WO2018145027A1 - Toe casing - Google Patents
Toe casing Download PDFInfo
- Publication number
- WO2018145027A1 WO2018145027A1 PCT/US2018/016900 US2018016900W WO2018145027A1 WO 2018145027 A1 WO2018145027 A1 WO 2018145027A1 US 2018016900 W US2018016900 W US 2018016900W WO 2018145027 A1 WO2018145027 A1 WO 2018145027A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- casing
- section
- toe
- casing section
- well
- Prior art date
Links
- 239000000463 material Substances 0.000 claims abstract description 46
- 229910000838 Al alloy Inorganic materials 0.000 claims abstract description 9
- 238000000034 method Methods 0.000 claims description 14
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 229910001069 Ti alloy Inorganic materials 0.000 abstract description 6
- 239000002131 composite material Substances 0.000 abstract description 5
- 229930195733 hydrocarbon Natural products 0.000 abstract description 5
- 150000002430 hydrocarbons Chemical class 0.000 abstract description 5
- 238000004519 manufacturing process Methods 0.000 abstract description 5
- 239000004215 Carbon black (E152) Substances 0.000 abstract description 2
- 238000005553 drilling Methods 0.000 description 12
- 230000015572 biosynthetic process Effects 0.000 description 6
- 238000005755 formation reaction Methods 0.000 description 6
- 230000008901 benefit Effects 0.000 description 4
- 229910052751 metal Inorganic materials 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- 229910045601 alloy Inorganic materials 0.000 description 3
- 239000000956 alloy Substances 0.000 description 3
- 239000011159 matrix material Substances 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000013459 approach Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- RTAQQCXQSZGOHL-UHFFFAOYSA-N Titanium Chemical compound [Ti] RTAQQCXQSZGOHL-UHFFFAOYSA-N 0.000 description 1
- 229910052782 aluminium Inorganic materials 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 230000003466 anti-cipated effect Effects 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000006731 degradation reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 229910052500 inorganic mineral Inorganic materials 0.000 description 1
- 239000011499 joint compound Substances 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 239000011156 metal matrix composite Substances 0.000 description 1
- 239000011707 mineral Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010936 titanium Substances 0.000 description 1
- 229910052719 titanium Inorganic materials 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B17/00—Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
- E21B17/14—Casing shoes for the protection of the bottom of the casing
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B17/00—Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
- E21B17/02—Couplings; joints
- E21B17/08—Casing joints
Definitions
- the invention relates generally to wells, such as those used to access subsurface formations containing minerals, such as oil and gas.
- tubular products which can traverse water depths, subterranean formations, and that ultimately access subterranean horizons of interest. These horizons may include locations where products are found that have commercial value, such as oil and gas deposits.
- tubular products such as drillpipe, casing, and so forth are assembled at the Earth's surface or on a floating vessel or platform, and run into a well.
- these tubular products are made of steel that is produced and utilized in standard lengths with standard coupling ends that can be readily threaded together to form an extended tubular string.
- One important phase of the drilling and completions process involves setting casing in the producing zone. This prevents the open hole from collapsing, reinforces the hole for completions operations, and allows a long term conduit for producing. .
- different techniques may be needed, such as to prevent degradation of the well bore, collapse of the rock, sand, mud or other materials comprising the well bore, and to access the horizons of commercial interest.
- Conventional casing techniques often include running a tubular casing string into the well following drilling. Such casing strings are typically made of steel and perform adequately in most applications, in some cases, however, it may be difficult or impossible, or economically infeasible to case extended sections of the well.
- reamers, tools, shoes, guides, and other structures have been used or proposed to aid in deploying rigid casing in sections of wells. Some of these may be designed to be drilled through. Others act as guides for the actual casing, but do not, and are not intended to themselves form any permanent part of the well casing. Indeed, given their construction, dimensions, and placement, they may be wholly unsuitable for use as actual casing.
- a system comprises a tubular casing section comprising a first material and extending through a first section of a subterranean well, and a toe casing section coupled to the lower end of the tubular casing section and extending into the furthest section of open hole of the well, the toe casing section comprising a second material different from the first material.
- the disclosure also provides a system comprising a tubular casing section comprising a first material and extending through a generally vertical section of a subterranean well and into a portion of an off-vertical section of the subterranean well continuous with the vertical section, and a toe casing section coupled to the distal end of the tubular casing section and extending into the furthest section of open-hole , the toe casing section comprising a second material different from the first material.
- the disclosure provides a method comprising assembling a toe casing section comprising a toe casing material, deploying the toe casing section into a well, assembling a casing section comprising a casing material different from the toe casing material, the toe casing section being secured to an upper section of casing, and deploying the whole casing into the well to set the toe casing section into the end of the open-hole section of the well.
- FIG. 1 is a diagrammatical representation of an example installation for drilling, completing, or servicing a well in accordance with the present techniques
- FIG. 2 is a diagrammatical representation of a sections of a tubular string extending into a well and including the toe casing section;
- FIG. 3 is a diagrammatical representation of a toe casing section inserted into a section of a well.
- FIG. 4 is a flow chart illustrating example operations for deploying a toe casing section into a well.
- FIG. 1 a well system is illustrated and designated generally by the reference numeral 10.
- the system is illustrated as an onshore operation located on the earth's surface 12 although the present techniques are not limited to such operations, but may be used in offshore applications, in which the drilling and service equipment and systems described would be located on a vessel or platform, and the well would be located below a body of water.
- the underlying ground or earth is illustrated below the surface such that well equipment is positioned near or over one or more wells.
- One or more subterranean horizons 16 are traversed by the well, which ultimately leads to one or more horizons of interest 18.
- the well and associated equipment permit, for example, accessing and extracting the hydrocarbons located in the hydrocarbon zones of interest, depending upon the purpose of the well.
- the horizons will hold hydrocarbons that will ultimately be produced from the well, such as oil and/or gas.
- the well equipment may be used for any operation on the well, such as drilling, completion, workover, and so forth. In many operations the installation may be temporarily located at the well site, and additional components may be provided.
- a derrick 14 allows for various tools, instruments and tubular strings to be assembled and lowered into the well, traversing both the horizons 16 and the particular horizons of interest 18.
- Well or surface equipment 20 will typically include draw works, a rotary table, generators, instrumentations, and so forth.
- Control and monitoring systems 22 allow for monitoring all aspects of drilling, completion, workover or any other operations performed, as well as well conditions, such as pressures, flow rates, depths, rates of penetration, and so forth.
- tubular stocks may be provided and used by the operation, and these may be stored on any suitable racks or other storage locations.
- a first of these is designated tubular 1 storage 24, and the second is designated tubular 2 storage 26.
- tubular products may comprise lengths of pipe with connectors at each end to allow for extended strings to be assembled, typically by screwing one into the other, or two tubular products connected via a single coupling.
- Different tubular stocks are used here to allow the operation to balance the technical qualities and performance possibilities of each against their costs.
- this second tubular stock may comprise, aluminum alloys, for example, but possibly also certain titanium alloys, composite materials, or metal matrix alloys. As discussed below, the operation judiciously selected which material to use based upon the nature of the well, the well position and geology, and the relative need to extend tubular strings into portions of the well that may not be readily accessed by conventional casing sections.
- a well comprises a first, generally vertical section 28 that extends through the upper horizons 16, and an off-vertical section 30 that extends through at least a portion of the zone of interest 18.
- the vertical section is formed to access the horizon of interest, and may extend to any desired depth, such as 7,000 feet to 12,000 feet.
- the off-vertical section may extend at any desired angle from the vertical section, which may be generally perpendicular to the vertical section, although other angles for this section may be used.
- a well or a well system may access a number of locations in one or more horizons of interest by directional drilling to create one or more such off-vertical sections.
- a casing 32 is illustrated as already deployed in the well.
- This casing may be at least partially surrounded by cement 34 after it is set, to fortify at least part of the well and to secure the casing in the zone of interest.
- the casing and cement sections may differ from well to well depending upon such factors as the geology of the subterranean horizons, the sizes desired, the anticipated conditions (e.g., pressures and flow) and so forth.
- an open hole section 36 extends into the horizon of interest.
- the hole through the zone of interest will rise and fall, "snaking" through the formation, often referred to as 'tortuosity' . .
- the casing extends to an end or limit 38 beyond which it may be very difficult or impossible, or very expensive to move conventional casing further into the drilled open hole.
- tubular section(s) are inserted permanently into the wellbore, may be cemented in place, and serve for both booking of reserves and for production from the well, such as by extraction of hydrocarbons (e.g., by perforation of the toe casing section(s) in at least one location).
- the casing 32 extends a length 40 through the vertical section 28 of the well and through a portion of the off-vertical section 30 to the limit 38.
- the casing comprises a tubular string that is run into the well following drilling.
- Such strings may comprise any suitable length of tubular products, and these will depend upon a number of factors, but typically the location of the horizon of interest (e.g., its depth and the length of the off-vertical section, the distance to a location of interest), the depth of the water, if offshore, and so forth.
- the tubular casing extends into the open hole section 36 and includes a toe casing section 44.
- the casing may include a casing shoe 46 to help navigate the casing through the open hole section.
- a heel 48 in the tubular string will be formed where the build section transitions into the horizontal section.
- the tubular string defined by the casing 32 and the toe casing 44 will typically be assembled by the well equipment, drawing from the tubular materials stored as discussed above. That is, once the well is drilled, the casing sections may be assembled by taking the casing sections from the storage, threading them end-to-end, and deploying them progressively into the well. Once the desired length of toe casing is assembled, the upper casing is added to the toe casing by accessing the other tubular material and assembling sections of it end-to-end in a similar manner.
- the toe casing 44 may be made of aluminum alloy, or another material that enables the casing to be more easily run into the open-hole section of the well, by decreasing frictional forces on the casing, and increasing hook load (e.g., titanium alloy, composite material, metal matrix alloys).
- the upper casing 32 may be made of conventional materials, such as steel.
- the tubular sections assembled in this way may comprise, for example, multiple sections of standard length (e.g., 40 foot sections) each having industry standard end connectors to facilitate their assembly.
- the vertical section of the well may extend as much as 7,000 to 12,000 or more feet vertically into the earth (note that the "vertical" section need not be strictly vertical, but may be inclined in at least a part of the well), the off-horizon section may extend another 5,000 to 20,000 feet.
- the toe casing section thus will be set in the furthest portion of the open-hole section. It is presently contemplated that the toe casing section 44 may be from 100 to 1,000 feet in length, although any suitable length may be used.
- FIG. 2 represents a section of toe casing as it might be deployed in a well.
- the toe casing section 44 will have a casing shoe 46 at an end to assist in advancing the casing through the open hole.
- the total length 52 of the toe casing may vary depending upon the well profile and the length of the open-hole section.
- FIG. 3 illustrates the toe casing 44 deployed in the open-hole section of the well.
- the well bore may be represented as a generally straight shaft, this will rarely be the case.
- the well will have side walls 54 that undulate or wind through the horizon due to many factors, particularly the geology of the surrounding formations and drilling practices and equipment used.
- Variability in the wellbore walls, indicated generally by reference numeral 56 may cause serious challenges in advancing conventional casing.
- special costly tools and techniques may be employed to rotate the casing, although these ultimately reach a limit beyond which further advancement is not cost effective.
- the toe casing made of a material such as an aluminum alloy, a titanium alloy, or a composite material, metal matrix alloy, on the other hand, may be more easily advanced into extended sections of open hole by the flexibility and lighter weight of the material of the toe casing, as indicated generally by reference numeral 58 in FIG. 3.
- FIG. 3 illustrates some space between the toe casing and the well bore for clarity, in actual wells there is minimal clearance, and the toe casing may be tightly surrounded by the local formation, following its contour and topology through the extent of the open-hole section.
- the toe casing may have an outer diameter of between about 3" and 18" and wall thickness between .25" and 1.5". Other or multiple dimensions may, of course, be used.
- the toe casing made of the materials disclosed may realize advantages for a number of reasons. Although the tubulars made of such materials may be more costly than conventional casing, they may reduce or eliminate the need for special tooling and techniques for forcing and turning the casing. Moreover, the toe casing may produce a buoyant effect by which the casing may be lifted somewhat in the hole, reducing drag and friction by virtue of its lighter weight. Further, such materials will have a lower modulus of elasticity and density, allowing some degree of flexibility to follow more tortuous contours of the well bore. Finally, the ability to case the well along extended sections of open-hole may allow operators to produce oil and gas that would otherwise be inaccessible if the casing did not reach total depth.
- Suitable materials for the toe casing may include, for example 2000 and 7000 series aluminum alloys, titanium alloys, and metal matrix composites.
- the toe casing section(s) may be made of materials that have significantly different material properties than the conventional casing used in the rest of the well application.
- expected or example densities may be on the order of 0.283 lb /in3 (+/- 8%), with a modulus of elasticity on the order of 29.5 x 106 psi (+/- 10%).
- Presently contemplated materials for the toe casing section(s) may have densities on the order of 0.070 - .180 lb / in3, with a modulus of elasticity on the order of 4 x 106 - 19 x 106 psi. It is believed that the combination of these two material properties, that is, the density and the modulus of elasticity, combined, offer the greatest advantage in terms of the ability to adapt and conform to the wellbore, and still serve as a true casing section in the completed well.
- Example operations for use of the disclosed toe casing are summarized in FIG. 4.
- the process 60 will typically begin with drilling or otherwise accessing a well, such as during a workover operation.
- these initial operations including drilling, casing and cementing surface and intermediate sections of the well are indicated by reference numeral 62.
- Sections of the well may then be drilled to access one or more target zones, as indicated by operation 64.
- Production casing may then be run into the well, including assembly and running in of the toe casing as discussed above, and as indicated by operation 66. Again, this may entail assembling a number of sections of tubular sections made of the toe casing material.
Landscapes
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Mechanical Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
- Piles And Underground Anchors (AREA)
- Orthopedics, Nursing, And Contraception (AREA)
Abstract
Description
Claims
Priority Applications (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
BR112019016032-9A BR112019016032A2 (en) | 2017-02-06 | 2018-02-05 | FINGER COATING |
CA3052316A CA3052316A1 (en) | 2017-02-06 | 2018-02-05 | Toe casing |
EP18748361.5A EP3577302A4 (en) | 2017-02-06 | 2018-02-05 | Toe casing |
SG11201907151PA SG11201907151PA (en) | 2017-02-06 | 2018-02-05 | Toe casing |
AU2018215552A AU2018215552A1 (en) | 2017-02-06 | 2018-02-05 | Toe casing |
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US201762455216P | 2017-02-06 | 2017-02-06 | |
US62/455,216 | 2017-02-06 | ||
US15/884,996 | 2018-01-31 | ||
US15/884,996 US20180223607A1 (en) | 2017-02-06 | 2018-01-31 | Toe casing |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2018145027A1 true WO2018145027A1 (en) | 2018-08-09 |
Family
ID=63038726
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/US2018/016900 WO2018145027A1 (en) | 2017-02-06 | 2018-02-05 | Toe casing |
Country Status (7)
Country | Link |
---|---|
US (1) | US20180223607A1 (en) |
EP (1) | EP3577302A4 (en) |
AU (1) | AU2018215552A1 (en) |
BR (1) | BR112019016032A2 (en) |
CA (1) | CA3052316A1 (en) |
SG (1) | SG11201907151PA (en) |
WO (1) | WO2018145027A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112177563A (en) * | 2019-07-01 | 2021-01-05 | 中国石油化工股份有限公司 | Well completion method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4484627A (en) * | 1983-06-30 | 1984-11-27 | Atlantic Richfield Company | Well completion for electrical power transmission |
US4890675A (en) * | 1989-03-08 | 1990-01-02 | Dew Edward G | Horizontal drilling through casing window |
US5163512A (en) | 1991-08-28 | 1992-11-17 | Shell Oil Company | Multi-zone open hole completion |
US5937955A (en) | 1997-05-28 | 1999-08-17 | Atlantic Richfield Co. | Method and apparatus for sealing a well bore and sidetracking a well from the well bore |
US20020121372A1 (en) * | 1998-11-16 | 2002-09-05 | Shell Oil Co. | Isolation of subterranean zones |
US20140010098A1 (en) | 2008-05-13 | 2014-01-09 | Xirrus, Inc. | System for allocating channels in a multi-radio wireless lan array |
US20140110098A1 (en) * | 2012-10-24 | 2014-04-24 | Wwt International, Inc. | Flexible casing guide running tool |
US20150308195A1 (en) * | 2014-04-29 | 2015-10-29 | Wwt North America Holdings, Inc. | Reamer shoe attachment for flexible casing shoe |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3266577A (en) * | 1963-10-14 | 1966-08-16 | Pan American Petroleum Corp | Guide shoe |
US6401820B1 (en) * | 1998-01-24 | 2002-06-11 | Downhole Products Plc | Downhole tool |
US9702222B2 (en) * | 2015-08-26 | 2017-07-11 | Geodynamics, Inc. | Reverse flow multiple tool system and method |
-
2018
- 2018-01-31 US US15/884,996 patent/US20180223607A1/en not_active Abandoned
- 2018-02-05 SG SG11201907151PA patent/SG11201907151PA/en unknown
- 2018-02-05 BR BR112019016032-9A patent/BR112019016032A2/en not_active Application Discontinuation
- 2018-02-05 EP EP18748361.5A patent/EP3577302A4/en not_active Withdrawn
- 2018-02-05 CA CA3052316A patent/CA3052316A1/en not_active Abandoned
- 2018-02-05 AU AU2018215552A patent/AU2018215552A1/en not_active Abandoned
- 2018-02-05 WO PCT/US2018/016900 patent/WO2018145027A1/en active Application Filing
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4484627A (en) * | 1983-06-30 | 1984-11-27 | Atlantic Richfield Company | Well completion for electrical power transmission |
US4890675A (en) * | 1989-03-08 | 1990-01-02 | Dew Edward G | Horizontal drilling through casing window |
US5163512A (en) | 1991-08-28 | 1992-11-17 | Shell Oil Company | Multi-zone open hole completion |
US5937955A (en) | 1997-05-28 | 1999-08-17 | Atlantic Richfield Co. | Method and apparatus for sealing a well bore and sidetracking a well from the well bore |
US20020121372A1 (en) * | 1998-11-16 | 2002-09-05 | Shell Oil Co. | Isolation of subterranean zones |
US20140010098A1 (en) | 2008-05-13 | 2014-01-09 | Xirrus, Inc. | System for allocating channels in a multi-radio wireless lan array |
US20140110098A1 (en) * | 2012-10-24 | 2014-04-24 | Wwt International, Inc. | Flexible casing guide running tool |
US20150308195A1 (en) * | 2014-04-29 | 2015-10-29 | Wwt North America Holdings, Inc. | Reamer shoe attachment for flexible casing shoe |
Non-Patent Citations (1)
Title |
---|
See also references of EP3577302A4 * |
Also Published As
Publication number | Publication date |
---|---|
EP3577302A4 (en) | 2020-11-04 |
EP3577302A1 (en) | 2019-12-11 |
BR112019016032A2 (en) | 2020-03-31 |
SG11201907151PA (en) | 2019-09-27 |
AU2018215552A1 (en) | 2019-08-22 |
US20180223607A1 (en) | 2018-08-09 |
CA3052316A1 (en) | 2018-08-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9027673B2 (en) | Universal drilling and completion system | |
US5560435A (en) | Method and apparatus for drilling multiple offshore wells from within a single conductor string | |
US7975771B2 (en) | Method for running casing while drilling system | |
CA1240309A (en) | Method for drilling deviated wellbores | |
US20130087389A1 (en) | Fluid Partition Unit | |
US6745853B2 (en) | Methods and apparatus for open hole drilling | |
US20170175468A1 (en) | Universal drilling and completion system | |
US20120234551A1 (en) | System and Method For Drilling A Well That Extends For A Large Horizontal Distance | |
US4431068A (en) | Extended reach drilling method | |
Sperber et al. | Drilling into geothermal reservoirs | |
US20180223607A1 (en) | Toe casing | |
WO2003042488A2 (en) | Deepwater slim hole well construction | |
CA2468602C (en) | A method of forming a bore | |
US11828118B2 (en) | Method and system for multilateral quick access in oil and gas industry | |
Hjelle et al. | World-record ERD well drilled from a floating installation in the North Sea | |
US11542791B1 (en) | Systems and methods for casing drilling subsea wells | |
GB2042609A (en) | Extended Reach Earth Drilling | |
Durdyyev | New Technologies and Protocols Concerning Horizontal Well Drilling and Completion | |
Ritchie et al. | Increasing the Reach and Selectivity of Completions in Extended Reach Horizontal Wells | |
WO2010026215A2 (en) | Narrow well bore | |
Colligan | The economics of deep water | |
Terrazas et al. | Drilling with Liner on Horizontal Oil Wells | |
Tavendale | Captain horizontal development wells: a review of key design and operational issues | |
Agarwal et al. | Snake wells-a new approach to high dipping multi-layered thin reservoirs | |
Zhang et al. | Critical aspects experienced in drilling a world record extended reach well in South China Sea |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 18748361 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 3052316 Country of ref document: CA |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112019016032 Country of ref document: BR |
|
ENP | Entry into the national phase |
Ref document number: 2018215552 Country of ref document: AU Date of ref document: 20180205 Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2018748361 Country of ref document: EP |
|
ENP | Entry into the national phase |
Ref document number: 112019016032 Country of ref document: BR Kind code of ref document: A2 Effective date: 20190802 |