WO2018004340A1 - Dispositif de protection contre l'affouillement et procédé d'agencement d'un dispositif de protection contre l'affouillement sur un fond marin - Google Patents

Dispositif de protection contre l'affouillement et procédé d'agencement d'un dispositif de protection contre l'affouillement sur un fond marin Download PDF

Info

Publication number
WO2018004340A1
WO2018004340A1 PCT/NL2017/050430 NL2017050430W WO2018004340A1 WO 2018004340 A1 WO2018004340 A1 WO 2018004340A1 NL 2017050430 W NL2017050430 W NL 2017050430W WO 2018004340 A1 WO2018004340 A1 WO 2018004340A1
Authority
WO
WIPO (PCT)
Prior art keywords
cover
scour
scour protector
compartment
protector
Prior art date
Application number
PCT/NL2017/050430
Other languages
English (en)
Inventor
Herbert Fenkes
Edwin Hendrik Theodoor Maria PETERS
Original Assignee
Pile Fabrics Gmbh
Ag Industries B.V.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pile Fabrics Gmbh, Ag Industries B.V. filed Critical Pile Fabrics Gmbh
Publication of WO2018004340A1 publication Critical patent/WO2018004340A1/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0017Means for protecting offshore constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • E02B3/127Flexible prefabricated covering elements, e.g. mats, strips bags filled at the side
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0065Monopile structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines

Definitions

  • the present invention relates to scour protector and to a method of arranging a scour protector on a seabed.
  • Scour is the removal by hydrodynamic forces of granular bed material in the vicinity of coastal structures, and is a specific form of the more general term "erosion”. Scour occurs whenever the hydrodynamic bottom shear stresses exceed the sediment critical shear stress, and is therefore typically present in fast running waters with granular soil.
  • Scour imposes a significant problem for subsea structures, such as monopile bases, jackets and also pipelines that are arranged on the seabed, where the scour takes place on the downstream side.
  • a scour hole with a depth to about twice the pile diameter may result.
  • the scour can lead to partial burial of these pipelines.
  • the scour can lead to a partial burial of these pipelines, and the problems are caused when a differential scour takes place due to different soil types, possibly leaving a pipeline spanning a gap.
  • Scour is normally prevented by the arrangement of large numbers of heavy rocks, preferably of different size, near a subsea structure. These heavy rocks must be transported to the desired location at sea, which is a logistic challenge.
  • WO 95/24531 Al is considered the closest prior art, and discloses a flexible and collapsible formwork, particularly for use when casting submarine areas as well areas above water level.
  • the formwork bag is formed by a top cloth and bottom cloth. Intermediate the two cloths, a number of spacers are placed, so that the formwork forms a substantially flat formwork bag.
  • the formwork bags provide a scour protector with a rectangular shape that is e.g. used as the bottom of ferry landings. If used for scour protection of e.g. a monopile base, the offered protection would be limited.
  • An object of the present invention is to provide scour protection, that is improved relative to the prior art and wherein at least one of the above stated problems is obviated.
  • the scour protector according to the present invention comprising one or more than one cover, wherein said scour protector comprises a passage having a shape and dimensioned to accommodate a monopile base and to surround the monopile base in a sunken state of said scour protector.
  • the scour protector surrounding the monopile base Due to the scour protector surrounding the monopile base, it provides an efficient and reliable scour protection.
  • the passage having a shape and dimensioned to accommodate a monopile base and to surround the monopile base in a sunken state of said scour protector provides a scour protector that may have a flat design.
  • a scour protector with a flat design is more reliable than e.g. stacked formwork bags, and less susceptible to being moved by currents.
  • the prior art proposes rectangular formwork bags.
  • a tubular construction such as a monopile base
  • multiple rectangular formwork bags will have to be used.
  • they need to be arranged partly on top of each other, increasing the height and vulnerability of the scour protection.
  • an upper formwork bag is exposed to currents.
  • placing multiple formwork bags on the seabed is a laborious and complex task.
  • a correct placement is simple and safe, and also guarantees optimal scour protection.
  • the passage is dimensioned to closely surround the monopile base in a sunken state of said scour protector.
  • the amount of space or gaps between the scour protector and the monopile base is limited if the passage is dimensioned to closely surround the monopile base, resulting in improved scour protection.
  • Said object is furthermore achieved with the method of arranging a scour protector on a seabed according to the present invention, comprising the steps of providing a scour protector that comprises a passage having a shape and dimensioned to accommodate a monopile base, and sinking the scour protector, wherein the scour protector in a sunken state thereof surrounds a monopile base of said monopile.
  • Figure 1 is a perspective view of a monopile base of a wind turbine, wherein a scour protector is arranged on the seabed;
  • Figure 2 is a side view of a monopile base of a wind turbine that experiences scour
  • Figure 3 is a side view of a monopile base of a wind turbine that is provided with a scour protector according to the invention
  • Figures 4 and 5 show cross-sectional side views of successive steps of providing and floating a cover of a scour protector on the sea surface next to a monopile base;
  • Figure 6 shows a top view of a scour protector according to the present invention;
  • Figures 7 and 8 show cross-sectional side views of successive steps of sinking ( Figure 7) a scour protector, and arranging said scour protector on the seabed ( Figure 8);
  • Figure 9 shows a cross-sectional side view of a scour protector after being arranged on the seabed
  • Figure 10 shows three successive steps how the situation of Figure 9 is obtained after some time
  • Figure 11 shows a cross-sectional side view of a cover of the scour protector according to the present invention
  • Figure 12 shows a further preferred embodiment wherein the top surface of the cover of the scour protector is provided with a plurality of outlet openings;
  • Figures 13-15 show cross-sectional side views of successive steps of arranging a scour protector according to an alternative embodiment on a seabed;
  • Figure 16 shows a perspective view of a scour protector according to a further preferred embodiment, in a collapsed state thereof;
  • Figure 17 shows a perspective view of the scour protector of Figure 16, in an extended state thereof;
  • Figure 18 shows a perspective detailed view of a ratchet-type arrangement of the arms of the scour protector of Figures 16 and 17;
  • Figure 19 shows a perspective view conform Figure 17, wherein the cover is filled with a filling medium
  • Figures 20-25 show successive steps of a first installation method of the scour protector of Figures 16-19;
  • Figures 26 and 27 show successive steps of a second installation method of the scour protector of Figures 16-19.
  • the scour protector 1 of Figures 1-15 comprises one or more than one cover 2, wherein said cover 2 is capable of floating when filled with air.
  • the cover 2 may have a state wherein said cover 2 is configured to float on water ( Figure 5).
  • Figure 5 In this floating state, the one or more than one cover 2 may be easily arranged at a desired position, and possibly connected to further covers 2.
  • initial floating of the cover 2 is not essential to provide a subsea scour protection in a final stage, the skilled person will understand that this capability to float may provide easy and comfortable placement of the scour protector around e.g. a monopile base.
  • a scour protector 1 comprising four connected covers 2 is arranged on the seabed 66 and around a subsea structure 50.
  • the subsea structure 50 is a monopile base 52 that supports a wind turbine 54.
  • Said monopile base 52 has a cable guide 56 through which an electricity cable 58 is guided to the seabed 66.
  • electricity cable 58 is, similar to a pipeline, also vulnerable to scour, and may be protected by a further scour protector 1 ' .
  • the further scour protector 1 ' shown in Figure 1 comprises a single cover 2, but the skilled person will understand that multiple covers 2 may be connected with each other and form a chain of covers 2 that may be arranged over an electricity cable 58 or a (not shown) pipeline.
  • the scour protector 1 When the scour protector 1 is arranged on the seabed 66 as shown in Figure 1 , it provides protection against scour, so that a scour hole 66 as shown in Figure 2 may be prevented. Over time, the scour protector 1 will experience a small-scale scour effect near its edges 8, and because the covers 2 are preferably substantially flexible, these edges 8 of the cover 2 will be buried to some extent, as shown in Figure 3. This process will be further elucidated using Figures 9 and 10. Once the situation shown in Figure 3 is obtained, the scour protector 1 offers optimum scour protection to the subsea structure 50.
  • the cover 2 may be floating if it is made of a mass density lower than the mass density of water, it may also float because air or another fluid is introduced into the cover 2.
  • said cover 2 comprises a compartment 10 with at least one inlet opening 12.
  • the cover 2 forms a mattress.
  • the covers 2, which are preferable made of textile, may be transported in a coiled state, i.e. in the form of a roll. When the cover 2 is filled with air, it automatically expands and will uncoil into an elongate rectangular shape. Once filled with air, the cover 2 is capable of floating on the sea surface 64 and may be arranged near a subsea structure 50, such as monopile base 52, that partly extends above the sea surface 64. The part of the subsea structure 50 that extends above the sea surface 64 is accommodated in an accommodation 28 of said cover 2.
  • the accommodation 28 of the cover 2 is dimensioned to accommodate and surround at least a part of a subsea structure 50 in a sunken state of said cover 2. As shown in Figure 1, also the cable guide 56 is accommodated in accommodation 28.
  • the scour protector 1 comprises a passage having a shape and dimensioned to accommodate a monopile base to surround the monopile base in a sunken state of said scour protector 1.
  • two accommodations 28 of connected covers 2 form the passage of the scour protector 1.
  • the passage preferably closely surrounds the monopile base in the sunken state thereof.
  • the step of Figures 4 and 5 is preferably executed when the monopile base 52 is being installed and still only extends for a limited height above the sea surface 64.
  • the wind turbine 54 may not have been arranged yet.
  • the scour protector 1 may be arranged on the seabed 66, said scour protector 1 having an accommodation dimensioned to accommodate a subsea structure 50.
  • This subsea structure 50 for instance a monopile base 52 may be arranged through said accommodation after the scour protector has been arranged on the seabed 66.
  • this (not shown) method puts high demands on the exact positioning of the scour protector 1 and aligning the subsea structure 50 with the accommodation of said subsea structure 50, it is preferred to arrange the scour protector 1 around and/or against a subsea structure 50 that is already arranged on the sea bed 66.
  • the accommodation 28 of the cover 2 of the scour protector 1 according to the invention also allows this scour protector 1 to be arranged easily around piles of other types of foundations, such as a tripod or tri-pile foundation.
  • couples of covers 2 are connected with at least one cover connector 26 when they are floating on the sea surface 64.
  • Each cover 2 preferably comprises multiple cover connectors 26.
  • the next step is sinking the at least one cover 2, i.e. the scour protector 1, into the sea ( Figure 7).
  • the covers 2 comprise a compartment 10 with at least one inlet opening 12, wherein said compartment 10 is fillable with a filling medium 42 that has a mass density equal to or lower than the mass density of water.
  • the compartment 10 of the cover 2 is filled with water as filling medium 42.
  • Outlet opening 14 may comprise a valve 16, that is preferably a pressure valve.
  • the filling medium 42 may also comprise water with suspended particles in order to increase the mass density of this suspension, and thereby accelerate the sinking process.
  • multiple outlet openings 14 of said compartment 10 are arranged on a top surface 4 of said cover 2, said multiple outlet openings 14 comprising valves 16 configured for evenly releasing fluid 40, 42 out of the compartment 10 of said cover 2.
  • a preferred step of further increasing the weight of at least one cover 2 of said scour protector 1 may be executed.
  • This step comprises at least partially replacing the filling medium 42 water in said compartment 10 with a further filling medium 44 that has a higher mass density than the filling medium 42 used for sinking said cover 2.
  • Said further filling medium 44 preferably comprises sand.
  • compartment 10 is only partially filled with sand as the further filling medium 42, thereby maintaining flexibility of said cover 2. Flexibility of the cover 2 provides an increased scour protection, as will be explained using Figures 9 and 10.
  • edges 8 of cover 2 are preferably tapered, so that the scour protector 1 is more aerodynamic and less susceptible for fluid flow. Furthermore, tapered edges 8 increase the flexibility of said edges 8, contributing to the effect shown in Figure 10.
  • cover 2 comprises a bottom 6 and a top surface 4 with a connector 18 arranged in between, said connector 18 having a predetermined length defining the thickness of the cover 2 when in use.
  • a filling medium 40, 42, 44 one or more than one connector 18 prevent bulging out of the scour protector 1.
  • the connectors 18 may theoretically be rigid bars, it is preferred that the connectors 18 are capable of being rolled up together with the cover 2. As flaps could interfere with certain types of filling medium, especially sand, it is preferred that the connectors are strings 20.
  • the strings 20 may comprise one or more than one fiber 22, and preferably a plurality of fibers 22. If said fibers 22 comprise glass fibers, this adds to the weight of the scour protector 1.
  • the strings 20 of the connector 18 preferably comprise a bundle, and multiple connectors 18 are arranged in a pattern in the compartment 10 of the cover 2, wherein this pattern leaves channels 24 for said filling medium, which is especially advantageous for the further filling medium 44 that preferably comprises sand.
  • the cover 2 is again preferably made out of textile, wherein the top surface 4 comprises pores 5, and wherein the bottom surface 6 comprises pores 7. Due to the pores 5, 7, the top and bottom surfaces 4, 6 are permeable for water and air.
  • the covers 2 of the scour protector 1 are preferably continuously pressurized with air, that partly escapes from the compartments 10 of the covers 2 through the pores 5, 7, as can be seen in Figure 13. It is noted that substantially continuously pressurizing means that a substantially continuous overpressure is maintained, but the skilled person will understand that small interruptions in pressurizing will not negatively influence the floatability of the cover 2.
  • a preferred step of further increasing the weight of at least one cover 2 of said scour protector 1 may be executed. This step comprises at least partially replacing the filling medium 42 water in said compartment 10 with a further filling medium 44 that has a higher mass density than the filling medium 42 used for sinking said cover 2, similar to Figure 8.
  • said further filling medium 44 comprises sand with seeds of water plants.
  • the water plants 72 such as sea weed, may grow through the pores 5 in the top surface 4 of the cover 2.
  • the plants 72 also influence the flow of water around the subsea structure 50. The water flow is reduced, and therefore contributes to the scour protection.
  • FIG. 16-27 An alternative and further preferred embodiment of a scour protector according to the invention is shown in Figures 16-27.
  • the scour protector 101 comprises a ring 102 that is dimensioned to surround the monopile base 52 in a sunken state of said scour protector 101.
  • the ring 102 has an
  • accommodation 103 that defines the passage having a shape and dimensioned to accommodate and surround the monopile base 52 in a sunken state of said scour protector 101.
  • the scour protector 101 further comprises a plurality of arms 104 that are configured to radially extend from said ring 102 in a sunken state of said scour protector 101, wherein one or more than one cover 105 is connected to one or more than one of said plurality of arms 104. When the arms 104 are extended, the cover 105 preferably spans between neighboring arms 104.
  • Figure 16 shows the scour protector 101 in a collapsed state, wherein it may be easily transported on board of a ship and arranged around a monopile base 52.
  • Perspective views of an extended state of said scour protector 101, wherein the plurality of arms 103 radially extend from said ring 102 are shown in Figures 17 and 19.
  • the cover 105 is made transparent in order to show the plurality of arms 104.
  • the cover 105 may be a sheet, such as a fabric or cloth, or alternatively a mattress-type cover as described in relation to the embodiment of Figures 1-15.
  • a cover 105 that is capable of floating when filled with air is preferred.
  • the arms 104 are arranged on the ring 102 with a ratchet-type arrangement 106 that is configured to allow a downward movement of the arms 104 relative to the ring 102 and to prevent an upward movement of the arms 104 relative to the ring 102.
  • a ratchet-type arrangement 106 that is configured to allow a downward movement of the arms 104 relative to the ring 102 and to prevent an upward movement of the arms 104 relative to the ring 102.
  • the scour protector 101 is shown in its sunken and active state.
  • the arms 104 extend radially from the ring 102 that defines the accommodation 103 for
  • the cover 105 is filled with a filling medium, preferably water and/or sand via inlet opening 106. Air or other medium that may have been in the cover prior to the filling medium is introduced, may leave the cover via outlet opening 107.
  • a filling medium preferably water and/or sand via inlet opening 106. Air or other medium that may have been in the cover prior to the filling medium is introduced, may leave the cover via outlet opening 107.
  • the principle of filling the cover 105, as well as the construction of the cover with connectors 108 is identical to the embodiment shown in Figures 1-15.
  • Figures 20-27 show simplified representations of the scour protector shown in Figures 16-19, wherein only two oppositely arranged arms 104 are shown.
  • the step of placing the accommodation 103 of the scour protector 101, that defines the passage, around a subsea structure, i.e. the monopile base 52, is preferably executed when the monopile base 52 is installed and only extends for a limited height above the sea surface 64.
  • a wind turbine may not have been arranged yet.
  • said ring 102 preferably comprises at least two ring parts 102a, 102b.
  • the ring parts 102a, 102b are pivotally connected.
  • Figures 20-25 show successive steps of a first installation method of the scour protector 101.
  • the scour protector 101 is arranged around the monopile base 52, wherein the monopile base 52 is accommodated in the accommodation 103 defined by the ring 102. Afterwards, the arms 104 are radially extended by pivoting them relative to the ring 102
  • the water as filling medium may be replaced by a further filling medium, such as sand.
  • the ratchet-type arrangement 106 shown in Figure 18 guarantees that the scour protector 101 is safely and reliably arranged on the seabed 66. When currents result in erosion below an arm 104, it may move downward - see left arm 104 in Figure 25. The ratchet- type arrangement 106 prevents an upward movement of said arm 104, and in this way the scour protector 101 will gradually dig itself into the seabed 66. If, on the other hand, sand is displaced by currents on top of the scour protector 101, this will also increase the stability of the scour protector 101 - see right arm 104 in Figure 25..
  • FIGS 26 and 27 show successive steps of a second installation method of the scour protector 101.
  • This second installation method differs from the first installation method described above, in that the scour protector 101 is first immersed below the sea level 64 in its collapsed state, and only during or after sinking the arms 104 are moved to their radially extending state.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Revetment (AREA)

Abstract

Un dispositif de protection contre l'affouillement comprend un ou plusieurs couvercles, ledit dispositif de protection contre l'affouillement comprenant un passage ayant une certaine forme et dimensionné pour recevoir une base à monopieu et pour entourer la base à monopieu dans un état enfoncé dudit dispositif de protection contre l'affouillement. En outre, l'invention porte sur un procédé associé d'agencement d'un dispositif de protection contre l'affouillement sur un fond marin, comprenant les étapes consistant à fournir un dispositif de protection contre l'affouillement qui comprend un passage ayant une forme permettant de recevoir une base à monopieu et dimensionné pour cela, et à enfoncer le dispositif de protection contre l'affouillement, le dispositif de protection contre l'affouillement entourant, dans un état enfoncé, la base à monopieu.
PCT/NL2017/050430 2016-06-28 2017-06-28 Dispositif de protection contre l'affouillement et procédé d'agencement d'un dispositif de protection contre l'affouillement sur un fond marin WO2018004340A1 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL2017059 2016-06-28
NL2017059A NL2017059B1 (en) 2016-06-28 2016-06-28 Scour protector and method of arranging a scour protector on a seabed

Publications (1)

Publication Number Publication Date
WO2018004340A1 true WO2018004340A1 (fr) 2018-01-04

Family

ID=56990923

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/NL2017/050430 WO2018004340A1 (fr) 2016-06-28 2017-06-28 Dispositif de protection contre l'affouillement et procédé d'agencement d'un dispositif de protection contre l'affouillement sur un fond marin

Country Status (2)

Country Link
NL (1) NL2017059B1 (fr)
WO (1) WO2018004340A1 (fr)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029691A (zh) * 2019-05-08 2019-07-19 天津大学前沿技术研究院有限公司 一种海上风电基础防冲刷层自动安装结构及安装方法
CN113186986A (zh) * 2021-05-18 2021-07-30 中国华能集团清洁能源技术研究院有限公司 一种海上风电单桩基础冲刷防护装置
CN114775527A (zh) * 2022-04-20 2022-07-22 广东省水利水电第三工程局有限公司 一种超深动水区护岸沉放摊铺板
JP7408498B2 (ja) 2020-06-30 2024-01-05 鹿島建設株式会社 洗堀抑制ユニット、水中植物再生方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1995024531A1 (fr) 1994-03-08 1995-09-14 Henry Andreassen Coffrage souple
GB2418948A (en) 2004-10-08 2006-04-12 Andrew Mountain Scour protection using fabric formwork to resemble rock armour protection
EP2270283A2 (fr) * 2008-03-14 2011-01-05 Deok-Rae Jo Appareil permettant de se passer d'affouillement pour des fondations sur piles
US20120128436A1 (en) * 2010-11-23 2012-05-24 Technip France Anti-scour disk and method
GB2497581A (en) 2011-12-16 2013-06-19 Andrew Mountain Internal sheet mesh reinforced fabric formwork scour protection apparatus
EP2767637A1 (fr) * 2013-02-14 2014-08-20 BEKA MareSOLUTIONs GmbH Dispositif constitué d'un matériau flexible et plat maintenu par une structure porteuse pour la protection contre l'affouillement et procédé de fabrication d'une structure porteuse
WO2015129053A1 (fr) * 2014-02-26 2015-09-03 Kyowa Co., Ltd. Protection de pieu

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9334616B2 (en) * 2011-10-31 2016-05-10 Gary E. Abeles Portable water-inflatable barrier with traversing steps

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1995024531A1 (fr) 1994-03-08 1995-09-14 Henry Andreassen Coffrage souple
GB2418948A (en) 2004-10-08 2006-04-12 Andrew Mountain Scour protection using fabric formwork to resemble rock armour protection
EP2270283A2 (fr) * 2008-03-14 2011-01-05 Deok-Rae Jo Appareil permettant de se passer d'affouillement pour des fondations sur piles
US20120128436A1 (en) * 2010-11-23 2012-05-24 Technip France Anti-scour disk and method
GB2497581A (en) 2011-12-16 2013-06-19 Andrew Mountain Internal sheet mesh reinforced fabric formwork scour protection apparatus
EP2767637A1 (fr) * 2013-02-14 2014-08-20 BEKA MareSOLUTIONs GmbH Dispositif constitué d'un matériau flexible et plat maintenu par une structure porteuse pour la protection contre l'affouillement et procédé de fabrication d'une structure porteuse
WO2015129053A1 (fr) * 2014-02-26 2015-09-03 Kyowa Co., Ltd. Protection de pieu

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029691A (zh) * 2019-05-08 2019-07-19 天津大学前沿技术研究院有限公司 一种海上风电基础防冲刷层自动安装结构及安装方法
JP7408498B2 (ja) 2020-06-30 2024-01-05 鹿島建設株式会社 洗堀抑制ユニット、水中植物再生方法
CN113186986A (zh) * 2021-05-18 2021-07-30 中国华能集团清洁能源技术研究院有限公司 一种海上风电单桩基础冲刷防护装置
CN113186986B (zh) * 2021-05-18 2022-11-22 中国华能集团清洁能源技术研究院有限公司 一种海上风电单桩基础冲刷防护装置
CN114775527A (zh) * 2022-04-20 2022-07-22 广东省水利水电第三工程局有限公司 一种超深动水区护岸沉放摊铺板

Also Published As

Publication number Publication date
NL2017059B1 (en) 2018-01-05

Similar Documents

Publication Publication Date Title
EP3495563B1 (fr) Système d'installation de matériau antiaffouillement dans une fondation marine autoflottante, procédés et utilisations associées au dit système
WO2018004340A1 (fr) Dispositif de protection contre l'affouillement et procédé d'agencement d'un dispositif de protection contre l'affouillement sur un fond marin
EP2559814B1 (fr) Fondation par gravité
EP2171159B1 (fr) Dispositif et procédé pour une structure de tour marine
AU2007205290B2 (en) Mooring system
WO2005038146A1 (fr) Fondations marines
WO2010032027A2 (fr) Procédé de localisation d'une structure sous-marine pour déploiement
US4486125A (en) Modular arctic structures system
US20230264789A1 (en) Method for installing at least one mooring line of a floating installation in a body of water and associated floating installation
TWI807197B (zh) 用於組裝離岸風力渦輪機的方法、用於離岸風力渦輪機的塔基及離岸風力渦輪機
KR102480830B1 (ko) 해양 에너지 하베스터를 위한 프레임
CN115581212A (zh) 一种离岸养殖系统及其设计方法
US20060078385A1 (en) Apparatus for creating a local reduction in wave height
US20130074758A1 (en) Anchoring apparatus for wave energy converters
KR101246709B1 (ko) 어류서식을 위한 바다목장을 갖는 내파성 인공 낚시섬
GB2475688A (en) An anchor having a number of floodable chambers
KR20000018384A (ko) 반원형 매트를 이용한 공기 부양식 방파제
WO2018056831A1 (fr) Appareil de culture immergé et procédé d'élévation ou d'abaissement de celui-ci
JP2024058259A (ja) 洗掘防止構造及びその構築方法
CN214143832U (zh) 一种水下桩基础冲刷防护装置
CN219012775U (zh) 用于海上设施的基础以及海上设施
CN104878793B (zh) 沉管隧道基床气囊起浮式土工布覆盖防淤系统及方法
WO2015126237A1 (fr) Structure de support en mer et ses procédés d'installation
AU2013205150A1 (en) Containment system

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17739341

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 17739341

Country of ref document: EP

Kind code of ref document: A1