WO2021174794A1 - Monitoring and verifying system and method for overall failure mode of soil-rock dual-element side slope - Google Patents

Monitoring and verifying system and method for overall failure mode of soil-rock dual-element side slope Download PDF

Info

Publication number
WO2021174794A1
WO2021174794A1 PCT/CN2020/113602 CN2020113602W WO2021174794A1 WO 2021174794 A1 WO2021174794 A1 WO 2021174794A1 CN 2020113602 W CN2020113602 W CN 2020113602W WO 2021174794 A1 WO2021174794 A1 WO 2021174794A1
Authority
WO
WIPO (PCT)
Prior art keywords
slope
displacement
monitoring
soil
rock
Prior art date
Application number
PCT/CN2020/113602
Other languages
French (fr)
Chinese (zh)
Inventor
李连祥
贾斌
李胜群
韩志霄
侯颖雪
Original Assignee
山东大学
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 山东大学 filed Critical 山东大学
Priority to AU2020433233A priority Critical patent/AU2020433233B2/en
Publication of WO2021174794A1 publication Critical patent/WO2021174794A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Definitions

  • the invention relates to the field of slope failure mode monitoring, in particular to a monitoring verification system and method for the overall failure mode of a soil-rock dual-element slope.
  • the present invention discloses a monitoring verification system and method for the overall failure mode of a soil-rock dual-element slope.
  • the failure mode of the slope can also provide guidance for the subsequent construction of the slope support structure.
  • the embodiment of the present invention proposes a method for monitoring and verifying the overall failure mode of a dual-element soil and rock slope, which includes the following steps:
  • step 6) Compare the slope slip line obtained in step 5) with the slip line obtained by the finite element method. If there is no difference, use the finite element software to simulate the next supporting structure and guide the construction. If there is a difference , Re-run finite element simulation, and compare again until there is no difference.
  • the deployment standards of the monitoring solution in step 2) are as follows:
  • the leveling base point needs to be placed on the top of the slope and outside the impact distance of the slope construction.
  • the impact distance is determined by the height of the slope.
  • the construction has the largest surface displacement of the slope top The scope of influence will not exceed the value of the thickness of the soil plus fully weathered rock layer.
  • the purpose of the monitoring scheme used in the present invention is to obtain the stability of the soil-rock dual-element slope during construction. Since the slope is composed of different stratums, in order to verify whether the interface will be A sudden change occurs, so most of the measuring points of the inclinometer tube are arranged at the interface of each layer, and a few are arranged inside the soil layer. Generally, the monitoring range of the inclinometer tube should exceed the area where slippage occurs during the finite element calculation (at least one inclinometer tube should be arranged outside the slip surface), and a monitoring point should be arranged at the soil-rock interface.
  • the slope top displacement monitoring point is arranged at the position 1m and 2m away from the intersection line of the slope top and the slope surface.
  • step 3 the specific steps of step 3) are as follows:
  • a level is arranged at the base point of the level.
  • the inclinometer tubes matched with the inclinometer should be pre-embedded at the displacement points of the deep soil.
  • the inclinometer tubes should be measured every 1m to ensure that the displacements of the soil layers at different depths are measured.
  • Inclined pipes should be arranged as far as possible at the interface of stratum, and multiple rows of inclinometer pipes are arranged to form multiple rows of deep soil displacement monitoring points.
  • step 6 the specific steps of step 6) are as follows:
  • step 5 verify the slip line obtained by the finite element software. If the difference between the two is not large, it can indicate that the calculation result of the finite element software is reliable. Calculate the construction steps to improve the construction location and quantity of the supporting structure.
  • the embodiment of the present invention proposes a monitoring and verification system for the overall failure mode of a soil-rock dual-element slope based on the above-mentioned method, including:
  • Surface displacement monitoring device which is installed on the top of the slope to monitor the horizontal and vertical displacement of the top of the slope
  • Inclinometer tube which is installed inside the slope soil and the soil-rock interface, used to monitor the horizontal displacement of the slope soil and the soil-rock interface;
  • the layered settlement instrument which is installed on the sliding surface of the slope, is used to monitor the vertical displacement of the slope soil;
  • the data processing device obtains the data monitored by the surface displacement monitoring device, the inclinometer and the layered settlement instrument, and analyzes the surface and internal displacement changes of the slope, especially the interface between the soil and the fully weathered rock and the interaction between the fully weathered rock and the strongly weathered rock
  • the displacement change at the interface determine the position of the slip line according to the monitoring and analysis of the slope surface displacement change, and draw the slope slip line according to the maximum displacement point inside the slope; compare the obtained slope slip line with Compare the slip lines obtained by the finite element method. If there is no difference, use the finite element software to simulate the next supporting structure and guide the construction. If there is a difference, perform the finite element simulation again and compare again until there is no difference.
  • the monitoring and verification system for the overall failure mode of the soil and rock dual-element slope proposed in the present invention can understand the specific change values of the horizontal and vertical displacements of the slope top through the surface displacement device installed on the top of the slope; understand the slope through the inclinometer tube
  • the change value of the internal vertical displacement of the slope can be learned through the layered settlement instrument, so that a comprehensive monitoring of the slope can be realized, and the displacement, inclination, and force of the slope can be fully understood in time. Verify the accuracy of the simulation.
  • the monitoring and verification system for the overall failure mode of the soil-rock dual-element slope provided by the present invention can obtain the slip curve of the slope through the monitoring data. This method not only verifies the failure of the soil-rock dual-element slope through the finite element calculation The model also provides an important basis for the calculation of the slope safety factor, and can guide the design and maintenance of the supporting structure.
  • the monitoring system of the present invention only uses the inclinometer tube, the layered settlement instrument and the round head steel bar to monitor the displacement of the slope top surface.
  • the cost is low, the operation is simple, and the existing mature instruments are used to obtain undiscovered things. Played the role of monitoring equipment.
  • Figure 1 is a flow chart of the present invention
  • Figure 2 is a diagram of the instrument layout of the soil-rock dual-element slope monitoring system of the present invention
  • Figure 3 is a top view of the slope displacement monitoring point
  • 1 is the surface displacement device
  • 2 is the inclinometer tube
  • 3 is the arc-planar slip surface
  • 4 is the interface between soil and fully weathered rock
  • 5 is the interface between fully weathered rock and strongly weathered rock
  • 6 is the measurement Inclined tube reading platform
  • 7 is the surface displacement monitoring point.
  • the soil removal + fully weathered rock slope exhibits the overall failure behavior of the circular arc sliding of the soil slope
  • the other three dual-element soil and rock slopes are basically circular arc + plane sliding overall failure modes.
  • the inclinometer tube has a sudden change in the displacement of the rock-soil interface, connects the sudden change points of the displacement to establish a slip curve, judges the nature of the plane slip surface of the soil-rock interface, and proves the overall failure mode of the soil-rock slope.
  • the monitoring and verification system for the overall failure mode of the soil-rock dual-element slope includes a surface displacement device 1 ( Refer to Figure 3 for the specific layout.
  • the surface displacement monitoring point 7 in Figure 3 represents the installation position of the surface displacement device 1), which is installed inside the soil, especially at the interface between soil and rock (corresponding to the interface between soil and fully weathered rock in Figure 2 4 and the interface between fully weathered rock and strongly weathered rock 5)
  • the surface displacement device 1 uses round-headed steel bars, and the specific installation method is: use round-headed steel bars chiseled into the ground to a certain depth at the slope top displacement monitoring point, and obtain the ground of the monitoring point by observing the settlement of the round head of the steel bar.
  • the horizontal displacement of the monitoring point can be obtained by observing the distance between the round head of the steel bar and the base point of the leveling, and the height of the round head steel bar on the ground can be easily observed.
  • the layered settlement instrument is arranged at the deep soil displacement monitoring points on the left and right sides of the slip surface obtained by finite element simulation. It is installed at the same time as the inclinometer, and the installation depth is 0.1h.
  • the cracking point of the slope top of the slip surface is located between 1.1h and 1.2h from the horizontal distance of the slope toe, so the installation position of the layered settlement instrument is 1.1h and 1.2h from the horizontal distance of the slope toe ).
  • the specific installation method of the inclinometer tube 2 is: pre-embedding the inclinometer tube at the deep soil displacement monitoring points, and the inclinometer tube 2 should measure data every 1m to ensure that different depths are measured.
  • the size of the displacement of the soil layer, and the inclinometer tube 2 should be arranged as far as possible at the interface of the stratum.
  • the arrangement of multiple rows of inclinometer tubes forms multiple rows of deep soil displacement monitoring points.
  • the data processing device obtains the data monitored by the surface displacement monitoring device, inclinometer and layered settlement instrument, and analyzes the surface and internal displacement changes of the slope, especially the interface between soil and fully weathered rock, and fully weathered rock and strong weathering
  • the displacement change at the rock interface; the position of the slip line is determined according to the monitoring and analysis of the slope surface displacement change, and the slip line of the slope is drawn according to the maximum displacement point inside the slope; the slope slip will be obtained
  • the line is compared with the slip line obtained by the finite element method. If there is no difference, the finite element software is used to simulate the next supporting structure and guide the construction. If there is a difference, perform the finite element simulation again and compare again until there is no difference. difference.
  • the monitoring and verification system for the overall failure mode of the soil and rock dual-element slope disclosed in this embodiment can understand the specific change values of the horizontal and vertical displacement of the slope top through the surface displacement device installed on the top of the slope; it can be learned through the inclinometer For the horizontal displacement inside the slope, the change value of the vertical displacement inside the slope can be learned through the layered settlement instrument, so that a comprehensive monitoring of the slope can be realized, and the displacement, inclination, and force of the slope can be fully understood in time , Compare with the slip line simulated by finite element software.
  • this embodiment also provides a monitoring verification method, that is, the slope is first simulated by finite element software to obtain the slip line of the slope, and then the slope is monitored, and the slope is obtained from the monitoring data.
  • the maximum internal displacement points connect these points into a curve to obtain the slip line of the slope, use the obtained slope slip line to verify the slip line obtained by the finite element software, if the difference between the two is not large, it can be explained
  • the calculation results of the finite element software are reliable. Then use the finite element software to calculate the subsequent construction steps to improve the construction position and quantity of the supporting structure. details as follows:
  • the deployment standards of the monitoring plan in step 2) are as follows:
  • the leveling base point needs to be placed on the top of the slope and outside the impact distance of the slope construction.
  • the impact distance is determined by the height of the slope.
  • the construction has the largest surface displacement of the slope top The scope of influence will not exceed the value of the thickness of the soil plus fully weathered rock layer.
  • the purpose of the monitoring scheme used in the present invention is to obtain the failure mode of the soil-rock dual-element slope during construction. Since the slope is composed of different strata, it is necessary to verify whether the interface will be damaged. A sudden change occurred, so most of the monitoring points of the inclinometer tube were arranged at the interface of each layer, and a few were arranged inside the soil layer. Generally, the monitoring range of the inclinometer tube should exceed the area where slippage occurs during the finite element calculation (at least one inclinometer tube should be arranged outside the slip surface), and a monitoring point should be arranged at the soil-rock interface.
  • the slope top displacement monitoring points are arranged according to the finite element calculation results. At least one slope top displacement monitoring point is arranged inside and outside the landslide body. In this example, it is arranged at a distance from the top of the slope. At the position of 0.1h and 0.2h intersecting the slope. (h is the slope height)
  • step 3 The specific steps of step 3) are as follows:
  • the inclinometer tube should be pre-embedded at the monitoring points of the deep soil displacement.
  • the inclinometer tube should measure the data every 1m to ensure that the displacement of the soil layer at different depths is measured, and the inclinometer tube should be as far as possible Arranged at the stratum interface, multiple rows of deep soil displacement monitoring points are formed through the arrangement of multiple rows of inclinometer tubes.
  • the installation depth is 0.1h.
  • the cracking point of the slope top of the slip surface is located between 1.1h and 1.2h from the horizontal distance of the slope toe, so the installation position of the layered settlement instrument is 1.1h and 1.2h from the horizontal distance of the slope toe )
  • step 4 the specific steps of the step 4) are as follows:
  • step 5 is as follows:
  • step 5-1) and step 5-2 determine the x and y coordinates of the maximum displacement point inside the slope, and then draw the slope slip curve (the maximum displacement is the horizontal displacement vector plus the vertical The modulus length value of the straight displacement vector), and then determine the failure mode of the slope.
  • step 4-3 here is an example.
  • the slope ratio is 1:1, and the toe of the slope is taken as the origin of the coordinate.
  • the cracking point of the slope top of the sliding surface is between 0.1h and 0.2h from the horizontal distance from the top of the slope.
  • the median value, the coordinates of the cracking point are (1.15h, h); according to the data in Table 3 and Table 4, we get:
  • the curve drawn according to the coordinates in the above figure is the arc slip line of the slope, and the boundary between the fully weathered rock layer and the strongly weathered rock layer is the slip line of the soil-rock dual-element slope. Then it is compared with the slip line obtained by the finite element method to verify the correctness of the result of the finite element method and provide support for the next step of the finite element analysis.

Abstract

A monitoring and verifying system and method for an overall failure mode of a soil-rock dual-element side slope. The method comprises: 1) simulating a side slope by means of finite element software to obtain a slip line of the side slope; 2) making, according to a side slope construction scheme, a monitoring scheme of monitoring displacement changes of a slope top and a potential slip surface; 3) performing construction according to an arrangement scheme, and performing monitoring; 4) collating monitoring data, and analyzing displacement change conditions of the surface and the interior of the side slope; 5) determining the position of the slip line according to the monitored and analyzed displacement change conditions of the surface of the side slope, and drawing the slip line of the side slope according to a maximum displacement point inside the side slope; and 6) verifying, according to the obtained slip line of the side slope, the slip line obtained by a finite element method, and providing guidance for the subsequent side slope support structure construction by means of the finite element software.

Description

一种土岩双元边坡整体破坏模式的监测验证系统与方法System and method for monitoring and verifying overall failure mode of soil-rock dual-element slope 技术领域Technical field
本发明涉及边坡破坏模式监测领域,特别涉及一种土岩双元边坡整体破坏模式的监测验证系统与方法。The invention relates to the field of slope failure mode monitoring, in particular to a monitoring verification system and method for the overall failure mode of a soil-rock dual-element slope.
背景技术Background technique
基坑开挖以及道路施工过程中,有时会遇到上边是土层、下边是岩石的边坡,我们称为土岩双元边坡。目前理论界一般认为土层边坡是整体圆弧破坏模式;岩层边坡整体破坏模式比较复杂,与岩石性状有关,呈多样性。国内外缺乏土岩双元边坡整体破坏模式的研究与共识。During foundation pit excavation and road construction, sometimes a slope with a soil layer on the top and a rock on the bottom is encountered. We call it a soil-rock dual-element slope. At present, the theoretical circle generally believes that the soil slope is the overall arc failure mode; the overall failure mode of the rock slope is relatively complicated, which is related to the rock properties and is diverse. There is a lack of research and consensus on the overall failure mode of soil-rock dual-element slopes at home and abroad.
近年来,随济南城市建设不断发展,出现了四种土岩双元基坑边坡。根据岩石风化程度不同,分别为土+全风化、土+全风化+强风化、土+全风化+强风化+中风化、土+中风化岩石边坡;研究并确定它们的整体破坏模式,对于促进国家相关技术进步和城市开发建设具有重要理论意义和工程价值;但是目前,现有技术中还没有关于上述坡体的破坏模式的确定方法。In recent years, with the continuous development of Jinan's urban construction, four types of soil-rock dual-element foundation pit slopes have appeared. According to different degrees of rock weathering, they are soil+full weathering, soil+full weathering+strong weathering, soil+full weathering+strong weathering+medium weathering, soil+medium weathering rock slopes; research and determine their overall failure mode, for It has important theoretical significance and engineering value to promote the country's relevant technological progress and urban development and construction; however, currently, there is no method for determining the failure mode of the above-mentioned slope in the existing technology.
发明内容Summary of the invention
为了解决现有技术中存在的技术问题,本发明公开了一种土岩双元边坡整体破坏模式的监测验证系统及方法,这个监测验证系统及方法既验证了有限元计算得到土岩双元边坡的破坏模式,也可为接下来的边坡支护结构施工提供指导。In order to solve the technical problems existing in the prior art, the present invention discloses a monitoring verification system and method for the overall failure mode of a soil-rock dual-element slope. The failure mode of the slope can also provide guidance for the subsequent construction of the slope support structure.
为了实现上述目的,本发明采用的技术方案如下:In order to achieve the above objectives, the technical solutions adopted by the present invention are as follows:
第一方面,本发明实施例提出了一种土岩双元边坡整体破坏模式的监测验证方法,包括以下步骤:In the first aspect, the embodiment of the present invention proposes a method for monitoring and verifying the overall failure mode of a dual-element soil and rock slope, which includes the following steps:
1)通过有限元软件对边坡进行模拟,得出边坡的滑移线;1) Simulate the slope through finite element software to obtain the slip line of the slope;
2)根据边坡施工方案制定监测坡顶及潜在滑移面处的位移变化的监测方案;包括深层土体位移点、坡顶位移监测点以及水准基点的布设方案;2) Develop a monitoring plan for monitoring the displacement changes at the top of the slope and the potential slip surface according to the slope construction plan; including the layout plan of deep soil displacement points, slope top displacement monitoring points and leveling base points;
3)根据步骤2)确定的布设方案进行施工,并进行监测;3) Carry out construction and monitor according to the layout plan determined in step 2);
4)对监测数据进行整理,分析边坡表面及内部位移变化情况,特别是土与全风化岩石交界面及全风化岩石与强风化岩石交界面处的位移变化;4) Sorting out the monitoring data, analyzing the surface and internal displacement changes of the slope, especially the displacement changes at the interface between soil and fully weathered rock and at the interface between fully weathered rock and strongly weathered rock;
5)根据监测分析得出边坡表面位移变化情况确定滑移线的位置,根据边坡内部最大位移点画出边坡的滑移线;5) Determine the position of the slip line according to the monitoring and analysis of the slope surface displacement change, and draw the slip line of the slope according to the maximum displacement point inside the slope;
6)将步骤5)得出的边坡滑移线与有限元法得到的滑移线进行对比,如果无差异,则通过有限元软件进行接下来的支护结构模拟并指导施工,如果有差异,重新进行有限元模拟,再次进行对比直到无差异。6) Compare the slope slip line obtained in step 5) with the slip line obtained by the finite element method. If there is no difference, use the finite element software to simulate the next supporting structure and guide the construction. If there is a difference , Re-run finite element simulation, and compare again until there is no difference.
作为进一步的技术方案,步骤2)中监测方案的布设标准如下:As a further technical solution, the deployment standards of the monitoring solution in step 2) are as follows:
2-1)确定水准基点的布设方案:水准基点需布设在坡顶,且位于边坡施工的影响距离之外,影响距离由边坡的高度决定,根据研究,施工对坡顶表面位移的最大影响范围不会超过土加全风化岩层厚度的值。2-1) Determine the layout plan of the leveling base point: the leveling base point needs to be placed on the top of the slope and outside the impact distance of the slope construction. The impact distance is determined by the height of the slope. According to the research, the construction has the largest surface displacement of the slope top The scope of influence will not exceed the value of the thickness of the soil plus fully weathered rock layer.
2-2)确定边坡施工对坡顶表面位移影响最大的区域:以坡顶与坡面的交线为起点,向背离边坡施工方向量出相当于土加全风化岩层厚度值的区域,这部分区域就是边坡施工对坡顶表面位移影响最大的区域,水准基点布设在此区域外即可。2-2) Determine the area where the slope construction has the greatest impact on the surface displacement of the slope top: starting from the intersection of the slope top and the slope surface, measure the area that is equivalent to the thickness of the soil plus the fully weathered rock layer in the direction away from the slope construction. This part of the area is the area where the slope construction has the greatest impact on the surface displacement of the slope top, and the leveling base point can be arranged outside this area.
2-3)确定深层土体位移监测点:本发明所采用的监测方案目的在于得到施工时土岩双元边坡的稳定性,由于边坡是由不同的地层构成,为验证界面处是否会产生突变,因此测斜管的测点位置多数布置在了各地层的交界面处,少量布置 在土层内部。一般地,测斜管监测范围应超出有限元计算时出现滑移的区域(在滑移面外至少布设一根测斜管),且在土岩交界面处应布设监测点。2-3) Determining the monitoring point of deep soil displacement: The purpose of the monitoring scheme used in the present invention is to obtain the stability of the soil-rock dual-element slope during construction. Since the slope is composed of different stratums, in order to verify whether the interface will be A sudden change occurs, so most of the measuring points of the inclinometer tube are arranged at the interface of each layer, and a few are arranged inside the soil layer. Generally, the monitoring range of the inclinometer tube should exceed the area where slippage occurs during the finite element calculation (at least one inclinometer tube should be arranged outside the slip surface), and a monitoring point should be arranged at the soil-rock interface.
2-4)确定坡顶位移监测点:坡顶位移监测点布置在距坡顶与坡面交线1m及2m的位置处。2-4) Determine the slope top displacement monitoring point: the slope top displacement monitoring point is arranged at the position 1m and 2m away from the intersection line of the slope top and the slope surface.
作为进一步的技术方案,所述步骤3)的具体步骤如下:As a further technical solution, the specific steps of step 3) are as follows:
3-1)在所述水准基点布设水准仪。3-1) A level is arranged at the base point of the level.
3-2)在所述坡顶位移监测点选用凿入地面一定深度的圆头钢筋,通过观察钢筋圆头的沉降得到监测点的地面沉降,通过观察钢筋圆头与水准基点的距离得到监测点的水平位移,圆头钢筋在地面的高度方便观察即可。3-2) At the slope top displacement monitoring point, round-head steel bars chiseled into the ground to a certain depth are selected, the ground settlement of the monitoring point is obtained by observing the settlement of the steel round head, and the monitoring point is obtained by observing the distance between the steel round head and the leveling base point The height of the round head steel bar on the ground can be easily observed.
3-3)在所述深层土体位移点处分别预埋与测斜仪配合的测斜管,测斜管应每隔1m测一次数据以保证测到不同深度土层的位移大小,且测斜管应尽可能布置在地层交界面处,通过多列测斜管的设置形成了多列深层土体位移监测点。3-3) The inclinometer tubes matched with the inclinometer should be pre-embedded at the displacement points of the deep soil. The inclinometer tubes should be measured every 1m to ensure that the displacements of the soil layers at different depths are measured. Inclined pipes should be arranged as far as possible at the interface of stratum, and multiple rows of inclinometer pipes are arranged to form multiple rows of deep soil displacement monitoring points.
3-4)在滑移面上部,周围土体竖直位移较大且水平位移较小,所以在有限元模拟得出的滑移面左右两侧的深层土体位移监测点布置分层沉降仪,与测斜管同时安装,安装深度为0.1h。3-4) On the upper part of the slip surface, the vertical displacement of the surrounding soil is large and the horizontal displacement is small, so the deep soil displacement monitoring points on the left and right sides of the slip surface obtained by finite element simulation are arranged with layered settlement instruments , Installed at the same time with the inclinometer, the installation depth is 0.1h.
作为进一步的技术方案,所述步骤4)的具体步骤如下:As a further technical solution, the specific steps of the step 4) are as follows:
4-1)收集整理各坡面位移监测点数据,绘制坡顶水平位移值统计表及坡顶沉降统计表;4-1) Collecting and sorting out the data of each slope displacement monitoring point, drawing the slope top horizontal displacement value statistical table and slope top settlement statistical table;
4-2)收集整理各深层土体位移监测点数据,利用监测点位移统计表进行统计。4-2) Collect and sort out the data of various deep soil displacement monitoring points, and use the displacement statistics table of the monitoring points to make statistics.
作为进一步的技术方案,所述步骤6)的具体步骤如下:As a further technical solution, the specific steps of step 6) are as follows:
根据步骤5)得到的边坡滑移线验证有限元软件得出的滑移线,如果两者差 异不大,就可说明有限元软件的计算结果时可靠的,接下来运用有限元软件对后续的施工步骤进行计算,改进支护结构的施工位置以及数量。According to the slope slip line obtained in step 5), verify the slip line obtained by the finite element software. If the difference between the two is not large, it can indicate that the calculation result of the finite element software is reliable. Calculate the construction steps to improve the construction location and quantity of the supporting structure.
第二方面,本发明的实施例基于上述方法,提出了一种土岩双元边坡整体破坏模式的监测验证系统,包括:In the second aspect, the embodiment of the present invention proposes a monitoring and verification system for the overall failure mode of a soil-rock dual-element slope based on the above-mentioned method, including:
表面位移监测装置,其安装在坡顶,用于监测坡顶的水平位移和垂直位移;Surface displacement monitoring device, which is installed on the top of the slope to monitor the horizontal and vertical displacement of the top of the slope;
测斜管,其安装在边坡土体内部及土岩交界面处,用于监测边坡土体内部以及土岩交界面处的水平位移;Inclinometer tube, which is installed inside the slope soil and the soil-rock interface, used to monitor the horizontal displacement of the slope soil and the soil-rock interface;
分层沉降仪,其安装在边坡滑移面,用于监测边坡土体的竖直位移;The layered settlement instrument, which is installed on the sliding surface of the slope, is used to monitor the vertical displacement of the slope soil;
数据处理装置,获取表面位移监测装置、测斜仪和分层沉降仪监测的数据,分析边坡表面及内部位移变化情况,特别是土与全风化岩石交界面及全风化岩石与强风化岩石交界面处的位移变化;根据监测分析得出边坡表面位移变化情况确定滑移线的位置,根据边坡内部最大位移点画出边坡的滑移线;将得出的边坡滑移线与有限元法得到的滑移线进行对比,如果无差异,则通过有限元软件进行接下来的支护结构模拟并指导施工,如果有差异,重新进行有限元模拟,再次进行对比,直到无差异。The data processing device obtains the data monitored by the surface displacement monitoring device, the inclinometer and the layered settlement instrument, and analyzes the surface and internal displacement changes of the slope, especially the interface between the soil and the fully weathered rock and the interaction between the fully weathered rock and the strongly weathered rock The displacement change at the interface; determine the position of the slip line according to the monitoring and analysis of the slope surface displacement change, and draw the slope slip line according to the maximum displacement point inside the slope; compare the obtained slope slip line with Compare the slip lines obtained by the finite element method. If there is no difference, use the finite element software to simulate the next supporting structure and guide the construction. If there is a difference, perform the finite element simulation again and compare again until there is no difference.
本发明提出的土岩双元边坡整体破坏模式的监测验证系统,能够通过安装在坡顶上的表面位移装置了解坡顶水平位移和垂直位移的具体变化值;通过测斜管了解到边坡内部的水平位移,通过分层沉降仪了解到边坡内部竖直位移的变化值,从而能够实现对边坡综合全面的监测,及时全面的了解边坡的位移、倾斜、以及受力情况,以验证模拟的准确性。The monitoring and verification system for the overall failure mode of the soil and rock dual-element slope proposed in the present invention can understand the specific change values of the horizontal and vertical displacements of the slope top through the surface displacement device installed on the top of the slope; understand the slope through the inclinometer tube For the internal horizontal displacement, the change value of the internal vertical displacement of the slope can be learned through the layered settlement instrument, so that a comprehensive monitoring of the slope can be realized, and the displacement, inclination, and force of the slope can be fully understood in time. Verify the accuracy of the simulation.
与现有土岩边坡监测系统相比,本发明的有益效果是:Compared with the existing soil and rock slope monitoring system, the beneficial effects of the present invention are:
1)本发明提供的土岩双元边坡整体破坏模式的监测验证系统,通过监测数 据可以得到边坡的滑移曲线,通过该方式既验证了有限元计算得到土岩双元边坡的破坏模式,又为边坡安全系数的计算提供重要依据,并可指导支护结构的设计以及维护工作。1) The monitoring and verification system for the overall failure mode of the soil-rock dual-element slope provided by the present invention can obtain the slip curve of the slope through the monitoring data. This method not only verifies the failure of the soil-rock dual-element slope through the finite element calculation The model also provides an important basis for the calculation of the slope safety factor, and can guide the design and maintenance of the supporting structure.
2)本发明的监测系统,只用到测斜管、分层沉降仪以及监测坡顶表面位移的圆头钢筋,成本低,操作简单,用既有成熟的仪器获得未发现的东西,充分地发挥了监测仪器的作用。2) The monitoring system of the present invention only uses the inclinometer tube, the layered settlement instrument and the round head steel bar to monitor the displacement of the slope top surface. The cost is low, the operation is simple, and the existing mature instruments are used to obtain undiscovered things. Played the role of monitoring equipment.
附图说明Description of the drawings
构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。The drawings of the specification forming a part of the application are used to provide a further understanding of the application, and the exemplary embodiments and descriptions of the application are used to explain the application, and do not constitute an improper limitation of the application.
图1为本发明流程图;Figure 1 is a flow chart of the present invention;
图2为本发明土岩双元边坡监测系统仪器布置图;Figure 2 is a diagram of the instrument layout of the soil-rock dual-element slope monitoring system of the present invention;
图3为坡面位移监测点俯视图;Figure 3 is a top view of the slope displacement monitoring point;
图中:1为表面位移装置,2为测斜管,3为圆弧-平面滑移面,4为土与全风化岩交界面,5为全风化岩与强风化岩交界面,6为测斜管读数平台,7为表面位移监测点。In the figure: 1 is the surface displacement device, 2 is the inclinometer tube, 3 is the arc-planar slip surface, 4 is the interface between soil and fully weathered rock, 5 is the interface between fully weathered rock and strongly weathered rock, and 6 is the measurement Inclined tube reading platform, 7 is the surface displacement monitoring point.
具体实施方式Detailed ways
应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步的说明。除非另有指明,本发明使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed descriptions are all illustrative and are intended to provide further explanations for the application. Unless otherwise specified, all technical and scientific terms used in the present invention have the same meaning as commonly understood by those of ordinary skill in the technical field to which this application belongs.
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非本发明另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使 用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合;It should be noted that the terms used here are only for describing specific embodiments, and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the present invention clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should also be understood that when the terms "comprising" and/or "including" are used in this specification, they Indicate the existence of features, steps, operations, devices, components, and/or combinations thereof;
近年来,随济南城市建设不断发展,出现了四种土岩双元基坑边坡。根据岩石风化程度不同,分别为土+全风化、土+全风化+强风化、土+全风化+强风化+中风化、土+中风化岩石边坡。研究并确定它们的整体破坏模式,对于促进国家相关技术进步和城市开发建设具有重要理论意义和工程价值。目前,现有技术中还没有关于上述坡体的破坏模式。In recent years, with the continuous development of Jinan's urban construction, four types of soil-rock dual-element foundation pit slopes have appeared. According to the different degree of rock weathering, they are soil+full weathering, soil+full weathering+strong weathering, soil+full weathering+strong weathering+medium weathering, soil+medium weathering rock slope. Studying and determining their overall destruction mode has important theoretical significance and engineering value for promoting the country's relevant technological progress and urban development and construction. At present, there is no failure mode of the above-mentioned slope in the prior art.
本发明根据有限元模拟结果,除土+全风化岩石边坡表现出土体边坡圆弧滑动整体破坏性状,其它三种土岩双元边坡基本都是圆弧+平面滑动整体破坏模式。为了验证和确定上述土岩双元边坡整体破坏模式结果,组合现有监测技术,利用测斜管监测边坡横断面不同位置深层土体水平位移,判断系列土岩界面处上层土体位移较大,测斜管在岩土界面位移突变,连接位移突变点建立滑移曲线,判断土岩界面平面滑移面性质,证明土岩边坡整体破坏模式。According to the finite element simulation result, the soil removal + fully weathered rock slope exhibits the overall failure behavior of the circular arc sliding of the soil slope, and the other three dual-element soil and rock slopes are basically circular arc + plane sliding overall failure modes. In order to verify and determine the results of the overall failure mode of the above-mentioned soil-rock dual-element slope, combined with existing monitoring technology, the horizontal displacement of the deep soil at different positions of the slope cross-section is monitored by the inclinometer, and the upper soil displacement at the series of soil-rock interfaces is judged. Large, the inclinometer tube has a sudden change in the displacement of the rock-soil interface, connects the sudden change points of the displacement to establish a slip curve, judges the nature of the plane slip surface of the soil-rock interface, and proves the overall failure mode of the soil-rock slope.
本实施例作为一种典型的实施例,如图2所示,该土岩双元边坡整体破坏模式的监测验证系统包括安装在坡顶监测坡顶水平位移和垂直位移的表面位移装置1(具体布置方式参考图3,图3中表面位移监测点7代表表面位移装置1的安装位置),安装在土体内部特别是土岩交界面处(对应图2中的土与全风化岩交界面4和全风化岩与强风化岩交界面5)监测深层土体位移的测斜管2以及安装在圆弧-平面滑移面3附近监测土体竖直位移的分层沉降仪以及数据处理装置。This embodiment is a typical embodiment. As shown in Figure 2, the monitoring and verification system for the overall failure mode of the soil-rock dual-element slope includes a surface displacement device 1 ( Refer to Figure 3 for the specific layout. The surface displacement monitoring point 7 in Figure 3 represents the installation position of the surface displacement device 1), which is installed inside the soil, especially at the interface between soil and rock (corresponding to the interface between soil and fully weathered rock in Figure 2 4 and the interface between fully weathered rock and strongly weathered rock 5) Inclinometer for monitoring the displacement of deep soils 2 and a layered settlement instrument and data processing device installed near the arc-planar slip surface 3 to monitor the vertical displacement of the soil .
进一步的,所述的表面位移装置1采用圆头钢筋,具体的安装方式是:在坡顶位移监测点选用凿入地面一定深度的圆头钢筋,通过观察钢筋圆头的沉降得到监测点的地面沉降,通过观察钢筋圆头与水准基点的距离得到监测点的水平位 移,圆头钢筋在地面的高度方便观察即可。Further, the surface displacement device 1 uses round-headed steel bars, and the specific installation method is: use round-headed steel bars chiseled into the ground to a certain depth at the slope top displacement monitoring point, and obtain the ground of the monitoring point by observing the settlement of the round head of the steel bar. For settlement, the horizontal displacement of the monitoring point can be obtained by observing the distance between the round head of the steel bar and the base point of the leveling, and the height of the round head steel bar on the ground can be easily observed.
进一步的,所述的分层沉降仪具体的布置方式参考附图2,沿坡体的高度方向设置多层,每一层设置多行和多列。具体的,在滑移面上部,周围土体竖直位移较大且水平位移较小,所以在有限元模拟得出的滑移面左右两侧的深层土体位移监测点布置分层沉降仪,与测斜管同时安装,安装深度为0.1h。(本例中,根据有限元计算,滑移面坡顶开裂点位于距坡脚水平距离1.1h及1.2h之间,所以分层沉降仪安装位置在距坡脚水平距离1.1h及1.2h处)。Further, for the specific arrangement of the layered sedimentation instrument, refer to FIG. 2, multiple layers are arranged along the height direction of the slope, and multiple rows and multiple columns are arranged on each layer. Specifically, on the upper part of the slip surface, the vertical displacement of the surrounding soil is large and the horizontal displacement is small. Therefore, the layered settlement instrument is arranged at the deep soil displacement monitoring points on the left and right sides of the slip surface obtained by finite element simulation. It is installed at the same time as the inclinometer, and the installation depth is 0.1h. (In this example, according to the finite element calculation, the cracking point of the slope top of the slip surface is located between 1.1h and 1.2h from the horizontal distance of the slope toe, so the installation position of the layered settlement instrument is 1.1h and 1.2h from the horizontal distance of the slope toe ).
进一步的,所述的测斜管2具体的安装方式是:在所述深层土体位移监测点处分别预埋测斜管,测斜管2应每隔1m测一次数据以保证测到不同深度土层的位移大小,且测斜管2应尽可能布置在地层交界面处,通过多列测斜管的设置形成了多列深层土体位移监测点。Further, the specific installation method of the inclinometer tube 2 is: pre-embedding the inclinometer tube at the deep soil displacement monitoring points, and the inclinometer tube 2 should measure data every 1m to ensure that different depths are measured. The size of the displacement of the soil layer, and the inclinometer tube 2 should be arranged as far as possible at the interface of the stratum. The arrangement of multiple rows of inclinometer tubes forms multiple rows of deep soil displacement monitoring points.
进一步的,数据处理装置获取表面位移监测装置、测斜仪和分层沉降仪监测的数据,分析边坡表面及内部位移变化情况,特别是土与全风化岩石交界面及全风化岩石与强风化岩石交界面处的位移变化;根据监测分析得出边坡表面位移变化情况确定滑移线的位置,根据边坡内部最大位移点画出边坡的滑移线;将得出的边坡滑移线与有限元法得到的滑移线进行对比,如果无差异,则通过有限元软件进行接下来的支护结构模拟并指导施工,如果有差异,重新进行有限元模拟,再次进行对比,直到无差异。Further, the data processing device obtains the data monitored by the surface displacement monitoring device, inclinometer and layered settlement instrument, and analyzes the surface and internal displacement changes of the slope, especially the interface between soil and fully weathered rock, and fully weathered rock and strong weathering The displacement change at the rock interface; the position of the slip line is determined according to the monitoring and analysis of the slope surface displacement change, and the slip line of the slope is drawn according to the maximum displacement point inside the slope; the slope slip will be obtained The line is compared with the slip line obtained by the finite element method. If there is no difference, the finite element software is used to simulate the next supporting structure and guide the construction. If there is a difference, perform the finite element simulation again and compare again until there is no difference. difference.
本实施例中公开的土岩双元边坡整体破坏模式的监测验证系统,能够通过安装在坡顶上的表面位移装置了解坡顶水平位移和垂直位移的具体变化值;通过测斜管了解到边坡内部的水平位移,通过分层沉降仪了解到边坡内部竖直位移的变化值,从而能够实现对边坡综合全面的监测,及时全面的了解边坡的位移、倾斜、 以及受力情况,与有限元软件模拟的滑移线进行对比。The monitoring and verification system for the overall failure mode of the soil and rock dual-element slope disclosed in this embodiment can understand the specific change values of the horizontal and vertical displacement of the slope top through the surface displacement device installed on the top of the slope; it can be learned through the inclinometer For the horizontal displacement inside the slope, the change value of the vertical displacement inside the slope can be learned through the layered settlement instrument, so that a comprehensive monitoring of the slope can be realized, and the displacement, inclination, and force of the slope can be fully understood in time , Compare with the slip line simulated by finite element software.
基于上述系统,本实施例还提供一种监测验证方法,即先通过有限元软件对边坡进行模拟,得出边坡的滑移线,再对边坡进行监测,通过监测数据得出边坡内部的最大位移点,将这些点连接为曲线,得到边坡的滑移线,用得到的边坡滑移线验证有限元软件得出的滑移线,如果两者差异不大,就可说明有限元软件的计算结果时可靠的,接下来运用有限元软件对后续的施工步骤进行计算,改进支护结构的施工位置以及数量。具体如下:Based on the above system, this embodiment also provides a monitoring verification method, that is, the slope is first simulated by finite element software to obtain the slip line of the slope, and then the slope is monitored, and the slope is obtained from the monitoring data. The maximum internal displacement points, connect these points into a curve to obtain the slip line of the slope, use the obtained slope slip line to verify the slip line obtained by the finite element software, if the difference between the two is not large, it can be explained The calculation results of the finite element software are reliable. Then use the finite element software to calculate the subsequent construction steps to improve the construction position and quantity of the supporting structure. details as follows:
1)通过有限元软件对边坡进行模拟,得出边坡的滑移线;1) Simulate the slope through finite element software to obtain the slip line of the slope;
2)根据边坡施工方案制定监测坡顶及潜在滑移面处的位移变化的监测方案;包括深层土体位移点、坡顶位移监测点以及水准基点的布设方案;2) Develop a monitoring plan for monitoring the displacement changes at the top of the slope and the potential slip surface according to the slope construction plan; including the layout plan of deep soil displacement points, slope top displacement monitoring points and leveling base points;
3)根据步骤2)确定的布设方案进行施工,并进行监测;3) Carry out construction and monitor according to the layout plan determined in step 2);
4)对监测数据进行整理,分析边坡表面及内部位移变化情况,特别是土与全风化岩石交界面及全风化岩石与强风化岩石交界面处的位移变化;4) Sorting out the monitoring data, analyzing the surface and internal displacement changes of the slope, especially the displacement changes at the interface between soil and fully weathered rock and at the interface between fully weathered rock and strongly weathered rock;
5)根据监测分析得出边坡表面位移变化情况确定滑移线的位置,根据边坡内部最大位移点画出边坡的滑移线;5) Determine the position of the slip line according to the monitoring and analysis of the slope surface displacement change, and draw the slip line of the slope according to the maximum displacement point inside the slope;
6)根据步骤5)得出的边坡滑移线验证有限元法得到的滑移线,并通过有限元软件为接下来的边坡支护结构施工提供指导。6) Verify the slip line obtained by the finite element method according to the slope slip line obtained in step 5), and provide guidance for the next slope support structure construction through the finite element software.
进一步地,步骤2)中监测方案的布设标准如下:Further, the deployment standards of the monitoring plan in step 2) are as follows:
2-1)确定水准基点的布设方案:水准基点需布设在坡顶,且位于边坡施工的影响距离之外,影响距离由边坡的高度决定,根据研究,施工对坡顶表面位移的最大影响范围不会超过土加全风化岩层厚度的值。2-1) Determine the layout plan of the leveling base point: the leveling base point needs to be placed on the top of the slope and outside the impact distance of the slope construction. The impact distance is determined by the height of the slope. According to the research, the construction has the largest surface displacement of the slope top The scope of influence will not exceed the value of the thickness of the soil plus fully weathered rock layer.
2-2)确定边坡施工对坡顶表面位移影响最大的区域:以坡顶与坡面的交线 为起点,向背离边坡施工方向量出相当于土加全风化岩层厚度值的区域,这部分区域就是边坡施工对坡顶表面位移影响最大的区域,水准基点布设在此区域外即可。2-2) Determine the area where the slope construction has the greatest impact on the surface displacement of the slope top: starting from the intersection of the slope top and the slope surface, measure the area that is equivalent to the thickness of the soil plus the fully weathered rock layer in the direction away from the slope construction. This part of the area is the area where the slope construction has the greatest impact on the surface displacement of the slope top, and the leveling base point can be arranged outside this area.
2-3)确定深层土体位移监测点:本发明所采用的监测方案目的在于得到施工时土岩双元边坡的破坏模式,由于边坡是由不同的地层构成,为验证界面处是否会产生突变,因此测斜管的监测点位置多数布置在了各地层的交界面处,少量布置在土层内部。一般地,测斜管监测范围应超出有限元计算时出现滑移的区域(在滑移面外至少布设一根测斜管),且在土岩交界面处应布设监测点。2-3) Determining the monitoring point of deep soil displacement: The purpose of the monitoring scheme used in the present invention is to obtain the failure mode of the soil-rock dual-element slope during construction. Since the slope is composed of different strata, it is necessary to verify whether the interface will be damaged. A sudden change occurred, so most of the monitoring points of the inclinometer tube were arranged at the interface of each layer, and a few were arranged inside the soil layer. Generally, the monitoring range of the inclinometer tube should exceed the area where slippage occurs during the finite element calculation (at least one inclinometer tube should be arranged outside the slip surface), and a monitoring point should be arranged at the soil-rock interface.
2-4)确定坡顶位移监测点:坡顶位移监测点根据有限元计算结果进行布置,在滑坡体内部及外部至少分别布置一个坡顶位移监测点,在本例中,布置在距坡顶与坡面交线0.1h及0.2h的位置处。(h为坡高)2-4) Determine the slope top displacement monitoring points: The slope top displacement monitoring points are arranged according to the finite element calculation results. At least one slope top displacement monitoring point is arranged inside and outside the landslide body. In this example, it is arranged at a distance from the top of the slope. At the position of 0.1h and 0.2h intersecting the slope. (h is the slope height)
所述步骤3)的具体步骤如下:The specific steps of step 3) are as follows:
3-1)在所述水准基点布设水准仪在所述水准基点布设水准仪。3-1) Deploying a leveling instrument at the leveling base point Deploying a leveling instrument at the leveling base point.
3-2)在所述坡顶位移监测点选用凿入地面一定深度的圆头钢筋,通过观察钢筋圆头的沉降得到监测点的地面沉降,通过观察钢筋圆头与水准基点的距离得到监测点的水平位移,圆头钢筋在地面的高度方便观察即可。3-2) At the slope top displacement monitoring point, round-head steel bars chiseled into the ground to a certain depth are selected, the ground settlement of the monitoring point is obtained by observing the settlement of the steel round head, and the monitoring point is obtained by observing the distance between the steel round head and the leveling base point The height of the round head steel bar on the ground can be easily observed.
3-3)在所述深层土体位移监测点处分别预埋测斜管,测斜管应每隔1m测一次数据以保证测到不同深度土层的位移大小,且测斜管应尽可能布置在地层交界面处,通过多列测斜管的设置形成了多列深层土体位移监测点。3-3) The inclinometer tube should be pre-embedded at the monitoring points of the deep soil displacement. The inclinometer tube should measure the data every 1m to ensure that the displacement of the soil layer at different depths is measured, and the inclinometer tube should be as far as possible Arranged at the stratum interface, multiple rows of deep soil displacement monitoring points are formed through the arrangement of multiple rows of inclinometer tubes.
3-4)在滑移面上部,周围土体竖直位移较大且水平位移较小,所以在有限元模拟得出的滑移面左右两侧的深层土体位移监测点布置分层沉降仪,与测斜管同时安装,安装深度为0.1h。(本例中,根据有限元计算,滑移面坡顶开裂点位 于距坡脚水平距离1.1h及1.2h之间,所以分层沉降仪安装位置在距坡脚水平距离1.1h及1.2h处)3-4) On the upper part of the slip surface, the vertical displacement of the surrounding soil is large and the horizontal displacement is small, so the deep soil displacement monitoring points on the left and right sides of the slip surface obtained by finite element simulation are arranged with layered settlement instruments , Installed at the same time with the inclinometer, the installation depth is 0.1h. (In this example, according to the finite element calculation, the cracking point of the slope top of the slip surface is located between 1.1h and 1.2h from the horizontal distance of the slope toe, so the installation position of the layered settlement instrument is 1.1h and 1.2h from the horizontal distance of the slope toe )
进一步地,所述步骤4)的具体步骤如下:Further, the specific steps of the step 4) are as follows:
4-1)收集整理各坡面位移监测点数据,绘制坡顶水平位移值统计表及坡顶沉降统计表;4-1) Collecting and sorting out the data of each slope displacement monitoring point, drawing the slope top horizontal displacement value statistical table and slope top settlement statistical table;
坡顶水平位移值统计表Statistical table of slope top horizontal displacement value
Figure PCTCN2020113602-appb-000001
Figure PCTCN2020113602-appb-000001
坡顶沉降值统计表Slope Top Settlement Value Statistics Table
Figure PCTCN2020113602-appb-000002
Figure PCTCN2020113602-appb-000002
4-2)收集整理各深层土体位移监测点数据(测斜管以及分层沉降仪),填入监测点位移统计表中;特别地,收集坡面位置测斜管的数据时,需站在预先搭建的平台上读数;(表中坐标为本例测斜管位置,在实际应用中根据各地层厚度灵活调节测斜管位置,满足1-3)的要求即可)4-2) Collect and sort out the data of various deep soil displacement monitoring points (inclinometer tube and layered settlement instrument), and fill in the monitoring point displacement statistics table; in particular, when collecting data on the slope position of the inclinometer tube, a station is required Read on the pre-built platform; (The coordinates in the table are the position of the inclinometer tube in this example. In actual applications, the position of the inclinometer tube can be flexibly adjusted according to the thickness of each layer to meet the requirements of 1-3).
深层土体水平位移值统计表Statistical Table of Horizontal Displacement Values of Deep Soil
Figure PCTCN2020113602-appb-000003
Figure PCTCN2020113602-appb-000003
Figure PCTCN2020113602-appb-000004
Figure PCTCN2020113602-appb-000004
深层土体沉降值统计表Statistical Table of Settlement Value of Deep Soil
Figure PCTCN2020113602-appb-000005
Figure PCTCN2020113602-appb-000005
进一步地,所述步骤5)的具体步骤如下:Further, the specific steps of step 5) are as follows:
根据步骤5-1)及步骤5-2)的监测点位移统计表,确定边坡内部最大位移点的x、y坐标,进而画出边坡的滑移曲线(最大位移为水平位移矢量加竖直位移矢量的模长值),进而确定边坡的破坏模式。为便于理解步骤4-3),特此示例。According to the monitoring point displacement statistics table in step 5-1) and step 5-2), determine the x and y coordinates of the maximum displacement point inside the slope, and then draw the slope slip curve (the maximum displacement is the horizontal displacement vector plus the vertical The modulus length value of the straight displacement vector), and then determine the failure mode of the slope. In order to facilitate the understanding of step 4-3), here is an example.
表1坡顶水平位移值统计表Table 1 Statistical Table of Horizontal Displacement Values of the Top of the Slope
Figure PCTCN2020113602-appb-000006
Figure PCTCN2020113602-appb-000006
表2坡顶沉降值统计表Table 2 Slope Top Settlement Value Statistics Table
Figure PCTCN2020113602-appb-000007
Figure PCTCN2020113602-appb-000007
表3深层土体水平位移值统计表Table 3 Statistical Table of Horizontal Displacement Values of Deep Soil
Figure PCTCN2020113602-appb-000008
Figure PCTCN2020113602-appb-000008
Figure PCTCN2020113602-appb-000009
Figure PCTCN2020113602-appb-000009
表4深层土体沉降值统计表Table 4 Statistical Table of Settlement Value of Deep Soil
Figure PCTCN2020113602-appb-000010
Figure PCTCN2020113602-appb-000010
本例中坡率为1:1,以坡脚为坐标原点,根据表1及表2的数据,判断滑移面坡顶开裂点介于距坡顶水平距离0.1h及0.2h之间,取中间值,开裂点坐标为(1.15h,h);根据表3及表4的数据,得出:In this example, the slope ratio is 1:1, and the toe of the slope is taken as the origin of the coordinate. According to the data in Table 1 and Table 2, it is judged that the cracking point of the slope top of the sliding surface is between 0.1h and 0.2h from the horizontal distance from the top of the slope. The median value, the coordinates of the cracking point are (1.15h, h); according to the data in Table 3 and Table 4, we get:
①距坡顶竖直距离0.1h处,判断滑移面介于距坡脚水平距离1.1h及1.2h之间,取中间值,坐标为(1.15h,0.9h)①At a vertical distance of 0.1h from the top of the slope, it is judged that the sliding surface is between 1.1h and 1.2h from the horizontal distance from the toe of the slope, whichever is the middle value, and the coordinates are (1.15h, 0.9h)
②距坡顶竖直距离0.3h处,判断滑移面介于距坡脚水平距离0.9h及1.1h之间,参考监测点距坡脚水平距离0.75h处的数据,按线性规律,推断出水平位移值为0的坐标为(1.067h,0.7h)②At a vertical distance of 0.3h from the top of the slope, it is judged that the slip surface is between 0.9h and 1.1h from the horizontal distance from the slope toe. Refer to the data at a horizontal distance of 0.75h from the monitoring point to the slope toe, and infer it according to the linear law. The coordinates where the horizontal displacement value is 0 are (1.067h, 0.7h)
③距坡顶竖直距离0.5h处,判断滑移面介于距坡脚水平距离0.6h及0.75h之间,取中间值,坐标为(0.675h,0.5h)③At a vertical distance of 0.5h from the top of the slope, it is judged that the sliding surface is between 0.6h and 0.75h from the horizontal distance from the toe of the slope, the middle value is taken, and the coordinates are (0.675h, 0.5h)
根据上图的坐标作出的曲线即为边坡的圆弧滑移线,与全风化岩层和强风化岩层界线连起来即为土岩双元边坡的滑移线。再与有限元法得到的滑移线进行对比,验证有限元法结果的正确性,为下一步有限元分析提供支撑。The curve drawn according to the coordinates in the above figure is the arc slip line of the slope, and the boundary between the fully weathered rock layer and the strongly weathered rock layer is the slip line of the soil-rock dual-element slope. Then it is compared with the slip line obtained by the finite element method to verify the correctness of the result of the finite element method and provide support for the next step of the finite element analysis.
以上所述仅为本申请的优选实施例而已,并不用于限制本申请,对于本领域的技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。The above descriptions are only preferred embodiments of the application, and are not intended to limit the application. For those skilled in the art, the application can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of this application shall be included in the protection scope of this application.

Claims (10)

  1. 一种土岩双元边坡整体破坏模式的监测验证方法,其特征在于,包括以下步骤:A method for monitoring and verifying the overall failure mode of a soil-rock dual-element slope, which is characterized in that it comprises the following steps:
    1)通过有限元软件对边坡进行模拟,得出边坡的滑移线;1) Simulate the slope through finite element software to obtain the slip line of the slope;
    2)根据边坡施工方案制定监测坡顶及潜在滑移面处的位移变化的监测方案;包括深层土体位移点、坡顶位移监测点以及水准基点的布设方案;2) Develop a monitoring plan for monitoring the displacement changes at the top of the slope and the potential slip surface according to the slope construction plan; including the layout plan of deep soil displacement points, slope top displacement monitoring points and leveling base points;
    3)根据步骤2)确定的布设方案进行施工,并进行监测;3) Carry out construction and monitor according to the layout plan determined in step 2);
    4)对监测数据进行整理,分析边坡表面及内部位移变化情况,特别是土与全风化岩石交界面及全风化岩石与强风化岩石交界面处的位移变化;4) Sorting out the monitoring data, analyzing the surface and internal displacement changes of the slope, especially the displacement changes at the interface between soil and fully weathered rock and at the interface between fully weathered rock and strongly weathered rock;
    5)根据监测分析得出边坡表面位移变化情况确定滑移线的位置,根据边坡内部最大位移点画出边坡的滑移线;5) Determine the position of the slip line according to the changes in the slope surface displacement obtained from the monitoring analysis, and draw the slip line of the slope according to the maximum displacement point inside the slope;
    6)将步骤5)得出的边坡滑移线与有限元法得到的滑移线进行对比,如果无差异,则通过有限元软件进行接下来的支护结构模拟并指导施工,如果有差异,重新进行有限元模拟,再次进行对比,直到无差异。6) Compare the slope slip line obtained in step 5) with the slip line obtained by the finite element method. If there is no difference, use the finite element software to simulate the next supporting structure and guide the construction. If there is a difference , Re-run finite element simulation, and compare again until there is no difference.
  2. 如权利要求1所述的监测验证方法,其特征在于,步骤1)中所述的水准基点的布设方案:The monitoring verification method according to claim 1, wherein the layout plan of the leveling base point in step 1):
    确定边坡施工对坡顶表面位移影响最大的区域,该区域为以坡顶与坡面的交线为起点,向背离边坡施工方向量出1倍边坡高度的区域;水准基点布设在坡顶,且位于边坡施工的影响距离之外。Determine the area where the slope construction has the greatest impact on the surface displacement of the slope top. This area is the area where the intersection of the slope top and the slope surface is taken as the starting point, and one time the slope height is measured away from the slope construction direction; the leveling base point is placed on the slope It is located beyond the influence distance of the slope construction.
  3. 如权利要求1所述的监测验证方法,其特征在于,步骤2)中深层土体位移监测点多数布置在了各地层的交界面处,少量布置在土层内部。The monitoring verification method according to claim 1, characterized in that, in step 2), most of the monitoring points of deep soil displacement are arranged at the interface of each layer, and a few are arranged inside the soil layer.
  4. 如权利要求1所述的监测验证方法,其特征在于,步骤2)中坡顶位移监 测点布置在距坡顶与坡面交线1m及2m的位置处。The monitoring verification method according to claim 1, characterized in that, in step 2), the slope top displacement monitoring points are arranged at positions 1m and 2m away from the intersection line of the slope top and the slope surface.
  5. 如权利要求1所述的监测验证方法,其特征在于,所述步骤3)中:在水准基点布设水准仪;在坡顶位移监测点选用凿入地面一定深度的圆头钢筋,通过观察钢筋圆头的沉降得到监测点的地面沉降,通过观察钢筋圆头与水准基点的距离得到监测点的水平位移。The monitoring verification method according to claim 1, characterized in that, in the step 3): arranging a level at the base point of the leveling; at the slope top displacement monitoring point, select round-headed steel bars chiseled into the ground to a certain depth, and observe the round-head of the steel bars. Observe the ground settlement of the monitoring point, and obtain the horizontal displacement of the monitoring point by observing the distance between the round head of the steel bar and the base point of the leveling.
  6. 如权利要求5所述的监测验证方法,其特征在于,所述步骤3)中:在深层土体位移点处分别预埋与测斜仪配合的测斜管,测斜管每隔一段距离设置一个,且测斜管布置在地层交界面处,通过多列测斜管的设置形成了多列深层土体位移监测点。The monitoring verification method according to claim 5, characterized in that, in the step 3): the inclinometer tubes matched with the inclinometer are respectively pre-embedded at the displacement points of the deep soil, and the inclinometer tubes are arranged at intervals One, and the inclinometer tube is arranged at the stratum interface, and multiple rows of deep soil displacement monitoring points are formed by the arrangement of multiple rows of inclinometer tubes.
  7. 如权利要求6所述的监测验证方法,其特征在于,所述步骤3)中:在有限元模拟得出的滑移面左右两侧的深层土体位移监测点布置分层沉降仪,与测斜管同时安装。The monitoring verification method according to claim 6, characterized in that, in the step 3): the deep soil displacement monitoring points on the left and right sides of the slip surface obtained by the finite element simulation are arranged with a layered settlement instrument, and Inclined pipes are installed at the same time.
  8. 如权利要求1所述的监测验证方法,其特征在于,所述步骤4)的具体步骤如下:The monitoring verification method according to claim 1, wherein the specific steps of step 4) are as follows:
    4-1)收集整理各坡面位移监测点数据,绘制坡顶水平位移值统计表及坡顶沉降统计表;4-1) Collect and sort out the data of each slope displacement monitoring point, draw the slope top horizontal displacement value statistics table and slope top settlement statistics table;
    4-2)收集整理各深层土体位移监测点数据,利用监测点位移统计表进行统计。4-2) Collect and sort out the data of various deep soil displacement monitoring points, and use the displacement statistics table of the monitoring points to make statistics.
  9. 如权利要求8所述的监测验证方法,其特征在于,所述步骤5)的具体步骤如下:The monitoring verification method according to claim 8, wherein the specific steps of step 5) are as follows:
    根据步骤4-1)及步骤4-2)的监测点位移统计表,确定边坡内部最大位移点的x、y坐标,进而画出边坡的滑移曲线,进而确定边坡的破坏模式。According to the monitoring point displacement statistics table of step 4-1) and step 4-2), determine the x and y coordinates of the maximum displacement point inside the slope, and then draw the slip curve of the slope, and then determine the failure mode of the slope.
  10. 一种土岩双元边坡整体破坏模式的监测验证系统,其特征在于,包括A monitoring and verification system for the overall failure mode of a soil-rock dual-element slope, which is characterized in that it includes
    表面位移监测装置,其安装在坡顶,用于监测坡顶的水平位移和垂直位移;Surface displacement monitoring device, which is installed on the top of the slope to monitor the horizontal and vertical displacement of the top of the slope;
    测斜管,其安装在边坡土体内部及土岩交界面处,用于监测边坡土体内部以及土岩交界面处的水平位移;Inclinometer tube, which is installed inside the slope soil and the soil-rock interface, used to monitor the horizontal displacement of the slope soil and the soil-rock interface;
    分层沉降仪,其安装在边坡滑移面,用于监测边坡土体的竖直位移;The layered settlement instrument, which is installed on the sliding surface of the slope, is used to monitor the vertical displacement of the slope soil;
    数据处理装置,获取表面位移监测装置、测斜仪和分层沉降仪监测的数据,分析边坡表面及内部位移变化情况,特别是土与全风化岩石交界面及全风化岩石与强风化岩石交界面处的位移变化;根据监测分析得出边坡表面位移变化情况确定滑移线的位置,根据边坡内部最大位移点画出边坡的滑移线;将得出的边坡滑移线与有限元法得到的滑移线进行对比,如果无差异,则通过有限元软件进行接下来的支护结构模拟并指导施工,如果有差异,重新进行有限元模拟,再次进行对比,直到无差异。The data processing device obtains the data monitored by the surface displacement monitoring device, the inclinometer and the layer settlement instrument, and analyzes the surface and internal displacement changes of the slope, especially the interface between the soil and the fully weathered rock and the interaction between the fully weathered rock and the strongly weathered rock The displacement change at the interface; determine the position of the slip line according to the monitoring and analysis of the slope surface displacement change, and draw the slope slip line according to the maximum displacement point inside the slope; compare the obtained slope slip line with Compare the slip lines obtained by the finite element method. If there is no difference, use the finite element software to simulate the next supporting structure and guide the construction. If there is a difference, perform the finite element simulation again and compare again until there is no difference.
PCT/CN2020/113602 2020-03-02 2020-09-04 Monitoring and verifying system and method for overall failure mode of soil-rock dual-element side slope WO2021174794A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2020433233A AU2020433233B2 (en) 2020-03-02 2020-09-04 System and method for monitoring and verifying global failure mode of soil and rock dual-element side slope

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202010135587.2 2020-03-02
CN202010135587.2A CN111305286B (en) 2020-03-02 2020-03-02 Monitoring and verifying system and method for soil-rock double-element slope overall failure mode

Publications (1)

Publication Number Publication Date
WO2021174794A1 true WO2021174794A1 (en) 2021-09-10

Family

ID=71152163

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/113602 WO2021174794A1 (en) 2020-03-02 2020-09-04 Monitoring and verifying system and method for overall failure mode of soil-rock dual-element side slope

Country Status (3)

Country Link
CN (1) CN111305286B (en)
AU (1) AU2020433233B2 (en)
WO (1) WO2021174794A1 (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113847956A (en) * 2021-09-23 2021-12-28 华北水利水电大学 Landslide sliding displacement and sliding speed monitoring method based on optical dispersion
CN114091162A (en) * 2021-11-26 2022-02-25 内蒙古平西白音华煤业有限公司 Improved Plante formula-based method for determining bearing capacity of inner soil discharge field substrate
CN114164843A (en) * 2021-11-10 2022-03-11 中交第四航务工程局有限公司 Construction method of high slope excavation slope protection system
CN114234780A (en) * 2021-11-09 2022-03-25 煤炭科学技术研究院有限公司 Slope sliding monitoring method and device
CN114659490A (en) * 2022-01-27 2022-06-24 江苏省水利科学研究院 Real-time monitoring and bank-caving early warning method for displacement of underwater bank slope at bank-caving easy-to-occur section
CN114855741A (en) * 2022-04-18 2022-08-05 中南大学 Intelligent monitoring method for long-term deformation of railway and station yard roadbed space on complex accumulation body
CN115198815A (en) * 2022-07-27 2022-10-18 东南大学 Side slope internal deformation distributed monitoring system based on piezoelectric self-sensing geotechnical cable and construction method
CN115354703A (en) * 2022-09-23 2022-11-18 广西华南岩土工程集团有限公司 Building engineering side slope displacement monitoring devices
CN115374639A (en) * 2022-08-23 2022-11-22 辽宁工程技术大学 Method for quantitatively determining peripheral surface subsidence of inclined-base refuse dump
CN115600510A (en) * 2022-11-28 2023-01-13 华北科技学院(中国煤矿安全技术培训中心)(Cn) Stability assessment method and system for soil-rock mixture side slope of strip mine refuse dump
CN115752319A (en) * 2022-10-18 2023-03-07 天津风霖物联网科技有限公司 Automatic horizontal displacement monitoring system and monitoring method
CN115897526A (en) * 2022-11-28 2023-04-04 泉州装备制造研究所 Soil slope sliding surface identification and reinforcement method
CN117349779A (en) * 2023-12-04 2024-01-05 水利部交通运输部国家能源局南京水利科学研究院 Method and system for judging potential sliding surface of deep-excavation expansive soil channel side slope
CN117552483A (en) * 2024-01-10 2024-02-13 山西金宝岛基础工程有限公司 Test method for foundation reinforcement influence range of dynamic compaction treatment
CN117686687A (en) * 2024-02-01 2024-03-12 内蒙古工业大学 Interface type scale model landslide simulation test device and simulation method

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111305286B (en) * 2020-03-02 2022-02-11 山东大学 Monitoring and verifying system and method for soil-rock double-element slope overall failure mode
CN112343065B (en) * 2020-09-30 2021-12-28 中冶成都勘察研究总院有限公司 Maintenance method for red bed mudstone block filler high-fill side slope
CN113931238A (en) * 2021-10-15 2022-01-14 中交天津港湾工程研究院有限公司 Method for monitoring position of potential slip surface of foundation pit slope

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003084070A (en) * 2001-09-10 2003-03-19 Geoscience Research Laboratory Method of analyzing vibration waveform, and monitor for monitoring slope face of bedrock
CN101963501A (en) * 2010-08-12 2011-02-02 刘文峰 Construction method for monitoring slope stability by using mobile inclinometer
CN102968884A (en) * 2012-12-04 2013-03-13 中铁二十一局集团有限公司 Slide-face type remote three-dimensional digital pre-warning method and system for stability of high slope
KR20140097783A (en) * 2013-01-30 2014-08-07 한밭대학교 산학협력단 Treatment method of inclined boundaries in a finite element model using the mild-slope equation
CN104501766A (en) * 2014-12-25 2015-04-08 青岛理工大学 Deep foundation pit excavation slope vertical displacement vector angle parameter monitoring and pre-warning method
CN105526908A (en) * 2015-09-16 2016-04-27 鞍钢集团矿业公司 Three dimensional laser scanning-GPS-combined side slope monitoring method
CN106777556A (en) * 2016-11-29 2017-05-31 武汉理工大学 A kind of spacial analytical method for assessing slope excavating phase stable state
CN106767476A (en) * 2016-11-11 2017-05-31 南京大学 A kind of slope stability monitoring and landslide early alarming and forecasting method based on all -fiber sensing network
CN107655444A (en) * 2017-09-08 2018-02-02 广西交通科学研究院有限公司 With reference to monitoring with finite element amendment with determine slope sliding face change method
CN107908890A (en) * 2017-11-27 2018-04-13 辽宁工程技术大学 A kind of Soft-rock slope stability finite element analysis and monitoring, method for protecting support
CN111305286A (en) * 2020-03-02 2020-06-19 山东大学 Monitoring and verifying system and method for soil-rock double-element slope overall failure mode

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103198619B (en) * 2013-03-08 2015-07-08 青岛理工大学 Motive power monitoring and warning method of rock mass landslide
CN104007246B (en) * 2014-05-14 2015-09-16 河南理工大学 The controlled sliding surface slope stability similar test system of three-dimensional coupling
CN106677151A (en) * 2015-11-11 2017-05-17 尤世元 Measuring method of slippage face
CN106650118B (en) * 2016-12-27 2019-12-20 青岛理工大学 Optimization design method for governing parameters of side slope slide-resistant pile

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003084070A (en) * 2001-09-10 2003-03-19 Geoscience Research Laboratory Method of analyzing vibration waveform, and monitor for monitoring slope face of bedrock
CN101963501A (en) * 2010-08-12 2011-02-02 刘文峰 Construction method for monitoring slope stability by using mobile inclinometer
CN102968884A (en) * 2012-12-04 2013-03-13 中铁二十一局集团有限公司 Slide-face type remote three-dimensional digital pre-warning method and system for stability of high slope
KR20140097783A (en) * 2013-01-30 2014-08-07 한밭대학교 산학협력단 Treatment method of inclined boundaries in a finite element model using the mild-slope equation
CN104501766A (en) * 2014-12-25 2015-04-08 青岛理工大学 Deep foundation pit excavation slope vertical displacement vector angle parameter monitoring and pre-warning method
CN105526908A (en) * 2015-09-16 2016-04-27 鞍钢集团矿业公司 Three dimensional laser scanning-GPS-combined side slope monitoring method
CN106767476A (en) * 2016-11-11 2017-05-31 南京大学 A kind of slope stability monitoring and landslide early alarming and forecasting method based on all -fiber sensing network
CN106777556A (en) * 2016-11-29 2017-05-31 武汉理工大学 A kind of spacial analytical method for assessing slope excavating phase stable state
CN107655444A (en) * 2017-09-08 2018-02-02 广西交通科学研究院有限公司 With reference to monitoring with finite element amendment with determine slope sliding face change method
CN107908890A (en) * 2017-11-27 2018-04-13 辽宁工程技术大学 A kind of Soft-rock slope stability finite element analysis and monitoring, method for protecting support
CN111305286A (en) * 2020-03-02 2020-06-19 山东大学 Monitoring and verifying system and method for soil-rock double-element slope overall failure mode

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113847956B (en) * 2021-09-23 2023-11-17 华北水利水电大学 Landslide sliding displacement and sliding speed monitoring method based on light dispersion
CN113847956A (en) * 2021-09-23 2021-12-28 华北水利水电大学 Landslide sliding displacement and sliding speed monitoring method based on optical dispersion
CN114234780A (en) * 2021-11-09 2022-03-25 煤炭科学技术研究院有限公司 Slope sliding monitoring method and device
CN114234780B (en) * 2021-11-09 2024-04-12 煤炭科学技术研究院有限公司 Sliding monitoring method and device for slope
CN114164843A (en) * 2021-11-10 2022-03-11 中交第四航务工程局有限公司 Construction method of high slope excavation slope protection system
CN114164843B (en) * 2021-11-10 2023-10-13 中交第四航务工程局有限公司 Construction method of high side slope excavation slope protection system
CN114091162A (en) * 2021-11-26 2022-02-25 内蒙古平西白音华煤业有限公司 Improved Plante formula-based method for determining bearing capacity of inner soil discharge field substrate
CN114659490A (en) * 2022-01-27 2022-06-24 江苏省水利科学研究院 Real-time monitoring and bank-caving early warning method for displacement of underwater bank slope at bank-caving easy-to-occur section
CN114855741A (en) * 2022-04-18 2022-08-05 中南大学 Intelligent monitoring method for long-term deformation of railway and station yard roadbed space on complex accumulation body
CN114855741B (en) * 2022-04-18 2022-12-30 中南大学 Intelligent monitoring method for long-term deformation of railway and station yard subgrade space on complex accumulation body
CN115198815B (en) * 2022-07-27 2023-08-25 东南大学 Side slope internal deformation distributed monitoring system based on piezoelectric self-sensing geotechnical cable and construction method
CN115198815A (en) * 2022-07-27 2022-10-18 东南大学 Side slope internal deformation distributed monitoring system based on piezoelectric self-sensing geotechnical cable and construction method
CN115374639B (en) * 2022-08-23 2023-11-14 辽宁工程技术大学 Quantitative determination method for surface subsidence around inclined substrate dumping site
CN115374639A (en) * 2022-08-23 2022-11-22 辽宁工程技术大学 Method for quantitatively determining peripheral surface subsidence of inclined-base refuse dump
CN115354703B (en) * 2022-09-23 2023-09-19 广西华南岩土工程集团有限公司 Building engineering side slope displacement monitoring devices
CN115354703A (en) * 2022-09-23 2022-11-18 广西华南岩土工程集团有限公司 Building engineering side slope displacement monitoring devices
CN115752319A (en) * 2022-10-18 2023-03-07 天津风霖物联网科技有限公司 Automatic horizontal displacement monitoring system and monitoring method
CN115752319B (en) * 2022-10-18 2023-08-15 天津风霖物联网科技有限公司 Automatic horizontal displacement monitoring system and monitoring method
CN115897526A (en) * 2022-11-28 2023-04-04 泉州装备制造研究所 Soil slope sliding surface identification and reinforcement method
CN115600510B (en) * 2022-11-28 2023-06-20 华北科技学院(中国煤矿安全技术培训中心) Stability evaluation method and system for soil-stone mixture side slope of strip mine dumping site
CN115600510A (en) * 2022-11-28 2023-01-13 华北科技学院(中国煤矿安全技术培训中心)(Cn) Stability assessment method and system for soil-rock mixture side slope of strip mine refuse dump
CN117349779A (en) * 2023-12-04 2024-01-05 水利部交通运输部国家能源局南京水利科学研究院 Method and system for judging potential sliding surface of deep-excavation expansive soil channel side slope
CN117349779B (en) * 2023-12-04 2024-02-09 水利部交通运输部国家能源局南京水利科学研究院 Method and system for judging potential sliding surface of deep-excavation expansive soil channel side slope
CN117552483A (en) * 2024-01-10 2024-02-13 山西金宝岛基础工程有限公司 Test method for foundation reinforcement influence range of dynamic compaction treatment
CN117552483B (en) * 2024-01-10 2024-04-16 山西金宝岛基础工程有限公司 Test method for foundation reinforcement influence range of dynamic compaction treatment
CN117686687A (en) * 2024-02-01 2024-03-12 内蒙古工业大学 Interface type scale model landslide simulation test device and simulation method
CN117686687B (en) * 2024-02-01 2024-04-16 内蒙古工业大学 Interface type scale model landslide simulation test device and simulation method

Also Published As

Publication number Publication date
CN111305286B (en) 2022-02-11
AU2020433233B2 (en) 2023-06-08
CN111305286A (en) 2020-06-19
AU2020433233A1 (en) 2022-01-06

Similar Documents

Publication Publication Date Title
WO2021174794A1 (en) Monitoring and verifying system and method for overall failure mode of soil-rock dual-element side slope
CN102434209B (en) Monitoring method for influence on adjacent existing structures from tunnel excavation
CN106644206B (en) A kind of pressure from surrounding rock calculation method for shallow tunnel
CN103150421A (en) Method for simultaneously determining pile position and critical depth of anti-slide pile by using displacement monitoring
CN109299578A (en) Excavation of foundation pit causes the calculation method of lower sleeping existing shield tunnel protuberance deformation
CN104328776B (en) A kind of method predicting that the soil body and surrounding enviroment are affected by power dynamic compaction tool
CN108693572A (en) A kind of ground stress field inversion method based on three-dimensional modeling
CN108318584A (en) Single-hole sound-wave combines the method for across hole CT detections pile quality and gradient
CN112035937B (en) Tunnel construction surrounding rock deformation analysis and informatization construction method
CN106383945A (en) Universal design calculation method for deep/shallow-buried vertical surrounding rock pressure of tunnel and underground space
CN106919770A (en) A kind of damage variable based on numerical simulation determines method
Lehtonen et al. Full-scale embankment failure test under simulated train loading
CN104613886B (en) Long-gauge FBG (Fiber Bragg Grating) based settlement joint two-dimensional deformation and opposite inclination monitoring method
CN109461359A (en) A kind of aqueous geological structure forward probe method in tunnel
CN110287511A (en) Pile Type and Construction Quality Control Method based on BIM technology
CN110046470A (en) A kind of shield driving causes ground settlement method for determination of amount after work
CN111539052B (en) Method for formulating settlement control standard of close-distance downward-penetrating pipe-jacking tunnel in subway shield interval
CN110245426B (en) Finite element refined simulation method for pipe gallery structure pipe jacking construction
CN101922159A (en) Method for quickly detecting quality of gravel pile
CN116680934B (en) Method for calculating vertical deformation of lower tunnel caused by stratum excavation based on unloading rate
CN103344214B (en) 1.6-degree parabolic extralarge pier measuring and pier body linear control method
CN107843712A (en) A kind of analogue means of the vertical mechanism that digs a hole of karst water
CN201738344U (en) Vibration safety monitoring device for support blasting demolition in foundation pit
CN108050986B (en) The method for determining Rock And Soil internal rupture face position is monitored based on multipoint displacement meter
CN115495956A (en) Safety evaluation method for unloading deformation of deep and large rocky foundation pit

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20923161

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2020433233

Country of ref document: AU

Date of ref document: 20200904

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20923161

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 20923161

Country of ref document: EP

Kind code of ref document: A1