WO2011147479A1 PCT/EP2010/064904 EP2010064904W WO2011147479A1 WO 2011147479 A1 WO2011147479 A1 WO 2011147479A1 EP 2010064904 W EP2010064904 W EP 2010064904W WO 2011147479 A1 WO2011147479 A1 WO 2011147479A1
Authority
WO
WIPO (PCT)
Prior art keywords
pile
wedge
collar
sleeve
foundation
Prior art date
Application number
PCT/EP2010/064904
Other languages
French (fr)
Inventor
Henrik Stiesdal
Original Assignee
Siemens Aktiengesellschaft
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens Aktiengesellschaft filed Critical Siemens Aktiengesellschaft
Priority to DK10765419.6T priority Critical patent/DK2576917T3/en
Priority to EP10765419.6A priority patent/EP2576917B1/en
Publication of WO2011147479A1 publication Critical patent/WO2011147479A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0073Details of sea bottom engaging footing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines

Definitions

  • a foundation for a wind turbine installation refers to a foundation for a wind turbine in ⁇ stallation, comprising a connection to one or more piles which can be driven into a seabed, and a connected pile- sleeve encasing the pile.
  • monopole foundations consist of a steel pile which is driven into the seabed.
  • Gravity founda ⁇ tions consist of a large base constructed from either con ⁇ crete or steel or a combination, which rests on the seabed. The wind turbine is dependent on gravity to remain erect.
  • Tripod foundations consist of three legs comprising piles on each end which are driven into the seabed. This type is gen ⁇ erally used at deeper depths. Usually the tripods are an ⁇ chored to the seabed and embedded into a pile sleeve by fill- ing the sleeve with concrete so that a bonding is effected by grouting .
  • a similar foundation is used for jacket foundations.
  • a jacket foundation consisting of a framework of tubes with different diameters is disclosed, which is fixed to a seabed by vertical tubes through which piles are driven into the seabed.
  • a grouting material is used, which requires curing be ⁇ fore subsequent installation steps can be performed.
  • connection further comprises a clamp connection, whereby the pile comprises a pile-collar, securely fixed to the pile, and the pile-collar and the pile-sleeve are connected by a wedge joint with mating wedge surfaces.
  • the present invention is based on the idea that instead of using concrete or grouting material for establishing a connection of the foundation to an underground like a seabed a clamp connection can be used which can be installed easier. Due to the fact that no grouting material is needed which normally has to be cured, the installation procedure can be shortened substantially. Another advantage of the clamp con ⁇ nection of the inventive foundation for a wind turbine in ⁇ stallation is that it is possible to dismantle the connection without destruction. Therefore according to the invention the wind turbine installation or a foot of the wind turbine installation is connected to the seabed by vertical forces so that a wedge joint is established, whereby the pile-collar is wedged with the pile-sleeve.
  • the pile- sleeve comprises a sleeve-collar with an inclined wedge sur ⁇ face.
  • the pile-sleeve which encases the pile-collar is equipped with the inclined wedge surface, which forms part of the wedge joint.
  • the inclined wedge surface is arranged such that it has a smaller diameter towards the underground and a larger diameter towards the wind turbine tower. Therefore the inclined wedge surface can cooperate with another wedge surface which is fixed to the wind turbine installation or a foot of the wind turbine installation so that this second wedge surface can be moved towards the inclined wedge surface of the sleeve-collar in order to create the wedge joint.
  • a wedge with an inclined wedge surface may be arranged between the pile-collar and the pile-sleeve. This wedge com- prises the (second) inclined wedge surface which is needed for the wedge joint.
  • the wedge may be loosely inserted between the pile- collar and the pile-sleeve.
  • the wedge of the inventive foundation may be fixed in posi ⁇ tion when locking, preferably by welding. The welding may be carried out when the wedge joint has been installed.
  • the wedge may have an outward flange for contacting the sleeve-collar in order to improve the transmission of forces during installation, when the wedge forces the sleeve-collar downward.
  • the wedge may be segmented and comprise at least two wedge parts. Accordingly two, three, four or more separate wedge parts can be used, which are spaced from each other in circumferential direction.
  • the pile- collar may have an outward flange, so that this flange can be impacted mechanically when the wedge joint is installed.
  • At least one surface of the pile-collar and/or at least one surface of the pile- sleeve and/or at least one surface of the wedge joint has an increased roughness, preferably through a surface treatment.
  • the increased roughness leads to an increased friction be ⁇ tween the contact surface, so that a higher clamping force is achieved .
  • at least one distance piece may be used between sleeve-collar and wedge during installation. The distance piece ensures that the wedge does not key the sleeve-collar too early when the wind turbine installation or a foot of the wind turbine tower is forced into the seabed. Subsequently, when the pile-collar is in contact with the wedge the distance piece can be removed.
  • the invention comprises a wind turbine installation.
  • the inventive wind turbine installation comprises a founda ⁇ tion as described before.
  • Fig. 1 shows a detail of an inventive foundation in a sec ⁇ tional view during installation
  • Fig. 2 shows the foundation of fig. 1 in a later stage for the installation
  • Fig. 3 shows the foundation of fig. 1 in the installed
  • Fig. 4 shows an inventive foundation for a wind turbine installation during installation in a sectional view, whereby a distance piece is used.
  • Fig. 1 shows a detail of a foundation 1 for a wind turbine installation in a sectional view.
  • Wind turbines are provided with a rotor shaft which is part of an electrical generator producing electricity during move ⁇ ment of the rotor relative to a stator of the generator.
  • the stator comprises a number of coils
  • the rotor comprises a number of permanent magnets so that an electric voltage is induced when the rotor is turned.
  • the generator is mounted on top of a wind turbine tower which is supported by a foun ⁇ dation comprising feet which are placed on a seabed and fixed in position by piles which are driven into the seabed.
  • Fig. 1 shows the lower part of a pile 2 of a foot of a wind turbine installation which is anchored to a seabed 3.
  • a pile- collar 4 is securely fixed. With suitable tools the lower end of the pile 2 undergoes mechanical impacts so that the pile 2 is driven vertically into the seabed 3.
  • a pile-sleeve 5 which comprises a sleeve-collar 16, rests on the seabed 3 and encases the pipe-collar 4.
  • the pile-sleeve 5 has a tubular shape and a larger diameter than the pile- collar 4, so that an annular area 6 separates pile-sleeve 5 from pile-collar 4.
  • the foundation 1 comprises the wedge joint with mating wedge surfaces.
  • a first inclined wedge surface 7 is formed on the pile-collar 16 of the pile-sleeve 5.
  • the wedge surface 7 is cone-shaped with a smaller diameter near the seabed 3 and a larger diameter in direction to the top of the pile 2.
  • the wedge joint further comprises a second inclined wedge surface 8, which is part of a tubular wedge 9, which is posi ⁇ tioned around pile-collar 4 during installation.
  • wedge 9 is loosely inserted between pile- collar 4 and pile-sleeve 5.
  • Fig. 1 shows the foundation 1 during installation. After installation of the pile-sleeve 5 on the seabed 3 the pile 2 which is surrounded by wedge 9 is inserted into the seabed 3 through pile-sleeve 5. On top of the pile 2 a vertical force is applied, as is indicated by an arrow 10.
  • the pile-collar 4 comprises an outward facing flange 11 on which the impact force can be applied.
  • Fig. 2 shows the state shortly before keying between wedge 9 and the inclined wedge surface 7 of pile-sleeve 5 starts.
  • the first wedge surface 7 and the second wedge surface 8 have undergone a surface treatment which has altered their rough ⁇ ness. Consequently friction between the two mating inclined surfaces is increased which supports the function of the clamp connection.
  • the wedge 9 is provided with an outwardly facing flange 12 at its top so that the flange 11 contacts the flange 12 of the wedge 9 during installation.
  • the wedge 9 is constantly driven vertically and forced against the outer surface of pile-collar 4, until the pile 2 with the pile-collar 4 is keyed to the pile-sleeve 5. In this state no further movement of the pile 2 relative to the pile-sleeve 5 is possible. This status is depicted in fig. 3.
  • the wedge 9 contacts the first wedge surface 7 of pile-sleeve 5 with its second wedge surface 8, in addition the inner surface 13 of wedge 9 contacts the pile-collar 4.
  • the wedge 9 keys the pile 2 and the pile-sleeve 5 together, so that the foundation construction 1 is locked in position.
  • the wedge 9 is shaped as a ring with the same cross-section as the pile-collar 4 and the pile-sleeve 5.
  • the wedge is segmented and comprises two, three or four wedge parts, which are spaced from each other in circumferential direction of the pile 2. After installation the wedge may be welded to the pile-collar 4 and/or the inclined wedge surface 7 of the pile-sleeve 5.
  • Fig. 4 shows a detail of another embodiment of a foundation for a wind turbine tower during installation in a sectional view.
  • like reference signs have been used.
  • an annular distance piece 14 with a similar diameter as the pile-sleeve 5 is positioned between wedge 9 and the upper horizontal surface 15 of sleeve-collar 16.
  • the distance piece 14 is used only during installation and ensures that the wedge 9 or wedge segments do not key the pile-collar 4 and the pile-sleeve 5 together too early when the pile-collar 4 is forced into the seabed 3.
  • the distance piece 14 is only needed before the flange 11 of the pile-collar 4 is in contact with the wedge 9.
  • the distance piece 14 is made from plas ⁇ tics, in other embodiments it may be made of rubber, wood, etc.
  • the distance piece 14 is removed manually or automati ⁇ cally when the flange 11 of the pile-collar 4 contacts the wedge 9. In many cases the impacts which are directed down ⁇ ward automatically push the distance piece 14 away.
  • the foundation as shown in the embodiments of fig. 1 to 4 is advantageous in that the clamp connection is easy to estab ⁇ lish, the process of piling and locking the pile-collar 4 together with the pile 2 of the foundation is done in a single step.
  • the installation method does not require curing of a grouting material, instead the foundation can be put into use as soon as it is established.
  • the clamp connection with the wedge joint makes it possible to disman ⁇ tle the connection without destruction.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Wind Motors (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A foundation (1) for a wind turbine tower, comprising a connection to one or more piles (2), which can be driven into a seabed (3), and a connected pile-sleeve (5) encasing the pile (2), characterised in that the connection further comprises a clamp connection whereby the pile (2) comprises a pile-collar (4), securely fixed to the pile (2), and the pile-collar (4) and the pile-sleeve (5) are connected by a wedge joint with mating wedge surfaces (7, 8).

Description

Description
A foundation for a wind turbine installation The invention refers to a foundation for a wind turbine in¬ stallation, comprising a connection to one or more piles which can be driven into a seabed, and a connected pile- sleeve encasing the pile. In existent offshore wind turbine installations different foundations are common: monopole foundations consist of a steel pile which is driven into the seabed. Gravity founda¬ tions consist of a large base constructed from either con¬ crete or steel or a combination, which rests on the seabed. The wind turbine is dependent on gravity to remain erect.
Tripod foundations consist of three legs comprising piles on each end which are driven into the seabed. This type is gen¬ erally used at deeper depths. Usually the tripods are an¬ chored to the seabed and embedded into a pile sleeve by fill- ing the sleeve with concrete so that a bonding is effected by grouting .
A similar foundation is used for jacket foundations. In EP 2 067 914 A2 a jacket foundation consisting of a framework of tubes with different diameters is disclosed, which is fixed to a seabed by vertical tubes through which piles are driven into the seabed. For the connection of the piles and the tubes a grouting material is used, which requires curing be¬ fore subsequent installation steps can be performed.
It is therefore an object of the present invention to provide a foundation for a wind turbine tower which can be installed faster and easier. According to the present invention this object is achieved in the above defined foundation for a wind turbine tower in that the connection further comprises a clamp connection, whereby the pile comprises a pile-collar, securely fixed to the pile, and the pile-collar and the pile-sleeve are connected by a wedge joint with mating wedge surfaces.
The present invention is based on the idea that instead of using concrete or grouting material for establishing a connection of the foundation to an underground like a seabed a clamp connection can be used which can be installed easier. Due to the fact that no grouting material is needed which normally has to be cured, the installation procedure can be shortened substantially. Another advantage of the clamp con¬ nection of the inventive foundation for a wind turbine in¬ stallation is that it is possible to dismantle the connection without destruction. Therefore according to the invention the wind turbine installation or a foot of the wind turbine installation is connected to the seabed by vertical forces so that a wedge joint is established, whereby the pile-collar is wedged with the pile-sleeve.
In the inventive foundation it is preferred that the pile- sleeve comprises a sleeve-collar with an inclined wedge sur¬ face. The pile-sleeve which encases the pile-collar is equipped with the inclined wedge surface, which forms part of the wedge joint. The inclined wedge surface is arranged such that it has a smaller diameter towards the underground and a larger diameter towards the wind turbine tower. Therefore the inclined wedge surface can cooperate with another wedge surface which is fixed to the wind turbine installation or a foot of the wind turbine installation so that this second wedge surface can be moved towards the inclined wedge surface of the sleeve-collar in order to create the wedge joint.
According to a preferred embodiment of the inventive founda¬ tion a wedge with an inclined wedge surface may be arranged between the pile-collar and the pile-sleeve. This wedge com- prises the (second) inclined wedge surface which is needed for the wedge joint. According to a further development of the inventive founda¬ tion the wedge may be loosely inserted between the pile- collar and the pile-sleeve. The use of a loose wedge facili¬ tates the clamping procedure where a mechanical force is ex- erted upon the pile-collar which keys the wedge and the sleeve-collar. In order to obtain a very reliable connection the wedge of the inventive foundation may be fixed in posi¬ tion when locking, preferably by welding. The welding may be carried out when the wedge joint has been installed.
In the inventive foundation the wedge may have an outward flange for contacting the sleeve-collar in order to improve the transmission of forces during installation, when the wedge forces the sleeve-collar downward.
According to another embodiment of the inventive foundation the wedge may be segmented and comprise at least two wedge parts. Accordingly two, three, four or more separate wedge parts can be used, which are spaced from each other in circumferential direction.
In order to facilitate the installation procedure the pile- collar may have an outward flange, so that this flange can be impacted mechanically when the wedge joint is installed.
In order to obtain a wedge joint with improved clamping characteristics it can be envisaged that at least one surface of the pile-collar and/or at least one surface of the pile- sleeve and/or at least one surface of the wedge joint has an increased roughness, preferably through a surface treatment. The increased roughness leads to an increased friction be¬ tween the contact surface, so that a higher clamping force is achieved . In order to improve installation of the inventive foundation at least one distance piece may be used between sleeve-collar and wedge during installation. The distance piece ensures that the wedge does not key the sleeve-collar too early when the wind turbine installation or a foot of the wind turbine tower is forced into the seabed. Subsequently, when the pile-collar is in contact with the wedge the distance piece can be removed.
Further the invention comprises a wind turbine installation.
The inventive wind turbine installation comprises a founda¬ tion as described before.
The invention and its underlaying principle will be better understood when consideration is given to the following detailed description of preferred embodiments.
In the accompanying drawings :
Fig. 1 shows a detail of an inventive foundation in a sec¬ tional view during installation;
Fig. 2 shows the foundation of fig. 1 in a later stage for the installation;
Fig. 3 shows the foundation of fig. 1 in the installed
state; and
Fig. 4 shows an inventive foundation for a wind turbine installation during installation in a sectional view, whereby a distance piece is used.
Fig. 1 shows a detail of a foundation 1 for a wind turbine installation in a sectional view.
Wind turbines are provided with a rotor shaft which is part of an electrical generator producing electricity during move¬ ment of the rotor relative to a stator of the generator. The stator comprises a number of coils, the rotor comprises a number of permanent magnets so that an electric voltage is induced when the rotor is turned. The generator is mounted on top of a wind turbine tower which is supported by a foun¬ dation comprising feet which are placed on a seabed and fixed in position by piles which are driven into the seabed. Fig. 1 shows the lower part of a pile 2 of a foot of a wind turbine installation which is anchored to a seabed 3. On the outer side of the pile 2, which is made out of steel, a pile- collar 4 is securely fixed. With suitable tools the lower end of the pile 2 undergoes mechanical impacts so that the pile 2 is driven vertically into the seabed 3.
A pile-sleeve 5 which comprises a sleeve-collar 16, rests on the seabed 3 and encases the pipe-collar 4. The pile-sleeve 5 has a tubular shape and a larger diameter than the pile- collar 4, so that an annular area 6 separates pile-sleeve 5 from pile-collar 4.
The foundation 1 comprises the wedge joint with mating wedge surfaces. A first inclined wedge surface 7 is formed on the pile-collar 16 of the pile-sleeve 5. The wedge surface 7 is cone-shaped with a smaller diameter near the seabed 3 and a larger diameter in direction to the top of the pile 2.
The wedge joint further comprises a second inclined wedge surface 8, which is part of a tubular wedge 9, which is posi¬ tioned around pile-collar 4 during installation. As can be seen in fig. 1 wedge 9 is loosely inserted between pile- collar 4 and pile-sleeve 5. Fig. 1 shows the foundation 1 during installation. After installation of the pile-sleeve 5 on the seabed 3 the pile 2 which is surrounded by wedge 9 is inserted into the seabed 3 through pile-sleeve 5. On top of the pile 2 a vertical force is applied, as is indicated by an arrow 10. The pile-collar 4 comprises an outward facing flange 11 on which the impact force can be applied. Subsequently the pile 2 is driven into the seabed 3 together with the pile-collar 4. During the installation procedure the vertical distance be¬ tween flange 11 and pile-sleeve 5 is reduced until the wedge surface 8 of wedge 9 contacts the wedge surface 7 of the pile-sleeve 5.
Fig. 2 shows the state shortly before keying between wedge 9 and the inclined wedge surface 7 of pile-sleeve 5 starts.
The first wedge surface 7 and the second wedge surface 8 have undergone a surface treatment which has altered their rough¬ ness. Consequently friction between the two mating inclined surfaces is increased which supports the function of the clamp connection. The wedge 9 is provided with an outwardly facing flange 12 at its top so that the flange 11 contacts the flange 12 of the wedge 9 during installation. As the position of the pile- sleeve 5 comprising the first inclined wedge surface is fixed the wedge 9 is constantly driven vertically and forced against the outer surface of pile-collar 4, until the pile 2 with the pile-collar 4 is keyed to the pile-sleeve 5. In this state no further movement of the pile 2 relative to the pile-sleeve 5 is possible. This status is depicted in fig. 3. As can be seen the wedge 9 contacts the first wedge surface 7 of pile-sleeve 5 with its second wedge surface 8, in addition the inner surface 13 of wedge 9 contacts the pile-collar 4. The wedge 9 keys the pile 2 and the pile-sleeve 5 together, so that the foundation construction 1 is locked in position.
In the embodiment of fig. 1 to 3 the wedge 9 is shaped as a ring with the same cross-section as the pile-collar 4 and the pile-sleeve 5. However, other embodiments are possible where the wedge is segmented and comprises two, three or four wedge parts, which are spaced from each other in circumferential direction of the pile 2. After installation the wedge may be welded to the pile-collar 4 and/or the inclined wedge surface 7 of the pile-sleeve 5.
Fig. 4 shows a detail of another embodiment of a foundation for a wind turbine tower during installation in a sectional view. For like components as in the embodiment of fig. 1 to 3 like reference signs have been used.
In contrast to the first embodiment an annular distance piece 14 with a similar diameter as the pile-sleeve 5 is positioned between wedge 9 and the upper horizontal surface 15 of sleeve-collar 16. The distance piece 14 is used only during installation and ensures that the wedge 9 or wedge segments do not key the pile-collar 4 and the pile-sleeve 5 together too early when the pile-collar 4 is forced into the seabed 3. The distance piece 14 is only needed before the flange 11 of the pile-collar 4 is in contact with the wedge 9. In the present embodiment the distance piece 14 is made from plas¬ tics, in other embodiments it may be made of rubber, wood, etc. The distance piece 14 is removed manually or automati¬ cally when the flange 11 of the pile-collar 4 contacts the wedge 9. In many cases the impacts which are directed down¬ ward automatically push the distance piece 14 away. The foundation as shown in the embodiments of fig. 1 to 4 is advantageous in that the clamp connection is easy to estab¬ lish, the process of piling and locking the pile-collar 4 together with the pile 2 of the foundation is done in a single step. The installation method does not require curing of a grouting material, instead the foundation can be put into use as soon as it is established. On the other hand the clamp connection with the wedge joint makes it possible to disman¬ tle the connection without destruction.

Claims

Claims
1. A foundation (1) for a wind turbine tower, comprising a connection to one or more piles (2), which can be driven into a seabed (3) , and a connected pile-sleeve (5) encasing the pile (2), characterised in that the connection further comprises a clamp connection whereby the pile (2) comprises a pile-collar (4), securely fixed to the pile (2), and the pile-collar (4) and the pile-sleeve (5) are connected by a wedge joint with mating wedge surfaces (7, 8) .
2. A foundation according to claim 1, characterised in that the pile-sleeve (5) comprises a sleeve-collar (16) with an inclined wedge surface (7) .
3. A foundation according to claim 1 or 2, characterised in that a wedge (9) with an inclined wedge surface (8) is ar¬ ranged between the pile-collar (4) and the pile-sleeve (5) .
4. A foundation according to claim 3, characterised in that the wedge (9) is loosely inserted between the pile-collar (4) and the pile-sleeve (5) .
5. A foundation according to claim 3, characterised in that the wedge (9) is fixed in position when locking, preferably by welding.
6. A foundation according to any of claims 3 to 5, charac¬ terised in that the wedge (9) has an outward flange (12) for contacting the sleeve-collar (16).
7. A foundation according to any of claims 3 to 6, characterised in that the wedge is segmented and comprises at least two wedge parts.
8. A foundation according to any of the preceding claims, characterised in that the pile-collar (4) has an outward flange (11).
9. A foundation according to any of the preceding claims, characterised in that at least one surface of the pile-collar (4) and/or at least one surface of the pile-sleeve (5) and/or at least one surface of the wedge joint has an increased roughness, preferably through a surface treatment.
10. A foundation according to any of the preceding claims, characterised in that at least one distance piece (14) is used between sleeve-collar (16) and wedge (9) during instal¬ lation .
11. A wind turbine installation, characterised in that it comprises a foundation (1) according to any of claims 1 to
PCT/EP2010/064904 2010-05-25 2010-10-06 A foundation for a wind turbine installation WO2011147479A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
DK10765419.6T DK2576917T3 (en) 2010-05-25 2010-10-06 FOUNDATION FOR A WINDMILL SYSTEM
EP10765419.6A EP2576917B1 (en) 2010-05-25 2010-10-06 A foundation for a wind turbine installation

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
EP10163751 2010-05-25
EP10163751.0 2010-05-25

Publications (1)

Publication Number Publication Date
WO2011147479A1 true WO2011147479A1 (en) 2011-12-01

Family

ID=43550353

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2010/064904 WO2011147479A1 (en) 2010-05-25 2010-10-06 A foundation for a wind turbine installation

Country Status (3)

Country Link
EP (1) EP2576917B1 (en)
DK (1) DK2576917T3 (en)
WO (1) WO2011147479A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101457154B1 (en) * 2014-06-30 2014-11-04 김동조 Support for high pressure cable of electric pole
EP3887602B1 (en) * 2018-11-28 2022-12-14 Imenco Corrosion Technology AS A device for securing a connection to be formed between a leg of a marine structure and a pile of a fundament fastened in a seabed

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3754403A (en) * 1972-02-09 1973-08-28 Texaco Inc Offshore marine structure embodying anchor pile means
GB2146057A (en) * 1983-09-01 1985-04-11 Norske Stats Oljeselskap Method and apparatus for draining off shallow gas from the seabed
GB2220432A (en) * 1988-07-08 1990-01-10 Micoperi Spa Driving hollow piles to form an underwater foundation
GB2278871A (en) * 1993-06-11 1994-12-14 Kvaerner Earl & Wright Foundation for an offshore platform
EP2067914A2 (en) 2007-12-04 2009-06-10 WeserWind GmbH Grid structure for an offshore construction, in particular an offshore wind energy converter, and method for manufacture thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3754403A (en) * 1972-02-09 1973-08-28 Texaco Inc Offshore marine structure embodying anchor pile means
GB2146057A (en) * 1983-09-01 1985-04-11 Norske Stats Oljeselskap Method and apparatus for draining off shallow gas from the seabed
GB2220432A (en) * 1988-07-08 1990-01-10 Micoperi Spa Driving hollow piles to form an underwater foundation
GB2278871A (en) * 1993-06-11 1994-12-14 Kvaerner Earl & Wright Foundation for an offshore platform
EP2067914A2 (en) 2007-12-04 2009-06-10 WeserWind GmbH Grid structure for an offshore construction, in particular an offshore wind energy converter, and method for manufacture thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101457154B1 (en) * 2014-06-30 2014-11-04 김동조 Support for high pressure cable of electric pole
EP3887602B1 (en) * 2018-11-28 2022-12-14 Imenco Corrosion Technology AS A device for securing a connection to be formed between a leg of a marine structure and a pile of a fundament fastened in a seabed
US11767652B2 (en) 2018-11-28 2023-09-26 Imenco Corrosion Technology As Device for securing a connection to be formed between a leg of a marine structure and a pile of a fundament fastened in a seabed

Also Published As

Publication number Publication date
DK2576917T3 (en) 2017-02-27
EP2576917A1 (en) 2013-04-10
EP2576917B1 (en) 2016-11-30

Similar Documents

Publication Publication Date Title
CN108474193B (en) Method of forming a wind turbine foundation and associated system for forming such a foundation
US8876486B2 (en) Marine wind turbine having a pylon vertically adjusted by setting
US9435096B2 (en) Underwater support concrete structure construction method
JP5278828B2 (en) How to install the jacket
EP3411595B1 (en) Method of replacing anchor bolts in wind turbine foundations
EP2383393A1 (en) Apparatus and method for producing a concrete foundation
EP2662497A1 (en) Wind turbine foundation
TW202020268A (en) Pile foundation and construction method of pile foundation
EP2576917B1 (en) A foundation for a wind turbine installation
EP3307954A1 (en) Monopile foundation for an offshore tower structure
EP3290692B1 (en) Wind-turbine tower, wind turbine, and method of assembling wind-turbine tower
JP2018062812A (en) Foundation structure, pile head structure of steel-pipe pile, and construction method for foundation structure
CN108487283B (en) Pile anchor press-in type sinking construction method for open caisson
US10100486B2 (en) Method for installing overhead transmission line supports on permafrost soils
JP2014218861A (en) Method for removing existing structure
KR101563531B1 (en) Method for combining concrete base of offshore supporting structure and steel pipe pile
JP6900816B2 (en) Foundation structure, pile head structure of steel pipe pile, and construction method of foundation structure
JP6513470B2 (en) Foundation pile for installation, foundation pile for installation of solar panels, installation method of foundation pile and installation method of foundation pile for solar panels
KR102160628B1 (en) Wind turbine structure for retrofitting spread footing in partial repowering , and construction method for the same
JP2006348690A (en) Retrofitting method for base isolation of existing building
KR101384168B1 (en) installation method of slab foundation for offshore wind power generator using position senser
KR200482746Y1 (en) The smart reinforcing member of phc pile
EP3994312B1 (en) Method of forming a wind turbine foundation
CN106414854B (en) Tubular foundation
KR20140140440A (en) Hybrid support structure and method for installing the same

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 10765419

Country of ref document: EP

Kind code of ref document: A1

REEP Request for entry into the european phase

Ref document number: 2010765419

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2010765419

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: DE