WO2022095494A1 - Dry desilting method for riverway - Google Patents

Dry desilting method for riverway Download PDF

Info

Publication number
WO2022095494A1
WO2022095494A1 PCT/CN2021/104828 CN2021104828W WO2022095494A1 WO 2022095494 A1 WO2022095494 A1 WO 2022095494A1 CN 2021104828 W CN2021104828 W CN 2021104828W WO 2022095494 A1 WO2022095494 A1 WO 2022095494A1
Authority
WO
WIPO (PCT)
Prior art keywords
river
construction
dredging
water
river channel
Prior art date
Application number
PCT/CN2021/104828
Other languages
French (fr)
Chinese (zh)
Inventor
周江
付立宏
朱成武
王婧馨
辛颖
李备
刘千孺
陈守伟
赵德岁
许磊
Original Assignee
中铁四局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁四局集团有限公司 filed Critical 中铁四局集团有限公司
Publication of WO2022095494A1 publication Critical patent/WO2022095494A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/88Dredgers; Soil-shifting machines mechanically-driven with arrangements acting by a sucking or forcing effect, e.g. suction dredgers
    • E02F3/90Component parts, e.g. arrangement or adaptation of pumps
    • E02F3/907Measuring or control devices, e.g. control units, detection means or sensors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/02Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
    • E02B3/023Removing sediments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/28Dredgers or soil-shifting machines for special purposes for cleaning watercourses or other ways
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/261Surveying the work-site to be treated
    • E02F9/262Surveying the work-site to be treated with follow-up actions to control the work tool, e.g. controller

Definitions

  • the present application relates to the technical field of river dredging treatment, in particular to a dry dredging method for river courses.
  • river channels cause soil migration, deposition, and deposition of other impurities such as algae contained in the water due to the scouring of running water in the long-term transportation process, resulting in river siltation.
  • the continuous accumulation of silt will lead to the rise of the river bed, making it difficult to transport water resources, and also affect the normal performance of various functions such as flood control, drainage, irrigation, water supply, and navigation. stinks.
  • the purpose of the present application is to provide a dry dredging method for river courses to solve or alleviate the above-mentioned problems in the prior art.
  • the present application provides a dry dredging method for a river channel, including: step S101, positioning and setting out, and measuring the elevation: setting out the construction area and the construction red line according to the construction design, and determining the construction scope; measuring the water surface elevation of the river Line, calculate the size of the water volume in sections; re-measure the elevation of the silt roof in the river channel to determine the amount of dredging in sections; step S102, clearing and leveling the site: according to the planning red line and the blue line of greening construction, clear the surface and grind the site.
  • Step S103 site hardening, temporary access road construction: use concrete to harden the empty site and roads, and bury drainage pipes
  • Step S104 cofferdam construction: according to the length of the river, the cofferdam positions are carried out on both banks Stake out, start from the shore, close in one direction, fill in layers, and roll in layers
  • step S105 pumping: according to the water surface and the elevation of the river bottom, calculate the total pumping volume, and pump the water into the downstream reaches
  • step S106 Sludge excavation and outbound transportation: each section excavates a longitudinal drainage ditch on both sides of the outer side of the river silt, so that the accumulated water returns to the tank and the water pump pumps water; Solids are excavated, loaded and shipped out.
  • the construction area and the construction red line are first set out according to the construction design, and the construction scope is determined; Re-measure the elevation of the silt roof in the river channel, determine the amount of dredging in sections, and realize the pre-construction positioning and setting out, and the preparations for the elevation measurement; during the construction process, according to the planning red line and greening construction blue line, the site is cleared.
  • the river dredging is carried out in sections, and the preliminary preparation and the later construction are carried out at the same time.
  • the construction process is efficient and fast, which not only ensures the smoothness of the river dredging project, but also ensures that the impact on the surrounding area is minimized.
  • the river channel is divided into sections and the cofferdam is built, and then the water in the river bank within the cofferdam is drained by the pump. After the water is drained, the dredging construction is carried out. According to the site conditions of the construction site, dredging is carried out along both sides of the river by means of long-arm excavator or manual excavation.
  • the dry dredging method of the river channel is adopted.
  • the river channel needs to be partially cut off, which is suitable for the dredging of the river channel with a certain space on both sides and easy to cut off construction; on the other hand, the river dredging is thorough and easy to control.
  • the dredging depth, the sludge concentration is high, and the transportation cost is low, so the engineering cost is relatively low.
  • Fig. 1 is the schematic flow sheet of the river course dry dredging method
  • Figure 2 is a schematic cross-sectional view of the cofferdam.
  • Fig. 1 is a schematic flow diagram of a dry dredging method for a river channel provided according to some embodiments of the present application; as shown in Fig. 1 , the dry dredging method for a river channel includes:
  • Step S101 positioning and setting out, measuring the elevation: setting out the construction area and the construction red line according to the construction design, and determining the construction scope; measuring and setting out the water surface elevation of the river channel, and calculating the size of the water volume; Re-test to determine the amount of dredging in stages;
  • the site network is established to ensure accurate elevation and location.
  • GPS and RTK are used to establish on-site control outlets to ensure accurate elevation and location.
  • a plane and elevation control system is established on-site to perform measurement control during the entire construction period.
  • the traverse measurement method is used to establish the plane control system, GPS, RTK and steel ruler are used to measure the line, and the straight line control pile is set.
  • the position of the control pile should be stable and reliable for easy protection during construction and convenient application.
  • the surveying instrument adopts GPS and RTK. According to the benchmarking point provided by the user, the elevation is led to each temporary benchmarking point. The temporary benchmarking point must be firm and stable. Close the retest with the design benchmark.
  • Step S102 site clearing and leveling: according to the planning red line and the greening construction blue line, clearing the site, rolling and leveling it to a preset standard compaction degree; specifically, the preset standard compaction degree is not less than 90%.
  • the site is cleared to the red line as a temporary construction access road and fence installation site; for the section without slope protection structure, shrubs and construction waste , through the excavation equipment (such as: excavator) to directly excavate the surface, transplant or cut down the green plants, and improve the construction efficiency.
  • the surface-clearing garbage is piled up at fixed points, and then transported to the dumping site by muck trucks.
  • the demolished slope protection structure mortar masonry and construction waste are piled up for road construction.
  • Step S103 site hardening, temporary access road construction: concrete hardening is used for the empty site and road, and drainage pipes are buried, wherein the hardened road slopes toward the river, and the slope is 2%; The thickness is 25 cm, and a PC drain pipe with a diameter of 150 mm is buried every 20 meters.
  • a construction access road is built 1 meter outside the river green belt and hardened.
  • the hardened road is 4.5 meters wide and 240 meters long, and some of the hardened access roads are selected as the safety experience area, and a drainage ditch is set outside the safety experience area to connect the river.
  • Step S104 cofferdam construction: stake out the cofferdam position on both banks according to the length of the river channel, start from the bank, close the individual items, fill in layers, and roll in layers; wherein, the slope of the cofferdam upstream side slope is 1: 2; The slope of the backwater surface of the cofferdam is 1:1.5;
  • FIG 2 is a schematic cross-sectional view of the cofferdam provided by the application; as shown in Figure 2, the cofferdam filling material is mainly clay, the top of the cofferdam is 3 meters wide, and the top surface of the cofferdam is 50 cm higher than the water surface of the river.
  • the slope on the upstream side of the cofferdam is smaller than that on the downstream side of the cofferdam, which can better achieve the water blocking effect of the cofferdam.
  • the water outlet surface shall follow the principle of layered filling and layered rolling, and the compaction degree shall not be lower than 90%. In this way, the construction effect of the cofferdam can be fully guaranteed and the construction safety of the cofferdam can be improved.
  • Step S105 pumping: according to the water surface and river bottom elevation, calculate the total pumping volume, and pump the water circle into the downstream reaches; specifically, determine the number and model of the pumping pumps according to the calculated pumping volume.
  • the water surface and river bottom elevations were measured, and the total pumped volume was calculated. Since the elevation of each section is different, the calculation is carried out in combination with the longitudinal section, the transverse section and the plan view. Select the number and model of the water pump according to the volume of the river water (for example: 150m 3 /h, 1500w), and perform temporary power distribution of the generator according to the selected model of the water pump.
  • Step S106 silt excavation and outbound transportation: excavate a longitudinal drainage ditch on each side of the outer side of the river silt in each section, so that the accumulated water returns to the tank, and the water pump pumps water; To solid, carry out excavation, loading and transportation; among them, the bottom of the river bed is leveled according to preset requirements after dredging.
  • the width of the drainage ditches excavated on both sides of the river silt in each subsection is 1 meter wide and 0.5 meters deep, so that the accumulated water in the river channel can be returned to the trough, and all the accumulated water can be pumped out by the water pump.
  • the silt is excavated to the river bank for stacking and drying, and the stacking height is not more than 1.5 meters, so as to prevent the silt from flowing into the river again.
  • the sludge When the sludge is dried to solid, it will be excavated and loaded into trucks for transportation.
  • measures shall be taken to prevent the occurrence of "drops, spills, leaks" and other phenomena; the transportation vehicles shall travel according to the designated route during the process of inward and outward transportation.
  • the site is cleared, rolled and leveled to the preset standard compaction degree
  • use concrete to harden the empty site and road to realize the surface cleaning, leveling and hardening of the site, so as to prepare for the construction of the cofferdam and dredging;
  • the single items are closed, filled in layers, and rolled in layers to complete the construction of the cofferdam; then, the water blocking operation on the upstream surface of the cofferdam is pumped, and it is pumped into the downstream river section for dredging the bottom of the river bed.
  • the river channel is divided into sections and cofferdams are built, and then the water in the river banks within the cofferdam is drained by pumps. After the water is drained, the dredging construction is carried out. According to the construction site conditions, long-arm excavators or manual excavation are often used to dredging along both sides of the river.
  • the dry dredging construction method of the river channel on the one hand, during the construction process, it is necessary to partially cut off the river channel, which is suitable for the dredging of the river channel with a certain space on both sides and easy to cut off construction; on the other hand, the river dredging is thorough and easy to control.
  • the dredging depth, the sludge concentration is high, and the transportation cost is low, so the engineering cost is relatively low.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Treatment Of Sludge (AREA)
  • Revetment (AREA)

Abstract

A dry desilting method for a riverway. In a working process, a river channel must be locally cut off, to allow both banks to have a certain amount of space and facilitate riverway desilting. Furthermore, riverway desilting is thorough, desilting depth is easy to control, sludge concentration is high, transportation costs are low, and engineering costs are relatively low. In the overall process, river channel desilting is carried out in segments, early-stage preparation and later-stage working is carried out at the same time, and the working process is efficient and rapid, thus both ensuring the smoothness of the river channel desilting project, and ensuring that impact on the surroundings is reduced to a minimum.

Description

河道干式清淤方法River dry dredging method 技术领域technical field
本申请涉及河道清淤处理技术领域,特别涉及一种河道干式清淤方法。The present application relates to the technical field of river dredging treatment, in particular to a dry dredging method for river courses.
背景技术Background technique
河道作为水资源输送的载体,长期输送过程中由于流水的冲刷导致土壤迁移、沉积,以及水中含有的藻类等其他杂质沉积,造成河道淤积。淤泥的不断累积将导致河床升高,造成水资源的输送困难,同时还影响到防洪、排涝、灌溉、供水、通航等各项功能的正常发挥,河道内污染物不断增加,影响水质变黑、变臭。为恢复河道正常功能,促进经济社会的快速发展,有必要将沉积在河底的淤泥进行疏浚。As the carrier of water resources transportation, river channels cause soil migration, deposition, and deposition of other impurities such as algae contained in the water due to the scouring of running water in the long-term transportation process, resulting in river siltation. The continuous accumulation of silt will lead to the rise of the river bed, making it difficult to transport water resources, and also affect the normal performance of various functions such as flood control, drainage, irrigation, water supply, and navigation. stinks. In order to restore the normal function of the river and promote the rapid economic and social development, it is necessary to dredging the silt deposited on the river bottom.
因此,需要提供一种针对上述现有技术不足的改进技术方案。Therefore, it is necessary to provide an improved technical solution for the deficiencies of the above-mentioned prior art.
发明内容SUMMARY OF THE INVENTION
本申请的目的在于提供一种河道干式清淤方法,以解决或缓解上述现有技术中存在的问题。The purpose of the present application is to provide a dry dredging method for river courses to solve or alleviate the above-mentioned problems in the prior art.
为了实现上述目的,本申请提供如下技术方案:In order to achieve the above purpose, the application provides the following technical solutions:
本申请提供了一种河道干式清淤方法,包括:步骤S101、定位放线、测标高:根据施工设计对施工区域及施工红线进行放线,确定施工范围;对河道的水面标高进行测量放线,计算分段水量大小;对河道内淤泥顶标高进行复测,确定分段清淤量;步骤S102、场地清表、平整:根据规划红线和绿化施工蓝线,对场地进行清表、碾压平整至预设标准压实度;步骤S103、场地硬化、临时便道施工:对空场地、道路采用混凝土硬化,埋设排水管;步骤S104、围堰施工:根据河道长度将围堰位置在两岸进行放样,自岸边起始,单向合拢,分层填筑,分层碾压;步骤S105、抽水:根据水面和河底标高,计算总的抽水体积,并将水抽入下游河段;步骤S106、淤泥开挖、外运:每一分段在河道淤泥外边两侧各开挖一条纵向排水沟,使积水归槽,水泵抽水;分段开挖淤泥至河岸堆放晾晒,直至淤泥晾晒至固体,进行开挖装车外运。The present application provides a dry dredging method for a river channel, including: step S101, positioning and setting out, and measuring the elevation: setting out the construction area and the construction red line according to the construction design, and determining the construction scope; measuring the water surface elevation of the river Line, calculate the size of the water volume in sections; re-measure the elevation of the silt roof in the river channel to determine the amount of dredging in sections; step S102, clearing and leveling the site: according to the planning red line and the blue line of greening construction, clear the surface and grind the site. Flattening to a preset standard compaction degree; Step S103, site hardening, temporary access road construction: use concrete to harden the empty site and roads, and bury drainage pipes; Step S104, cofferdam construction: according to the length of the river, the cofferdam positions are carried out on both banks Stake out, start from the shore, close in one direction, fill in layers, and roll in layers; step S105, pumping: according to the water surface and the elevation of the river bottom, calculate the total pumping volume, and pump the water into the downstream reaches; step S106. Sludge excavation and outbound transportation: each section excavates a longitudinal drainage ditch on both sides of the outer side of the river silt, so that the accumulated water returns to the tank and the water pump pumps water; Solids are excavated, loaded and shipped out.
有益效果:Beneficial effects:
本申请提供的河道干式清淤方法中,在施工前,首先根据施工设计对施工区域及施工红线进行放线,确定施工范围;对河道的水面标高进行测量放线,计算分段水量大小;对河道内淤泥顶标高进行复测,确定分段清淤量,实现施工前的定位放线、测标高的准备工作;施工过程中,在根据规划红线和绿化施工蓝线,对场地进行清表、碾压整平至预设标准压实度后,对空场地、道路采用混凝土硬化,实现场地的清表、整平和硬化,为围堰施工和清淤做好准备;然后,根据河道场地将围堰位置在河道两岸进行放样,自岸边起始,单项合拢,分层填筑,分层碾压,完成围堰施工;进而,对围堰迎水面的阻水进行抽水作业,将其抽入下游河段,以便对河床底进行清淤;最后,分段开挖淤泥至河岸堆放晾晒,直至淤泥晾晒至固体,进行开挖装车外运,实现河道的完全清淤工作。整个过程,河道清淤分段进行,前期准备与后期施工同时进行,施工过程高效快速,既保证了河道清淤工程的顺畅,又保证了对周边的影响降至最小。In the river channel dry dredging method provided by the present application, before construction, the construction area and the construction red line are first set out according to the construction design, and the construction scope is determined; Re-measure the elevation of the silt roof in the river channel, determine the amount of dredging in sections, and realize the pre-construction positioning and setting out, and the preparations for the elevation measurement; during the construction process, according to the planning red line and greening construction blue line, the site is cleared. , After rolling and leveling to the preset standard compaction degree, use concrete to harden the empty site and road to realize the surface cleaning, leveling and hardening of the site, and prepare for the construction of the cofferdam and dredging; then, according to the river site, the The location of the cofferdam is staked out on both sides of the river, starting from the bank, closing the individual items, filling in layers, and rolling in layers to complete the cofferdam construction; Enter the downstream reaches of the river to dredging the bottom of the river bed; finally, excavate the silt in sections and stack it on the river bank for drying, until the silt is dried to solid, and then excavate, load, and transport to achieve complete dredging of the river. In the whole process, the river dredging is carried out in sections, and the preliminary preparation and the later construction are carried out at the same time. The construction process is efficient and fast, which not only ensures the smoothness of the river dredging project, but also ensures that the impact on the surrounding area is minimized.
河道干式清淤方法在施工时,将河道进行分段并修筑围堰,之后利用水泵将围堰范围内的河泊积水排干,将水排干之后再进行清淤施工,清淤常根据施工现场场地条件采用长臂式挖掘机开挖或人工开挖的方式沿河道两岸进行清淤。During the construction of the dry dredging method of the river channel, the river channel is divided into sections and the cofferdam is built, and then the water in the river bank within the cofferdam is drained by the pump. After the water is drained, the dredging construction is carried out. According to the site conditions of the construction site, dredging is carried out along both sides of the river by means of long-arm excavator or manual excavation.
采用河道干式清淤方法,一方面,施工过程中,需要对河道进行局部断流,适合两岸具有一定空间且便于断流施工的河道清淤;另一方面,河泊清淤彻底,易于控制清淤深度,污泥浓度高,运输成本低,因而工程成本相对较低。The dry dredging method of the river channel is adopted. On the one hand, during the construction process, the river channel needs to be partially cut off, which is suitable for the dredging of the river channel with a certain space on both sides and easy to cut off construction; on the other hand, the river dredging is thorough and easy to control. The dredging depth, the sludge concentration is high, and the transportation cost is low, so the engineering cost is relatively low.
附图说明Description of drawings
图1为河道干式清淤方法的流程示意图;Fig. 1 is the schematic flow sheet of the river course dry dredging method;
图2为围堰断面示意图。Figure 2 is a schematic cross-sectional view of the cofferdam.
具体实施方式Detailed ways
图1为根据本申请的一些实施例提供的一种河道干式清淤方法的流程示意图;如图1所示,该河道干式清淤方法包括:Fig. 1 is a schematic flow diagram of a dry dredging method for a river channel provided according to some embodiments of the present application; as shown in Fig. 1 , the dry dredging method for a river channel includes:
步骤S101、定位放线、测标高:根据施工设计对施工区域及施工红线进行放线,确定施工范围;对河道的水面标高进行测量放线,计算分段水量大小;对河道内淤泥顶标高进行复测,确定分段清淤量;Step S101, positioning and setting out, measuring the elevation: setting out the construction area and the construction red line according to the construction design, and determining the construction scope; measuring and setting out the water surface elevation of the river channel, and calculating the size of the water volume; Re-test to determine the amount of dredging in stages;
根据预先确定的坐标及高程,建立现场网点,确保高程和位置准确。具体的,根据建设设计提供的坐标及高程,用GPS和RTK建立现场控制网点,确保高程和位置准确,进一步的,在现场建立平面及高程控制系统,以在整个施工期间进行测量控制。According to the pre-determined coordinates and elevation, the site network is established to ensure accurate elevation and location. Specifically, according to the coordinates and elevations provided by the construction design, GPS and RTK are used to establish on-site control outlets to ensure accurate elevation and location. Further, a plane and elevation control system is established on-site to perform measurement control during the entire construction period.
其中,平面控制系统中,采用导线测量方法建立平面控制系统,采用GPS、RTK以及钢尺进行测量放线,设置直线控制桩。在此,控制桩的位置应稳定可靠,便于施工期间保护以及适用方便。高程控制系统中,测量仪器采用GPS和RTK,根据用户提供的水准点,将标高引至各临时水准点上,临时水准点必须坚固稳定,距离不得大于200米,且前后通视,临时水准点与设计水准点复测闭合。Among them, in the plane control system, the traverse measurement method is used to establish the plane control system, GPS, RTK and steel ruler are used to measure the line, and the straight line control pile is set. Here, the position of the control pile should be stable and reliable for easy protection during construction and convenient application. In the elevation control system, the surveying instrument adopts GPS and RTK. According to the benchmarking point provided by the user, the elevation is led to each temporary benchmarking point. The temporary benchmarking point must be firm and stable. Close the retest with the design benchmark.
步骤S102、场地清表、平整:根据规划红线和绿化施工蓝线,对场地进行清表、碾压平整至预设标准压实度;具体的,预设标准压实度不低于90%。Step S102, site clearing and leveling: according to the planning red line and the greening construction blue line, clearing the site, rolling and leveling it to a preset standard compaction degree; specifically, the preset standard compaction degree is not less than 90%.
在本申请实施例中,根据规划红线和绿化施工蓝线,为了不印象后期绿化施工,场地清表至红线,作为临时施工便道及围挡安装场地;对于无护坡结构、存在灌木及建筑垃圾段,通过开挖设备(比如:挖掘机)直接开挖清表,对绿植进行移栽或砍伐,提高施工效率。清表垃圾进行固定点堆放,后通过渣土车运至堆土场,破除的护坡结构浆砌石及建筑垃圾堆放,用于便道修筑。In the embodiment of this application, according to the planning red line and the greening construction blue line, in order not to impress the later greening construction, the site is cleared to the red line as a temporary construction access road and fence installation site; for the section without slope protection structure, shrubs and construction waste , through the excavation equipment (such as: excavator) to directly excavate the surface, transplant or cut down the green plants, and improve the construction efficiency. The surface-clearing garbage is piled up at fixed points, and then transported to the dumping site by muck trucks. The demolished slope protection structure mortar masonry and construction waste are piled up for road construction.
步骤S103、场地硬化、临时便道施工:对空场地、道路采用混凝土硬化,埋设排水管,其中,硬化道路坡向河道,坡度为2%;具体的,对空场地、道路采用C15混凝土硬化,道路厚度均为25厘米,且每间隔20米埋设一根直径为150毫米的PC排水管。Step S103, site hardening, temporary access road construction: concrete hardening is used for the empty site and road, and drainage pipes are buried, wherein the hardened road slopes toward the river, and the slope is 2%; The thickness is 25 cm, and a PC drain pipe with a diameter of 150 mm is buried every 20 meters.
在河道绿化带外1米修筑施工便道,并硬化,其中,硬化道路宽4.5米,长240米,并选择其中部分硬化便道作为安全体验区,在安全体验区外侧设置排水沟,连通河道。A construction access road is built 1 meter outside the river green belt and hardened. Among them, the hardened road is 4.5 meters wide and 240 meters long, and some of the hardened access roads are selected as the safety experience area, and a drainage ditch is set outside the safety experience area to connect the river.
步骤S104、围堰施工:根据河道长度将围堰位置在两岸进行放样,自岸边起始,单项合拢,分层填筑,分层碾压;其中,围堰迎水面边坡坡度为1:2;围堰背水面边坡坡度为1:1.5;Step S104, cofferdam construction: stake out the cofferdam position on both banks according to the length of the river channel, start from the bank, close the individual items, fill in layers, and roll in layers; wherein, the slope of the cofferdam upstream side slope is 1: 2; The slope of the backwater surface of the cofferdam is 1:1.5;
图2为本申请提供的围堰断面示意图;如图2所示,围堰填筑材料以粘性土为主,围堰顶宽3米,围堰顶面高出河道水面50厘米。围堰迎水面一侧 的坡度小于围堰背水面一侧的坡度,籍此,能够更好的实现围堰阻水效果。围堰填筑过程中出水面遵循分层填筑、分层碾压的原则,且压实度不低于90%。籍此,充分保证围堰施工效果,提高围堰施工安全。Figure 2 is a schematic cross-sectional view of the cofferdam provided by the application; as shown in Figure 2, the cofferdam filling material is mainly clay, the top of the cofferdam is 3 meters wide, and the top surface of the cofferdam is 50 cm higher than the water surface of the river. The slope on the upstream side of the cofferdam is smaller than that on the downstream side of the cofferdam, which can better achieve the water blocking effect of the cofferdam. During the cofferdam filling process, the water outlet surface shall follow the principle of layered filling and layered rolling, and the compaction degree shall not be lower than 90%. In this way, the construction effect of the cofferdam can be fully guaranteed and the construction safety of the cofferdam can be improved.
步骤S105、抽水:根据水面和河底标高,计算总的抽水体积,并将水周抽入下游河段;具体的,根据计算的抽水体积,确定抽水水泵的数量型号。Step S105, pumping: according to the water surface and river bottom elevation, calculate the total pumping volume, and pump the water circle into the downstream reaches; specifically, determine the number and model of the pumping pumps according to the calculated pumping volume.
对每一段,测定水面和河底标高,算出总的抽水体积。由于每个断面标高不同,结合纵断面、横断面和平面图进行计算。根据河水体积选取水泵的数量型号(比如:150m 3/h,1500w),并根据选取的水泵的型号进行发电机临时配电。 For each section, the water surface and river bottom elevations were measured, and the total pumped volume was calculated. Since the elevation of each section is different, the calculation is carried out in combination with the longitudinal section, the transverse section and the plan view. Select the number and model of the water pump according to the volume of the river water (for example: 150m 3 /h, 1500w), and perform temporary power distribution of the generator according to the selected model of the water pump.
由于现场施工用电量不大,且大额度用电时间段较短(水泵抽水耗电量较大),施工线路较长,因而采用临时发电机供电。而且,由于现场前期用水量较少,用水量多为后期河道岸带修复和绿化用水,因而在河道清淤段不需要引入市政用水。Due to the small electricity consumption in the construction site, the short period of time for large-scale electricity consumption (the water pumping consumes a large amount of electricity), and the construction line is long, a temporary generator is used for power supply. Moreover, since the water consumption in the early stage of the site is relatively small, and the water consumption is mostly used for river bank restoration and greening in the later stage, there is no need to introduce municipal water in the dredging section of the river.
步骤S106、淤泥开挖、外运:每一分段在河道淤泥外边两侧各开挖一条纵向排水沟,使积水归槽,水泵抽水;分段开挖淤泥至河岸堆放晾晒,直至淤泥晾晒至固体,进行开挖装车外运;其中,河床底清淤后按预设要求进行整平。Step S106, silt excavation and outbound transportation: excavate a longitudinal drainage ditch on each side of the outer side of the river silt in each section, so that the accumulated water returns to the tank, and the water pump pumps water; To solid, carry out excavation, loading and transportation; among them, the bottom of the river bed is leveled according to preset requirements after dredging.
每一分段在河道淤泥外边两侧开挖的排水沟的宽度为1米,深度为0.5米,籍此,便于河道内的积水归槽,通过水泵将积水抽取全部积水。The width of the drainage ditches excavated on both sides of the river silt in each subsection is 1 meter wide and 0.5 meters deep, so that the accumulated water in the river channel can be returned to the trough, and all the accumulated water can be pumped out by the water pump.
开挖淤泥时采用分段开挖,先在河岸修筑好开挖设备的上下通道,通道坡度不大于1:3,淤泥上机械施工采用钢板护底,以防止开挖机械陷入淤泥,开挖机械每前进一段,均提前铺好道路。河床底在清淤完成后按要求进行整平。When excavating the silt, use segmented excavation. First, build the upper and lower passages of the excavation equipment on the river bank. The slope of the passage is not greater than 1:3. The mechanical construction on the silt uses steel plate bottom protection to prevent the excavation machinery from sinking into the silt. Every time you move forward, the road is paved in advance. The bottom of the river bed shall be leveled as required after the dredging is completed.
淤泥开挖至河岸进行堆放晾晒,堆放高度不大于1.5米,籍此,以避免淤泥再次流入河道内。当淤泥晾晒至固体时,进行开挖装车外运。运送过程中,采取措施防止出现“滴、撒、漏”等现象;运送车辆在内运货外运过程中按指定线路行驶。The silt is excavated to the river bank for stacking and drying, and the stacking height is not more than 1.5 meters, so as to prevent the silt from flowing into the river again. When the sludge is dried to solid, it will be excavated and loaded into trucks for transportation. During the transportation process, measures shall be taken to prevent the occurrence of "drops, spills, leaks" and other phenomena; the transportation vehicles shall travel according to the designated route during the process of inward and outward transportation.
河道筑围堰,分段进行施工,将围堰段内河道积水全部抽干,然后用挖机清除河道底淤泥,淤泥临时堆放至岸边,晾晒5~7天后使用渣土车外运至弃土场。整个过程,河道清淤分段进行,前期准备与后期施工同时进行,施 工过程高效快速。Build cofferdams in the river, and carry out construction in sections, drain all the water in the cofferdam section, and then remove the silt at the bottom of the river with excavators. Wasteland. In the whole process, the river dredging is carried out in stages, the preliminary preparation and the later construction are carried out at the same time, and the construction process is efficient and fast.
在施工前,首先根据施工设计对施工区域及施工红线进行放线,确定施工范围;对河道的水面标高进行测量放线,计算分段水量大小;对河道内淤泥顶标高进行复测,确定分段清淤量,实现施工前的定位放线、测标高的准备工作;施工过程中,在根据规划红线和绿化施工蓝线,对场地进行清表、碾压整平至预设标准压实度后,对空场地、道路采用混凝土硬化,实现场地的清表、整平和硬化,为围堰施工和清淤做好准备;然后,根据河道场地将围堰位置在河道两岸进行放样,自岸边起始,单项合拢,分层填筑,分层碾压,完成围堰施工;进而,对围堰迎水面的阻水进行抽水作业,将其抽入下游河段,以便对河床底进行清淤;最后,分段开挖淤泥至河岸堆放晾晒,直至淤泥晾晒至固体,进行开挖装车外运,实现河道的完全清淤工作。整个过程,河道清淤分段进行,前期准备与后期施工同时进行,施工过程高效快速,既保证了河道清淤工程的顺畅,又保证了对周边的影响降至最小。Before construction, first set out the construction area and construction red line according to the construction design to determine the construction scope; measure and set out the water surface elevation of the river channel to calculate the size of the water volume; re-measure the elevation of the silt roof in the channel to determine the subsection During the construction process, according to the planning red line and green construction blue line, the site is cleared, rolled and leveled to the preset standard compaction degree Then, use concrete to harden the empty site and road to realize the surface cleaning, leveling and hardening of the site, so as to prepare for the construction of the cofferdam and dredging; At the beginning, the single items are closed, filled in layers, and rolled in layers to complete the construction of the cofferdam; then, the water blocking operation on the upstream surface of the cofferdam is pumped, and it is pumped into the downstream river section for dredging the bottom of the river bed. ; Finally, excavate the silt in sections and stack it on the river bank for drying, until the silt is dried to solid, and then excavate, load, and transport to achieve complete dredging of the river. In the whole process, the river dredging is carried out in sections, and the preliminary preparation and the later construction are carried out at the same time. The construction process is efficient and fast, which not only ensures the smoothness of the river dredging project, but also ensures that the impact on the surrounding area is minimized.
河道干式清淤施工方法在施工时,将河道进行分段并修筑围堰,之后利用水泵将围堰范围内的河泊积水排干,将水排干之后再进行清淤施工,清淤常根据施工现场场地条件采用长臂式挖掘机开挖或人工开挖的方式沿河道两岸进行清淤。During construction, the river channel is divided into sections and cofferdams are built, and then the water in the river banks within the cofferdam is drained by pumps. After the water is drained, the dredging construction is carried out. According to the construction site conditions, long-arm excavators or manual excavation are often used to dredging along both sides of the river.
河道干式清淤施工方法,一方面,施工过程中,需要对河道进行局部断流,适合两岸具有一定空间且便于断流施工的河道清淤;另一方面,河泊清淤彻底,易于控制清淤深度,污泥浓度高,运输成本低,因而工程成本相对较低。The dry dredging construction method of the river channel, on the one hand, during the construction process, it is necessary to partially cut off the river channel, which is suitable for the dredging of the river channel with a certain space on both sides and easy to cut off construction; on the other hand, the river dredging is thorough and easy to control. The dredging depth, the sludge concentration is high, and the transportation cost is low, so the engineering cost is relatively low.

Claims (10)

  1. 一种河道干式清淤方法,其特征在于,包括:A dry dredging method for a river course, comprising:
    步骤S101、定位放线、测标高:根据施工设计对施工区域及施工红线进行放线,确定施工范围;对河道的水面标高进行测量放线,计算分段水量大小;对河道内淤泥顶标高进行复测,确定分段清淤量;Step S101, positioning and setting out, measuring the elevation: setting out the construction area and the construction red line according to the construction design, and determining the construction scope; measuring and setting out the water surface elevation of the river channel, and calculating the size of the water volume; Re-test to determine the amount of dredging in stages;
    步骤S102、场地清表、平整:根据规划红线和绿化施工蓝线,对场地进行清表、碾压平整至预设标准压实度;Step S102, clearing and leveling the site: according to the planning red line and the greening construction blue line, clearing the site, rolling and leveling it to a preset standard compaction degree;
    步骤S103、场地硬化、临时便道施工:对空场地、道路采用混凝土硬化,埋设排水管,其中,硬化道路坡向河道,坡度为2%;Step S103, site hardening, temporary access road construction: use concrete to harden the empty site and road, and bury the drainage pipe, wherein the hardened road slopes toward the river, and the slope is 2%;
    步骤S104、围堰施工:根据河道长度将围堰位置在两岸进行放样,自岸边起始,单向合拢,分层填筑,分层碾压;其中,围堰迎水面边坡坡度为1:2;围堰背水面边坡坡度为1:1.5;Step S104, cofferdam construction: stake out the position of the cofferdam on both banks according to the length of the river channel, start from the bank, close in one direction, fill in layers, and roll in layers; wherein, the slope of the cofferdam upstream side slope is 1 : 2; the slope of the backwater surface of the cofferdam is 1:1.5;
    步骤S105、抽水:根据水面和河底标高,计算总的抽水体积,并将水抽入下游河段;Step S105, pumping water: calculating the total pumping volume according to the water surface and the elevation of the river bottom, and pumping the water into the downstream reaches;
    步骤S106、淤泥开挖、外运:每一分段在河道淤泥外边两侧各开挖一条纵向排水沟,使积水归槽,水泵抽水;分段开挖淤泥至河岸堆放晾晒,直至淤泥晾晒至固体,进行开挖装车外运;其中,河床底清淤后按预设要求进行整平。Step S106, silt excavation and outbound transportation: excavate a longitudinal drainage ditch on each side of the outer side of the river silt in each section, so that the accumulated water returns to the tank, and the water pump pumps water; To solid, carry out excavation, loading and transportation; among them, the bottom of the river bed is leveled according to preset requirements after dredging.
  2. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S101中,根据预先确定的坐标及高程,建立现场网点,确保高程和位置准确。The dry dredging method for a river channel according to claim 1, characterized in that, in step S101, an on-site network point is established according to predetermined coordinates and elevations to ensure accurate elevation and location.
  3. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S101中,采用导线测量方法建立平面控制系统,采用GPS、RTK及钢尺进行测量放线。The method for dry dredging of a river channel according to claim 1, characterized in that, in step S101, a plane control system is established by using a wire measurement method, and GPS, RTK and steel ruler are used to measure and pay out the line.
  4. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S102中,预设标准压实度不低于90%。The dry dredging method for a river channel according to claim 1, wherein in step S102, the preset standard compaction degree is not less than 90%.
  5. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S103中,对空场地、道路采用C15混凝土硬化,道路厚度均为25厘米,且每间隔30米埋设一根直径为150毫米的PC排水管。The method for dry dredging of a river channel according to claim 1, characterized in that, in step S103, C15 concrete is used to harden the empty site and road, the thickness of the road is 25 cm, and every 30 meters is buried with a diameter of 150mm PC drain.
  6. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S104中,围堰填筑材料为粘性土,围堰顶宽3米,围堰顶面高出河道水面50厘米。The method for dry dredging of a river course according to claim 1, wherein in step S104, the cofferdam filling material is clay soil, the top of the cofferdam is 3 meters wide, and the top surface of the cofferdam is 50 cm higher than the water surface of the river.
  7. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S105中,根据计算的抽水体积,确定抽水水泵的数量型号。The dry dredging method for a river channel according to claim 1, characterized in that, in step S105, the quantity and model of the pumping water pumps are determined according to the calculated pumping volume.
  8. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S106中,排水沟的宽度为1米,深度为0.5米。The dry dredging method for a river channel according to claim 1, wherein in step S106, the width of the drainage ditch is 1 meter and the depth is 0.5 meters.
  9. 根据权利要求1所述的河道干式清淤方法,其特征在于,在步骤S106中,在分段开挖淤泥前,沿河道的河岸修筑坡度不大于1:3的开挖设备通道,并采用钢板护底。The method for dry dredging of a river channel according to claim 1, wherein in step S106, before the silt is excavated in sections, an excavation equipment channel with a slope of not more than 1:3 is built along the bank of the river channel, and Use steel plate bottom protection.
  10. 根据权利要求1-9任一所述的河道干式清淤方法,其特征在于,在步骤S106中,淤泥在河岸的堆放高度不大于1.5米。The dry dredging method for a river channel according to any one of claims 1-9, characterized in that, in step S106, the stacking height of silt on the river bank is not greater than 1.5 meters.
PCT/CN2021/104828 2021-06-18 2021-07-06 Dry desilting method for riverway WO2022095494A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110680949.0A CN113250266A (en) 2021-06-18 2021-06-18 Dry-type dredging method for river channel
CN202110680949.0 2021-06-18

Publications (1)

Publication Number Publication Date
WO2022095494A1 true WO2022095494A1 (en) 2022-05-12

Family

ID=77188633

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/104828 WO2022095494A1 (en) 2021-06-18 2021-07-06 Dry desilting method for riverway

Country Status (3)

Country Link
CN (1) CN113250266A (en)
LU (1) LU503303B1 (en)
WO (1) WO2022095494A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638355B (en) * 2021-08-20 2022-07-15 福建省红日水利水电工程有限公司 Intelligent construction method for water conservancy river regulation engineering
CN114150612B (en) * 2021-11-17 2023-05-02 中交水利水电建设有限公司 Construction method suitable for small river channel topology and excavation
CN114892749B (en) * 2022-05-17 2023-02-07 河海大学 Treatment method of black and odorous river channel

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005005736A2 (en) * 2003-07-04 2005-01-20 Saipem S.P.A. Trenching apparatus and method
CN103422466A (en) * 2013-07-31 2013-12-04 张家港市绿岩生态技术有限公司 Black and odorous river regulating and recovering method
CN106380042A (en) * 2016-09-23 2017-02-08 浙江水利水电学院 Circulating water purification system and method applicable to lakes
WO2017159692A1 (en) * 2016-03-18 2017-09-21 正佳 近藤 Vacuum consolidation and dredging method, tower-like airtight preloading caisson, and dedicated work ship
CN108611932A (en) * 2018-05-15 2018-10-02 中铁第六勘察设计院集团有限公司 It is a kind of pass through pool, fish pond location multiply road railway high-fill roadbed construction method
CN109056761A (en) * 2018-08-17 2018-12-21 上海宝冶集团有限公司 Channel cleanout method
CN110804993A (en) * 2019-11-26 2020-02-18 深圳市东深工程有限公司 River regulation construction method
CN111908748A (en) * 2020-08-03 2020-11-10 中建水务环保有限公司 River channel dredging method
CN111997157A (en) * 2020-08-18 2020-11-27 深圳市利源水务设计咨询有限公司 Black-eliminating and deodorizing construction method for hidden culverts in urban dense areas

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103031836B (en) * 2013-01-08 2016-03-09 中交四航工程研究院有限公司 A kind of method of building road on new hydraulically filled sludge ground fast
CN104358188B (en) * 2014-11-20 2017-01-18 中铁八局集团有限公司 Filling construction method for collapsible loess subgrade
CN109354376B (en) * 2018-11-15 2021-04-09 泉州师范学院 Daily maintainability dredging method for sediment of medium and small water bodies
CN112681350A (en) * 2020-12-16 2021-04-20 中国二冶集团有限公司 River cofferdam diversion construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005005736A2 (en) * 2003-07-04 2005-01-20 Saipem S.P.A. Trenching apparatus and method
CN103422466A (en) * 2013-07-31 2013-12-04 张家港市绿岩生态技术有限公司 Black and odorous river regulating and recovering method
WO2017159692A1 (en) * 2016-03-18 2017-09-21 正佳 近藤 Vacuum consolidation and dredging method, tower-like airtight preloading caisson, and dedicated work ship
CN106380042A (en) * 2016-09-23 2017-02-08 浙江水利水电学院 Circulating water purification system and method applicable to lakes
CN108611932A (en) * 2018-05-15 2018-10-02 中铁第六勘察设计院集团有限公司 It is a kind of pass through pool, fish pond location multiply road railway high-fill roadbed construction method
CN109056761A (en) * 2018-08-17 2018-12-21 上海宝冶集团有限公司 Channel cleanout method
CN110804993A (en) * 2019-11-26 2020-02-18 深圳市东深工程有限公司 River regulation construction method
CN111908748A (en) * 2020-08-03 2020-11-10 中建水务环保有限公司 River channel dredging method
CN111997157A (en) * 2020-08-18 2020-11-27 深圳市利源水务设计咨询有限公司 Black-eliminating and deodorizing construction method for hidden culverts in urban dense areas

Also Published As

Publication number Publication date
LU503303A1 (en) 2023-01-10
CN113250266A (en) 2021-08-13
LU503303B1 (en) 2023-05-12

Similar Documents

Publication Publication Date Title
WO2022095494A1 (en) Dry desilting method for riverway
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN107938692A (en) A kind of draining and recharge construction method and structure
CN106049379B (en) Temporary power generation method during construction lag of downstream of spillway and rockfill self-breaking dam
CN106930231A (en) A kind of construction method of the engineering flood bank reinforcing that is applied to pass the flood period
CN109208545B (en) Construction method of artificial landscape overflow dam with energy dissipation effect
CN110656621A (en) River channel closure system structure and construction method
CN114718101A (en) Seepage interception structure of tailing pond of seepage interception wall combined dewatering well and construction method thereof
CN111962459A (en) Urban debris flow channel type comprehensive treatment system for abandoned slag yard and construction method thereof
CN109083100B (en) River channel excavation construction process after mud blowing and landing
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN219080361U (en) Mountain-side abrupt slope terrain channel structure
CN201778330U (en) Clay waterproof curtain wall
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN102704437A (en) Coal mining subsidence area cultivation water source reconstruction method suitable for complex mountain area
CN206220172U (en) Tubular type diversion pumping plant
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit
CN114134920A (en) Post-cast strip advanced sealing construction method
CN114319545A (en) High-impermeability concrete drainage ditch system and construction method thereof
CN113700111A (en) Construction method of rainwater permeation, drainage and reuse integrated system
CN111827198A (en) Construction method for central control water replacement and filling in tidal lake water environment ecological restoration
CN209025095U (en) A kind of caisson structure
CN113250265A (en) River channel half-dry type dredging method
CN209293018U (en) Lead wall method bored pile construction structure
CN220868277U (en) Earth-rock dam preloading structure suitable for sand gravel foundation

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21888196

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21888196

Country of ref document: EP

Kind code of ref document: A1