WO2012030947A1 - System and method for paralleling electrical power generators - Google Patents

System and method for paralleling electrical power generators Download PDF

Info

Publication number
WO2012030947A1
WO2012030947A1 PCT/US2011/049949 US2011049949W WO2012030947A1 WO 2012030947 A1 WO2012030947 A1 WO 2012030947A1 US 2011049949 W US2011049949 W US 2011049949W WO 2012030947 A1 WO2012030947 A1 WO 2012030947A1
Authority
WO
WIPO (PCT)
Prior art keywords
alternator
electricity
electrical bus
parallel electrical
generator
Prior art date
Application number
PCT/US2011/049949
Other languages
French (fr)
Inventor
Douglas W. Dorn
Isaac S. Frampton
Original Assignee
Kohler Co.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kohler Co. filed Critical Kohler Co.
Priority to EP20167279.7A priority Critical patent/EP3694075A1/en
Priority to EP11822552.3A priority patent/EP2612413A4/en
Priority to CN201180029774.1A priority patent/CN102971927B/en
Publication of WO2012030947A1 publication Critical patent/WO2012030947A1/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/40Synchronising a generator for connection to a network or to another generator
    • H02J3/42Synchronising a generator for connection to a network or to another generator with automatic parallel connection when synchronisation is achieved

Definitions

  • the present invention relates to systems that use a plurality of electric power generators working together; and more particularly, to systems which operate multiple electric power generators in parallel to provide the power in a more efficient and flexible manner.
  • Standby generators provide electrical power when power is unavailable from an electric utility company (e.g. during weather disturbances) or to provide power at a remote location where utility company power is not available.
  • One type of standby electric generator comprises an internal combustion engine driving an electrical alternator that produces alternating electricity.
  • Other types of standby electric generators include photovoltaic arrays and wind turbine generators.
  • An electrical distribution system that has a parallel electrical bus through which power produced by a plurality of energy sources is supplied to electrical loads.
  • the energy sources includes a generator arrangement comprising an alternator, a circuit breaker, an output sensor, a bus sensor, and genset controller.
  • the alternator produces alternating electricity and the circuit breaker selectively connects and disconnects the alternator to and from the parallel electrical bus.
  • the output sensor senses a
  • characteristic of the alternating electricity such as voltage or current
  • the bus sensor sensing that characteristic of electricity in the parallel electrical bus
  • the genset controller is connected to the output sensor, the bus sensor and the circuit breaker, and controls the excitation and speed of the alternator. Prior to applying the alternating electricity to the parallel electrical bus, the genset controller:
  • the genset controller operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus; [0013] c) if electricity is present on the parallel electrical bus, then the genset controller:
  • [0015] 2 operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus.
  • each energy source can implement independently a load sharing function. This enables the power produced by an energy to be adjusted so that the total power demanded by all the loads is equitably divided among the different energy sources.
  • FIGURE 1 is a diagram showing an exemplary generator that has an
  • FIGURE 2 is a block schematic diagram of an exemplary electrical system that has a plurality of energy sources
  • FIGURE 3 is a flowchart of a synchronization process performed by each energy source upon starting.
  • FIGURE 4 is a flowchart of a load sharing function performed by each energy source.
  • a generator 10 sometimes called an engine generator set or simply a genset, comprises an prime mover, such as an internal combustion engine 12, coupled by a shaft 14 to an electrical alternator 16.
  • the generator 10 provides back-up electrical power to a building in the event that power from an electric utility company is interrupted. Such interruption is detected by an external device that sends a signal to a genset controller 22 which responds by sending a start command via a communication bus 20 to an engine control subsystem 24.
  • the communication bus 20 may conform to the Computer Area
  • CAN Controller Area Network
  • the generator 10 produces electrical power on a yacht.
  • the internal combustion engine 12 may also provide propulsion power for the yacht, in which case the alternator 16 is connected to the internal combustion engine through a transmission that enables the speed of the alternator to be varied independently of the speed of the internal combustion engine 12.
  • a standby generator may be provided to supply electrical power when the yacht is moored and operation of the main engine is not required for propulsion. When the yacht is at a dock, electrical power can be received from a connection to utility company lines on shore.
  • the genset controller 22 is a microcomputer based subsystem that executes a control program which governs the operation of the alternator 16.
  • a control program which governs the operation of the alternator 16.
  • An example of such a genset controller is described in U.S. Patent No. 6,555,929, which description is incorporated by reference herein.
  • the genset controller 22 receives signals from an operator control panel 18 and output sensors 26 that sense the voltage and the current levels of the electricity produced by the alternator 16.
  • the genset controller 22 regulates the output voltage by determining whether and by how much the sensed voltage level deviates from the nominal voltage level (e.g., 240 volts) that is desired.
  • the nominal voltage level e.g., 240 volts
  • any deviation causes the excitation controller 25 to employ a conventional voltage regulation technique that controls the engine speed and the excitation voltage applied to a field winding in the alternator 16.
  • the output voltage produced by the alternator 16 is regulated to a substantially constant level in a known manner.
  • the three-phase output 19 of the alternator 16 is fed through the output sensors 26 to three output lines 30 of the generator 10.
  • the genset controller 22 receives signals from the output sensors 26 indicating parameters of the alternator's electrical output, such as voltage and current levels, and from those signals derives the frequency and the polarity angle of the alternating voltage produced by the alternator.
  • a bus sensor in the form of a voltage sensor 38, is connected to one phase of the electrical distribution system so that the genset controller 22 can determine the magnitude, frequency, and polarity angle of the alternating voltage on the parallel electrical bus 42.
  • a breaker driver 28 is provided to operate external motorized circuit breakers to open and close a set of contacts that connect the output lines 30 to an electrical distribution system, as will be described.
  • the breaker driver 28 responds to a control signal from the genset controller 22 and conveys a status signal back to the genset controller 22 indicating the conductive state of the contacts, i.e., open or closed.
  • An optional normally-closed, manual circuit breaker 29 may be included for manually disconnecting the alternator output 19 from three output lines 30.
  • the genset controller 22 is coupled via a communication interface 32 to first and second communication links 34 and 36, over which data, commands and other messages are exchanged with external devices.
  • This communication employs a conventional protocol, such as RS485, CAN, or Ethernet. Hardwired or wireless communication links can be used.
  • the first communication link 34 handles messages related to synchronizing a plurality of energy sources that are connected in parallel to the same electrical distribution system.
  • the second communication link 36 interfaces the generator 10 to other external devices, such as monitoring equipment and a controller that manages electrical loads in a building.
  • an "energy source” generically refers to an apparatus that produces single-phase or three-phase electricity.
  • an exemplary electrical distribution system 40 comprises a three-phase parallel electrical bus 42 that has separate conductors A, B and C.
  • the parallel electrical bus 42 is coupled to utility company lines 44 by an automatic transfer switch (ATS) 45.
  • ATS automatic transfer switch
  • This automatic transfer switch 45 is similar to conventional devices that detect when electricity from the utility lines 44 is interrupted, such as when power lines are knocked down during a storm. When the utility line electricity is interrupted, the automatic transfer switch 45 sends a signal indicating that event via control line 46, and then opens contacts which disconnect the utility lines 44 from the parallel electrical bus 42.
  • the exemplary electrical distribution system 40 has a plurality of energy sources 47, 48, and 49 comprising first, second and third generators (gensets) 51 , 52, and 53 individually connected to the parallel electrical bus 42 by motorized circuit breakers 56, 57, and 58, respectively.
  • Another energy source s 50 includes an alternative energy producer 50, such as a photovoltaic array, a wind turbine generator, a geothermal driven electrical generator, a heat pump, or a similar device, also is connected to the parallel electrical bus 42 by another motorized circuit breaker 59.
  • an alternative energy producer 50 such as a photovoltaic array, a wind turbine generator, a geothermal driven electrical generator, a heat pump, or a similar device
  • a lesser or greater number of energy sources than are illustrated can be provided.
  • the present technique for paralleling multiple energy sources enables both three-phase and single-phase energy sources to be connected to the three-phase parallel electrical bus 42.
  • the first and second generators 51 and 52 are three-phase devices
  • the third generator 53 is a single-phase device which is only
  • phase lines B and C of the parallel electrical bus 42 are connected to phase lines B and C of the parallel electrical bus 42.
  • the single- phase third generator 53 is actively connected to the parallel electrical bus when the three-phase energy sources are inactive.
  • the parallel electrical bus 42 is connected through a distribution panel 60 to various loads within a structure 65, such as a building or a vehicle.
  • the loads are coupled to the power distribution panel by individual contactors 62, which can be electrically operated to disconnect specific loads from the power distribution panel 60 and thus from the parallel electrical bus 42.
  • Those contactors 62 are operated by a computerized controller, commonly referred to as a load manager 64, in the structure.
  • the load manager 64 also is connected to a plurality of load sensors 66 that measure the magnitudes of power consumed by the various electrical loads.
  • load managers are conventional devices that monitor the magnitude of all the electrical loads being powered and compare the aggregate power requirements of those loads to the total amount of electrical power available from the parallel electrical bus 42.
  • the load manager 64 opens one or more of the contactors 62 to disconnect the associated load from the parallel electrical bus 42. This operation is often referred to as "load shedding.” For example, during an extremely hot day, the electric utility company may request that customers shed or disconnect nonessential loads from the electrical utility lines because of the high demand for electricity resulting from increased operation of air conditioning systems.
  • the backup power supplied by the various energy sources 47-49 can be allocated to only high priority or essential loads by the load manager 64 within building 65 operating the contactors 62 to disconnect low priority or non-essential loads. For example, during such an interrupted power condition, backup power in a hospital will be allocated first to life support systems and other critical loads, whereas non-essential loads, such as most building lights, can be disconnected. Such a load manager is commonplace in buildings.
  • the electrical distribution system 40 utilizes an improved and unique process for activating and managing multiple energy sources and synchronizing the outputs of those sources so that the electricity they produce can be combined on the same parallel electrical bus.
  • the automatic transfer switch 45 upon disconnecting the utility company lines 44, sends an interruption message over control line 46 to the load manager 64 in the building 65.
  • the load manager 64 responds in a conventional manner by operating selected contactors 62 to disconnect non-essential loads from the parallel electrical bus 42. Subsequently, should the energy sources 47-49 apply a sufficient the amount of current to the parallel electrical bus 42 to power all the loads, any previously opened contactor 62 can be closed so that both essential and
  • non-essential loads are powered during the utility line interruption.
  • manager knows the maximum power generation capacity of all the energy sources 47-49 and senses the power demands of each load circuit extending from the power distribution panel 60.
  • the load manager 64 further responds to the interruption message from the automatic transfer switch 45 by sending start commands via the second communication link 36 to the first and second energy sources 47and 48.
  • the third energy source 49 has a single-phase generator 53 and is only started in special situations, as will be described.
  • the interruption message on control line 46 from the automatic transfer switch 45 can be communicated directly to each of the first and second energy sources 47and 48 and functions as the start command. In that latter case, the interruption message is applied directly to an input of the genset controller 22 within each of the generators 51-53, as shown in Figure 1. In either case, first and second energy sources 47and 48 respond to that start command by commencing the production of electricity.
  • the computer in each the genset controller 22 or in another type of energy source independently executes a software synchronization routine 70 which ensures that the alternating electricity from all the energy sources is phase synchronized.
  • This software routine is in addition to the conventional program that the genset controller 22 executes to govern the operation of the generator 10.
  • the synchronization routine 70 commences at step 72 upon the receipt of the start command.
  • the genset controller 22 sends an activation signal via bus 20 to the engine control subsystem 24 instructing that the engine 12 be started at step 74.
  • the genset controller begins monitoring the magnitude and frequency of the output voltage produced by alternator 16.
  • the genset controller 22 inspects the signals received from the output sensors 26 to ascertain those electrical parameters.
  • a determination is made at step 78 whether the output voltage has a magnitude and a frequency that are acceptable for applying the electricity from the alternator 16 to the parallel electrical bus 42.
  • the frequency of the alternating output voltage should be at or within an acceptable range of the nominal frequency (50 or 60 Hz) for the alternating electricity.
  • the magnitude of the output voltage also should be within a predefined tolerance of the nominal voltage level (e.g., 240 volts). If the output of the alternator 16 has not yet reached the acceptable levels, the execution of the synchronization routine 70 returns to step 76. The control process loops through steps 76 and 78 until the alternator output is found to have reached an acceptable level.
  • step 80 a determination is made whether another energy source is already connected to the parallel electrical bus 42. That determination is made by the genset controller 22 inspecting the input from the voltage sensor 38 which indicates whether an electrical voltage is present on the parallel electrical bus 42.
  • the voltage sensor 38 only detects the phase voltage between conductors B and C of the parallel electrical bus 42, although all three-phase voltages could be sensed.
  • a current sensor may be to detect electricity on the bus in place of the voltage sensor 38.
  • step 84 acknowledgements are not received from all of the other energy sources, execution of the synchronization routine 70 returns to step 80 to determine whether another source now is applying electricity to the parallel electrical bus 42. This looping continues until either electricity is found on that bus or acknowledgement messages are received from all the other energy sources. If necessary, a standard conflict resolution technique is employed to enable one of the energy sources to be the first one to connect to the parallel electrical bus 42.
  • the synchronization routine 70 advances to step 86 at which the genset controller 22 in the first generator (genset) 51 sends a command to the breaker driver 28 which in turn activates the associated motorized circuit breaker 56. This causes that circuit breaker 56 to connect the output lines 30 of the first generator 51 to the parallel electrical bus 42. Thereafter, execution of the synchronization routine in the first generator terminates.
  • the second generator 52 continues to execute its synchronization routine 70.
  • the electricity produced by the other energy sources cannot be applied to the parallel electrical bus 42 unless that electricity is in phase synchronization with the electricity already present on that bus.
  • synchronization routine execution by each other energy source e.g. second generator 52, now discovers the electricity from the first generator 51 on the parallel electrical bus 42 at step 80 and branches to step 90.
  • the phase relationship between the output voltage produced by the respective alternator 16 and the voltage on the parallel electrical bus 42 is determined by the genset controller 22.
  • the BC output voltage level, detected by the output sensors 26, is inspected to determine the output voltage polarity angle.
  • polarity angle detection of the BC voltage on the parallel electrical bus 42 is performed using the output from the voltage sensor 38. The difference between those voltage polarity angles indicates whether the alternating electricity produced by the energy source is synchronized with the alternating electricity on the parallel electrical bus.
  • the polarity angles of the alternating currents at the alternator output and in the parallel electrical bus 42 can be used to determine when the output of the respective alternator 16 is synchronized to the parallel electrical bus 42.
  • step 92 the difference between those voltage polarity angles is inspected to determine whether the alternator output is in synchronization with the electricity on the parallel electrical bus 42. That synchronization is considered as occuring when the voltage polarity angle difference is zero or at least less than a predefined small tolerable amount. If the output of the second generator 52 is not in synchronism, the software synchronization routine 70 advances to step 94 where the genset controller 22 issues a command to the engine control subsystem 24 to change the speed of the engine 12 to alter the frequency of the output of the alternator 16.
  • the genset controller 22 uses the magnitude of the voltage polarity angle difference and whether its generator's output is leading or lagging the alternating bus voltage to determine whether the engine speed should be increased or decreased and by how much.
  • the engine control subsystem 24 varies the speed of the engine 12 in a conventional manner, such as by controlling the engine throttle to varies the supply of fuel.
  • the synchronization routine 70 returns to step 90 to repeat sensing the two voltages and determining whether they are or are not in synchronism.
  • step 92 the output of the second generator 52 is found to be synchronized with the voltage present on the parallel electrical bus 42, at which time the process branches to step 95.
  • a speed command is sent by the genset controller 22 to the engine control subsystem 24 indicating that the engine 12 should be operated at the nominal speed for generating the appropriate electrical frequency (i.e., 50 or 60 Hz).
  • the genset controller sends an activation signal to the breaker driver 28 which responds by closing the associated circuit breaker 57, thereby connecting the output lines 30 of the second generator 52 to the parallel electrical bus 42. Execution of the synchronization routine 70 by the second generator 52 then terminates at step 98.
  • each of the other energy sources synchronizes its output voltage waveform to the alternating bus voltage.
  • the synchronization routine 70 executed in each of the energy sources 47-49 ensures that its respective electrical output is synchronized and compatible with the electricity already present on the parallel electrical bus.
  • the synchronization is performed independently by each of those other energy sources which eliminates the need for external devices to perform the synchronization analysis and send separate instructions to each energy source.
  • each energy source contains the intelligence to perform its own synchronization
  • additional energy sources can be added to an existing electrical distribution system 40 without having to modify the previously installed equipment and control apparatus.
  • Such an additional energy source merely has to be connected to the parallel electrical bus 42 and to the two communication links 34 and 36. If a load manager 64 is not present, an additional connection may have to be made to the control line 46 from the automatic transfer switch 45 to receive the start command.
  • the operation of the synchronization routine 70 has been described in the context of engine-generators sets (gensets) 51-53, a similar routine is executed by a controller within the other types of energy sources.
  • the other energy sources have mechanisms for synchronizing their electrical output to the electricity already present on the parallel electrical bus 42.
  • wind turbine generators and photovoltaic arrays typically have inverters that convert internal DC voltage to an alternating output voltage.
  • the inverter can be controlled to shift the phase of the output voltage to synchronize that alternating voltage waveform with the alternating voltage on present on utility lines.
  • the present invention also enables the controller in each energy source 47-49 to perform load sharing which equitably distributes power demands of the loads the among the energy sources without requiring an additional centralized controller. That is achieved by operating all the energy sources at approximately the same proportion of their maximum power capacity. Even if the energy sources 47-49 do not have the same power generating capacity (i.e. identical maximum power rating), operating each one at the same proportion of its maximum power capacity equitably shares the power requirements of the loads among all the operating energy sources.
  • each genset controller 22 periodically determines the magnitude of both the real and reactive power being supplied at its outputs 19.
  • Each generator 51-53 executes a load sharing function 100 depicted by the flowchart in Figure 4.
  • the respective genset controller 22 reads the output voltage and current levels from the associated output sensors 26 and at step 104 uses conventional techniques to derive values indicating the real power and the reactive power being produced.
  • the real power value is compared to a maximum real power rating for the generator at step 106 to determine the percentage of the maximum real power rating that is being produced, thus yielding a real power percentage.
  • the measured reactive power value is compared to a maximum reactive power rating for the generator to determine the percentage of the maximum reactive power rating that is being produced, thus yielding a reactive power percentage.
  • the genset controller 22 sends its real power percentage and reactive power percentage to the other energy sources 47-49 via the first communication link 34 at step 108. Therefore, every energy source knows the level at which all the energy sources are operating.
  • Each genset controller 22 compares its real power percentage and reactive power percentage to those of the other energy sources to determine whether the respective energy source is producing more or less than its equitable share of the overall power demand. For example, a given genset controller 22 at step 110 computes the average real power percentage for all the active energy sources 47-49 and computes the average reactive power percentage for all the energy sources. Thereafter at step 112, the genset controller 22 alters operation of the respective alternator 16 to produce that average percentage of its maximum real power rating. For an energy source that is an engine-generator set, the real power is controlled by varying the fuel flow to the engine 12. Thus the engine throttle is varied until the alternator produces the desired amount of real power.
  • Operation of the respective alternator 16 also is adjusted to produce the average percentage of its maximum reactive power rating.
  • the reactive power is controlled by varying the excitation of the field winding in the alternator 16.
  • the load sharing function 100 is performed periodically by each energy source 47-49, thereby accommodating dynamic changes in the electrical distribution system 40. In this manner, all the energy sources tend to operate at the same proportion of their maximum power capacity without requiring a separate central controller that governs the load sharing.
  • the electrical distribution system 40 also performs other load management techniques. For example, at certain time of the day the electrical loads are reduced to a level that can be satisfied efficiently by less than all of the available energy sources. In one instance where the electrical distribution system is on a yacht, very few electrical devices are active at night when the yacht is moored in a harbor. The entire electrical load may comprise a relatively small number of lights, that may even be powered by a single-phase of electic current. In contrast, the moored yacht during the daytime has many active electrical loads, such as cooking equipment in the galley, entertainment systems, and a larger number of interior lights. Therefore, at a predefined time during the night, the load manager 64 for the yacht automatically opens the contactors 62 for predetermined electrical loads that normally are inactive at that time. The contactors remaining closed are connected to the B and C lines of the parallel electrical bus 42.
  • the load manager 64 transmits a start command over the second communication link 36 to the third generator (genset) 53.
  • the third generator 53 is a single-phase source which normally is in a dormant state when one ot both of the three-phase first and second generators 51 and 52 is active. After the third generator 53 begins producing an acceptable output level that is synchronized to the electricity already present on the parallel electrical bus 42, the third circuit breaker 58 is closed to apply the third generator's output to that bus. This event is signalled to the load manager 64 via the second communication link 36 which reacts by sending a shutdown command over that link to the first and second generators 51 and 52.
  • the load manager 64 issues commands that restart the dormant three-phase, first and second energy sources 47 and 48. Once those energy sources are up to speed and their outputs are synchronized to the electricity present on the parallel electrical bus 42, the associated circuit breaker 56 or 57 closes. After the first and second energy sources 47 and 48 are applying current to the parallel electrical bus 42, the third energy source 49 is disconnected from that bus and shut down. Then the load manager 64 closes the contactors for all the loads so that the yacht is fully powered for another day.

Abstract

A plurality of generators can be connected in parallel to a common electrical bus. Each generator has a controller that regulates the voltage and frequency of the electricity being produced. Before a given generator connects to the electrical bus, its controller senses whether electricity is present on the bus and if not, the connection is made. Otherwise, the controller synchronizes the electricity being produced to the electricity is present on the bus before the connection occurs. The controller in each generator may also implement a load sharing function which ensures that the plurality of generators equitably share in providing the total amount of power demanded by the loads. The load sharing can be accomplished by controlling the generators to operate a substantially identical percentages of their individual maximum power generation capacity.

Description

SYSTEM AND METHOD FOR
PARALLELING ELECTRICAL POWER GENERATORS
Cross-Reference to Related Applications
Not Applicable
Statement Regarding Federally
Sponsored Research or Development
Not Applicable
Background of the Invention
1. Field of the Invention
[0001] The present invention relates to systems that use a plurality of electric power generators working together; and more particularly, to systems which operate multiple electric power generators in parallel to provide the power in a more efficient and flexible manner.
2. Description of the Related Art
[0002] Standby generators provide electrical power when power is unavailable from an electric utility company (e.g. during weather disturbances) or to provide power at a remote location where utility company power is not available. One type of standby electric generator comprises an internal combustion engine driving an electrical alternator that produces alternating electricity. Other types of standby electric generators include photovoltaic arrays and wind turbine generators.
[0003] For electrical systems that require large amounts of power, there can be advantages to employing multiple small generators, rather than a single large generator. In this regard, if one generator fails or requires maintenance, a multi-generator system can still supply some power, whereas a single generator system will not. Further, in a multi-generator system load growth can be accommodated by adding another generator, rather than bearing the cost of replacing a single very large generator with an even larger one.
[0004] Furthermore, large generators present difficulties in shipping and installation complexity. Thus by using several smaller generators one can distribute the overall generator weight over a broader area, avoiding the need for special strengthening of the supporting area (e.g. of a roof). Moreover, some smaller generators require less frequent maintenance. A variety of generator systems with multiple generator sets have been described previously as in U.S. patents 4,136,286, 6,653,821 and 7,656,060.
[0005] Nevertheless, when using multiple generators with outputs connected in parallel, there is a need to synchronize the alternating electricity that each device produces. This involves matching phase angles of the alternating output voltage and current from each generator. In addition, the magnitude of the voltage produced by each generator must be identical. Traditional generator paralleling techniques have been quite complex, often requiring several additional pieces of equipment to achieve the needed functions. This may include separate synchronizers, load managers, and/or switch gear. Moreover, prior art paralleling systems can require significant time to synchronize the operation of the multiple generators once a power need is appreciated.
[0006] In addition, traditional systems are not well suited to mix the power from different types of energy sources (e.g. single-phase generators with three-phase generators), or to address mechanical and electrical load differences, or to address differences in optimal generator usage based on noise, fuel and other requirements at particular times during the day.
[0007] One company has noted that conventional two-generator paralleling systems often have as many as fourteen controllers to manage speed, load sharing, synchronization, voltage regulation, the internal combustion engine, and load protection. They then proposed to reduce the number of controllers by creating an integrated digital control, an integrated paralleling switch, and an integrated master control that are linked by a communication bus to the individual generators. This system, however, still requires additional control equipment beyond the controllers in each generator, adding cost and complexity to the overall system.
[0008] Hence, there is a need for improvements in the design of systems for paralleling and operating multi-generator systems.
Summary of the Invention
[0009] An electrical distribution system that has a parallel electrical bus through which power produced by a plurality of energy sources is supplied to electrical loads. The energy sources includes a generator arrangement comprising an alternator, a circuit breaker, an output sensor, a bus sensor, and genset controller. The alternator produces alternating electricity and the circuit breaker selectively connects and disconnects the alternator to and from the parallel electrical bus. The output sensor senses a
characteristic of the alternating electricity, such as voltage or current, and the bus sensor sensing that characteristic of electricity in the parallel electrical bus.
[0010] The genset controller is connected to the output sensor, the bus sensor and the circuit breaker, and controls the excitation and speed of the alternator. Prior to applying the alternating electricity to the parallel electrical bus, the genset controller:
[0011] a) determines whether electricity is present on the parallel electrical bus;
[0012] b) if electricity is not present on the parallel electrical bus, the genset controller operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus; [0013] c) if electricity is present on the parallel electrical bus, then the genset controller:
[0014] 1) varies operation of the alternator to synchronize the alternating electricity produced by the alternator to the electricity present on the parallel electrical bus; and thereafter
[0015] 2) operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus.
[0016] In another aspect of the electrical distribution system enables a single-phase generator to supply power to the parallel electrical bus at certain times when the aggregate load is relatively small, and enables a three-phase generator to supply power to the parallel electrical bus at other times.
[0017] It should be appreciated that this system avoids the need for many equipment parts previously required to achieve the paralleling of multiple energy sources on the same electrical bus. It further provides flexibility as to the types of power and loads that the system can accommodate.
[0018] Alternative energy sources such as wind turbines, solar generators, heat pumps, and the like can also be readily incorporated.
[0019] Optionally, each energy source can implement independently a load sharing function. This enables the power produced by an energy to be adjusted so that the total power demanded by all the loads is equitably divided among the different energy sources. [0020] The foregoing and other advantages of the present invention will be apparent from the following description. In that description reference is made to the accompanying drawings which form a part thereof, and in which there is shown by way of illustration, and not limitation, preferred embodiments of the invention.
Such embodiments do not necessarily represent the full scope of the invention, and reference should therefore be made to the claims herein for interpreting the scope of the invention.
Brief Description of the Drawings
[0001] FIGURE 1 is a diagram showing an exemplary generator that has an
alternator which incorporates the present invention;
[0021] FIGURE 2 is a block schematic diagram of an exemplary electrical system that has a plurality of energy sources;
[0022] FIGURE 3 is a flowchart of a synchronization process performed by each energy source upon starting; and
[0023] FIGURE 4 is a flowchart of a load sharing function performed by each energy source.
Detailed Description of the Invention
[0024] With initial reference to Figure 1 , a generator 10, sometimes called an engine generator set or simply a genset, comprises an prime mover, such as an internal combustion engine 12, coupled by a shaft 14 to an electrical alternator 16. In one application, the generator 10 provides back-up electrical power to a building in the event that power from an electric utility company is interrupted. Such interruption is detected by an external device that sends a signal to a genset controller 22 which responds by sending a start command via a communication bus 20 to an engine control subsystem 24. The communication bus 20 may conform to the Computer Area
Network (CAN) J- 1939 standard promulgated by SAE International, however, other communication bus protocols may be used. The genset controller 22 and the engine control subsystem 24 respectively control operation of the alternator 16 and the internal combustion engine 12.
[0025] In another application, the generator 10 produces electrical power on a yacht. There the internal combustion engine 12 may also provide propulsion power for the yacht, in which case the alternator 16 is connected to the internal combustion engine through a transmission that enables the speed of the alternator to be varied independently of the speed of the internal combustion engine 12. A standby generator may be provided to supply electrical power when the yacht is moored and operation of the main engine is not required for propulsion. When the yacht is at a dock, electrical power can be received from a connection to utility company lines on shore.
[0026] The genset controller 22 is a microcomputer based subsystem that executes a control program which governs the operation of the alternator 16. An example of such a genset controller is described in U.S. Patent No. 6,555,929, which description is incorporated by reference herein. The genset controller 22 receives signals from an operator control panel 18 and output sensors 26 that sense the voltage and the current levels of the electricity produced by the alternator 16. The genset controller 22 regulates the output voltage by determining whether and by how much the sensed voltage level deviates from the nominal voltage level (e.g., 240 volts) that is desired. Any deviation causes the excitation controller 25 to employ a conventional voltage regulation technique that controls the engine speed and the excitation voltage applied to a field winding in the alternator 16. By selectively controlling the intensity of the magnetic field emitted from the field winding, the output voltage produced by the alternator 16 is regulated to a substantially constant level in a known manner.
[0027] The three-phase output 19 of the alternator 16 is fed through the output sensors 26 to three output lines 30 of the generator 10. The genset controller 22 receives signals from the output sensors 26 indicating parameters of the alternator's electrical output, such as voltage and current levels, and from those signals derives the frequency and the polarity angle of the alternating voltage produced by the alternator. A bus sensor, in the form of a voltage sensor 38, is connected to one phase of the electrical distribution system so that the genset controller 22 can determine the magnitude, frequency, and polarity angle of the alternating voltage on the parallel electrical bus 42. A breaker driver 28 is provided to operate external motorized circuit breakers to open and close a set of contacts that connect the output lines 30 to an electrical distribution system, as will be described. The breaker driver 28 responds to a control signal from the genset controller 22 and conveys a status signal back to the genset controller 22 indicating the conductive state of the contacts, i.e., open or closed. An optional normally-closed, manual circuit breaker 29 may be included for manually disconnecting the alternator output 19 from three output lines 30.
[0028] The genset controller 22 is coupled via a communication interface 32 to first and second communication links 34 and 36, over which data, commands and other messages are exchanged with external devices. This communication employs a conventional protocol, such as RS485, CAN, or Ethernet. Hardwired or wireless communication links can be used. The first communication link 34 handles messages related to synchronizing a plurality of energy sources that are connected in parallel to the same electrical distribution system. The second communication link 36 interfaces the generator 10 to other external devices, such as monitoring equipment and a controller that manages electrical loads in a building.
[0029] Several of the generators 10 can be connected in parallel as energy sources in an electrical distribution system. As used herein, an "energy source" generically refers to an apparatus that produces single-phase or three-phase electricity. With reference to Figure 2, an exemplary electrical distribution system 40 comprises a three-phase parallel electrical bus 42 that has separate conductors A, B and C. The parallel electrical bus 42 is coupled to utility company lines 44 by an automatic transfer switch (ATS) 45. This automatic transfer switch 45 is similar to conventional devices that detect when electricity from the utility lines 44 is interrupted, such as when power lines are knocked down during a storm. When the utility line electricity is interrupted, the automatic transfer switch 45 sends a signal indicating that event via control line 46, and then opens contacts which disconnect the utility lines 44 from the parallel electrical bus 42. Whereas, some automatic transfer switches, upon disconnecting the utility lines, also connect a standby energy source to the parallel electrical bus, that connection does not occur in the present distribution system 40. Instead, separate circuit breakers 56-59 are employed to individually connect each standby energy source 47-50 to the parallel electrical bus 42, as will be described. [0030] Specifically, the exemplary electrical distribution system 40 has a plurality of energy sources 47, 48, and 49 comprising first, second and third generators (gensets) 51 , 52, and 53 individually connected to the parallel electrical bus 42 by motorized circuit breakers 56, 57, and 58, respectively. Another energy source s 50 includes an alternative energy producer 50, such as a photovoltaic array, a wind turbine generator, a geothermal driven electrical generator, a heat pump, or a similar device, also is connected to the parallel electrical bus 42 by another motorized circuit breaker 59. A lesser or greater number of energy sources than are illustrated can be provided. The present technique for paralleling multiple energy sources enables both three-phase and single-phase energy sources to be connected to the three-phase parallel electrical bus 42. In this regard, note that the first and second generators 51 and 52 are three-phase devices, whereas the third generator 53 is a single-phase device which is only
connected to phase lines B and C of the parallel electrical bus 42. Normally the single- phase third generator 53 is actively connected to the parallel electrical bus when the three-phase energy sources are inactive.
[0031] The parallel electrical bus 42 is connected through a distribution panel 60 to various loads within a structure 65, such as a building or a vehicle. In some installations, the loads are coupled to the power distribution panel by individual contactors 62, which can be electrically operated to disconnect specific loads from the power distribution panel 60 and thus from the parallel electrical bus 42. Those contactors 62 are operated by a computerized controller, commonly referred to as a load manager 64, in the structure. The load manager 64 also is connected to a plurality of load sensors 66 that measure the magnitudes of power consumed by the various electrical loads. Such load managers are conventional devices that monitor the magnitude of all the electrical loads being powered and compare the aggregate power requirements of those loads to the total amount of electrical power available from the parallel electrical bus 42. Under specific conditions or at predefined times of the day, the load manager 64 opens one or more of the contactors 62 to disconnect the associated load from the parallel electrical bus 42. This operation is often referred to as "load shedding." For example, during an extremely hot day, the electric utility company may request that customers shed or disconnect nonessential loads from the electrical utility lines because of the high demand for electricity resulting from increased operation of air conditioning systems. In addition, as will be further described, when electricity from the utility company lines 44 is unavailable, the backup power supplied by the various energy sources 47-49 can be allocated to only high priority or essential loads by the load manager 64 within building 65 operating the contactors 62 to disconnect low priority or non-essential loads. For example, during such an interrupted power condition, backup power in a hospital will be allocated first to life support systems and other critical loads, whereas non-essential loads, such as most building lights, can be disconnected. Such a load manager is commonplace in buildings.
Industrial Applicability
[0032] The electrical distribution system 40 utilizes an improved and unique process for activating and managing multiple energy sources and synchronizing the outputs of those sources so that the electricity they produce can be combined on the same parallel electrical bus. Assume that the electricity from the utility lines 44 is interrupted and that the energy sources 47-49 need to be activated to supply power to the loads. At such time, the automatic transfer switch 45, upon disconnecting the utility company lines 44, sends an interruption message over control line 46 to the load manager 64 in the building 65. The load manager 64 responds in a conventional manner by operating selected contactors 62 to disconnect non-essential loads from the parallel electrical bus 42. Subsequently, should the energy sources 47-49 apply a sufficient the amount of current to the parallel electrical bus 42 to power all the loads, any previously opened contactor 62 can be closed so that both essential and
non-essential loads are powered during the utility line interruption. The load
manager knows the maximum power generation capacity of all the energy sources 47-49 and senses the power demands of each load circuit extending from the power distribution panel 60.
[0033] The load manager 64 further responds to the interruption message from the automatic transfer switch 45 by sending start commands via the second communication link 36 to the first and second energy sources 47and 48. Note that the third energy source 49 has a single-phase generator 53 and is only started in special situations, as will be described. Alternatively, if the electrical distribution system 40 does not have a load manager 64, the interruption message on control line 46 from the automatic transfer switch 45 can be communicated directly to each of the first and second energy sources 47and 48 and functions as the start command. In that latter case, the interruption message is applied directly to an input of the genset controller 22 within each of the generators 51-53, as shown in Figure 1. In either case, first and second energy sources 47and 48 respond to that start command by commencing the production of electricity.
[0034] With reference to Figure 3, the computer in each the genset controller 22 or in another type of energy source, independently executes a software synchronization routine 70 which ensures that the alternating electricity from all the energy sources is phase synchronized. This software routine is in addition to the conventional program that the genset controller 22 executes to govern the operation of the generator 10.
[0035] The synchronization routine 70 commences at step 72 upon the receipt of the start command. In response, the genset controller 22 sends an activation signal via bus 20 to the engine control subsystem 24 instructing that the engine 12 be started at step 74. Then, the genset controller begins monitoring the magnitude and frequency of the output voltage produced by alternator 16. Specifically, at step 76, the genset controller 22 inspects the signals received from the output sensors 26 to ascertain those electrical parameters. A determination is made at step 78 whether the output voltage has a magnitude and a frequency that are acceptable for applying the electricity from the alternator 16 to the parallel electrical bus 42. For example, the frequency of the alternating output voltage should be at or within an acceptable range of the nominal frequency (50 or 60 Hz) for the alternating electricity. The magnitude of the output voltage also should be within a predefined tolerance of the nominal voltage level (e.g., 240 volts). If the output of the alternator 16 has not yet reached the acceptable levels, the execution of the synchronization routine 70 returns to step 76. The control process loops through steps 76 and 78 until the alternator output is found to have reached an acceptable level.
[0036] Once the alternator output is acceptable, the synchronization routine 70 advances to step 80 at which a determination is made whether another energy source is already connected to the parallel electrical bus 42. That determination is made by the genset controller 22 inspecting the input from the voltage sensor 38 which indicates whether an electrical voltage is present on the parallel electrical bus 42. The voltage sensor 38 only detects the phase voltage between conductors B and C of the parallel electrical bus 42, although all three-phase voltages could be sensed. Alternatively, a current sensor may be to detect electricity on the bus in place of the voltage sensor 38.
[0037] Assume that the first generator 51 reaches an acceptable operating level before the second generator 52, thus electricity is not present on the parallel electrical bus (the bus id "dead"). Now the synchronization routine 70 executed by the first generator 51 advances to step 82 at which a "first on" message is broadcast over the first
communication link 34 indicating that this energy source 47 is now in a proper operating state and wants to be first one to connect to the parallel electrical bus 42. That message is received by the other energy sources which reply with an acknowledge message stating that they are not yet at an acceptable operating level and granting permission for the first generator 51 to apply its electrical output to the parallel electrical bus 42. If at step 84, acknowledgements are not received from all of the other energy sources, execution of the synchronization routine 70 returns to step 80 to determine whether another source now is applying electricity to the parallel electrical bus 42. This looping continues until either electricity is found on that bus or acknowledgement messages are received from all the other energy sources. If necessary, a standard conflict resolution technique is employed to enable one of the energy sources to be the first one to connect to the parallel electrical bus 42.
[0038] When all the acknowledgement messages are received, the synchronization routine 70 advances to step 86 at which the genset controller 22 in the first generator (genset) 51 sends a command to the breaker driver 28 which in turn activates the associated motorized circuit breaker 56. This causes that circuit breaker 56 to connect the output lines 30 of the first generator 51 to the parallel electrical bus 42. Thereafter, execution of the synchronization routine in the first generator terminates.
[0039] At this time, the second generator 52 continues to execute its synchronization routine 70. The electricity produced by the other energy sources cannot be applied to the parallel electrical bus 42 unless that electricity is in phase synchronization with the electricity already present on that bus. To that end, synchronization routine execution by each other energy source, e.g. second generator 52, now discovers the electricity from the first generator 51 on the parallel electrical bus 42 at step 80 and branches to step 90. At this juncture in Figure 3, the phase relationship between the output voltage produced by the respective alternator 16 and the voltage on the parallel electrical bus 42 is determined by the genset controller 22. The BC output voltage level, detected by the output sensors 26, is inspected to determine the output voltage polarity angle. At the same time, polarity angle detection of the BC voltage on the parallel electrical bus 42 is performed using the output from the voltage sensor 38. The difference between those voltage polarity angles indicates whether the alternating electricity produced by the energy source is synchronized with the alternating electricity on the parallel electrical bus. Alternatively the polarity angles of the alternating currents at the alternator output and in the parallel electrical bus 42 can be used to determine when the output of the respective alternator 16 is synchronized to the parallel electrical bus 42.
[0040] At step 92, the difference between those voltage polarity angles is inspected to determine whether the alternator output is in synchronization with the electricity on the parallel electrical bus 42. That synchronization is considered as occuring when the voltage polarity angle difference is zero or at least less than a predefined small tolerable amount. If the output of the second generator 52 is not in synchronism, the software synchronization routine 70 advances to step 94 where the genset controller 22 issues a command to the engine control subsystem 24 to change the speed of the engine 12 to alter the frequency of the output of the alternator 16. The genset controller 22 uses the magnitude of the voltage polarity angle difference and whether its generator's output is leading or lagging the alternating bus voltage to determine whether the engine speed should be increased or decreased and by how much. The engine control subsystem 24 varies the speed of the engine 12 in a conventional manner, such as by controlling the engine throttle to varies the supply of fuel. After issuing the engine speed command, the synchronization routine 70 returns to step 90 to repeat sensing the two voltages and determining whether they are or are not in synchronism.
[0041] Eventually at step 92, the output of the second generator 52 is found to be synchronized with the voltage present on the parallel electrical bus 42, at which time the process branches to step 95. Here, a speed command is sent by the genset controller 22 to the engine control subsystem 24 indicating that the engine 12 should be operated at the nominal speed for generating the appropriate electrical frequency (i.e., 50 or 60 Hz). Then at step 96, the genset controller sends an activation signal to the breaker driver 28 which responds by closing the associated circuit breaker 57, thereby connecting the output lines 30 of the second generator 52 to the parallel electrical bus 42. Execution of the synchronization routine 70 by the second generator 52 then terminates at step 98.
[0042] In this manner, once one of the energy sources connects to the parallel electrical bus 42, each of the other energy sources synchronizes its output voltage waveform to the alternating bus voltage. In this matter, the synchronization routine 70 executed in each of the energy sources 47-49 ensures that its respective electrical output is synchronized and compatible with the electricity already present on the parallel electrical bus. Thus, the synchronization is performed independently by each of those other energy sources which eliminates the need for external devices to perform the synchronization analysis and send separate instructions to each energy source.
[0043] With this technique, since each energy source contains the intelligence to perform its own synchronization, additional energy sources can be added to an existing electrical distribution system 40 without having to modify the previously installed equipment and control apparatus. Such an additional energy source merely has to be connected to the parallel electrical bus 42 and to the two communication links 34 and 36. If a load manager 64 is not present, an additional connection may have to be made to the control line 46 from the automatic transfer switch 45 to receive the start command.
[0044] Although the operation of the synchronization routine 70 has been described in the context of engine-generators sets (gensets) 51-53, a similar routine is executed by a controller within the other types of energy sources. The other energy sources have mechanisms for synchronizing their electrical output to the electricity already present on the parallel electrical bus 42. For example, wind turbine generators and photovoltaic arrays typically have inverters that convert internal DC voltage to an alternating output voltage. The inverter can be controlled to shift the phase of the output voltage to synchronize that alternating voltage waveform with the alternating voltage on present on utility lines. [0045] In addition to providing the synchronization, the present invention also enables the controller in each energy source 47-49 to perform load sharing which equitably distributes power demands of the loads the among the energy sources without requiring an additional centralized controller. That is achieved by operating all the energy sources at approximately the same proportion of their maximum power capacity. Even if the energy sources 47-49 do not have the same power generating capacity (i.e. identical maximum power rating), operating each one at the same proportion of its maximum power capacity equitably shares the power requirements of the loads among all the operating energy sources.
[0046] For this load sharing function 100, each genset controller 22 periodically determines the magnitude of both the real and reactive power being supplied at its outputs 19. Each generator 51-53 executes a load sharing function 100 depicted by the flowchart in Figure 4. At step 102, the respective genset controller 22 reads the output voltage and current levels from the associated output sensors 26 and at step 104 uses conventional techniques to derive values indicating the real power and the reactive power being produced. The real power value is compared to a maximum real power rating for the generator at step 106 to determine the percentage of the maximum real power rating that is being produced, thus yielding a real power percentage. Similarly the measured reactive power value is compared to a maximum reactive power rating for the generator to determine the percentage of the maximum reactive power rating that is being produced, thus yielding a reactive power percentage.
[0047] Then, the genset controller 22 sends its real power percentage and reactive power percentage to the other energy sources 47-49 via the first communication link 34 at step 108. Therefore, every energy source knows the level at which all the energy sources are operating.
[0048] Each genset controller 22 compares its real power percentage and reactive power percentage to those of the other energy sources to determine whether the respective energy source is producing more or less than its equitable share of the overall power demand. For example, a given genset controller 22 at step 110 computes the average real power percentage for all the active energy sources 47-49 and computes the average reactive power percentage for all the energy sources. Thereafter at step 112, the genset controller 22 alters operation of the respective alternator 16 to produce that average percentage of its maximum real power rating. For an energy source that is an engine-generator set, the real power is controlled by varying the fuel flow to the engine 12. Thus the engine throttle is varied until the alternator produces the desired amount of real power. Operation of the respective alternator 16 also is adjusted to produce the average percentage of its maximum reactive power rating. The reactive power is controlled by varying the excitation of the field winding in the alternator 16. The load sharing function 100 is performed periodically by each energy source 47-49, thereby accommodating dynamic changes in the electrical distribution system 40. In this manner, all the energy sources tend to operate at the same proportion of their maximum power capacity without requiring a separate central controller that governs the load sharing.
[0049] The electrical distribution system 40 also performs other load management techniques. For example, at certain time of the day the electrical loads are reduced to a level that can be satisfied efficiently by less than all of the available energy sources. In one instance where the electrical distribution system is on a yacht, very few electrical devices are active at night when the yacht is moored in a harbor. The entire electrical load may comprise a relatively small number of lights, that may even be powered by a single-phase of electic current. In contrast, the moored yacht during the daytime has many active electrical loads, such as cooking equipment in the galley, entertainment systems, and a larger number of interior lights. Therefore, at a predefined time during the night, the load manager 64 for the yacht automatically opens the contactors 62 for predetermined electrical loads that normally are inactive at that time. The contactors remaining closed are connected to the B and C lines of the parallel electrical bus 42.
[0050] Then the load manager 64 transmits a start command over the second communication link 36 to the third generator (genset) 53. The third generator 53 is a single-phase source which normally is in a dormant state when one ot both of the three-phase first and second generators 51 and 52 is active. After the third generator 53 begins producing an acceptable output level that is synchronized to the electricity already present on the parallel electrical bus 42, the third circuit breaker 58 is closed to apply the third generator's output to that bus. This event is signalled to the load manager 64 via the second communication link 36 which reacts by sending a shutdown command over that link to the first and second generators 51 and 52. Those energy sources respond by opening the respective circuit breakers 56 and 57 and terminating operation, thereby leaving only the single-phase third generator 53 active to supply the necessary power. Therefore, only the smaller third generator 53 is active which reduces diminishes engine fuel consumption and minimizes machinery noise during the night. [0051] At a prescribed time the next morning, the load manager 64 issues commands that restart the dormant three-phase, first and second energy sources 47 and 48. Once those energy sources are up to speed and their outputs are synchronized to the electricity present on the parallel electrical bus 42, the associated circuit breaker 56 or 57 closes. After the first and second energy sources 47 and 48 are applying current to the parallel electrical bus 42, the third energy source 49 is disconnected from that bus and shut down. Then the load manager 64 closes the contactors for all the loads so that the yacht is fully powered for another day.
[0052] The foregoing description was primarily directed to a preferred embodiment of the invention. Although some attention was given to various alternatives within the scope of the invention, it is anticipated that one skilled in the art will likely realize additional alternatives that are now apparent from disclosure of embodiments of the invention. Accordingly, the scope of the invention should be determined from the following claims and not limited by the above disclosure.

Claims

CLAIMS What is claimed is:
1. A generator arrangement for supplying electricity to a parallel electrical bus to which at least one other energy source is able to supply electricity, said generator arrangement comprising:
an alternator that produces alternating electricity;
a circuit breaker selectively connecting and disconnecting the alternator to and from the parallel electrical bus;
an output sensor for sensing at least one of voltage and current of the alternating electricity;
a bus sensor for sensing at least one of voltage and current of electricity in the parallel electrical bus; and
a genset controller connected to the output sensor, the bus sensor and the circuit breaker, and operatively connected to control excitation and speed of the alternator; prior to applying the alternating electricity to the parallel electrical bus, the genset controller: a) determines whether electricity is present on the parallel electrical bus, b) if electricity is not present on the parallel electrical bus, the genset controller operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus,
c) if electricity is present on the parallel electrical bus, then the genset controller:
1) varies operation of the alternator to synchronize the alternating electricity produced by the alternator to the electricity present on the parallel electrical bus, and thereafter 2) operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus.
2. The generator arrangement as recited in claim 1 further comprising an internal combustion engine driving the alternator; and the genset controller varies operation of the alternator by altering speed of the internal combustion engine.
3. The generator arrangement as recited in claim 1, wherein the genset controller varies operation of the alternator by altering speed of the alternator.
4. The generator arrangement as recited in claim 1, wherein the alternator comprises a field winding that produces a magnetic field; and the genset controller varying operation of the alternator comprises altering the magnetic field.
5. The generator arrangement as recited in claim 1, further comprising a communication interface for exchanging messages with all other energy sources.
6. The generator arrangement as recited in claim 5, wherein the genset controller sends a message via the communication interface to inform other energy sources that the alternating electricity produced by the alternator is about to be applied to the parallel electrical bus.
7. The generator arrangement as recited in claim 6, wherein the genset controller operates the circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus only upon receiving a response message other energy sources
8. The generator arrangement as recited in claim 1, wherein the genset controller further implements a load sharing function by:
determining a given operating level of the alternator;
detecting an operating level of each of the other energy sources; and
adjusting operation of the alternator so that the given operating level is substantially identical to the operating levels of the other energy sources.
9. The generator arrangement as recited in claim 1, wherein the genset controller further implements a load sharing function by:
determining a given percentage of a maximum power capacity at which the alternator is operating;
detecting a percentage of a respective maximum power capacity at which each other energy source is operating, thereby producing a percentage set;
calculating an average percentage from the given percentage and the percentage set; and
adjusting operation of the alternator so that the given percentage substantially equals the average percentage.
10. The generator arrangement as recited in claim 9 wherein implementation of the load sharing function by the genset controller further comprises sending an indication of the given percentage to other energy sources.
11. A system for supplying electricity to a parallel electrical bus, said system comprising:
a first generator arrangement having a first alternator that produces alternating electricity at an output, a first circuit breaker selectively connecting and disconnecting the output of the first alternator to and from the parallel electrical bus, a first output sensor for sensing a characteristic of the alternating electricity produced by the first alternator, a first bus sensor for sensing the characteristic of electricity in the parallel electrical bus, and a first genset controller connected to the first output sensor, the first bus sensor and the first circuit breaker, and operatively connected to control excitation and speed of the first alternator; and
a second generator arrangement having a second alternator that produces alternating electricity at an output, a second circuit breaker selectively connecting and disconnecting the output of the second alternator to and from the parallel electrical bus, a second output sensor for sensing a parameter of the alternating electricity produced by the second alternator, a second bus sensor for sensing the parameter of electricity in the parallel electrical bus, and a second genset controller connected to the second output sensor, the second bus sensor and the second circuit breaker, and operatively connected to control excitation and speed of the second alternator;
wherein each of the first and second genset controller:
a) determines whether electricity is present on the parallel electrical bus;
b) if electricity is not present on the parallel electrical bus, operates a respective one of the first and second circuit breaker to apply the alternating electricity to the parallel electrical bus; c) if electricity is present on the parallel electrical bus, then the first or second genset controller:
1) varies operation of a respective one of the first and second alternator to synchronize the alternating electricity produced by that alternator to the electricity present on the parallel electrical bus; and thereafter
2) operates a respective one of the first and second circuit breaker to apply the alternating electricity to the parallel electrical bus.
12. The system as recited in claim 1 1, wherein the first generator produces three-phase electricity and the second generator produces single-phase electricity.
13. The system as recited in claim 1 1, wherein the first generator is an engine-generator set.
14. The system as recited in claim 1 1, wherein the second generator is selected from the group consisting of a photovoltaic array, a wind turbine generator, a geothermal powered electrical generator, and a heat pump,
15. A method for operating a generator arrangement to furnish alternating electricity to a parallel electrical bus to which one or more other energy sources also supply electricity, wherein the generator arrangement has an alternator that produces the alternating and a genset controller that regulates a voltage and a frequency of the alternating electricity, said method comprising:
the genset controller performing steps of:
a) sensing whether electricity is present on the parallel electrical bus; b) if electricity is not present on the parallel electrical bus, operating a circuit breaker to apply the alternating electricity produced by the alternator to the parallel electrical bus;
c) if electricity is present on the parallel electrical bus:
1) synchronizing the alternating electricity produced by the alternator to the electricity on the parallel electrical bus; and thereafter
2) operating the circuit breaker to apply the alternating electricity to the parallel electrical bus.
16. The method as recited in claim 15 further comprising, when the genset controller determines that electricity is not present on the parallel electrical bus, sending a message to the other energy sources; and operating a circuit breaker to apply the alternating electricity to the parallel electrical bus only upon receipt of a reply message from all the other energy sources.
17. The method as recited in claim 15 wherein synchronizing the electricity comprises:
sensing a given occurrence of a characteristic of the alternating electricity produced by the generator;
sensing a particular occurrence of the characteristic of the electricity on the parallel electrical bus;
determining a difference in time between the given occurrence and the particular occurrence; and
altering operation of the first generator so that the difference in time is no greater that a predefined amount.
18. The method as recited in claim 17 wherein altering operation of the first generator comprising varying speed of the first generator.
19. The method as recited in claim 15 further comprising the genset controller: measuring a first level of power produced by the alternator;
detecting levels of power produced by the other energy sources; and
adjusting operation of the alternator so that the alternator and the other energy sources produce substantially identical levels of power.
20. The method as recited in claim 15 further comprising:
determining a first percentage of a given maximum power capacity at which the alternator is operating;
for each other energy source, detecting a percentage of respective maximum power capacities at which each other energy source is operating, thereby producing a percentage set;
calculating an average percentage from the first percentage and the percentage set; and
adjusting operation of the first generator until the alternator is operating at the average percentage of the given maximum power capacity.
21. The method as recited in claim 20 further comprising sending an indication of the first percentage to the other energy sources.
22. The method as recited in claim 20 wherein detecting a percentage for each other energy source comprises receiving value from each other energy source.
23. A method for operating a generator arrangement to furnish alternating electricity to a parallel electrical bus to which one or more other energy sources are able to supply electricity, wherein the generator arrangement has an alternator that produces the alternating electricity and a genset controller that regulates voltage and frequency of the alternating electricity, said method comprising the genset controller:
measuring a first level of power produced by the alternator;
for each other energy source, detecting a level of power being produced; and adjusting operation of the alternator so that the alternator and the other energy sources produce substantially identical levels of power.
24. The method as recited in claim 23 wherein:
measuring a first level of power comprises determining a first percentage of a maximum power capacity at which the alternator is operating;
for each other energy source, detecting a percentage of a respective maximum power capacity at which that other energy source is operating, thereby producing a percentage set; and
adjusting operation of the alternator comprises calculating an average percentage from the first percentage and the percentage set, and adjusting the alternator so that the first percentage substantially equals the average percentage.
25. The method as recited in claim 24 wherein detecting a percentage comprises receiving an indication of that percentage from another energy source.
26. The method as recited in claim 24 further comprising sending an indication of the first percentage to each other energy source.
PCT/US2011/049949 2010-09-01 2011-08-31 System and method for paralleling electrical power generators WO2012030947A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
EP20167279.7A EP3694075A1 (en) 2010-09-01 2011-08-31 System and method for paralleling electrical power generators
EP11822552.3A EP2612413A4 (en) 2010-09-01 2011-08-31 System and method for paralleling electrical power generators
CN201180029774.1A CN102971927B (en) 2010-09-01 2011-08-31 For the system and method for parallel generator

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US12/873,608 2010-09-01
US12/873,608 US8766479B2 (en) 2010-09-01 2010-09-01 System and method for paralleling electrical power generators

Publications (1)

Publication Number Publication Date
WO2012030947A1 true WO2012030947A1 (en) 2012-03-08

Family

ID=45696176

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2011/049949 WO2012030947A1 (en) 2010-09-01 2011-08-31 System and method for paralleling electrical power generators

Country Status (4)

Country Link
US (1) US8766479B2 (en)
EP (2) EP2612413A4 (en)
CN (1) CN102971927B (en)
WO (1) WO2012030947A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103529716A (en) * 2012-07-02 2014-01-22 科勒公司 Generator management system that selectively activates generators based on an operating parameter
WO2016019012A1 (en) * 2014-07-29 2016-02-04 Innovus Power, Inc. Method of optimizing dispatch of variable speed engine-generator sets
US9368972B2 (en) 2012-07-27 2016-06-14 Kohler Co. Generator management system that determines a time to activate and deactivate generators based on the load level
US9778632B2 (en) 2012-07-02 2017-10-03 Kohler Co. Generator management system and method that selectively activate at least one of a plurality of generators in a power generation system

Families Citing this family (41)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9509139B1 (en) * 2010-12-28 2016-11-29 Reliance Controls Corporation Transfer switch for automatically switching neutrals for one or more loads between two electrical sources of power
US9293924B2 (en) * 2011-02-15 2016-03-22 Raytheon Company Electrical phase synchronization
US9128130B2 (en) * 2011-09-15 2015-09-08 Schweitzer Engineering Laboratories, Inc. Systems and methods for synchronizing distributed generation systems
US9562715B2 (en) * 2012-03-21 2017-02-07 Thermo King Corporation Power regulation system for a mobile environment-controlled unit and method of controlling the same
WO2013155264A1 (en) * 2012-04-11 2013-10-17 Kirk Jones Stackable multi-unit power take-off assembly for atv
US9698625B2 (en) 2012-07-02 2017-07-04 Kohler Co. Power generation system with anticipatory operation
US9903617B2 (en) * 2013-03-15 2018-02-27 Hotstart, Inc. Engine heater control system
US10089641B2 (en) * 2013-08-28 2018-10-02 San Diego Gas & Electric Company Interconnect socket adapter for adapting one or more power sources and power sinks
US9787099B2 (en) * 2013-09-12 2017-10-10 Kohler, Co. Automatic diagnosis or repair for a generator controller
US9543874B2 (en) * 2013-12-06 2017-01-10 Fca Us Llc Dual alternator system
US9882386B2 (en) * 2014-04-23 2018-01-30 Nec Corporation Consensus-based distributed cooperative control for microgrid voltage regulation and reactive power sharing
US9979337B2 (en) * 2014-04-24 2018-05-22 Generac Power Systems, Inc. Method of loadshedding for a variable speed, constant frequency generator
US10277229B2 (en) 2014-04-25 2019-04-30 Kohler Co. Communication over generator bus
US9350281B2 (en) * 2014-05-09 2016-05-24 Alonso Rodiguez Circuit and method for frequency synthesis for signal detection in automatic voltage regulation for synchronous generators
US9467080B2 (en) * 2014-08-13 2016-10-11 Kohler, Co. Protective functions for parallel generators
US10069331B2 (en) 2015-01-09 2018-09-04 Generac Power Systems, Inc. Load shed module
US9689330B2 (en) * 2015-01-28 2017-06-27 Kohler Co. DPF regeneration in a power system that includes parallel generators
US9798342B2 (en) 2015-02-23 2017-10-24 Schweitzer Engineering Laboratories, Inc. Detection and correction of fault induced delayed voltage recovery
US9580129B2 (en) 2015-05-13 2017-02-28 Burromax LLC Assembly comprising an internal combustion engine selectively couple to generator and to another mechanically driven device
US10697367B2 (en) 2015-06-29 2020-06-30 Enchanted Rock, Ltd. Engine generator set with a more compact, modular design and improved cooling characteristics
CN108475924B (en) * 2015-12-18 2021-04-23 瓦锡兰芬兰有限公司 Power plant and method for controlling a power plant
US9800055B2 (en) * 2016-01-21 2017-10-24 Schweitzer Engineering Laboratories, Inc. Synchronization of generators using a common time reference
CN105715363A (en) * 2016-03-21 2016-06-29 江苏鲲鹏电力设备有限公司 Fuel-saved and energy-saved diesel generator
US10291028B2 (en) * 2016-07-29 2019-05-14 Cummins Power Generation Ip, Inc. Masterless distributed power transfer control
DE102016116573A1 (en) * 2016-09-05 2018-03-08 Wobben Properties Gmbh Method for transmitting control manipulated variables from a controller, in particular a wind farm controller of a wind farm, to units and to a unit to be controlled and a controller
US11108242B2 (en) 2016-12-05 2021-08-31 Ge Aviation Systems, Llc Method and system for load sharing among multiple DC generators
JP6875907B2 (en) * 2017-03-30 2021-05-26 本田技研工業株式会社 Generator system
US10312694B2 (en) 2017-06-23 2019-06-04 Schweitzer Engineering Laboratories, Inc. Mode-based output synchronization using relays and a common time source
US10734814B2 (en) 2017-08-14 2020-08-04 Caterpillar Inc. Maintenance optimization control system for load sharing between engines
US10256638B2 (en) 2017-08-24 2019-04-09 Ge Aviation Systems Llc Method and system for operating a set of generators
US10691149B2 (en) * 2017-09-13 2020-06-23 Ge Aviation Systems Llc Controller and method for operating a power distribution system
US11479080B2 (en) * 2018-10-19 2022-10-25 Systematic Power Manufacturing, Llc Hybrid energy power module for mobile electrical devices
US11245266B2 (en) * 2018-11-13 2022-02-08 Kohler Co. Offline synchronization of generators
CN109921468B (en) * 2019-04-12 2023-08-18 福建广通机电科技有限公司 Parallel operation control method for small single-phase generator set
US11539316B2 (en) 2019-07-30 2022-12-27 General Electric Company Active stability control of compression systems utilizing electric machines
US11146073B2 (en) 2019-11-01 2021-10-12 Caterpillar Inc. System and method for optimization of engines on a common variable frequency bus
WO2021150820A1 (en) 2020-01-24 2021-07-29 Cummins Power Generation Inc. Power system sequencing scheme for any arbitrary topology
EP4094336A1 (en) 2020-01-24 2022-11-30 Cummins Power Generation Inc. Scalable rules-based object-oriented power system control scheme
WO2021150822A1 (en) * 2020-01-24 2021-07-29 Cummins Power Generation Inc. Object based robust and redundant distributed power system control
US20230174215A1 (en) * 2021-12-02 2023-06-08 Brunswick Corporation Marine propulsion and generator systems and methods
US20240097588A1 (en) * 2022-08-04 2024-03-21 Google Llc Synthetic generator synchronization

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3185857A (en) * 1960-02-01 1965-05-25 Lear Siegler Inc Control apparatus for the parallel operation of alternators
US4136286A (en) 1977-07-05 1979-01-23 Woodward Governor Company Isolated electrical power generation system with multiple isochronous, load-sharing engine-generator units
US5754033A (en) * 1996-03-13 1998-05-19 Alaska Power Systems Inc. Control system and circuits for distributed electrical-power generating stations
US6104171A (en) 1998-11-23 2000-08-15 Caterpillar Inc. Generator set with redundant bus sensing and automatic generator on-line control
US6555929B1 (en) * 2000-10-24 2003-04-29 Kohler Co. Method and apparatus for preventing excessive reaction to a load disturbance by a generator set
US6653821B2 (en) 2001-06-15 2003-11-25 Generac Power Systems, Inc. System controller and method for monitoring and controlling a plurality of generator sets
US7019495B2 (en) * 2003-08-28 2006-03-28 C.E. Neihoff & Co. Inter-regulator control of multiple electric power sources
US20080277945A1 (en) 2007-05-07 2008-11-13 Cummins Power Generation Ip, Inc. Protection techniques for a back-up electric power system
US7656060B2 (en) 2007-10-31 2010-02-02 Caterpillar Inc. Power system with method for adding multiple generator sets

Family Cites Families (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4879624A (en) 1987-12-24 1989-11-07 Sundstrand Corporation Power controller
US5168208A (en) 1988-05-09 1992-12-01 Onan Corporation Microprocessor based integrated generator set controller apparatus and method
US5182464A (en) 1991-01-09 1993-01-26 Techmatics, Inc. High speed transfer switch
US5729059A (en) 1995-06-07 1998-03-17 Kilroy; Donald G. Digital no-break power transfer system
US5734255A (en) 1996-03-13 1998-03-31 Alaska Power Systems Inc. Control system and circuits for distributed electrical power generating stations
US5949153A (en) * 1997-03-06 1999-09-07 Consolidated Natural Gas Service Company, Inc. Multi-engine controller
US6668629B1 (en) 1999-11-26 2003-12-30 General Electric Company Methods and apparatus for web-enabled engine-generator systems
US6522030B1 (en) * 2000-04-24 2003-02-18 Capstone Turbine Corporation Multiple power generator connection method and system
US6631310B1 (en) 2000-09-15 2003-10-07 General Electric Company Wireless engine-generator systems digital assistant
US6657416B2 (en) 2001-06-15 2003-12-02 Generac Power Systems, Inc. Control system for stand-by electrical generator
US6639331B2 (en) * 2001-11-30 2003-10-28 Onan Corporation Parallel generator power system
US6914763B2 (en) 2002-01-15 2005-07-05 Wellspring Heritage, Llc Utility control and autonomous disconnection of distributed generation from a power distribution system
US6892145B2 (en) 2002-02-25 2005-05-10 General Electric Company Method and system for conditionally triggered system data capture
US6847297B2 (en) 2003-01-06 2005-01-25 General Electric Company Locator devices and methods for centrally controlled power distribution systems
DE102006001984A1 (en) 2006-01-16 2007-07-19 Robert Bosch Gmbh Method and device for providing a supply voltage by means of parallel-connected generator units
US7816813B2 (en) * 2006-09-28 2010-10-19 Asco Power Technologies, L.P. Method and apparatus for parallel engine generators
US7557544B2 (en) 2007-04-23 2009-07-07 Cummins Power Generation Ip, Inc. Zero crossing detection for an electric power generation system
US8106633B2 (en) * 2008-12-18 2012-01-31 Caterpillar Inc. Generator set control system
CN101494384B (en) * 2008-12-25 2010-12-08 吴晓勇 Control circuit for multi-machine parallel connection of sine-wave generator and multi-machine parallel connection system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3185857A (en) * 1960-02-01 1965-05-25 Lear Siegler Inc Control apparatus for the parallel operation of alternators
US4136286A (en) 1977-07-05 1979-01-23 Woodward Governor Company Isolated electrical power generation system with multiple isochronous, load-sharing engine-generator units
US5754033A (en) * 1996-03-13 1998-05-19 Alaska Power Systems Inc. Control system and circuits for distributed electrical-power generating stations
US6104171A (en) 1998-11-23 2000-08-15 Caterpillar Inc. Generator set with redundant bus sensing and automatic generator on-line control
US6555929B1 (en) * 2000-10-24 2003-04-29 Kohler Co. Method and apparatus for preventing excessive reaction to a load disturbance by a generator set
US6653821B2 (en) 2001-06-15 2003-11-25 Generac Power Systems, Inc. System controller and method for monitoring and controlling a plurality of generator sets
US7019495B2 (en) * 2003-08-28 2006-03-28 C.E. Neihoff & Co. Inter-regulator control of multiple electric power sources
US20080277945A1 (en) 2007-05-07 2008-11-13 Cummins Power Generation Ip, Inc. Protection techniques for a back-up electric power system
US7656060B2 (en) 2007-10-31 2010-02-02 Caterpillar Inc. Power system with method for adding multiple generator sets

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP2612413A4

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103529716A (en) * 2012-07-02 2014-01-22 科勒公司 Generator management system that selectively activates generators based on an operating parameter
US9431942B2 (en) 2012-07-02 2016-08-30 Kohler Co. Generator management system that selectively activates generators based on an operating parameter
CN103529716B (en) * 2012-07-02 2016-09-07 科勒公司 The generator management system of generator is activated selectively according to operating parameter
US9778632B2 (en) 2012-07-02 2017-10-03 Kohler Co. Generator management system and method that selectively activate at least one of a plurality of generators in a power generation system
US10649420B2 (en) 2012-07-02 2020-05-12 Kohler Co. Generator management system and method that selectively activate at least one of a plurality of generators in a power generation system
US9368972B2 (en) 2012-07-27 2016-06-14 Kohler Co. Generator management system that determines a time to activate and deactivate generators based on the load level
WO2016019012A1 (en) * 2014-07-29 2016-02-04 Innovus Power, Inc. Method of optimizing dispatch of variable speed engine-generator sets

Also Published As

Publication number Publication date
US20120049638A1 (en) 2012-03-01
EP2612413A4 (en) 2017-08-30
CN102971927A (en) 2013-03-13
CN102971927B (en) 2016-01-06
EP2612413A1 (en) 2013-07-10
EP3694075A1 (en) 2020-08-12
US8766479B2 (en) 2014-07-01

Similar Documents

Publication Publication Date Title
US8766479B2 (en) System and method for paralleling electrical power generators
US20120205986A1 (en) Multiple single phase generator configuration
US10156225B2 (en) Method for black starting wind turbine, wind farm, and restoring wind farm and wind turbine, wind farm using the same
US8519565B2 (en) Generator set control system
US8106633B2 (en) Generator set control system
US20090160187A1 (en) Control system and method for operating a wind farm in a balanced state
US8987930B2 (en) Wind farm and method for operating a wind farm
US20120200155A1 (en) Electric power distribution methods and apparatus
EP3308444B1 (en) Method and apparatus for control of intelligent loads in microgrids
EP2690738B1 (en) Generator management system that determines a time to activate and deactivate generators based on the load level
US9467070B2 (en) Decentralized power generation plant having a device and method for detecting an island network
AU2010285341B2 (en) Power regulating system for solar power station
US20110320053A1 (en) Control system having user-defined connection criteria
JPH10201105A (en) Photovoltaic power generation system
JP2013063000A (en) System interconnection protection system, system interconnection protection device, and power conditioner
EP3350898B1 (en) Micro-grid having a diesel generator with clutch
CN109792152B (en) Non-master distributed power transmission control
KR101644522B1 (en) Power supply system of ac microgrid three phase
Zhou et al. Grid-connected and islanded operation of a hybrid power system
JP2018207574A (en) Microgrid control system and method
US20140203647A1 (en) Distributed power generation system and method of operating the same
Astriani et al. Load sharing control between PV power plant and diesel generator to mitigate effect of PV fluctuation using PID algorithm
CN114204604A (en) Load sharing with interconnect power generation
US20200076201A1 (en) Island Grid And Method For Operating An Island Grid
Zhang et al. Generator Automatic Control System

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 201180029774.1

Country of ref document: CN

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11822552

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 2011822552

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2564/MUMNP/2012

Country of ref document: IN

NENP Non-entry into the national phase

Ref country code: DE