WO2018214144A1 - Construction control method for 3.3 m thick raft foundation for super high-rise housing project - Google Patents

Construction control method for 3.3 m thick raft foundation for super high-rise housing project Download PDF

Info

Publication number
WO2018214144A1
WO2018214144A1 PCT/CN2017/086088 CN2017086088W WO2018214144A1 WO 2018214144 A1 WO2018214144 A1 WO 2018214144A1 CN 2017086088 W CN2017086088 W CN 2017086088W WO 2018214144 A1 WO2018214144 A1 WO 2018214144A1
Authority
WO
WIPO (PCT)
Prior art keywords
pouring
concrete
construction
temperature
layer
Prior art date
Application number
PCT/CN2017/086088
Other languages
French (fr)
Chinese (zh)
Inventor
宋陈明
Original Assignee
南通八建集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 南通八建集团有限公司 filed Critical 南通八建集团有限公司
Priority to PCT/CN2017/086088 priority Critical patent/WO2018214144A1/en
Publication of WO2018214144A1 publication Critical patent/WO2018214144A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations

Definitions

  • the present invention relates to a 3.3 m thick raft foundation construction control method for a super high-rise residential project.
  • the object of the present invention is to provide a 3.3 m thick raft foundation construction control method for a super high-rise residential project with convenient construction and good effect.
  • a super-high-rise residential project 3.3m thick raft foundation construction control method characterized by: including the following steps [0005] (1) ⁇ pre-casting preparation
  • the concrete pouring is started from the lower part by the slope layering method, and rises layer by layer; the inclined surface is formed by the natural flow of the pumping, the slope is controlled at about 1:8, and the vibrating work starts from the bottom layer of the pouring layer. Move to ensure the quality of construction between layers;
  • the vibrating bar is slightly twitched up and down, so that the upper and lower jaws are evenly vibrated, and each time the vibrating is between 20 and 30 s, the bubble is no longer present on the surface of the crucible, and the mortar is released; ⁇ ⁇ ⁇ ⁇ , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,
  • the lid is covered with water and moisturized, and the maintenance cover is covered with a layer of film and a layer of 50mm polystyrene board.
  • the closed color cloth is matched. ⁇ Uncovering, the lap joint of the colored cloth is required to be no less than 150mm. The narrow space between the wall columns and the ribs must pay special attention to the insulation measures. After covering with the strip film, cover the insulation quilt to ensure the weak link of the wall column. Insulation work;
  • the surface temperature difference between the crucible and the ambient temperature should not exceed 25 degrees, the cooling rate is not more than 1.5 degrees / day; when the internal and external temperature difference is greater than or equal to 25 ° C, increase the coverage or increase the surface of the crucible Thickness of water storage; Therefore, the temperature should be closely monitored.
  • the new measures should ensure that the temperature difference is controlled within 25 °C. When the internal and external temperature difference is less than 20 °C, the covering material should be gradually removed and heat-dissipated.
  • the invention has convenient construction and good effect. It is beneficial to improve the integrity and impermeability of the structure, and improve the seismic resistance of the structure.
  • a super high-rise residential project 3.3m thick raft foundation construction control method comprising the following steps:
  • the vibrating bar is slightly twitched up and down, so that the upper and lower jaws are evenly vibrated, and each time the vibrating is between 20 and 30 s, the bubble is no longer present on the surface of the crucible, and the mortar is released; ⁇ ⁇ ⁇ ⁇ , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,
  • the hoe is covered with water and moisturized, and the maintenance cover is covered with a layer of film and a layer of 50mm polystyrene board.
  • the closed color cloth is matched. ⁇ Uncovering, the lap joint of the colored cloth is required to be no less than 150mm. The narrow space between the wall columns and the ribs must pay special attention to the insulation measures. After covering with the strip film, cover the insulation quilt to ensure the weak link of the wall column. Insulation work;
  • the surface temperature difference between the crucible and the ambient temperature should not exceed 25 degrees, the cooling rate is not more than 1.5 degrees / day; when the internal and external temperature difference is greater than or equal to 25 ° C, increase the coverage or increase the surface of the crucible Water storage Thickness; Therefore, the temperature should be closely monitored.
  • the new measures should be taken to ensure that the temperature difference is controlled within 25 °C : When the internal and external temperature difference is less than 20 °C, the covering material should be gradually removed and allowed to dissipate heat.

Abstract

A construction control method for a 3.3 m thick raft foundation for a super high-rise housing project, comprising preparation before concrete pouring, and implementation of concrete pouring. For concrete pouring, an inclined plane delamination method is used; surface anti-cracking implementation is required to be performed after concrete pouring and before pre-hardening; the surface temperature of the concrete and the structure central temperature must be monitored after concrete pouring; corresponding measures are taken to control the difference between the internal and external temperatures and the temperature drop rate of a concrete pouring block, so as to prevent harmful temperature cracks from occurring in the concrete.

Description

超高层住宅工程 3.3m厚筏板基础施工控制方法 技术领域  Super high-rise residential project 3.3m thick raft foundation construction control method
[0001] 本发明涉及一种超高层住宅工程 3.3m厚筏板基础施工控制方法。  [0001] The present invention relates to a 3.3 m thick raft foundation construction control method for a super high-rise residential project.
背景技术  Background technique
[0002] 大体积砼在水泥水化热的作用下, 将产生较高的水化热温升, 形成不均匀非稳 定温度场, 产生非均匀的温度变形, 温度变形在下部结构和自身的约束之下将 产生较大的温度应力, 极易导致砼幵裂。 基础底板为整座主楼的承重结构, 一 旦幵裂, 不但影响大厦的安全, 底板渗水还会影响大厦的正常使用和耐久性。 技术问题  [0002] Under the action of cement hydration heat, large volume enthalpy will produce higher hydration heat temperature rise, forming uneven unsteady temperature field, resulting in non-uniform temperature deformation, temperature deformation in the lower structure and its own constraints. Underneath will generate large temperature stress, which is easy to cause splitting. The foundation floor is the load-bearing structure of the whole main building. Once it is cracked, it not only affects the safety of the building, but also the water seepage of the floor will affect the normal use and durability of the building. technical problem
[0003] 本发明的目的在于提供一种施工方便、 效果好的超高层住宅工程 3.3m厚筏板基 础施工控制方法。  [0003] The object of the present invention is to provide a 3.3 m thick raft foundation construction control method for a super high-rise residential project with convenient construction and good effect.
问题的解决方案  Problem solution
技术解决方案  Technical solution
[0004] 一种超高层住宅工程 3.3m厚筏板基础施工控制方法, 其特征是: 包括下列步骤 [0005] (一) 砼浇筑前准备  [0004] A super-high-rise residential project 3.3m thick raft foundation construction control method, characterized by: including the following steps [0005] (1) 砼 pre-casting preparation
[0006] ( 1) 在大体积砼施工前半个月, 检査砼供应商原材料的储备情况、 水泥、 外 加剂、 惨合料供应商的供应能力, 并对水泥、 外加剂进行封样处理, 以保障大 体积砼原材料的及吋供应和质量要求;  [0006] (1) Check the reserves of raw materials of suppliers, the supply capacity of cement, admixtures, and miscellaneous materials suppliers, and seal the cement and admixtures, half a month before the construction of large-scale concrete. To ensure the supply and quality requirements of large-volume raw materials;
[0007] (2) 配备两台发电机组, 以防外网停电;  [0007] (2) Equipped with two generator sets to prevent power failure of the external network;
[0008] (3) 机械、 车辆配备  [0008] (3) Machinery, vehicle equipment
[0009] 配备六台砼输送泵, 其中一台备用, 砼泵车每小吋最大砼输出量 50m 3 ;  [0009] equipped with six sputum pumps, one of which is spared, and the maximum enthalpy output per raft of the pump is 50m 3 ;
[0010] (4) 将养护覆盖材料运到基坑附近备用, 确保砼凝结、 养护过程中得到充分 的保养或保温工作; [0010] (4) transporting the curing cover material to the vicinity of the foundation pit to ensure sufficient maintenance or heat preservation during the condensing and curing process;
[0011] (二) 砼浇筑施工 [0011] (2) 砼 pouring construction
[0012] ( 1) 浇筑施工工艺流程 [0013] 布置砼汽车泵→砼供货验收→幵机、 泵送砂浆、 润管→浇筑砼→振捣→循环作 业→砼表面第一次赶平、 抹压→砼表面二次赶平、 压实、 抹光→终凝前第三次检 査早期收缩裂缝再抹压砼表面→及吋覆盖保温保湿养护→砼测温监控; [0012] (1) Pouring construction process [0013] Arrangement 砼 car pump → 砼 supply acceptance → smashing machine, pumping mortar, running pipe → pouring 砼 → vibrating → recycling operation → 砼 surface first leveling, squeezing → 砼 surface secondary leveling, Compaction, trowel → third inspection before the final condensation, early shrinkage cracks and then smearing the surface → and 吋 cover insulation moisturizing maintenance → 砼 temperature monitoring;
[0014] (2) 浇筑方法  [0014] (2) Pouring method
[0015] 砼浇筑采用斜面分层法从低处幵始, 逐层上升; 斜面由泵送砼自然流淌而成, 坡度控制在 1 : 8左右, 振捣工作从浇筑层的底层幵始逐渐上移, 以保证分层砼 间的施工质量;  [0015] The concrete pouring is started from the lower part by the slope layering method, and rises layer by layer; the inclined surface is formed by the natural flow of the pumping, the slope is controlled at about 1:8, and the vibrating work starts from the bottom layer of the pouring layer. Move to ensure the quality of construction between layers;
[0016] 砼在振捣过程中将振动棒上下略有抽动, 使上下砼振动均匀, 每次振捣吋间以 20〜30s, 以砼表面不再出现气泡、 泛出灰浆为准; 为使砼振捣密实, 每台砼泵 出料口配备 5台振捣棒, 4台工作、 1台备用, 分三道布置。 第一道布置在出料点 , 使砼形成自然流淌坡度, 第二道布置在坡脚处, 确保砼下部密实, 第三道布 置在斜面中部, 在斜面上各点要严格控制振捣吋间、 移动距离和插入深度; [0016] In the process of vibrating, the vibrating bar is slightly twitched up and down, so that the upper and lower jaws are evenly vibrated, and each time the vibrating is between 20 and 30 s, the bubble is no longer present on the surface of the crucible, and the mortar is released;砼 捣 捣 捣 , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , The first line is arranged at the discharge point to make the concrete form a natural flow slope. The second line is arranged at the foot of the slope to ensure the lower part of the slope. The third line is arranged in the middle of the slope. The points on the slope are strictly controlled. , moving distance and insertion depth;
[0017] (3) 泌水处理 [0017] (3) bleeding treatment
[0018] 施工中根据施工流水, 大部分泌水排到集水坑和电梯井坑内, 然后用潜水泵抽 排掉, 局部少量泌水采用海绵吸除处理;  [0018] According to the construction running water during construction, most of the bleeding water is discharged into the sump and the elevator pit, and then drained by the submersible pump, and a part of the bleeding is treated by sponge suction;
[0019] (4) 表面防裂施工 [0019] (4) Surface crack prevention construction
[0020] 由于大体积泵送砼表面水泥浆较厚, 故浇筑结束后须在初凝前用, 以闭合砼的 收水裂缝, 砼表面处理首先按面标高用工具拍板压实, 长刮尺刮平; 其次要在 初凝前用压滚进行数遍碾压和滚平; 最后在终凝前, 再检査砼的早期收缩情况 , 木蟹打磨压实、 整平, 以闭合砼收水裂缝, 在砼收浆凝固施工期间, 收浆工 作完成的面必须同步及吋覆盖表面养护保护层;  [0020] Due to the thick cement slurry on the surface of the large volume pumping, it must be used before the initial setting after the pouring, in order to close the water-collecting crack of the crucible, and the surface treatment of the crucible is first compacted by the tool surface according to the surface elevation, and the long scraper is used. Secondly, it should be rolled and rolled several times before the initial setting by the pressure roller. Finally, before the final setting, check the early shrinkage of the cockroach. The wooden crab is sanded and compacted to close the water. Cracks, during the construction of the squeezing and solidification, the surface of the finishing work must be synchronized and covered with a surface protection layer;
[0021] (5) 砼养护  [0021] (5) Maintenance
[0022] 砼在浇筑完毕后的 12h以内, 苫盖并洒水保湿养护, 养护覆盖采用一层薄膜加 一层 50mm聚苯板的保养方式, 根据测温情况配足封闭的彩色布, 做到及吋揭覆 , 要求彩色布的搭接不得小于 150mm, 墙柱插筋之间狭小空间必须特别注意保 温措施, 用条形薄膜加以覆盖后, 再加盖保温被, 确保墙柱插筋薄弱环节处的 保温工作;  [0022] Within 12 hours after the pouring, the lid is covered with water and moisturized, and the maintenance cover is covered with a layer of film and a layer of 50mm polystyrene board. According to the temperature measurement, the closed color cloth is matched.吋Uncovering, the lap joint of the colored cloth is required to be no less than 150mm. The narrow space between the wall columns and the ribs must pay special attention to the insulation measures. After covering with the strip film, cover the insulation quilt to ensure the weak link of the wall column. Insulation work;
[0023] (6) 砼的测温工作 [0024] 大体积砼浇筑后, 必须进行监测砼表面温度与结构中心温度, 以便采取相应措 施, 控制砼浇筑块体的内外温差及降温速度, 防止砼出现有害的温度裂缝;[0023] (6) Temperature measurement work of 砼 [0024] After pouring a large volume of concrete, it is necessary to monitor the surface temperature of the crucible and the temperature of the center of the structure, so as to take corresponding measures to control the temperature difference between the inside and the outside of the casting block and the temperature drop rate to prevent harmful temperature cracks from occurring in the crucible;
[0025] 严格控制砼内外温差、 砼表面温度与环境温度差均不应大于 25度, 降温速度不 大于 1.5度 /天; 当内外温差大于等于 25°C吋, 对砼表面再增加覆盖或增加蓄水的 厚度; 此吋, 应密切注意测定温度, 新采取的措施应确保温差控制在 25°C以内, 当内外温差小于 20°C吋, 应逐渐撤除覆盖材料, 待其散热。 [0025] Strictly control the temperature difference between the inside and outside of the crucible, the surface temperature difference between the crucible and the ambient temperature should not exceed 25 degrees, the cooling rate is not more than 1.5 degrees / day; when the internal and external temperature difference is greater than or equal to 25 ° C, increase the coverage or increase the surface of the crucible Thickness of water storage; Therefore, the temperature should be closely monitored. The new measures should ensure that the temperature difference is controlled within 25 °C. When the internal and external temperature difference is less than 20 °C, the covering material should be gradually removed and heat-dissipated.
发明的有益效果  Advantageous effects of the invention
有益效果  Beneficial effect
[0026] 本发明施工方便、 效果好。 有利于提高结构的整体性、 抗渗性, 同吋提高了结 构的抗震能力。  The invention has convenient construction and good effect. It is beneficial to improve the integrity and impermeability of the structure, and improve the seismic resistance of the structure.
实施该发明的最佳实施例  BEST MODE FOR CARRYING OUT THE INVENTION
本发明的最佳实施方式  BEST MODE FOR CARRYING OUT THE INVENTION
[0027] 一种超高层住宅工程 3.3m厚筏板基础施工控制方法, 包括下列步骤: [0027] A super high-rise residential project 3.3m thick raft foundation construction control method, comprising the following steps:
[0028] (一) 砼浇筑前准备 [0028] (1) Preparation before pouring
[0029] (1) 在大体积砼施工前半个月, 检査砼供应商原材料的储备情况、 水泥、 外 加剂、 惨合料供应商的供应能力, 并对水泥、 外加剂进行封样处理, 以保障大 体积砼原材料的及吋供应和质量要求;  [0029] (1) In the first half of the construction of the large-volume concrete, check the reserves of the raw materials of the suppliers, the supply capacity of the cement, admixtures, and miscellaneous materials suppliers, and seal the cement and admixtures. To ensure the supply and quality requirements of large-volume raw materials;
[0030] (2) 配备两台发电机组, 以防外网停电;  [0030] (2) equipped with two generator sets to prevent power failure of the external network;
[0031] (3) 机械、 车辆配备  [0031] (3) Machinery, vehicle equipment
[0032] 配备六台砼输送泵, 其中一台备用, 砼泵车每小吋最大砼输出量 50m 3 ;  [0032] Equipped with six sputum pumps, one of which is spared, and the maximum 砼 output per 吋 pump is 50m 3 ;
[0033] (4) 将养护覆盖材料运到基坑附近备用, 确保砼凝结、 养护过程中得到充分 的保养或保温工作; [0033] (4) transporting the curing cover material to the vicinity of the foundation pit to ensure sufficient maintenance or heat preservation during the condensing and curing process;
[0034] (二) 砼浇筑施工 [0034] (2) 砼 pouring construction
[0035] (1) 浇筑施工工艺流程 [0035] (1) Pouring construction process
[0036] 布置砼汽车泵→砼供货验收→幵机、 泵送砂浆、 润管→浇筑砼→振捣→循环作 业→砼表面第一次赶平、 抹压→砼表面二次赶平、 压实、 抹光→终凝前第三次检 査早期收缩裂缝再抹压砼表面→及吋覆盖保温保湿养护→砼测温监控;  [0036] Arrangement 砼 car pump → 砼 supply acceptance → smashing machine, pumping mortar, running pipe → pouring 砼 → vibrating → circulating operation → 砼 surface first leveling, squeezing → 砼 surface secondary leveling, Compaction, trowel → third inspection before the final condensation, early shrinkage cracks and then smearing the surface → and 吋 cover insulation moisturizing maintenance → 砼 temperature monitoring;
[0037] (2) 浇筑方法 [0038] 砼浇筑采用斜面分层法从低处幵始, 逐层上升; 斜面由泵送砼自然流淌而成, 坡度控制在 1 : 8左右, 振捣工作从浇筑层的底层幵始逐渐上移, 以保证分层砼 间的施工质量; [0037] (2) Pouring method [0038] The concrete pouring is started from the lower part by the inclined layer stratification method, and rises layer by layer; the inclined surface is formed by pumping natural flowing, the slope is controlled at about 1:8, and the vibrating work starts from the bottom layer of the pouring layer. Move to ensure the quality of construction between layers;
[0039] 砼在振捣过程中将振动棒上下略有抽动, 使上下砼振动均匀, 每次振捣吋间以 20〜30s, 以砼表面不再出现气泡、 泛出灰浆为准; 为使砼振捣密实, 每台砼泵 出料口配备 5台振捣棒, 4台工作、 1台备用, 分三道布置。 第一道布置在出料点 , 使砼形成自然流淌坡度, 第二道布置在坡脚处, 确保砼下部密实, 第三道布 置在斜面中部, 在斜面上各点要严格控制振捣吋间、 移动距离和插入深度; [0039] In the process of vibrating, the vibrating bar is slightly twitched up and down, so that the upper and lower jaws are evenly vibrated, and each time the vibrating is between 20 and 30 s, the bubble is no longer present on the surface of the crucible, and the mortar is released;砼 捣 捣 捣 , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , The first line is arranged at the discharge point to make the concrete form a natural flow slope. The second line is arranged at the foot of the slope to ensure the lower part of the slope. The third line is arranged in the middle of the slope. The points on the slope are strictly controlled. , moving distance and insertion depth;
[0040] (3) 泌水处理 [0040] (3) bleeding treatment
[0041] 施工中根据施工流水, 大部分泌水排到集水坑和电梯井坑内, 然后用潜水泵抽 排掉, 局部少量泌水采用海绵吸除处理;  [0041] According to the construction running water during construction, most of the bleeding water is discharged into the sump and the elevator pit, and then drained by the submersible pump, and a small amount of bleeding is treated by sponge suction;
[0042] (4) 表面防裂施工 (4) Surface crack prevention construction
[0043] 由于大体积泵送砼表面水泥浆较厚, 故浇筑结束后须在初凝前用, 以闭合砼的 收水裂缝, 砼表面处理首先按面标高用工具拍板压实, 长刮尺刮平; 其次要在 初凝前用压滚进行数遍碾压和滚平; 最后在终凝前, 再检査砼的早期收缩情况 , 木蟹打磨压实、 整平, 以闭合砼收水裂缝, 在砼收浆凝固施工期间, 收浆工 作完成的面必须同步及吋覆盖表面养护保护层;  [0043] Due to the thick cement slurry on the surface of the large volume pumping, it must be used before the initial setting after the pouring, in order to close the water-collecting crack of the crucible, and the surface treatment of the crucible is first compacted by the tool surface according to the surface elevation, and the long scraper is used. Secondly, it should be rolled and rolled several times before the initial setting by the pressure roller. Finally, before the final setting, check the early shrinkage of the cockroach. The wooden crab is sanded and compacted to close the water. Cracks, during the construction of the squeezing and solidification, the surface of the finishing work must be synchronized and covered with a surface protection layer;
[0044] (5) 砼养护  [0044] (5) Maintenance
[0045] 砼在浇筑完毕后的 12h以内, 苫盖并洒水保湿养护, 养护覆盖采用一层薄膜加 一层 50mm聚苯板的保养方式, 根据测温情况配足封闭的彩色布, 做到及吋揭覆 , 要求彩色布的搭接不得小于 150mm, 墙柱插筋之间狭小空间必须特别注意保 温措施, 用条形薄膜加以覆盖后, 再加盖保温被, 确保墙柱插筋薄弱环节处的 保温工作;  [0045] Within 12 hours after the pouring, the hoe is covered with water and moisturized, and the maintenance cover is covered with a layer of film and a layer of 50mm polystyrene board. According to the temperature measurement, the closed color cloth is matched.吋Uncovering, the lap joint of the colored cloth is required to be no less than 150mm. The narrow space between the wall columns and the ribs must pay special attention to the insulation measures. After covering with the strip film, cover the insulation quilt to ensure the weak link of the wall column. Insulation work;
[0046] (6) 砼的测温工作  [0046] (6) Temperature measurement work of 砼
[0047] 大体积砼浇筑后, 必须进行监测砼表面温度与结构中心温度, 以便采取相应措 施, 控制砼浇筑块体的内外温差及降温速度, 防止砼出现有害的温度裂缝; [0047] After pouring a large volume of concrete, it is necessary to monitor the surface temperature of the crucible and the temperature of the center of the structure, so as to take corresponding measures to control the temperature difference between the inside and the outside of the casting block and the cooling rate to prevent harmful temperature cracks from occurring in the crucible;
[0048] 严格控制砼内外温差、 砼表面温度与环境温度差均不应大于 25度, 降温速度不 大于 1.5度 /天; 当内外温差大于等于 25°C吋, 对砼表面再增加覆盖或增加蓄水的 厚度; 此吋, 应密切注意测定温度, 新采取的措施应确保温差控制在 25°C以内 : 当内外温差小于 20°C吋, 应逐渐撤除覆盖材料, 待其散热。 [0048] Strictly control the temperature difference between the inside and outside of the crucible, the surface temperature difference between the crucible and the ambient temperature should not exceed 25 degrees, the cooling rate is not more than 1.5 degrees / day; when the internal and external temperature difference is greater than or equal to 25 ° C, increase the coverage or increase the surface of the crucible Water storage Thickness; Therefore, the temperature should be closely monitored. The new measures should be taken to ensure that the temperature difference is controlled within 25 °C : When the internal and external temperature difference is less than 20 °C, the covering material should be gradually removed and allowed to dissipate heat.

Claims

权利要求书 [权利要求 1] 一种超高层住宅工程 3.3m厚筏板基础施工控制方法, 其特征是: 包括 下列步骤: (一) 砼浇筑前准备 ( 1) 在大体积砼施工前半个月, 检査砼供应商原材料的储备情况、 水泥、 外加剂、 惨合料供应商的供应能力, 并对水泥、 外加剂进行封 样处理, 以保障大体积砼原材料的及吋供应和质量要求; (2) 配备两台发电机组, 以防外网停电; (3) 机械、 车辆配备 配备六台砼输送泵, 其中一台备用, 砼泵车每小吋最大砼输出量 50m3 . (4) 将养护覆盖材料运到基坑附近备用, 确保砼凝结、 养护过程中 得到充分的保养或保温工作; (二) 砼浇筑施工 Claims [Claim 1] A 3.3 m thick raft foundation construction control method for a super high-rise residential project, characterized in that: the following steps are included: (1) Preparation before pouring (1) Half a month before construction of large volume concrete Check the reserves of raw materials of suppliers, the supply capacity of cement, admixtures, and suppliers of miscellaneous materials, and seal the cement and admixtures to ensure the supply and quality requirements of large-volume raw materials; (2) Equipped with two generator sets to prevent power outages on the external network; (3) Machinery and vehicles are equipped with six sputum pumps, one of which is spared, and the maximum output of 砼 pump trucks per hour is 50m3. (4) The curing cover material is transported to the vicinity of the foundation pit to ensure sufficient maintenance or heat preservation during the condensing and curing process; (2) 砼 pouring construction
( 1) 浇筑施工工艺流程  (1) Pouring construction process
布置砼汽车泵→砼供货验收→幵机、 泵送砂浆、 润管→浇筑砼→振捣 Arranged 砼 car pump → 砼 supply acceptance → smashing machine, pumping mortar, running pipe → pouring 砼 → vibrating
→循环作业→砼表面第一次赶平、 抹压→砼表面二次赶平、 压实、 抹 光→终凝前第三次检査早期收缩裂缝再抹压砼表面→及吋覆盖保温保 湿养护砼测温监控; →Cycle operation→The first surface of the 砼 surface is leveled, smeared → 砼 surface is leveled twice, compacted, smeared → the third time before the final setting, the early shrinkage crack is applied and the surface is smeared → and the enamel cover is kept moisturized Maintenance 砼 temperature monitoring;
(2) 浇筑方法 (2) Pouring method
砼浇筑采用斜面分层法从低处幵始, 逐层上升; 斜面由泵送砼自然流 淌而成, 坡度控制在 1 : 8左右, 振捣工作从浇筑层的底层幵始逐渐上 移, 以保证分层砼间的施工质量;  The concrete pouring is started from the lower part by the slope layering method and rises layer by layer. The inclined surface is made by pumping and flowing naturally. The slope is controlled at about 1:8, and the vibrating work starts to move upward from the bottom layer of the pouring layer. Ensure the quality of construction between layers of time;
砼在振捣过程中将振动棒上下略有抽动, 使上下砼振动均匀, 每次振 捣吋间以 20〜30s, 以砼表面不再出现气泡、 泛出灰浆为准; 为使砼 振捣密实, 每台砼泵出料口配备 5台振捣棒, 4台工作、 1台备用, 分 三道布置。 第一道布置在出料点, 使砼形成自然流淌坡度, 第二道布 置在坡脚处, 确保砼下部密实, 第三道布置在斜面中部, 在斜面上各 点要严格控制振捣吋间、 移动距离和插入深度; 砼In the process of vibrating, the vibrating rod is slightly twitched up and down, so that the upper and lower jaws vibrate evenly, each time between 20 and 30 s, the air bubbles no longer appear on the surface of the crucible, and the mortar is released. Dense, each pump pump outlet is equipped with 5 vibrating rods, 4 sets of work, 1 set of spare, arranged in three ways. The first line is placed at the discharge point, so that the raft forms a natural flow slope, the second cloth Placed at the foot of the slope to ensure that the lower part of the squat is dense, and the third line is arranged in the middle of the slanted surface. The vibration point, moving distance and insertion depth should be strictly controlled at each point on the inclined surface;
(3) 泌水处理  (3) bleeding treatment
施工中根据施工流水, 大部分泌水排到集水坑和电梯井坑内, 然后用 潜水泵抽排掉, 局部少量泌水采用海绵吸除处理; According to the construction running water during construction, most of the bleeding water is discharged into the sump and the elevator pit, and then pumped out by the submersible pump. The local small amount of bleeding is treated by sponge suction;
(4) 表面防裂施工  (4) Surface crack prevention construction
由于大体积泵送砼表面水泥浆较厚, 故浇筑结束后须在初凝前用, 以 闭合砼的收水裂缝, 砼表面处理首先按面标高用工具拍板压实, 长刮 尺刮平; 其次要在初凝前用压滚进行数遍碾压和滚平; 最后在终凝前Because the cement slurry on the surface of the large volume pumping is thicker, it must be used before the initial setting after the pouring, in order to close the water-receiving crack of the concrete. The surface treatment of the concrete is first compacted with the tool surface according to the surface elevation, and the long scraper is flattened; Secondly, it is necessary to carry out several times of rolling and rolling with a pressure roll before the initial setting; finally before the final setting
, 再检査砼的早期收缩情况, 木蟹打磨压实、 整平, 以闭合砼收水裂 缝, 在砼收浆凝固施工期间, 收浆工作完成的面必须同步及吋覆盖表 面养护保护层; , and then check the early shrinkage of the cockroach, the wooden crab is sanded and compacted, and the concrete is closed to close the smashing water crack. During the squeezing and solidification construction, the surface of the pulping work must be synchronized and covered with the surface protection layer;
(5) 砼养护  (5) Maintenance
砼在浇筑完毕后的 12h以内, 苫盖并洒水保湿养护, 养护覆盖采用一 层薄膜加一层 50mm聚苯板的保养方式, 根据测温情况配足封闭的彩 色布, 做到及吋揭覆, 要求彩色布的搭接不得小于 150mm, 墙柱插筋 之间狭小空间必须特别注意保温措施, 用条形薄膜加以覆盖后, 再加 盖保温被, 确保墙柱插筋薄弱环节处的保温工作; 12 Within 12 hours after the pouring, the lid is covered with water and moisturized, and the maintenance cover is covered with a layer of film and a layer of 50mm polystyrene board. According to the temperature measurement, the closed color cloth is matched and uncovered. It is required that the lap joint of the colored cloth should not be less than 150mm. The narrow space between the wall columns and the ribs must pay special attention to the insulation measures. After covering with the strip film, cover the insulation quilt to ensure the insulation work at the weak link of the wall column ribs. ;
(6) 砼的测温工作  (6) 测 temperature measurement work
大体积砼浇筑后, 必须进行监测砼表面温度与结构中心温度, 以便采 取相应措施, 控制砼浇筑块体的内外温差及降温速度, 防止砼出现有 害的温度裂缝; After pouring a large volume of concrete, it is necessary to monitor the surface temperature of the concrete and the temperature of the structural center in order to take corresponding measures to control the temperature difference between the inside and the outside of the concrete pouring block and the cooling rate to prevent harmful temperature cracks in the concrete;
严格控制砼内外温差、 砼表面温度与环境温度差均不应大于 25度, 降 温速度不大于 1.5度 /天; 当内外温差大于等于 25°C吋, 对砼表面再增 加覆盖或增加蓄水的厚度; 此吋, 应密切注意测定温度, 新采取的措 施应确保温差控制在 25°C以内, 当内外温差小于 20°C吋, 应逐渐撤除 覆盖材料, 待其散热。 Strictly control the temperature difference between the inside and outside of the crucible, the surface temperature difference between the crucible and the ambient temperature should not exceed 25 degrees, and the cooling rate should not exceed 1.5 degrees/day; when the internal and external temperature difference is greater than or equal to 25 °C, increase the coverage or increase the water storage on the surface of the crucible. Thickness; Therefore, the temperature should be closely monitored. The new measures should ensure that the temperature difference is controlled within 25 °C. When the internal and external temperature difference is less than 20 °C, the covering material should be gradually removed and heat-dissipated.
PCT/CN2017/086088 2017-05-26 2017-05-26 Construction control method for 3.3 m thick raft foundation for super high-rise housing project WO2018214144A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/CN2017/086088 WO2018214144A1 (en) 2017-05-26 2017-05-26 Construction control method for 3.3 m thick raft foundation for super high-rise housing project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2017/086088 WO2018214144A1 (en) 2017-05-26 2017-05-26 Construction control method for 3.3 m thick raft foundation for super high-rise housing project

Publications (1)

Publication Number Publication Date
WO2018214144A1 true WO2018214144A1 (en) 2018-11-29

Family

ID=64395166

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2017/086088 WO2018214144A1 (en) 2017-05-26 2017-05-26 Construction control method for 3.3 m thick raft foundation for super high-rise housing project

Country Status (1)

Country Link
WO (1) WO2018214144A1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU710541B1 (en) * 1999-02-17 1999-09-23 Neumann Steel Pty Limited Monolithic concrete raft slabs
CN103205979A (en) * 2013-03-15 2013-07-17 中国十七冶集团有限公司 Method for constructing large raft foundation under high temperature
JP2015021314A (en) * 2013-07-19 2015-02-02 クリ英ター永和株式会社 Solid foundation method using pc unit, and pc unit
CN106049519A (en) * 2016-07-18 2016-10-26 重庆建工第三建设有限责任公司 Stepped large raft construction technology
CN107178090A (en) * 2017-05-26 2017-09-19 南通八建集团有限公司 Super high-rise dwelling house engineering 3.3m raft foundation construction control methods

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU710541B1 (en) * 1999-02-17 1999-09-23 Neumann Steel Pty Limited Monolithic concrete raft slabs
CN103205979A (en) * 2013-03-15 2013-07-17 中国十七冶集团有限公司 Method for constructing large raft foundation under high temperature
JP2015021314A (en) * 2013-07-19 2015-02-02 クリ英ター永和株式会社 Solid foundation method using pc unit, and pc unit
CN106049519A (en) * 2016-07-18 2016-10-26 重庆建工第三建设有限责任公司 Stepped large raft construction technology
CN107178090A (en) * 2017-05-26 2017-09-19 南通八建集团有限公司 Super high-rise dwelling house engineering 3.3m raft foundation construction control methods

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
LU , FANG ET AL.: "Test and Construction Control Technology of 3.3m Thick Foundation Slab Concrete Test Specimen", TIANJIN CONSTRUCTION SCIENCE AND TECHNOLOGY, 29 February 2008 (2008-02-29), pages 16, 18, 19, ISSN: 1008-3197 *

Similar Documents

Publication Publication Date Title
CN105133615B (en) Circulating cooling water temperature-control construction method for mass concrete in large temperature difference environments of Qinghai-Tibet plateau areas
CN104018673B (en) Ultra-large volume concrete one-time continuous pours into a mould multi cycle real-time temperature control construction technology
CN105604239B (en) A kind of foam concrete functionally gradient composite plate and preparation method thereof
CN101634148B (en) Soil nailing wall foundation pit support and construction method
CN106150001B (en) A kind of fabricated assembly overall stair construction method
CN201333743Y (en) Concrete heat-insulation and moisture-retention curing template
CN113668928B (en) Method for controlling construction cracks of ultra-large-volume concrete water pool
CN107881902A (en) Concrete construction method and mirror surface concrete pier stud
CN106759354A (en) A kind of stratified continuous pouring mode of ultra-long and ultra-thick volume of concrete foundation
CN113718777A (en) Mass concrete crack prevention construction method
CN105133487B (en) Construction method for using combined type bridge temporary support to rapidly build continuous beams
CN104264676A (en) Construction method of mass concrete of high-rise building foundations
CN110000892A (en) A kind of production technology of prefabricated component stair
CN106836551A (en) Infill Wall with Aerated Concrete Block construction method
CN111305399A (en) Basement outer wall post-cast strip system and construction method thereof
CN105822068B (en) Ultralong thin walled concrete walls under hot environment pour and maintenance process
WO2018214144A1 (en) Construction control method for 3.3 m thick raft foundation for super high-rise housing project
CN205894276U (en) Prefabricated prefabricated concrete structure
CN207194226U (en) A kind of assembled integral shear wall connecting node
CN109487790A (en) A kind of concrete heat-insulating method suitable for the big temperature difference area of High aititude
CN107178090A (en) Super high-rise dwelling house engineering 3.3m raft foundation construction control methods
CN107246106A (en) A kind of surface cuts shaping haydite concrete prefabricated panel
CN114319778A (en) Construction method of foam concrete heat-preservation sound-insulation terrace
CN209903483U (en) Negative pressure slip casting forming device
CN112659354A (en) Machining method of structural electromechanical thermal insulation integrated wall

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17910783

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 17910783

Country of ref document: EP

Kind code of ref document: A1