WO2020135894A3 PCT/CN2020/076792 CN2020076792W WO2020135894A3 WO 2020135894 A3 WO2020135894 A3 WO 2020135894A3 CN 2020076792 W CN2020076792 W CN 2020076792W WO 2020135894 A3 WO2020135894 A3 WO 2020135894A3
Authority
WO
WIPO (PCT)
Prior art keywords
lines
tested
nodes
transmission line
combination scheme
Prior art date
Application number
PCT/CN2020/076792
Other languages
French (fr)
Chinese (zh)
Other versions
WO2020135894A2 (en
Inventor
张章
袁博
王颖
王涛
邵华
康伟
陈亮
张丽洁
杨洋
申永鹏
李光毅
Original Assignee
国网河北省电力有限公司经济技术研究院
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 国网河北省电力有限公司经济技术研究院 filed Critical 国网河北省电力有限公司经济技术研究院
Publication of WO2020135894A2 publication Critical patent/WO2020135894A2/en
Publication of WO2020135894A3 publication Critical patent/WO2020135894A3/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Monitoring And Testing Of Transmission In General (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The invention provides a method and device for establishing a transmission line on/off switching combination scheme for limiting short circuit current. The method applies to the technical field of power systems, and comprises: setting an initial number k of lines to be switched off and a maximum number kmax of lines to be switched off; determining, for each node to be tested among a plurality of nodes to be tested, a k-self impedance upon switching off k lines; determining, on the basis of the k-self impedance of each of said nodes, k lines that meet scheme requirements and k lines that do not meet scheme requirements; on the basis of a preset step length d, increasing the initial number k of lines to be switched off to k+d; when k+d≤kmax, considering those nodes among the k lines that do not meet scheme requirements as nodes to be tested, and returning to the step of determining, for each node to be tested among a plurality of nodes to be tested, a k-self impedance upon switching off k lines, and then proceeding to the subsequent step; when k+d>kmax or when the current set of nodes to be tested is null, determining that the establishment of the transmission line on/off switching combination scheme is complete. The method and device for establishing a transmission line on/off switching combination scheme for limiting short circuit current allows for an on/off switching combination scheme to be established quickly.
PCT/CN2020/076792 2018-12-26 2020-02-26 Method and device for establishing transmission line on/off switching combination scheme for limiting short circuit current WO2020135894A2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201811600334.7A CN109638845B (en) 2018-12-26 2018-12-26 Method and device for establishing switching combination scheme of power transmission line
CN201811600334.7 2018-12-26

Publications (2)

Publication Number Publication Date
WO2020135894A2 WO2020135894A2 (en) 2020-07-02
WO2020135894A3 true WO2020135894A3 (en) 2020-08-13

Family

ID=66077975

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/076792 WO2020135894A2 (en) 2018-12-26 2020-02-26 Method and device for establishing transmission line on/off switching combination scheme for limiting short circuit current

Country Status (2)

Country Link
CN (1) CN109638845B (en)
WO (1) WO2020135894A2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109638845B (en) * 2018-12-26 2020-07-28 国网河北省电力有限公司经济技术研究院 Method and device for establishing switching combination scheme of power transmission line

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102427235A (en) * 2011-12-14 2012-04-25 北京天地华泰采矿工程技术有限公司 Methods for distributing reactive power compensation capacity and switching branch circuits of passive filter
US20160139212A1 (en) * 2014-11-13 2016-05-19 Eleon Energy, Inc. Methods and systems for power restoration planning employing simulation and transient test analysis
CN109638845A (en) * 2018-12-26 2019-04-16 浙江大学 Transmission line of electricity switching assembled scheme method for building up and device

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101958548A (en) * 2009-07-20 2011-01-26 符国录 Method and system for suppressing harmonics by utilizing passive filter device
CN107959284A (en) * 2016-10-14 2018-04-24 华北电力大学(保定) A kind of power flow transfer recognizer based on multiple branch circuit excision and away from path
CN108711865B (en) * 2018-07-04 2021-03-30 云南电网有限责任公司 Receiving-end power grid stability control load shedding method based on WAMS

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102427235A (en) * 2011-12-14 2012-04-25 北京天地华泰采矿工程技术有限公司 Methods for distributing reactive power compensation capacity and switching branch circuits of passive filter
US20160139212A1 (en) * 2014-11-13 2016-05-19 Eleon Energy, Inc. Methods and systems for power restoration planning employing simulation and transient test analysis
CN109638845A (en) * 2018-12-26 2019-04-16 浙江大学 Transmission line of electricity switching assembled scheme method for building up and device

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
TIAN, SHIJUN ETC.: "Transmission Switching Considering Short-circuit Current Limitations", 2017 IEEE CONFERENCE ON ENERGY INTERNET AND ENERGY SYSTEM INTEGRATION (EI2), 4 January 2018 (2018-01-04), XP033288377, DOI: 20200525103303A *
YING, LINZHI ET AL.: "Adjustment for Power Grid Configuration to Limit Short-circuit Current Based on Improved Ant Colony Optimization", AUTOMATION OF ELECTRIC POWER SYSTEMS, vol. 42, no. 01, 10 January 2018 (2018-01-10), DOI: 9500300 *
ZHANG, ZHANG ET AL.: "A Method of Searching All Feasible Breaking-Line Schemes for Limiting Short-Circuit Current", PROCEEDINGS OF THE CSU-EPSA, vol. 36, no. 22, 9 September 2019 (2019-09-09), ISSN: 1003-8930, DOI: 20200525103003PX *

Also Published As

Publication number Publication date
CN109638845A (en) 2019-04-16
WO2020135894A2 (en) 2020-07-02
CN109638845B (en) 2020-07-28

Similar Documents

Publication Publication Date Title
EP4184960A3 (en) Communications system, communication method, and apparatus thereof
MX2019015296A (en) Radio bearer configuration method and apparatus.
EP3761721A4 (en) Power control method and device, and communication node
EP3902305A4 (en) Signal transmission method, terminal device, and network device
AR108438A1 (en) UPPER LINK POWER CONTROL FOR SOUND REFERENCE SIGNAL CARRIER-BASED SWITCHING
EP3823357A4 (en) Session management method, terminal device and network device
EP3739969A4 (en) Power control method, first communication node, and second communication node
EP3570598A4 (en) Power control method, terminal device and network device
MX2018001832A (en) Methods of operating network nodes in a communication network, and network nodes implementing the same.
MX2019008053A (en) Communication method, access network device, and terminal.
MX2019009411A (en) Terminal device, core network device, and communication control method.
AR114118A1 (en) METHODS AND USER EQUIPMENT TO RESUME A CONNECTION WITH FULL CONFIGURATION
MX2019003991A (en) Terminal device, mobility management entity (mme), cotrol plane function (cpf), and communication control method.
EP3780745A4 (en) Signal transmission method, network device, and terminal device
EP3860215A4 (en) Method for handover switching, terminal device, and network device
EP4047877A4 (en) Network topology discovery method and node device
EP3823228A4 (en) Message processing method and apparatus, communication device, and switching circuit
PH12019502167A1 (en) Wireless communication method and device
EP3843459A4 (en) Communication system switching method and terminal device
MX2015016812A (en) Method of implementing download control procedure and device utilizing same.
GB2548417A (en) An interface circuit having a data bus interface
EP3965510A4 (en) Configuration activation/deactivation method, network device and terminal
WO2019072318A3 (en) Methods and devices for establishing communication between nodes in blockchain system
AR113506A1 (en) METHOD AND APPARATUS FOR UPLOAD TRANSMISSION
MX2020007884A (en) Cell search method and terminal device.

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20734631

Country of ref document: EP

Kind code of ref document: A2

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20734631

Country of ref document: EP

Kind code of ref document: A2