WO2013067120A1 - Adding and shedding loads using load levels to determine timing - Google Patents
Adding and shedding loads using load levels to determine timing Download PDFInfo
- Publication number
- WO2013067120A1 WO2013067120A1 PCT/US2012/062967 US2012062967W WO2013067120A1 WO 2013067120 A1 WO2013067120 A1 WO 2013067120A1 US 2012062967 W US2012062967 W US 2012062967W WO 2013067120 A1 WO2013067120 A1 WO 2013067120A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- generator
- loads
- load
- amount
- time
- Prior art date
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/12—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
- H02J3/14—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2310/00—The network for supplying or distributing electric power characterised by its spatial reach or by the load
- H02J2310/10—The network having a local or delimited stationary reach
- H02J2310/12—The local stationary network supplying a household or a building
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J9/00—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
- H02J9/04—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/248—UPS systems or standby or emergency generators
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Control Of Eletrric Generators (AREA)
Abstract
Some embodiments relate to a method of adding and shedding loads that are connected to a generator. The method includes determining whether a plurality of loads is being supplied with power by the generator and then determining the total load that the generator is supplying to the plurality of loads. The method further includes determining whether to change a number of the loads in the plurality of loads based on the amount of load L that is being supplied by the generator. The method further includes determining an amount of time T in which to change the number of loads in the plurality of loads based on the amount of load that is being supplied by the generator.
Description
ADDING AND SHEDDING LOADS USING
LOAD LEVELS TO DETERMINE TIMING
CLAIM OF PRIORITY
This application claims the benefit of priority of U.S. Patent Application Serial No. 13/289,131, entitled "ADDING AND SHEDDING LOADS USING LOAD LEVELS TO DETERMINE TIMING," filed on November 4, 2011, which application is incorporated by reference herein in its entirety.
TECHNICAL FIELD
Embodiments pertain to a system and method for adding and shedding loads.
BACKGROUND
The process of prioritizing loads that are connected to a power supply that has limited capacity is typically referred as load shedding. As an example, power may be supplied by a standby generator where load shedding is required because the standby generator has a capacity that is less than the requirements of the entire attached load.
Water heaters and air conditioners are among the commonly utilized devices that are powered loads by a power source (e.g., a generator). These loads may need to be shed when a residence is being supplied by a limited capacity generator. Existing load shedding systems typically prioritize each load and then determine if the limited capacity power source is able to supply the loads before adding each load. If the limited capacity power source becomes overloaded, then the load control system will remove one or more loads to allow the power source to continue supplying power to the more important connected loads.
Utilizing a load shedding system may allow a smaller standby generator to be installed thereby decreasing the generator costs that are associated with powering a facility. In addition, load shedding may decrease costs by limiting the peak demand for power during certain times of the day because such systems
often allow a power generation utility to keep a less efficient generation plant offline and then pass the savings on to the customer (i.e., the generator user).
One of the drawbacks with existing load shedding systems is that although custom-designed and configured load shedding schemes work well under some conditions; many load shedding systems do not work well when operating a variety of loads under a variety of conditions.
One of the biggest challenges for a load shedding system is a high- priority switching load. In one example scenario, a high-priority switching load may be deactivated which allows less important loads to be added. Therefore, once the high-priority switching load is eventually turned on, the power source becomes overloaded. The load shedding system must then shed several loads before the load that is actually causing the overload is removed. The additional time that is required to shed multiple loads increases the likelihood of the power source becoming overloaded for an undesirable period of time. Although many existing load shedding systems are customized in an attempt to minimize unintended power source dropouts, such systems are still often unable to adequately handle high-priority switching loads.
Another drawback with conventional load shedding systems is that in some scenarios, all of the loads may not be drawing power from the generator during an overload condition. As an example, six loads may be activated by the system even though only two of the loads are actually drawing power. As a result, when an overload occurs after all these loads have been added, the system may have to take unnecessary time to shed as many as five loads before actual load on the power source decreases at all. This increase in time to shed the appropriate load could result in the power source going offline.
Load shedding systems must also typically be carefully configured in order to work in each application because standard load shedding logic does not accurately match the load profile of a typical power source or a typical motor load. As a result, these existing systems are typically unable to start large motors that would otherwise typically lie within the starting capabilities of the generator. Configuring a typical load shedding system to permit starting a large motor will typically result in inadequate protection for the generator.
BRIEF DESCRIPTION OF THE DRAWINGS
FIG. 1 illustrates an example load shedding system.
FIG. 2 illustrates an example engine driven generator that may be used with the load shedding system shown in FIG. 1.
FIG. 3 illustrates an example of how time T varies when a given load is added based on the generator load L and the available generator capacity at a point in time as compared to a conventional method of adding loads.
FIGS. 4 and 5 illustrate an example of how time T varies for a given load being shed based on the correspond overload of a generator as compared to a conventional method of shedding loads.
FIG. 6A shows conventional under- frequency load shedding techniques handling motor starting and overload conditions.
FIG. 6B shows under-frequency load shedding techniques handling motor starting and overload conditions in accordance with some example embodiments.
FIG. 7 illustrates decreasing the time to shed subsequent loads after a previous load shedding operation in accordance with some example
embodiments.
FIG. 8 is a block diagram that illustrates a diagrammatic representation of a machine in the example form of a computer system 400 within which a set of instructions for causing the machine to perform any one or more of the methodologies discussed herein may be executed.
DETAILED DESCRIPTION
The following description and the drawings sufficiently illustrate specific embodiments to enable those skilled in the art to practice them. Other embodiments may incorporate structural, logical, electrical, process, and other changes. Portions and features of some embodiments may be included in, or substituted for, those of other embodiments. Embodiments set forth in the claims encompass all available equivalents of those claims.
A method of adding and shedding loads LI, L2, L3, L4 that are connected to a generator 12 will now be described with reference to FIG. 1. The method includes determining whether a plurality of loads LI, L2, L3, L4 is being
supplied with power by the generator 12 and then determining the total load that the generator 12 is supplying to the plurality of loads LI , L2, L3, L4.
The method further includes determining whether to change a number of the loads in the plurality of loads LI , L2, L3, L4 based on the amount of load L that is being supplied by the generator 12. As shown in FIGS. 3-6, the method further includes determining an amount of time T in which to change the number of loads in the plurality of loads based on the amount of load L that is being supplied by the generator 12.
In some embodiments, determining whether a plurality of loads LI , L2, L3, L4 are being supplied with power by the generator 12 may include monitoring the position of an automatic transfer switch 13. It should be noted that the plurality of loads LI, L2, L3, L4 are being supplied with power by generator 12 when the automatic transfer switch 13 is in an emergency position.
In alternative embodiments, determining whether a plurality of loads LI , L2, L3, L4 are being supplied with power by the generator 12 may include measuring a position of a throttle 17 that is part of the generator 12 (see e.g., FIG. 2). It should be noted that the generator 12 may be established as supplying power to the plurality of loads LI, L2, L3, L4 when the throttle 17 position is in a position other than a "no load" position.
In still other embodiments, determining whether a plurality of loads LI,
L2, L3, L4 are being supplied with power by the generator 12 may include monitoring the generator load L. As examples, monitoring the generator load L may be done by (i) measuring the generator 12 operating frequency; (ii) measuring the generator 12 operating voltage; and/or (iii) measuring the generator 12 current.
In addition, determining the total load L that the generator 12 is supplying to the plurality of loads LI , L2, L3 , L4 may include (i) measuring the generator operating frequency; (ii) measuring the generator operating voltage; and/or (iii) measuring the generator current.
In some embodiments, determining the total load L that the generator 12 is supplying to the plurality of loads LI , L2, L3, L4 includes determining the output torque of a prime mover (i.e., an engine) of the generator 12. The output torque may be calculated by (i) measuring fuel injection time duration 18 within the generator 12; (ii) measuring the intake manifold 16 pressure within the
generator 12; and/or (iii) measuring a position of a throttle 17 within the generator 12. It should be noted the output torque may be calculated for spark- ignited and compression-ignited engines as well as other types of prime movers. INCREASING THE NUMBER OF LOADS
In some embodiments, determining an amount of time T in which to change the number of loads in the plurality of loads LI , L2, L3, L4 may be based on the amount of load L that is being supplied by the generator 12 includes increasing the number of loads based on an available load capacity of the generator 12.
As used herein, the available load capacity of the generator 12 is the difference between the maximum loading threshold of the generator 12 and a load the generator 12 is supplying at a particular point in time. As examples, the maximum loading threshold of the generator may be adjustable by a user via a user interface 20 (see FIG. 1), and/or may be based on a rating determined by a manufacturer of the generator 12. As examples, the user interface 20 may be part of a load control module 14, automatic transfer switch 13, generator controller 15 or a stand-alone device.
FIG. 3 illustrates an example of how time T varies when a given load is added based on the generator load L and the available generator capacity at a point in time as compared to a conventional method of adding loads. The amount of time T to add a load is varied based on the available generator capacity. As the available generator capacity increases, the time T to add a load decreases.
Therefore, the method allows generator loads to be added more quickly when there is substantial available generator capacity and more slowly when there is limited available generator capacity. This time adjustment provides (i) improved protection to the generator as the generator approaches maximum capacity; and (ii) power load as quickly as possible when there is minimal generator loading (as compared to conventional methods).
DECREASING THE NUMBER OF LOADS
In some embodiments, determining an amount of time T in which to change the number of loads in the plurality of loads LI , L2, L3, L4 may be based
on the amount of load L that is being supplied by the generator 12 includes decreasing the number of loads based on an overload of the generator 12.
As used herein, the overload of the generator 12 is a difference between a generator load at a particular point in time and a maximum loading threshold of the generator. As examples, the maximum loading threshold of the generator may be adjustable by a user interface 20 (see FIG. 1), and/or may be based on a rating determined by a manufacturer of the generator 12.
FIGS. 4 and 5 illustrate an example of how time T varies for a given load being shed based on the corresponding overload of the generator 12 as compared to a conventional method of shedding loads. The amount of time T to shed a load is varied based on the overload of the generator 12. As the overload increases, the time T to shed a load decreases.
Therefore, the method allows generator loads to be shed more quickly when there is substantial generator overload and more slowly when generator 12 is not as heavily overloaded. This time adjustment (i) provides improved protection to the generator 12 when there is substantial generator overload by shedding loads more quickly (see e.g., FIG. 4); and (ii) permits motor starting (see e.g., FIG. 5) (as compared to conventional methods).
As shown in FIG. 6B, determining an amount of time in which to change the number of loads in the plurality of loads based on the amount of load that is being supplied by the generator includes decreasing the number of loads based on generator operating frequency. In some embodiments, the amount of time to decrease the number of loads will decrease as the generator operating frequency decreases.
As shown in FIG. 6A, conventional under-frequency load shedding techniques shed load after the generator has remained below a fixed threshold for a specified period of time. This type of operating parameter results in poor power quality being supplied to loads and could also result in unintended shedding during motor starting, especially when using heavily loaded large AC motors.
Comparing FIGS. 6A and 6B demonstrates how the methods described herein may improve on conventional under frequency load shedding techniques. FIG. 6A illustrates conventional under frequency load shedding techniques for a given motor starting load and a given overload while FIG. 6B illustrates the
under frequency load shedding techniques described herein for the same motor starting load and the same overload.
It should be noted that while FIGS 3, 4, 5 and 6 illustrate linear time/load curves, other embodiments are contemplated where these curves may be non- linear. The shape of these curves will depend on a variety of design
considerations.
FIGS. 1 and 7 illustrate a method of adding and shedding loads that are connected to a generator in accordance with another example embodiment. The method includes determining whether a plurality of loads LI, L2, L3, L4 is being supplied with power by the generator 12 and determining the load L that the generator is supplying to the plurality of loads LI , L2, L3, L4.
The method further includes determining whether to change a number of the loads in the plurality of loads LI , L2, L3, L4 based on the amount of load that is being supplied by the generator 12 and changing the number of loads in the plurality of loads LI , L2, L3, L4. The method further includes determining an amount of time in which to further change the number of loads where the amount of time is determined by whether the number of loads increases or decreases during the previous change of the number of loads.
In some embodiments, determining an amount of time in which to further change the number of loads in the plurality of loads LI , L2, L3, L4 includes increasing the amount of time to decrease the number of loads when the previous change of the number of loads increased the number of loads.
Other embodiments are contemplated where determining an amount of time in which to further change the number of loads in the plurality of loads includes decreasing the amount of time to decrease the number of loads when the previous change of the number of loads decreased the number of loads.
It should be noted that embodiments are also contemplated where determining an amount of time in which to further change the number of loads in the plurality of loads LI , L2, L3, L4 includes decreasing the amount of time to decrease the number of loads when the previous change of the number of loads decreased the number of loads.
In still other embodiments, determining an amount of time in which to further change the number of loads in the plurality of loads LI, L2, L3, L4
includes increasing the amount of time to increase the number of loads when the previous change of the number of loads decreased the number of loads.
FIG. 7 illustrates decreasing the time to shed subsequent loads after a previous load shedding operation. In the example scenario that is illustrated in FIG. 7, three of six loads are not demanding power from the generator which results in no decrease to the generator load when these loads are shed. The subsequent decreases in the time to shed each load allows these loads to be shed before there is significant degradation to the quality of power being supplied to these loads.
The methods described herein may permit load control operation that work well when there a variety of loads that operate under a variety of conditions. In addition, the methods may be able to more adequately handle high-priority switching loads. The methods may also reduce the time to shed multiple loads more quickly until the actual load on the power source decreases. This decrease in time to shed the appropriate load may allow the power source to remain online.
Example Machine Architecture
FIG. 8 is a block diagram that illustrates a diagrammatic representation of a machine in the example form of a computer system 400 within which a set of instructions for causing the machine to perform any one or more of the methodologies discussed herein may be executed. In some embodiments, the computer system 400 may operate in the capacity of a server or a client machine in a server-client network environment, or as a peer machine in a peer-to-peer (or distributed) network environment.
The computer system 400 may be a server computer, a client computer, a personal computer (PC), a tablet PC, a set-top box (STB), a Personal Digital Assistant (PDA), a cellular telephone, a Web appliance, a network router, switch or bridge, or any machine capable of executing a set of instructions (sequential or otherwise) that specify actions to be taken by that machine. Further, while only a single machine is illustrated, the term "machine" shall also be taken to include any collection of machines that individually or jointly execute a set (or multiple sets) of instructions to perform any one or more of the methodologies discussed herein.
The example computer system 400 may include a processor 460 (e.g., a central processing unit (CPU), a graphics processing unit (GPU) or both), a main memory 470 and a static memory 480, all of which communicate with each other via a bus 408. The computer system 400 may further include a video display unit 410 (e.g., liquid crystal displays (LCD) or cathode ray tube (CRT)). The computer system 400 also may include an alphanumeric input device 420 (e.g., a keyboard), a cursor control device 430 (e.g., a mouse), a disk drive unit 440, a signal generation device 450 (e.g., a speaker), and a network interface device 490.
The disk drive unit 440 may include a machine -readable medium 422 on which is stored one or more sets of instructions (e.g., software 424) embodying any one or more of the methodologies or functions described herein. The software 424 may also reside, completely or at least partially, within the main memory 470 and/or within the processor 460 during execution thereof by the computer system 400, the main memory 470 and the processor 460 also constituting machine-readable media. It should be noted that the software 424 may further be transmitted or received over a network (e.g., network 380 in FIG. 3) via the network interface device 490.
While the machine -readable medium 422 is shown in an example embodiment to be a single medium, the term "machine -readable medium" should be taken to include a single medium or multiple media (e.g., a centralized or distributed database, and/or associated caches and servers) that store the one or more sets of instructions. The term "machine-readable medium" shall also be taken to include any medium that is capable of storing, encoding or carrying a set of instructions for execution by the machine and that cause the machine to perform any one or more of example embodiments described herein. The term "machine -readable medium" shall accordingly be taken to include, but not be limited to, solid-state memories and optical and magnetic media.
Thus, a computerized method and system are described herein. Although the present invention has been described with reference to specific example embodiments, it will be evident that various modifications and changes may be made to these embodiments without departing from the invention. Accordingly, the specification and drawings are to be regarded in an illustrative rather than a restrictive sense.
The Abstract is provided to comply with 37 C.F.R. Section 1.72(b) requiring an abstract that will allow the reader to ascertain the nature and gist of the technical disclosure. It is submitted with the understanding that it will not be used to limit or interpret the scope or meaning of the claims. The following claims are hereby incorporated into the detailed description, with each claim standing on its own as a separate embodiment.
Claims
1. A method of adding and shedding loads that are connected to a generator, the method comprising:
determining whether a plurality of loads is being supplied with power by the generator;
determining the load that the generator is supplying to the plurality of loads;
determining whether to change a number of the loads in the plurality of loads based on the amount of load that is being supplied by the generator; and determining an amount of time in which to change the number of loads in the plurality of loads based on the amount of load that is being supplied by the generator.
2. The method of claim 1 , wherein determining whether a plurality of loads are being supplied with power by the generator includes monitoring the position of an automatic transfer switch.
3. The method of claim 1 , wherein determining whether a plurality of loads are being supplied with power by the generator includes monitoring the generator load.
4. The method of claim 3, wherein monitoring the generator load includes measuring the generator operating frequency.
5. The method of claim 3, wherein monitoring the generator load includes monitoring the torque of a prime mover within the generator, wherein monitoring the torque of a prime mover within the generator includes measuring fuel injection time duration within the generator, wherein monitoring the torque of a prime mover within the generator includes measuring the intake manifold pressure within the generator,, wherein monitoring the torque of a prime mover within the generator includes measuring a position of a throttle within the generator.
6. The method of claim 1 , wherein determining the load that the generator is supplying to the plurality of loads includes measuring the current that the generator is supplying to the plurality of loads, wherein determining the load that the generator is supplying to the plurality of loads includes measuring the generator operating frequency, wherein determining the load that the generator is supplying to the plurality of loads includes measuring the generator operating voltage.
7. The method of claim 1 , wherein determining an amount of time in which to change the number of loads in the plurality of loads based on the amount of load that is being supplied by the generator includes increasing the number of loads based on an available load capacity of the generator.
8. The method of claim 7, wherein the available load capacity of the generator is a difference between a maximum loading threshold of the generator and a generator load at a particular point in time.
9. The method of claim 8, wherein the maximum loading threshold of the generator is adjustable by a user.
10. The method of claim 8, wherein the maximum loading threshold of the generator is based on a rating provided by a manufacturer of the generator.
11. The method of claim 8, wherein the amount of time to increase the number of loads will increase as the available load capacity decreases.
12. The method of claim 1 , wherein determining an amount of time in which to change the number of loads in the plurality of loads based on the amount of load that is being supplied by the generator includes decreasing the number of loads based on an overload of the generator.
13. The method of claim 12, wherein the overload of the generator is a difference between a generator load at a particular point in time and a maximum loading threshold of the generator.
14. The method of claim 13, wherein the maximum loading threshold of the generator is adjustable by a user.
15. The method of claim 13, wherein the maximum loading threshold of the generator is based on a rating provided by a manufacturer of the generator.
16. The method of claim 12, wherein the amount of time to decrease the number of loads will decrease as the generator overload increases.
17. The method of claim 1 , wherein determining an amount of time in which to change the number of loads in the plurality of loads based on the amount of load that is being supplied by the generator includes decreasing the number of loads based on generator operating frequency.
18. The method of claim 17, wherein the amount of time to decrease the number of loads will decrease as the generator operating frequency decreases.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201280049499.4A CN103858312B (en) | 2011-11-04 | 2012-11-01 | Maneuvering load level determines the time to increase and reduce load |
EP12846078.9A EP2742576B1 (en) | 2011-11-04 | 2012-11-01 | Adding and shedding loads using load levels to determine timing |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/289,131 | 2011-11-04 | ||
US13/289,131 US9991709B2 (en) | 2011-11-04 | 2011-11-04 | Adding and shedding loads using load levels to determine timing |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2013067120A1 true WO2013067120A1 (en) | 2013-05-10 |
Family
ID=48192742
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/US2012/062967 WO2013067120A1 (en) | 2011-11-04 | 2012-11-01 | Adding and shedding loads using load levels to determine timing |
Country Status (4)
Country | Link |
---|---|
US (2) | US9991709B2 (en) |
EP (1) | EP2742576B1 (en) |
CN (1) | CN103858312B (en) |
WO (1) | WO2013067120A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10193381B2 (en) | 2016-09-27 | 2019-01-29 | Reliance Controls Corporation | Load management and switching devices and methods |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11522365B1 (en) | 2011-05-26 | 2022-12-06 | J. Carl Cooper | Inverter power source load dependent frequency control and load shedding |
US10840735B1 (en) | 2011-05-26 | 2020-11-17 | J. Carl Cooper | Power source load control |
US11183843B1 (en) | 2011-05-26 | 2021-11-23 | J. Carl Cooper | Power source load control |
US10879727B1 (en) | 2011-05-26 | 2020-12-29 | James Carl Cooper | Power source load control |
RU2623456C2 (en) * | 2011-12-22 | 2017-06-26 | Филипс Лайтинг Холдинг Б.В. | Overload detection device |
WO2014143187A1 (en) | 2013-03-15 | 2014-09-18 | Michael Armstrong | Lifing and performance optimization limit management for turbine engine |
US9755458B2 (en) | 2013-12-19 | 2017-09-05 | Kohler, Co. | Bus recovery after overload |
CN104218589B (en) * | 2014-09-22 | 2016-05-18 | 天津大学 | Based on the low frequency deloading method of household type temperature control load |
US10175737B1 (en) * | 2015-12-22 | 2019-01-08 | Amazon Technologies, Inc. | Managing electrical resiliency in a datacenter |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050216131A1 (en) | 2004-03-24 | 2005-09-29 | Sodemann Wesley C | Residential load power management system |
US20070273214A1 (en) * | 2006-05-23 | 2007-11-29 | Wang Kon-King M | System and method for connecting power sources to a power system |
US7514815B2 (en) * | 2004-09-28 | 2009-04-07 | American Power Conversion Corporation | System and method for allocating power to loads |
US7854283B2 (en) * | 1998-04-03 | 2010-12-21 | Rockwell Collins Control Technologies, Inc. | Optimization method for power generation systems |
US20110215645A1 (en) * | 2010-03-05 | 2011-09-08 | Active Power, Inc. | Containerized continuous power system and method |
Family Cites Families (100)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4031406A (en) | 1975-06-16 | 1977-06-21 | Pacific Technology, Inc. | Method and apparatus for controlling electrical loads |
US4099067A (en) | 1975-08-25 | 1978-07-04 | Caterpillar Tractor Co. | Load-shedding control for diesel-electric sets |
US4064485A (en) | 1976-07-22 | 1977-12-20 | Pacific Technology, Inc. | Digital load control circuit and method for power monitoring and limiting system |
US4034233A (en) | 1976-07-22 | 1977-07-05 | Pacific Technology | Power monitoring and regulating circuit and method having an analog input representing power rate and a digital output for controlling the on/off states of a plurality of loads |
US4639657A (en) | 1984-08-30 | 1987-01-27 | Basler Electric Company | Electrical control apparatus and methods |
US4701690A (en) | 1985-11-27 | 1987-10-20 | Basler Electric Company | Transfer apparatus, regulating apparatus and methods |
US4731547A (en) | 1986-12-12 | 1988-03-15 | Caterpillar Inc. | Peak power shaving apparatus and method |
US4800291A (en) | 1987-03-04 | 1989-01-24 | Basler Electric Company | Electronic circuit for control of a voltage regulator of an electrical generator |
US5536976A (en) * | 1994-03-03 | 1996-07-16 | Gas Research Institute | Multiple service load solid state switching for controlled cogeneration system |
US5414640A (en) | 1991-07-05 | 1995-05-09 | Johnson Service Company | Method and apparatus for adaptive demand limiting electric consumption through load shedding |
US5294879A (en) | 1991-11-01 | 1994-03-15 | Basler Electric Company | Microprocessor-controlled regulator |
US5422517A (en) | 1993-05-26 | 1995-06-06 | United Technologies Corporation | Control of electric loads during generator failure in a multi-generator system |
GB9412261D0 (en) | 1994-06-18 | 1994-08-10 | Smiths Industries Plc | Electrical systems |
US5572438A (en) | 1995-01-05 | 1996-11-05 | Teco Energy Management Services | Engery management and building automation system |
US5640060A (en) | 1995-02-09 | 1997-06-17 | Basler Electric Company | Apparatus for synchronizing frequency and phase of two voltage sources |
US5761073A (en) | 1995-02-09 | 1998-06-02 | Basler Electric Company | Programmable apparatus for synchronizing frequency and phase of two voltage sources |
US5880537A (en) | 1997-01-10 | 1999-03-09 | Caterpillar Inc. | Uninterruptable power supply |
US5861683A (en) | 1997-05-30 | 1999-01-19 | Eaton Corporation | Panelboard for controlling and monitoring power or energy |
US6191500B1 (en) | 1998-11-06 | 2001-02-20 | Kling Lindquist Partnership, Inc. | System and method for providing an uninterruptible power supply to a critical load |
US6104171A (en) | 1998-11-23 | 2000-08-15 | Caterpillar Inc. | Generator set with redundant bus sensing and automatic generator on-line control |
US6107927A (en) | 1998-12-10 | 2000-08-22 | Caterpillar Inc. | Generator set controller with integral synchroscope mode |
US6172432B1 (en) | 1999-06-18 | 2001-01-09 | Gen-Tran Corporation | Automatic transfer switch |
US6181028B1 (en) | 1999-08-19 | 2001-01-30 | Generac Power Systems, Inc. | Transfer mechanism for transferring power between a utility source and a stand-by generator |
US6163088A (en) | 1999-09-30 | 2000-12-19 | Caterpillar Inc. | Method and apparatus for providing standby power from a generator using capacitor supplied voltage |
US6668629B1 (en) | 1999-11-26 | 2003-12-30 | General Electric Company | Methods and apparatus for web-enabled engine-generator systems |
EP1262008B1 (en) | 2000-01-28 | 2009-09-09 | Cummins Generator Technologies Limited | Ac power generating system |
AU7174700A (en) | 2000-05-04 | 2001-11-08 | Vasu Tech Limited | Configurable electronic controller |
US6631310B1 (en) | 2000-09-15 | 2003-10-07 | General Electric Company | Wireless engine-generator systems digital assistant |
US6876103B2 (en) | 2000-12-29 | 2005-04-05 | General Electric Company | Automatic transfer switch systems and controllers |
US6552888B2 (en) | 2001-01-22 | 2003-04-22 | Pedro J. Weinberger | Safety electrical outlet with logic control circuit |
WO2002066974A2 (en) | 2001-02-19 | 2002-08-29 | Rosemount Analytical Inc. | Improved generator monitoring, control and efficiency |
US6657416B2 (en) | 2001-06-15 | 2003-12-02 | Generac Power Systems, Inc. | Control system for stand-by electrical generator |
US6653821B2 (en) | 2001-06-15 | 2003-11-25 | Generac Power Systems, Inc. | System controller and method for monitoring and controlling a plurality of generator sets |
US6747368B2 (en) | 2001-08-30 | 2004-06-08 | Harold M. Jarrett, Jr. | Wireless control of power transfer switches for electrical load management |
US6798187B1 (en) | 2001-09-26 | 2004-09-28 | Reliance Controls Corporation | Generator status information display for power transfer switch |
US7146256B2 (en) | 2002-02-14 | 2006-12-05 | Yanmar Co., Ltd. | Power source switching unit and power source management system comprising it |
US20070222295A1 (en) | 2002-09-05 | 2007-09-27 | Paul Wareham | System and method for power load management |
US20040075343A1 (en) | 2002-09-05 | 2004-04-22 | Paul Wareham | System and method for power load management |
JP4585740B2 (en) | 2002-09-13 | 2010-11-24 | 株式会社日立グローバルストレージテクノロジーズ | Magnetic recording / reproducing device |
JP3968298B2 (en) | 2002-12-06 | 2007-08-29 | 株式会社日立製作所 | Power supply |
US7786616B2 (en) | 2003-02-07 | 2010-08-31 | Cummins Power Generation Inc. | Generator with DC boost and split bus bidirectional DC-to-DC converter for uninterruptible power supply system or for enhanced load pickup |
WO2004073135A2 (en) | 2003-02-10 | 2004-08-26 | Briggs & Stratton Power Products Group, Llc | Monitoring system for a generator |
JP2004260944A (en) | 2003-02-26 | 2004-09-16 | Sharp Corp | Power generation equipment, method and apparatus for controlling the same, communication apparatus, its program, and control system of power generation equipment |
US7149605B2 (en) | 2003-06-13 | 2006-12-12 | Battelle Memorial Institute | Electrical power distribution control methods, electrical energy demand monitoring methods, and power management devices |
US7291938B2 (en) | 2003-06-17 | 2007-11-06 | Honeywell International Inc. | Power supply apparatus and method based on parasitic power extraction |
US7015599B2 (en) | 2003-06-27 | 2006-03-21 | Briggs & Stratton Power Products Group, Llc | Backup power management system and method of operating the same |
JP2005057900A (en) | 2003-08-05 | 2005-03-03 | Kokusan Denki Co Ltd | Inverter generator driven by engine |
JP4713852B2 (en) | 2003-08-28 | 2011-06-29 | ルネサスエレクトロニクス株式会社 | Frequency generation circuit and communication system using the same |
US7208850B2 (en) | 2003-09-02 | 2007-04-24 | Generac Power Systems, Inc. | Power strip transfer mechanism |
WO2005040992A2 (en) | 2003-10-24 | 2005-05-06 | Square D Company | Intelligent power management control system |
JP3808864B2 (en) | 2003-12-03 | 2006-08-16 | 株式会社ケーヒン | Coordinated control device |
US7239045B2 (en) | 2003-12-19 | 2007-07-03 | Eaton Corporation | Power distribution system and control system for same |
US7177728B2 (en) | 2003-12-30 | 2007-02-13 | Jay Warren Gardner | System and methods for maintaining power usage within a set allocation |
CN101394090B (en) | 2004-03-16 | 2011-09-28 | 东京电力株式会社 | Power system protecting system |
US20070222294A1 (en) * | 2004-04-09 | 2007-09-27 | Jirou Tsukida | Underfrequency Load Shedding Protection System |
US7146266B2 (en) * | 2004-07-01 | 2006-12-05 | Ford Global Technologies, Llc | Controlling a hydraulic hybrid vehicle powertrain having an internal combustion engine and a hydraulic pump/motor |
US7356384B2 (en) | 2004-07-15 | 2008-04-08 | Briggs & Stratton Corporation | Load management system |
US7582986B2 (en) | 2004-10-08 | 2009-09-01 | Schweitzer Engineering Laboratories, Inc. | Compensated inverse-time undervoltage load shedding systems |
US7230345B2 (en) | 2005-01-12 | 2007-06-12 | Generac Power Systems, Inc. | Method for exercising a stand-by electrical generator |
US7345456B2 (en) | 2005-01-24 | 2008-03-18 | Basler Electric Company | Power system stabilizer providing excitation limiter functions |
US7274974B2 (en) | 2005-02-22 | 2007-09-25 | Square D Company | Independent automatic shedding branch circuit breaker |
CN100413190C (en) | 2005-03-11 | 2008-08-20 | 昂宝电子(上海)有限公司 | System and method for controlling frequency of adaptive switch |
US7336003B2 (en) | 2005-04-05 | 2008-02-26 | Eaton Corporation | Transfer switch and power system including the same |
US7218998B1 (en) | 2005-07-11 | 2007-05-15 | Neale Stephen D | System and method for limiting power demand in an energy delivery system |
US7778737B2 (en) | 2005-09-07 | 2010-08-17 | Comverge, Inc. | Method and system for local load control |
US7608948B2 (en) | 2006-06-20 | 2009-10-27 | Lutron Electronics Co., Inc. | Touch screen with sensory feedback |
US7747355B2 (en) | 2006-11-07 | 2010-06-29 | Potenco, Inc. | Electrical power generator with adaptive coupling |
US7598623B2 (en) | 2006-12-29 | 2009-10-06 | Cummins Power Generation Ip, Inc. | Distinguishing between different transient conditions for an electric power generation system |
US7573145B2 (en) | 2006-11-16 | 2009-08-11 | Cummins Power Generation Ip, Inc. | Electric power generation system controlled to reduce perception of operational changes |
US7855466B2 (en) | 2006-12-29 | 2010-12-21 | Cummins Power Generation Ip, Inc. | Electric power generation system with current-controlled power boost |
US20080157600A1 (en) | 2006-12-29 | 2008-07-03 | Cummins Power Generation Ip, Inc. | Operator interface for an electric power generation system |
US7619324B2 (en) | 2007-01-29 | 2009-11-17 | Caterpillar Inc. | Power system with multiple generator sets |
GB0702253D0 (en) | 2007-02-06 | 2007-03-14 | Cummins Generator Technologies | Method of and apparatus for controlling excitation |
GB0703190D0 (en) | 2007-02-19 | 2007-03-28 | Cummins Generator Technologies | Load angle measurement and pole slip detection |
US7557544B2 (en) | 2007-04-23 | 2009-07-07 | Cummins Power Generation Ip, Inc. | Zero crossing detection for an electric power generation system |
US7521822B2 (en) | 2007-05-07 | 2009-04-21 | Cummins Power Generation Ip, Inc. | Protection techniques for a back-up electric power system |
US7715951B2 (en) | 2007-08-28 | 2010-05-11 | Consert, Inc. | System and method for managing consumption of power supplied by an electric utility |
US8868378B2 (en) | 2007-09-19 | 2014-10-21 | Briggs And Stratton Corporation | Power monitoring system |
US8494686B2 (en) | 2007-10-14 | 2013-07-23 | Enmetric Systems, Inc. | Electrical energy usage monitoring system |
US7656060B2 (en) | 2007-10-31 | 2010-02-02 | Caterpillar Inc. | Power system with method for adding multiple generator sets |
US8198753B2 (en) | 2007-10-31 | 2012-06-12 | Caterpillar Inc. | Power system with method for adding multiple generator sets |
US20090113874A1 (en) | 2007-11-02 | 2009-05-07 | Caterpillar Inc. | System and method for electrically regenerating a particulate filter assembly of a generator set |
US20090152951A1 (en) | 2007-12-18 | 2009-06-18 | Caterpillar Inc. | Electric system for providing uninterruptible power |
US7980340B2 (en) * | 2007-12-27 | 2011-07-19 | Byd Co. Ltd. | Hybrid vehicle having power assembly arranged transversely in engine compartment |
US20090179498A1 (en) | 2008-01-14 | 2009-07-16 | Lathrop Todd M | Transfer switch controller providing an alternating current voltage to a generator and transfer switch including the same |
US20090195224A1 (en) | 2008-01-31 | 2009-08-06 | Basler Electric Company | Digital Excitation Control System Utilizing Self-Tuning PID Gains and an Associated Method of Use |
US8275488B2 (en) | 2008-01-31 | 2012-09-25 | Basler Electric Co. | Digital excitation control system utilizing swarm intelligence and an associated method of use |
US20090216386A1 (en) | 2008-02-26 | 2009-08-27 | Wedel Francis X | Load shed transfer mechanism and method |
US8058850B2 (en) | 2008-05-21 | 2011-11-15 | Honeywell International, Inc. | Overload control of an electric power generation system with unknown availability of mechanical power capacity |
US20100019574A1 (en) | 2008-07-24 | 2010-01-28 | John Baldassarre | Energy management system for auxiliary power source |
US8222548B2 (en) | 2008-07-30 | 2012-07-17 | Generac Power Systems, Inc. | Automatic transfer switch |
US7956762B2 (en) | 2008-09-15 | 2011-06-07 | Caterpillar Inc. | Method and apparatus for power generation failure diagnostics |
US8519565B2 (en) | 2008-10-24 | 2013-08-27 | Caterpillar Inc. | Generator set control system |
US8258640B2 (en) | 2008-10-30 | 2012-09-04 | Caterpillar Inc. | Power system having transient control |
US8716896B2 (en) | 2008-12-12 | 2014-05-06 | Caterpillar Inc. | Genset control system implementing engine synchronization |
US8106633B2 (en) | 2008-12-18 | 2012-01-31 | Caterpillar Inc. | Generator set control system |
US8237300B2 (en) | 2008-12-19 | 2012-08-07 | Caterpillar Inc. | Genset power system having multiple modes of operation |
US8324755B2 (en) | 2009-03-06 | 2012-12-04 | Briggs And Stratton Corporation | Power management system and method of operating the same |
US8627797B2 (en) * | 2009-06-11 | 2014-01-14 | Illinois Tool Works Inc. | Automatic start and stop of a portable engine driven power source |
TWI396954B (en) | 2009-11-11 | 2013-05-21 | Richtek Technology Corp | Frequency control circuit and method for a non-constant frequency voltage regulator |
-
2011
- 2011-11-04 US US13/289,131 patent/US9991709B2/en active Active
-
2012
- 2012-11-01 CN CN201280049499.4A patent/CN103858312B/en active Active
- 2012-11-01 EP EP12846078.9A patent/EP2742576B1/en active Active
- 2012-11-01 WO PCT/US2012/062967 patent/WO2013067120A1/en active Application Filing
-
2018
- 2018-05-11 US US15/977,854 patent/US10790664B2/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7854283B2 (en) * | 1998-04-03 | 2010-12-21 | Rockwell Collins Control Technologies, Inc. | Optimization method for power generation systems |
US20050216131A1 (en) | 2004-03-24 | 2005-09-29 | Sodemann Wesley C | Residential load power management system |
US7514815B2 (en) * | 2004-09-28 | 2009-04-07 | American Power Conversion Corporation | System and method for allocating power to loads |
US20070273214A1 (en) * | 2006-05-23 | 2007-11-29 | Wang Kon-King M | System and method for connecting power sources to a power system |
US20110215645A1 (en) * | 2010-03-05 | 2011-09-08 | Active Power, Inc. | Containerized continuous power system and method |
Non-Patent Citations (1)
Title |
---|
See also references of EP2742576A4 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10193381B2 (en) | 2016-09-27 | 2019-01-29 | Reliance Controls Corporation | Load management and switching devices and methods |
Also Published As
Publication number | Publication date |
---|---|
US20130116847A1 (en) | 2013-05-09 |
EP2742576A1 (en) | 2014-06-18 |
US20180262004A1 (en) | 2018-09-13 |
EP2742576B1 (en) | 2017-12-20 |
US9991709B2 (en) | 2018-06-05 |
CN103858312A (en) | 2014-06-11 |
US10790664B2 (en) | 2020-09-29 |
EP2742576A4 (en) | 2015-12-23 |
CN103858312B (en) | 2018-09-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10790664B2 (en) | Adding and shedding loads using load levels to determine timing | |
US10649420B2 (en) | Generator management system and method that selectively activate at least one of a plurality of generators in a power generation system | |
US9627907B2 (en) | Storage battery control device, storage battery control method, program, electricity storage system, and power supply system | |
CN111989459B (en) | Load management algorithm for optimizing engine efficiency | |
US8533514B2 (en) | Power-capping based on UPS capacity | |
US9368972B2 (en) | Generator management system that determines a time to activate and deactivate generators based on the load level | |
WO2016101509A1 (en) | Charging control method and device | |
US20160344186A1 (en) | Generator management system that selectively activates generators based on an operating parameter | |
US9727104B2 (en) | Various PSUs adaptive server and method | |
EP3012939A1 (en) | Generator management system and method that selectively activate at least one of a plurality of generators in a power generation system | |
JP2012032117A (en) | Hot-water storage type hot-water supply system | |
US20110035533A1 (en) | System and method for data-processing | |
EP2654174B1 (en) | Charging an energy storage device with a variable speed generator | |
CN113799659B (en) | Whole fuel cell vehicle energy distribution method | |
US10547254B2 (en) | Apparatus for controlling multiple inverters and inverter system including the same | |
JP2019154120A (en) | Operation planning method, operation planning apparatus, and program | |
CN109753400B (en) | Energy consumption adjusting method and edge data center system | |
CN114188575B (en) | Power interval-based power regulation and control method for multi-stack fuel cell system | |
CN113067401B (en) | Superconducting fan control method and device with energy storage device | |
JP2018152965A (en) | Generator operation control apparatus and generator operation control method | |
CN105866499A (en) | Power display method and device | |
CN113300636A (en) | Motor star-delta conversion starting method and device and compressor system | |
CN112130656A (en) | Method, system, equipment and medium for optimizing power supply of server power supply | |
CN109981029A (en) | A kind of control method and device of motor | |
CN116111675A (en) | Current regulation method and device and charging equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12846078 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2012846078 Country of ref document: EP |
|
NENP | Non-entry into the national phase |
Ref country code: DE |