US967442A - Pile-protecting. - Google Patents
Pile-protecting. Download PDFInfo
- Publication number
- US967442A US967442A US54552410A US1910545524A US967442A US 967442 A US967442 A US 967442A US 54552410 A US54552410 A US 54552410A US 1910545524 A US1910545524 A US 1910545524A US 967442 A US967442 A US 967442A
- Authority
- US
- United States
- Prior art keywords
- pile
- coating
- piles
- protecting
- casing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000010426 asphalt Substances 0.000 description 13
- 239000011248 coating agent Substances 0.000 description 12
- 238000000576 coating method Methods 0.000 description 12
- 239000000463 material Substances 0.000 description 8
- 239000004568 cement Substances 0.000 description 5
- 239000011280 coal tar Substances 0.000 description 5
- 239000004576 sand Substances 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 239000010425 asbestos Substances 0.000 description 3
- 150000001875 compounds Chemical class 0.000 description 3
- 238000011049 filling Methods 0.000 description 3
- 239000000203 mixture Substances 0.000 description 3
- 229910052895 riebeckite Inorganic materials 0.000 description 3
- 241000238631 Hexapoda Species 0.000 description 2
- 238000007792 addition Methods 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 238000002844 melting Methods 0.000 description 2
- 230000008018 melting Effects 0.000 description 2
- 238000002156 mixing Methods 0.000 description 2
- 238000012856 packing Methods 0.000 description 2
- 239000011253 protective coating Substances 0.000 description 2
- 230000001464 adherent effect Effects 0.000 description 1
- 238000009835 boiling Methods 0.000 description 1
- 239000003245 coal Substances 0.000 description 1
- 239000004615 ingredient Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000002791 soaking Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000011269 tar Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2292—Holders used for protection, repair or reinforcement of the post or pole
Definitions
- Our invention relates to improvements in protecting piles from the ravages of marine insects, and from decay.
- Such piles may be of any suitable length, as or 70 feet, to allow a sufficient portion to be driven into the mud for an appropriate support, and a sufficient portion extending above the water, with an intervening portion of such length as will be normally submerged in the water.
- a coating which is preferably put on in two stages.
- the composition may consist of coal tar, asphalt, bitumen, asbestos7 fine sand, gravel and cement.
- Ve have found that the following proportions are well adapted for the purpose: one barrel of coal tar, known as No. l; five barrels of asphalt; six barrels of bitumen; 200 lbs. of gravel; 100 lbs. of sand; 100 lbs. cement.
- the application may be made as follows: The bark and irregularities of the pile are removed, and it is made fair and smooth to receive the covering. Then it is covered with the rst layer, consisting of the ingredients mentioned.
- the coal tar, asphalt and bitumen being first melted in a properly constructed tank, the piles are so mounted that they may be revolved horizontally upon their aXis over this tank, and the compound applied in any suitable or desired manner.- After the first coat is put on, the pile is laid out to dry.
- the kettles are brought to boiling point,
- the pile A is raised toa vertical position, as shown in Fig. 2, and a casing 2 of either black or galvanized iron is attached in such a manner as to leave a space between pile and casing equal to the One of these jackets being let down to the4 proper level.
- a gasket or packing of rope or. other material 4 is fitted into the lower end of the casing, and the easing is afterward i filled with the compound.
- successive additions are made within such a length of time that the lower ones will not have set, and the successive additions will be intimately connected therewith so as to form a complete covering for the pile for the distance desired.
- the gasket or packing 4 may be nailed to the pile to form a tapered protection to prevent disturbing the coating when the pile is driven.
- the second kettle is heated by steam.
- the mixture is brought to the proper consistency by adding portions from the first kettle.
- the second coat may be called a filling; it is put on in the following manner:
- a funnel 3 is provided, adjustable to fit inside the casing, outside of the first coat.
- the filling coat must be of the proper consistency to fill the space between the first coat and the casing, yet not be too thin. It is worked into place as the material is added through the funnel, and packed as it goes in. This is done by a long iron tamper. After the covering has become firm and solid, the casing may be removed, or left in place as desired.
- a protecting coating for piles and submerged structures consisting of coal tar, asphalt, bitumen, asbestos, sand and cement mixed and applied hot.
- the method of coating piles consisting in melting a body of coal 1 tar, asphalt, bitumen, and mixing therewith sand and cement, revolving the pile above a tank containing the melted material, and bringing said material into adherent contact with the pile, then allowing the coating to set and harden, then raising the pile into a vert-ical position and closing it with sectional casings of larger diameter, and filling said casings successively with the coating material superposed upon the first named coating.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Description
J. ROWE 6L M. MOGARTY.
PILE PROTEGTING.
APPLIUATION FILED rimas. 1910.
4 967,442. Patented Aug. 16, 1910.
fnl Nouns PITRE! cm. wsullmun. u. c.
JAMES ROWE AND MATTI-IEW MCCATY, OF SAN FRANCISCO, CALIFORNIA.
PILE-PROTEGTING.
Specification of Letters Patent.
Patented Aug. 16, 1910.
Application filed February 23, 1910. Serial No. 545,524.
To all whom it may concern:
Beit known that we, JAMES Rowe and MATTI-inw MCCARTY, citizens of the Unit/ed States, residing in the city and county of San Francisco and State of California, have invented new and useful Improvements in Pile-Protecting, of which the following is a specification.
Our invention relates to improvements in protecting piles from the ravages of marine insects, and from decay.
It consists of a novel compound, and its application to those portions of the pile which it is desired to protect, and in details which will be more fully explained by reference to the accompanying drawings, in which- Figure l shows the first stage of the application. Fig. 2 shows the second stage.
In order-to properly protect piles from decay, and the ravages of marine insects, it is necessary to coat such portions of the pile as are exposed to the action of the water above the mud, and below the higher point at which the water touches them. Such piles may be of any suitable length, as or 70 feet, to allow a sufficient portion to be driven into the mud for an appropriate support, and a sufficient portion extending above the water, with an intervening portion of such length as will be normally submerged in the water. In order to protect such piles we apply a coating which is preferably put on in two stages. The composition may consist of coal tar, asphalt, bitumen, asbestos7 fine sand, gravel and cement. Ve have found that the following proportions are well adapted for the purpose: one barrel of coal tar, known as No. l; five barrels of asphalt; six barrels of bitumen; 200 lbs. of gravel; 100 lbs. of sand; 100 lbs. cement.
The application may be made as follows: The bark and irregularities of the pile are removed, and it is made fair and smooth to receive the covering. Then it is covered with the rst layer, consisting of the ingredients mentioned. The coal tar, asphalt and bitumen being first melted in a properly constructed tank, the piles are so mounted that they may be revolved horizontally upon their aXis over this tank, and the compound applied in any suitable or desired manner.- After the first coat is put on, the pile is laid out to dry.
A second kettle is charged as follows: 10
barrels of bitumen, 4 barrels of asbestos.
The kettles are brought to boiling point,
and may be side by side. To apply the second coating, the pile A is raised toa vertical position, as shown in Fig. 2, and a casing 2 of either black or galvanized iron is attached in such a manner as to leave a space between pile and casing equal to the One of these jackets being let down to the4 proper level., a gasket or packing of rope or. other material 4, is fitted into the lower end of the casing, and the easing is afterward i filled with the compound. When the first ,cylinder or casing has been filled, a second casing is let down upon the top of it, and this again also filled, and so on until the proper' length of coating has been applied to the pile. Successive additions are made within such a length of time that the lower ones will not have set, and the successive additions will be intimately connected therewith so as to form a complete covering for the pile for the distance desired. The gasket or packing 4 may be nailed to the pile to form a tapered protection to prevent disturbing the coating when the pile is driven.
The second kettle is heated by steam. The mixture is brought to the proper consistency by adding portions from the first kettle. The second coat may be called a filling; it is put on in the following manner: A funnel 3 is provided, adjustable to fit inside the casing, outside of the first coat. The filling coat must be of the proper consistency to fill the space between the first coat and the casing, yet not be too thin. It is worked into place as the material is added through the funnel, and packed as it goes in. This is done by a long iron tamper. After the covering has become firm and solid, the casing may be removed, or left in place as desired.
In order to protect the top of the pile from damage by the elements by water falling thereon and soaking in,we prefer to bore a hole of sufficient size into the top of the pile, as shown at 8, and upon this pile after it has been driven, is placed a cap of the protective material which fills the opening vcylinder may be fitted thereon to retain the plying a second coating thereover.
8, and is then allowed to spread out over the top of the pile. If desired an inclosing material until it is properly set and hardened. Piles thus protected will last without decay or deteriorationfor very long periods.
Having thus described our invention, what we claim and desire to secure by Letters Patent isl. A protecting coating for piles and submerged structures, said coating consisting of coal tar, asphalt, bitumen, asbestos, sand and cement mixed and applied hot.
2.-The method of applying a protective coating to piles, said method consisting in melting and intimately mixing the components of the covering, revolving the pile above the tank containing the mixture, and bringing the melted material into Contact therewith so that it will adhere, allowing the coat-ing to harden, and subsequently ap- 3. The method of coating piles, said method consisting in melting a body of coal 1 tar, asphalt, bitumen, and mixing therewith sand and cement, revolving the pile above a tank containing the melted material, and bringing said material into adherent contact with the pile, then allowing the coating to set and harden, then raising the pile into a vert-ical position and closing it with sectional casings of larger diameter, and filling said casings successively with the coating material superposed upon the first named coating.
4. As an article of manufacture, a pile having the bark removed and made smooth, and a protective coating on the pile and composed of coal tar, asphalt, bitumen, asbestos, sand, gravel and cement.
In testimony whereof we have hereunto set our hands in the presence of two subscribing witnesses.
JAMES ROVVE. MATTHEW MCCARTY. Witnesses:
G. H. STRONG, CHARLES EDELMAN.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US54552410A US967442A (en) | 1910-02-23 | 1910-02-23 | Pile-protecting. |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US54552410A US967442A (en) | 1910-02-23 | 1910-02-23 | Pile-protecting. |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US967442A true US967442A (en) | 1910-08-16 |
Family
ID=3035834
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US54552410A Expired - Lifetime US967442A (en) | 1910-02-23 | 1910-02-23 | Pile-protecting. |
Country Status (1)
| Country | Link |
|---|---|
| US (1) | US967442A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2724156A (en) * | 1952-09-04 | 1955-11-22 | Francis B Shaw | Pole boot |
| US3999399A (en) * | 1973-06-07 | 1976-12-28 | Walter A. Plummer | Protective guard means for wood piling and a method of installing same under dry working conditions |
-
1910
- 1910-02-23 US US54552410A patent/US967442A/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2724156A (en) * | 1952-09-04 | 1955-11-22 | Francis B Shaw | Pole boot |
| US3999399A (en) * | 1973-06-07 | 1976-12-28 | Walter A. Plummer | Protective guard means for wood piling and a method of installing same under dry working conditions |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US1871508A (en) | Metallic conduit | |
| US790230A (en) | Method of protecting piles or the like. | |
| US3045709A (en) | Protective casing for pipes and the like | |
| US2808851A (en) | Double wrapped prestressed concrete pipe | |
| US715362A (en) | Preserving wood or iron poles and timbers. | |
| US947237A (en) | Protecting submerged supporting-columns. | |
| US1879430A (en) | Dam and method of constructing the same | |
| US954973A (en) | Fitting for pile-casings. | |
| US3380254A (en) | Protective linings and method of forming the same in watercourses | |
| US299425A (en) | John j | |
| US1914897A (en) | Means for protecting gas or water pipes, electric cables, or the like | |
| US3078324A (en) | Pipe coating composition comprising asphalt and a filler graded to maximum density | |
| US195990A (en) | Improvement in preserving wooden piles and timber | |
| US539485A (en) | Pile-covering | |
| US1964987A (en) | Process of constructing bituminous macadam roads | |
| US910453A (en) | Concrete-incased pile. | |
| US468291A (en) | bedbury | |
| US2240778A (en) | Method of and means for curing concrete | |
| US842079A (en) | Covering for roofs and the like. | |
| US414251A (en) | Pile or timber | |
| US441584A (en) | Protecting and preserving piles | |
| US927357A (en) | Concrete pile-covering. | |
| US366444A (en) | Pile-covering | |
| US414246A (en) | Coating for wooden structures | |
| DE333495C (en) | Process to bond bitumen or bituminous layers with surfaces made of cement concrete or similar materials |