WO2012054891A1 - Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles - Google Patents

Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles Download PDF

Info

Publication number
WO2012054891A1
WO2012054891A1 PCT/US2011/057378 US2011057378W WO2012054891A1 WO 2012054891 A1 WO2012054891 A1 WO 2012054891A1 US 2011057378 W US2011057378 W US 2011057378W WO 2012054891 A1 WO2012054891 A1 WO 2012054891A1
Authority
WO
WIPO (PCT)
Prior art keywords
ice
hull
rig
conical piled
water
Prior art date
Application number
PCT/US2011/057378
Other languages
English (en)
Inventor
Randall S. Shafer
Peter G. Noble
Ravi P. Aurora
Thomas E. Ramsey
Ted H. Westerman
Dominique P. Berta
Original Assignee
Conocophillips Company
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from US13/277,791 external-priority patent/US20120128426A1/en
Priority claimed from US13/277,755 external-priority patent/US8821071B2/en
Application filed by Conocophillips Company filed Critical Conocophillips Company
Priority to RU2013123049/03A priority Critical patent/RU2564711C2/ru
Priority to CA2811946A priority patent/CA2811946C/fr
Priority to US13/279,120 priority patent/US8807875B2/en
Priority to KR1020137010002A priority patent/KR20130120463A/ko
Priority to CN201180050455.9A priority patent/CN103180513B/zh
Priority to EP11779048.5A priority patent/EP2630303B1/fr
Priority to PCT/US2011/057378 priority patent/WO2012054891A1/fr
Publication of WO2012054891A1 publication Critical patent/WO2012054891A1/fr
Priority to SG2013022595A priority patent/SG189116A1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B35/4413Floating drilling platforms, e.g. carrying water-oil separating devices
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0017Means for protecting offshore constructions
    • E02B17/0021Means for protecting offshore constructions against ice-loads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C11/00Equipment for dwelling or working underwater; Means for searching for underwater objects
    • B63C11/48Means for searching for underwater objects
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C7/00Salvaging of disabled, stranded, or sunken vessels; Salvaging of vessel parts or furnishings, e.g. of safes; Salvaging of other underwater objects
    • B63C7/26Means for indicating the location of underwater objects, e.g. sunken vessels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/021Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto with relative movement between supporting construction and platform
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/027Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto steel structures
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/02Supports for the drilling machine, e.g. derricks or masts specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/008Drilling ice or a formation covered by ice
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/02Drilling rigs characterised by means for land transport with their own drive, e.g. skid mounting or wheel mounting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling
    • E21B7/136Underwater drilling from non-buoyant support
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B2211/00Applications
    • B63B2211/06Operation in ice-infested waters
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/006Platforms with supporting legs with lattice style supporting legs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0069Gravity structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0073Details of sea bottom engaging footing
    • E02B2017/0082Spudcans, skirts or extended feet

Definitions

  • This invention relates to mobile offshore drilling units, often called “jack-up” drilling units or rigs that are used in shallow water, typically less than 400 feet, for drilling for hydrocarbons.
  • a jack-up or mobile offshore drilling unit can be used for about 45-90 days in the short, open-water summer season. Predicting when the drilling season starts and ends is a game of chance and many efforts are undertaken to determine when the jack-up may be safely towed to the drilling location and drilling may be started. Once started, there is considerable urgency to complete the well to avoid having to disconnect and retreat in the event of ice incursion before the well is complete. Even during the few weeks of open water, ice floes present a significant hazard to jack-up drilling rigs where the drilling rig is on location and legs of the jack-up drilling rig are exposed and quite vulnerable to damage.
  • Jack-up rigs are mobile, self-elevating, offshore drilling and workover platforms equipped with legs that are arranged to be lowered to the sea floor and then to lift the hull out of the water.
  • Jack-up rigs typically include the drilling and/or workover equipment, leg-jacking system, crew quarters, loading and unloading facilities, storage areas for bulk and liquid materials, helicopter landing deck and other related facilities and equipment.
  • a jack-up rig is designed to be towed to the drilling site and jacked-up out of the water so that the wave action of the sea only impacts the legs which have a fairly small cross section and thus allows the wave action to pass by without imparting significant movement to the jack-up rig.
  • the legs of a jack-up provide little defense against ice floe collisions and an ice floe of any notable size is capable of causing structural damage to one or more legs and/or pushing the rig off location. If this type of event were to happen before the drilling operations were suspended and suitable secure and abandon had been completed, a hydrocarbon leak would possibly occur. Even a small risk of such a leak is completely unacceptable in the oil and gas industry, to the regulators and to the public.
  • the invention more particularly relates to a system including an ice worthy jack-up rig for drilling for hydrocarbons in potential ice conditions in offshore areas including a flotation hull having a relatively flat deck at the upper portion thereof.
  • the flotation hull further includes an ice bending shape along the lower portion thereof and extending downwardly and inwardly around the periphery of the hull where the ice bending shape extends from an area of the hull near the level of the deck and extends downwardly near the bottom of the hull.
  • An ice deflecting portion is arranged to extend around the perimeter of the bottom of the hull to direct ice around the hull and not under the hull.
  • At least three legs are positioned within the perimeter of the bottom of the flotation hull wherein the legs are arranged to be lifted up off the seafloor so that the rig may be towed through shallow water and also extend to the sea floor and extend further to lift the hull partially or fully out of the water.
  • a jack-up device is associated with each leg to both lift the leg from the sea bottom so that the ice worthy jack up rig may float by the buoyancy of the hull and push the legs down to the seafloor and push the hull partially up and out of the water when ice floes threaten the rig and fully out of the water when ice is not present.
  • the system further includes a conical piled monopod having a body with a base at the bottom and a top deck at the top wherein the base is attached to pilings that are driven into the seafloor when the conical piled monopod structure is installed for use.
  • the body of the conical pile monopod includes an inclined ice engaging surface around the body extending from a wider lower region to a narrower upper region where the lower region is below the sea surface and the upper region is above the sea surface.
  • the conical piled monopod further includes tabs with sockets arranged to receive a foot on at least one of the legs to be attached and held in place for drilling through the conical piled monopod.
  • the rig is arranged to work with the conical piled monopod by lifting its hull out of the water and extend over the conical piled monopod to drill down through the conical piled monopod, lower itself into the water to assume an ice defensive position such that ice would contact the ice bending shape of the rig when thin ice is present, and be moved away when thick ice is present.
  • the invention further relates to a method for drilling wells in ice prone waters.
  • the method includes providing a conical piled monopod having a body with a base at the bottom and a top deck at the top and an inclined ice engaging surface around the body extending from a wider lower region to a narrower upper region where the lower region is below the sea surface and the upper region is above the sea surface wherein the conical piled monopod includes at least one tab with a socket for receiving and holding a foot of a jack-up drilling rig.
  • Pilings are driven into the seafloor and attaching the pilings to the conical piled monopod to fix the conical piled monopod to the sea floor.
  • a rig has flotation hull and a relatively flat deck at the upper portion thereof and an ice bending shape along the lower portion thereof where the ice bending shape extends from an area of the hull near the level of the deck and extends downwardly near the bottom of the hull.
  • An ice deflecting portion is provided to extend around the perimeter of the bottom of the hull to direct ice around the hull and not under the hull. At least three legs are positioned within the perimeter of the bottom of the hull.
  • Each leg is jacked down in a manner that at least one foot on the bottom of one of the legs engages the socket on the tab of the conical piled monopod and the remaining feet engage the sea floor or another socket on a tab and lifts the hull up and fully out of the water when ice is not threatening the rig while the rig is drilling a well on a drill site.
  • the hull is further lowered into the water into an ice defensive configuration so that the ice bending shape extends above and below the sea surface to bend ice that comes against the rig to cause the ice to submerge under the water and endure bending forces that break the ice where the ice flows past the rig.
  • a well is drilled from the rig over the side of the deck and down through the conical piled monopod.
  • Figure 1 is an elevation view of the present invention where the drilling rig is floating in the water and available to be towed to a well drilling site;
  • Figure 2 is an elevation view of the present invention where the drilling rig is jacked up out of the water;
  • Figure 3 is an elevation view of the first embodiment of the present invention where the drilling rig is partially lowered into the ice/water interface, but still supported by its legs, in a defensive configuration for drilling during potential ice conditions;
  • Figure 4 is an enlarged fragmentary elevation view showing one end of the first embodiment of the present invention in the Figure 3 configuration with ice moving against the rig;
  • Figure 5 is an elevation view showing the drilling rig moving to a conical piled monopod for drilling down through the conical piled monopod;
  • Figure 6 is an elevation view showing the drilling rig arranged over the conical piled monopod to drill down through the conical piled monopod;
  • Figure 7 is an elevation view showing the drilling rig arranged adjacent to the conical piled monopod in it ice defensive configuration;
  • Figure 8 is a top view showing the drilling rig positioned to drill down through the conical piled monopod.
  • an ice worthy jack-up rig is generally indicated by the arrow 10.
  • jack-up rig 10 is shown with its hull 20 floating in the sea and legs 25 in a lifted arrangement where much of the length of the legs 25 extend above the deck 21 of the hull 20.
  • derrick 30 mounted to drilling cantilever 24 and with other conventional equipment and systems, facilitate the drill of wells.
  • the jack-up rig 10 may be towed from one drilling site to another and to and from shore bases for maintenance and other shore service.
  • the legs 25 are lowered through the openings 27 in hull 20 until the feet 26 at the bottom ends of the legs 25 engage the seafloor 15 as shown in Figure 2.
  • the feet 26 are connected to spud cans 28 to secure the rig 10 to the seafloor.
  • jacking rigs within openings 27 push the legs 25 down and therefore, the hull 20 is lifted out of the water. With the hull 20 fully jacked-up and out of the water, any wave action and heavy seas more easily break past the legs 25 as compared to the effect of waves against a large buoyant object like the hull 20.
  • the ice-worthy jack-up drilling rig 10 of the present invention is designed to resist ice floes by assuming an ice defensive, hull-in- water configuration as shown in Figure 3.
  • ice tends to dampen waves and rough seas, so the sea surface 12 appears less threatening, however, the hazards of the marine environment have only altered, and not lessened.
  • the hull 20 is lowered into the water to contact same, but not to the extent that the hull 20 would begin to float.
  • a significant portion of the weight of the rig 10 preferably remains on the legs 25 to hold the position of the rig 10 on the drill site against any pressure an ice flow might bring.
  • the rig 10 is lowered so that inwardly sloped, ice-bending surface 41 , as best seen in Figure 4 bridges the sea surface 12 to engage any floating ice that may come upon the rig 10.
  • the sloped ice-bending surface 41 runs from shoulder 42, which is at the edge of the deck 26, down to neckline 44. Ice deflector 45 extends downward from neckline 44.
  • the ice-bending surface 41 causes the leading edge of the ice floe 51 to submerge under the sea surface 12 and apply a significant bending force that breaks large ice floes into smaller, less damaging, less hazardous bits of ice. For example, it is conceivable that an ice floe being hundreds of feet and maybe miles across could come toward the rig 10. If the ice floe is broken into bits that are less than twenty feet in the longest dimension, such bits are able to pass around the rig 10 with much less concern.
  • a conical piled monopod has been pre-installed to the seafloor.
  • the conical piled monopod 60 is a structure that may be used in ice-prone, offshore locations at much lower cost as compared to a conventional gravity based structure (GBS).
  • a conical piled monopod 60 includes a body 65, a base 67 and a top deck 70.
  • the base 67 preferably has the form of a flange with holes or perforations spaced around the perimeter of the conical piled monopod 60.
  • the base 67 is arranged to rest on the seafloor 15.
  • the weight of the conical piled monopod is preferably carried by a plurality of pilings 68 that are driven deep into the seafloor 15 and then attached to the conical piled monopod 60. It is typical to drive the pilings 68 between about 35 and about 75 meters into the seabed to permanently fix the conical piled monopod 60 in its offshore location.
  • the pilings 68 are typically strong, but hollow tubes or pipe like structures that act like long nails and provide a very structurally efficient arrangement for a permanent platform for offshore hydrocarbon drilling and production operations.
  • the pilings have a relatively large diameter of between 1 and 3 meters with a wall thickness of about 2 to 10 cm.
  • One particular advantage of the present invention is that with the weight of the conical piled monopod 60 supported by the pilings 68, little or no seabed preparation is necessary prior to installation and to the extent there is any seabed preparation, it is principally to create a level seafloor to set the conical piled monopod 60 onto as the pilings 68 are installed.
  • a seabed comprising soft, muddy materials is not likely to be excavated and replaced with firmer materials.
  • the pilings 68 provide resistance to: (a) forces that cause structures to slide along the seafloor, (b) forces that cause structures to overturn such as forces acting several meters above the base of a structure; and (c) forces that cause vertical movement both upwardly and downwardly.
  • the resistance to both upward and downward motion or movement is important in resisting toppling forces that may be imposed by ice.
  • the pilings 68 at the front side of the conical piled monopod 60 resist lifting forces that ice may impose on the upstream side to resist toppling over while the pilings 68 at the far side or back side or downstream side of the conical piled monopod 60 resist downward motion that would allow the back side to roll deeper into the seafloor 15.
  • Using such long pilings provides a structurally efficient base for year around operations in an ice prone offshore ice environment that must resist ice loads that can be quite substantial.
  • the pilings act like nails that hold the platform in place and are structurally more efficient than in the case of a GBS where resistance to overturning is provided only by the size and weight of the structure.
  • the length and number of the pilings 68 will be dictated by the magnitude of the predicted vertical and lateral forces and by the strength of the soil layers into which the pilings are driven.
  • the pilings are strategically arranged around the periphery of the base 67 to provide resistance to sliding and toppling forces with maximum structural efficiency.
  • the base may include at least eight and preferably at least 16 pilings, and up to as many as 64 pilings, around the periphery at a spacing that would maximize structural efficiency and create a pile cluster where the number of clusters work together to resist lateral forces and support the conical piled monopod 60.
  • the pilings 68 typically extend between 35 and 75 meters into the seabed depending on predicted loads and the strength characteristics of the soil.
  • the conical piled monopod 60 is shown as an eight sided faceted structure but a round or circular configuration may also be employed. It is preferred that the structure be faceted for ease of fabrication having six, eight, or even 12 sides, preferably all being equal in dimension and where the conical piled monopod 60 is symmetrical.
  • the body 65 of the conical piled monopod 60 includes a sloped, ice-engaging surface 72 that extends from below the sea surface 12 to above the sea surface 12 such that ice in the sea, particularly floating ice, engages the body 65 at the sloped, ice-engaging surface 72.
  • the ice-engaging surface 72 extends around the periphery of the conical piled monopod 60 so that ice from any direction will come into contact with the body 65 at the ice-engaging surface 72.
  • the slope of the ice-engaging surface 72 causes any sheet of ice to rise up the slope and bend to a point of breaking and is typically between 40 degrees and 60 degrees from the horizontal and more preferably about 55 degrees from the horizontal.
  • the conical piled monopod includes a shape to turn away ice that pushes all the way up ice-engaging surface 72.
  • a deck 70 is at the top of the conical piled monopod 60 may be equipped with a drilling template for drilling many wells.
  • the conical piled monopod 60 is a substantial structure typically having a dimension of deck 70 being more than 75 meters across. While being large and strong, one advantage of a conical piled monopod over a gravity based structure is that it is generally lighter in weight or more particularly, density, prior to any water ballasting. Solid ballast material is generally not needed for a conical piled monopod. While a gravity based structure (GBS) typically has a density of from 0.21 tonnes/m to 0.25 tonnes/m , a conical piled monopod may be constructed to be 0.20 tonnes/m down to about 0.18 tonnes/m . Often, a GBS would need solid ballast to increase its weight to provide resistance to sliding and overturning.
  • the conical piled monopod 60 may be designed to be in lighter weight.
  • the lighter density of a conical piled monopod may also translate into lower fabrication and transportation cost, not including the lower installation cost due to the avoided site preparation costs for preparing the seafloor for a large GBS system and for the high density ballast material often added to a GBS.
  • conical piled monopods 60 may be equipped with a derrick and systems for drilling wells, there is a cost savings if the wells can be drilled by a jack-up rig as the conical piled monopod may be sized somewhat smaller and of course having cost savings on size alone, not to mention the cost savings for all the drilling related equipment and systems.
  • Drilling well through the conical piled monopod with an ice worthy drilling rig such as rig 10 provides additional cost savings in that the rig does not necessarily have to be towed away at the first sign of ice. More wells may be drilled per year with an ice worthy rig 10 that can stay on station longer into the fall when other drill rigs are long gone.
  • the drilling rig 10 moves in as shown in Figure 5 and sets up to drill down through the conical piled monopod 60 as shown in Figure 6.
  • tabs 75 extending out from base 67 that include pilings 68 to be secured to the seafloor 15.
  • Spud cans 28 closest to the conical piled monopod 60 are aligned to set into sockets on the top of the tabs 75 and held in place by clasps 78.
  • the rig 10 is provided additional resistance to movement by ice pressure by attaching to the conical piled monopod.
  • This arrangement has been described as an "Ahab Socket" referring to the captain in Moby Dick inserting his peg leg into a knothole in the boat to stabilize himself while hunting whales.
  • the legs 25 of the ice- worthy drilling rig 10 which will be constructed stronger than conventional legs for jack-up rigs will be able to withstand limited ice threats.
  • the ice-worthy drilling rig 10 has the option to stay on location, suspend drilling operations and assume an ice defensive configuration as shown in Figure 7. In this position, ice that comes into contact with either or both of the rig 10 and conical piled monopod 60 will be broken up and directed to pass around the system.
  • drilling may resume and when the ice becomes too thick, the rig 10 may be fully removed from the location until the following drilling season.
  • the hull 20 (as well as its strength) that provides ice bending and breaking capabilities and expands the time window for drilling that substantially lowers costs for ice prone locations. While it is preferred that the rig 10 sets up adjacent one of the facets of the conical piled monopod as shown in Figure 8, but may approach from any direction as indicated by 20A.
  • the hull 20 preferably has a faceted or multisided shape that provides the advantages of a circular or oval shape, and may be less expensive to construct.
  • the plates that make up the hull would likely be formed of flat sheets and so that the entire structure comprises segments of flat material such as steel would likely require less complication.
  • the ice-breaking surface would preferably extend at least about five meters above the water level, recognizing that water levels shift up and down with tides and storms and perhaps other influences. The height above the water level accommodates ice floes that are quite thick or having ridges that extend well above the sea surface 12, but since the height of the shoulder 42 is well above the sea surface 12, the tall ice floes will be forced down as they come into contact with the rig 10.
  • the deck 21 at the top of the hull 20 should be far enough above the water line so that waves are not able to wash across the deck.
  • the deck 25 is preferred to be at least 7 to 8 meters above the sea surface 12.
  • the neckline 42 is preferred to be at least 4 to 8 meters below the sea surface 12 to adequately bend the ice floes to break them up into more harmless bits.
  • the hull 20 is preferably in the range of 5-16 meters in height from the flat of bottom to the deck 20, more preferably 8-16 meters or 11-16 meters.
  • the legs 25 and the openings 27 through which they are connected to the hull 20 are within the perimeter of the ice deflector 45 so that the ice floes are less likely to contact the legs while the rig 10 is in its defensive ice condition configuration as shown in Figure 3 and sometimes called hull-in-water configuration.
  • the rig 10 does not have to handle every ice floe threat to significantly add value to oil and gas companies. If rig 10 can extend the drilling season by as little as a month, that would be a fifty percent improvement in some ice prone areas and therefore provide a very real cost saving benefit to the industry.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Environmental & Geological Engineering (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Acoustics & Sound (AREA)
  • Earth Drilling (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

La présente invention concerne une plateforme de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique, servant à la fois au forage de puits et à la production d'hydrocarbures en des emplacements susceptibles d'être pris par la glace. La plateforme de forage selon l'invention fonctionne comme une plateforme de forage auto-élévatrice classique lorsqu'elle se trouve en pleine eau avec la coque auto-élevée hors de l'eau. Cependant, dans des conditions où de la glace est présente, les jambes sont maintenues en place à l'aide d'emboîtures incorporées au fond océanique afin de résister au mouvement latéral de la plateforme de forage, et dans des douilles fixées à la plateforme monopode sur pile conique. La coque et la plateforme monopode sur pile conique sont constituées de surfaces d'écartement de la glace servant à écarter et à briser la glace entrant en contact avec la coque et la plateforme monopode.
PCT/US2011/057378 2010-10-21 2011-10-21 Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles WO2012054891A1 (fr)

Priority Applications (8)

Application Number Priority Date Filing Date Title
RU2013123049/03A RU2564711C2 (ru) 2010-10-21 2011-10-21 Самоподъемное буровое морское основание ледового класса с одиночной конической опорой на свайном основании и установочными гнездами
CA2811946A CA2811946C (fr) 2010-10-21 2011-10-21 Unite de forage auto-elevatrice specialement adaptee a la glace comportant une plateforme monopode sur pile conique et des douilles
US13/279,120 US8807875B2 (en) 2010-10-21 2011-10-21 Ice worthy jack-up drilling unit with conical piled monopod and sockets
KR1020137010002A KR20130120463A (ko) 2010-10-21 2011-10-21 파일링된 원뿔형 모노포드 및 소켓을 구비한 얼음에 적합한 잭-업 굴착선
CN201180050455.9A CN103180513B (zh) 2010-10-21 2011-10-21 抗冰型自升式钻井单元和钻井方法
EP11779048.5A EP2630303B1 (fr) 2010-10-21 2011-10-21 Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles
PCT/US2011/057378 WO2012054891A1 (fr) 2010-10-21 2011-10-21 Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles
SG2013022595A SG189116A1 (en) 2010-10-21 2012-10-21 Ice worthy jack-up drilling unit with conical piled monopod and sockets

Applications Claiming Priority (9)

Application Number Priority Date Filing Date Title
US40549710P 2010-10-21 2010-10-21
US61/405,497 2010-10-21
US41495010P 2010-11-18 2010-11-18
US61/414,950 2010-11-18
US13/277,755 2011-10-20
US13/277,791 US20120128426A1 (en) 2010-10-21 2011-10-20 Ice worthy jack-up drilling unit
US13/277,791 2011-10-20
US13/277,755 US8821071B2 (en) 2010-11-18 2011-10-20 Conical piled monopod
PCT/US2011/057378 WO2012054891A1 (fr) 2010-10-21 2011-10-21 Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles

Publications (1)

Publication Number Publication Date
WO2012054891A1 true WO2012054891A1 (fr) 2012-04-26

Family

ID=48173979

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2011/057378 WO2012054891A1 (fr) 2010-10-21 2011-10-21 Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles

Country Status (7)

Country Link
EP (1) EP2630303B1 (fr)
KR (1) KR20130120463A (fr)
CN (1) CN103180513B (fr)
CA (1) CA2811946C (fr)
RU (1) RU2564711C2 (fr)
SG (1) SG189116A1 (fr)
WO (1) WO2012054891A1 (fr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016192729A1 (fr) * 2015-05-29 2016-12-08 Maersk Drilling A/S Procédé de forage arctique

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3972199A (en) * 1972-06-26 1976-08-03 Chevron Research Company Low adhesional arctic offshore platform
WO2007126477A2 (fr) * 2006-03-30 2007-11-08 Exxonmobil Upstream Research Company Système de forage arctique pendant toute l'année, mobile

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1230745A (fr) * 1978-03-29 1987-12-29 James C. Pearce Construction marine, conique, multiangle, pour regions arctiques
FI822158L (fi) * 1982-06-15 1983-12-16 Waertsilae Oy Ab Borrningsplattform
RU2048372C1 (ru) * 1991-01-25 1995-11-20 Борис Борисович Клячкин Устройство для разрушения льда
RU2361039C2 (ru) * 2007-02-19 2009-07-10 Виктор Ильич Мищевич Способ сооружения многоопорной технологической платформы
CN201172814Y (zh) * 2007-12-04 2008-12-31 中国石油集团海洋工程有限公司 浅海自升式试采作业平台
CN100575613C (zh) * 2008-06-12 2009-12-30 天津大学 自动螺旋升降的主动抗冰装置

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3972199A (en) * 1972-06-26 1976-08-03 Chevron Research Company Low adhesional arctic offshore platform
WO2007126477A2 (fr) * 2006-03-30 2007-11-08 Exxonmobil Upstream Research Company Système de forage arctique pendant toute l'année, mobile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016192729A1 (fr) * 2015-05-29 2016-12-08 Maersk Drilling A/S Procédé de forage arctique
US10415315B2 (en) 2015-05-29 2019-09-17 Maersk Drilling A/S. Arctic drilling process

Also Published As

Publication number Publication date
SG189116A1 (en) 2013-05-31
EP2630303B1 (fr) 2015-07-22
CN103180513A (zh) 2013-06-26
CN103180513B (zh) 2016-06-08
CA2811946A1 (fr) 2012-04-26
KR20130120463A (ko) 2013-11-04
CA2811946C (fr) 2015-06-09
EP2630303A1 (fr) 2013-08-28
RU2013123049A (ru) 2014-11-27
RU2564711C2 (ru) 2015-10-10

Similar Documents

Publication Publication Date Title
CA2813426C (fr) Unite de forage auto-elevatrice specialement adaptee a la glace equipee d'un systeme de tension de pre-chargement
US8807875B2 (en) Ice worthy jack-up drilling unit with conical piled monopod and sockets
US8870497B2 (en) Ice worthy jack-up drilling unit with conical piled monopod
US20120125688A1 (en) Ice worthy jack-up drilling unit secured to the seafloor
US20120128432A1 (en) Ice worthy jack-up drilling unit with moon pool for protected drilling in ice
CA2812596C (fr) Unite de forage auto-elevatrice specialement adaptee a la glace avec agitation de gaz et protections de jambe contre la glace
US20120128426A1 (en) Ice worthy jack-up drilling unit
EP2630303B1 (fr) Unité de forage auto-élévatrice spécialement adaptée à la glace comportant une plateforme monopode sur pile conique et des douilles
CA2812597C (fr) Unite de forage auto-elevatrice specialement adaptee a la glace comportant une plateforme monopode sur pile conique
US8801333B2 (en) Ice worthy jack-up drilling unit with gas agitation and leg ice shields
CA2811938C (fr) Unite plate-forme de forage auto-elevatrice en milieu de glace a prevention de la glace a gaz en mouvement
WO2012054801A1 (fr) Unité de forage auto-élévatrice spécialement adaptée à la glace et fixée au fond de la mer

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11779048

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2811946

Country of ref document: CA

WWE Wipo information: entry into national phase

Ref document number: 2011779048

Country of ref document: EP

ENP Entry into the national phase

Ref document number: 20137010002

Country of ref document: KR

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2013123049

Country of ref document: RU

Kind code of ref document: A