WO2021196451A1 - Deep cable-anchored pile supporting system and construction method therefor - Google Patents

Deep cable-anchored pile supporting system and construction method therefor Download PDF

Info

Publication number
WO2021196451A1
WO2021196451A1 PCT/CN2020/102446 CN2020102446W WO2021196451A1 WO 2021196451 A1 WO2021196451 A1 WO 2021196451A1 CN 2020102446 W CN2020102446 W CN 2020102446W WO 2021196451 A1 WO2021196451 A1 WO 2021196451A1
Authority
WO
WIPO (PCT)
Prior art keywords
anchor
anchor cable
pile
cable
piles
Prior art date
Application number
PCT/CN2020/102446
Other languages
French (fr)
Chinese (zh)
Inventor
刘飞
刘小波
王涛
李仁民
王建兰
Original Assignee
江苏东合南岩土科技股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 江苏东合南岩土科技股份有限公司 filed Critical 江苏东合南岩土科技股份有限公司
Publication of WO2021196451A1 publication Critical patent/WO2021196451A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/54Piles with prefabricated supports or anchoring parts; Anchoring piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Definitions

  • the invention relates to a deep anchor pile supporting system and a construction method thereof.
  • foundation pit engineering has become an important part of construction engineering, municipal engineering and rail transit engineering. Due to the increasing density of buildings in the city, traffic congestion, narrow sites, and poor geological conditions, it is very common for deep foundation pits to be adjacent to existing buildings, which limits the choice of deep foundation pit support types.
  • the supporting structure of pile plus internal support and the supporting structure of pile wall plus internal support can effectively control deformation, but it is inconvenient to excavate soil, high cost and long construction period. Supporting structures such as piles and anchors are convenient for excavation, low cost, and convenient for construction. However, because of the restrictions on the red lines of anchors in many places, they are not allowed to be used.
  • Ground horizontal anchor pile refers to the construction of anchor piles in the soil stability area at a certain distance from the outside of the foundation pit. Crown-beam connection, the other end is connected with the crown-beam on the anchor pile, a certain prestress is applied to the tie rod through the connecting fastener, and a part of the earth pressure of the soil in the upper part of the foundation pit acting on the supporting pile is transmitted to the anchor pile A type of supporting structure. It has the advantages of low cost, simple operation, flexible use, and less construction clearance. However, because horizontal anchor piles can only be set on shallow foundations, and only one layer can be set, the horizontal pulling force provided by the anchor piles is not large, which will cause greater deformation.
  • the present invention first proposes a deep anchor pile support system, which includes a plurality of inner row piles arranged along a first set direction, at least one of the inner row piles is formed as an anchor pile, corresponding to Each anchor pile is provided with an anchor pile, and the anchor pile is arranged on the side of the corresponding anchor pile away from the foundation pit;
  • a group of anchor cables A is arranged between each anchor pile and the corresponding anchor pile.
  • Each group of anchor cables A includes a first anchor cable A and a second anchor cable A.
  • the first anchor cable A and the second anchor cable A are both pre-stressed anchor cables; the two ends of each first anchor cable A are called the first front end A and the first rear end A respectively, and the two ends of each second anchor cable A are called respectively Is the second front end A and the second rear end A;
  • An inner row of anchor rope purlins A is provided on the inner side of the inner row of piles; an outer row of anchor rope purlins is provided on the outer side of the top of the anchor piles;
  • the first front end A of the first anchor cable A passes through the corresponding anchor cable pile and is connected to the inner row of anchor cable purlins A, and the first rear end A of the first anchor cable A extends upward in the oblique direction and passes through the The corresponding anchor piles are then connected to the outer row of anchor rope purlins;
  • the second front end A of the second anchor cable A passes through the corresponding anchor cable pile and then is connected to the inner row of anchor cable purlins A, and the second rear end A of the second anchor cable A extends downward in the oblique direction and is connected To the corresponding anchor pile.
  • the anchor piles are arranged in the vertical direction or in the inclined direction.
  • the anchor piles are inclined from bottom to top toward the side away from the foundation pit, or from bottom to top toward the inner direction of the foundation pit.
  • the angle between the anchor pile and the vertical is 5-30°.
  • a first anchor cable A and a second anchor cable A are provided.
  • the first anchor cable A and the second anchor cable A are respectively upward and downward in the inclined direction. Extend downward to form two-way tension on the anchor pile. While generating a horizontal pulling force toward the outside of the foundation pit, it can also produce upward and downward pulling forces on the anchor pile.
  • the horizontal pulling force can produce resistance to the anchor cable pile towards the outside. Under the conduction of the inner row of anchor rope purlin A, the resistance can be transmitted to other inner rows that are not connected with anchor cables, so that all the inner rows are The rows of piles form a pulling force towards the external force. The upward and downward pulling forces will be at least partially cancelled.
  • the two-way stretching in this application will at least reduce the upward lifting force on the anchor cable pile, so that the anchor cable pile It can be held in the soil more stably, and because it reduces the upward lifting force of the anchor piles, the depth of the anchor piles and all the inner rows of piles below the bottom of the foundation pit can be reduced, thereby reducing the anchor piles and all the inner rows.
  • the length of the piles reduces the construction cost, and because the length of the inner row of piles is reduced, the sinking time of the inner row of piles can also be reduced, and the construction efficiency is improved.
  • both ends of the first anchor cable A and the second anchor cable A are fixed to the anchor pile force, the construction area can be reduced, especially when the foundation pit construction is carried out around the existing building, due to the limited construction scope, It is also impossible to construct the jet-grouted pile anchor cable on the side wall of the foundation pit, and only large-diameter filling piles can be used as the foundation pit support system around the foundation pit, which not only has high construction costs, but also has a long construction period.
  • the deep anchor pile support system in the present application can effectively solve this problem, and can be constructed within a smaller red line range.
  • the angle between the first anchor cable A and the horizontal plane is 15-30°
  • the angle between the first anchor cable A and the second anchor cable A is 50-120°
  • the angle between the first anchor cable A and the horizontal plane is 50-120°.
  • the angle between the first anchor cable A and the horizontal plane is smaller than the angle between the second anchor cable A and the horizontal plane.
  • This design can make the inner row of anchor rope purlin A close to the top of the inner row of piles to the greatest extent, reduce the unsupported distance of the upper part of the inner row of piles, and at the same time make the connection point of the second anchor rope A and the anchor pile more towards the anchor pile The bottom of the pile.
  • this design can make the second anchor cable A generate a downward force greater than the upward force generated by the first anchor cable A. The force is divided to form a downward pressure on the anchor pile.
  • the inner row of anchor cable purlins A is formed by two rows of section steels, both of which extend in the horizontal direction and are arranged side by side at intervals in the vertical direction.
  • the first front end A of the first anchor cable A and the second anchor The second front end A of the cable A passes through the vertical gap between the two rows of section steels and then is fixed on the inner row of anchor cable purlins A.
  • the structure of the inner row anchor rope purlin A can facilitate the insertion of the first anchor rope A and the second anchor rope A, avoiding the first anchor rope A and the second anchor rope A on the inner row anchor rope purlin A
  • the hole A passes through can maintain the integrity of the inner row of anchor ropes surrounding purlin A.
  • At least one inner row of anchor rope purlins B is also arranged on the inner side of the inner row of piles, corresponding to each inner row of anchor rope purlins B, and a set of anchor piles is provided between each anchor pile and the corresponding anchor pile.
  • Anchor B The two ends of the anchor cable B are called the first front end B and the first rear end B respectively, and the two ends of each second anchor cable B are called the second front end B and the second rear end B respectively;
  • the first front end B of the first anchor cable B penetrates the corresponding anchor cable pile and then is connected to the corresponding inner row of anchor cable purlins B, and the first rear end B of the first anchor cable B extends upward in the oblique direction And connect to the corresponding anchor pile;
  • the second front end B of the second anchor cable B penetrates the corresponding anchor cable pile and then is connected to the corresponding inner row anchor cable purlin B, and the second rear end B of the second anchor cable B is downward in the inclined direction Extend and connect to the corresponding anchor pile.
  • one or more inner row anchor rope purlins B can be set.
  • first anchor ropes B and second anchor ropes B are first anchor ropes B and second anchor ropes B. Because the first anchor rope B and the second anchor cable B extend upward and downward respectively, so that the first anchor cable B and the second anchor cable B partially offset the force produced by the anchor pile and the anchor pile in the vertical direction, reducing the impact on the anchor pile or the anchor pile. The upward lifting force of the anchor pile can keep the anchor pile or anchor pile stably in place.
  • the included angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B is 50-130°, and the first anchor cable The angle between B and the horizontal plane is 20-45°.
  • the included angle between the first anchor cable B and the horizontal plane in the same group of anchor cables B is smaller than the included angle between the second anchor cable B and the horizontal plane, so as to form a net downward force to press down the anchor cable pile.
  • each second anchor cable C is arranged between each anchor rope pile and the corresponding anchor pile.
  • the two ends of each second anchor cable C are respectively called the second front end C and the second rear end C;
  • the second anchor cable C is a prestressed anchor cable;
  • the second front end C of the second anchor cable C penetrates through the corresponding anchor cable pile and then is connected to the inner row of anchor cable purlins C, and the second rear end C of the second anchor cable C extends downward in the oblique direction and is connected To the corresponding anchor pile;
  • the inner row of anchor rope purlin C is located above the inner row of anchor rope purlin A.
  • first anchor cable A Due to the inclined arrangement of the first anchor cable A, there is a certain distance between the position of the inner row of anchor cable purlin A and the ground, so that the top of the inner row of piles may bend into the foundation pit, in order to avoid the top of the inner row of piles Under the external pressure, it bends towards the inner side of the foundation pit, and an inner row of anchor rope enclosing purlin C is added above the inner row of anchor rope enclosing purlin A, and a corresponding second anchor rope C is set.
  • the piles are connected to the anchor piles in an inclined direction. After ensuring stable support on the top of the inner row of piles, it also provides downward pressure for the anchor piles.
  • the anchor piles remain in the soil as a whole, they The body has greater anti-floating ability, so after adding the inner row of anchor cable purlin C and the corresponding second anchor cable C, the friction between the anchor pile and the soil can be fully utilized, and the second anchor can pass through The cable C transfers the friction to the inner row of piles, while avoiding the outward bending of the top of the inner row of piles, it also exerts downward pressure on the anchor piles, so that the anchor piles can be stably maintained at the set position. .
  • the inner row of piles is at least one of H steel piles, steel sheet piles, combined steel sheet piles, steel tube piles or precast concrete piles
  • the anchor piles are H steel piles, steel sheet piles, combined steel sheet piles, and steel tube piles. Or at least one of precast concrete piles.
  • the above-mentioned various types of piles can be used to better realize the application, so as to make full use of the existing various prefabricated piles.
  • the elevation of the bottom of the anchor pile is lower than the elevation of the bottom of the anchor pile.
  • the anchor pile When the elevation of the bottom of the anchor pile is lower than that of the anchor pile, since the elevation of the bottom of the anchor pile and the anchor pile is lower than the set elevation of the bottom of the foundation pit, the anchor pile can be obtained in the soil. The stable state provides sufficient pulling force for the anchor pile.
  • the net distance between the anchor pile and the corresponding anchor pile is 1-10 meters, more preferably 3-8 meters. It is possible to make the anchor pile and the anchor pile have a sufficient thickness of soil to ensure that the soil can form a stable pressure and binding force on the anchor pile, avoid the soil between the anchor pile and the anchor pile from being too thin, and Due to the slight deviation of the soil to the inner side of the foundation pit, the friction between the anchor pile and the soil is reduced.
  • the net distance between the anchor pile and the corresponding anchor pile refers to the net distance between the anchor pile and the intersection of the anchor pile and the plane where the ground is located.
  • the present invention also provides a construction method of a deep anchored pile support system, which is used to construct the deep anchored pile support system in the above solution, which includes the following steps:
  • the inner row of anchor holes is formed at the set position of the inner row of piles as the anchor pile, and the outer row of anchor holes is formed at the set position of the anchor pile;
  • the anchor cable A After passing the second rear end A of the first anchor cable A freely through the corresponding outer row anchor cable holes on the anchor piles and the corresponding surrounding purlin anchor cable holes on the outer row anchor cable purlins, The anchor cable A is stretched to cause the first anchor cable A to generate internal stress and form a pre-stressed anchor cable; fix the first front end A of the first anchor cable A on the inner row of anchor cable purlins A, and fix the first The first rear end A of the anchor cable A is fixed on the outer row of anchor cable purlins;
  • the tensioning of the first anchor cable A and the second anchor cable A is performed synchronously or step by step;
  • the first anchor cable A and the second anchor cable A can be tensioned in the foundation pit, so that the first anchor cable A and the second anchor cable A form a pre-stressed anchor cable, especially the second anchor cable
  • the cable A is formed as a pre-stressed anchor cable.
  • the two ends of the second anchor cable A are pre-arranged into the soil by using anchor cable piles and anchor piles, and then the second anchor cable A is stretched in the foundation pit to form a pre-stressed anchor cable.
  • the soil around the foundation pit is often used in the form of mixing piles with the excavation of the foundation pit.
  • the concrete construction is canceled, and both the first anchor cable A and the second anchor cable A can be fixed on the anchor piles to provide a reaction force for the tension of the first anchor cable A and the second anchor cable A to ensure Formation of prestressed anchor cables. Due to the cancellation of the concrete construction, after the formation of the prestressed anchor cable, the foundation pit can be continuously excavated, which can effectively improve the excavation efficiency of the foundation pit.
  • a tension groove is first opened on the path through which the first anchor cable A and the second anchor cable A pass, so that the first anchor cable A and the second anchor cable A
  • the second anchor cables A are all arranged in the tension groove.
  • the first anchor cable A and the second anchor cable A When the first anchor cable A and the second anchor cable A are stretched, the first anchor cable A and the second anchor cable A need to cut the soil to reach the set position, and the tension is tight. Hard areas or large debris in the soil will hinder the cutting of the soil by the first anchor cable A and the second anchor cable A, and sometimes cause damage to the first anchor cable A and the second anchor cable A. destroy.
  • the tension slot is first opened, so that the first anchor cable A and the second anchor cable A can reach the set position through the tension slot smoothly, avoiding the above situation happened.
  • the anchor cable can be set in a deep layer with good soil quality to provide a relatively large anchor tension and effectively control the deformation of the supporting structure.
  • the upper and lower component forces can be offset, which can reduce the risk of anchor piles floating up and supporting piles sinking.
  • the application of prestress is completed during the shallow excavation of the foundation pit, and it can be directly excavated to the end in the later stage, and the construction speed is fast; and the prestress of each layer of anchor cables can be adjusted during the construction process, and the deformation control effect is good.
  • the environmental impact is small.
  • This application is suitable for a variety of stratum conditions, from soft soil to medium-hard stratum, gravel layer, various soft and hard weathered rock layers, etc. can be used.
  • This application occupies less land, no internal support, pre-stressed anchor cables do not require grouting, fast construction, can effectively limit lateral deformation, supporting structures including inner row piles, anchor piles and anchor cables can be recycled and are economical Advantages such as significant benefits.
  • FIG. 1 is a schematic diagram of the structure of Embodiment 1 of the present invention.
  • Fig. 2 is a plan view of Fig. 1.
  • Fig. 3 is a schematic diagram of the structure of Embodiment 2 of the present invention.
  • Fig. 4 is a top view of Fig. 3.
  • Fig. 5 is a schematic structural diagram of Embodiment 3 of the present invention.
  • Fig. 6 is a plan view of Fig. 5.
  • Fig. 7 is a schematic diagram of a first anchor pile with an anchor cable installed.
  • Figure 8 is a schematic diagram of the first anchor pile after the completion of sinking.
  • Fig. 9 is a schematic diagram of the sinking process of the first anchor pile with the anchor cable installed.
  • Figure 10 is a schematic diagram of connecting the anchor rope to the first outer row of anchor rope purlins.
  • Figure 11 is a schematic diagram after the anchor cable is tensioned.
  • Figure 12 is a schematic diagram after the excavation of the foundation pit is completed.
  • Figure 13 is a schematic view of the opening of the first anchor pile.
  • Fig. 14 is a schematic diagram of the first anchor cable pile with an anchor cable passing through it.
  • FIG. 15 is a schematic diagram of the structure of Embodiment 4 of the present invention.
  • Fig. 16 is a cross-sectional view taken along the line D-D in Fig. 15.
  • FIG. 17 is a schematic diagram of the structure of Embodiment 5 of the present invention.
  • the direction toward the center of the foundation pit is called the inner side
  • the direction opposite to the inner side is called the outer side
  • the first deep anchor pile support system which includes a plurality of first inner row piles 11 arranged along a first set direction, part of the first inner row piles are formed as first anchor cables
  • the pile 111 is provided with a first anchor pile 121 corresponding to each first anchor pile 111, and the first anchor pile 121 is arranged on the side of the corresponding first anchor pile 111 away from the first foundation pit 130.
  • first inner row of piles 11 On the inner side of the first inner row of piles 11 is provided a first inner row of anchor rope purlins A14, and on the outer side of the top of the first anchor pile 121 is provided a first outer row of anchor rope purlins 13, the first outer row The anchor rope enclosing purlin 13 is pressed against each first anchor pile.
  • the first outer row of anchor rope purlin 13 is arranged on the ground 110.
  • the direction of the arrow 810 indicates the extending direction of the first set direction in Embodiment 1.
  • the mark 120 indicates the bottom of the first foundation pit 130.
  • the elevation of the bottom of the first anchor pile 121 is lower than the elevation of the bottom of the first inner row of piles 11, that is, the elevation of the bottom of the first anchor pile 121 is lower than the elevation of the bottom of the first anchor pile 111.
  • the first clear distance S1 between the first anchor pile 121 and the corresponding first anchor pile 111 is 5 meters.
  • a group of anchor cables AI is arranged between each first anchor cable pile 111 and the corresponding first anchor pile, and each group of anchor cables AI includes a first anchor cable AI15 and a second anchor cable AI16, The first anchor cable AI15 and the second anchor cable AI16 are both pre-stressed anchor cables.
  • the two ends of each first anchor cable AI15 are called the first front end A and the first rear end A, respectively, and the two ends of each second anchor cable AI16 are called the second front end A and the second rear end A, respectively.
  • the first front end A of the first anchor cable AI15 penetrates the corresponding first anchor cable pile 111 and then is connected to the first inner row of anchor cable purlins A14, and the first rear end A of the first anchor cable AI15 is along the oblique direction It extends upward and penetrates the corresponding first anchor pile 121 and then connects to the first outer row of anchor rope purlin 13.
  • the second front end A of the second anchor cable AI16 penetrates the corresponding first anchor cable pile 111 and then is connected to the first inner row of anchor cable purlins A14, and the second rear end A of the second anchor cable AI16 is along the oblique direction It extends downward and is connected to the corresponding first anchor pile 121.
  • the included angle ⁇ 1 between the first anchor cable AI15 and the horizontal plane is 15°; the included angle ⁇ 1 between the first anchor cable AI15 and the second anchor cable AI16 is 60°.
  • the first inner row of piles 11 including the first anchor piles adopts first H steel piles, each of the first H steel piles are arranged at intervals along the first set direction, and the webs of the first H steel piles The plate extends in a direction perpendicular to the first set direction.
  • the first anchor pile 121 adopts second H steel piles, each second H steel pile is arranged at intervals along a first set direction, and the webs of the second H steel piles extend in a direction parallel to the first set direction.
  • the first inner row of anchor rope purlin A14 is formed by two rows of I-beams 141. Both rows of I-beams 141 extend in the horizontal direction and are arranged side by side at intervals in the vertical direction.
  • the first front end A of the AI 15 and the second front end A of the second anchor A I 16 both pass through the vertical gap between the two rows of section steels and are fixed on the first inner row of anchor cable purlins A14.
  • the structure of the first inner row of anchor rope enclosure A14 in this embodiment is also called a double-splice I-steel structure.
  • the outer purlin 13 of the first outer row of anchor cables is made of H-shaped steel.
  • the connections of the first anchor cable AI15 and the second anchor cable AI16 with the first inner row anchor cable purlin A14, the first outer row anchor cable purlin 13 and the first anchor pile 121 all use steel cable anchors.
  • Existing steel tapered anchors including clip-type anchors of JM type, XM type, QM type, BM type, etc., and various types of steel cable anchors can meet the needs of this application, and will not be repeated.
  • the cable anchor adopts a BM clip-type anchor.
  • the connection between the cable anchor and each anchor cable will be described below.
  • the first front end A of the first anchor cable AI15 and the second front end A of the second anchor cable AI16 are two rows of workers passing through the inner row of anchor cables A14. After the gap between the beams 141, a cable anchor is installed, and the cable anchor is supported on the two rows of I-beams 141.
  • the first rear end A of the first anchor cable AI15 penetrates the flange of the H-shaped steel as the first outer row of anchor cable purlin 13 and then installs the cable anchor, and supports the cable anchor on the flange of the H-shaped steel. .
  • the second rear end A of the second anchor cable AI16 penetrates the web of the H-shaped steel as the first anchor pile 121 and then installs the cable anchor, and supports the anchor on the web of the H-shaped steel.
  • the first inner row of piles 11 and the first anchor piles 121 both sink into the ground in the vertical direction.
  • the construction method of the first deep anchor pile support system includes the following steps:
  • the first inner row of piles 11 and the first anchor pile 121 Prepare the first inner row of piles 11 and the first anchor pile 121.
  • the first inner row is formed at the setting position of the first inner row of piles as the first anchor pile 111.
  • the first outer row of anchor holes and the second outer row of anchor holes are formed at fixed positions.
  • the first outer row of anchor holes is used for piercing the first anchor cable AI, and the second outer row of anchor holes is used for piercing The second anchor cable AI.
  • the first outer row of anchor cable holes and the second outer row of anchor cable holes are not shown in the drawings.
  • a first hole 115 is opened at the first set position of the first anchor pile 111, and a second hole 116 is opened at the second set position.
  • the first inner row of piles 11 is made of H steel
  • a first hole 115 is opened on the same side of each flange 112 relative to the web 113
  • a second hole 116 is opened on the other side of each flange 112 relative to the web 113
  • the first hole 115 is used for piercing the first anchor cable AI15
  • the second hole 116 is for piercing the second anchor cable AI16.
  • first hole and the second hole may be combined into a common hole, so that the first anchor cable AI and the second anchor cable AI pass through the common hole.
  • the first anchor cable AI is freely inserted into the two first holes 115, and the second anchor cable AI is freely inserted into the two second holes 116.
  • the first anchor pile 111 carrying the first anchor cable AI and the second anchor cable AI and other first inner row piles are sunk into the ground, and the first rear end A of the first anchor cable AI Facing the outside and being held on the ground 110, and making the second rear end A of the second anchor cable AI face the outside and being held on the ground 110.
  • the second outer row of anchor cable holes can be eliminated, and the second rear end A of the second anchor cable AI can be tied to the set position of the first anchor pile.
  • other methods can also be used to fix the second rear end A of the second anchor cable AI at the set position of the first anchor pile.
  • the purpose of providing the outer purlin holes on the first outer row of anchor rope purlins is for the subsequent tensioning process to be able to stretch the first anchor rope AI on the ground. It is understandable that the other In the embodiment, if it is not necessary to stretch the first anchor cable AI on the ground, the outer row of purlin holes can be eliminated, and the first anchor cable AI can be directly fixed on the first outer row of anchor cable purlins.
  • the first front end A of the first anchor rope AI is stretched by a jack in the foundation pit, so that the first anchor rope AI generates internal stress and forms a prestressed anchor rope , And then lock the steel cable anchor on the first front end A of the first anchor cable AI, and support the steel cable anchor on the first inner row of anchor cable purlin A.
  • the first anchor cable AI and the second anchor cable AI are simultaneously tensioned.
  • first anchor cable AI and the second anchor cable AI can also be tensioned step by step.
  • the steel cable anchor when the first anchor cable AI is stretched, can also be locked on the first front end A of the first anchor cable AI first, and then the first anchor cable The first rear end A of AI is stretched.
  • the first anchor cable AI and the second anchor cable AI need to cut the soil to reach the set position and tensioned. Hard areas, or large debris in the soil, will hinder the cutting of the soil by the first anchor cable AI and the second anchor cable AI, and sometimes cause damage to the first anchor cable AI and the second anchor cable AI. destroy.
  • the first anchor cable AI and the second anchor cable AI are first opened on the path.
  • the slot is stretched so that the first anchor cable AI and the second anchor cable AI are arranged in the tension slot, and then the first anchor cable AI and the second anchor cable AI are stretched.
  • the second deep anchor pile support system which includes a plurality of second inner row piles 21 arranged along a first set direction, part of the second inner row piles are formed as second anchor cables
  • the pile 211 corresponds to each second anchor pile 211 provided with a second anchor pile 221, and the second anchor pile 221 is arranged on the side of the corresponding second anchor pile 211 away from the second foundation pit 150.
  • a second inner row of anchor rope purlin A242 is provided on the inner side of the second inner row of piles 21.
  • a second outer row of anchor rope purlin 23 is provided on the outer side of the top of the second anchor pile 221.
  • the second outer row of anchor rope purlin 23 is arranged on the ground.
  • the direction of the arrow 820 indicates the extending direction of the first set direction in the second embodiment.
  • the elevation of the bottom of the second anchor pile 221 is lower than the elevation of the bottom of the second inner row of piles 21, that is, the elevation of the bottom of the second anchor pile 221 is lower than the elevation of the bottom of the second anchor pile 211.
  • the second net distance S2 between the second anchor pile 221 and the corresponding second anchor pile 211 is 8 meters.
  • a set of anchor cables AII is provided between each second anchor cable pile 211 and the corresponding second anchor pile 221, and each group of anchor cables AII includes a first anchor cable AII25 and a second anchor cable AII26. .
  • the first anchor cable AII25 and the second anchor cable AII26 are both pre-stressed anchor cables.
  • the two ends of each first anchor cable AII25 are called the first front end A and the first rear end A, respectively, and the two ends of each second anchor cable AII26 are called the second front end A and the second rear end A respectively;
  • the first front end A of the first anchor cable AII25 penetrates the corresponding second anchor cable pile 211 and then is connected to the second inner row of anchor cable purlins A242.
  • the first rear end A of the first anchor cable AII25 is along the oblique direction It extends upward and penetrates through the second anchor pile 221 and then is connected to the second outer row of anchor rope purlin 23.
  • the second front end A of the second anchor cable AII26 penetrates the corresponding second anchor cable pile 211 and then is connected to the second inner row of anchor cable purlins A242, and the second rear end A of the second anchor cable AII26 is along the oblique direction It extends downward and is connected to the second anchor pile 221.
  • the included angle ⁇ 2 between the first anchor cable AII25 and the horizontal plane is 30°; the included angle ⁇ 2 between the first anchor cable AII25 and the second anchor cable AII26 is 70°.
  • the second inner row of piles 21 adopts Larsen steel sheet piles.
  • the Larsen steel sheet piles are arranged along the first set direction and interlock with each other.
  • the webs of the Larsen steel sheet piles are along the direction of the first set direction. extend.
  • the second anchor pile 221 adopts steel pipe piles, and the steel pipe piles are arranged at intervals along the first set direction.
  • the second inner row anchor rope purlin A24 is formed by two rows of H-shaped steel, and the specific structure is similar to the first inner row anchor rope purlin A14 in Embodiment 1, and will not be repeated.
  • the second outer row of anchor rope enclosing purlin 23 is made of H-shaped steel.
  • connections of the first anchor cable AII25 and the second anchor cable AII26 with the second inner row anchor cable purlin A242, the second outer row anchor cable purlin 23, and the second anchor pile 221 all use steel cable anchors.
  • the connection methods are similar to those in Embodiment 1, and will not be repeated here.
  • an inner row of anchor rope enclosing purlin C241 is added, corresponding to the inner row of anchor rope enclosing purlin C, a second anchor pile is provided between each second anchor pile and the corresponding second anchor pile.
  • Two anchor cables C27, the two ends of each second anchor cable C are respectively called the second front end C and the second rear end C.
  • the inner row of anchor rope purlins C241 is located above the second inner row of anchor rope purlins A242 and is located inside the top of the second inner row of piles 21.
  • the structure of the inner row of anchor rope enclosure purlin C241 is the same as the structure of the second inner row of anchor rope enclosure purlin A242, and will not be repeated.
  • the second front end C of the second anchor cable C penetrates through the corresponding second anchor cable pile and then is connected to the inner row of anchor cable purlins C241, and the second rear end C of the second anchor cable C extends downward in the oblique direction And connected to the second anchor pile 221.
  • the connection method of the second anchor cable C and the inner row anchor cable purlin C241 is the same as the connection method of the second anchor cable AI16 and the first inner row anchor cable purlin A14, and the connection of the second anchor cable C to the second anchor pile 221 The method is the same as that of the second anchor cable AI16 and the first anchor pile 121.
  • only one inner row anchor cable enclosure C241 and the corresponding second anchor cable C27 are provided. It can be understood that in other embodiments, more than two inner row anchor cable enclosure purlins C241 and Corresponding second anchor cable C27.
  • the second inner row of piles and the second anchor piles are both sunk into the ground in the vertical direction.
  • the construction method of the second deep anchor pile support system includes the following steps:
  • the second inner row of piles as the second anchor piles is formed at the setting position for the second anchor cable C27, the first anchor cable AII25 and The inner anchor cable hole of the second anchor cable AII26 is formed on the second anchor pile with outer anchor cable holes for piercing the second anchor cable C27, the first anchor cable AII25 and the second anchor cable AII26.
  • the second anchor cable C27 is connected to the second anchor pile and the second anchor pile in the same manner as the second anchor cable AI is connected to the first anchor pile and the first anchor pile.
  • the tension and fixation of the first anchor cable AII25 and the second anchor cable AII26 are the same as the tension and fixation of the first anchor cable AI and the second anchor cable AI, and will not be repeated.
  • This embodiment is an improvement on the basis of Embodiment 2. Compared with Embodiment 2, this embodiment adds an inner row of anchor rope purlin B, and correspondingly adds a first anchor rope B and a second anchor rope B. This embodiment will be described below.
  • the third deep anchor pile support system which includes a plurality of third inner row piles 31 arranged along a first set direction, part of the third inner row piles are formed as third anchor cables
  • the pile 311 is provided with a third anchor pile 321 corresponding to each third anchor pile 311, and the third anchor pile 321 is arranged on the side of the corresponding third anchor pile 311 away from the third foundation pit 160.
  • a third inner row of anchor rope purlin A342 is provided on the inner side of the third inner row of piles 31.
  • a third outer row of anchor rope purlin 33 is provided outside the top of the third anchor pile 321.
  • the third outer row of anchor rope purlin 33 is arranged on the ground.
  • the direction of the arrow 830 in FIG. 6 indicates the extending direction of the first set direction in the third embodiment.
  • the elevation of the bottom of the third anchor pile 321 is lower than the elevation of the bottom of the third inner row of piles 31, that is, the elevation of the bottom of the third anchor pile 321 is lower than the elevation of the bottom of the third anchor pile 311.
  • the third clear distance S3 between the third anchor pile 321 and the corresponding third anchor pile 311 is 10 meters.
  • a group of anchor cables AIII is arranged between each third anchor pile 311 and the corresponding third anchor pile 321, and each group of anchor cables AIII includes a first anchor cable AIII35 and a second anchor cable AIII36 .
  • the third inner row of anchor rope purlins A342 has the same structure as the second inner row of anchor rope purlins A242 in the second embodiment.
  • the installation method of the first anchor cable AIII35 and the second anchor cable AIII36 is the same as the installation method of the first anchor cable AII25 and the second anchor cable AII26 in Embodiment 2, and will not be repeated.
  • the angle ⁇ 3 between the first anchor cable AIII35 and the horizontal plane is 20°; the angle ⁇ 3 between the first anchor cable AIII35 and the second anchor cable AIII36 is 80°.
  • the third inner row of piles 31 is a combined steel sheet pile, and the combined steel sheet pile is composed of a U-shaped steel sheet pile 315 and an H steel pile 316.
  • the third anchor pile 321 is an H steel pile.
  • the installation methods of the inner row anchor rope purlin CIII341 and the second anchor cable CIII37 are the same as the installation methods of the inner row anchor rope purlin C241 and the second anchor cable C27 in the second embodiment.
  • the inner row of anchor rope purlin CIII341 is located above the third inner row of anchor rope purlin A342, and is located inside the top of the third inner row of piles 31.
  • an inner row of anchor rope purlin B343 is added.
  • the inner row of anchor rope purlin B343 is located below the third inner row of anchor rope purlin A342 and is installed inside the third inner row of piles 31.
  • each group of anchor ropes B is arranged between each third anchor pile 311 and the corresponding third anchor pile 321, and each group of anchor ropes B includes a first Anchor rope B38 and a second anchor rope B39. Both the first anchor cable B and the second anchor cable B are pre-stressed anchor cables.
  • the two ends of each first anchor cable B38 are called the first front end B and the first rear end B, respectively.
  • the two ends of each second anchor cable B39 are called a second front end B and a second rear end B, respectively.
  • the first front end B of the first anchor cable B penetrates through the third anchor cable pile 311 and then is connected to the inner row of anchor cable purlins B.
  • the first rear end B of the first anchor cable B extends upward in the oblique direction and is connected to On the third anchor pile 321.
  • the second front end B of the second anchor cable B penetrates the third anchor cable pile 311 and then is connected to the inner row of anchor cable purlins B, and the second rear end B of the second anchor cable B extends downward in the oblique direction and is connected To the third anchor pile 321.
  • the structure of the inner row of anchor rope purlin B343 is the same as that of the third inner row of anchor rope purlin A342.
  • the connection mode of the first anchor cable B38 and the second anchor cable B39 with the inner row anchor cable purlin B343 is the same as the connection method of the first anchor cable AIII35 and the second anchor cable AIII36 with the third inner row anchor cable purlin A342.
  • the first front end of the first anchor cable B38 penetrates the corresponding third anchor cable pile and is connected to the inner row of anchor cable purlins B343.
  • the first rear end of the first anchor cable B38 extends upward in the inclined direction and is connected to the corresponding On the third anchor pile 321.
  • the second front end of the second anchor cable B39 penetrates through the corresponding third anchor cable pile and is connected to the inner row of anchor cable purlins B343.
  • the second rear end of the second anchor cable B39 extends downward in the oblique direction and is connected to the Corresponding to the third anchor pile 321.
  • the angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B is 75°, and the angle between the first anchor cable B and the horizontal plane is 30°. It can be understood that in other embodiments, the angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B and the angle between the first anchor cable B and the horizontal plane can be respectively 50° and 20°, 80° and 30°, 100° and 40°, and 130° and 45°.
  • the inner row of piles may also be at least one of steel pipe piles or precast concrete piles
  • the anchor piles may also be at least one of steel sheet piles, combined steel sheet piles or precast concrete piles.
  • the inner row anchor cable enclosure purlin CIII341 and the corresponding second anchor cable CIII37 in this embodiment 3 can be eliminated, and only the third inner row anchor cable enclosure purlin A342 and the inner row anchor cable enclosure are retained.
  • the third inner row of piles and the third anchor pile are both sunk into the ground in the vertical direction.
  • the construction method of the third deep anchor pile support system includes the following steps:
  • This embodiment is an improvement on the basis of embodiment 1. It is basically the same as embodiment 1. The difference is that the fourth anchor pile 421 is arranged obliquely. The angle ⁇ between the pile 421 and the vertical direction is 10°. That is, the inclination angle of the fourth anchor pile 421 toward the outside of the foundation pit is 10°. It can be understood that in other embodiments, the inclination angle of the fourth anchor pile 421 toward the outside of the foundation pit may also be 5°, 15°, 20°, or 30°.
  • the fourth clear distance S4 between the fourth anchor pile 421 and the corresponding fourth anchor pile 411 is 3 meters.
  • Fig. 16 is a cross-sectional view taken along the direction D-D in Fig. 15, where the cross-section D-D is located in the plane where the ground is located.
  • FIGS. 15 and 16 of this embodiment as in FIGS. 1 and 2 denote the same structural components.
  • the inclined setting of anchor piles is mainly used in areas with a small construction area. Of course, areas with a large construction area can also be used.
  • This embodiment is an improvement on the basis of Embodiment 4.
  • This embodiment is basically the same as Embodiment 4, and the difference lies in the inclination direction of the anchor pile.
  • the fifth anchor pile 521 is inclined from bottom to top toward one side of the inner direction of the foundation pit, and in this embodiment, in the vertical direction, the bottom of the fifth anchor pile 521 extends outward Out of the construction red line area, in Figure 17, the dashed line 500 represents the construction red line.
  • the pile top of the fifth anchor pile 521 is still located within the construction red line, after the foundation pit construction is completed, after the fifth anchor pile 521 is removed, the underground structure will not exceed the construction red line.
  • This embodiment is suitable for situations where the edge of the foundation pit is narrower from the construction red line.
  • the distance between the fifth anchor pile 511 and the construction red line is 1.2 meters.
  • FIG. 17 and FIG. 15 of this embodiment denote the same structural components.
  • the inclined setting of anchor piles is mainly used in areas with a small construction area. Of course, areas with a large construction area can also be used.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Disclosed is a deep cable-anchored pile supporting system, comprising an anchor cable pile, and an anchor pile, which is arranged on a side of the anchor cable pile that is away from a foundation pit, wherein a first anchor cable A and a second anchor cable A are provided between the anchor cable pile and the anchor pile; an inner-row anchor cable enclosure A is provided on the inner side of the anchor cable pile; an outer-row anchor cable enclosure is provided on the outer side of the top of the anchor pile; one end of the first anchor cable A penetrates the anchor cable pile and is then connected to the inner-row anchor cable enclosure A, and the other end of the first anchor cable A extends upwards in an inclined direction, penetrates the anchor pile and is then connected to the outer-row anchor cable enclosure; and one end of the second anchor cable A penetrates the anchor cable pile and is then connected to the inner-row anchor cable enclosure A, and the other end of the second anchor cable A extends downwards in an inclined direction and is connected to the anchor pile. A construction method for the deep cable-anchored pile supporting system is further disclosed. The present application can be carried out in a limited construction range, and improves the construction efficiency.

Description

一种深层锚拉桩支护体系及其施工方法Deep anchored pile supporting system and construction method thereof 技术领域Technical field
本发明涉及一种深层锚拉桩支护体系及其施工方法。The invention relates to a deep anchor pile supporting system and a construction method thereof.
背景技术Background technique
随着国家新型城镇化建设的快速发展,基坑工程已成为建筑工程、市政工程和轨道交通工程等的重要组成部分。由于城市内建筑密度越来越大,交通拥挤,场地狭小,地质条件可选性差,深基坑邻近既有建筑物非常普遍,使得深基坑支护型式选择受到限制。桩加内支撑的支护结构以及桩墙加内支撑的支护结构可以有效控制变形,但是挖土不方便,造价高,工期长。桩加锚杆之类的支护结构,挖土方便,造价低,施工便捷,但是由于很多地方限制锚杆出红线,不允许使用。With the rapid development of the country's new urbanization construction, foundation pit engineering has become an important part of construction engineering, municipal engineering and rail transit engineering. Due to the increasing density of buildings in the city, traffic congestion, narrow sites, and poor geological conditions, it is very common for deep foundation pits to be adjacent to existing buildings, which limits the choice of deep foundation pit support types. The supporting structure of pile plus internal support and the supporting structure of pile wall plus internal support can effectively control deformation, but it is inconvenient to excavate soil, high cost and long construction period. Supporting structures such as piles and anchors are convenient for excavation, low cost, and convenient for construction. However, because of the restrictions on the red lines of anchors in many places, they are not allowed to be used.
地面水平锚拉桩是指在距基坑外侧一定距离处的土体稳定区内施工锚桩,在支护桩背面挖沟槽或自然地坪以上拉上拉杆,其一端与支护桩上的冠梁连接,另一端与锚桩上的冠梁连接,通过连接紧固件对拉杆施加一定的预应力,将基坑上部土体作用于支护桩上的土压力的一部分传给锚桩的一种支护结构型式。具有成本低、操作简便、使用灵活、占用施工净空少等优点。但是由于水平拉锚桩只能设置在浅层地基,且只能设置一层,锚桩提供的水平拉力不大,会产生较大的变形。Ground horizontal anchor pile refers to the construction of anchor piles in the soil stability area at a certain distance from the outside of the foundation pit. Crown-beam connection, the other end is connected with the crown-beam on the anchor pile, a certain prestress is applied to the tie rod through the connecting fastener, and a part of the earth pressure of the soil in the upper part of the foundation pit acting on the supporting pile is transmitted to the anchor pile A type of supporting structure. It has the advantages of low cost, simple operation, flexible use, and less construction clearance. However, because horizontal anchor piles can only be set on shallow foundations, and only one layer can be set, the horizontal pulling force provided by the anchor piles is not large, which will cause greater deformation.
发明内容Summary of the invention
为解决上述问题,本发明首先提出了一种深层锚拉桩支护体系,其包括沿第一设定方向布置的若干根内排桩,至少有一根内排桩形成为锚索桩,对应于每根锚索桩均设置有一根锚桩,锚桩设置在所对应的锚索桩的背离基坑的一侧;To solve the above problems, the present invention first proposes a deep anchor pile support system, which includes a plurality of inner row piles arranged along a first set direction, at least one of the inner row piles is formed as an anchor pile, corresponding to Each anchor pile is provided with an anchor pile, and the anchor pile is arranged on the side of the corresponding anchor pile away from the foundation pit;
在每根锚索桩与所对应的锚桩之间均设置有一组锚索A,每组锚索A均包括一根第一锚索A和一根第二锚索A,该第一锚索A和第二锚索A均为预应力锚索;每根第一锚索A的两端分别称为第一前端A和第一后端A,每根第二锚索A的两端分别称为第二前端A和第二后端A;A group of anchor cables A is arranged between each anchor pile and the corresponding anchor pile. Each group of anchor cables A includes a first anchor cable A and a second anchor cable A. The first anchor cable A and the second anchor cable A are both pre-stressed anchor cables; the two ends of each first anchor cable A are called the first front end A and the first rear end A respectively, and the two ends of each second anchor cable A are called respectively Is the second front end A and the second rear end A;
在内排桩的内侧设置有一道内排锚索围檩A;在锚桩的顶部的外侧设置有一道外排锚索围檩;An inner row of anchor rope purlins A is provided on the inner side of the inner row of piles; an outer row of anchor rope purlins is provided on the outer side of the top of the anchor piles;
该第一锚索A的第一前端A贯穿所对应的锚索桩后连接到内排锚索围檩A上,该第一锚索A的第一后端A沿倾斜方向向上延伸并贯穿所对应的锚桩后连接到外排锚索围檩上;The first front end A of the first anchor cable A passes through the corresponding anchor cable pile and is connected to the inner row of anchor cable purlins A, and the first rear end A of the first anchor cable A extends upward in the oblique direction and passes through the The corresponding anchor piles are then connected to the outer row of anchor rope purlins;
该第二锚索A的第二前端A贯穿所对应的锚索桩后连接到内排锚索围檩A上,该第二锚索A的第二后端A沿倾斜方向向下延伸并连接到所对应的锚桩上。The second front end A of the second anchor cable A passes through the corresponding anchor cable pile and then is connected to the inner row of anchor cable purlins A, and the second rear end A of the second anchor cable A extends downward in the oblique direction and is connected To the corresponding anchor pile.
包括锚索桩在内,在内排桩与锚桩之间均不设置联系梁。Including the anchor piles, there is no connecting beam between the inner row of piles and the anchor piles.
本申请中,锚桩沿竖直方向设置,或沿倾斜方向设置,当锚桩沿倾斜方向设置时,锚桩由下向上朝远离基坑方向的一侧倾斜,或由下向上朝基坑内部方向的一侧倾斜,锚桩与竖直方向之间的夹角为5-30°。In this application, the anchor piles are arranged in the vertical direction or in the inclined direction. When the anchor piles are arranged in the inclined direction, the anchor piles are inclined from bottom to top toward the side away from the foundation pit, or from bottom to top toward the inner direction of the foundation pit. The angle between the anchor pile and the vertical is 5-30°.
在该深层锚拉桩支护体系中,设置了第一锚索A和第二锚索A,相对于锚索桩,由于第一锚索A和第二锚索A分别沿倾斜方向向上和向下延伸,对锚索桩形成双向拉伸,在产生朝向基坑外侧方向的水平拉力的同时,还能够对锚索桩分别生产向上和向下的拉力。水平拉力能够对锚索桩产生朝向外侧的抵抗力,在内排锚索围檩A的传导下,该抵抗力能够传递到其他的未连接有锚索的内排上,从而使个所有的内排桩形成朝向外力的拉力。向上和向下的拉力至少会有部分取消,相比单纯地采用朝向外侧向上倾斜的单边锚索,本申请中的双向拉伸至少会减少对锚索桩向上的提升力,使锚索桩能够更稳定地保持在土体中,也由于减少了对锚索桩向上的提升力,可以减少锚索桩以及全部内排桩在基坑底面以下的深度,从而减少锚索桩以及全部内排桩的长度,降低施工成本,并由于减少了内排桩的长度,也可以减少内排桩的下沉时间,提高施工效率。In the deep anchor pile support system, a first anchor cable A and a second anchor cable A are provided. Compared with the anchor cable pile, the first anchor cable A and the second anchor cable A are respectively upward and downward in the inclined direction. Extend downward to form two-way tension on the anchor pile. While generating a horizontal pulling force toward the outside of the foundation pit, it can also produce upward and downward pulling forces on the anchor pile. The horizontal pulling force can produce resistance to the anchor cable pile towards the outside. Under the conduction of the inner row of anchor rope purlin A, the resistance can be transmitted to other inner rows that are not connected with anchor cables, so that all the inner rows are The rows of piles form a pulling force towards the external force. The upward and downward pulling forces will be at least partially cancelled. Compared with simply adopting a unilateral anchor cable inclined upward to the outside, the two-way stretching in this application will at least reduce the upward lifting force on the anchor cable pile, so that the anchor cable pile It can be held in the soil more stably, and because it reduces the upward lifting force of the anchor piles, the depth of the anchor piles and all the inner rows of piles below the bottom of the foundation pit can be reduced, thereby reducing the anchor piles and all the inner rows. The length of the piles reduces the construction cost, and because the length of the inner row of piles is reduced, the sinking time of the inner row of piles can also be reduced, and the construction efficiency is improved.
由于第一锚索A和第二锚索A的一端均固定在锚桩力,由此可以减少施工的占地范围,尤其是在现有建筑的周围进行基坑施工时,由于施工范围有限,也无法在基坑侧壁上进行旋喷桩锚索的施工,只能在基坑周围采用大直径的灌装桩作为基坑支护体系,不但施工成本高,而且施工周期长。本申请中的深层锚拉桩支护体系可以有效地解决该问题,能够在较小的红线范围内进行施工。Since both ends of the first anchor cable A and the second anchor cable A are fixed to the anchor pile force, the construction area can be reduced, especially when the foundation pit construction is carried out around the existing building, due to the limited construction scope, It is also impossible to construct the jet-grouted pile anchor cable on the side wall of the foundation pit, and only large-diameter filling piles can be used as the foundation pit support system around the foundation pit, which not only has high construction costs, but also has a long construction period. The deep anchor pile support system in the present application can effectively solve this problem, and can be constructed within a smaller red line range.
本申请中的包括锚索桩在内的所有内排桩与锚桩之间均不设置联系梁,由此可以取消联系梁的养护时间,在完成内排桩与锚桩的下沉后,即可进行基坑的挖据,无需等到联系梁的凝固,可提供施工效率。由于取消了联系梁,在对第一锚索A和第二锚索A进行张拉时,可使锚索桩朝向基坑外侧产生轻微的变形,并对基坑周壁的土体进行挤压,使基坑周围的土体更加密实,有利于提高基坑的安全性。In this application, all the inner row of piles including the anchor piles and the anchor piles are not provided with contact beams, so the maintenance time of the contact beams can be cancelled. After the inner row of piles and the anchor piles are settled, that is The excavation of the foundation pit can be carried out without waiting for the solidification of the contact beam, which can provide construction efficiency. Due to the cancellation of the connecting beam, when the first anchor cable A and the second anchor cable A are tensioned, the anchor cable piles can be slightly deformed toward the outside of the foundation pit, and the soil around the foundation pit can be squeezed. Make the soil around the foundation pit more dense and solid, which is conducive to improving the safety of the foundation pit.
进一步,第一锚索A与水平面之间的夹角为15-30°,第一锚索A与第二锚索A之间的夹角为50-120°,且同一组锚索A中的第一锚索A与水平面之间的夹角小于第二锚索A与水平面之间的夹角。Further, the angle between the first anchor cable A and the horizontal plane is 15-30°, the angle between the first anchor cable A and the second anchor cable A is 50-120°, and the angle between the first anchor cable A and the horizontal plane is 50-120°. The angle between the first anchor cable A and the horizontal plane is smaller than the angle between the second anchor cable A and the horizontal plane.
该设计能够使内排锚索围檩A最大限度靠近内排桩的顶部,减少内排桩的上部无支撑的距离,同时可以使第二锚索A与锚桩的连接点更朝向锚桩的桩底。在第一锚索A和第二锚索A具有同样张力的情况下,相对于锚索桩,该设计可以使第二锚索A产生向下的分力大于第一锚索A产生的向上的分力,形成对锚索桩的向下压力。This design can make the inner row of anchor rope purlin A close to the top of the inner row of piles to the greatest extent, reduce the unsupported distance of the upper part of the inner row of piles, and at the same time make the connection point of the second anchor rope A and the anchor pile more towards the anchor pile The bottom of the pile. In the case that the first anchor cable A and the second anchor cable A have the same tension, relative to the anchor cable pile, this design can make the second anchor cable A generate a downward force greater than the upward force generated by the first anchor cable A. The force is divided to form a downward pressure on the anchor pile.
具体地,该内排锚索围檩A由两排型钢所形成,该两排型钢均沿水平方向延伸且沿竖直方向间隔并排布置,第一锚索A的第一前端A和第二锚索A的第二前端A均穿过该两排型钢竖直方向之间的间隙后被固定在内排锚索围檩A上。Specifically, the inner row of anchor cable purlins A is formed by two rows of section steels, both of which extend in the horizontal direction and are arranged side by side at intervals in the vertical direction. The first front end A of the first anchor cable A and the second anchor The second front end A of the cable A passes through the vertical gap between the two rows of section steels and then is fixed on the inner row of anchor cable purlins A.
该内排锚索围檩A的结构可以便于第一锚索A和第二锚索A的穿设,避免在内排锚索围檩A上开设用于第一锚索A和第二锚索A穿过的孔洞,可以保持内排锚索围檩A的完整性。The structure of the inner row anchor rope purlin A can facilitate the insertion of the first anchor rope A and the second anchor rope A, avoiding the first anchor rope A and the second anchor rope A on the inner row anchor rope purlin A The hole A passes through can maintain the integrity of the inner row of anchor ropes surrounding purlin A.
进一步,在内排桩的内侧还设置有至少一道内排锚索围檩B,对应于每道内排锚索围檩B,在每根锚索桩与所对应的锚桩之间均设置有一组锚索B,每组锚索B均包括一根第一锚索B和一根第二锚索B,该第一锚索B和第二锚索B均为预应力锚索;每根第一锚索B的两端分别称为第一前端B和第一后端B,每根第二锚索B的两端分别称为第二前端B和第二后端B;Furthermore, at least one inner row of anchor rope purlins B is also arranged on the inner side of the inner row of piles, corresponding to each inner row of anchor rope purlins B, and a set of anchor piles is provided between each anchor pile and the corresponding anchor pile. Anchor B The two ends of the anchor cable B are called the first front end B and the first rear end B respectively, and the two ends of each second anchor cable B are called the second front end B and the second rear end B respectively;
该第一锚索B的第一前端B贯穿所对应的锚索桩后连接到所对应的内排锚索围檩B上,该第一锚索B的第一后端B沿倾斜方向向上延伸并连接到所对应的锚桩上;The first front end B of the first anchor cable B penetrates the corresponding anchor cable pile and then is connected to the corresponding inner row of anchor cable purlins B, and the first rear end B of the first anchor cable B extends upward in the oblique direction And connect to the corresponding anchor pile;
该第二锚索B的第二前端B贯穿所对应的锚索桩后连接到所对应的内排锚索围檩B上,该第二锚索B的第二后端B沿倾斜方向向下延伸并连接到所对应的锚桩上。The second front end B of the second anchor cable B penetrates the corresponding anchor cable pile and then is connected to the corresponding inner row anchor cable purlin B, and the second rear end B of the second anchor cable B is downward in the inclined direction Extend and connect to the corresponding anchor pile.
根据不同的基坑深度,可以设置一道或多道内排锚索围檩B,对应于每道内排锚索围檩B均设置有第一锚索B和第二锚索B,由于第一锚索B和第二锚索B分别向上和向下延伸,使第一锚索B和第二锚索B对锚索桩及锚桩在竖向所生产的作用力部分抵消,减少对锚索桩或锚桩向上提升的力量,能够使锚索桩或锚桩稳定地保持在原位。Depending on the depth of the foundation pit, one or more inner row anchor rope purlins B can be set. Corresponding to each inner row anchor rope purlin B, there are first anchor ropes B and second anchor ropes B. Because the first anchor rope B and the second anchor cable B extend upward and downward respectively, so that the first anchor cable B and the second anchor cable B partially offset the force produced by the anchor pile and the anchor pile in the vertical direction, reducing the impact on the anchor pile or the anchor pile. The upward lifting force of the anchor pile can keep the anchor pile or anchor pile stably in place.
进一步,为保证对锚索桩形成稳定的向下的拉力,同一组锚索B中的第一锚索B与第二锚索B之间的夹角为50-130°,且第一锚索B与水平面之间的夹角为20-45°。优选使同一组锚索B中的第一锚索B与水平面之间的夹角小于第二锚索B与水平面之间的夹角,以形成向下的净力量,对锚索桩下压。Further, in order to ensure a stable downward pulling force on the anchor cable piles, the included angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B is 50-130°, and the first anchor cable The angle between B and the horizontal plane is 20-45°. Preferably, the included angle between the first anchor cable B and the horizontal plane in the same group of anchor cables B is smaller than the included angle between the second anchor cable B and the horizontal plane, so as to form a net downward force to press down the anchor cable pile.
在内排桩的内侧还设置有一道内排锚索围檩C,对应于该道内排锚索围檩C,在每根锚索桩与所对应的锚桩之间均设置有一根第二锚索C,每根第二锚索C的两端分别称为第二前端C和第二后端C;该第二锚索C为预应力锚索;There is also an inner row of anchor rope surrounding purlins C on the inner side of the inner row of piles, corresponding to the inner row of anchor rope surrounding purlins C of the road, and a second anchor cable is arranged between each anchor rope pile and the corresponding anchor pile. C, the two ends of each second anchor cable C are respectively called the second front end C and the second rear end C; the second anchor cable C is a prestressed anchor cable;
该第二锚索C的第二前端C贯穿所对应的锚索桩后连接到内排锚索围檩C上,该第二锚索C的第二后端C沿倾斜方向向下延伸并连接到所对应的锚桩上;The second front end C of the second anchor cable C penetrates through the corresponding anchor cable pile and then is connected to the inner row of anchor cable purlins C, and the second rear end C of the second anchor cable C extends downward in the oblique direction and is connected To the corresponding anchor pile;
该道内排锚索围檩C位于内排锚索围檩A的上方。The inner row of anchor rope purlin C is located above the inner row of anchor rope purlin A.
由于将第一锚索A倾斜设置,使得内排锚索围檩A的位置与地面之间具有一定的距离,使得内排桩的顶部具有向基坑内弯曲的可能,为了避免内排桩的顶部在外部压力下向基坑内侧方向弯曲,在内排锚索围檩A的上方增设一道内排锚索围檩C,并设置相应的第二锚索C,由于第二锚索C由锚索桩沿倾斜方向向下连接到锚桩上,在保证了内排桩的顶部获得稳定的支撑后,还为锚索桩提供了向下的压力,由于锚桩整体保留在土体中,与土体具有之间具有更大的抗浮能力,因此增设内排锚索围檩C及相应的第二锚索C后,可以充分利用锚桩与土 体之间的摩擦力,并通过第二锚索C将该摩擦例传递到内排桩上,在避免内排桩的顶部向外弯曲的同时,并对锚索桩形成向下的压力,使锚索桩能够稳定地保持在设定位置上。Due to the inclined arrangement of the first anchor cable A, there is a certain distance between the position of the inner row of anchor cable purlin A and the ground, so that the top of the inner row of piles may bend into the foundation pit, in order to avoid the top of the inner row of piles Under the external pressure, it bends towards the inner side of the foundation pit, and an inner row of anchor rope enclosing purlin C is added above the inner row of anchor rope enclosing purlin A, and a corresponding second anchor rope C is set. The piles are connected to the anchor piles in an inclined direction. After ensuring stable support on the top of the inner row of piles, it also provides downward pressure for the anchor piles. Because the anchor piles remain in the soil as a whole, they The body has greater anti-floating ability, so after adding the inner row of anchor cable purlin C and the corresponding second anchor cable C, the friction between the anchor pile and the soil can be fully utilized, and the second anchor can pass through The cable C transfers the friction to the inner row of piles, while avoiding the outward bending of the top of the inner row of piles, it also exerts downward pressure on the anchor piles, so that the anchor piles can be stably maintained at the set position. .
具体地,该内排桩为H钢桩、钢板桩、组合钢板桩、钢管桩或预制混凝土桩中的至少一种,该锚桩为H钢桩、钢板桩、组合钢板桩、钢管桩或预制混凝土桩中的至少一种。采用上述各类桩体均能够较好地实现本申请,以充分地利用现有的各种预制桩。Specifically, the inner row of piles is at least one of H steel piles, steel sheet piles, combined steel sheet piles, steel tube piles or precast concrete piles, and the anchor piles are H steel piles, steel sheet piles, combined steel sheet piles, and steel tube piles. Or at least one of precast concrete piles. The above-mentioned various types of piles can be used to better realize the application, so as to make full use of the existing various prefabricated piles.
进一步,为了使锚桩能够与地下土体产生足量的摩擦力,避免锚桩在锚索桩的作用下向上移动,锚桩的桩底标高低于锚索桩的桩底标高。Furthermore, in order to enable the anchor pile to generate sufficient friction with the underground soil and prevent the anchor pile from moving upward under the action of the anchor pile, the elevation of the bottom of the anchor pile is lower than the elevation of the bottom of the anchor pile.
将锚桩的桩底标高低于锚索桩的桩底标高时,由于锚索桩与锚桩的桩底标高均低于基坑底部的设定标高,因此可以使锚桩在土体中获得稳定的状态,为锚索桩提供足量的拉力。When the elevation of the bottom of the anchor pile is lower than that of the anchor pile, since the elevation of the bottom of the anchor pile and the anchor pile is lower than the set elevation of the bottom of the foundation pit, the anchor pile can be obtained in the soil. The stable state provides sufficient pulling force for the anchor pile.
本申请中,锚索桩与所对应的锚桩之间的净距离为1-10米,进一步优选为3-8米。可以使锚索桩与锚桩之件具有足够厚度的土体,以保证土体能够对锚桩形成稳定的压力和包合力,避免由于锚索桩与锚桩之间的土体太薄,且由于土体向基坑内侧发生轻微偏移而导致锚桩与土体之间的摩擦力降低。锚索桩与所对应的锚桩之间的净距离是指锚索桩和锚桩与地面所在平面相交处之间的净距离。In this application, the net distance between the anchor pile and the corresponding anchor pile is 1-10 meters, more preferably 3-8 meters. It is possible to make the anchor pile and the anchor pile have a sufficient thickness of soil to ensure that the soil can form a stable pressure and binding force on the anchor pile, avoid the soil between the anchor pile and the anchor pile from being too thin, and Due to the slight deviation of the soil to the inner side of the foundation pit, the friction between the anchor pile and the soil is reduced. The net distance between the anchor pile and the corresponding anchor pile refers to the net distance between the anchor pile and the intersection of the anchor pile and the plane where the ground is located.
为使上述技术方案顺利进行,本发明还提供一种深层锚拉桩支护体系的施工方法,其用于施工上述方案中的深层锚拉桩支护体系,其包括以下步骤:In order to make the above technical solution proceed smoothly, the present invention also provides a construction method of a deep anchored pile support system, which is used to construct the deep anchored pile support system in the above solution, which includes the following steps:
(1)准备内排桩和锚桩,在作为锚索桩的内排桩的设定位置上形成有内排锚索孔,在锚桩的设定位置上形成有外排锚索孔;(1) Prepare the inner row of piles and anchor piles. The inner row of anchor holes is formed at the set position of the inner row of piles as the anchor pile, and the outer row of anchor holes is formed at the set position of the anchor pile;
(2)将第一锚索A和第二锚索A自由地穿设在锚索桩上的前排锚索孔内,然后将内排桩沉入地下,第一锚索A的一部分和第二锚索A的一部分随锚索桩沉入地下,并使第一锚索A的第一后端A朝向外侧并保持在地面,以及使第二锚索A的第二后端A朝向外侧并保持在地面;(2) Pass the first anchor cable A and the second anchor cable A freely in the front row of anchor cable holes on the anchor piles, and then sink the inner row of piles into the ground. A part of the first anchor cable A and the first A part of the second anchor cable A sinks into the ground along with the anchor cable pile, and the first rear end A of the first anchor cable A faces outward and remains on the ground, and the second rear end A of the second anchor cable A faces outward and Keep on the ground
将第二锚索A的第二后端A固定在锚桩的后端设定位置上,然后将锚桩沉入地下;Fix the second rear end A of the second anchor cable A at the set position of the rear end of the anchor pile, and then sink the anchor pile into the ground;
(3)开挖基坑,直到内排锚索围檩A的施工标高,然后安装内排锚索围檩A;(3) Excavate the foundation pit up to the construction elevation of the inner row of anchor cables and purlin A, and then install the inner row of anchor cables and purlin A;
在将第一锚索A的第二后端A依次自由地穿过锚桩上所对应的外排锚索孔及外排锚索围檩上所对应的围檩锚索孔后,对第一锚索A进行张拉,使第一锚索A产生内应力,形成为预应力锚索;并将第一锚索A的第一前端A固定在内排锚索围檩A上,将第一锚索A的第一后端A固定在外排锚索围檩上;After passing the second rear end A of the first anchor cable A freely through the corresponding outer row anchor cable holes on the anchor piles and the corresponding surrounding purlin anchor cable holes on the outer row anchor cable purlins, The anchor cable A is stretched to cause the first anchor cable A to generate internal stress and form a pre-stressed anchor cable; fix the first front end A of the first anchor cable A on the inner row of anchor cable purlins A, and fix the first The first rear end A of the anchor cable A is fixed on the outer row of anchor cable purlins;
对第二锚索A进行张拉,使第二锚索A产生内应力,形成为预应力锚索,并将第二锚索A的第二前端A固定在内排锚索围檩A上;Tension the second anchor cable A to generate internal stress on the second anchor cable A to form a pre-stressed anchor cable, and fix the second front end A of the second anchor cable A on the inner row of anchor cable purlins A;
对第一锚索A和第二锚索A的张拉同步进行或分步进行;The tensioning of the first anchor cable A and the second anchor cable A is performed synchronously or step by step;
(4)开挖基坑到设计标高,施工地下室的主体结构,同步进行换撑结构的施工;然后拆除围檩,拔除锚桩。根据不同的地质条件,拔除内排桩或将内排桩保留在原位,当地质条件 较好时,可以将内排桩部分或全部拔除,回收利用。当地质条件不好,或对周围建筑物有较大影响时,可以将内排桩保持在原位。(4) Excavate the foundation pit to the design elevation, construct the main structure of the basement, and simultaneously carry out the construction of the support structure; then remove the purlin and pull out the anchor pile. According to different geological conditions, remove the inner row of piles or keep the inner row of piles in place. When the local conditions are good, the inner row of piles can be partially or completely removed and recycled. When the geological conditions are not good, or the surrounding buildings are greatly affected, the inner row of piles can be kept in place.
该施工方法中,能够在基坑内对第一锚索A和第二锚索A进行张拉,从而使第一锚索A和第二锚索A形成预应力锚索,尤其可以使第二锚索A形成为预应力锚索。本实施方法中,利用锚索桩和锚桩将第二锚索A的两端预先布置到土体中,然后在基坑内对第二锚索A进行张拉,形成预应力锚索。在目前尚无法有效地利用锚桩的位于土体的部分,为了对内排桩形成有效的约束,往往是随着基坑的开挖,在基坑周围的土体中,采用搅拌桩的形式来安装锚索,并将该锚索连接内排上,该方式虽然能够有效地对内排桩形成有效的约束,但是施工周期长,成本较大,尤其是需要等到搅拌桩凝固后,才能形成有效的锚索,限制了基坑施工的效率。In this construction method, the first anchor cable A and the second anchor cable A can be tensioned in the foundation pit, so that the first anchor cable A and the second anchor cable A form a pre-stressed anchor cable, especially the second anchor cable The cable A is formed as a pre-stressed anchor cable. In this implementation method, the two ends of the second anchor cable A are pre-arranged into the soil by using anchor cable piles and anchor piles, and then the second anchor cable A is stretched in the foundation pit to form a pre-stressed anchor cable. In the part of the soil where the anchor pile cannot be effectively used, in order to form an effective constraint on the inner row of piles, the soil around the foundation pit is often used in the form of mixing piles with the excavation of the foundation pit. To install the anchor cable and connect the anchor cable to the inner row. Although this method can effectively form an effective constraint on the inner row of piles, the construction period is long and the cost is high, especially after the mixing pile is solidified. Effective anchor cables limit the efficiency of foundation pit construction.
本施工方法中,取消了混凝土的施工,第一锚索A和第二锚索A均能够固定在锚桩上,为第一锚索A和第二锚索A的张拉提供反力,保证预应力锚索的形成。由于取消了混凝土的施工,在完成预应力锚索的形成后,即可进行基坑的继续挖掘,可有效地提高基坑的挖掘效率。In this construction method, the concrete construction is canceled, and both the first anchor cable A and the second anchor cable A can be fixed on the anchor piles to provide a reaction force for the tension of the first anchor cable A and the second anchor cable A to ensure Formation of prestressed anchor cables. Due to the cancellation of the concrete construction, after the formation of the prestressed anchor cable, the foundation pit can be continuously excavated, which can effectively improve the excavation efficiency of the foundation pit.
进一步,在对第一锚索A和第二锚索A进行张拉前,首先在第一锚索A和第二锚索A所要经过的路径上开设张拉槽,使第一锚索A和第二锚索A均布置在该张拉槽内。Further, before the first anchor cable A and the second anchor cable A are stretched, a tension groove is first opened on the path through which the first anchor cable A and the second anchor cable A pass, so that the first anchor cable A and the second anchor cable A The second anchor cables A are all arranged in the tension groove.
在对第一锚索A和第二锚索A进行张拉时,第一锚索A和第二锚索A需要对土体进行切割,才能到达设定位置,并且张紧,在部分土质较硬的区域,或者土体中具有较大杂物时,会阻碍第一锚索A和第二锚索A对土体的切割,有时还会对第一锚索A和第二锚索A造成破坏。When the first anchor cable A and the second anchor cable A are stretched, the first anchor cable A and the second anchor cable A need to cut the soil to reach the set position, and the tension is tight. Hard areas or large debris in the soil will hinder the cutting of the soil by the first anchor cable A and the second anchor cable A, and sometimes cause damage to the first anchor cable A and the second anchor cable A. destroy.
在对第一锚索A和第二锚索A张拉前,首先开设张拉槽后,可以使第一锚索A和第二锚索A经张拉槽顺利到达设定位置,避免上述情况的发生。Before the first anchor cable A and the second anchor cable A are stretched, the tension slot is first opened, so that the first anchor cable A and the second anchor cable A can reach the set position through the tension slot smoothly, avoiding the above situation happened.
与现有技术相比,本申请总体的有益效果是:Compared with the prior art, the overall beneficial effects of this application are:
锚索可以设置在深层且土质较好土层中,提供比较大的锚拉力,可以有效控制支护结构的变形。通过设置向上和向下锚索,上下分力可以抵消,可以减小锚桩上浮和支护桩下沉风险。The anchor cable can be set in a deep layer with good soil quality to provide a relatively large anchor tension and effectively control the deformation of the supporting structure. By setting up and down anchor cables, the upper and lower component forces can be offset, which can reduce the risk of anchor piles floating up and supporting piles sinking.
在基坑浅层开挖时就完成了预应力的施加,后期可直接开挖到底,施工速度快;且可以在施工过程中对各层锚索预应力进行调整,变形控制效果好,对周边环境影响小。The application of prestress is completed during the shallow excavation of the foundation pit, and it can be directly excavated to the end in the later stage, and the construction speed is fast; and the prestress of each layer of anchor cables can be adjusted during the construction process, and the deformation control effect is good. The environmental impact is small.
本申请适用于多种地层条件,软土到中硬的地层、砂砾层、各种软硬风化岩层等都可以使用。This application is suitable for a variety of stratum conditions, from soft soil to medium-hard stratum, gravel layer, various soft and hard weathered rock layers, etc. can be used.
本申请占地少、无内支撑、预应力锚索不需要注浆、施工快捷、能有效限制侧向变形、包括内排桩、锚桩和锚索在内的支护结构可循环使用、经济效益显著等优点。This application occupies less land, no internal support, pre-stressed anchor cables do not require grouting, fast construction, can effectively limit lateral deformation, supporting structures including inner row piles, anchor piles and anchor cables can be recycled and are economical Advantages such as significant benefits.
附图说明Description of the drawings
图1是本发明的实施例1的结构示意图。FIG. 1 is a schematic diagram of the structure of Embodiment 1 of the present invention.
图2是图1的俯视图。Fig. 2 is a plan view of Fig. 1.
图3是本发明的实施例2的结构示意图。Fig. 3 is a schematic diagram of the structure of Embodiment 2 of the present invention.
图4是图3的俯视图。Fig. 4 is a top view of Fig. 3.
图5是本发明的实施例3的结构示意图。Fig. 5 is a schematic structural diagram of Embodiment 3 of the present invention.
图6是图5的俯视图。Fig. 6 is a plan view of Fig. 5.
图7是安装有锚索的第一锚索桩的示意图。Fig. 7 is a schematic diagram of a first anchor pile with an anchor cable installed.
图8是第一锚索桩完成下沉后的示意图。Figure 8 is a schematic diagram of the first anchor pile after the completion of sinking.
图9是安装有锚索的第一锚桩下沉过程的示意图。Fig. 9 is a schematic diagram of the sinking process of the first anchor pile with the anchor cable installed.
图10是将锚索连接到第一外排锚索围檩上的示意图。Figure 10 is a schematic diagram of connecting the anchor rope to the first outer row of anchor rope purlins.
图11是完成锚索张拉后的示意图。Figure 11 is a schematic diagram after the anchor cable is tensioned.
图12是完成基坑挖掘后的示意图。Figure 12 is a schematic diagram after the excavation of the foundation pit is completed.
图13是第一锚索桩的开孔示意图。Figure 13 is a schematic view of the opening of the first anchor pile.
图14是第一锚索桩穿设有锚索的示意图。Fig. 14 is a schematic diagram of the first anchor cable pile with an anchor cable passing through it.
图15是本发明的实施例4的结构示意图。FIG. 15 is a schematic diagram of the structure of Embodiment 4 of the present invention.
图16是图15中D-D向的截面图。Fig. 16 is a cross-sectional view taken along the line D-D in Fig. 15.
图17是本发明的实施例5的结构示意图。FIG. 17 is a schematic diagram of the structure of Embodiment 5 of the present invention.
具体实施方式Detailed ways
在本申请中,将朝向基坑中心的方向称为内侧,将与该内侧相反的方向称为外侧。In this application, the direction toward the center of the foundation pit is called the inner side, and the direction opposite to the inner side is called the outer side.
实施例1Example 1
请参阅图1和图2,第一深层锚拉桩支护体系,其包括沿第一设定方向布置的若干根第一内排桩11,其中部分第一内排桩形成为第一锚索桩111,对应于每根第一锚索桩111均设置有一根第一锚桩121,第一锚桩121设置在所对应的第一锚索桩111的背离第一基坑130的一侧。Please refer to Figures 1 and 2, the first deep anchor pile support system, which includes a plurality of first inner row piles 11 arranged along a first set direction, part of the first inner row piles are formed as first anchor cables The pile 111 is provided with a first anchor pile 121 corresponding to each first anchor pile 111, and the first anchor pile 121 is arranged on the side of the corresponding first anchor pile 111 away from the first foundation pit 130.
在第一内排桩11的内侧设置有一道第一内排锚索围檩A14,在第一锚桩121的顶部的外侧设置有一道第一外排锚索围檩13,该第一外排锚索围檩13抵压在各第一锚桩上。On the inner side of the first inner row of piles 11 is provided a first inner row of anchor rope purlins A14, and on the outer side of the top of the first anchor pile 121 is provided a first outer row of anchor rope purlins 13, the first outer row The anchor rope enclosing purlin 13 is pressed against each first anchor pile.
在本实施例中,该第一外排锚索围檩13布置在地面110上。在图2中,箭头810的指向表示实施例1中的第一设定方向的延伸方向。标记120表示第一基坑130的底部。In this embodiment, the first outer row of anchor rope purlin 13 is arranged on the ground 110. In FIG. 2, the direction of the arrow 810 indicates the extending direction of the first set direction in Embodiment 1. The mark 120 indicates the bottom of the first foundation pit 130.
第一锚桩121的桩底标高低于第一内排桩11的桩底标高,即第一锚桩121的桩底标高低于第一锚索桩111的桩底标高。且第一锚桩121与所对应的第一锚索桩111之间的第一净距离S1为5米。The elevation of the bottom of the first anchor pile 121 is lower than the elevation of the bottom of the first inner row of piles 11, that is, the elevation of the bottom of the first anchor pile 121 is lower than the elevation of the bottom of the first anchor pile 111. And the first clear distance S1 between the first anchor pile 121 and the corresponding first anchor pile 111 is 5 meters.
在每根第一锚索桩111与所对应的第一锚桩之间均设置有一组锚索AⅠ,每组锚索AⅠ均包括一根第一锚索AⅠ15和一根第二锚索AⅠ16,该第一锚索AⅠ15和第二锚索AⅠ16均为预应力锚索。每根第一锚索AⅠ15的两端分别称为第一前端A和第一后端A,每根第二锚索AⅠ16的两端分别称为第二前端A和第二后端A。A group of anchor cables AI is arranged between each first anchor cable pile 111 and the corresponding first anchor pile, and each group of anchor cables AI includes a first anchor cable AI15 and a second anchor cable AI16, The first anchor cable AI15 and the second anchor cable AI16 are both pre-stressed anchor cables. The two ends of each first anchor cable AI15 are called the first front end A and the first rear end A, respectively, and the two ends of each second anchor cable AI16 are called the second front end A and the second rear end A, respectively.
该第一锚索AⅠ15的第一前端A贯穿所对应的第一锚索桩111后连接到第一内排锚索围檩A14上,该第一锚索AⅠ15的第一后端A沿倾斜方向向上延伸并贯所对应的穿第一锚桩121后连接到第一外排锚索围檩13上。The first front end A of the first anchor cable AI15 penetrates the corresponding first anchor cable pile 111 and then is connected to the first inner row of anchor cable purlins A14, and the first rear end A of the first anchor cable AI15 is along the oblique direction It extends upward and penetrates the corresponding first anchor pile 121 and then connects to the first outer row of anchor rope purlin 13.
该第二锚索AⅠ16的第二前端A贯穿所对应的第一锚索桩111后连接到第一内排锚索围檩A14上,该第二锚索AⅠ16的第二后端A沿倾斜方向向下延伸并连接到所对应的第一锚桩121上。The second front end A of the second anchor cable AI16 penetrates the corresponding first anchor cable pile 111 and then is connected to the first inner row of anchor cable purlins A14, and the second rear end A of the second anchor cable AI16 is along the oblique direction It extends downward and is connected to the corresponding first anchor pile 121.
其中,第一锚索AⅠ15与水平面之间的夹角α1为15°;第一锚索AⅠ15与第二锚索AⅠ16之间的夹角β1为60°。The included angle α1 between the first anchor cable AI15 and the horizontal plane is 15°; the included angle β1 between the first anchor cable AI15 and the second anchor cable AI16 is 60°.
本实施例中,包括第一锚索桩在内的第一内排桩11采用第一H钢桩,各第一H钢桩沿第一设定方向间隔布置,且第一H钢桩的腹板沿垂直于第一设定方向的方向延伸。该第一锚桩121采用第二H钢桩,各第二H钢桩沿第一设定方向间隔布置,且第二H钢桩的腹板沿平行于第一设定方向的方向延伸。In this embodiment, the first inner row of piles 11 including the first anchor piles adopts first H steel piles, each of the first H steel piles are arranged at intervals along the first set direction, and the webs of the first H steel piles The plate extends in a direction perpendicular to the first set direction. The first anchor pile 121 adopts second H steel piles, each second H steel pile is arranged at intervals along a first set direction, and the webs of the second H steel piles extend in a direction parallel to the first set direction.
本实施例中,该第一内排锚索围檩A14由两排工字钢141所形成,该两排工字钢141均沿水平方向延伸且沿竖直方向间隔并排布置,第一锚索AⅠ15的第一前端A和第二锚索AⅠ16的第二前端A均穿过该两排型钢竖直方向之间的间隙后被固定在第一内排锚索围檩A14上。本实施例中的第一内排锚索围檩A14的结构也称为双拼工字钢结构。In this embodiment, the first inner row of anchor rope purlin A14 is formed by two rows of I-beams 141. Both rows of I-beams 141 extend in the horizontal direction and are arranged side by side at intervals in the vertical direction. The first front end A of the AI 15 and the second front end A of the second anchor A I 16 both pass through the vertical gap between the two rows of section steels and are fixed on the first inner row of anchor cable purlins A14. The structure of the first inner row of anchor rope enclosure A14 in this embodiment is also called a double-splice I-steel structure.
第一外排锚索围檩13采用H型钢制作。The outer purlin 13 of the first outer row of anchor cables is made of H-shaped steel.
本实施例中,第一锚索AⅠ15和第二锚索AⅠ16与第一内排锚索围檩A14、第一外排锚索围檩13以及第一锚桩121的连接均采用钢索锚具来连接。现有的钢质锥形锚具、包括JM型、XM型、QM型、BM型等型号的夹片型锚具,等各类钢索锚具均能够满足本申请的需要,不再赘述。具体在本实施例中,钢索锚具采用BM夹片型锚具。In this embodiment, the connections of the first anchor cable AI15 and the second anchor cable AI16 with the first inner row anchor cable purlin A14, the first outer row anchor cable purlin 13 and the first anchor pile 121 all use steel cable anchors. To connect. Existing steel tapered anchors, including clip-type anchors of JM type, XM type, QM type, BM type, etc., and various types of steel cable anchors can meet the needs of this application, and will not be repeated. Specifically, in this embodiment, the cable anchor adopts a BM clip-type anchor.
以下来说明钢索锚具与各锚索的连接,其中第一锚索AⅠ15的第一前端A和第二锚索AⅠ16的第二前端A是穿过内排锚索围檩A14的两排工字钢141之间的间隙后安装钢索锚具,并将钢索锚具支撑在两排工字钢141上。The connection between the cable anchor and each anchor cable will be described below. The first front end A of the first anchor cable AI15 and the second front end A of the second anchor cable AI16 are two rows of workers passing through the inner row of anchor cables A14. After the gap between the beams 141, a cable anchor is installed, and the cable anchor is supported on the two rows of I-beams 141.
第一锚索AⅠ15的第一后端A是贯穿作为第一外排锚索围檩13的H型钢的翼缘后安装钢索锚具,并将钢索锚具支撑在H型钢的翼缘上。The first rear end A of the first anchor cable AⅠ15 penetrates the flange of the H-shaped steel as the first outer row of anchor cable purlin 13 and then installs the cable anchor, and supports the cable anchor on the flange of the H-shaped steel. .
第二锚索AⅠ16的第二后端A是贯穿作为第一锚桩121的H型钢的腹板后安装钢索锚具,并将钢索锚具支撑在H型钢的腹板上。The second rear end A of the second anchor cable AI16 penetrates the web of the H-shaped steel as the first anchor pile 121 and then installs the cable anchor, and supports the anchor on the web of the H-shaped steel.
本实施例中的第一内排桩11和第一锚桩121均沿竖直方向下沉到地下。In this embodiment, the first inner row of piles 11 and the first anchor piles 121 both sink into the ground in the vertical direction.
以下对本实施例1中的第一深层锚拉桩支护体系的施工进行说明。The construction of the first deep anchor pile supporting system in the first embodiment will be described below.
该第一深层锚拉桩支护体系的施工方法,包括以下步骤:The construction method of the first deep anchor pile support system includes the following steps:
(1)准备第一内排桩11和第一锚桩121,在作为第一锚索桩111的第一内排桩的设定位置上形成有第一内排,在第一锚桩的设定位置上形成有第一外排锚索孔和第二外排锚索孔,其中第一外排锚索孔用于穿设第一锚索AⅠ,第二外排锚索孔用于穿设第二锚索AⅠ。该第一外排锚索孔和第二外排锚索孔在附图中均未显示。(1) Prepare the first inner row of piles 11 and the first anchor pile 121. The first inner row is formed at the setting position of the first inner row of piles as the first anchor pile 111. The first outer row of anchor holes and the second outer row of anchor holes are formed at fixed positions. The first outer row of anchor holes is used for piercing the first anchor cable AI, and the second outer row of anchor holes is used for piercing The second anchor cable AI. The first outer row of anchor cable holes and the second outer row of anchor cable holes are not shown in the drawings.
请参阅图13,在第一锚桩111的第一设定位置上开设第一孔115,在第二设定位置上开设第二孔116,本实施例中第一内排桩11采用H钢桩,在每个翼缘112相对于腹板113的同一侧各开设了一个第一孔115,并在每个翼缘112相对于腹板113的另一侧各开设了一个第二孔116,其中第一孔115用于穿设第一锚索AⅠ15,第二孔116用于穿设第二锚索AⅠ16。Referring to FIG. 13, a first hole 115 is opened at the first set position of the first anchor pile 111, and a second hole 116 is opened at the second set position. In this embodiment, the first inner row of piles 11 is made of H steel For the pile, a first hole 115 is opened on the same side of each flange 112 relative to the web 113, and a second hole 116 is opened on the other side of each flange 112 relative to the web 113, The first hole 115 is used for piercing the first anchor cable AI15, and the second hole 116 is for piercing the second anchor cable AI16.
可以理解,在其他实施例中,第一孔和第二孔可以合并为一个公共孔,使第一锚索AⅠ和第二锚索AⅠ穿设在该公共孔内。It can be understood that, in other embodiments, the first hole and the second hole may be combined into a common hole, so that the first anchor cable AI and the second anchor cable AI pass through the common hole.
(2)请参阅图7和图14,将第一锚索AⅠ自由地穿设在该两个第一孔115内,将第二锚索AⅠ自由地穿设在两个第二孔116内。请参阅图8,将携带第一锚索AⅠ和第二锚索AⅠ的第一锚索桩111、以及其他第一内排桩沉入地下,并使第一锚索AⅠ的第一后端A朝向外侧并保持在地面110,以及使第二锚索AⅠ的第二后端A朝向外侧并保持在地面110。(2) Referring to FIGS. 7 and 14, the first anchor cable AI is freely inserted into the two first holes 115, and the second anchor cable AI is freely inserted into the two second holes 116. Referring to Figure 8, the first anchor pile 111 carrying the first anchor cable AI and the second anchor cable AI and other first inner row piles are sunk into the ground, and the first rear end A of the first anchor cable AI Facing the outside and being held on the ground 110, and making the second rear end A of the second anchor cable AI face the outside and being held on the ground 110.
请参阅图8,将第二锚索AⅠ的第二后端A穿过第二外排锚索孔后,将钢索锚具固定在第二锚索AⅠ的第二后端A上,且能够使钢索锚具支撑在第一锚桩121的腹板上,避免第二锚索AⅠ的第二后端A脱出第二外排锚索孔,然后将第一锚桩沉入地下。Please refer to Figure 8, after passing the second rear end A of the second anchor cable AI through the second outer row of anchor cable holes, fix the steel cable anchor on the second rear end A of the second anchor cable AI, and be able to The steel cable anchor is supported on the web of the first anchor pile 121 to prevent the second rear end A of the second anchor cable AI from coming out of the second outer row of anchor cable holes, and then the first anchor pile is sunk into the ground.
可以理解,在其他实施例中,可以取消第二外排锚索孔,将第二锚索AⅠ的第二后端A绑扎在第一锚桩的设定位置上即可。当然也可以采用其他方法将第二锚索AⅠ的第二后端A固定在第一锚桩的设定位置上。It can be understood that, in other embodiments, the second outer row of anchor cable holes can be eliminated, and the second rear end A of the second anchor cable AI can be tied to the set position of the first anchor pile. Of course, other methods can also be used to fix the second rear end A of the second anchor cable AI at the set position of the first anchor pile.
(3)完成第一内排桩11和第一锚桩111的下沉后,请参阅图10,在地面安装第一外排锚索围檩13。在第一外排锚索围檩的翼缘上开设有外排围檩孔,该外排围檩孔在附图中未显示。(3) After the sinking of the first inner row of piles 11 and the first anchor pile 111 is completed, referring to Figure 10, install the first outer row of anchor rope purlin 13 on the ground. The flange of the first outer row of anchor rope purlins is provided with outer row purlin holes, and the outer row purlin holes are not shown in the drawings.
将第一锚索AⅠ的第一后端穿过外排围檩孔后,将钢索锚具固定在第一锚索AⅠ的第二后端A上,且能够使钢索锚具支撑在第一外排锚索围檩的翼缘上,避免第一锚索AⅠ的第一后端A脱出外排围檩孔。After passing the first rear end of the first anchor cable AI through the outer purlin hole, fix the steel cable anchor on the second rear end A of the first anchor cable AI, and enable the steel cable anchor to be supported on the second rear end A. On the flange of an outer row of anchor ropes surrounding purlins, prevent the first rear end A of the first anchor cable AⅠ from coming out of the outer row of surrounding purlin holes.
在本实施例中,在第一外排锚索围檩上设置外排围檩孔是为了后续的张拉过程中,能够在地面对第一锚索AⅠ进行张拉,可以理解,在其他实施例中,如无需在地面对第一锚索AⅠ进行张拉,可以取消该外排围檩孔,而将第一锚索AⅠ直接固定在第一外排锚索围檩上。In this embodiment, the purpose of providing the outer purlin holes on the first outer row of anchor rope purlins is for the subsequent tensioning process to be able to stretch the first anchor rope AI on the ground. It is understandable that the other In the embodiment, if it is not necessary to stretch the first anchor cable AI on the ground, the outer row of purlin holes can be eliminated, and the first anchor cable AI can be directly fixed on the first outer row of anchor cable purlins.
请参阅图11,开挖第一基坑,直到第一内排锚索围檩A的施工标高,暂停第一基坑的开挖,然后安装第一内排锚索围檩A。Please refer to Figure 11, excavate the first foundation pit until the construction elevation of the first inner row of anchor rope purlin A, suspend the excavation of the first foundation pit, and then install the first inner row of anchor rope purlin A.
完成第一内排锚索围檩A的安装后,在基坑内利用千斤顶对第一锚索AⅠ的第一前端A进行张拉,使第一锚索AⅠ产生内应力,形成为预应力锚索,然后将钢索锚具锁合在第一锚索AⅠ的第一前端A上,并将钢索锚具支撑在第一内排锚索围檩A。After completing the installation of the first inner row of anchor rope purlin A, the first front end A of the first anchor rope AⅠ is stretched by a jack in the foundation pit, so that the first anchor rope AⅠ generates internal stress and forms a prestressed anchor rope , And then lock the steel cable anchor on the first front end A of the first anchor cable AI, and support the steel cable anchor on the first inner row of anchor cable purlin A.
然后再利用千斤顶对第二锚索AⅠ的第二前端A进行张拉,使第二锚索AⅠ产生内应力,形成为预应力锚索,然后将钢索锚具锁合在第二锚索AⅠ的第二前端A上,并将钢索锚具支撑在第一内排锚索围檩A。Then use the jack to stretch the second front end A of the second anchor cable AⅠ, so that the second anchor cable AⅠ generates internal stress, forming a pre-stressed anchor cable, and then lock the steel cable anchor to the second anchor cable AⅠ On the second front end A of the A, and the steel cable anchor is supported on the first inner row of anchor cable purlin A.
本实施例中,对第一锚索AⅠ和第二锚索AⅠ同步进行张拉。In this embodiment, the first anchor cable AI and the second anchor cable AI are simultaneously tensioned.
当然,在其他实施例中,也可以对第一锚索AⅠ和第二锚索AⅠ分步进行张拉。Of course, in other embodiments, the first anchor cable AI and the second anchor cable AI can also be tensioned step by step.
可以理解,在其他实施例中,在对第一锚索AⅠ进行张拉时,还可以先将钢索锚具锁合在第一锚索AⅠ的第一前端A上,然后对第一锚索AⅠ的第一后端A进行张拉。It can be understood that, in other embodiments, when the first anchor cable AI is stretched, the steel cable anchor can also be locked on the first front end A of the first anchor cable AI first, and then the first anchor cable The first rear end A of AI is stretched.
当然,对并不必须在完成第一锚桩的下沉后立即进行第一外排锚索围檩的安装,只要在对第一锚索AⅠ进行张拉前,完成第一外排锚索围檩的安装即可。Of course, it is not necessary to install the first outer row of anchor rope purlins immediately after the completion of the sinking of the first anchor pile, as long as the first outer row of anchor ropes is completed before the first anchor rope AⅠ is stretched. The purlin can be installed.
请参阅图12,在完成对第一锚索AⅠ和第二锚索AⅠ的张拉后,继续开挖第一基坑并完成。Please refer to Figure 12, after finishing the tensioning of the first anchor cable AI and the second anchor cable AI, continue to excavate the first foundation pit and complete it.
在对第一锚索AⅠ和第二锚索AⅠ进行张拉时,第一锚索AⅠ和第二锚索AⅠ需要对土体进行切割,才能到达设定位置,并且张紧,在部分土质较硬的区域,或者土体中具有较大杂物时,会阻碍第一锚索AⅠ和第二锚索AⅠ对土体的切割,有时还会对第一锚索AⅠ和第二锚索AⅠ造成破坏。When tensioning the first anchor cable AⅠ and the second anchor cable AⅠ, the first anchor cable AⅠ and the second anchor cable AⅠ need to cut the soil to reach the set position and tensioned. Hard areas, or large debris in the soil, will hinder the cutting of the soil by the first anchor cable AⅠ and the second anchor cable AⅠ, and sometimes cause damage to the first anchor cable AⅠ and the second anchor cable AⅠ. destroy.
为避免上述情况的发生,在其他实施例中,在对第一锚索AⅠ和第二锚索AⅠ进行张拉前,首先在第一锚索AⅠ和第二锚索AⅠ所要经过的路径上开设张拉槽,使第一锚索AⅠ和第二锚索AⅠ布置在该张拉槽内,然后在对第一锚索AⅠ和第二锚索AⅠ进行张拉。In order to avoid the occurrence of the above situation, in other embodiments, before the first anchor cable AI and the second anchor cable AI are stretched, the first anchor cable AI and the second anchor cable AI are first opened on the path. The slot is stretched so that the first anchor cable AI and the second anchor cable AI are arranged in the tension slot, and then the first anchor cable AI and the second anchor cable AI are stretched.
实施例2Example 2
请参阅图3和图4,第二深层锚拉桩支护体系,其包括沿第一设定方向布置的若干根第二内排桩21,其中部分第二内排桩形成为第二锚索桩211,对应于每根第二锚索桩211均设置有一根第二锚桩221,第二锚桩221设置在所对应的第二锚索桩211的背离第二基坑150的一侧。Please refer to Figures 3 and 4, the second deep anchor pile support system, which includes a plurality of second inner row piles 21 arranged along a first set direction, part of the second inner row piles are formed as second anchor cables The pile 211 corresponds to each second anchor pile 211 provided with a second anchor pile 221, and the second anchor pile 221 is arranged on the side of the corresponding second anchor pile 211 away from the second foundation pit 150.
在第二内排桩21的内侧设置有一道第二内排锚索围檩A242。在第二锚桩221的顶部的外侧设置有一道第二外排锚索围檩23。在本实施例中,该第二外排锚索围檩23布置在地面上。在图4中,箭头820的指向表示实施例2中的第一设定方向的延伸方向。A second inner row of anchor rope purlin A242 is provided on the inner side of the second inner row of piles 21. A second outer row of anchor rope purlin 23 is provided on the outer side of the top of the second anchor pile 221. In this embodiment, the second outer row of anchor rope purlin 23 is arranged on the ground. In FIG. 4, the direction of the arrow 820 indicates the extending direction of the first set direction in the second embodiment.
第二锚桩221的桩底标高低于第二内排桩21的桩底标高,即第二锚桩221的桩底标高低于第二锚索桩211的桩底标高。且第二锚桩221与所对应的第二锚索桩211之间的第二净距离S2为8米。The elevation of the bottom of the second anchor pile 221 is lower than the elevation of the bottom of the second inner row of piles 21, that is, the elevation of the bottom of the second anchor pile 221 is lower than the elevation of the bottom of the second anchor pile 211. And the second net distance S2 between the second anchor pile 221 and the corresponding second anchor pile 211 is 8 meters.
在每根第二锚索桩211与所对应的第二锚桩221之间均设置有一组锚索AⅡ,每组锚索AⅡ均包括一根第一锚索AⅡ25和一根第二锚索AⅡ26。该第一锚索AⅡ25和第二锚索AⅡ26均为预应力锚索。每根第一锚索AⅡ25的两端分别称为第一前端A和第一后端A,每根第二锚索AⅡ26的两端分别称为第二前端A和第二后端A;A set of anchor cables AII is provided between each second anchor cable pile 211 and the corresponding second anchor pile 221, and each group of anchor cables AII includes a first anchor cable AII25 and a second anchor cable AII26. . The first anchor cable AII25 and the second anchor cable AII26 are both pre-stressed anchor cables. The two ends of each first anchor cable AII25 are called the first front end A and the first rear end A, respectively, and the two ends of each second anchor cable AII26 are called the second front end A and the second rear end A respectively;
该第一锚索AⅡ25的第一前端A贯穿所对应的第二锚索桩211后连接到第二内排锚索围檩A242上,该第一锚索AⅡ25的第一后端A沿倾斜方向向上延伸并贯穿第二锚桩221后连接到第二外排锚索围檩23上。The first front end A of the first anchor cable AII25 penetrates the corresponding second anchor cable pile 211 and then is connected to the second inner row of anchor cable purlins A242. The first rear end A of the first anchor cable AII25 is along the oblique direction It extends upward and penetrates through the second anchor pile 221 and then is connected to the second outer row of anchor rope purlin 23.
该第二锚索AⅡ26的第二前端A贯穿所对应的第二锚索桩211后连接到第二内排锚索围檩A242上,该第二锚索AⅡ26的第二后端A沿倾斜方向向下延伸并连接到第二锚桩221上。The second front end A of the second anchor cable AII26 penetrates the corresponding second anchor cable pile 211 and then is connected to the second inner row of anchor cable purlins A242, and the second rear end A of the second anchor cable AII26 is along the oblique direction It extends downward and is connected to the second anchor pile 221.
其中,第一锚索AⅡ25与水平面之间的夹角α2为30°;第一锚索AⅡ25与第二锚索AⅡ26之间的夹角β2为70°。The included angle α2 between the first anchor cable AII25 and the horizontal plane is 30°; the included angle β2 between the first anchor cable AII25 and the second anchor cable AII26 is 70°.
本实施例中,该第二内排桩21采用拉森钢板桩,各拉森钢板桩沿第一设定方向布置、且相互咬合,拉森钢板桩的腹板沿第一设定方向的方向延伸。该第二锚桩221采用钢管桩,各钢管桩沿第一设定方向间隔布置。In this embodiment, the second inner row of piles 21 adopts Larsen steel sheet piles. The Larsen steel sheet piles are arranged along the first set direction and interlock with each other. The webs of the Larsen steel sheet piles are along the direction of the first set direction. extend. The second anchor pile 221 adopts steel pipe piles, and the steel pipe piles are arranged at intervals along the first set direction.
本实施例中的第二内排锚索围檩A24由两排H型钢所形成,具体结构与实施例1中的第一内排锚索围檩A14类似,不再赘述。In this embodiment, the second inner row anchor rope purlin A24 is formed by two rows of H-shaped steel, and the specific structure is similar to the first inner row anchor rope purlin A14 in Embodiment 1, and will not be repeated.
第二外排锚索围檩23采用H型钢制作。The second outer row of anchor rope enclosing purlin 23 is made of H-shaped steel.
本实施例中,第一锚索AⅡ25和第二锚索AⅡ26与第二内排锚索围檩A242、第二外排锚索围檩23以及第二锚桩221的连接均采用钢索锚具来连接,连接方式均与实施例1类似,不再赘述。In this embodiment, the connections of the first anchor cable AII25 and the second anchor cable AII26 with the second inner row anchor cable purlin A242, the second outer row anchor cable purlin 23, and the second anchor pile 221 all use steel cable anchors. The connection methods are similar to those in Embodiment 1, and will not be repeated here.
本实施例中,增设了一道内排锚索围檩C241,对应于该道内排锚索围檩C,在每根第二锚索桩与所对应的第二锚桩之间均设置有一根第二锚索C27,每根第二锚索C的两端分别称为第二前端C和第二后端C。该内排锚索围檩C241位于第二内排锚索围檩A242的上方,且位于第二内排桩21的顶部的内侧。内排锚索围檩C241与第二内排锚索围檩A242的结构相同,不再赘述。In this embodiment, an inner row of anchor rope enclosing purlin C241 is added, corresponding to the inner row of anchor rope enclosing purlin C, a second anchor pile is provided between each second anchor pile and the corresponding second anchor pile. Two anchor cables C27, the two ends of each second anchor cable C are respectively called the second front end C and the second rear end C. The inner row of anchor rope purlins C241 is located above the second inner row of anchor rope purlins A242 and is located inside the top of the second inner row of piles 21. The structure of the inner row of anchor rope enclosure purlin C241 is the same as the structure of the second inner row of anchor rope enclosure purlin A242, and will not be repeated.
该第二锚索C的第二前端C贯穿所对应的第二锚索桩后连接到内排锚索围檩C241上,该第二锚索C的第二后端C沿倾斜方向向下延伸并连接到第二锚桩221上。第二锚索C与内排锚索围檩C241的连接方式同第二锚索AⅠ16与第一内排锚索围檩A14的连接方式,第二锚索C的与第二锚桩221的连接方式同第二锚索AⅠ16与第一锚桩121的连接方式。The second front end C of the second anchor cable C penetrates through the corresponding second anchor cable pile and then is connected to the inner row of anchor cable purlins C241, and the second rear end C of the second anchor cable C extends downward in the oblique direction And connected to the second anchor pile 221. The connection method of the second anchor cable C and the inner row anchor cable purlin C241 is the same as the connection method of the second anchor cable AⅠ16 and the first inner row anchor cable purlin A14, and the connection of the second anchor cable C to the second anchor pile 221 The method is the same as that of the second anchor cable AI16 and the first anchor pile 121.
在本实施例中,仅设置了一道内排锚索围檩C241及相应的第二锚索C27,可以理解,在其他实施例中,还可以设置两道以上的内排锚索围檩C241及相应的第二锚索C27。In this embodiment, only one inner row anchor cable enclosure C241 and the corresponding second anchor cable C27 are provided. It can be understood that in other embodiments, more than two inner row anchor cable enclosure purlins C241 and Corresponding second anchor cable C27.
本实施例中的第二内排桩和第二锚桩均沿竖直方向下沉到地下。In this embodiment, the second inner row of piles and the second anchor piles are both sunk into the ground in the vertical direction.
该第二深层锚拉桩支护体系的施工方法,包括以下步骤:The construction method of the second deep anchor pile support system includes the following steps:
(1)准备第二内排桩和第二锚桩,在作为第二锚索桩的第二内排桩的设定位置上形成有用于穿设第二锚索C27、第一锚索AⅡ25和第二锚索AⅡ26的内锚索孔,在第二锚桩上形成有用于穿设第二锚索C27、第一锚索AⅡ25和第二锚索AⅡ26的外锚索孔。(1) Prepare the second inner row of piles and the second anchor piles. The second inner row of piles as the second anchor piles is formed at the setting position for the second anchor cable C27, the first anchor cable AII25 and The inner anchor cable hole of the second anchor cable AⅡ26 is formed on the second anchor pile with outer anchor cable holes for piercing the second anchor cable C27, the first anchor cable AⅡ25 and the second anchor cable AⅡ26.
(2)将第二锚索C27、第一锚索AⅡ25和第二锚索AⅡ26分别自由地穿设在相应的内锚索孔内,然后将第二锚索桩及其他第二内排桩下沉到地下。将第二锚索C27和第二锚索AⅡ26分别穿设到相应的外锚索孔内,并在分别在第二锚索C27的第二后端C和第二锚索AⅡ26的第二后端A上安装钢索锚具,避免第二锚索C和第二锚索A脱出外锚索孔。将第二锚桩下沉到地下,安装第二外排锚索围檩。(2) Put the second anchor cable C27, the first anchor cable AⅡ25 and the second anchor cable AⅡ26 into the corresponding inner anchor cable holes freely, and then lower the second anchor cable pile and other second inner row piles Sink to the ground. Pass the second anchor cable C27 and the second anchor cable AII26 into the corresponding outer anchor cable holes, respectively, and at the second rear end C of the second anchor cable C27 and the second anchor cable AII26 respectively Install steel cable anchors on A to prevent the second anchor cable C and the second anchor cable A from coming out of the outer anchor cable hole. The second anchor pile is sunk into the ground, and the second outer row of anchor rope purlins is installed.
(3)开挖第二基坑,直到内排锚索围檩C的施工标高,暂停第二基坑的开挖,安装内排锚索围檩C,对第二锚索C进行张拉,并用钢索锚具将第二锚索C的第二前端C固定在内排锚索围檩C上。(3) Excavate the second foundation pit until the construction elevation of the inner row of anchor cables C, suspend the excavation of the second foundation pit, install the inner row of anchor cables C, and stretch the second anchor cable C. A steel cable anchor is used to fix the second front end C of the second anchor cable C on the inner row anchor cable enclosure C.
第二锚索C27连接到第二锚索桩和第二锚桩的方式与第二锚索AⅠ连接到第一锚索桩和第一锚桩的方式相同。The second anchor cable C27 is connected to the second anchor pile and the second anchor pile in the same manner as the second anchor cable AI is connected to the first anchor pile and the first anchor pile.
继续开挖第二基坑,直到第二外排锚索围檩23的施工标高,暂停第二基坑的开挖,安装第二外排锚索围檩23,并对第一锚索AⅡ25和第二锚索AⅡ26的张拉及固定。Continue to excavate the second foundation pit until the construction elevation of the second outer row of anchor rope purlin 23, suspend the excavation of the second foundation pit, install the second outer row of anchor rope purlin 23, and connect the first anchor rope AⅡ25 and Tension and fixation of the second anchor cable AⅡ26.
对第一锚索AⅡ25和第二锚索AⅡ26的张拉及固定与第一锚索AⅠ和第二锚索AⅠ的张拉及固定相同,不再赘述。The tension and fixation of the first anchor cable AII25 and the second anchor cable AII26 are the same as the tension and fixation of the first anchor cable AⅠ and the second anchor cable AⅠ, and will not be repeated.
继续土方开挖至第二基坑的设定深度。Continue earth excavation to the set depth of the second foundation pit.
实施例3Example 3
本实施例是在实施例2基础上的改进,相比实施例2,本实施例增设了一道内排锚索围檩B,并相应地增设了第一锚索B和第二锚索B。以下对本实施例进行说明。This embodiment is an improvement on the basis of Embodiment 2. Compared with Embodiment 2, this embodiment adds an inner row of anchor rope purlin B, and correspondingly adds a first anchor rope B and a second anchor rope B. This embodiment will be described below.
请参阅图5和图6,第三深层锚拉桩支护体系,其包括沿第一设定方向布置的若干根第三内排桩31,其中部分第三内排桩形成为第三锚索桩311,对应于每根第三锚索桩311均设置有一根第三锚桩321,第三锚桩321设置在所对应的第三锚索桩311的背离第三基坑160的一侧。Please refer to Figures 5 and 6, the third deep anchor pile support system, which includes a plurality of third inner row piles 31 arranged along a first set direction, part of the third inner row piles are formed as third anchor cables The pile 311 is provided with a third anchor pile 321 corresponding to each third anchor pile 311, and the third anchor pile 321 is arranged on the side of the corresponding third anchor pile 311 away from the third foundation pit 160.
在第三内排桩31的内侧设置有一道第三内排锚索围檩A342。在第三锚桩321的顶部的外侧设置有一道第三外排锚索围檩33。在本实施例中,该第三外排锚索围檩33布置在地面上。图6中的箭头830的指向表示实施例3中的第一设定方向的延伸方向。A third inner row of anchor rope purlin A342 is provided on the inner side of the third inner row of piles 31. A third outer row of anchor rope purlin 33 is provided outside the top of the third anchor pile 321. In this embodiment, the third outer row of anchor rope purlin 33 is arranged on the ground. The direction of the arrow 830 in FIG. 6 indicates the extending direction of the first set direction in the third embodiment.
第三锚桩321的桩底标高低于第三内排桩31的桩底标高,即第三锚桩321的桩底标高低于第三锚索桩311的桩底标高。且第三锚桩321与所对应的第三锚索桩311之间的第三净距离S3为10米。The elevation of the bottom of the third anchor pile 321 is lower than the elevation of the bottom of the third inner row of piles 31, that is, the elevation of the bottom of the third anchor pile 321 is lower than the elevation of the bottom of the third anchor pile 311. And the third clear distance S3 between the third anchor pile 321 and the corresponding third anchor pile 311 is 10 meters.
在每根第三锚索桩311与所对应的第三锚桩321之间均设置有一组锚索AⅢ,每组锚索AⅢ均包括一根第一锚索AⅢ35和一根第二锚索AⅢ36。A group of anchor cables AⅢ is arranged between each third anchor pile 311 and the corresponding third anchor pile 321, and each group of anchor cables AⅢ includes a first anchor cable AⅢ35 and a second anchor cable AⅢ36 .
该第三内排锚索围檩A342与实施例2中的第二内排锚索围檩A242的结构相同。第一锚索AⅢ35和第二锚索AⅢ36的安装方式同实施例2中的第一锚索AⅡ25和第二锚索AⅡ26的安装方式,不再赘述。The third inner row of anchor rope purlins A342 has the same structure as the second inner row of anchor rope purlins A242 in the second embodiment. The installation method of the first anchor cable AIII35 and the second anchor cable AIII36 is the same as the installation method of the first anchor cable AII25 and the second anchor cable AII26 in Embodiment 2, and will not be repeated.
本实施例中,第一锚索AⅢ35与水平面之间的夹角α3为20°;第一锚索AⅢ35与第二锚索AⅢ36之间的夹角β3为80°。In this embodiment, the angle α3 between the first anchor cable AIII35 and the horizontal plane is 20°; the angle β3 between the first anchor cable AIII35 and the second anchor cable AIII36 is 80°.
本实施例中,该第三内排桩31为组合钢板桩,该组合钢板桩由U型钢板桩315和H钢桩316组成。该第三锚桩321为H钢桩。In this embodiment, the third inner row of piles 31 is a combined steel sheet pile, and the combined steel sheet pile is composed of a U-shaped steel sheet pile 315 and an H steel pile 316. The third anchor pile 321 is an H steel pile.
内排锚索围檩CⅢ341以及第二锚索CⅢ37的安装方式均与实施例2中的内排锚索围檩C241以及第二锚索C27的安装方式相同。内排锚索围檩CⅢ341位于第三内排锚索围檩A342的上方,且位于第三内排桩31的顶部的内侧。The installation methods of the inner row anchor rope purlin CIII341 and the second anchor cable CIII37 are the same as the installation methods of the inner row anchor rope purlin C241 and the second anchor cable C27 in the second embodiment. The inner row of anchor rope purlin CIII341 is located above the third inner row of anchor rope purlin A342, and is located inside the top of the third inner row of piles 31.
本实施例中,增设了一道内排锚索围檩B343,该内排锚索围檩B343位于第三内排锚索围檩A342的下方,并安装在第三内排桩31的内侧。In this embodiment, an inner row of anchor rope purlin B343 is added. The inner row of anchor rope purlin B343 is located below the third inner row of anchor rope purlin A342 and is installed inside the third inner row of piles 31.
对应于该道内排锚索围檩B343,在每根第三锚索桩311与所对应的第三锚桩321之间均设置有一组锚索B,每组锚索B均包括一根第一锚索B38和一根第二锚索B39。该第一锚索B和一根第二锚索B均为预应力锚索。每根第一锚索B38的两端分别称为第一前端B和第一后端B。每根第二锚索B39的两端分别称为第二前端B和第二后端B。Corresponding to the inner row of anchor rope purlins B343, a group of anchor ropes B is arranged between each third anchor pile 311 and the corresponding third anchor pile 321, and each group of anchor ropes B includes a first Anchor rope B38 and a second anchor rope B39. Both the first anchor cable B and the second anchor cable B are pre-stressed anchor cables. The two ends of each first anchor cable B38 are called the first front end B and the first rear end B, respectively. The two ends of each second anchor cable B39 are called a second front end B and a second rear end B, respectively.
该第一锚索B的第一前端B贯穿第三锚索桩311后连接到内排锚索围檩B上,该第一锚索B的第一后端B沿倾斜方向向上延伸并连接到第三锚桩321上。The first front end B of the first anchor cable B penetrates through the third anchor cable pile 311 and then is connected to the inner row of anchor cable purlins B. The first rear end B of the first anchor cable B extends upward in the oblique direction and is connected to On the third anchor pile 321.
该第二锚索B的第二前端B贯穿第三锚索桩311后连接到内排锚索围檩B上,该第二锚索B的第二后端B沿倾斜方向向下延伸并连接到第三锚桩321上。The second front end B of the second anchor cable B penetrates the third anchor cable pile 311 and then is connected to the inner row of anchor cable purlins B, and the second rear end B of the second anchor cable B extends downward in the oblique direction and is connected To the third anchor pile 321.
内排锚索围檩B343的结构与第三内排锚索围檩A342的结构相同。第一锚索B38以及第二锚索B39与内排锚索围檩B343连接方式同第一锚索AⅢ35和第二锚索AⅢ36与第三内排锚索围檩A342的连接方式。The structure of the inner row of anchor rope purlin B343 is the same as that of the third inner row of anchor rope purlin A342. The connection mode of the first anchor cable B38 and the second anchor cable B39 with the inner row anchor cable purlin B343 is the same as the connection method of the first anchor cable AIII35 and the second anchor cable AIII36 with the third inner row anchor cable purlin A342.
第一锚索B38的第一前端贯穿所对应的第三锚索桩后连接到内排锚索围檩B343上,第一锚索B38的第一后端沿倾斜方向向上延伸并连接到所对应的第三锚桩321上。The first front end of the first anchor cable B38 penetrates the corresponding third anchor cable pile and is connected to the inner row of anchor cable purlins B343. The first rear end of the first anchor cable B38 extends upward in the inclined direction and is connected to the corresponding On the third anchor pile 321.
第二锚索B39的第二前端贯穿所对应的第三锚索桩后连接到内排锚索围檩B343上,第二锚索B39的第二后端沿倾斜方向向下延伸并连接到所对应的第三锚桩321上。The second front end of the second anchor cable B39 penetrates through the corresponding third anchor cable pile and is connected to the inner row of anchor cable purlins B343. The second rear end of the second anchor cable B39 extends downward in the oblique direction and is connected to the Corresponding to the third anchor pile 321.
本实施例中,同一组锚索B中的第一锚索B与第二锚索B之间的夹角为75°,且第一锚索B与水平面之间的夹角为30°。可以理解在其他实施例中,同一组锚索B中的第一锚索B与第二锚索B之间的夹角以及第一锚索B与水平面之间的夹角可以分别为50°和20°、80°和30°、100°和40°以及130°和45°。In this embodiment, the angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B is 75°, and the angle between the first anchor cable B and the horizontal plane is 30°. It can be understood that in other embodiments, the angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B and the angle between the first anchor cable B and the horizontal plane can be respectively 50° and 20°, 80° and 30°, 100° and 40°, and 130° and 45°.
可以理解,在其他实施例中,内排桩还可以为钢管桩或预制混凝土桩中的至少一种,锚桩还可以为钢板桩、组合钢板桩或预制混凝土桩中的至少一种。It can be understood that in other embodiments, the inner row of piles may also be at least one of steel pipe piles or precast concrete piles, and the anchor piles may also be at least one of steel sheet piles, combined steel sheet piles or precast concrete piles.
可以理解,在其他实施例中,该实施例3中的内排锚索围檩CⅢ341及相应的第二锚索CⅢ37可以取消,仅保留第三内排锚索围檩A342、内排锚索围檩B343以及相应的第一锚索AⅢ35、第二锚索AⅢ36、第一锚索B38和第二锚索B39。It can be understood that in other embodiments, the inner row anchor cable enclosure purlin CIII341 and the corresponding second anchor cable CIII37 in this embodiment 3 can be eliminated, and only the third inner row anchor cable enclosure purlin A342 and the inner row anchor cable enclosure are retained. Purlin B343 and corresponding first anchor cable AIII35, second anchor cable AIII36, first anchor cable B38 and second anchor cable B39.
本实施例中的第三内排桩和第三锚桩均沿竖直方向下沉到地下。In this embodiment, the third inner row of piles and the third anchor pile are both sunk into the ground in the vertical direction.
该第三深层锚拉桩支护体系的施工方法,包括以下步骤:The construction method of the third deep anchor pile support system includes the following steps:
(1)准备第三内排桩和第三锚桩,在作为第三锚索桩的第三内排桩的设定位置上形成有用于穿设第二锚索CⅢ37、第一锚索AⅢ35、第二锚索AⅢ36、第一锚索B38和第二锚索B39的内锚索孔,在第三锚桩上形成有用于穿设第二锚索CⅢ37、第一锚索AⅢ35、第二锚索AⅢ36、第一锚索B38和第二锚索B39的外锚索孔。(1) Prepare the third inner row of piles and the third anchor pile, and form the third inner row of piles as the third anchor pile at the setting position for piercing the second anchor cable CⅢ37, the first anchor cable AⅢ35, The inner anchor cable holes of the second anchor cable AⅢ36, the first anchor cable B38 and the second anchor cable B39 are formed on the third anchor pile for piercing the second anchor cable CⅢ37, the first anchor cable AⅢ35, and the second anchor cable AⅢ36, the outer anchor cable hole of the first anchor cable B38 and the second anchor cable B39.
(2)将第二锚索CⅢ37、第一锚索AⅢ35、第二锚索AⅢ36、第一锚索B38和第二锚索B39分别自由地穿设在相应的内锚索孔内,然后将第三锚索桩及其他第三内排桩下沉到地下。将第二锚索CⅢ37、第二锚索AⅢ36、第一锚索B38和第二锚索B39分别穿设到相应的外锚索孔内,并分别在第二锚索CⅢ37第二后端C、第二锚索AⅢ36的第二后端A、第一锚索B38的第一后端B、以及第二锚索B39的第二后端B上安装钢索锚具,避免各锚索脱出外锚索孔。将第三锚桩下沉到地下,安装第三外排锚索围檩。(2) Put the second anchor cable CⅢ37, the first anchor cable AⅢ35, the second anchor cable AⅢ36, the first anchor cable B38 and the second anchor cable B39 into the corresponding inner anchor cable holes freely, and then set the first anchor cable Three-anchor piles and other third inner-row piles sink to the ground. Pass the second anchor rope CⅢ37, the second anchor rope AⅢ36, the first anchor rope B38 and the second anchor rope B39 into the corresponding outer anchor rope holes respectively, and respectively in the second anchor rope CⅢ37 second rear end C, Install steel cable anchors on the second rear end A of the second anchor cable AⅢ36, the first rear end B of the first anchor cable B38, and the second rear end B of the second anchor cable B39 to prevent each anchor cable from falling out of the outer anchor Sokong. The third anchor pile is sunk into the ground, and the third outer row of anchor rope purlins is installed.
(3)开挖第三基坑,(3) Excavate the third foundation pit,
依照开挖第二基坑的步骤完成内排锚索围檩CⅢ和第二锚索CⅢ安装,并完成第三内排锚索围檩A、第一锚索AⅢ和第二锚索AⅢ的安装。Follow the steps of excavating the second foundation pit to complete the installation of the inner row of anchor cables CⅢ and the second anchor cable CⅢ, and complete the installation of the third inner row of anchor cables A, the first anchor cable AⅢ and the second anchor cable AⅢ .
继续开挖第三基坑,直到内排锚索围檩B的施工标高,暂停第三基坑的开挖,安装内排锚索围檩B,对第一锚索B和第二锚索B进行张拉,并用钢索锚具将第一锚索B和第二锚索B固定在内排锚索围檩B上。Continue to excavate the third foundation pit until the construction elevation of the inner row of anchor rope purlin B. Suspend the excavation of the third foundation pit, install the inner row of anchor rope surrounding purlin B, and fix the first anchor rope B and the second anchor rope B. Tension is performed, and the first anchor rope B and the second anchor rope B are fixed on the inner row of anchor rope purlins B with steel rope anchors.
继续开挖第三基坑并完成。Continue to excavate the third foundation pit and complete it.
实施例4Example 4
本实施例是在实施例1基础上的改进,与实施例1基本相同,其不同在于,第四锚桩421倾斜设置,具体为由下向上朝远离基坑方向的一侧倾斜,第四锚桩421与竖直方向的夹角θ为10°。即第四锚桩421朝向基坑外侧的倾斜角为10°。可以理解,在其它实施例中,第四锚桩421朝向基坑外侧的倾斜角还可以为5°、15°、20°或30°。This embodiment is an improvement on the basis of embodiment 1. It is basically the same as embodiment 1. The difference is that the fourth anchor pile 421 is arranged obliquely. The angle θ between the pile 421 and the vertical direction is 10°. That is, the inclination angle of the fourth anchor pile 421 toward the outside of the foundation pit is 10°. It can be understood that in other embodiments, the inclination angle of the fourth anchor pile 421 toward the outside of the foundation pit may also be 5°, 15°, 20°, or 30°.
且第四锚桩421与所对应的第四锚索桩411之间的第四净距离S4为3米。And the fourth clear distance S4 between the fourth anchor pile 421 and the corresponding fourth anchor pile 411 is 3 meters.
图16为图15中D-D向的截面图,其中D-D截面位于地面所在的平面内。Fig. 16 is a cross-sectional view taken along the direction D-D in Fig. 15, where the cross-section D-D is located in the plane where the ground is located.
本实施例的图15和图16与图1和图2中相同的标记表示相同的结构部件。The same reference numerals in FIGS. 15 and 16 of this embodiment as in FIGS. 1 and 2 denote the same structural components.
将锚桩倾斜设置主要应用于施工范围较少的区域,当然施工范围较大的区域也可使用。The inclined setting of anchor piles is mainly used in areas with a small construction area. Of course, areas with a large construction area can also be used.
实施例5Example 5
本实施例是在实施例4基础上的改进,该实施例与实施例4基本相同,其不同在于锚桩的倾斜方向。This embodiment is an improvement on the basis of Embodiment 4. This embodiment is basically the same as Embodiment 4, and the difference lies in the inclination direction of the anchor pile.
请参阅图17,本实施例中,第五锚桩521由下向上朝基坑内部方向的一侧倾斜,而且本实施例中,在竖直方向上,第五锚桩521的桩底向外伸出施工红线区域,在图17中,虚线500表示施工红线。当第五锚桩521的桩顶仍位于施工红线范围内,在基坑施工结束后,拔除第五锚桩521后,不会造成地下结构超出施工红线范围。本实施例适宜于基坑边缘距离施工红线较窄的情况,本实施例中,第五锚索桩511与施工红线之间的距离为1.2米,将第五锚桩521倾斜设置,并使第五锚桩的桩底向外伸出施工红线后,在保证地面施工仍符合施工要求的情况下,增大第五锚索桩511与第五锚桩521之间的土体量,以提高土体对第五锚桩521的抱合力,提供足量的抗拔能力。Referring to FIG. 17, in this embodiment, the fifth anchor pile 521 is inclined from bottom to top toward one side of the inner direction of the foundation pit, and in this embodiment, in the vertical direction, the bottom of the fifth anchor pile 521 extends outward Out of the construction red line area, in Figure 17, the dashed line 500 represents the construction red line. When the pile top of the fifth anchor pile 521 is still located within the construction red line, after the foundation pit construction is completed, after the fifth anchor pile 521 is removed, the underground structure will not exceed the construction red line. This embodiment is suitable for situations where the edge of the foundation pit is narrower from the construction red line. In this embodiment, the distance between the fifth anchor pile 511 and the construction red line is 1.2 meters. After the bottom of the five-anchor pile extends out of the construction red line, while ensuring that the ground construction still meets the construction requirements, increase the amount of soil between the fifth anchor pile 511 and the fifth anchor pile 521 to improve the soil The cohesive force of the body on the fifth anchor pile 521 provides sufficient resistance to pulling out.
本实施例的图17与图15中相同的标记表示相同的结构部件。将锚桩倾斜设置主要应用于施工范围较少的区域,当然施工范围较大的区域也可使用。The same reference numerals in FIG. 17 and FIG. 15 of this embodiment denote the same structural components. The inclined setting of anchor piles is mainly used in areas with a small construction area. Of course, areas with a large construction area can also be used.

Claims (10)

  1. 一种深层锚拉桩支护体系,其特征在于,包括沿第一设定方向布置的若干根内排桩,至少有一根内排桩形成为锚索桩,对应于每根锚索桩均设置有一根锚桩,锚桩设置在所对应的锚索桩的背离基坑的一侧;A deep anchor pile support system, which is characterized in that it comprises a plurality of inner row piles arranged along a first set direction, at least one of the inner row piles is formed as an anchor pile, which is set corresponding to each anchor pile There is an anchor pile, which is set on the side of the corresponding anchor pile away from the foundation pit;
    在每根锚索桩与所对应的锚桩之间均设置有一组锚索A,每组锚索A均包括一根第一锚索A和一根第二锚索A,该第一锚索A和第二锚索A均为预应力锚索;每根第一锚索A的两端分别称为第一前端A和第一后端A,每根第二锚索A的两端分别称为第二前端A和第二后端A;A group of anchor cables A is arranged between each anchor pile and the corresponding anchor pile. Each group of anchor cables A includes a first anchor cable A and a second anchor cable A. The first anchor cable A and the second anchor cable A are both pre-stressed anchor cables; the two ends of each first anchor cable A are called the first front end A and the first rear end A respectively, and the two ends of each second anchor cable A are called respectively Is the second front end A and the second rear end A;
    在内排桩的内侧设置有一道内排锚索围檩A;在锚桩的顶部的外侧设置有一道外排锚索围檩;An inner row of anchor rope purlins A is provided on the inner side of the inner row of piles; an outer row of anchor rope purlins is provided on the outer side of the top of the anchor piles;
    该第一锚索A的第一前端A贯穿所对应的锚索桩后连接到内排锚索围檩A上,该第一锚索A的第一后端A沿倾斜方向向上延伸并贯穿所对应的锚桩后连接到外排锚索围檩上;The first front end A of the first anchor cable A passes through the corresponding anchor cable pile and is connected to the inner row of anchor cable purlins A, and the first rear end A of the first anchor cable A extends upward in the oblique direction and passes through the The corresponding anchor piles are then connected to the outer row of anchor rope purlins;
    该第二锚索A的第二前端A贯穿所对应的锚索桩后连接到内排锚索围檩A上,该第二锚索A的第二后端A沿倾斜方向向下延伸并连接到所对应的锚桩上。The second front end A of the second anchor cable A passes through the corresponding anchor cable pile and then is connected to the inner row of anchor cable purlins A, and the second rear end A of the second anchor cable A extends downward in the oblique direction and is connected To the corresponding anchor pile.
  2. 根据权利要求1所述的深层锚拉桩支护体系,其特征在于,The deep anchored pile supporting system according to claim 1, characterized in that:
    第一锚索A与水平面之间的夹角为15-30°,第一锚索A与第二锚索A之间的夹角为50-120°,且同一组锚索A中的第一锚索A与水平面之间的夹角小于第二锚索A与水平面之间的夹角。The angle between the first anchor cable A and the horizontal plane is 15-30°, the angle between the first anchor cable A and the second anchor cable A is 50-120°, and the first anchor cable A in the same group The angle between the anchor cable A and the horizontal plane is smaller than the angle between the second anchor cable A and the horizontal plane.
  3. 根据权利要求1所述的深层锚拉桩支护体系,其特征在于,The deep anchored pile supporting system according to claim 1, characterized in that:
    该内排锚索围檩A由两排型钢所形成,该两排型钢均沿水平方向延伸且沿竖直方向间隔并排布置,第一锚索A的第一前端A和第二锚索A的第二前端A均穿过该两排型钢竖直方向之间的间隙后被固定在内排锚索围檩A上。The inner row of anchor rope purlins A is formed by two rows of section steels, both of which extend in the horizontal direction and are arranged side by side at intervals in the vertical direction. The first front end A of the first anchor cable A and the second anchor cable A The second front end A passes through the vertical gap between the two rows of section steels and is fixed on the inner row of anchor rope surrounding purlins A.
  4. 根据权利要求1-3任一项所述的深层锚拉桩支护体系,其特征在于,The deep anchored pile supporting system according to any one of claims 1-3, characterized in that:
    在内排桩的内侧还设置有至少一道内排锚索围檩B,对应于每道内排锚索围檩B,在每根锚索桩与所对应的锚桩之间均设置有一组锚索B,每组锚索B均包括一根第一锚索B和一根第二锚索B,该第一锚索B和第二锚索B均为预应力锚索;每根第一锚索B的两端分别称为第一前端B和第一后端B,每根第二锚索B的两端分别称为第二前端B和第二后端B;At least one inner row of anchor rope purlins B is also arranged on the inner side of the inner row of piles, corresponding to each inner row of anchor rope purlins B, and a set of anchor ropes is arranged between each anchor pile and the corresponding anchor pile B. Each group of anchor cables B includes a first anchor cable B and a second anchor cable B. The first anchor cable B and the second anchor cable B are both pre-stressed anchor cables; each first anchor cable The two ends of B are respectively called the first front end B and the first rear end B, and the two ends of each second anchor cable B are called the second front end B and the second rear end B respectively;
    该第一锚索B的第一前端B贯穿所对应的锚索桩后连接到所对应的内排锚索围檩B上,该第一锚索B的第一后端B沿倾斜方向向上延伸并连接到所对应的锚桩上;The first front end B of the first anchor cable B penetrates the corresponding anchor cable pile and then is connected to the corresponding inner row of anchor cable purlins B, and the first rear end B of the first anchor cable B extends upward in the oblique direction And connect to the corresponding anchor pile;
    该第二锚索B的第二前端B贯穿所对应的锚索桩后连接到所对应的内排锚索围檩B上,该第二锚索B的第二后端B沿倾斜方向向下延伸并连接到所对应的锚桩上。The second front end B of the second anchor cable B penetrates the corresponding anchor cable pile and then is connected to the corresponding inner row anchor cable purlin B, and the second rear end B of the second anchor cable B is downward in the inclined direction Extend and connect to the corresponding anchor pile.
  5. 根据权利要求4所述的深层锚拉桩支护体系,其特征在于,The deep anchored pile supporting system according to claim 4, characterized in that:
    同一组锚索B中的第一锚索B与第二锚索B之间的夹角为50-130°,且第一锚索B与水平面之间的夹角为20-45°。The angle between the first anchor cable B and the second anchor cable B in the same group of anchor cables B is 50-130°, and the angle between the first anchor cable B and the horizontal plane is 20-45°.
  6. 根据权利要求1-3任一项所述的深层锚拉桩支护体系,其特征在于,The deep anchored pile supporting system according to any one of claims 1-3, characterized in that:
    在内排桩的内侧还设置有一道内排锚索围檩C,对应于该道内排锚索围檩C,在每根锚索桩与所对应的锚桩之间均设置有一根第二锚索C,每根第二锚索C的两端分别称为第二前端C和第二后端C;该第二锚索C为预应力锚索;There is also an inner row of anchor rope surrounding purlins C on the inner side of the inner row of piles, corresponding to the inner row of anchor rope surrounding purlins C of the road, and a second anchor cable is arranged between each anchor rope pile and the corresponding anchor pile. C, the two ends of each second anchor cable C are respectively called the second front end C and the second rear end C; the second anchor cable C is a prestressed anchor cable;
    该第二锚索C的第二前端C贯穿所对应的锚索桩后连接到内排锚索围檩C上,该第二锚索C的第二后端C沿倾斜方向向下延伸并连接到所对应的锚桩上;The second front end C of the second anchor cable C penetrates through the corresponding anchor cable pile and then is connected to the inner row of anchor cable purlins C, and the second rear end C of the second anchor cable C extends downward in the oblique direction and is connected To the corresponding anchor pile;
    该道内排锚索围檩C位于内排锚索围檩A的上方。The inner row of anchor rope purlin C is located above the inner row of anchor rope purlin A.
  7. 根据权利要求1所述的深层锚拉桩支护体系,其特征在于,该内排桩为H钢桩、钢板桩、组合钢板桩、钢管桩或预制混凝土桩中的至少一种,该锚桩为H钢桩、钢板桩、组合钢板桩、钢管桩或预制混凝土桩中的至少一种。The deep anchor pile support system according to claim 1, wherein the inner row of piles is at least one of H steel piles, steel sheet piles, composite steel sheet piles, steel pipe piles or precast concrete piles, and the anchor The pile is at least one of H steel pile, steel sheet pile, combined steel sheet pile, steel pipe pile or precast concrete pile.
  8. 根据权利要求1所述的深层锚拉桩支护体系,其特征在于,The deep anchored pile supporting system according to claim 1, characterized in that:
    锚桩的桩底标高低于锚索桩的桩底标高。The elevation of the bottom of the anchor pile is lower than the elevation of the bottom of the anchor pile.
  9. 一种深层锚拉桩支护体系的施工方法,其用于施工权利要求1所述的深层锚拉桩支护体系,其特征在于,包括以下步骤:A construction method of a deep anchored pile supporting system, which is used to construct the deep anchored pile supporting system of claim 1, characterized in that it comprises the following steps:
    (1)准备内排桩和锚桩,在作为锚索桩的内排桩的设定位置上形成有内排锚索孔,在锚桩的设定位置上形成有外排锚索孔;(1) Prepare the inner row of piles and anchor piles. The inner row of anchor holes is formed at the set position of the inner row of piles as the anchor pile, and the outer row of anchor holes is formed at the set position of the anchor pile;
    (2)将第一锚索A和第二锚索A自由地穿设在锚索桩上的前排锚索孔内,然后将内排桩沉入地下,第一锚索A的一部分和第二锚索A的一部分随锚索桩沉入地下,并使第一锚索A的第一后端A朝向外侧并保持在地面,以及使第二锚索A的第二后端A朝向外侧并保持在地面;(2) Pass the first anchor cable A and the second anchor cable A freely in the front row of anchor cable holes on the anchor piles, and then sink the inner row of piles into the ground. A part of the first anchor cable A and the first A part of the second anchor cable A sinks into the ground along with the anchor cable pile, and the first rear end A of the first anchor cable A faces outward and remains on the ground, and the second rear end A of the second anchor cable A faces outward and Keep on the ground
    将第二锚索A的第二后端A固定在锚桩的后端设定位置上,然后将锚桩沉入地下;Fix the second rear end A of the second anchor cable A at the set position of the rear end of the anchor pile, and then sink the anchor pile into the ground;
    (3)开挖基坑,直到内排锚索围檩A的施工标高,然后安装内排锚索围檩A;(3) Excavate the foundation pit up to the construction elevation of the inner row of anchor cables and purlin A, and then install the inner row of anchor cables and purlin A;
    在将第一锚索A的第二后端A依次自由地穿过锚桩上所对应的外排锚索孔及外排锚索围檩上所对应的围檩锚索孔后,对第一锚索A进行张拉,使第一锚索A产生内应力,形成为预应力锚索;并将第一锚索A的第一前端A固定在内排锚索围檩A上,将第一锚索A的第一后端A固定在外排锚索围檩上;After passing the second rear end A of the first anchor cable A freely through the corresponding outer row anchor cable holes on the anchor piles and the corresponding surrounding purlin anchor cable holes on the outer row anchor cable purlins, The anchor cable A is stretched to cause the first anchor cable A to generate internal stress and form a pre-stressed anchor cable; fix the first front end A of the first anchor cable A on the inner row of anchor cable purlins A, and fix the first The first rear end A of the anchor cable A is fixed on the outer row of anchor cable purlins;
    对第二锚索A进行张拉,使第二锚索A产生内应力,形成为预应力锚索,并将第二锚索A的第二前端A固定在内排锚索围檩A上;Tension the second anchor cable A to generate internal stress on the second anchor cable A to form a pre-stressed anchor cable, and fix the second front end A of the second anchor cable A on the inner row of anchor cable purlins A;
    对第一锚索A和第二锚索A的张拉同步进行或分步进行;The tensioning of the first anchor cable A and the second anchor cable A is performed synchronously or step by step;
    (4)开挖基坑到设计标高,施工地下室的主体结构,同步进行换撑结构的施工;然后拆除围檩,拔除锚桩。(4) Excavate the foundation pit to the design elevation, construct the main structure of the basement, and simultaneously carry out the construction of the support structure; then remove the purlin and pull out the anchor pile.
  10. 根据权利要求9所述的施工方法,其特征在于,在对第一锚索A和第二锚索A进行张拉前,首先在第一锚索A和第二锚索A所要经过的路径上开设张拉槽,使第一锚索A和第二锚索A均布置在该张拉槽内。The construction method according to claim 9, characterized in that, before the first anchor cable A and the second anchor cable A are stretched, the first anchor cable A and the second anchor cable A are to be traversed on the path A tension slot is opened so that both the first anchor cable A and the second anchor cable A are arranged in the tension slot.
PCT/CN2020/102446 2020-03-31 2020-07-16 Deep cable-anchored pile supporting system and construction method therefor WO2021196451A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202010242064.8 2020-03-31
CN202010242064.8A CN111335327B (en) 2020-03-31 2020-03-31 Deep anchor pile supporting system and construction method thereof

Publications (1)

Publication Number Publication Date
WO2021196451A1 true WO2021196451A1 (en) 2021-10-07

Family

ID=71178624

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/102446 WO2021196451A1 (en) 2020-03-31 2020-07-16 Deep cable-anchored pile supporting system and construction method therefor

Country Status (2)

Country Link
CN (1) CN111335327B (en)
WO (1) WO2021196451A1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113981983A (en) * 2021-10-19 2022-01-28 中国化学工程第十六建设有限公司 Foundation pit support-free supporting structure and method
CN114032932A (en) * 2021-12-15 2022-02-11 中煤科工重庆设计研究院(集团)有限公司 Construction method of mixed retaining structure
CN114197489A (en) * 2021-12-31 2022-03-18 中国煤炭地质总局水文地质局 Method for reinforcing slope protection pile during deepening of foundation pit
CN114319387A (en) * 2022-01-28 2022-04-12 北京建工集团有限责任公司 Composite supporting structure positioning device and construction method thereof
CN114482072A (en) * 2022-03-04 2022-05-13 西南交通大学 Soft soil close-connection double-foundation-pit combined anchor design method, supporting structure and construction method
CN114753378A (en) * 2022-05-05 2022-07-15 中铁十局集团第五工程有限公司 Upper-span rail transit foundation pit reinforcing construction method
CN115198760A (en) * 2022-07-12 2022-10-18 中国建筑第八工程局有限公司 Support system for soft soil geological pit and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335327B (en) * 2020-03-31 2024-06-07 江苏东合南岩土科技股份有限公司 Deep anchor pile supporting system and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5244316A (en) * 1991-05-17 1993-09-14 Wright William M Borer-resistant waterfront retaining bulkhead
KR20110003815A (en) * 2009-07-06 2011-01-13 이하란 Prestressed temporary construction structure and method for land-side protection wall using the same
CN102767186A (en) * 2012-07-16 2012-11-07 中铁隧道集团有限公司 Foundation pit containment structure with prestress ribs on vertical soil-retaining structure and construction method
CN204780938U (en) * 2015-06-12 2015-11-18 唐孟雄 Novel recoverable anchor formula double row pile supporting construction that draws
CN206887962U (en) * 2017-02-18 2018-01-16 北京东地岩土工程有限公司 Soil nailing and anchor pole combined type double-row pile foundation pit support structure
CN207109812U (en) * 2017-07-12 2018-03-16 浙江坤德创新岩土工程有限公司 A kind of reinforced anchor rod support system
CN207260160U (en) * 2017-09-12 2018-04-20 甘肃中建市政工程勘察设计研究院 The strong anchor supporting construction of thin stake that a kind of long-short pile combines
CN108612081A (en) * 2018-05-18 2018-10-02 中铁二院昆明勘察设计研究院有限责任公司 A kind of combined type multilayer Larsen steel sheet pile combination supporting system and construction method
CN111335327A (en) * 2020-03-31 2020-06-26 江苏东合南岩土科技股份有限公司 Deep anchor pile supporting system and construction method thereof

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120132818A (en) * 2011-05-30 2012-12-10 쌍용건설 주식회사 Reinforcement structure for soil retaining wall using raker and reinforcement method thereof
CN104328788B (en) * 2014-09-26 2016-02-10 安徽水利开发股份有限公司 Double rows slip casting stake with draw shotcrete layer combined supporting construction method
CN104612160B (en) * 2014-11-18 2016-03-30 中大建设有限公司 A kind of next-door neighbour's existing building pit maintenance soil structure and construction method
CN105155548B (en) * 2015-06-02 2018-05-22 谢纯 A kind of drag-line double-row pile (wall) supporting construction
CN205205833U (en) * 2015-12-10 2016-05-04 吕光辉 Soil nail and stock combined type double row pile underground structure
CN108589738A (en) * 2018-05-22 2018-09-28 中国建筑第八工程局有限公司 Half gravity dam formula foundation pit enclosure structure and its construction method
CN110820763A (en) * 2019-11-29 2020-02-21 兰州理工大学 Truss type cast-in-situ bored pile supporting method for mucky soil deep foundation pit
CN212104116U (en) * 2020-03-31 2020-12-08 江苏东合南岩土科技股份有限公司 Deep anchor pile supporting system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5244316A (en) * 1991-05-17 1993-09-14 Wright William M Borer-resistant waterfront retaining bulkhead
KR20110003815A (en) * 2009-07-06 2011-01-13 이하란 Prestressed temporary construction structure and method for land-side protection wall using the same
CN102767186A (en) * 2012-07-16 2012-11-07 中铁隧道集团有限公司 Foundation pit containment structure with prestress ribs on vertical soil-retaining structure and construction method
CN204780938U (en) * 2015-06-12 2015-11-18 唐孟雄 Novel recoverable anchor formula double row pile supporting construction that draws
CN206887962U (en) * 2017-02-18 2018-01-16 北京东地岩土工程有限公司 Soil nailing and anchor pole combined type double-row pile foundation pit support structure
CN207109812U (en) * 2017-07-12 2018-03-16 浙江坤德创新岩土工程有限公司 A kind of reinforced anchor rod support system
CN207260160U (en) * 2017-09-12 2018-04-20 甘肃中建市政工程勘察设计研究院 The strong anchor supporting construction of thin stake that a kind of long-short pile combines
CN108612081A (en) * 2018-05-18 2018-10-02 中铁二院昆明勘察设计研究院有限责任公司 A kind of combined type multilayer Larsen steel sheet pile combination supporting system and construction method
CN111335327A (en) * 2020-03-31 2020-06-26 江苏东合南岩土科技股份有限公司 Deep anchor pile supporting system and construction method thereof

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113981983A (en) * 2021-10-19 2022-01-28 中国化学工程第十六建设有限公司 Foundation pit support-free supporting structure and method
CN113981983B (en) * 2021-10-19 2023-05-02 中国化学工程第十六建设有限公司 Foundation pit support-free supporting structure and method
CN114032932A (en) * 2021-12-15 2022-02-11 中煤科工重庆设计研究院(集团)有限公司 Construction method of mixed retaining structure
CN114197489A (en) * 2021-12-31 2022-03-18 中国煤炭地质总局水文地质局 Method for reinforcing slope protection pile during deepening of foundation pit
CN114319387A (en) * 2022-01-28 2022-04-12 北京建工集团有限责任公司 Composite supporting structure positioning device and construction method thereof
CN114319387B (en) * 2022-01-28 2022-07-01 北京建工集团有限责任公司 Construction method of composite supporting structure positioning device
CN114482072A (en) * 2022-03-04 2022-05-13 西南交通大学 Soft soil close-connection double-foundation-pit combined anchor design method, supporting structure and construction method
CN114482072B (en) * 2022-03-04 2023-01-31 西南交通大学 Soft soil close-connection double-foundation-pit combined anchor design method, supporting structure and construction method
CN114753378A (en) * 2022-05-05 2022-07-15 中铁十局集团第五工程有限公司 Upper-span rail transit foundation pit reinforcing construction method
CN115198760A (en) * 2022-07-12 2022-10-18 中国建筑第八工程局有限公司 Support system for soft soil geological pit and construction method thereof

Also Published As

Publication number Publication date
CN111335327A (en) 2020-06-26
CN111335327B (en) 2024-06-07

Similar Documents

Publication Publication Date Title
WO2021196451A1 (en) Deep cable-anchored pile supporting system and construction method therefor
WO2021196449A1 (en) Foundation pit supporting system and construction method therefor
CN108343071A (en) A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN113417649B (en) Underground tunnel small-section to large-section expanding excavation method
WO2023024348A1 (en) Recyclable prestressed support system and construction method
CN111119198A (en) A reinforced structure that is used for SMW worker method stake to strut system
US20240263419A1 (en) Provisional facility for retaining earth by using ground anchors and guide brackets for stepwise retention during deep excavation, and method for constructing same
CN114319376A (en) Deep foundation pit supporting and excavating structure for complicated irregular staged implementation and construction method
CN111593739A (en) Cement mixing pile enclosure wall-profile steel cantilever type combined support
CN212104116U (en) Deep anchor pile supporting system
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
CN112195698A (en) Construction method for road crossing under road section with heavy traffic pressure
CN217974413U (en) Deep and shallow foundation pit supporting construction structure
CN209941693U (en) Open cut interval support system of crossing river
CN216739669U (en) Steel pipe inclined support resisting foundation pit support micro-deformation
CN111350193A (en) Open type foundation pit supporting method
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN212404803U (en) Tunnel inverted arch combined type cableway bridge abutment
CN211816326U (en) Combined retaining structure of half H-shaped anti-slide pile and retaining plate
JPH1077644A (en) Earthquake resisting pile foundation construction method
CN111485560A (en) Deep foundation pit supporting structure under ultra-wide pipeline and deep foundation pit construction method under ultra-wide pipeline
CN117107784B (en) Cover-excavation reverse construction method adopting recyclable steel pipe pile
CN109056717A (en) It is a kind of without support suspension device and its construction method
CN116220700B (en) Prestressed active support control method for underground excavation underground engineering
CN220565238U (en) Pile anchor and inner support combined supporting system suitable for large-height-difference deep foundation pit

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20928860

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20928860

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 20928860

Country of ref document: EP

Kind code of ref document: A1