WO2021023246A1 - Open foundation pit block construction system and method - Google Patents

Open foundation pit block construction system and method Download PDF

Info

Publication number
WO2021023246A1
WO2021023246A1 PCT/CN2020/107264 CN2020107264W WO2021023246A1 WO 2021023246 A1 WO2021023246 A1 WO 2021023246A1 CN 2020107264 W CN2020107264 W CN 2020107264W WO 2021023246 A1 WO2021023246 A1 WO 2021023246A1
Authority
WO
WIPO (PCT)
Prior art keywords
support
temporary
construction
area
foundation pit
Prior art date
Application number
PCT/CN2020/107264
Other languages
French (fr)
Chinese (zh)
Inventor
郑礼彬
凌杰
姚鑫豪
顾亮
Original Assignee
上海建工二建集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 上海建工二建集团有限公司 filed Critical 上海建工二建集团有限公司
Publication of WO2021023246A1 publication Critical patent/WO2021023246A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Definitions

  • the invention relates to the technical field of foundation pit engineering, in particular to an open foundation pit block construction system and method.
  • the foundation pit design is based on the principle of "safety, reasonableness, economy, and ease of construction". As the depth of the foundation pit becomes deeper, the complexity of the supporting system and the number of supports increase, and the construction period and construction difficulty also follow.
  • the deep foundation pit is constructed by the normal construction method. According to the conventional construction, the construction process at the structural stage is generally formed and maintained by the bottom plate construction. After the concrete strength reaches 80% of the design requirement, the previous support can be removed.
  • the first floor structure shall be constructed according to this construction principle until the basement roof is completed. The core idea is that the basement deep foundation pit must be constructed as a whole.
  • the block enclosure and separation system (such as retaining piles and underground continuous walls for separation) must be completed before excavation, and then the construction of the pit shall be carried out.
  • the principle is that the basement structure of one pit is completed Then excavate adjacent foundation pits.
  • the foundation pit When the excavation of the foundation pit has been completed and the separation enclosure system has not been set up in advance, the foundation pit must be constructed simultaneously as a whole, and some areas cannot be constructed first.
  • the purpose of the present invention is to provide an open foundation pit block construction system and method, which are safe and reliable.
  • foundation pits that have been excavated and constructed without a partitioned enclosure system, they can achieve the purpose of pre-construction in some areas of the foundation pit. After the excavation of the foundation pit and the separation enclosure system is not constructed, the existing construction of the part of the foundation pit cannot be performed.
  • the present invention provides the following technical solutions:
  • An open block construction system for foundation pits is used for excavated foundation pits.
  • the foundation pit is at least divided into a first construction area, a support replacement area and a post construction area.
  • the foundation pit is provided with several layers of supports from bottom to top, Each support includes a horizontal support that penetrates the first construction area, the support change area, and the later construction area, and a longitudinal support that intersects the transverse support.
  • the support change area is located between the first construction area and the later construction area.
  • a support change structure for supporting the support located in the support change area is provided in the foundation pit.
  • the support replacement structure includes a first temporary support replacement column, a support replacement board wall, a replacement support rod member, and a second temporary replacement support column.
  • the slab wall is arranged on both sides of the lateral support, one end of the re-supporting slab wall is close to the first construction area, and the other end is close to the post-construction area.
  • the first temporary re-supporting columns are arranged on both sides of the re-supporting slab wall.
  • the upper and lower sides of the transverse support sandwiched between the supporting board walls are respectively provided with an upper edge banding beam and a lower edge banding beam.
  • the two ends of the upper edge banding beam and the lower edge banding beam correspond to
  • the supporting board wall is fixedly connected, the second temporary supporting column is arranged on the bottom plate of the first construction area, and the supporting bar is arranged between the second temporary supporting column and the corresponding first temporary supporting column Pieces.
  • the bracing structure further includes a third temporary bracing column for supporting the second temporary bracing column, and the third temporary bracing column
  • a strut changing member is arranged between the corresponding second temporary strut changing column.
  • the second temporary bracing column is provided with two bracing rod members for each heightening part, and the bracing rod member located above is connected to the first temporary brace rod member.
  • the same heightening part on the changing support column, the lower changing support rod piece is connected to the last construction part on the first temporary changing support column, and the connection point between the two changing support rod parts and the second temporary changing support column is higher than
  • the elevation before the heightening of the supporting board wall is smaller than that after the heightening of the supporting board wall.
  • the first temporary support column is fixedly connected with the adjacent longitudinal support.
  • the invention also discloses a construction method of the open foundation pit block construction system as described above, which includes the following steps:
  • Step 1 Divide the excavated foundation pit into a first construction area, a support replacement area, and a later construction area.
  • the support replacement area is located between the first construction area and the later construction area.
  • Step two construct the bottom plate of the support change area and the bottom plate of the first construction area.
  • construct the support change structure used to support the bottom support of the support change area.
  • the support change structure includes Replacing the slab wall, the first temporary replacing pillar, the upper edge banding beam, the lower edge banding beam, the second temporary replacing pillar with corbels, and the corresponding first and second temporary replacing pillars
  • the bracing rod member between the columns, the bracing wall, the first temporary bracing column, the upper edge banding beam, and the lower edge banding beam are located in the bracing region, and the bracing wall is set on the bottom support On both sides of the lateral support, one end of the support wall is close to the first construction area, and the other end is close to the post-construction area.
  • the first temporary support column is set at both ends of the support wall, and is sandwiched between The upper and lower sides of the transverse support between the support board walls are respectively provided with the upper edge banding beam and the lower edge banding beam, and the two ends of the upper edge banding beam and the lower edge banding beam are respectively corresponding to the support Fixed connection of board and wall;
  • Step 3 When the concrete strength of the support replacement structure to be used to support the bottom support of the support replacement area reaches the design strength, remove the lowest support of the first construction area;
  • Step 4 The wall of the support replacement area and the first temporary replacement support columns at both ends are raised to the upper support elevation.
  • the construction is used to support the support replacement structure above the support replacement area and the bottom of the first construction area
  • the floor slab, the support change structure used to support a support above the support change area includes a heightened part on the second temporary support column, the heightened part provided on the second temporary support column and the corresponding first temporary support Change the support rod between the support pillars;
  • Step 5 The concrete to be used to support the support replacement structure above the support replacement area and the lowermost floor of the first construction area reaches the design strength, and the first construction area is removed and then the upper layer of support is removed;
  • Step 6 repeat steps 4 and 5 until the uppermost support of the first construction area is removed, and the roof structure of the first construction area is completed;
  • Step seven follow the structure of the construction area after completion
  • Step 8 Remove the support structure from top to bottom;
  • Step Nine complete the structure of the support replacement area.
  • the second temporary support column is provided with a corbel for arranging the corresponding support rod member.
  • the support replacement structure further includes a third temporary support post for supporting the second temporary support post, and the third temporary support post A strut changing member is arranged between the supporting column and the corresponding second temporary supporting column.
  • the third temporary support column is provided with a corbel for arranging the corresponding support member.
  • the second temporary support column is provided with two support change rods at each heightened part, and the upper support change rod is connected The same heightened part of the first temporary support column, the lower part of the support replacement rod is connected to the last construction part of the first temporary support column, and the connection of the two support rod parts to the second temporary support column
  • the location is higher than the elevation before the heightening of the supporting board wall and smaller than the elevation after the heightening of the supporting board wall.
  • the open-type foundation pit block construction system provided by the present invention, for the foundation pits that have been excavated but cannot be divided into the enclosure system through construction to achieve partial priority construction of the foundation pit, by dividing the foundation pit into the first construction area and replacing the support Area and post-construction area, the support replacement area is located between the first construction area and the post-construction area, and each support in the foundation pit includes lateral supports that penetrate the first construction area, the support replacement area and the post-construction area And the longitudinal support that intersects with the horizontal support, by setting up the support change structure for supporting the support change area, the support of the corresponding layer in the first construction area can be removed first, and then the underground structure construction of the corresponding layer in the first construction area can be carried out. Without having to complete the overall construction of the foundation pit, the priority construction of the partial area of the foundation pit can be realized to meet the requirements of special construction period.
  • the construction method of the open foundation pit block construction system divides the excavated foundation pit into a first construction area, a support replacement area and a later construction area, and the support replacement area is located between the first construction area and Between the post-construction areas, by sequentially setting up the support replacement structure for supporting the support replacement area, the support of the corresponding layer of the first construction area can be removed first, and then the underground structure of the corresponding layer of the first construction area can be carried out Therefore, it is possible to achieve priority construction in partial areas of the foundation pit without completing the overall construction of the foundation pit to meet the requirements of the special construction period.
  • FIGS 1 to 25 are schematic diagrams of the construction process of the construction method of the open foundation pit block construction system according to the embodiment of the present invention (also are the structural schematic diagrams of the open foundation pit block construction system at each step).
  • Fig. 2 is a cross-sectional view of 1-1 in Fig. 1.
  • Fig. 5 is a cross-sectional view of 2-2 of Fig. 4.
  • Fig. 8 is a 3-3 sectional view of Fig. 7.
  • FIG. 1 discloses an open foundation pit block construction system for an already excavated foundation pit.
  • the foundation pit is at least divided into a first construction area and a replacement support
  • Each support includes a horizontal support 2 that penetrates the first construction area, a support replacement area, and a post construction area, and a longitudinal support 3 that intersects the horizontal support 2.
  • the support change area is located between the first construction area and the post construction area, and a support change structure for supporting the support located in the support change area is provided in the foundation pit.
  • the open-type foundation pit block construction system provided by the present invention, for the foundation pits that have been excavated but cannot be divided into the enclosure system through construction to achieve partial priority construction of the foundation pit, by dividing the foundation pit into the first construction area and replacing the support Area and post-construction area, the support replacement area is located between the first construction area and the post-construction area, and each support in the foundation pit includes lateral supports that penetrate the first construction area, the support replacement area and the post-construction area 2 and the longitudinal support 3 that intersects with the lateral support 2.
  • the support replacement structure for supporting the support replacement area By setting the support replacement structure for supporting the support replacement area, the support of the corresponding layer in the first construction area can be removed first, and then the underground structure of the corresponding layer in the first construction area can be removed Therefore, it is possible to achieve priority construction in partial areas of the foundation pit without completing the overall construction of the foundation pit to meet the requirements of the special construction period.
  • the support replacement structure includes a first temporary support replacement column 4, a support replacement board wall 5, a support replacement member 6 and a second temporary replacement support column 7.
  • the supporting board wall 5 is arranged on both sides of the lateral support 2, one end of the supporting board wall 5 is close to the first construction area, the other end is close to the post construction area, and the first temporary supporting column 4 is arranged at At both ends of the supporting board wall 5, the upper and lower sides of the lateral support 2 sandwiched between the supporting board wall 5 are respectively provided with an upper edge banding beam 8 and a lower edge banding beam 9, the upper sealing The two ends of the edge beam 8 and the lower edge banding beam 9 are respectively fixedly connected to the corresponding support plate wall 5, the second temporary support column 7 is arranged on the bottom plate 1 of the first construction area, and the second temporary A strut changing member 6 is provided between the supporting pole 7 and the corresponding first temporary supporting pole 4.
  • the support wall 5 By arranging the support wall 5 on both sides of the lateral support 2, the upper and lower sides of the lateral support 2 sandwiched between the support wall 5 are provided with an upper edge banding beam 8 and a lower edge banding beam 9, respectively, The two ends of the upper edge banding beam 8 and the lower edge banding beam 9 are respectively fixedly connected to the corresponding support plate wall 5, which can realize the support of the lateral support 2.
  • the provision of the first temporary support column 4 can strengthen the strength of the support plate wall 5; by arranging a second temporary support column 7 on the bottom plate 1 of the first construction area, the second temporary support column 7
  • the bracing rod member 6 is arranged between the corresponding first temporary bracing column 4, which can further improve the supporting effect of the bracing plate wall 5 on the lateral support 2 and realize the safe and reliable construction of the foundation pit.
  • the support replacement structure further includes a third temporary support post 10 for supporting the second temporary support post 7, and the third temporary support post
  • a strut changing member 6 is arranged between the strut 10 and the corresponding second temporary strut changing 7.
  • a third temporary support post 10 can be added, and the third temporary support post 10 and the corresponding second temporary support post 10 can be added.
  • the supporting rod member 6 is arranged between 7 to improve the stability of the second temporary supporting column 7, thereby ensuring the stability of the supporting structure and ensuring construction safety.
  • the second temporary bracing column 7 is provided with two bracing rod members 6 each time the height is increased, and the bracing rod member 6 located above is connected The same heightened part on the first temporary support column 4, the lower support rod member 6 is connected to the last construction part of the first temporary support column 4, and the two support rod members 6 are connected to the second temporary
  • the joint of the brace 7 is higher than the elevation of the support wall 5 before heightening and less than the elevation of the brace wall 5 after heightening, so that it is between the first temporary replacement support column 4 and the second temporary replacement support column 7
  • a broken-line support structure is formed to provide strong support to the first temporary support column 4, and further to achieve stable support for the support located in the support change area.
  • the third temporary bracing column 10 is provided with a corbel (not shown) for arranging the corresponding bracing rod member 6.
  • a corbel (not shown) for arranging the corresponding bracing rod member 6.
  • the first temporary support column 4 is fixedly connected to the adjacent longitudinal support 3, so that the longitudinal support 3 of the foundation pit can be used for the first temporary support
  • the supporting function of the column 4 improves the stability of the first temporary support replacement column 4, thereby further improving the stability of the support replacement structure.
  • the present invention also discloses a construction method of the open foundation pit block construction system as described above, which includes the following steps:
  • Step 1 Divide the excavated foundation pit into a first construction area, a support replacement area, and a later construction area.
  • the support replacement area is located between the first construction area and the later construction area.
  • Step two please refer to Figure 1 to Figure 2. Construction of the bottom plate 1 of the support replacement area and the bottom plate 1 of the first construction area. After the concrete strength of the bottom plate 1 reaches the design requirements, construct the bottom support for the support replacement area Support replacement structure, the support replacement structure includes the support replacement wall 5, the first temporary replacement support column 4, the upper edge sealing beam 8, the lower edge sealing beam 9, and the second temporary replacement support column 7 with a corbel And the supporting rod member 6 arranged between the corresponding first temporary supporting column 4 and the second temporary supporting column 7, the supporting plate wall 5, the first temporary supporting column 4, the upper edge banding beam 8, The lower edge banding beam 9 is located in the support replacement area, the support replacement wall 5 is arranged on both sides of the lowermost supported transverse support 2, one end of the support replacement wall 5 is close to the first construction area, and the other end is close to the rear In the construction area, the first temporary bracing column 4 is arranged at both ends of the bracing wall 5, and the upper and lower sides of the lateral support 2 sandwiched between the bracing wall 5 are respectively
  • Step 3 Refer to Figure 3.
  • the concrete strength of the support replacement structure to be used to support the bottom support of the support replacement area reaches the design strength, remove the lowest support of the first construction area;
  • Step 4 please refer to Figure 4 to Figure 5.
  • the support wall 5 and the first temporary support column 4 at both ends in the support change area are raised to the upper support elevation, and the construction is used to support the change of a support above the support change area.
  • the support structure and the lowermost floor 12 of the first construction area, the support replacement structure used to support a support above the support replacement area includes a heightened part on the second temporary support replacement column 7, which is arranged in the second temporary support replacement The heightened part of the column 7 and the corresponding first temporary change support rod member 6 between the support column 4;
  • Step 5 please refer to Figure 6.
  • the concrete to be used to support the support replacement structure above the support replacement area and the lowermost floor 12 of the first construction area reaches the design strength, and the first construction area is removed and then the upper layer of support is removed;
  • Step 6 refer to Figure 7 to Figure 10, repeat steps 4 and 5 until the top support of the first construction area is removed, and the roof structure of the first construction area is completed;
  • Step 7 refer to Figure 11 to Figure 16, and follow the structure of the construction area after completion;
  • Step 8 Please refer to Figure 17 to Figure 19 to remove the support structure from top to bottom;
  • Step 9 Please refer to Figure 20 to Figure 25 to complete the structure of the support replacement area.
  • the construction method of the open foundation pit block construction system divides the excavated foundation pit into a first construction area, a support replacement area and a later construction area, and the support replacement area is located between the first construction area and Between the post-construction areas, by sequentially setting up the support replacement structure for supporting the support replacement area, the support of the corresponding layer of the first construction area can be removed first, and then the underground structure of the corresponding layer of the first construction area can be carried out Therefore, it is possible to achieve priority construction in partial areas of the foundation pit without completing the overall construction of the foundation pit to meet the requirements of the special construction period.
  • the support replacement structure further includes a third temporary support post 10 for supporting the second temporary support post 7, and the second temporary support post 7
  • the third temporary support change post 10 and the corresponding second temporary support change post 7 are provided with a support change member 6.
  • a third temporary support post 10 can be added, and the third temporary support post 10 and the corresponding second temporary support post 10 can be added.
  • the supporting rod member 6 is arranged between 7 to improve the stability of the second temporary supporting column 7, thereby ensuring the stability of the supporting structure and ensuring construction safety.
  • the third temporary support column 10 is provided with a corbel for arranging the corresponding support rod member 6.
  • the second temporary support pole 7 is provided with a corbel for arranging the corresponding support pole member 6.
  • the second temporary support column 7 is provided with two support rod members 6 each time the height is increased, and the upper support rod Piece 6 is connected to the same heightened part of the first temporary support column 4, and the lower part of the support replacement member 6 is connected to the last construction part of the first temporary change of support column 4.
  • the junction of the temporary support column 7 is higher than the elevation of the support replacement wall 5 before heightening and less than the elevation of the support replacement wall 5 after the heightening, so that the first temporary support column 4 is replaced with the second temporary support column
  • a broken-line support structure is formed between 7 to provide strong support for the first temporary support column 4, and further to achieve stable support for the support located in the support change area.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to the technical field of foundation pit engineering, and relates to an open foundation pit block construction system and method. The problem in which a partition wall enclosure structure cannot be constructed after an existing foundation pit is excavated, and thereby construction cannot be expedited locally, is targeted. In the present invention, for a foundation pit that has been excavated but cannot be constructed by dividing an enclosure system to achieve partial priority construction for the foundation pit, the foundation pit is divided into a pre-construction region, a support replacement region and a post-construction region; the support replacement region is located between the pre-construction region and the post-construction region; each support in the foundation pit comprises a horizontal support that penetrates the pre-construction region, the support replacement region and the post-construction region, and a longitudinal support intersecting with the horizontal support; a support replacement structure for supporting the support replacement region is provided, so that a support of a corresponding layer of the pre-construction region may first be removed, and an underground structure of the corresponding layer of the pre-construction region may then be constructed, and thereby the priority construction of the partial region of the foundation pit may be implemented without needing the overall construction of the foundation pit to be complete, which thus meets the requirements for special construction periods.

Description

开放式基坑分块施工系统及方法Open foundation pit block construction system and method 技术领域Technical field
本发明涉及基坑工程技术领域,特别涉及一种开放式基坑分块施工系统及方法。The invention relates to the technical field of foundation pit engineering, in particular to an open foundation pit block construction system and method.
背景技术Background technique
随着经济的发展与人们居住环境要求的提高,近年来我国建筑、市政等工程得到飞速的发展。在都市中土地稀缺,寸土寸金,因而在建筑向高空发展的同时,地下空间的利用也成为了一个重要的方向。高层及多层建筑的地下室、地下商场、地下车库等工程施工,都会面临地基基础工程和深基坑工程。With the development of economy and the improvement of people's living environment requirements, my country's construction and municipal projects have developed rapidly in recent years. In cities, land is scarce, and every inch of land is expensive, so while buildings are developing to the sky, the use of underground space has also become an important direction. The construction of basements, underground shopping malls, and underground garages in high-rise and multi-story buildings will all face foundation engineering and deep foundation pit engineering.
基坑设计以“安全、合理、经济、便于施工”为原则,随着基坑深度越深,支护体系复杂程度和支撑数量随之增加,施工工期和施工难度也随之而来。The foundation pit design is based on the principle of "safety, reasonableness, economy, and ease of construction". As the depth of the foundation pit becomes deeper, the complexity of the supporting system and the number of supports increase, and the construction period and construction difficulty also follow.
深基坑采用顺作法施工,按常规施工来说,在其结构阶段施工工艺一般为底板施工形成并养护,其混凝土强度达到设计要求的80%后,才能拆除上一道支撑,拆除支撑后施工上一层楼板结构,按此施工原则施工直至地下室顶板完毕。其核心思路为地下室深基坑必须整体施工。The deep foundation pit is constructed by the normal construction method. According to the conventional construction, the construction process at the structural stage is generally formed and maintained by the bottom plate construction. After the concrete strength reaches 80% of the design requirement, the previous support can be removed. The first floor structure shall be constructed according to this construction principle until the basement roof is completed. The core idea is that the basement deep foundation pit must be constructed as a whole.
若在深基坑需进行分块施工,必须在开挖前完成分块围护分隔体系(如围护桩、地下连续墙进行分隔),随后进行分坑施工,其原则其中一坑地下室结构完成后开挖相邻基坑。If the deep foundation pit needs to be constructed in blocks, the block enclosure and separation system (such as retaining piles and underground continuous walls for separation) must be completed before excavation, and then the construction of the pit shall be carried out. The principle is that the basement structure of one pit is completed Then excavate adjacent foundation pits.
当基坑已经完成开挖,且没有提前设置分隔围护体系的情况下,基坑必须整体同步施工,无法部分区域先行施工。When the excavation of the foundation pit has been completed and the separation enclosure system has not been set up in advance, the foundation pit must be constructed simultaneously as a whole, and some areas cannot be constructed first.
发明内容Summary of the invention
本发明的目的在于提供一种开放式基坑分块施工系统及方法,安全、可靠, 对于已经开挖施工且未施工分隔围护体系的基坑可以实现基坑部分区域先行施工的目的,解决基坑开挖后且未施工分隔围护体系时,基坑局部无法现行施工的问题。The purpose of the present invention is to provide an open foundation pit block construction system and method, which are safe and reliable. For foundation pits that have been excavated and constructed without a partitioned enclosure system, they can achieve the purpose of pre-construction in some areas of the foundation pit. After the excavation of the foundation pit and the separation enclosure system is not constructed, the existing construction of the part of the foundation pit cannot be performed.
为解决上述技术问题,本发明提供如下技术方案:In order to solve the above technical problems, the present invention provides the following technical solutions:
一种开放式基坑分块施工系统,用于已开挖基坑,所述基坑至少分成先施工区域、换撑区域以及后施工区域,所述基坑内由下至上设有若干层支撑,每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑以及与横向支撑相交的纵向支撑,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内设置有用于支撑位于换撑区域的所述支撑的换撑结构。An open block construction system for foundation pits is used for excavated foundation pits. The foundation pit is at least divided into a first construction area, a support replacement area and a post construction area. The foundation pit is provided with several layers of supports from bottom to top, Each support includes a horizontal support that penetrates the first construction area, the support change area, and the later construction area, and a longitudinal support that intersects the transverse support. The support change area is located between the first construction area and the later construction area. A support change structure for supporting the support located in the support change area is provided in the foundation pit.
优选的,在上述的开放式基坑分块施工系统中,所述换撑结构包括第一临时换撑柱、换撑板墙、换撑杆件及第二临时换撑柱,所述换撑板墙设置于所述横向支撑的两侧,所述换撑板墙的一端靠近先施工区域,另一端靠近后施工区域,所述第一临时换撑柱设置于所述换撑板墙的两端,夹设于所述换撑板墙之间的横向支撑的上、下侧分别设置上封边梁与下封边梁,所述上封边梁与下封边梁的两端分别与对应的换撑板墙固定连接,所述第二临时换撑柱设置于所述先施工区域的底板上,所述第二临时换撑柱与对应的第一临时换撑柱之间设置换撑杆件。Preferably, in the above-mentioned open foundation pit block construction system, the support replacement structure includes a first temporary support replacement column, a support replacement board wall, a replacement support rod member, and a second temporary replacement support column. The slab wall is arranged on both sides of the lateral support, one end of the re-supporting slab wall is close to the first construction area, and the other end is close to the post-construction area. The first temporary re-supporting columns are arranged on both sides of the re-supporting slab wall. The upper and lower sides of the transverse support sandwiched between the supporting board walls are respectively provided with an upper edge banding beam and a lower edge banding beam. The two ends of the upper edge banding beam and the lower edge banding beam correspond to The supporting board wall is fixedly connected, the second temporary supporting column is arranged on the bottom plate of the first construction area, and the supporting bar is arranged between the second temporary supporting column and the corresponding first temporary supporting column Pieces.
优选的,在上述的开放式基坑分块施工系统中,所述换撑结构还包括用于支撑所述第二临时换撑柱的第三临时换撑柱,所述第三临时换撑柱与对应的第二临时换撑柱之间设置换撑杆件。Preferably, in the above-mentioned open foundation pit block construction system, the bracing structure further includes a third temporary bracing column for supporting the second temporary bracing column, and the third temporary bracing column A strut changing member is arranged between the corresponding second temporary strut changing column.
优选的,在上述的开放式基坑分块施工系统中,所述第二临时换撑柱上每次加高的部分设置两根换撑杆件,位于上方的换撑杆件连接第一临时换撑柱上同次加高的部分,位于下方的换撑杆件连接第一临时换撑柱上上次施工的部分,两根换撑杆件与第二临时换撑柱的连接处高于换撑板墙加高前的标高且小于换撑板墙加高后的标高。Preferably, in the above-mentioned open-type foundation pit block construction system, the second temporary bracing column is provided with two bracing rod members for each heightening part, and the bracing rod member located above is connected to the first temporary brace rod member. The same heightening part on the changing support column, the lower changing support rod piece is connected to the last construction part on the first temporary changing support column, and the connection point between the two changing support rod parts and the second temporary changing support column is higher than The elevation before the heightening of the supporting board wall is smaller than that after the heightening of the supporting board wall.
优选的,在上述的开放式基坑分块施工系统中,所述第一临时换撑柱与相邻的纵向支撑固定连接。Preferably, in the above-mentioned open foundation pit block construction system, the first temporary support column is fixedly connected with the adjacent longitudinal support.
本发明还公开了一种如上所述的开放式基坑分块施工系统的施工方法,包括如下步骤:The invention also discloses a construction method of the open foundation pit block construction system as described above, which includes the following steps:
步骤一,将已经开挖的基坑划分为先施工区域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内由下至上设有若干层支撑,每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑以及与横向支撑相交的纵向支撑;Step 1: Divide the excavated foundation pit into a first construction area, a support replacement area, and a later construction area. The support replacement area is located between the first construction area and the later construction area. There are several layers of support at the top, and each support includes the horizontal support that penetrates the first construction area, the support replacement area and the later construction area, and the longitudinal support that intersects the horizontal support;
步骤二,施工换撑区域的底板及先施工区域的底板,待所述底板的混凝土强度达到设计要求后,施工用于支撑换撑区域最下方支撑的换撑结构,所述换撑结构包括位于换撑板墙、第一临时换撑柱、上封边梁、下封边梁、位带有牛腿的第二临时换撑柱以及设置于相应第一临时换撑柱以及第二临时换撑柱之间的换撑杆件,所述换撑板墙、第一临时换撑柱、上封边梁、下封边梁位于换撑区域,所述换撑板墙设置于所述最下方支撑的横向支撑的两侧,所述换撑板墙的一端靠近先施工区域,另一端靠近后施工区域,所述第一临时换撑柱设置于所述换撑板墙的两端,夹设于所述换撑板墙之间的横向支撑的上、下侧分别设置所述上封边梁与下封边梁,所述上封边梁与下封边梁的两端分别与对应的换撑板墙固定连接;Step two, construct the bottom plate of the support change area and the bottom plate of the first construction area. After the concrete strength of the bottom plate meets the design requirements, construct the support change structure used to support the bottom support of the support change area. The support change structure includes Replacing the slab wall, the first temporary replacing pillar, the upper edge banding beam, the lower edge banding beam, the second temporary replacing pillar with corbels, and the corresponding first and second temporary replacing pillars The bracing rod member between the columns, the bracing wall, the first temporary bracing column, the upper edge banding beam, and the lower edge banding beam are located in the bracing region, and the bracing wall is set on the bottom support On both sides of the lateral support, one end of the support wall is close to the first construction area, and the other end is close to the post-construction area. The first temporary support column is set at both ends of the support wall, and is sandwiched between The upper and lower sides of the transverse support between the support board walls are respectively provided with the upper edge banding beam and the lower edge banding beam, and the two ends of the upper edge banding beam and the lower edge banding beam are respectively corresponding to the support Fixed connection of board and wall;
步骤三,待用于支撑换撑区域最下方支撑的换撑结构的混凝土强度达到设计强度时,拆除先施工区域的最下方的支撑;Step 3: When the concrete strength of the support replacement structure to be used to support the bottom support of the support replacement area reaches the design strength, remove the lowest support of the first construction area;
步骤四,换撑区域中换撑板墙及两端的第一临时换撑柱加高至上一道支撑标高处,施工用于支撑换撑区域上方一道支撑的换撑结构以及先施工区域的最下方的楼板,所述用于支撑换撑区域上方一道支撑的换撑结构包括在第二临时换撑柱上加高的部分,设置于第二临时换撑柱的加高部分以及对应的第一临时换撑柱之间的换撑杆件;Step 4: The wall of the support replacement area and the first temporary replacement support columns at both ends are raised to the upper support elevation. The construction is used to support the support replacement structure above the support replacement area and the bottom of the first construction area The floor slab, the support change structure used to support a support above the support change area includes a heightened part on the second temporary support column, the heightened part provided on the second temporary support column and the corresponding first temporary support Change the support rod between the support pillars;
步骤五,待用于支撑换撑区域上方一道支撑的换撑结构以及先施工区域的最下方的楼板的混凝土达到设计强度,拆除先施工区域的再上一层支撑; Step 5. The concrete to be used to support the support replacement structure above the support replacement area and the lowermost floor of the first construction area reaches the design strength, and the first construction area is removed and then the upper layer of support is removed;
步骤六,重复步骤四和步骤五,直至拆除先施工区域的最上方支撑,并完成先施工区域的顶板结构; Step 6, repeat steps 4 and 5 until the uppermost support of the first construction area is removed, and the roof structure of the first construction area is completed;
步骤七,顺做完成后施工区域的结构;Step seven, follow the structure of the construction area after completion;
步骤八,从上至下拆除换撑结构; Step 8. Remove the support structure from top to bottom;
步骤九,顺做完成换撑区域结构。Step Nine, complete the structure of the support replacement area.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述第二临时换撑柱上设有用于安置对应的换撑杆件的牛腿。Preferably, in the above-mentioned construction method of the open foundation pit block construction system, the second temporary support column is provided with a corbel for arranging the corresponding support rod member.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述换撑结构还包括用于支撑所述第二临时换撑柱的第三临时换撑柱,所述第三临时换撑柱与对应的第二临时换撑柱之间设置换撑杆件。Preferably, in the construction method of the open foundation pit block construction system, the support replacement structure further includes a third temporary support post for supporting the second temporary support post, and the third temporary support post A strut changing member is arranged between the supporting column and the corresponding second temporary supporting column.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述第三临时换撑柱上设有用于安置对应的换撑杆件的牛腿。Preferably, in the above-mentioned construction method of the open foundation pit block construction system, the third temporary support column is provided with a corbel for arranging the corresponding support member.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述第二临时换撑柱上每次加高的部分设置两根换撑杆件,位于上方的换撑杆件连接第一临时换撑柱上同次加高的部分,位于下方的换撑杆件连接第一临时换撑柱上上次施工的部分,两根换撑杆件与第二临时换撑柱的连接处高于换撑板墙加高前的标高且小于换撑板墙加高后的标高。Preferably, in the construction method of the open-type foundation pit block construction system described above, the second temporary support column is provided with two support change rods at each heightened part, and the upper support change rod is connected The same heightened part of the first temporary support column, the lower part of the support replacement rod is connected to the last construction part of the first temporary support column, and the connection of the two support rod parts to the second temporary support column The location is higher than the elevation before the heightening of the supporting board wall and smaller than the elevation after the heightening of the supporting board wall.
由以上公开的技术方案可知,与现有技术相比,本发明的有益效果如下:From the technical solutions disclosed above, compared with the prior art, the beneficial effects of the present invention are as follows:
本发明提供的开放式基坑分块施工系统,对于已经开挖好而无法通过施工分割围护体系来实现基坑的局部优先施工的基坑,通过将基坑划分为先施工区域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内的每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑以及与横向支撑相交的纵向支撑,通过设置用于支撑换撑区域的支撑的换撑结构,可以先行拆除先施工区域的对应层的支撑,然后进行先施工区域的对应层的地下结构施工,从而不用基坑整体施工完毕,就可以实现基坑局部区域的优先施工,满足特殊工期要求。The open-type foundation pit block construction system provided by the present invention, for the foundation pits that have been excavated but cannot be divided into the enclosure system through construction to achieve partial priority construction of the foundation pit, by dividing the foundation pit into the first construction area and replacing the support Area and post-construction area, the support replacement area is located between the first construction area and the post-construction area, and each support in the foundation pit includes lateral supports that penetrate the first construction area, the support replacement area and the post-construction area And the longitudinal support that intersects with the horizontal support, by setting up the support change structure for supporting the support change area, the support of the corresponding layer in the first construction area can be removed first, and then the underground structure construction of the corresponding layer in the first construction area can be carried out. Without having to complete the overall construction of the foundation pit, the priority construction of the partial area of the foundation pit can be realized to meet the requirements of special construction period.
本发明提供的开放式基坑分块施工系统的施工方法,通过将已经开挖的基坑划分为先施工区域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,通过由下至上依次设置用于支撑换撑区域的支 撑的换撑结构,可以先行拆除先施工区域的对应层的支撑,然后进行先施工区域的对应层的地下结构施工,从而不用基坑整体施工完毕,就可以实现基坑局部区域的优先施工,满足特殊工期要求。The construction method of the open foundation pit block construction system provided by the present invention divides the excavated foundation pit into a first construction area, a support replacement area and a later construction area, and the support replacement area is located between the first construction area and Between the post-construction areas, by sequentially setting up the support replacement structure for supporting the support replacement area, the support of the corresponding layer of the first construction area can be removed first, and then the underground structure of the corresponding layer of the first construction area can be carried out Therefore, it is possible to achieve priority construction in partial areas of the foundation pit without completing the overall construction of the foundation pit to meet the requirements of the special construction period.
附图说明Description of the drawings
图1至图25为本发明实施例的开放式基坑分块施工系统的施工方法的施工流程示意图(同时也是开放式基坑分块施工系统在各步骤时的结构示意图)。1 to 25 are schematic diagrams of the construction process of the construction method of the open foundation pit block construction system according to the embodiment of the present invention (also are the structural schematic diagrams of the open foundation pit block construction system at each step).
图2为图1的1-1剖面图。Fig. 2 is a cross-sectional view of 1-1 in Fig. 1.
图5为图4的2-2剖面图。Fig. 5 is a cross-sectional view of 2-2 of Fig. 4.
图8为图7的3-3剖面图。Fig. 8 is a 3-3 sectional view of Fig. 7.
图中:1-底板、2-横向支撑、3-纵向支撑、4-第一临时换撑柱、5-换撑板墙、6-换撑杆件、7-第二临时换撑柱、8-上封边梁、9-下封边梁、10-第三临时换撑柱、11-主体结构柱、12-楼面。In the picture: 1-bottom plate, 2-transverse support, 3-longitudinal support, 4-first temporary replacement support column, 5-replacement board wall, 6-replacement support member, 7-second temporary replacement support, 8 -Upper edge banding beam, 9-bottom edge banding beam, 10-third temporary replacement support column, 11-main structural column, 12-floor.
具体实施方式detailed description
以下结合附图和具体实施例对本发明作进一步详细说明。以下将由所列举之实施例结合附图,详细说明本发明的技术内容及特征。需另外说明的是,附图均采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本发明实施例的目的。为叙述方便,下文中所述的“上”、“下”与附图的上、下的方向一致,但这不能成为本发明技术方案的限制。The present invention will be further described in detail below in conjunction with the drawings and specific embodiments. Hereinafter, the technical content and features of the present invention will be described in detail by the listed embodiments in combination with the accompanying drawings. It should be additionally noted that the drawings are in a very simplified form and all use imprecise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. For the convenience of description, the "up" and "down" described below are consistent with the directions of the upper and lower directions of the drawings, but this cannot be a limitation of the technical solution of the present invention.
请参阅图1,并结合参阅图2至图25,本实施例公开了一种开放式基坑分块施工系统,用于已开挖基坑,所述基坑至少分成先施工区域、换撑区域以及后施工区域,所述基坑内由下至上设有若干层支撑,每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑2以及与横向支撑2相交的纵向支撑3,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内设置有用于支撑位于换撑区域的所述支撑的换撑结构。Please refer to Figure 1 in conjunction with Figures 2 to 25. This embodiment discloses an open foundation pit block construction system for an already excavated foundation pit. The foundation pit is at least divided into a first construction area and a replacement support There are several layers of supports in the foundation pit from bottom to top. Each support includes a horizontal support 2 that penetrates the first construction area, a support replacement area, and a post construction area, and a longitudinal support 3 that intersects the horizontal support 2. The support change area is located between the first construction area and the post construction area, and a support change structure for supporting the support located in the support change area is provided in the foundation pit.
本发明提供的开放式基坑分块施工系统,对于已经开挖好而无法通过施工分割围护体系来实现基坑的局部优先施工的基坑,通过将基坑划分为先施工区 域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内的每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑2以及与横向支撑2相交的纵向支撑3,通过设置用于支撑换撑区域的支撑的换撑结构,可以先行拆除先施工区域的对应层的支撑,然后进行先施工区域的对应层的地下结构施工,从而不用基坑整体施工完毕,就可以实现基坑局部区域的优先施工,满足特殊工期要求。The open-type foundation pit block construction system provided by the present invention, for the foundation pits that have been excavated but cannot be divided into the enclosure system through construction to achieve partial priority construction of the foundation pit, by dividing the foundation pit into the first construction area and replacing the support Area and post-construction area, the support replacement area is located between the first construction area and the post-construction area, and each support in the foundation pit includes lateral supports that penetrate the first construction area, the support replacement area and the post-construction area 2 and the longitudinal support 3 that intersects with the lateral support 2. By setting the support replacement structure for supporting the support replacement area, the support of the corresponding layer in the first construction area can be removed first, and then the underground structure of the corresponding layer in the first construction area can be removed Therefore, it is possible to achieve priority construction in partial areas of the foundation pit without completing the overall construction of the foundation pit to meet the requirements of the special construction period.
优选的,在上述的开放式基坑分块施工系统中,所述换撑结构包括第一临时换撑柱4、换撑板墙5、换撑杆件6及第二临时换撑柱7,所述换撑板墙5设置于所述横向支撑2的两侧,所述换撑板墙5的一端靠近先施工区域,另一端靠近后施工区域,所述第一临时换撑柱4设置于所述换撑板墙5的两端,夹设于所述换撑板墙5之间的横向支撑2的上、下侧分别设置上封边梁8与下封边梁9,所述上封边梁8与下封边梁9的两端分别与对应的换撑板墙5固定连接,所述第二临时换撑柱7设置于所述先施工区域的底板1上,所述第二临时换撑柱7与对应的第一临时换撑柱4之间设置换撑杆件6。通过在横向支撑2的两侧设置换撑板墙5,夹设于所述换撑板墙5之间的横向支撑2的上、下侧分别设置上封边梁8与下封边梁9,所述上封边梁8与下封边梁9的两端分别与对应的换撑板墙5固定连接,可以实现对横向支撑2的支撑,通过在所述换撑板墙5的两端分别设置所述第一临时换撑柱4,可以加强换撑板墙5的强度;通过在所述先施工区域的底板1上设置第二临时换撑柱7,所述第二临时换撑柱7与对应的第一临时换撑柱4之间设置换撑杆件6,可以进一步提高换撑板墙5对横向支撑2的支撑作用,实现基坑的安全、可靠施工。Preferably, in the above-mentioned open foundation pit block construction system, the support replacement structure includes a first temporary support replacement column 4, a support replacement board wall 5, a support replacement member 6 and a second temporary replacement support column 7. The supporting board wall 5 is arranged on both sides of the lateral support 2, one end of the supporting board wall 5 is close to the first construction area, the other end is close to the post construction area, and the first temporary supporting column 4 is arranged at At both ends of the supporting board wall 5, the upper and lower sides of the lateral support 2 sandwiched between the supporting board wall 5 are respectively provided with an upper edge banding beam 8 and a lower edge banding beam 9, the upper sealing The two ends of the edge beam 8 and the lower edge banding beam 9 are respectively fixedly connected to the corresponding support plate wall 5, the second temporary support column 7 is arranged on the bottom plate 1 of the first construction area, and the second temporary A strut changing member 6 is provided between the supporting pole 7 and the corresponding first temporary supporting pole 4. By arranging the support wall 5 on both sides of the lateral support 2, the upper and lower sides of the lateral support 2 sandwiched between the support wall 5 are provided with an upper edge banding beam 8 and a lower edge banding beam 9, respectively, The two ends of the upper edge banding beam 8 and the lower edge banding beam 9 are respectively fixedly connected to the corresponding support plate wall 5, which can realize the support of the lateral support 2. The provision of the first temporary support column 4 can strengthen the strength of the support plate wall 5; by arranging a second temporary support column 7 on the bottom plate 1 of the first construction area, the second temporary support column 7 The bracing rod member 6 is arranged between the corresponding first temporary bracing column 4, which can further improve the supporting effect of the bracing plate wall 5 on the lateral support 2 and realize the safe and reliable construction of the foundation pit.
优选的,在上述的开放式基坑分块施工系统中,所述换撑结构还包括用于支撑所述第二临时换撑柱7的第三临时换撑柱10,所述第三临时换撑柱10与对应的第二临时换撑柱7之间设置换撑杆件6。当第二临时换撑柱7加高后,稳定性变弱的时候,可以通过增设第三临时换撑柱10,并在所述第三临时换撑柱10与对应的第二临时换撑柱7之间设置换撑杆件6,来提高第二临时换撑柱7的稳定性,从而保证换撑结构的稳定性,确保施工安全性。Preferably, in the above-mentioned open foundation pit block construction system, the support replacement structure further includes a third temporary support post 10 for supporting the second temporary support post 7, and the third temporary support post A strut changing member 6 is arranged between the strut 10 and the corresponding second temporary strut changing 7. When the second temporary support post 7 is increased and the stability becomes weaker, a third temporary support post 10 can be added, and the third temporary support post 10 and the corresponding second temporary support post 10 can be added. The supporting rod member 6 is arranged between 7 to improve the stability of the second temporary supporting column 7, thereby ensuring the stability of the supporting structure and ensuring construction safety.
优选的,在上述的开放式基坑分块施工系统中,所述第二临时换撑柱7上每次加高的部分设置两根换撑杆件6,位于上方的换撑杆件6连接第一临时换撑柱4上同次加高的部分,位于下方的换撑杆件6连接第一临时换撑柱4上上次施工的部分,两根换撑杆件6与第二临时换撑柱7的连接处高于换撑板墙5加高前的标高且小于换撑板墙5加高后的标高,从而在第一临时换撑柱4与第二临时换撑柱7之间形成折线型的支撑结构,从而对第一临时换撑柱4提供有力支撑,进而对位于换撑区域的支撑实现稳固支撑。Preferably, in the above-mentioned open-type foundation pit block construction system, the second temporary bracing column 7 is provided with two bracing rod members 6 each time the height is increased, and the bracing rod member 6 located above is connected The same heightened part on the first temporary support column 4, the lower support rod member 6 is connected to the last construction part of the first temporary support column 4, and the two support rod members 6 are connected to the second temporary The joint of the brace 7 is higher than the elevation of the support wall 5 before heightening and less than the elevation of the brace wall 5 after heightening, so that it is between the first temporary replacement support column 4 and the second temporary replacement support column 7 A broken-line support structure is formed to provide strong support to the first temporary support column 4, and further to achieve stable support for the support located in the support change area.
优选的,在上述的开放式基坑分块施工系统中,所述第三临时换撑柱10上设有用于安置对应的换撑杆件6的牛腿(未标示)。通过设置牛腿,可以不但便于设置换撑杆件6,而且可以提高换撑杆件6的稳定性。Preferably, in the above-mentioned open foundation pit block construction system, the third temporary bracing column 10 is provided with a corbel (not shown) for arranging the corresponding bracing rod member 6. By arranging the corbel, it is not only convenient to install the strut changing member 6, but also the stability of the strut changing member 6 can be improved.
优选的,在上述的开放式基坑分块施工系统中,所述第一临时换撑柱4与相邻的纵向支撑3固定连接,如此可以利用基坑的纵向支撑3对第一临时换撑柱4的支撑作用,提高所述第一临时换撑柱4的稳定性,从而进一步提高换撑结构的稳定性。Preferably, in the above-mentioned open foundation pit block construction system, the first temporary support column 4 is fixedly connected to the adjacent longitudinal support 3, so that the longitudinal support 3 of the foundation pit can be used for the first temporary support The supporting function of the column 4 improves the stability of the first temporary support replacement column 4, thereby further improving the stability of the support replacement structure.
请继续参阅图1至图25,本发明还公开了一种如上所述的开放式基坑分块施工系统的施工方法,包括如下步骤:Please continue to refer to FIGS. 1-25. The present invention also discloses a construction method of the open foundation pit block construction system as described above, which includes the following steps:
步骤一,将已经开挖的基坑划分为先施工区域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内由下至上设有若干层支撑,每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑2以及与横向支撑2相交的纵向支撑3;Step 1: Divide the excavated foundation pit into a first construction area, a support replacement area, and a later construction area. The support replacement area is located between the first construction area and the later construction area. There are several layers of supports at the top, and each support includes a horizontal support 2 that penetrates the first construction area, a support replacement area, and a later construction area, and a longitudinal support 3 that intersects the horizontal support 2;
步骤二,请参阅图1至图2,施工换撑区域的底板1及先施工区域的底板1,待所述底板1的混凝土强度达到设计要求后,施工用于支撑换撑区域最下方支撑的换撑结构,所述换撑结构包括位于换撑板墙5、第一临时换撑柱4、上封边梁8、下封边梁9、位带有牛腿的第二临时换撑柱7以及设置于相应第一临时换撑柱4以及第二临时换撑柱7之间的换撑杆件6,所述换撑板墙5、第一临时换撑柱4、上封边梁8、下封边梁9位于换撑区域,所述换撑板墙5设置于所述最下方支撑的横向支撑2的两侧,所述换撑板墙5的一端靠近先施 工区域,另一端靠近后施工区域,所述第一临时换撑柱4设置于所述换撑板墙5的两端,夹设于所述换撑板墙5之间的横向支撑2的上、下侧分别设置所述上封边梁8与下封边梁9,所述上封边梁8与下封边梁9的两端分别与对应的换撑板墙5固定连接;Step two, please refer to Figure 1 to Figure 2. Construction of the bottom plate 1 of the support replacement area and the bottom plate 1 of the first construction area. After the concrete strength of the bottom plate 1 reaches the design requirements, construct the bottom support for the support replacement area Support replacement structure, the support replacement structure includes the support replacement wall 5, the first temporary replacement support column 4, the upper edge sealing beam 8, the lower edge sealing beam 9, and the second temporary replacement support column 7 with a corbel And the supporting rod member 6 arranged between the corresponding first temporary supporting column 4 and the second temporary supporting column 7, the supporting plate wall 5, the first temporary supporting column 4, the upper edge banding beam 8, The lower edge banding beam 9 is located in the support replacement area, the support replacement wall 5 is arranged on both sides of the lowermost supported transverse support 2, one end of the support replacement wall 5 is close to the first construction area, and the other end is close to the rear In the construction area, the first temporary bracing column 4 is arranged at both ends of the bracing wall 5, and the upper and lower sides of the lateral support 2 sandwiched between the bracing wall 5 are respectively provided Upper edge banding beam 8 and lower edge banding beam 9, both ends of said upper edge banding beam 8 and lower edge banding beam 9 are respectively fixedly connected to the corresponding supporting board wall 5;
步骤三,请参阅图3,待用于支撑换撑区域最下方支撑的换撑结构的混凝土强度达到设计强度时,拆除先施工区域的最下方的支撑; Step 3. Refer to Figure 3. When the concrete strength of the support replacement structure to be used to support the bottom support of the support replacement area reaches the design strength, remove the lowest support of the first construction area;
步骤四,请参阅图4至图5,换撑区域中换撑板墙5及两端的第一临时换撑柱4加高至上一道支撑标高处,施工用于支撑换撑区域上方一道支撑的换撑结构以及先施工区域的最下方的楼板12,所述用于支撑换撑区域上方一道支撑的换撑结构包括在第二临时换撑柱7上加高的部分,设置于第二临时换撑柱7的加高部分以及对应的第一临时换撑柱4之间的换撑杆件6; Step 4, please refer to Figure 4 to Figure 5. The support wall 5 and the first temporary support column 4 at both ends in the support change area are raised to the upper support elevation, and the construction is used to support the change of a support above the support change area. The support structure and the lowermost floor 12 of the first construction area, the support replacement structure used to support a support above the support replacement area includes a heightened part on the second temporary support replacement column 7, which is arranged in the second temporary support replacement The heightened part of the column 7 and the corresponding first temporary change support rod member 6 between the support column 4;
步骤五,请参阅图6,待用于支撑换撑区域上方一道支撑的换撑结构以及先施工区域的最下方的楼板12的混凝土达到设计强度,拆除先施工区域的再上一层支撑; Step 5, please refer to Figure 6. The concrete to be used to support the support replacement structure above the support replacement area and the lowermost floor 12 of the first construction area reaches the design strength, and the first construction area is removed and then the upper layer of support is removed;
步骤六,请参阅图7至图10,重复步骤四和步骤五,直至拆除先施工区域的最上方支撑,并完成先施工区域的顶板结构; Step 6, refer to Figure 7 to Figure 10, repeat steps 4 and 5 until the top support of the first construction area is removed, and the roof structure of the first construction area is completed;
步骤七,请参阅图11至图16,顺做完成后施工区域的结构; Step 7, refer to Figure 11 to Figure 16, and follow the structure of the construction area after completion;
步骤八,请参阅图17至图19,从上至下拆除换撑结构; Step 8. Please refer to Figure 17 to Figure 19 to remove the support structure from top to bottom;
步骤九,请参阅图20至图25,顺做完成换撑区域结构。Step 9: Please refer to Figure 20 to Figure 25 to complete the structure of the support replacement area.
本发明提供的开放式基坑分块施工系统的施工方法,通过将已经开挖的基坑划分为先施工区域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,通过由下至上依次设置用于支撑换撑区域的支撑的换撑结构,可以先行拆除先施工区域的对应层的支撑,然后进行先施工区域的对应层的地下结构施工,从而不用基坑整体施工完毕,就可以实现基坑局部区域的优先施工,满足特殊工期要求。The construction method of the open foundation pit block construction system provided by the present invention divides the excavated foundation pit into a first construction area, a support replacement area and a later construction area, and the support replacement area is located between the first construction area and Between the post-construction areas, by sequentially setting up the support replacement structure for supporting the support replacement area, the support of the corresponding layer of the first construction area can be removed first, and then the underground structure of the corresponding layer of the first construction area can be carried out Therefore, it is possible to achieve priority construction in partial areas of the foundation pit without completing the overall construction of the foundation pit to meet the requirements of the special construction period.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述换撑结构还包括用于支撑所述第二临时换撑柱7的第三临时换撑柱10,所述第三临时 换撑柱10与对应的第二临时换撑柱7之间设置换撑杆件6。当第二临时换撑柱7加高后,稳定性变弱的时候,可以通过增设第三临时换撑柱10,并在所述第三临时换撑柱10与对应的第二临时换撑柱7之间设置换撑杆件6,来提高第二临时换撑柱7的稳定性,从而保证换撑结构的稳定性,确保施工安全性。Preferably, in the construction method of the open foundation pit block construction system described above, the support replacement structure further includes a third temporary support post 10 for supporting the second temporary support post 7, and the second temporary support post 7 The third temporary support change post 10 and the corresponding second temporary support change post 7 are provided with a support change member 6. When the second temporary support post 7 is increased and the stability becomes weaker, a third temporary support post 10 can be added, and the third temporary support post 10 and the corresponding second temporary support post 10 can be added. The supporting rod member 6 is arranged between 7 to improve the stability of the second temporary supporting column 7, thereby ensuring the stability of the supporting structure and ensuring construction safety.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述第三临时换撑柱10上设有用于安置对应的换撑杆件6的牛腿。所述第二临时换撑柱7上设有用于安置对应的换撑杆件6的牛腿。通过设置牛腿,可以不但便于设置换撑杆件6,而且可以提高换撑杆件6的稳定性。Preferably, in the construction method of the open foundation pit block-by-block construction system, the third temporary support column 10 is provided with a corbel for arranging the corresponding support rod member 6. The second temporary support pole 7 is provided with a corbel for arranging the corresponding support pole member 6. By arranging the corbel, it is not only convenient to install the strut changing member 6, but also the stability of the strut changing member 6 can be improved.
优选的,在上述的开放式基坑分块施工系统的施工方法中,所述第二临时换撑柱7上每次加高的部分设置两根换撑杆件6,位于上方的换撑杆件6连接第一临时换撑柱4上同次加高的部分,位于下方的换撑杆件6连接第一临时换撑柱4上上次施工的部分,两根换撑杆件6与第二临时换撑柱7的连接处高于换撑板墙5加高前的标高且小于换撑板墙5加高后的标高,从而在第一临时换撑柱4与第二临时换撑柱7之间形成折线型的支撑结构,从而对第一临时换撑柱4提供有力支撑,进而对位于换撑区域的支撑实现稳固支撑。Preferably, in the construction method of the open foundation pit block construction system described above, the second temporary support column 7 is provided with two support rod members 6 each time the height is increased, and the upper support rod Piece 6 is connected to the same heightened part of the first temporary support column 4, and the lower part of the support replacement member 6 is connected to the last construction part of the first temporary change of support column 4. The two replacement support members 6 and the second 2. The junction of the temporary support column 7 is higher than the elevation of the support replacement wall 5 before heightening and less than the elevation of the support replacement wall 5 after the heightening, so that the first temporary support column 4 is replaced with the second temporary support column A broken-line support structure is formed between 7 to provide strong support for the first temporary support column 4, and further to achieve stable support for the support located in the support change area.
上述描述仅是对本发明较佳实施例的描述,并非对本发明范围的任何限定,本发明领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求书的保护范围。The foregoing description is only a description of the preferred embodiments of the present invention and does not limit the scope of the present invention in any way. Any changes or modifications made by persons of ordinary skill in the field of the present invention based on the foregoing disclosure shall fall within the protection scope of the claims.

Claims (10)

  1. 一种开放式基坑分块施工系统,其特征在于,用于已开挖基坑,所述基坑至少分成先施工区域、换撑区域以及后施工区域,所述基坑内由下至上设有若干层支撑,每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑以及与横向支撑相交的纵向支撑,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内设置有用于支撑位于换撑区域的所述支撑的换撑结构。An open foundation pit block construction system, characterized in that it is used for an excavated foundation pit. The foundation pit is at least divided into a first construction area, a support replacement area and a post-construction area. The foundation pit is provided with Several layers of support, each support includes a horizontal support that penetrates the first construction area, the support change area, and the post construction area, and a longitudinal support that intersects the transverse support, the support change area is located between the first construction area and the post construction area In between, the foundation pit is provided with a support changing structure for supporting the support located in the support changing area.
  2. 如权利要求1所述的开放式基坑分块施工系统,其特征在于,所述换撑结构包括第一临时换撑柱、换撑板墙、换撑杆件及第二临时换撑柱,所述换撑板墙设置于所述横向支撑的两侧,所述换撑板墙的一端靠近先施工区域,另一端靠近后施工区域,所述第一临时换撑柱设置于所述换撑板墙的两端,夹设于所述换撑板墙之间的横向支撑的上、下侧分别设置上封边梁与下封边梁,所述上封边梁与下封边梁的两端分别与对应的换撑板墙固定连接,所述第二临时换撑柱设置于所述先施工区域的底板上,所述第二临时换撑柱与对应的第一临时换撑柱之间设置换撑杆件。The open-type foundation pit block construction system according to claim 1, wherein the support replacement structure includes a first temporary support replacement column, a support replacement board wall, a support replacement member, and a second temporary replacement support column, The supporting board wall is arranged on both sides of the lateral support, one end of the supporting board wall is close to the first construction area, and the other end is close to the post construction area, and the first temporary supporting column is arranged on the supporting wall At both ends of the slab wall, the upper and lower sides of the transverse support sandwiched between the supporting slab wall are respectively provided with an upper edge banding beam and a lower edge banding beam, two of the upper edge banding beam and the lower edge banding beam The two ends are respectively fixedly connected to the corresponding supporting wall, the second temporary supporting column is arranged on the bottom plate of the first construction area, and the second temporary supporting column is between the corresponding first temporary supporting column Set up replacement strut pieces.
  3. 如权利要求2所述的开放式基坑分块施工系统,其特征在于,所述换撑结构还包括用于支撑所述第二临时换撑柱的第三临时换撑柱,所述第三临时换撑柱与对应的第二临时换撑柱之间设置换撑杆件。The open-type foundation pit block construction system according to claim 2, wherein the supporting structure further comprises a third temporary supporting column for supporting the second temporary supporting column, and the third temporary supporting column A bracing rod member is arranged between the temporary bracing column and the corresponding second temporary bracing column.
  4. 如权利要求3所述的开放式基坑分块施工系统,其特征在于,所述第二临时换撑柱上每次加高的部分设置两根换撑杆件,位于上方的换撑杆件连接第一临时换撑柱上同次加高的部分,位于下方的换撑杆件连接第一临时换撑柱上上次施工的部分,两根换撑杆件与第二临时换撑柱的连接处高于换撑板墙加高前的标高且小于换撑板墙加高后的标高。The open-type foundation pit block construction system according to claim 3, characterized in that, on the part of the second temporary support column that is increased each time, two support rod members are provided, and the upper support rod member Connect the same heightened part on the first temporary re-supporting column, the lower re-supporting rod piece connects the last construction part on the first temporary re-supporting column, the two re-supporting rod parts and the second temporary re-supporting column The joint is higher than the elevation of the wall before and less than the elevation of the wall after the wall is increased.
  5. 如权利要求2所述的开放式基坑分块施工系统,其特征在于,所述第一临时换撑柱与相邻的纵向支撑固定连接。The open-type foundation pit block construction system according to claim 2, wherein the first temporary support column is fixedly connected with the adjacent longitudinal support.
  6. 一种如权利要求1-5中任意一项所述的开放式基坑分块施工系统的施工方法,其特征在于,包括如下步骤:A construction method of an open foundation pit block construction system according to any one of claims 1-5, characterized in that it comprises the following steps:
    步骤一,将已经开挖的基坑划分为先施工区域、换撑区域以及后施工区域,所述换撑区域位于所述先施工区域与所述后施工区域之间,所述基坑内由下至 上设有若干层支撑,每道支撑包括贯通先施工区域、换撑区域以及后施工区域的横向支撑以及与横向支撑相交的纵向支撑;Step 1: Divide the excavated foundation pit into a first construction area, a support replacement area, and a later construction area. The support replacement area is located between the first construction area and the later construction area. There are several layers of support at the top, and each support includes the horizontal support that penetrates the first construction area, the support replacement area and the later construction area, and the longitudinal support that intersects the horizontal support;
    步骤二,施工换撑区域的底板及先施工区域的底板,待所述底板的混凝土强度达到设计要求后,施工用于支撑换撑区域最下方支撑的换撑结构,所述换撑结构包括位于换撑板墙、第一临时换撑柱、上封边梁、下封边梁、位带有牛腿的第二临时换撑柱以及设置于相应第一临时换撑柱以及第二临时换撑柱之间的换撑杆件,所述换撑板墙、第一临时换撑柱、上封边梁、下封边梁位于换撑区域,所述换撑板墙设置于所述最下方支撑的横向支撑的两侧,所述换撑板墙的一端靠近先施工区域,另一端靠近后施工区域,所述第一临时换撑柱设置于所述换撑板墙的两端,夹设于所述换撑板墙之间的横向支撑的上、下侧分别设置所述上封边梁与下封边梁,所述上封边梁与下封边梁的两端分别与对应的换撑板墙固定连接;Step two, construct the bottom plate of the support change area and the bottom plate of the first construction area. After the concrete strength of the bottom plate meets the design requirements, construct the support change structure used to support the bottom support of the support change area. The support change structure includes Replacing the slab wall, the first temporary replacing pillar, the upper edge banding beam, the lower edge banding beam, the second temporary replacing pillar with corbels, and the corresponding first and second temporary replacing pillars The bracing rod member between the columns, the bracing wall, the first temporary bracing column, the upper edge banding beam, and the lower edge banding beam are located in the bracing region, and the bracing wall is set on the bottom support On both sides of the lateral support, one end of the support wall is close to the first construction area, and the other end is close to the post-construction area. The first temporary support column is set at both ends of the support wall, and is sandwiched between The upper and lower sides of the transverse support between the support board walls are respectively provided with the upper edge banding beam and the lower edge banding beam, and the two ends of the upper edge banding beam and the lower edge banding beam are respectively corresponding to the support Fixed connection of board and wall;
    步骤三,待用于支撑换撑区域最下方支撑的换撑结构的混凝土强度达到设计强度时,拆除先施工区域的最下方的支撑;Step 3: When the concrete strength of the support replacement structure to be used to support the bottom support of the support replacement area reaches the design strength, remove the lowest support of the first construction area;
    步骤四,换撑区域中换撑板墙及两端的第一临时换撑柱加高至上一道支撑标高处,施工用于支撑换撑区域上方一道支撑的换撑结构以及先施工区域的最下方的楼板,所述用于支撑换撑区域上方一道支撑的换撑结构包括在第二临时换撑柱上加高的部分,设置于第二临时换撑柱的加高部分以及对应的第一临时换撑柱之间的换撑杆件;Step 4: The wall of the support replacement area and the first temporary replacement support columns at both ends are raised to the upper support elevation. The construction is used to support the support replacement structure above the support replacement area and the bottom of the first construction area The floor slab, the support change structure used to support a support above the support change area includes a heightened part on the second temporary support column, the heightened part provided on the second temporary support column and the corresponding first temporary support Change the support rod between the support pillars;
    步骤五,待用于支撑换撑区域上方一道支撑的换撑结构以及先施工区域的最下方的楼板的混凝土达到设计强度,拆除先施工区域的再上一层支撑;Step 5. The concrete to be used to support the support replacement structure above the support replacement area and the lowermost floor of the first construction area reaches the design strength, and the first construction area is removed and then the upper layer of support is removed;
    步骤六,重复步骤四和步骤五,直至拆除先施工区域的最上方支撑,并完成先施工区域的顶板结构;Step 6, repeat steps 4 and 5 until the uppermost support of the first construction area is removed, and the roof structure of the first construction area is completed;
    步骤七,顺做完成后施工区域的结构;Step seven, follow the structure of the construction area after completion;
    步骤八,从上至下拆除换撑结构;Step 8. Remove the support structure from top to bottom;
    步骤九,顺做完成换撑区域结构。Step Nine, complete the structure of the support replacement area.
  7. 如权利要求6所述的开放式基坑分块施工系统的施工方法,其特征在于,所述第二临时换撑柱上设有用于安置对应的换撑杆件的牛腿。7. The construction method of the open foundation pit block construction system according to claim 6, wherein the second temporary support column is provided with a corbel for arranging the corresponding support member.
  8. 如权利要求6所述的开放式基坑分块施工系统的施工方法,其特征在于,所述换撑结构还包括用于支撑所述第二临时换撑柱的第三临时换撑柱,所述第三临时换撑柱与对应的第二临时换撑柱之间设置换撑杆件。The construction method of the open-type foundation pit block construction system according to claim 6, wherein the supporting structure further comprises a third temporary supporting column for supporting the second temporary supporting column, so A strut changing member is arranged between the third temporary changing support column and the corresponding second temporary changing support column.
  9. 如权利要求8所述的开放式基坑分块施工系统的施工方法,其特征在于,所述第三临时换撑柱上设有用于安置对应的换撑杆件的牛腿。The construction method of the open foundation pit block construction system according to claim 8, wherein the third temporary support column is provided with a corbel for arranging the corresponding support member.
  10. 如权利要求6所述的开放式基坑分块施工系统的施工方法,其特征在于,所述第二临时换撑柱上每次加高的部分设置两根换撑杆件,位于上方的换撑杆件连接第一临时换撑柱上同次加高的部分,位于下方的换撑杆件连接第一临时换撑柱上上次施工的部分,两根换撑杆件与第二临时换撑柱的连接处高于换撑板墙加高前的标高且小于换撑板墙加高后的标高。The construction method of the open-type foundation pit block construction system according to claim 6, characterized in that, each heightening part of the second temporary support column is provided with two support rod members, and the upper replacement The struts are connected to the same heightened part on the first temporary replacing column, the lower replacing rod is connected to the last construction part of the first temporary replacing pillar, and the two replacing rods are connected to the second temporary replacing The joints of the supporting columns are higher than the elevation before the heightening of the supporting board wall and smaller than the elevation after the heightening of the supporting board wall.
PCT/CN2020/107264 2019-08-07 2020-08-06 Open foundation pit block construction system and method WO2021023246A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201910723566.X 2019-08-07
CN201910723566.XA CN110409454A (en) 2019-08-07 2019-08-07 Open foundation pit block construction system and method

Publications (1)

Publication Number Publication Date
WO2021023246A1 true WO2021023246A1 (en) 2021-02-11

Family

ID=68366227

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/107264 WO2021023246A1 (en) 2019-08-07 2020-08-06 Open foundation pit block construction system and method

Country Status (2)

Country Link
CN (1) CN110409454A (en)
WO (1) WO2021023246A1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113833018A (en) * 2021-09-09 2021-12-24 广东省重工建筑设计院有限公司 Existing line reconstruction method
CN114277844A (en) * 2022-01-24 2022-04-05 中国建筑第八工程局有限公司 Construction method of underground structure
CN114541409A (en) * 2022-01-22 2022-05-27 北京市政路桥股份有限公司 Support replacing method for integrated support structure of pipe gallery and tunnel foundation pit
CN114960680A (en) * 2022-06-27 2022-08-30 福建江夏学院 Be favorable to auxiliary supporting structure of foundation ditch of drainage
CN115030186A (en) * 2022-07-15 2022-09-09 中建桥梁有限公司 Foundation pit supporting construction method for multi-layer basement requiring dismantling of existing foundation pit diaphragm wall
CN115125960A (en) * 2022-08-05 2022-09-30 中建市政工程有限公司 Common foundation pit excavation method for adjacent foundation pits with different bottom elevations
CN115387344A (en) * 2022-08-19 2022-11-25 中建三局第三建设工程有限责任公司 Double-foundation-pit double-working-condition rapid construction method
CN116025005A (en) * 2023-01-05 2023-04-28 北京住总集团有限责任公司 Subway station main body structure construction method influenced by double rows of lattice columns
CN116815790A (en) * 2023-08-28 2023-09-29 上海建工一建集团有限公司 Foundation pit supporting servo system with two sides adjacent to protection objects and construction method thereof

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409454A (en) * 2019-08-07 2019-11-05 上海建工二建集团有限公司 Open foundation pit block construction system and method
CN113006083A (en) * 2021-03-02 2021-06-22 中建八局南方建设有限公司 Support changing construction method for foundation pit inner support
CN115404904A (en) * 2022-06-23 2022-11-29 中国建筑第八工程局有限公司 Underground diaphragm wall chamber-divided type dismantling construction method adjacent to subway foundation pit

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03267417A (en) * 1990-03-19 1991-11-28 Masatada Saito Earth retaining steel strut having square cross section
CN201526052U (en) * 2009-09-07 2010-07-14 上海市第一建筑有限公司 Temporary supporting wall for group pit construction
KR20100138455A (en) * 2009-06-25 2010-12-31 코오롱건설주식회사 Block for backfilling and method backfilling by that
CN204435388U (en) * 2014-12-24 2015-07-01 重庆建工住宅建设有限公司 Deep foundation ditch stage construction support changing structure for use
CN110055975A (en) * 2019-04-25 2019-07-26 中建四局第四建筑工程有限公司 A kind of large-span deep foundation pit basement stage construction method and temporary structure
CN110409454A (en) * 2019-08-07 2019-11-05 上海建工二建集团有限公司 Open foundation pit block construction system and method
CN211080241U (en) * 2019-08-07 2020-07-24 上海建工二建集团有限公司 Open foundation pit block construction system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10138616B2 (en) * 2016-08-12 2018-11-27 Wuhan Zhihe Geotechnical Engineering Co., Ltd. Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
CN109723085B (en) * 2019-01-17 2020-11-27 中建三局集团有限公司 Deep foundation pit division construction rib wall support replacing structure and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03267417A (en) * 1990-03-19 1991-11-28 Masatada Saito Earth retaining steel strut having square cross section
KR20100138455A (en) * 2009-06-25 2010-12-31 코오롱건설주식회사 Block for backfilling and method backfilling by that
CN201526052U (en) * 2009-09-07 2010-07-14 上海市第一建筑有限公司 Temporary supporting wall for group pit construction
CN204435388U (en) * 2014-12-24 2015-07-01 重庆建工住宅建设有限公司 Deep foundation ditch stage construction support changing structure for use
CN110055975A (en) * 2019-04-25 2019-07-26 中建四局第四建筑工程有限公司 A kind of large-span deep foundation pit basement stage construction method and temporary structure
CN110409454A (en) * 2019-08-07 2019-11-05 上海建工二建集团有限公司 Open foundation pit block construction system and method
CN211080241U (en) * 2019-08-07 2020-07-24 上海建工二建集团有限公司 Open foundation pit block construction system

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113833018A (en) * 2021-09-09 2021-12-24 广东省重工建筑设计院有限公司 Existing line reconstruction method
CN114541409A (en) * 2022-01-22 2022-05-27 北京市政路桥股份有限公司 Support replacing method for integrated support structure of pipe gallery and tunnel foundation pit
CN114277844B (en) * 2022-01-24 2023-07-25 中国建筑第八工程局有限公司 Construction method of underground structure
CN114277844A (en) * 2022-01-24 2022-04-05 中国建筑第八工程局有限公司 Construction method of underground structure
CN114960680A (en) * 2022-06-27 2022-08-30 福建江夏学院 Be favorable to auxiliary supporting structure of foundation ditch of drainage
CN114960680B (en) * 2022-06-27 2023-09-22 福建江夏学院 Auxiliary supporting structure of foundation pit for facilitating drainage
CN115030186B (en) * 2022-07-15 2023-04-25 中建桥梁有限公司 Foundation pit support construction method for removing existing foundation pit underground continuous wall of multilayer basement
CN115030186A (en) * 2022-07-15 2022-09-09 中建桥梁有限公司 Foundation pit supporting construction method for multi-layer basement requiring dismantling of existing foundation pit diaphragm wall
CN115125960A (en) * 2022-08-05 2022-09-30 中建市政工程有限公司 Common foundation pit excavation method for adjacent foundation pits with different bottom elevations
CN115387344A (en) * 2022-08-19 2022-11-25 中建三局第三建设工程有限责任公司 Double-foundation-pit double-working-condition rapid construction method
CN115387344B (en) * 2022-08-19 2023-09-12 中建三局第三建设工程有限责任公司 Double-foundation pit double-working-condition rapid construction method
CN116025005A (en) * 2023-01-05 2023-04-28 北京住总集团有限责任公司 Subway station main body structure construction method influenced by double rows of lattice columns
CN116025005B (en) * 2023-01-05 2023-07-25 北京住总集团有限责任公司 Subway station main body structure construction method influenced by double rows of lattice columns
CN116815790A (en) * 2023-08-28 2023-09-29 上海建工一建集团有限公司 Foundation pit supporting servo system with two sides adjacent to protection objects and construction method thereof
CN116815790B (en) * 2023-08-28 2023-11-17 上海建工一建集团有限公司 Construction method of foundation pit supporting servo system with two sides adjacent to protection object

Also Published As

Publication number Publication date
CN110409454A (en) 2019-11-05

Similar Documents

Publication Publication Date Title
WO2021023246A1 (en) Open foundation pit block construction system and method
CN105350639B (en) A kind of facade intersects grid structure peripheral frame and its installation method
CN202202412U (en) Rectangular steel pipe concrete special-shaped column-steel beam framework middle node
CN106121270B (en) A kind of frame or frame cut strengthening reconstruction structure and its construction method
CN106592996A (en) Reconstructing method for small foreign-style house
CN202202413U (en) Rectangular steel tube concrete special-shaped column and steel beam frame corner node
CN211080241U (en) Open foundation pit block construction system
CN208152256U (en) A kind of repair type super high rise structure
CN103437360B (en) A kind of not support replacement construction method in deep-foundation pit engineering
CN103147591B (en) Construction method for adding earthquake-proof layer to brick concrete building
CN202202415U (en) Side node of rectangular steel pipe concrete special-shaped column and steel beam framework
CN105804086A (en) Construction method for support change joints in foundation trench reverse building method construction
Garai et al. Three-Dimensional Exterior Bracing Systems for Tall Buildings
CN211257915U (en) Floor-adding structure of existing building underground space
CN210049272U (en) Insertion type column base structure of reinforced concrete frame column
JP2000291031A (en) Construction method for base isolation structure
JP6552145B1 (en) Underground shelter and construction method of underground shelter
JP3308407B2 (en) How to create an underground structure
CN209509556U (en) Underpin the constructing structure of no basement building underground space increasing layer
JP3381066B2 (en) Existing building seismic isolation method and seismic isolation building
JP2004060310A (en) Wooden earthquake-proof construction using earthquake-proof core
JPH09228398A (en) Construction method for pile support type multistoried building
JPH0657769A (en) Underground concrete structure and working method thereof
Carroll et al. China central television headquarters-Structural design
JP4354381B2 (en) Extension method

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20849501

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20849501

Country of ref document: EP

Kind code of ref document: A1