一防渗体;在水泥浆硬化前将第二防渗体的一端埋入第一防渗体中形成搭接;在第一填筑层上,在第二防渗体的两侧依次填筑砂石料或黏土,形成多个具有坡度的子填筑层,所述第二防渗体沿着所述坡度铺设,呈Z字走向;最上层的两个子填筑层大致齐平,其上能够进一步施工形成路面;第二防渗体采用一层或多层防渗土工布。Construction of the filling layer and its anti-seepage body: Backfill sand and gravel or clay on the sand cushion layer to form the first filling layer; spray cement slurry into the first filling layer, and form the first anti-seepage body after the cement slurry hardens; Embed one end of the second anti-seepage body into the first anti-seepage body to form an overlap before the cement slurry hardens; on the first filling layer, fill sand and gravel or clay in sequence on both sides of the second anti-seepage body, A plurality of sub-filling layers with a slope are formed, and the second anti-seepage body is laid along the slope in a Z-shaped direction; the two sub-filling layers of the uppermost layer are approximately flush, and further construction can be carried out on it to form a road surface; The second anti-seepage body adopts one or more layers of anti-seepage geotextiles.
  10. 根据权利要求7所述的防渗路堤的施工工艺,其特征在于,更具体地,包括:The construction technology of anti-seepage embankment according to claim 7, is characterized in that, more specifically, comprises:
    砂垫层施工:在位于水面下的软土层表面依次铺设土工布和土工格栅; 在土工格栅上铺设砂垫层;Sand cushion construction: Lay geotextiles and geogrids sequentially on the surface of the soft soil layer under the water surface; lay sand cushions on the geogrid;
    塑料排水板施工:采用船舶进行水上插板,将多个塑料排水板打入软土层中,并使各个塑料排水板的一端位于砂垫层中;Construction of plastic drainage boards: use ships to insert boards on the water, drive multiple plastic drainage boards into the soft soil layer, and make one end of each plastic drainage board located in the sand cushion;
    填筑层及其防渗体施工:在砂垫层上回填砂石料或黏土出水面,形成第一填筑层;Construction of the filling layer and its anti-seepage body: backfill sand and gravel or clay out of the water surface on the sand cushion layer to form the first filling layer;
    在第一填筑层中喷入水泥浆,待水泥浆硬化后形成第一防渗体;第一防渗体不接触砂垫层;Spray cement slurry into the first filling layer, and form the first anti-seepage body after the cement slurry hardens; the first anti-seepage body does not contact the sand cushion;
    在水泥浆未硬化前将柔性的第二防渗体的一端埋入第一防渗体的水泥浆内0.3m以上,与第一防渗体形成完全搭接防渗;第二防渗体采用一层或多层防渗土工布;Before the cement slurry is hardened, one end of the flexible second anti-seepage body is buried in the cement slurry of the first anti-seepage body for more than 0.3m, forming a complete overlap with the first anti-seepage body for anti-seepage; the second anti-seepage body adopts One or more layers of anti-seepage geotextile;
    在第一填筑层上,在第二防渗体的两侧轮流填筑砂石料或黏土,形成具有坡度的多个子填筑层;第二防渗体沿着所述坡度铺设,呈弯折形;On the first filling layer, sand and gravel or clay are alternately filled on both sides of the second anti-seepage body to form multiple sub-filling layers with a slope; the second anti-seepage body is laid along the slope and is bent shape;
    最上层的子填筑层大致齐平,其上能够进一步施工形成路面;The uppermost sub-filling layer is approximately flush, on which further construction can be made to form a pavement;
    第三防渗体施工:待填筑层施工完毕、软土层沉降稳定后,在砂垫层中喷入水泥浆,待水泥浆硬化后形成第三防渗体;第三防渗体下部位于软土层中,第三防渗体还与第一防渗体相接;Construction of the third anti-seepage body: After the construction of the filling layer is completed and the settlement of the soft soil layer is stable, cement slurry is sprayed into the sand cushion layer, and the third anti-seepage body is formed after the cement slurry hardens; the lower part of the third anti-seepage body is located in the soft soil layer. In the soil layer, the third anti-seepage body is also in contact with the first anti-seepage body;
    路面施工:在填筑层上进行路面及附属结构施工,形成路堤。Pavement construction: Carry out pavement and auxiliary structure construction on the filling layer to form an embankment.
  11. 一种防渗路堤,采用权利要求7-10任一项所述的防渗路堤的施工工艺得到。An anti-seepage embankment obtained by adopting the construction process of the anti-seepage embankment described in any one of claims 7-10.
PCT/CN2022/106400 2022-07-19 2022-07-19 Anti-seepage embankment and construction process WO2023029782A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/CN2022/106400 WO2023029782A1 (en) 2022-07-19 2022-07-19 Anti-seepage embankment and construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2022/106400 WO2023029782A1 (en) 2022-07-19 2022-07-19 Anti-seepage embankment and construction process

Publications (1)

Publication Number Publication Date
WO2023029782A1 true WO2023029782A1 (en) 2023-03-09

Family

ID=85410810

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/106400 WO2023029782A1 (en) 2022-07-19 2022-07-19 Anti-seepage embankment and construction process

Country Status (1)

Country Link
WO (1) WO2023029782A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960485A (en) * 2022-07-19 2022-08-30 中交第一航务工程局有限公司 Seepage-proofing embankment adaptable to settlement foundation and construction process
CN116607461A (en) * 2023-06-19 2023-08-18 宿迁市宿城区水利工程建设服务中心 River channel seepage prevention structure and river channel seepage prevention method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1521811A1 (en) * 1987-11-13 1989-11-15 Восточно-Сибирское Отделение Всесоюзного Проектно-Изыскательского И Научно-Исследовательского Института " Гидропроект" Им.С.Я.Жука Method of matching earth dam to a structure or rock foundation
RU2128267C1 (en) * 1996-06-27 1999-03-27 Товарищество с ограниченной ответственностью "Научно-производственный центр "Материалы и конструкции для трубопроводов" Motor road on permafrost
WO2006027000A1 (en) * 2004-09-07 2006-03-16 Osama Kamal Roshdy Full displacement technique for soil improvement and constructing walls and piles
CN1773022A (en) * 2005-11-05 2006-05-17 陶钧炳 Fast soft foundation dyke building method and technology
CN102359096A (en) * 2010-11-11 2012-02-22 东南大学 Method for strengthening deep soft soil foundation by sealing
CN109736291A (en) * 2018-12-24 2019-05-10 华中科技大学 One kind owing consolidation and blows on the base of alluvial plain that biological cement is reinforcing road bed and its construction method
CN209816885U (en) * 2019-01-25 2019-12-20 三峡大学 Novel cofferdam structure under soft covering layer
CN210766223U (en) * 2019-05-24 2020-06-16 中冶华成(武汉)工程有限公司 Roadbed structure capable of preventing settlement during drainage
CN111305240A (en) * 2020-03-02 2020-06-19 中铁第一勘察设计院集团有限公司 Cofferdam retaining and protecting structure for coastal soft soil hydraulic reclamation and construction method thereof
CN113585303A (en) * 2021-07-28 2021-11-02 江西省港航建设投资集团有限公司 Seepage-proofing stable cofferdam structure and construction method thereof
RU2763752C1 (en) * 2020-10-30 2022-01-10 Федеральное государственное бюджетное научное учреждение "Федеральный научный центр "Кабардино-Балкарский научный центр Российской академии наук" (КБ НЦ РАН) Method for restoring the geophysical stability of an emergency ground dam on a weak foundation
CN114960485A (en) * 2022-07-19 2022-08-30 中交第一航务工程局有限公司 Seepage-proofing embankment adaptable to settlement foundation and construction process

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1521811A1 (en) * 1987-11-13 1989-11-15 Восточно-Сибирское Отделение Всесоюзного Проектно-Изыскательского И Научно-Исследовательского Института " Гидропроект" Им.С.Я.Жука Method of matching earth dam to a structure or rock foundation
RU2128267C1 (en) * 1996-06-27 1999-03-27 Товарищество с ограниченной ответственностью "Научно-производственный центр "Материалы и конструкции для трубопроводов" Motor road on permafrost
WO2006027000A1 (en) * 2004-09-07 2006-03-16 Osama Kamal Roshdy Full displacement technique for soil improvement and constructing walls and piles
CN1773022A (en) * 2005-11-05 2006-05-17 陶钧炳 Fast soft foundation dyke building method and technology
CN102359096A (en) * 2010-11-11 2012-02-22 东南大学 Method for strengthening deep soft soil foundation by sealing
CN109736291A (en) * 2018-12-24 2019-05-10 华中科技大学 One kind owing consolidation and blows on the base of alluvial plain that biological cement is reinforcing road bed and its construction method
CN209816885U (en) * 2019-01-25 2019-12-20 三峡大学 Novel cofferdam structure under soft covering layer
CN210766223U (en) * 2019-05-24 2020-06-16 中冶华成(武汉)工程有限公司 Roadbed structure capable of preventing settlement during drainage
CN111305240A (en) * 2020-03-02 2020-06-19 中铁第一勘察设计院集团有限公司 Cofferdam retaining and protecting structure for coastal soft soil hydraulic reclamation and construction method thereof
RU2763752C1 (en) * 2020-10-30 2022-01-10 Федеральное государственное бюджетное научное учреждение "Федеральный научный центр "Кабардино-Балкарский научный центр Российской академии наук" (КБ НЦ РАН) Method for restoring the geophysical stability of an emergency ground dam on a weak foundation
CN113585303A (en) * 2021-07-28 2021-11-02 江西省港航建设投资集团有限公司 Seepage-proofing stable cofferdam structure and construction method thereof
CN114960485A (en) * 2022-07-19 2022-08-30 中交第一航务工程局有限公司 Seepage-proofing embankment adaptable to settlement foundation and construction process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960485A (en) * 2022-07-19 2022-08-30 中交第一航务工程局有限公司 Seepage-proofing embankment adaptable to settlement foundation and construction process
CN116607461A (en) * 2023-06-19 2023-08-18 宿迁市宿城区水利工程建设服务中心 River channel seepage prevention structure and river channel seepage prevention method
CN116607461B (en) * 2023-06-19 2023-12-12 宿迁市宿城区水利工程建设服务中心 River channel seepage prevention structure and river channel seepage prevention method

Similar Documents

Publication Publication Date Title
WO2023029782A1 (en) Anti-seepage embankment and construction process
CN104863113A (en) Method for curing in-situ soil in situ and stirring device
CN103981876B (en) For deep soft foundation river course be close to combined member and the construction method that river embankment is built together
CN105200881B (en) The construction method of High-cold regions roadbed freeze-harm Comprehensive Treatment structure
CN106759223A (en) Controllable rigid pile+displacement hull+reinforcement cushion combined composite foundation
CN113957913A (en) Construction method of film bag sand filling combined steel sheet pile cofferdam
CN110965416A (en) Bamboo reinforcement system for reinforcing high-fill roadbed in mountainous area and construction method
CN114960485B (en) Seepage-proofing embankment adaptable to sedimentation foundation and construction process
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN114718012A (en) Composite dyke body ecological sea dike structure on soft soil foundation and construction method thereof
WO2021088445A1 (en) Waterproof curtains at ends of underwater channel foundation pit along water banks
CN219621703U (en) Water conservancy river course slope protection structure
CN111335263B (en) Method for building artificial island
JP2004108142A (en) Method for construction of a control type revetment
CN115450236A (en) Cofferdam anti-seepage structure and construction method thereof
CN211498907U (en) Waterproof curtain at end of underwater channel foundation pit along two sides of water
CN212427150U (en) Overseas side cofferdam structure
CN209669789U (en) Port engineering sloping breakwater and sheet pile upstanding bank mixed structure
CN113106924A (en) Slope top anchoring method for side slope seepage-proofing waterproof blanket
CN111472359A (en) Method for replacing and filling peat soil soft foundation box culvert foundation
Kimura et al. Offshore construction of bulkhead waste facilities by H-joint steel pipe sheet piles
CN111305050A (en) Protection process for existing piers on two sides in tunnel construction
CN111519603A (en) Device for comprehensively treating uneven settlement of underground buried pipe of soft soil foundation by combination of replacement and filling and grouting and construction method
CN217811147U (en) Sand filling pipe bag paving combined double-layer lock catch steel pipe pile seepage-proofing drainage system
CN114960730B (en) Method and structure for building asphalt core wall dam base without foundation pit

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22862923

Country of ref document: EP

Kind code of ref document: A1