US925204A - Concrete construction and method of producing the same. - Google Patents

Concrete construction and method of producing the same. Download PDF

Info

Publication number
US925204A
US925204A US44981208A US1908449812A US925204A US 925204 A US925204 A US 925204A US 44981208 A US44981208 A US 44981208A US 1908449812 A US1908449812 A US 1908449812A US 925204 A US925204 A US 925204A
Authority
US
United States
Prior art keywords
concrete
blocks
construction
forms
boxes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US44981208A
Inventor
Gustave A M Liljencrantz
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US44981208A priority Critical patent/US925204A/en
Application granted granted Critical
Publication of US925204A publication Critical patent/US925204A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/20Caisson foundations combined with pile foundations

Definitions

  • ooNcRETB GoNsTRUoTIoN AND METHOD or PRoDUoING THE snm PPLIOATION FILED AUG. 22 925,204.
  • the invention consists in a general way in the formation of large concrete blocks at intervals crosswise of the structure to be produced, and connecting these blocks, as also their reinforcing, by intermediate blocks of approximately like construction, each block being constructed within a box form having a number of cell boxes which are placed therein, spaced from each other and from the walls of the principal box or form, and filled with sand, rock or other cheap material at the same time the spaces thereabout at the outside are filled with concrete. Vhen the concrete reaches the tops of the cell boxes the latter are covered and the concrete carried a suitable distance thereabove, thus producing absolute monoiiths.
  • Blocks made in accordance with my process may be used in the construction of new superstructures over cribs sunk to the proper height; for rebuilding superstructures over old crib work, for new pier work or docks, in which case large blocks should be placed on a pile foundation sawed off at a suitable height; for docks in lakes or rivers where the bottom consists of solid rock; for bridge abutments or intermediate piers; for retaining walls, dams and other bulky, heavy structures where the cross-section and base must be of considerable magnitude and would consequently make the work very expensive if of solid concrete.
  • Figure l is a sectional plan of my improved concrete construction at an intermediate stage of the process
  • Fig. 2 is a section on the line 2-2 of Fig. l, looking' in the direction of the arrows
  • Fig. 3 is a plan of the construction, partly in section, at an advanced stage of the process
  • Fig. e@ is a crosssection of the same substantially on the line -Ll---t of Fig. 3
  • Fig. 5 is a longitudinal section of the structure on the line of Fig.
  • Fig. 6 illustrates the ⁇ construction of the intermediate blocks when it is preferred t0 keep vthe sea water out of the concrete during the period of setting
  • Fig. 7 is a fragmentary plan of one of the outer box forms
  • Figs. 8 and 9 are sectional views illustrating the manner of connecting the reinforcing 0f the initially formed blocks preparatory to forming the intermediate connecting blocks of the structure
  • Fig. l0 is a sectional View illustrating the connection of the side walls of the form with the transverse tie-rods
  • Fig. ll is a longitudinal section through one of the concrete blocks used below the normal water level in constructing the foundation for the intermediate blocks, as in Fig. 6.
  • the hitherto adopted method of building new concrete superstructures over old crib work consisted in brief in the removing of the old timber work to lone or two feet below low water, to form thereon a timber foundation suitable to support the concrete blocks of sufficient height to bring their top surfaces above the average high water mark; by connecting these blocks on opposite sides of the pier by means of anchor or tie-rods; filling the spaces between them with concrete, and finally constructing the upper part on the foundation so formed according to some adopted design.
  • This manner of procedure requires much of the lower work to be done below two, three or more feet of water, which is necessarily costly and slow.
  • the construction in accordance with my invention islas followszAfter the old crib work, and protruding drift bolts, have been removed to the desired elevation, generally about one foot below low water, where the timber may be considered as always wet and, therefore, not liable to rot, and it is found that the tops of the side timbers 5, 5, are in a horizontal plane, there is nothing further required in forming the foundation than the placing lengthwise of the pier, and resting on the top cross-ties 6, in one or more rows, as may be deemed necessary for the support of the large forms with their concrete filling, timbers T, with their upper surfaces in the same horizontal plane as those of the side timbers 5.
  • the block forms 9 are preferably constructed of sound and merchantable lumber'. As the lower part is to be submerged some two or three feet below the water level, that much of the box must be made water-tight or at least substantially so. For this reason they should be made from matched lumber of a thickness to give them sufficient strength to resist the pressure of the concrete filling when in a plastic condition before its setting, and the seams should be callred, if required.
  • the bottom of the block form must also be made strong enough to carry the weight of the concrete before the setting of the latter, although the supporting timbers 7 decrease this requirement materially, and after the concrete has set, the bottom of each block form will in itself have all necessary strength to be supported by the side timbers alone by reason of I-beams 10 or other suitable reinforcing, arranged transversely of the structure to be produced.
  • the ends of the block forms which are to shape the sides of the superstructures will be detachably connected or nailed to the bottom of the form, and must have the inner side smooth to give the concrete a finished surface.
  • the sides of these forms are also made detachable but need not have smooth surfaces except at the joints. ln the construe tion of these sides they are made to form buttresses l1, as best shown in Fig. l, which l are located at two or more places at each side of the finished concrete block, to insure a better connection between intermediate blocks and provide against any tendency of the connecting blocks being disturbed by heavy wave motion against the pier.
  • After the four side walls of the block form are in their proper positions they are secured together by as many iron bands l2 (see Figs.
  • the cell. boxes 9 are preferably made of the cheapest kind of lumber, and since they are generally uniform in shape and dimensions, this lumber may be out to order in the mills to the required size and afterward nailed together, thus diminishing the cost of manufacture in so far as practicable. ln order that the cell boxes may be sufficiently strong to resist the pressure of the concrete before it sets, they may be braced on the inside, or, more generally, lled with sand, slag, riprap, or any other heavy cheap material, simultaneously with the placing of the concrete in the spaces formed between ihem and the blot-lt form, maintaining ⁇ both the fillingl of the cell boxes and the concrete at the sa me level during the process of construction. rl'he cell boxes should also be such as not to absorb water from the concrete, which condition insured by coating the wood with paraflin, asphaltine or the like.
  • the whole height of the superstructure from the base to the crown is formed by a continuous operation, and will constitute, when finished, a perfect monolith. If the side timbers 5 of the foundation. do not lie in a horizontal plane, this inequality is compensated for when the top of the superstructure is reached, which can be given any desired finish either with a crown along the middle or sloped ⁇ in either direction, etc. ln locatingl the successive 'ion of block forms they must be placed sulliciently far apart to permit of the removal of the detachable lsides. if this distance is ⁇ just large enough for the purpose, and the intervening space is lilled with solid concrete, it will make the all unnecessarily heavy.
  • rl ⁇ he formation of the foundation for the concrete between the initially finished blocks may be made by either of the following methods: rThe lirst is illustrated in Fig. -,.L wl ei'ein the water surface in this space may be reached some two feet or more above the ⁇ upper tie of the sub-construction which forms the main support for the concrete work. rihis construction prefere. le where the placing of the concrete directly in the water is not ob jeetionable, in which case the llooring is formed resting on the crossties and crib filling and the concrete placed over this until it reaches above the water level.
  • each block 22 For each block 22 is provided a U-shaped hanger 23 having hooked extremities which serve the double purpose of convenience in handling and placing by means of a derrick, and, further, to make a strong connection with the mass of concrete placed about and above them. ln this construction an intermediate support will be provided in the nature of timbers 24.
  • the regular stone filling of the crib should be built up equal to the height of the blocks and the side timbers, then covered with small stone and gravel, as is done for thewhole foundation. Over this gravel is placed a covering of burlap 2G.
  • the building of the superstructure proceeds when the intermediate connecting blocks or sections of the pier are completed.
  • the process of construction as herein described is comparatively cheap, embodies simplicity, and permits of increasing or decreasing the strength of the structure, as desired, according to the requirements under different conditions, by means of the cell boxes.
  • the concrete walls will be larger and consequently stronger.
  • the cell boxes may be placed in several layers, thus adding one or more horizontal walls and accordingly increasing the strength, as, for example, in high retaining walls.
  • pier l in the appended claims, mean to include docks, wharves, break-waters and similar structures.
  • a pier having a superstructure Colnposod of a series of cellular concrete sections arranged cross-wise of the pier and oonneeted together.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Description

12909. a sums-snm 1.
Patented June 15,
G. M. LILJBNURANTZ.
ooNcRETB GoNsTRUoTIoN AND METHOD or PRoDUoING THE snm PPLIOATION FILED AUG. 22 925,204.
By mrtg@ ATTORNEYS Patented June 15, 1909.
3 SHEETS-SHEET 2.
G. A. M. LILJENCRANTZ. CONCRETE ooNsTEUoTIoN AND METHOD oE TEoDUoING TEE SAME A1I:ILIfJA'lON FILED AUG. 22, 1908. 925,204.
A TTOH/VEYS Patented June 15, l1909.
a sums-SHEET a.,`
LILJENGRANTZ. CONCRETE CONSTRUCTION ANI) METHOD OF PBODUCING THE SAME.
G. A. M
APPLIMTION FILED AUG.
THE :vonnis Fermes co.. WASHINGTON. n, c
GUSTAVE A. M. LILJENORANTZ, OF CHICAGO, ILLINOIS.
CONCRETE CONSTRUCTION AND METHOD 0F PRODUCING SAME.
To all whom t may concern:
lie it known that I, Gus'ravn A. M. LiL- Jnncnan'rz, a citizen of the United States, and a resident of Chicago, in the county of Cook and State of Illinois, have invented a new and improved Concrete Construction and inlethod of Producing the Same, of which the following is a full, clear, and exact description.
The invention consists in a general way in the formation of large concrete blocks at intervals crosswise of the structure to be produced, and connecting these blocks, as also their reinforcing, by intermediate blocks of approximately like construction, each block being constructed within a box form having a number of cell boxes which are placed therein, spaced from each other and from the walls of the principal box or form, and filled with sand, rock or other cheap material at the same time the spaces thereabout at the outside are filled with concrete. Vhen the concrete reaches the tops of the cell boxes the latter are covered and the concrete carried a suitable distance thereabove, thus producing absolute monoiiths.
Blocks made in accordance with my process may be used in the construction of new superstructures over cribs sunk to the proper height; for rebuilding superstructures over old crib work, for new pier work or docks, in which case large blocks should be placed on a pile foundation sawed off at a suitable height; for docks in lakes or rivers where the bottom consists of solid rock; for bridge abutments or intermediate piers; for retaining walls, dams and other bulky, heavy structures where the cross-section and base must be of considerable magnitude and would consequently make the work very expensive if of solid concrete.
Reference is to be had to the accompanying drawings forming a part of this specification, in which similar characters of reference indicate corresponding parts in all the views.
Figure l is a sectional plan of my improved concrete construction at an intermediate stage of the process; Fig. 2 is a section on the line 2-2 of Fig. l, looking' in the direction of the arrows; Fig. 3 is a plan of the construction, partly in section, at an advanced stage of the process; Fig. e@ is a crosssection of the same substantially on the line -Ll---t of Fig. 3; Fig. 5 is a longitudinal section of the structure on the line of Fig.
Specification of Letters Patent.
Application filed August 22, 1908.
Patented June 15, 1909.
Serial No. 449,812.
3; Fig. 6 illustrates the` construction of the intermediate blocks when it is preferred t0 keep vthe sea water out of the concrete during the period of setting; Fig. 7 is a fragmentary plan of one of the outer box forms; Figs. 8 and 9 are sectional views illustrating the manner of connecting the reinforcing 0f the initially formed blocks preparatory to forming the intermediate connecting blocks of the structure; Fig. l0 is a sectional View illustrating the connection of the side walls of the form with the transverse tie-rods; and Fig. ll is a longitudinal section through one of the concrete blocks used below the normal water level in constructing the foundation for the intermediate blocks, as in Fig. 6.
For all structures built on concrete, as retaining walls, etc., the construction will be very simple and will be readily understood from the following detail description, which covers that for the building of pier superstructures. These have been especially selected for a more minute description, because .having to be built in part below water level it requires special treatment in several respects. 1
The hitherto adopted method of building new concrete superstructures over old crib work, consisted in brief in the removing of the old timber work to lone or two feet below low water, to form thereon a timber foundation suitable to support the concrete blocks of sufficient height to bring their top surfaces above the average high water mark; by connecting these blocks on opposite sides of the pier by means of anchor or tie-rods; filling the spaces between them with concrete, and finally constructing the upper part on the foundation so formed according to some adopted design. This manner of procedure requires much of the lower work to be done below two, three or more feet of water, which is necessarily costly and slow.
The construction in accordance with my invention islas followszAfter the old crib work, and protruding drift bolts, have been removed to the desired elevation, generally about one foot below low water, where the timber may be considered as always wet and, therefore, not liable to rot, and it is found that the tops of the side timbers 5, 5, are in a horizontal plane, there is nothing further required in forming the foundation than the placing lengthwise of the pier, and resting on the top cross-ties 6, in one or more rows, as may be deemed necessary for the support of the large forms with their concrete filling, timbers T, with their upper surfaces in the same horizontal plane as those of the side timbers 5. Should there be any notable difference in elevation between the side timbers on opposite sides of the pier, this may be remedied by shimming. A slight difference` however, may be ignored, as the top of the concrete can be given absolutely the desired elevation when formed, will hereinafter appear. The foundation being thus secured, the spaces between t-he side timbers and supports respectively should be filled as near as practical to the height of the tops of these timbers, when all is in readiness for placing the forms thereon. These' forms or boxes are of two kinds, first, the large boxes S, and, second, the smaller boxes 9, which, for the purpose of convenience, l will term respectively, the block forms and the cell boxes. The outer or block form determines the outside dimensions of the finished concrete block, and the cell boxes the dimensions of the cells or openings in the concrete mass.
rThe block forms 9 are preferably constructed of sound and merchantable lumber'. As the lower part is to be submerged some two or three feet below the water level, that much of the box must be made water-tight or at least substantially so. For this reason they should be made from matched lumber of a thickness to give them sufficient strength to resist the pressure of the concrete filling when in a plastic condition before its setting, and the seams should be callred, if required. The bottom of the block form must also be made strong enough to carry the weight of the concrete before the setting of the latter, although the supporting timbers 7 decrease this requirement materially, and after the concrete has set, the bottom of each block form will in itself have all necessary strength to be supported by the side timbers alone by reason of I-beams 10 or other suitable reinforcing, arranged transversely of the structure to be produced.
The ends of the block forms which are to shape the sides of the superstructures will be detachably connected or nailed to the bottom of the form, and must have the inner side smooth to give the concrete a finished surface. The sides of these forms are also made detachable but need not have smooth surfaces except at the joints. ln the construe tion of these sides they are made to form buttresses l1, as best shown in Fig. l, which l are located at two or more places at each side of the finished concrete block, to insure a better connection between intermediate blocks and provide against any tendency of the connecting blocks being disturbed by heavy wave motion against the pier. After the four side walls of the block form are in their proper positions they are secured together by as many iron bands l2 (see Figs.
l and 2) as may be necessary. These bands are fastened together at the corners by bolts 13. The bands are provided with holes at suitable points, through which pass tie-rods 14 and l5, respectively arranged crosswise and lengthwise of the pier, and designed to hold the opposite sides of the forms together, and also reinforce the finished construction. rlie inside length of the block form is made equal to the width of the crib. as that dimension will determine the width of the new superstructure, the width of the form depending upon the size of form that can be conveniently handled with a. derriclr. Thus, for a pier of comparatively small width, the form may be larger than for a pier of larger width, and vice versa.
The cell. boxes 9 are preferably made of the cheapest kind of lumber, and since they are generally uniform in shape and dimensions, this lumber may be out to order in the mills to the required size and afterward nailed together, thus diminishing the cost of manufacture in so far as practicable. ln order that the cell boxes may be sufficiently strong to resist the pressure of the concrete before it sets, they may be braced on the inside, or, more generally, lled with sand, slag, riprap, or any other heavy cheap material, simultaneously with the placing of the concrete in the spaces formed between ihem and the blot-lt form, maintaining` both the fillingl of the cell boxes and the concrete at the sa me level during the process of construction. rl'he cell boxes should also be such as not to absorb water from the concrete, which condition insured by coating the wood with paraflin, asphaltine or the like.
ln placing the block forms in position, i
they should be so arranged that the ends at the inside are in exact line with the proposed site of the finished concrete superstructure. ltlbeams l() or other suitable reinforcing` (see Eig. 5) are then placed in the bottom of the box, extending from side to side, and after concrete has been filled in sutlieiently to cover them, the cell boxes, with their tops open, are properly located between the longitudinal and transverse tiebars. The filling of these boxes and of the outlying spaces, then simultaneously proceeds until the tops of the cell boxes are reached, when the covers are applied and the concrete continued over as well as around them until the desired crown is attained. Thus the whole height of the superstructure from the base to the crown is formed by a continuous operation, and will constitute, when finished, a perfect monolith. If the side timbers 5 of the foundation. do not lie in a horizontal plane, this inequality is compensated for when the top of the superstructure is reached, which can be given any desired finish either with a crown along the middle or sloped `in either direction, etc. ln locatingl the succes 'ion of block forms they must be placed sulliciently far apart to permit of the removal of the detachable lsides. if this distance is `just large enough for the purpose, and the intervening space is lilled with solid concrete, it will make the all unnecessarily heavy. lt is, therefore, deemed better to make the space large enough to place the cell boxes in, as shown in Figs. S and 5, and proceed vith the tilling in a similar manner as for the initial blocks. after the forms for producing the 'walls at the sides have been placed in posilion, as indicated in Fig.
ln connecting the `initially formed blocks with the intermediate blocks, after the former have been made and had suliicient time to sel'. the sides of the block forms are removed to make room for the special end l'ornis 1T (see Fig. 3), which are held in place by means of tie-bars 14a, which, in construction. are the same or similar to the tie-bars it. The end forms 1T should reach below the side timbers. In removing the side walls of the block forms, the nuts are taken olf the tie-bars l5 and the bolts 13 removed at which time the side walls may be slipped from the concrete. The threaded ends of the bolts are then connected with a turn-buckle, preferably as illustrated in Figs. t3 and 9, this buckle consisting of eyenuts 'lo' and a connecting link 19, the link being applied after each eye-nut has been threaded to the proper position. rlhese connections will form a strong reinforcement when surrounded with the concrete.
i t will be observed from Fig. l0 that the lieb-ars ll instead of being in the nat-ure of a continuous rod, at each end are provided with a foot in which is threaded the bolt 2O passed through the end wall of the block torni. the ends of the tie-bar proper being` spaced from the end wall by a thimble 2l, and when the bolt and wall are detached, the hole in the concrete produced by the thimble can be filled up with a thick wet mixture of cement and sand, which will prevent the rust marks usually left upon the concrete after the iron bolts have been cut otl` at the surface.
rl`he formation of the foundation for the concrete between the initially finished blocks may be made by either of the following methods: rThe lirst is illustrated in Fig. -,.L wl ei'ein the water surface in this space may be reached some two feet or more above the `upper tie of the sub-construction which forms the main support for the concrete work. rihis construction prefere. le where the placing of the concrete directly in the water is not ob jeetionable, in which case the llooring is formed resting on the crossties and crib filling and the concrete placed over this until it reaches above the water level. A' ter the I-beams l0 have been placed in position the cell boxes are then properly located and the filling proceeded with, as described for the initially formed blocks. if the placing of the concrete in *l water is objectionable then the construction may be carried out in the manner shown in Fig. G. rllhis involves the use of two concrete blocks 22, as shown in Fig. l1, equal in length to the space between the two finished concrete sections, and having a width equal to that of the side timbers of the crib, the height of the blocks being about equal to the height of the water level above the top of the side timbers. For each block 22 is provided a U-shaped hanger 23 having hooked extremities which serve the double purpose of convenience in handling and placing by means of a derrick, and, further, to make a strong connection with the mass of concrete placed about and above them. ln this construction an intermediate support will be provided in the nature of timbers 24. When the two concrete side blocks and the timbers referred to are in place, the regular stone filling of the crib should be built up equal to the height of the blocks and the side timbers, then covered with small stone and gravel, as is done for thewhole foundation. Over this gravel is placed a covering of burlap 2G. The building of the superstructure proceeds when the intermediate connecting blocks or sections of the pier are completed. The forms 17 -are removed in the same manner as the end walls of the block forms.
The process of construction as herein described is comparatively cheap, embodies simplicity, and permits of increasing or decreasing the strength of the structure, as desired, according to the requirements under different conditions, by means of the cell boxes. By making these boxes smaller, the concrete walls will be larger and consequently stronger. By constructingagreater number of cell boxes there will be a greater number of cross walls, also adding to the strength of the structure. The cell boxes may be placed in several layers, thus adding one or more horizontal walls and accordingly increasing the strength, as, for example, in high retaining walls.
By the term pier l in the appended claims, mean to include docks, wharves, break-waters and similar structures.
Having thus described my invention, I claim as new and desire to secure by Letters Patent:
l. 'lhe herein-described process of consti-noting the superstructure of a pier over crib work, which consists in filling in the substructure with ballast to a point slightly below low water level to provide a foundas tion, arranging on this foundation in spaced relation a succession of approximately water-tight box forms each having Cell boxes, filling' in the spaces between the cell boxes and forms with Concrete, removing the walls of the forms after the Concrete has set, and joining` the blocks produced to oonerete blocks of like construction.
2. A pier having a superstructure Colnposod of a series of cellular concrete sections arranged cross-wise of the pier and oonneeted together.
3. The herein-described process of Constructing the superstructure of a pier, which consists in arranging on the foundation of the pier, in spaced relation, a succession of box forins each having cell boxes, filling in the forms around the boxes with concrete, removing the walls of the forms and joining the blocks produced to concrete blocks of like construction.
In testimony whereof I have signed my naine to this specification in the presence of two subscribing` witnesses.
GUSTAVE A. M. LILJENCRANTZ.
Witnesses JAMES J. REYNOLDS, H. E. h/IARSHALL.A
US44981208A 1908-08-22 1908-08-22 Concrete construction and method of producing the same. Expired - Lifetime US925204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US44981208A US925204A (en) 1908-08-22 1908-08-22 Concrete construction and method of producing the same.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US44981208A US925204A (en) 1908-08-22 1908-08-22 Concrete construction and method of producing the same.

Publications (1)

Publication Number Publication Date
US925204A true US925204A (en) 1909-06-15

Family

ID=2993633

Family Applications (1)

Application Number Title Priority Date Filing Date
US44981208A Expired - Lifetime US925204A (en) 1908-08-22 1908-08-22 Concrete construction and method of producing the same.

Country Status (1)

Country Link
US (1) US925204A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4824290A (en) * 1985-11-17 1989-04-25 Ahmad Masoudi Method of constructing a rigid structure upon the bottom of a water as well as lost casing for performing said method
US20140306088A1 (en) * 2013-04-16 2014-10-16 Richard J. Dryburgh Concrete slab forming apparatus

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4824290A (en) * 1985-11-17 1989-04-25 Ahmad Masoudi Method of constructing a rigid structure upon the bottom of a water as well as lost casing for performing said method
US20140306088A1 (en) * 2013-04-16 2014-10-16 Richard J. Dryburgh Concrete slab forming apparatus
US9169643B2 (en) * 2013-04-16 2015-10-27 Richard J. Dryburgh Concrete slab forming apparatus

Similar Documents

Publication Publication Date Title
US925204A (en) Concrete construction and method of producing the same.
US1083289A (en) Method of building concrete dock-walls.
US1063672A (en) Process of constructing sewers, aqueducts, &c.
US1952380A (en) Wall structure
US718441A (en) Method of making substructures for buildings.
US677649A (en) Combined box-cap and shoe-plank holder.
US483697A (en) Dry-dock
US1394571A (en) Subaqueous structure and method
US1167159A (en) Construction of concrete sewers, aqueducts, &c.
US1221067A (en) Tunnel and method of building same.
US891966A (en) Concrete sea-wall.
US1124955A (en) Pile construction.
US2102254A (en) Method and apparatus for building sea walls
US1858664A (en) Emergency closure or lock for weirs, sluice gates, and the like
US635906A (en) Construction of docks, &c.
US1054224A (en) Construction of sea-walls, piers, pontoons, &c.
US574729A (en) gillespie
US1487021A (en) Reenforced-concrete construction
US317337A (en) goodridge
US637935A (en) Block for building moles, dams, piers, & c.
US838389A (en) Method of constructing masonry structures.
US659157A (en) Freezing-tank for manufacturing artificial ice.
US1221068A (en) Method of building and placing piers.
US901040A (en) Sea-wall.
US1165134A (en) Pile or column construction.