WO2012121607A1 - Offshore foundation for installation on the seabed and method for installation of the offshore foundation - Google Patents

Offshore foundation for installation on the seabed and method for installation of the offshore foundation Download PDF

Info

Publication number
WO2012121607A1
WO2012121607A1 PCT/NO2012/050012 NO2012050012W WO2012121607A1 WO 2012121607 A1 WO2012121607 A1 WO 2012121607A1 NO 2012050012 W NO2012050012 W NO 2012050012W WO 2012121607 A1 WO2012121607 A1 WO 2012121607A1
Authority
WO
WIPO (PCT)
Prior art keywords
cells
foundation
bucket
installation
seabed
Prior art date
Application number
PCT/NO2012/050012
Other languages
French (fr)
Inventor
Trond LANDBØ
Niklas NORMANN
Original Assignee
Vici Ventus Technology As
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Vici Ventus Technology As filed Critical Vici Ventus Technology As
Publication of WO2012121607A1 publication Critical patent/WO2012121607A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0065Monopile structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0073Details of sea bottom engaging footing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/95Mounting on supporting structures or systems offshore
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Sustainable Energy (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Chemical & Material Sciences (AREA)
  • Sustainable Development (AREA)
  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

Offshore foundation and a method for an installation of a foundation on the seabed 25 with mounted deck equipment 20, preferably for wind turbines or oil and gas. The foundation 1 comprises at least three cells 3 and at least one tower 13 preferably arranged centrically between the cells 3. The at least three cells 3 are arranged with the internal sliding bucket cells 6, which in an extended condition during the installation of the foundation 1 on the seabed 25 protrudes up through the water line 26 and in a submerged condition is arranged within the at least three cells 3.

Description

Offshore foundation for installation on the seabed, and method for installation of the offshore foundation
The present invention is related to an offshore platform, and a method for installation of the foundation on the seabed, with mounted deck equipment, primarily for wind turbines or oil and gas, as the foundation comprises at least three cells and at least one tower tower preferably arranged centrically between the cells.
Specifically, the foundation consists of at least one tower (cylinder / cone) with a wider foundation design in the bottom. One objective of such foundations is to be able to assemble a foundation and deck equipment (top side) close to the shore, to tow complete units to the offshore location and install when ballasting. The foundation is preferably of the type mono-tower gravity foundation or a skirt piled foundation, a "volume foundation" preferably built with concrete or steel that is self-floating in all the temporary floating phases. These foundations often have a lower limit for water depths, in which one may obtain stability in floating phases without the use of aids. This is particularly a challenge if you want a full assembly of the foundation and topside / wind turbine close to the shore. A known solution to obtain floating stability for mono-tower foundations is to make use of temporary buoyancy in the form of separate buoyancy tanks mounted on the structure prior to installation, and dismantle these after the foundation has been put in place. The latter in order to avoid these tanks being subject to large wave loads. Such temporary floating bodies will lead to costly naval operations both before and after the installation.
Another known solution is to mount permanent buoyancy tanks which are to remain after the installation, but which then will have the disadvantage that they significantly incur additional wave loads which the structure will have to be able to withstand throughout its service life.
One goal of the present invention is to provide a design that has the full stability in all floating phases, including installation at the field, at water depths that are normally too shallow to obtain such stability for this kind of foundations. Another goal is that the above-mentioned stability has to be achieved in a manner that does not require costly naval operations before and after installation, and which does not incur large wave loads during operation.
A further goal is that the construction or the offshore foundation should be removable from the seabed in a manner that is simple and cost effective.
The aims of the present invention are achieved by an offshore foundation for installation on the seabed with mounted deck equipment, preferably for wind turbines or oil and gas, as the foundation comprises at least three cells and at least one tower preferably arranged centrically between the cells,
characterized in that the at least three cells are arranged with the internal sliding bucket cells in an extended state during the installation of the foundation on the seabed protrude up through the water line, and are arranged within the at least three cells in a submerged condition.
Preferred embodiments of the offshore foundation are further elaborated in claims two to nine inclusive.
Further, the objectives of the present invention are achieved by a method for installing an offshore foundation with mounted deck equipment, preferably for wind turbines or oil and gas, as the foundation comprises at least three cells and at least one tower preferably arranged centrically between the cells,
characterized in that the at least three cells are arranged with internal sliding bucket cells, where the upper area of the bucket cells is positioned above the waterline during installation and immersion of the foundation to the seabed as the air is trapped in the cavities of the bucket cells, formed between the internal wall and the top surface of the bucket cells and the water surface or the foundation plate, and after installation of the foundation on the seabed the air in the cavity is released out, and water is filled in, whereby the bucket cells is lowered into the cells.
One preferred embodiment of the invention will hereinafter be explained with reference to the figures, where
Figure 1 shows an offshore foundation with attached deck equipment, according to the invention,
Figure 2 shows a plan view through the section 2-2 in Figure 1 ,
Figure 3 shows a detail of a bucket cell of the offshore foundation in Figure 1 and Figure 2,
Figures 4a-h show the offshore foundation in a stepwise phase from the
construction until it is installed on the seabed,
Figure 5 shows the offshore foundation with mounted deck equipment and with an alternative embodiment of the bucket cells,
Figure 6 shows a plan view through section 2-2 of Figure 5, and
Figure 7 shows a detail of the alternative bucket cell of the offshore foundation in
Figures 5 and 6.
With particular reference to Figures 1 , 2 and 3, an offshore foundation 1 is shown. The foundation 1 comprises at least three cells 3 and at least one tower 13 preferably arranged centrically between the cells 3. Deck equipment 20, in the form of a wind turbine, is mounted on the tower 13. The cells 3 are arranged with the internal sliding bucket cells 6, which in an extended condition upon installation of the foundation 1 on the seabed 25 protrude up through the water line 26, where they in a submerged condition are arranged within the at least three cells 3.
With particular reference to Figure 3, the sliding bucket cells 6 are shown as cylinders with an upper top plate 7 and a lower outer peripheral flange design 8. The cells 3 are arranged with an internal upper ring joist 4 which implies that, when the sliding bucket cells 6 are in an extended state, they will bump into and stop at the internal upper ring joist 4.
Bucket cells 6 can be arranged with a valve 1 1 for discharge or introduction of air, respectively, out of or into the cell cavities of the bucket formed between the inner cell wall and the top surface 9, 10 of bucket cells and the water surface 16.
Bucket cells 6 can be made of steel or concrete, or a combination of these materials and other suitable materials.
Bucket cells 6 can also be arranged with at least one telescoping part in the form of at least a cylinder jacket at the outside of the internal bucket cell 6.
Figures 4a-4h show a stepwise build-up of the offshore foundation 1 until it is ballasted and installed on the seabed 25.
Figure 4a shows the cells 3 with the internally arranged gliding bucket cells 6 in a floating state.
Figure 4b shows the complete offshore foundation 1 with the tower 13 mounted. Figure 4c shows the ballasting and embedding of the offshore foundation as the gliding bucket cells 6 are in a partially extended state.
Figure 4d shows ballasting until the bucket cells are in an extended condition, in which the lower outer peripheral flange design 8 bumps into against the internal upper ring joist 4 The exterior water line 26 and the internal water surface 16 are here shown. The cavity, which is enclosed by the water surface 16 and the internal cell wall and the top surface 9, 10 of bucket, is filled with air, and the cells 3 are filled with water.
Figure 4e shows the filling of solid ballast for transportation of a foundation 1 to the site where the installation is to take place.
Figure 4f shows the ballasting of the offshore foundation 1 when mounting on the deck equipment 20.
Figure 4g shows deballasting of the offshore foundation 1 with mounted deck equipment 20 upon transportation to the installation site.
Figure 4h shows an offshore foundation installed at the seabed 25. After installation, valve 1 1 is opened and the air in the bucket cells 6 is released, such that they sink down into the cells 3. Extra ballast 27 is also shown added into the lower tower area of the offshore foundation.
With reference to figures 5, 6, and 7, the offshore foundation 1 is shown in an alternative embodiment. Here also, the foundation 1 comprises the three cells 3 and one tower 13 being centrically arranged between the cells 3. With particular reference to Figure 6, it is here shown that the foundation has a somewhat different design compared with the embodiment discussed in Figures 1 , 2 and 3. Furthermore, with reference to Figure 7, the sliding bucket cell 6 is arranged with a lower foundation plate 14. The sliding bucket cell is also arranged with a second valve 12, which will be located below the external waterline 26 after installation of the foundation 1 on the seabed 25. The alternative embodiment of the sliding bucket cells 6, with both the upper top plate 7 and the lower foundation plate 14, results in a very favorable stabilizing effect for the offshore foundation 1 . An internal waterline is avoided in the bucket cells 6, and you do not have to take into account that the air inside the bucket cells 6 is being compressed, which affects both the stability and requires feeding of pressure as the draft is changed. This alternative embodiment of the bucket cells 6 results in that bucket cells 6 become dense, and must therefore be equipped with a second valve 12 located below the external waterline 26 after installation of the foundation 1 on the seabed 25. The second valve 12 may be opened to the sea, such that water can be filled into the bucket. The aforementioned valve 1 1 arranged in the upper part of the bucket cell 6 is used for evacuation of air when the bucket cells 6 is filled with water and for pumping the air when they are to be emptied of water.
The offshore foundation 1 obtains full stability in all floating phases, including the installation at the field. This is obtained by use of the sliding bucket cells 6 (preferably in steel, but concrete and other materials may be used), which runs through the water line, and significantly increases the moment of inertia of the water level. The construction according to the invention results in achieving full effects of the bucket cells during installation, and that these disappear into the foundation structure after installation in order to avoid increased wave loads. It does not require that you actively control the buoyancy of the bucket cells 6. It is the trapped air that raises the gliding bucket cells 6 or the cylinders above the waterline at all times, and lift them until the lower outer peripheral flange design 8 stops against the internal upper ring joist 4 in the cells 3 The gliding bucket cells 6 will then serve as fixed buoyancy bodies until the foundation 1 has been placed on the seabed 26. After installation has been completed, the valve 1 1 is opened and the air in the bucket cells 6 is released, such that they sink into the cells 3.
Any removal of the offshore foundation 1 will occur in the reverse order; you will then pump air into the gliding bucket cells 6 until they rise above the water line 26 and stops against the ring joist 4. You will then be able to raise the foundation 1 by pumping water out of the central chamber and the tower 13. Then the offshore foundation can be towed ashore and be dismantled into their respective parts.
In the demonstrated embodiment of the offshore foundation 1 , the cells 3, or the box, are approximately half the water depth and the buckets 6 with a similar height, so they just protrude up during the installation. At deeper waters, these bucket cells may have an additional jacket of steel cylinder on the outside, extra telescopic joints, which allow for that the box height is reduced to about one-third of the water depth, and the bucket cell 6 and the additional cylinder jacket have similar heights such that the bucket cell protrudes up through the water line 26.

Claims

120510/[RADGIVER] PATENT CLAIMS
1. Offshore foundation (1 ) for installation on the seabed (25) with mounted deck equipment (20), preferably for wind turbines or oil and gas, as the foundation (1) comprises at least three cells (3) and at least one tower (13) preferably arranged centrically between the cells (3),
characterized in that the at least three cells (3) are arranged with the internal sliding bucket cells (6) in an extended state during the installation of the foundation (1) on the seabed (25) protrude up through the water line (26), and are arranged within the at least three cells (3) in a submerged condition.
2. Offshore foundation (1 ) according to claim ^characterized in that the sliding bucket cells (6) are cylinders with an upper top plate (7) and a lower external peripheral flange design (8), and the at least three cells (3) are arranged with an internal upper ring joist (4) whereby the lower external peripheral flange design bumps into the internal upper ring joist when the gliding bucket cells (6) are in an extended state.
3. Offshore foundation (1) according to claims 1 or 2,
characterized in that the sliding bucket cells (6) are arranged with a valve (11) for discharge or introduction of air, respectively, out of or into the cavities of the bucket cells, formed between the inside of the cell wall and the top surface (9, 10) of the bucket cells and the water surface (16).
4. Offshore foundation (1 ) according to any of the preceding claims, characterized in that the sliding bucket cells (6) are further arranged with a lower bottom plate (14).
5. Offshore foundation (1 ) according to claim 4, characterized in that the sliding bucket cells (6) are arranged with a second valve ( 2) located below the external water line (26) after installation of the foundation (1) at the seabed (25).
6. Offshore foundation (1 ) according to any of the preceding claims,
characterized in that the sliding bucket cells (6) are made of steel.
7. Offshore foundation (1) according to any of claims 1 - 5,
characterized in that the sliding bucket cells (6) are made of concrete.
8. Offshore foundation (1) according to any of preceding claims,
characterized in that the sliding bucket cells (6) are arranged with at least a telescopic joint, in the form of at least a cylinder jacket on the outside of the internal bucket cell (6). ,
9. Method for installing an offshore foundation (1 ) with mounted deck equipment (20), preferably for wind turbines or oil and gas, as the foundation (1 ) comprises at least three cells (3) and at least one tower (13) preferably arranged centrically between the cells (3),
characterized in that the at least three cells (3) are arranged with internal sliding bucket cells (6), where the upper area of the bucket cells is positioned above the waterline (26) during installation and immersion of the foundation (1) to the seabed (25) as the air is trapped in the cavities of the bucket cells, formed between the internal wall and the top surface (9, 10) of the bucket cells and the water surface (16) or the foundation plate (14), and after installation of the foundation (1) on the seabed (25) the air in the cavity is released out, and water is filled in, whereby the bucket cells (6) is lowered into the cells (3).
PCT/NO2012/050012 2011-03-10 2012-02-02 Offshore foundation for installation on the seabed and method for installation of the offshore foundation WO2012121607A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NO20110369A NO332557B1 (en) 2011-03-10 2011-03-10 Offshore foundation for installation on the seabed as well as methods for installation of the offshore foundation
NO20110369 2011-03-10

Publications (1)

Publication Number Publication Date
WO2012121607A1 true WO2012121607A1 (en) 2012-09-13

Family

ID=46798416

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/NO2012/050012 WO2012121607A1 (en) 2011-03-10 2012-02-02 Offshore foundation for installation on the seabed and method for installation of the offshore foundation

Country Status (2)

Country Link
NO (1) NO332557B1 (en)
WO (1) WO2012121607A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2971413A1 (en) * 2013-03-14 2016-01-20 Arranged bvba Pressure vessel based tower structure
CN109306706A (en) * 2018-11-01 2019-02-05 合肥学院 A kind of major-minor bucket sea bed perforation device and its construction method
US11173987B2 (en) 2016-10-18 2021-11-16 Atkins Energy, Inc. Offshore floating structures

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988967A (en) * 2017-04-19 2017-07-28 浙江大学 A kind of multi-cavity pulsed levelling device and method for offshore wind turbine barrel base

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2124684A (en) * 1982-07-29 1984-02-22 Condesign As Offshore platform
US20040169376A1 (en) * 2001-07-06 2004-09-02 Jacques Ruer Offshore wind turbine and method for making same
WO2009154472A2 (en) * 2008-06-20 2009-12-23 Seatower As Support structure for use in the offshore wind farm industry

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2124684A (en) * 1982-07-29 1984-02-22 Condesign As Offshore platform
US20040169376A1 (en) * 2001-07-06 2004-09-02 Jacques Ruer Offshore wind turbine and method for making same
WO2009154472A2 (en) * 2008-06-20 2009-12-23 Seatower As Support structure for use in the offshore wind farm industry

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2971413A1 (en) * 2013-03-14 2016-01-20 Arranged bvba Pressure vessel based tower structure
EP2971413B1 (en) * 2013-03-14 2022-08-03 Arranged bv Tower structure being made of pressure tanks
US11173987B2 (en) 2016-10-18 2021-11-16 Atkins Energy, Inc. Offshore floating structures
CN109306706A (en) * 2018-11-01 2019-02-05 合肥学院 A kind of major-minor bucket sea bed perforation device and its construction method

Also Published As

Publication number Publication date
NO20110369A1 (en) 2012-09-11
NO332557B1 (en) 2012-10-22

Similar Documents

Publication Publication Date Title
KR102155794B1 (en) Process for installing an offshore tower
EP2310670B1 (en) Support structure for use in the offshore wind farm industry
CA2811853C (en) Process for installing an offshore tower
EP2559814B1 (en) Gravity foundation
EP3584373B1 (en) Maritime structure for laying the foundations of buildings and its method of installation
CA2980959C (en) Gravity-based foundation for the installation of offshore wind turbines
EA020551B1 (en) Offshore station, foundation for an offshore station, and method for building an offshore station
MX2013004327A (en) Offshore tower for drilling and/or production.
NO346090B1 (en) Single column semi-submersible platform for fixed anchoring in deep water
WO2012121607A1 (en) Offshore foundation for installation on the seabed and method for installation of the offshore foundation
WO2010143976A2 (en) A foundation, a method of manufacturing the foundation, and a method of installing the foundation on a seabed
AU2021202442B2 (en) Gravity-Based Structure For Off-Shore Structures
EP2189576A1 (en) Foundation system for marine structures in deep water
TWM494747U (en) Operation platform on water
GB2503104A (en) Submersible platform for attaching a plurality of energy producing devices

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 12755477

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 12755477

Country of ref document: EP

Kind code of ref document: A1