US3902422A - Explosive fracturing of deep rock - Google Patents

Explosive fracturing of deep rock Download PDF

Info

Publication number
US3902422A
US3902422A US382845A US38284573A US3902422A US 3902422 A US3902422 A US 3902422A US 382845 A US382845 A US 382845A US 38284573 A US38284573 A US 38284573A US 3902422 A US3902422 A US 3902422A
Authority
US
United States
Prior art keywords
rock
segment
holes
liquid
cavities
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US382845A
Inventor
David Linn Coursen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ETI EXPLOSIVES TECHNOLOGIES INTE
Original Assignee
EI Du Pont de Nemours and Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by EI Du Pont de Nemours and Co filed Critical EI Du Pont de Nemours and Co
Priority to US382845A priority Critical patent/US3902422A/en
Priority to AU71586/74A priority patent/AU489283B2/en
Priority to CA000205542A priority patent/CA1123726A/en
Priority to GB5174/77A priority patent/GB1482024A/en
Priority to GB32879/74A priority patent/GB1482023A/en
Priority to US05/535,808 priority patent/US3999803A/en
Priority to US05/547,750 priority patent/US4239286A/en
Application granted granted Critical
Publication of US3902422A publication Critical patent/US3902422A/en
Priority to CA000397641A priority patent/CA1144473A/en
Assigned to ETI EXPLOSIVES TECHNOLOGIES INTE reassignment ETI EXPLOSIVES TECHNOLOGIES INTE ASSIGNMENT OF ASSIGNORS INTEREST. Assignors: E.I. DU PONT DE NEMOURS AND COMPANY
Assigned to TORONTO DOMINION BANK reassignment TORONTO DOMINION BANK SECURITY INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: ETI EXPLOSIVES TECHNOLOGIES INTERNATIONAL INC.
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/25Methods for stimulating production
    • E21B43/26Methods for stimulating production by forming crevices or fractures
    • E21B43/263Methods for stimulating production by forming crevices or fractures using explosives
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/28Dissolving minerals other than hydrocarbons, e.g. by an alkaline or acid leaching agent
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/30Specific pattern of wells, e.g. optimising the spacing of wells
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping

Definitions

  • AppL NO; 382,845 High permeability is maintainedin an explosively fractured segment of rock by flushing the fractured rock with liquid, i.e., by sweeping liquid through the fracture zones with high-pressure gas, between sequential 166/63 detonations therein so as to entrain and remove fines [51] int. Cl.
  • F42d 3/04 th refron Ore bodies prepared by the blast/flush pr Field of Search 299/4, cess with the blasting carried out in substantially verti- 102/22, 23 cal, optionally chambered, drilled shot holes can be leached in situ via a number of holes previously used References Cited as injection holes in the flushing procedure and a UNITED STATES PATENTS number of holes which are preserved upper portions 2,630,182 3/1953 Klotz JR u H 166/63 of the shot holes used in the detonation process.
  • the present invention relates to the production of a network of fractures in a deep underground segment of rock by means of explosives, e.g., to prepare deep ore bodies for in situ leaching.
  • Processes for fracturing deep rock are becoming increasingly important as it becomes necessary to tap deep mineralized rock masses, e.g., ore bodies or oil or gas reservoirs located from about 100 feet to about a few thousand feet beneath the earths surface, in order to supplement or replace dwindling energy sources and minerals supplies.
  • Numerous deposits of ore, for example ore containing copper, nickel, or silver lie too deep to mine by openpit methods or are too low in grade to mine by underground methods.
  • Open-pit methods incur both in costs and the environmental impact associated with moving large quantities of earth and rock.
  • Underground methods incur unusually high costs per unit volume of ore mined, as well as difficult safety problems.
  • the leaching of ore in place circumvents these difficulties and therefore can be preferred technique for winning values from some ores that are unsuitable, or marginally suitable, for working by traditional mining methods.
  • the leachability of a fractured ore body depends on the size of the ore fragments, and on the permeability of the intact ore as well as of the fracture system separating the fragments.
  • the permeability of the fracture system separating the fragments which is variable and generally much higher than the permeability of a single fragment, is determined by a network of wider, open fractures (determining the permeability of the ore body as a whole), and a network of narrower, open fractures (determining the irrigability of individual particles to be leached). Therefore, in explosively fracturing a segment of an ore body to prepare it properly for in situ leaching, the objective is not simply an indiscriminate reduction in the fragment size of the ore body.
  • This invention provides a process for producing a fracture network in a deep subsurface segment of rock, e.g., in an ore body, comprising (a) forming an assemblage of cavities, e.g., drill holes or tunnels, in the segment of rock; (b) positioning explosive charges in a plurality of the cavities in the sections thereof located in the segment of rock to be fractured, e.g., in sections of drill holes which have been previously chambered, such as by an explosive springing procedure; (0) providing for the presence of liquid in the segment of rock, e.g., by virtue of the location of the segment of rock below the water table so that water naturally is present in, or flows into, fractures therein, or by introducing liquid into one or more cavities therein; and (d) detonating the charges sequentially in a manner such as to progressively produce a cluster of overlapping fracture zones, the detonation of each charge in the detonation sequence producing a fracture zone which is subject to the cumulative effect of
  • the cavities formed are substantially vertical drill holes
  • some of the holes in the assemblage preferably are left uncharged with explosive, and these holes employed as a set of passageways within the fracture network from the earths surface, generally to substantially the bottom of the blasted rock, e.g., for the introduction of liquid and/or gas to (or removal thereof from) the fracture network.
  • the uncharged holes preferably are drilled and provided with support casing prior to the detonation of charges in adjacent holes.
  • the sections of substantially vertical shot holes located in the overburden that overlies the rock segment to be fractured preferably survive the blasting process and serve as an additional set of passageways, leading from substantially the top of the blasted rock to the earths surface, also for liquid and/or gas passage.
  • liquid is driven through the fracture zones produced by the sequential detonation of explosive charges in a plurality of cavities in a segment or rock, in a manner such as to entrain the fines found in the fracture zones, and the fines-laden liquid removed from the rock.
  • This flushing of the blasted rock is achieved by sweeping or driving liquid at high velocity through the fracture zones by injecting gas into said zones at high pressure, the liquid moving laterally and upwardly through the blasted rock, passing into the fractures, for example, from the passageways formed by uncharged substantially vertical drill holes and out of the fractures into passageways formed by preserved sections of substantially vertical detonated holes located in the overburden.
  • deep as used herein to describe a subsurface segment of rock denotes a depth at which the det- 'onation causes no significant change in the overlying topography, i.e., the surface does not swell.
  • deep rock as described herein lies at a depth of at least 100, and usually not more than 3000, feet.
  • Fracture zones and fractured rock herein denote zones and rock in which new fractures have been formed, or existing fractures opened up, by the detonations. Fracturing denotes herein a treatment which reduces the size of, and/or misaligns, rock fragments.
  • FIG. 1 is a schematic representation in plan view of a subsurface segment of rock which has been fragmented by the blast/flush process of the invention, and the liquid circulation pattern between holes therein;
  • FIG. 2 is a schematic representation in elevation showing the surface-to-surface liquid circulation pattern through the segment of rock shown in FIG. 1;
  • FIG. 3 is a schematic representation of a shot hole pattern described in the example.
  • FIG. 4 is a plot showing the effect of repeated blast/- flush operations on the permeability of a fracture zone produced with the shot hole pattern shown in FIG. 3.
  • explosive charges are detonated sequentially in separate cavities in a segment of mineralized rock to be fractured, each detonation in the sequence producing a zone of fracture in the rock and being delayed until liquid is present in the fractured rock around the cavity containing the charge to be detonated, especially in fracture zones produced by the previous detonation of charges in cavities adjacent thereto.
  • the detonations occur while fractures in the surrounding rock are filled with liquid, or the rock is in a flooded, or liquid-soaked, condition.
  • the cavities e.g., drill holes or tunnels, containing the explosive charges are spaced sufficiently close together, and the charges are sufficiently large, that the fracture zones produced by the detonations therein overlap one another.
  • each fracture zone is within the region of influence of other detonations and is subject to the cumulative effect of a succession of detonations of explosive charges in a group of adjacent cavities.
  • This cumulative effect permits the fragment size-reduction and disorientation needed to enhance leachability to be obtained readily from the available explosive energy.
  • the degree of overlapping of the fracture zones which are generally cylindrical in shape, is at least that required to locate all of the rock, in the segment of rock to be fractured, within the fracture zone produced by the detonation of at least one of the charges.
  • the cavities in the assemblage in which explosive charges are to be detonated can be substantially vertical holes (shot or blast holes) drilled into the segment of rock from the surface or from a cavity in the rock, or substantially horizontal cavities such as tunnels, driven in the rock, e.g., from a hillside or shaft.
  • substantially vertical holes shots or blast holes
  • substantially horizontal cavities such as tunnels, driven in the rock, e.g., from a hillside or shaft.
  • the cavity volume is provided by tunnel driving techniques such as are employed in coyote blasts, for example, or drilling techniques, possibly associated with chambering procedures, will be largely a question of economics, although technical practicability depending on such factors as topography, compressive strength of the rock, etc., will influence the selection of the method.
  • Substantially vertical drill holes are preferred in many cases since the preserved sections of the shot holes can be used subsequently as passageways to or from the fractured rock, reducing the number of holes needed to be drilled solely to provide passageways for liquid injection or e
  • blast cavities need not form a regular pattern, and regularity of pattern actually may not be desirable or practical, a somewhat regular pattern is indicated in a formation of reasonably uniform contour, structure, and physical strength to assure a high degree of uniformity in the fracture network produced.
  • a regular pattern e.g., to use one or more additional blast cavities where needed to provide the required overlapping of fracture zones. Nevertheless, substantial regularity of pattern generally will be provided in the arrangement of most of the blast cavities.
  • the distance between explosive charges (and, also therefore, between cavities) of a given composition and size is such that a cluster of overlapping fracture zones is produced by the detonation of adjacent charges.
  • the extent or radius of the fracture zone. that can be expected to result from the detonation of an explosive charge of a given composition, density, shape, and size under a given amount of confinement in a given geological mass can be approximated by making some experimental shots and studying the fracture zones surrounding the blast cavities by using one or more geophysical methods.
  • geophysical methods include l coring, (2) measurements in satellite holes of compressional and shear wave propagation, of permeability and of electrical conductivity, and (3) acoustic holography. Based on these studies, the cavities are spaced close enough together to provide the required overlapping of fracture zones.
  • Adjacent blast cavities or explosive charges are blast cavities or explosive charges which, although spaced from one another, are immediate or nearest neighbors to one another, as contrasted to blast cavities or explosive charges which are more distant neighbors or separated from one another by one or more other blast cavities or explosive charges.
  • the delaying of each detonation until liquid is present in the fracture volume surrounding the cavities is believed to have two beneficial effects.
  • the liquid can lubricate the fractures so that opposing faces can move suddenly in shear more easily, thereby enhancing fragmentation of the surrounding rock, which is no longer supported by the relatively high resistance of a dry fracture to transient shear.
  • liquid-filled fracture volume cannot be rammed shut by the suddenly applied pressure of an explosion. This incompressible behavior, together with the low resistance of the liquid-filled fractures to sudden small displacements in shear, is believed to cause disorientation of individual rock fragments and dilation and swelling of the bed of fragments as a whole.
  • each detonation creates a misalignment or disarrangement of fragments with an accompanying increase in void volume. Therefore, when the fracture zones produced by the successive detonations in adjacent cavities partially overlap, the fracture zone around each cavity thereby being subject to additional fracturing and/or disorientation produced by the detonations in the adjacent cavities, and previously produced fracture zones are flooded, each fracture zone will be swelled in incre ments, with each detonation jacking it to larger volume, and higher permeability, against the pressure of the surrounding rock.
  • the present process makes use of the lubricating effect and incompressible behavior of the liquid in the fractures, and does not require the use of high liquid pressures, e.g., of the magnitude needed to lift the overburden and enlarge the fractures before blasting.
  • a liquid pressure in the fractures at the time of blasting equal to the head of liquid above the blast zone is sufficient.
  • any readily available, relatively cheap liquid e.g., water or water mixtures, can be used to flood the rock. lf leaching of ore is performed in the course of the detonation sequence, a lixiviant can be used as the flooding liquid.
  • any fluid explosive which may be used in the present process will be gelled to a viscosity that will hinder any appreciable loss thereof from the blast cavities to the surrounding fracture zones, and in any case will not be sufficiently sensitive to be detonated in said zones.
  • the explosive charges may escape into the fracture zones, such material will behave as a non-explosive liquid therein. Accordingly, the flooding liquid is non-explosive.
  • a preferred blast cavity pattern for use in the present process is one in which substantially all of the internal cavities, i.e., cavities not located at the edge of the pattern, are surrounded by at least four adjacent blast cavities, e.g., a pattern in which the blast cavities are at the corners of adjacent polygons, which are either quadrangles or triangles and which are as close to equilatera] as permitted by wander of the cavities, as shown in FIG. 1.
  • blast holes in a group of adjacent substantially vertical drill holes can be drilled prior to the sequential detonation of the charges, this procedure is not preferred inasmuch as it could be necessary to apply a support casing to the as-yet undetonated holes in the sections thereof located in the segment of rock to be fractured to prevent them from collapsing as a result of detonations in adjacent holes.
  • Casing of the shot holes in these sections usually would be considered economically unsound because the casing would occupy volume that could otherwise be loaded with explosive and because casing in these sections of the holes is not needed in subsequent leaching operations. Therefore, it is preferred that in a group of adjacent drilled shot holes the detonation of each charge takes place before adjacent shot holes are drilled.
  • the avoidance of the presence of drilled shot holes during detonations refers to holes in a group of adjacent holes, e.g., a central hole and four to six surrounding holes. However, shot holes farther removed from the detonations can be pre-drilled.
  • the total amount of drilling needed for verticalcavity blasting can be reduced by drilling one or more branch or off-set holes by side-tracking from one or more points in the preserved upper portion of a trunk hole which extends to the surface.
  • Each off-set hole is drilled after the charges in the trunk hole and other offset holes thereof have been detonated. Such holes will be inclined at small angles to one another.
  • liquid is present in the rock around each cavity prior to the detonation of the charge therein. This means that liquid is present in any pre-existent fractures in the zone which will become a fracture zone as a result of the detonation of the charge in that cavity, and in fractures produced by previous detonations in cavities adjacent thereto. This condition permits the above-described incremental swelling of overlapping fracture zones to take place.
  • the liquid level in the rock around the hole should be at least as high as the top of the charge in the hole, thereby assuring the presence of liquid throughout the height of the formation where fracturing will occur.
  • the liquid level in the rock around the cavity should be at least as high as the radius of fracture to be produced by the detonation of the charge therein.
  • the segment of rock to be fractured is located below the water table, the position of the water table above it will conform to the water levels in undisturbed holes, and may be inferred at other locations by interpolation between the elevations of the water levels in undisturbed holes.
  • the water table will almost always be sufficiently horizontal that the first charge can be detonated when the elevation of the liquid level in any nearby hole is at least as high as the elevation to be reached by the top of the charge (or radius of fracture in the horizontal cavity case).
  • the level before loading of the explosive into the cavity should be the level measured.
  • the liquid level in cavities within the resulting fracture zone drops in proportion to the new fracture volume produced, the expulsion of liquid from the immediate vicinity of the charge by the gaseous products of detonation, and the drainage of liquid into the cavity created by the detonation.
  • the detonation of the next charge in the sequence in a cavity adjacent to the first is delayed until the liquid in the formation around the next cavity (including the new fracture volume produced by the previous detonation in an adjacent cavity) returns to its required level.
  • explosive charges in blast cavities elsewhere in a section of the formation that is not strongly influenced by a previous detonation (i.e., where the liquid level has not dropped below the required elevation as a result of the previous detonation) can be detonated at any time after the previous detonation.
  • the delay to allow flooding applies to detonations in cavities which are adjacent to previously detonated cavities, where the previously formed fracture zones will be subject to the effect of the next detonation.
  • some of the holes in an assemblage of substantially vertical holes preferably are left uncharged with explosive, these holes providing passageways to the fractured rock to allow the introduction of gases and/or liquids thereto, e.g., in a subse' quent leaching operation.
  • These holes which can thus be looked upon as injection holes (although they may serve as ejection or recovery holes depending on the required flow pattern), are also useful in preparing the ore body for leaching, as will be described more fully hereinafter, and it is preferred, on the basis of ease of drilling, that they be drilied prior to the sequential det onation process in holes surrounding them.
  • Pre-drilled injection holes are provided with a support casing, e.g., unperforated pipe grouted to the upper part of the hole wall, at least in the section thereof located in the segment of rock to be fractured, and ungrouted perforated pipe or a wellscreen in the bottom section of the hole, in order to prevent hole collapse as a result of the detonations.
  • a support casing e.g., unperforated pipe grouted to the upper part of the hole wall, at least in the section thereof located in the segment of rock to be fractured, and ungrouted perforated pipe or a wellscreen in the bottom section of the hole, in order to prevent hole collapse as a result of the detonations.
  • a support casing e.g., unperforated pipe grouted to the upper part of the hole wall, at least in the section thereof located in the segment of rock to be fractured, and ungrouted perforated pipe or a wellscreen in the bottom section of the hole, in order to prevent hole collapse
  • the location and pattern of the injection holes are selected on the basis of their intended function during the fracturing and leaching processes, which will be described in detail hereinafter.
  • the overall purpose of these holes usually is to provide a means for introducing gases and/or liquids into the fracture network produced, or being produced, and therefore the injection holes should be distributed throughout the segment of rock among the blast cavities in a manner such that they lie within the fracture zones produced by the detonations.
  • the resulting fracture zone permits communication between a neighboring injection hole and the portion of the shot hole remaining in the overburden.
  • the shot hole remnants thereby act as passageways to complete the liquid circuit through the fractured rock.
  • an injection hole lying within the fracture zone produced by a previous detonation in a cavity adjacent to a cavity to be shot can be employed to determine whether the liquid level in the rock surrounding the cavity to be shot has recovered sufficiently to flood the section to be blasted.
  • a nearby injection hole can be used.
  • Liquid is run into a blast cavity after the explosive charge has been emplaced therein (if the charge is stable in the presence of water), and liquid level measurements, if required, are made in nearby injection holes.
  • hydraulic potential measurements e.g., pressure measurements made with a piezometer, or liquid level measurements, will not be required after each detonation, inasmuch as the experience gained in determining the necessary delay times to permit recovery of hydraulic potential between a few of the early detonations in the sequence will usually allow the practitioner to select with confidence suitable delay times to be used between subsequent detonations.
  • the exact delay required depends on the size of each blast, the void volume to be filled, the elevation of the segment to be blasted relative to the water table, and the hydraulic transmissibility of the surrounding rock, delays on the order of hours or days generally will be needed.
  • the time required for a shot hole to be drilled, or a tunnel to be driven, and loaded with explosive usually will be more than sufficient for the hydraulic potential around the cavity and the previously detonated adjacent cavities to recover to the minimum required level either by natural influx of water from the surrounding rock or by introduction through cavities made in the formation.
  • delays refer to the time between detonations of adjacent charges, and that one or more charges whose zones of fracture are non-adjacent (i.e., whose regions of influence are mutually exclusive) can be detonated at much shorter delay times or even simultaneously.
  • the flushing can be accomplished by the pressure injection of liquid and gas into the fractured rock through one or more injection holes, and removal of the finesladen liquid from the fractured rock by bringing it to the surface through one or more detonated shot holes, in the preserved sections of the latter which pass through the overburden to the surface.
  • Liquid and gas e.g., water or other aqueous liquid and air or oxygen
  • gas alone can be injected so as to sweep ahead the liquid already present in the fractures.
  • a liquefied gas such as air, nitrogen, oxygen, can be introduced into the injection holes and allowed to vaporize therein and thereafter drive the liquid through the fractures.
  • the circulation of the liquid is powered by gas lift such that the gas chases the liquid upward and outward through the broken formation, and fines are driven toward the zones of severest fracture, where their concentration is heaviest, from which zones they are ejected with the liquid.
  • This direction of sweep is preferred inasmuch as the reverse direction drives the fines more deeply into the less severely worked zones of the formation away from their point of heaviest concentration and can cause an intensified clogging of the fractures.
  • the surging high-velocity flow which develops with the upward two-phase flushing system removes fines that prevent free irrigation around the fragments.
  • two or more vertically separated injection zones in a given injection hole can be employed, one substantially at the bottom of the fractured rock and one or more others above it.
  • the buoyancy of the pressurized gas alone can be sufficient to raise the fines-laden liquid to the surface of the ground when the water table is relatively close to the surface.
  • the buoyancy is insufficient, the liquid can be pumped up the collar of the shot hole.
  • the gas injection pressure should be higher than the ambient hydrostatic pressure at the position in the injection hole where injection occurs, and preferably higher than the lithostatic pressure at this position.
  • the minimum gas pressure required for flushing is highest at the start of the operation and falls as gas injection proceeds.
  • a detonation in any given cavity be followed by detonations in no more than two or three adjacent cavities, and most preferably by a detonation in no adjacent cavity, before the fracture zone produced by the detonation in the given cavity has been flushed out as described.
  • a detonation in any given cavity be followed by detonations in no more than two or three adjacent cavities, and most preferably by a detonation in no adjacent cavity, before the fracture zone produced by the detonation in the given cavity has been flushed out as described.
  • a cyclic blast/flush/blast/flush, etc. process is preferred.
  • One or more fracture zones can be flushed at the same time, and flushing of the same zone can be repeated, if desired.
  • An already flushed zone can be left untreated during the flushing of adjacent zones by plugging the ejection hole in that zone. Flushing of one or more zones can be carried out while adjacent blast cavities are being drilled and loaded.
  • the detonation of the charges in sequence permits the preservatioon of the sections of substantially vertical shot holes that pass through the overburden (the strata overlying the rock segment being worked), and these sections of the shot holes can serve as ejection holes in the flushing process, as described above.
  • The' reduced fragment size and unclogged fracture network achieved after all of the charges have been detonated, and the detonations followed by a flushing procedure produce, in the case of an ore body, an ore which is well-prepared for in situ leaching.
  • the present invention also provides a leaching process wherein fines are flushed out of a mass of ore by driving lixiviant through the mass by means of highpressure gas, e.g., in a specific circulation pattern.
  • an ore body which has been prepared for leaching by detonating explosive charges in separate cavities therein e.g., according to a process of this invention, is leached in situ by introducing lixiviant for the ore into the prepared ore body through a plurality of injection holes therein and intermittently or continuously driving the lixiviant through the ore body to a plurality of recovery holes by means of high-pressure oxidizing gas, the lixiviant moving laterally and upwardly from zones that have been less severely worked, to others that have been most severely worked, by the detonations, whereby fines are removed from the ore body.
  • the lixiviant for the ore can be injected into the ore body through injection holes which have previously been used in the flushing steps, and fines-laden pregnant leach solution recovered from the ore body through the preserved upper portions of shot holes, piping having been grouted into all holes used to circulate lixiviants and pumps provided as necessary to inject lixiviants in one set of holes and remove pregnant liquor from another set of holes.
  • the bottom ends of the pipes and any other positions along the pipes where lixiviants are to be injected or collected are provided with perforations or wellscreens.
  • the lixiviant e.g., sulfuric acid/water or sulfuric acid/nitric acid/water for ores whose acid consumption is within tolerable levels, or Ni-LOH/water for ores having a high acid consumption
  • a gas usually an oxidizing gas, preferably oxygen, air, N or mixtures thereof, are injected into the base of the prepared ore body at high pressure.
  • an oxidizing gas preferably oxygen, air, N or mixtures thereof
  • the holes designated by the letter S are substantially vertical shot holes. Within the blasted segment of rock, these holes are destroyed by the detonations which have taken place therein in the fracturing process and are replaced by the adjacent, overlapping fracture zones shown in the upper half of the figure, and also denoted by the letter S, to indicate a previous shot hole.
  • the shot holes rather than the fracture zones are shown in the lower half of the figure so that liquid circulation lines can be indicated clearly.
  • the holes designated I are injection holes. These holes are uniformly distributed among the shot holes as shown.
  • the arrows indicate the direction of flow of liquid from injection holes 1,, l I I 1;, and I to the preserved upper section of shot hole S and from injection holes I,,, I I I,,, and two other undepicted injection holes to the preserved upper section of shot hole S
  • the preserved upper section of shot hole S is plugged off while shot holes S and S are being used for flushing or as recovery holes for pregnant leach solution. At the same time, liquid injected into these injection holes is being driven to other open shot holes.
  • piping in injection hole I and shot hole S is shown as it passess through overburden 1 to the fractured rock segment 2.
  • Piping 6 in injection hole I leads from the earths surface 3 to substantially the bottom of rock segment 2.
  • Piping 7 in shot hole S leads from the earth s surface 3 to the top of rock segment 2.
  • Fracture zone 4 has been produced by the detonation of an explosive charge in shot hole S, which before the detonation led to substantially the bottom of rock segment 2.
  • Piping 7 terminates in well screen 5, and piping 6 is provided with perforations vertically spaced along the length thereof located in rock segment 2.
  • liquid is injected into fractured rock segment 2 through the perforations in piping 6, then is driven by pressurized gas through the fractured rock as indicated by the arrows, and leaves the top of the rock segment through piping 7. Lateral as well as upward flow occurs from the less severely worked zone around hole I to the most severely worked zone, i.e., fracture zone 4.
  • Regulation of the rate at which gas and liquid lixiviant are injected and collected at the various injection and collection holes allows a high degree of control of the in situ leaching process.
  • the injection and collection pressures can be regulated to obtain a relatively uniform flow through the ore body in spite of variations in permeability from place to place. Shifting the injection or collection from one set of holes to another will change the direction of flow through the ore and can be used to frustrate channelling.
  • the regulation of pressures and flow rates at the various holes can be used to maintain a net flow of ground water toward the operation under conditions that might otherwise result in the escape of leach solution.
  • Leakage of the leach solution is also reduced in the present process as a result of the carriage of some of the fines away from the area of gas agitation where they settle out and plug the leak.
  • the gasliquid pressure injection can be intermittent or continuous, depending upon the degree to which the ore tends to plug up, and the frequency with which flow patterns are changed to obtain uniform and complete leaching throughout the ore.
  • lixiviant When lixiviant is introduced into an injection hole simultaneously with gas, its injection pressure should be equal to that of the gas, i.e., higher than the ambient hydrostatic pressure at the injection point, and preferably higher than the lithostatic pressure at this point. In some cases, especially at greater depths, the injection of lixiviant and oxidizing gas at sufficient pressure to exceed the lithostatic pressure may be necessary in order to get sufficient flow rate through the ore. If, in some or all of the injection holes, there are periods of time when lixiviant alone is introduced into the ore, this introduction preferably is done at a pressure at least as high as the lithostatic pressure at the injection position. That is, the pumping pressure preferably is at least as high as the lithostatic pressure minus the heads of fluid in the piping leading from the pump to the injection po sition.
  • permeability can be increased also in ore masses such as mine waste dumps by driving lixiviant through fractures therein by means of gas at sufficiently high pressure that the lixiviant is swept through at a rate sufficiently high to entrain fines present in the fractures, and removing the finesladen lixiviant from the ore mass.
  • the sections of substantially vertical shot holes which are located in the segment of rock to be fractured are first chambered to larger diameter, and the explosive charges positioned in the chambered portions.
  • drilling costs are reduced by drilling widely spaced-apart shot holes of smaller diameter than is required to accommodate the size of explosive charges to be employed, and enlarging or springing the lower parts of the shot holes to produce chambers having the volume required to hold the explosive charge.
  • the sections of the holes in the rock segment are chambered either by drilling them out, e.g., with an expansion bit, or by detonating explosive charges therein.
  • the chambering method is not critical, the preferred method generally being the one that results in the lowest overall cost per unit of chamber volume for the particular rock segment in question.
  • explosive charges used for springing may be 20 feet or more in length. If rock fragments tend to fall from the walls of an explosively sprung hole and thus to occupy some of the volume required for the explosive charge subsequently to be used in producing the fracture zone, the
  • hole to be sprung can be drilled deeper so that the bottom of the hole is located below the bottom of the formation. In this manner, any loss in volume that is to be available for explosive loading is minimized since a portion of the chamber volume below the segment of rock to be fractured can hole the fallen rock fragments.
  • the extreme magnitude and concentration of the energy produced in a nuclear blast imply that it will be difficult, if not impossible, to achieve (a) a high degree of uniformity in explosion-energy distribution and ore breakage, (b) close hydraulic control of the flow of lixiviants without an appreciable amount of additional drilling to increase the number of injection and extraction points, and (c) a close match of the broken volume with the outline of the ore body, particularly for small or irregular ore bodies, such a match resulting in economies in the use of the available explosive energy and in the consumption of lixiviants.
  • the charges While single explosive charges generally will be deto nated in sequence to produce the fracture zones, the charges also can be multi-component charges positioned in separate cavities and detonated substantially simultaneously as a group to produce each fracture zone, each detonation in the sequence of detonations in such a case being a group of detonations.
  • the formation to be fractured was a bedded series of shales and silt stones, dipping about 45, located at a depth of to feet below the surface, and therefore subjected to a lithostatic pressure of about 70 to 90 p.s.i.
  • the water table was at a depth of about 15 feet below the surface.
  • a 3-inch-diameter hole was drilled into the formation to a depth of feet. This hole was used as a coresampling and permeability-testing hole, and also as an injection hole for purposes of flushing surrounding shot holes.
  • a core test revealed a competent silty shale at the 70-90 foot depth.
  • a well screen was installed in the hole at the 7090 foot level, and piping to the well screen was grouted to the hole. Cement filled the hole below the well screen.
  • the pattern of shot holes used is shown in FIG. 3.
  • Three shot holes (SH 1, SH 2, and SH 3) were located 16.25 feet from the injection hole I, their centers lying on radii from the center of hole I and the lines joining them forming an equilateral triangle. The distance between these shot holes was 28 feet.
  • Three shot holes (SH 4, SH 5, and SH 6) were located 32.5feet from hole 1, their centers also lying on120 radii from the center of hole 1, and the lines joining them (also forming an equilateral triangle) being bisected by the centers of holes SH 1, SH 2, and SH 3.
  • the distance between holes SH 4, SH 5, and SH 6 was 56 feet. It is seen that in this arrangement the lines joining adjacent (i.e., nearest neighbor) shot holes formed equilateral triangles.
  • SH 1, SH 2, and SH 3 each had four shot holes adjacent thereto (SH 2, SH 3, SH 4, and SH 5 for SH 1; SH 1, SH 3, SH 5, and SH 6 for SH 2; and SH 1, SH 2, SH 4, and SH 6 for SH 3), and SH 4, SH 5, and SH 6 each had two shot holes adjacent thereto (SH 1 and SH 3 for SH 4; SH 1 and SH 2 for SH 5; and SH 2 and SH 3 for SH 6).
  • Shot hole SH 1 was drilled first.
  • the hole was 5 inches in diameter and 91 feet deep and was loaded with 255 pounds of an aluminized water gel explosive having the following composition: 18.9% ammonium nitrate, 10.5% sodium nitrate, 29.6% methylamine nitrate, 30% aluminum, and 11% water.
  • the explosive column was 21.7 feet high, and was covered by a layer of water which naturally flowed into and filled the remainder of the hole and stemmed the explosive charge.
  • the water level in the injection hole was above the level of the top of the explosive charge in the shot hole, indicating that the rock surrounding the shot hole was properly flooded. Before the explosive charge was initiated, the permeability and sound velocity of the rock surrounding the injection hole were measured.
  • the permeability was determined by slug tests, in which the permeability is inferred from the rate at which the head of liquid subsides toward the ambient level in a hole after the rapid introduction of a slug of liquid therein (see Ferris, .I. G., et 21]., Theory of Aquifer Tests, US. Geological Survey, Water-Supply Paper l536-E, 1962).
  • the sound velocity measured at depths of 74.5 feet to 85 feet between the injection hole, shot hole SH 1, and a test hole collared 13 feet on the opposite side of the injection hole, was 3970 meters per second.
  • the explosive charge in shot hole SH 1 in the flooded formation was detonated, whereupon the water level in the injection hole dropped to below its pre-detonation level, as a result of the formation of a new fracture volume around shot hole SH 1, the chasing of water from the rock fractures by the gaseous detonation products, and the flow of water into the cavity created by the explosive charge.
  • the second shot hole (shot hole SH 2) was drilled to the same size as shot hole SH 1, and the rock surrounding shot hole SH 1 was then flushed with water by (a) blowing compressed air into the bottom of the open injection hole (b) injecting water through a packer in the injection hole, and (c) three long air injections, and then (d) 18 short air injections through a packer in the injection hole.
  • the total flushing time was about 4 hours.
  • Silt-laden water was ejected from shot hole SH 1 (but not shot hole SH 2) during the flushing, indicating the preservation of the top of shot hole SH 1, the circulation of the water from the bottom of the rock segment (bottom of the injection hole) laterally and upward through the fracture network to the top of the rock segment (bottom of shot hole SH 1 and the removal of fines from the fractures.
  • the permeability was measured in the injection hole (as described above) before and after the flushing operations.
  • Shot hole SH 2 and subsequently drilled shot hole SH 3 were loaded and the charges therein detonated as described for shot hole SH 1.
  • the water level in the injection hole returned to its pre-detonation level, above the level of the top of the explosive charge in shot hole SH 1 before detonation, in about 18 hours. Thereafter, the charge in shot hole SH 2 was detonated, whereupon the water level in the injection hole again dropped to below its predetonation level.
  • the rock surrounding shot hole SH 2 was flushed with water, and siltladen water ejected from shot hole SH 2, by sealing off shot hole SH 1 and (a) injecting air through a packer in the injection hole, (b) blowing compressed air into the bottom of the open injection hole, and (c) injecting air through a packer while blowing compressed air into the bottom of shot hole SH 3.
  • the total flushing time was about 1 1 hours.
  • the permeability was again measured before and after the flushing operations.
  • the remaining shot holes SH 4, SH 5, and SH 5 were drilled, loaded, and detonated in the same manner as holes SH 1, SH 2, and SH 3, with the detonations occurring after the return of the water level in the injection hole to its predonation level.
  • the rock surrounding hole SH 4 was flushed by three air injections in the injection hole, each followed by water injection; between the shooting of shot holes SH 5 and SH 6, the rock surrounding hole SH 5 was flushed by injecting air into the injection hole, and blowing air down hole SH 6 (unshot), separately and simultaneously; and after hole SH 6 was shot, the rock surrounding it was flushed by alternately injecting air into the injection hole and blowing air down the surviving section of hole SH 6.
  • the permeabilities measured by slug tests in the injection hole before the blast/flush process began and after each blast and flush operation at each of the six holes are plotted in FIG. 4 as a function of the operation performed, the permeabilities being presented in millidarcys on a logarithmic scale as the ordinate.
  • Nineteen points are shown, including those obtained after the four flushing procedures (a, b, c, and d) described above after the shooting of hole SH 1; three flushing procedures (a, b, and c) after the shooting of hole SH 2; and two flushing procedures (a and b) after the shooting of hole SH 3.
  • Each point denotes the average permeability measured after a given operation.
  • the plot shows that the permeability of the rock was increased considerably (from 500 to over 2000 millidarcys) by the total six-cycle blast/flush process, and that variations in permeability occurring during the cyclical shooting and flushing tend to decrease as the rock is broken and swelled.
  • the plotted experimental values also show that the rapid flow of water to the remnant of a shot hole achieved by means of air injection through another hole or by strong pumping from a shot hole (by blowing air into the bottom of an open shot hole, for example) increases the permeability after blasting, best results having been achieved when both air injection at the injection hole and strong pumping at a nearby shot hole was used. While blasting was found generally to decrease the permeability, permeability which had previously been reduced by the injection of water (alone or as a final flushing step after blasting) was increased by blasting.
  • the degree of dilation produced in the rock by the first three of the above-described detonations in flooded rock was estimated from calculations of poros ity based on sound velocity measurements.
  • the sound velocity around the injection hole after the three blasts was 3650 meters per second at a 12 foot radius from the hole, and 2530 meters per second through paths in the blasted rock running from the shot holes in to the injection hole (compared with 3970 meters per second in the same prism of rock before blasting).
  • the total porosity in the rock (111) was calculated from the following empirical equation for the sound velocity (or, in m/sec) as a function of porosity, for flooded ocean sediments having various degrees of lithification:
  • a process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment;
  • a process of claim 8 wherein a pluraity of holes of said assemblage are drilled from the earths surface and are left uncharged with explosive, said holes forming passageways within the fracture network from the earths surface to substantially the bottom of said segment of rock.
  • a process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment;
  • a process of claim 15 wherein liquid is driven through, and fines-laden liquid removed from, the fracture zone produced by the detonation of an explosive charge in a given cavity prior to the detonation of explosive charges in cavities adjacent thereto.
  • a process of claim 15 wherein an assemblage of substantially vertical holes is drilled into said rock from the earths surface; explosive charges are detonated in the sections of a plurality of said holes in said segment of rock in a manner such that the sections of said detonated holes located in the overburden that overlies said segment of rock survive the detonations and form a first set of passageways from the earths surface to said segment of rock, said first set of passageways leading substantially to the top of said segment of rock; a remaining plurality of holes of said assemblage are left uncharged with explosive and form a second set of passageways from the earths surface to said segment of rock, said second set of passageways leading substantially to the bottom of said segment of rock; and liquid is driven through said fracture zones laterally and upwardly from said second set of passageways to said first set of passageways and is brought to the surface through said first set of passageways.
  • a process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment;
  • a process of claim 24 wherein liquid is driven through, and fines-laden liquid removed from, the fracture zone produced by the detonation of an explosive charge in a given cavity prior to the detonation of explosive charges in cavities adjacent thereto.
  • Claims 18 and 19 line 1, the numeral "15" each occurrence, should read l7 Claim 20, line 1, the numeral "17” should read l9 Claim 9, line 2, cancel "to be”.
  • Claims 18 and 19 line 1, the occurrence, should read l7 Claim 20, line 1, the numeral "17” should read l9 Claim 9, line 2, cancel "to be”.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • General Engineering & Computer Science (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

Producing a fracture network in deep rock, e.g., in an ore body, by detonating explosive charges sequentially in separate cavities therein, the detonations producing a cluster of overlapping fracture zones and each detonation occurring after liquid has entered the fracture zones produced by previous adjacent detonations. High permeability is maintained in an explosively fractured segment of rock by flushing the fractured rock with liquid, i.e., by sweeping liquid through the fracture zones with high-pressure gas, between sequential detonations therein so as to entrain and remove fines therefrom. Ore bodies prepared by the blast/flush process with the blasting carried out in substantially vertical, optionally chambered, drilled shot holes can be leached in situ via a number of holes previously used as injection holes in the flushing procedure and a number of holes which are preserved upper portions of the shot holes used in the detonation process. In the leaching of ore, fines are removed from fractures therein by intermittent or continuous flushing of the ore with lixiviant and high-pressure gas, e.g., air, using, in the case of the in situ leaching of an explosively fractured ore body, a lateral and upward flow of lixiviant from zones that have been less severely, to others that have been most severely, worked by multiple detonations in the ore body.

Description

waited tates Patet Qoursen Sept. 2, 197 S [5 EXPLOSIVE FRACTURING OF DEEP ROCK [57] ABSTRACT lnventori David Linn Course", Mercersburg, Producing a fracture network in deep rock, e.g., in an ore body, by detonating explosive charges sequentially [73] Assigneez L Du Pom de Nemours and in separate cavities therein, the detonations producing Company Wilmington, Dd a cluster of overlappmgfracture Zones and each detonat1on occurring after l1qu1d has entered the fracture Filedi y 26, 1973 zones produced by previous adjacent detonations. [21] AppL NO; 382,845 High permeability is maintainedin an explosively fractured segment of rock by flushing the fractured rock with liquid, i.e., by sweeping liquid through the fracture zones with high-pressure gas, between sequential 166/63 detonations therein so as to entrain and remove fines [51] int. Cl. F42d 3/04 th refron Ore bodies prepared by the blast/flush pr Field of Search 299/4, cess with the blasting carried out in substantially verti- 102/22, 23 cal, optionally chambered, drilled shot holes can be leached in situ via a number of holes previously used References Cited as injection holes in the flushing procedure and a UNITED STATES PATENTS number of holes which are preserved upper portions 2,630,182 3/1953 Klotz JR u H 166/63 of the shot holes used in the detonation process. In the 2,530,307 3/1953 Martin 299/4 X leaching of ore, fines are removed from fractures 2,952,449 9/1960 Bays 299/4 therein by intermittent or continuous flushing of the 3,434,757 3/1969 Prats 299/13 ore with lixiviant and high-pressure gas, e.g., air, us- 3,465,2318 9/1969 Dixon 299/13 ing, in the case of the in situ leaching of an explosively 3466094 9/1969 Hawonh r 299/13 fractured ore body, a lateral and upward flow of lixivi- 365O564 3/1972 Williamson 299/13 X ant from zones that have been less severely, to others 3,710,718 1/1973 Grant 102/23 that have been most Severely Worked by multiple 3,777,815 12/1973 Boardman et a1. 299/13 X Primary Examiner-Verlin R. Pendegrass onations in the ore body.
25 Claims, 4 Drawing Figures PATENTEB 35? 21975 SHEET 1 BF 2 PATENTEDSEP 2181s SHEET 2 OF 2 SH 4 SHOT HOLE PATTERN Q T T O 0 0 ll SUCCESSIVE OPERATIONS EXPLOSIVE FRACTURING OF DEEP ROCK BACKGROUND OF THE INVENTION The present inventionrelates to the production of a network of fractures in a deep underground segment of rock by means of explosives, e.g., to prepare deep ore bodies for in situ leaching.
Processes for fracturing deep rock are becoming increasingly important as it becomes necessary to tap deep mineralized rock masses, e.g., ore bodies or oil or gas reservoirs located from about 100 feet to about a few thousand feet beneath the earths surface, in order to supplement or replace dwindling energy sources and minerals supplies. Numerous deposits of ore, for example ore containing copper, nickel, or silver, lie too deep to mine by openpit methods or are too low in grade to mine by underground methods. Open-pit methods incur both in costs and the environmental impact associated with moving large quantities of earth and rock. Underground methods incur unusually high costs per unit volume of ore mined, as well as difficult safety problems. In contrast, the leaching of ore in place circumvents these difficulties and therefore can be preferred technique for winning values from some ores that are unsuitable, or marginally suitable, for working by traditional mining methods.
Usually however, ore that is favorably situated for leaching in place has such a large fragment size and such low permeability to leach solutions that the leaching rate would be too low to support a commercial leaching operation. In such cases, it becomes necessary to prepare the ore for leaching, by fragmenting it in a manner such as to provide the necessary permeability and leachability. The use of explosives to fracture underground segments of mineralized rock to create areas of high permeability has often been suggested. In an oilor gas-bearing formation the fracturing is required to increase the overall drainage area exposed to the bore of a well penetrating the formation, and thus increase the rate at which hydrocarbon fluids drain toward the well. In an ore body the fracturing is required to increase the surface area of ore accessible to an injected lixiviant, and thus increase the leachability.
The use of nuclear explosives has been proposed for fracturing large-volume, deep ore bodies for subsequent in situ leaching. Also, the use of multiple chemical explosive charges in deep reservoir rock has been described in a method for stimulating hydrocarbonbearing rock, e.g., in US. Pat. No. 3,674,089. However, if a deep ore body, i.e., one lying at depths of about from 100 to 3000 feet from the surface, is to be effectively leached in place, and the ore prepared for leaching by blasting, i.e., blasting in the absence of a free face for the ore to swell toward, it becomes necessary to employ special blasting and associated techniques which will provide and maintain the type of fracture network required for efiicient leaching.
The leachability of a fractured ore body depends on the size of the ore fragments, and on the permeability of the intact ore as well as of the fracture system separating the fragments. The permeability of the fracture system separating the fragments, which is variable and generally much higher than the permeability of a single fragment, is determined by a network of wider, open fractures (determining the permeability of the ore body as a whole), and a network of narrower, open fractures (determining the irrigability of individual particles to be leached). Therefore, in explosively fracturing a segment of an ore body to prepare it properly for in situ leaching, the objective is not simply an indiscriminate reduction in the fragment size of the ore body. Smallersize, well-irrigated fragments have a higher leaching rate than larger-size fragments, but fragment-size reduction by means of blasting processes heretofore known to the art, when applied to deep ore, tends to leave large unbroken fragments of rock, or to create a network of fractures that are largely closed or plugged with fines. An explosive fracturing process is needed which reduces the larger fragmments to a size that will leach at an economically acceptable rate, and that will result in a network of open fractures throughout the blasted ore that will permit it to be well-irrigated with leach liquid.
SUMMARY OF THE INVENTION This invention provides a process for producing a fracture network in a deep subsurface segment of rock, e.g., in an ore body, comprising (a) forming an assemblage of cavities, e.g., drill holes or tunnels, in the segment of rock; (b) positioning explosive charges in a plurality of the cavities in the sections thereof located in the segment of rock to be fractured, e.g., in sections of drill holes which have been previously chambered, such as by an explosive springing procedure; (0) providing for the presence of liquid in the segment of rock, e.g., by virtue of the location of the segment of rock below the water table so that water naturally is present in, or flows into, fractures therein, or by introducing liquid into one or more cavities therein; and (d) detonating the charges sequentially in a manner such as to progressively produce a cluster of overlapping fracture zones, the detonation of each charge in the detonation sequence producing a fracture zone which is subject to the cumulative effect of a succession of detonations of explosive charges in a group of adjacent cavities, and the detonation of the charge in each cavity being delayed until liquid is present in fracture zones produced by the previous detonation of charges in cavities adjacent thereto, as determinable by measuring the hydraulic potential, e.g., the liquid level, in the cavity, or in a cavity adjacent thereto.
When the cavities formed are substantially vertical drill holes, some of the holes in the assemblage preferably are left uncharged with explosive, and these holes employed as a set of passageways within the fracture network from the earths surface, generally to substantially the bottom of the blasted rock, e.g., for the introduction of liquid and/or gas to (or removal thereof from) the fracture network. The uncharged holes preferably are drilled and provided with support casing prior to the detonation of charges in adjacent holes. The sections of substantially vertical shot holes located in the overburden that overlies the rock segment to be fractured preferably survive the blasting process and serve as an additional set of passageways, leading from substantially the top of the blasted rock to the earths surface, also for liquid and/or gas passage.
In a preferred explosive fracturing process, liquid is driven through the fracture zones produced by the sequential detonation of explosive charges in a plurality of cavities in a segment or rock, in a manner such as to entrain the fines found in the fracture zones, and the fines-laden liquid removed from the rock. This flushing of the blasted rock is achieved by sweeping or driving liquid at high velocity through the fracture zones by injecting gas into said zones at high pressure, the liquid moving laterally and upwardly through the blasted rock, passing into the fractures, for example, from the passageways formed by uncharged substantially vertical drill holes and out of the fractures into passageways formed by preserved sections of substantially vertical detonated holes located in the overburden. Best results are achieved when substantially each detonation is followed by a flushing step applied to the fracture zone thereby produced, before the next detonation in an adjacent cavity occurs, and this is preferred. In the leaching of amass of ore, e.g., in the in situ leaching of an explosively fractured ore body or in dump leaching, fines also preferably are flushed out of fractures therein by sweeping the lixiviant therethrough at high velocity by high-pressure gas.
The term deep as used herein to describe a subsurface segment of rock denotes a depth at which the det- 'onation causes no significant change in the overlying topography, i.e., the surface does not swell. As a rule, deep rock as described herein lies at a depth of at least 100, and usually not more than 3000, feet. Fracture zones and fractured rock herein denote zones and rock in which new fractures have been formed, or existing fractures opened up, by the detonations. Fracturing denotes herein a treatment which reduces the size of, and/or misaligns, rock fragments.
BRIEF DESCRIPTION OF THE DRAWING The explosive fracturing process of the invention will be described with reference to the attached drawing in which FIG. 1 is a schematic representation in plan view of a subsurface segment of rock which has been fragmented by the blast/flush process of the invention, and the liquid circulation pattern between holes therein;
FIG. 2 is a schematic representation in elevation showing the surface-to-surface liquid circulation pattern through the segment of rock shown in FIG. 1;
FIG. 3 is a schematic representation of a shot hole pattern described in the example; and
FIG. 4 is a plot showing the effect of repeated blast/- flush operations on the permeability of a fracture zone produced with the shot hole pattern shown in FIG. 3.
DETAILED DESCRIPTION OF THE INVENTION In the present process, explosive charges are detonated sequentially in separate cavities in a segment of mineralized rock to be fractured, each detonation in the sequence producing a zone of fracture in the rock and being delayed until liquid is present in the fractured rock around the cavity containing the charge to be detonated, especially in fracture zones produced by the previous detonation of charges in cavities adjacent thereto. Thus, the detonations occur while fractures in the surrounding rock are filled with liquid, or the rock is in a flooded, or liquid-soaked, condition. The cavities e.g., drill holes or tunnels, containing the explosive charges are spaced sufficiently close together, and the charges are sufficiently large, that the fracture zones produced by the detonations therein overlap one another. Thus, each fracture zone is within the region of influence of other detonations and is subject to the cumulative effect of a succession of detonations of explosive charges in a group of adjacent cavities. This cumulative effect permits the fragment size-reduction and disorientation needed to enhance leachability to be obtained readily from the available explosive energy. The degree of overlapping of the fracture zones, which are generally cylindrical in shape, is at least that required to locate all of the rock, in the segment of rock to be fractured, within the fracture zone produced by the detonation of at least one of the charges.
The cavities in the assemblage in which explosive charges are to be detonated (i.e., blast cavities) can be substantially vertical holes (shot or blast holes) drilled into the segment of rock from the surface or from a cavity in the rock, or substantially horizontal cavities such as tunnels, driven in the rock, e.g., from a hillside or shaft. Whether the cavity volume is provided by tunnel driving techniques such as are employed in coyote blasts, for example, or drilling techniques, possibly associated with chambering procedures, will be largely a question of economics, although technical practicability depending on such factors as topography, compressive strength of the rock, etc., will influence the selection of the method. Substantially vertical drill holes are preferred in many cases since the preserved sections of the shot holes can be used subsequently as passageways to or from the fractured rock, reducing the number of holes needed to be drilled solely to provide passageways for liquid injection or ejection.
Although the blast cavities need not form a regular pattern, and regularity of pattern actually may not be desirable or practical, a somewhat regular pattern is indicated in a formation of reasonably uniform contour, structure, and physical strength to assure a high degree of uniformity in the fracture network produced. In some cases, as core tests reveal unpredictable changes in the rock occurring during the sequential blasting process, it may be desirable to deviate from a regular pattern, e.g., to use one or more additional blast cavities where needed to provide the required overlapping of fracture zones. Nevertheless, substantial regularity of pattern generally will be provided in the arrangement of most of the blast cavities. It will be understood, of course, that in the case of substantially vertical drill holes the actual pattern of the holes within the segment of rock to be fractured may approach, rather than match, the hole pattern at the surface, inasmuch as the available drilling equipment may not be counted on to produce parallel holes at depths of the order considered herein.
Regardless of the blast cavity pattern employed, the distance between explosive charges (and, also therefore, between cavities) of a given composition and size is such that a cluster of overlapping fracture zones is produced by the detonation of adjacent charges. Although it may not be possible to delineate the fracture zones with precision, the extent or radius of the fracture zone. that can be expected to result from the detonation of an explosive charge of a given composition, density, shape, and size under a given amount of confinement in a given geological mass can be approximated by making some experimental shots and studying the fracture zones surrounding the blast cavities by using one or more geophysical methods. Such methods include l coring, (2) measurements in satellite holes of compressional and shear wave propagation, of permeability and of electrical conductivity, and (3) acoustic holography. Based on these studies, the cavities are spaced close enough together to provide the required overlapping of fracture zones.
Adjacent blast cavities or explosive charges, as described herein, are blast cavities or explosive charges which, although spaced from one another, are immediate or nearest neighbors to one another, as contrasted to blast cavities or explosive charges which are more distant neighbors or separated from one another by one or more other blast cavities or explosive charges.
Although I do not intend that my invention be limited by theoretical considerations, the delaying of each detonation until liquid is present in the fracture volume surrounding the cavities is believed to have two beneficial effects. First, the liquid can lubricate the fractures so that opposing faces can move suddenly in shear more easily, thereby enhancing fragmentation of the surrounding rock, which is no longer supported by the relatively high resistance of a dry fracture to transient shear. Secondly, liquid-filled fracture volume cannot be rammed shut by the suddenly applied pressure of an explosion. This incompressible behavior, together with the low resistance of the liquid-filled fractures to sudden small displacements in shear, is believed to cause disorientation of individual rock fragments and dilation and swelling of the bed of fragments as a whole. Each detonation creates a misalignment or disarrangement of fragments with an accompanying increase in void volume. Therefore, when the fracture zones produced by the successive detonations in adjacent cavities partially overlap, the fracture zone around each cavity thereby being subject to additional fracturing and/or disorientation produced by the detonations in the adjacent cavities, and previously produced fracture zones are flooded, each fracture zone will be swelled in incre ments, with each detonation jacking it to larger volume, and higher permeability, against the pressure of the surrounding rock. The present process makes use of the lubricating effect and incompressible behavior of the liquid in the fractures, and does not require the use of high liquid pressures, e.g., of the magnitude needed to lift the overburden and enlarge the fractures before blasting. A liquid pressure in the fractures at the time of blasting equal to the head of liquid above the blast zone is sufficient. Also, any readily available, relatively cheap liquid, e.g., water or water mixtures, can be used to flood the rock. lf leaching of ore is performed in the course of the detonation sequence, a lixiviant can be used as the flooding liquid. For reasons of economy as well as because of the safety risks associated with the use of explosives which are sensitive enough to deto nate in extremely small diameters, the use of explosive liquids in the fracture zones is not contemplated. Any fluid explosive which may be used in the present process will be gelled to a viscosity that will hinder any appreciable loss thereof from the blast cavities to the surrounding fracture zones, and in any case will not be sufficiently sensitive to be detonated in said zones. Thus, while small amounts of the explosive charges may escape into the fracture zones, such material will behave as a non-explosive liquid therein. Accordingly, the flooding liquid is non-explosive.
A preferred blast cavity pattern for use in the present process is one in which substantially all of the internal cavities, i.e., cavities not located at the edge of the pattern, are surrounded by at least four adjacent blast cavities, e.g., a pattern in which the blast cavities are at the corners of adjacent polygons, which are either quadrangles or triangles and which are as close to equilatera] as permitted by wander of the cavities, as shown in FIG. 1.
Although all of the blast holes in a group of adjacent substantially vertical drill holes can be drilled prior to the sequential detonation of the charges, this procedure is not preferred inasmuch as it could be necessary to apply a support casing to the as-yet undetonated holes in the sections thereof located in the segment of rock to be fractured to prevent them from collapsing as a result of detonations in adjacent holes. Casing of the shot holes in these sections usually would be considered economically unsound because the casing would occupy volume that could otherwise be loaded with explosive and because casing in these sections of the holes is not needed in subsequent leaching operations. Therefore, it is preferred that in a group of adjacent drilled shot holes the detonation of each charge takes place before adjacent shot holes are drilled. In practice, one might drill and, if desired, chamber (as described later), one shot hole of a group of adjacent holes, load the hole or chamber with explosive, allow water to enter the formation surrounding the hole or chamber, and detonate the charge, and then repeat the sequence of steps with adjacent holes. In each successive sequence of steps, the entrance of water into the formation can occur prior to, or during, any of the other steps, however. The avoidance of the presence of drilled shot holes during detonations refers to holes in a group of adjacent holes, e.g., a central hole and four to six surrounding holes. However, shot holes farther removed from the detonations can be pre-drilled.
The total amount of drilling needed for verticalcavity blasting can be reduced by drilling one or more branch or off-set holes by side-tracking from one or more points in the preserved upper portion of a trunk hole which extends to the surface. Each off-set hole is drilled after the charges in the trunk hole and other offset holes thereof have been detonated. Such holes will be inclined at small angles to one another.
Most of the ore bodies and other mineralized formations to which the present process is expected to be primarily applicable will be located below the water table, and in such a case, unless the section to be blasted rises locally above the water table, or the rock surrounding this section is so impermeable that flooding of the fracture zone does not occur by natural flow, the section will be naturally flooded, or water-soaked, before the sequential blasting begins, and after a certain period of time has elapsed after each detonation to allow the water to flow naturally into the newly formed fractures. If natural flooding is incomplete or absent, water or some other liquid can be pumped into the cavity to be shot after the explosive charge has been emplaced therein, and also into any available nearby uncharged cavities, at a sufficiently high flow rate to cause the rock to be blasted to be in a flooded condition at the time of detonation.
As stated previously, liquid is present in the rock around each cavity prior to the detonation of the charge therein. This means that liquid is present in any pre-existent fractures in the zone which will become a fracture zone as a result of the detonation of the charge in that cavity, and in fractures produced by previous detonations in cavities adjacent thereto. This condition permits the above-described incremental swelling of overlapping fracture zones to take place. In the case of substantially vertical drill holes, the liquid level in the rock around the hole should be at least as high as the top of the charge in the hole, thereby assuring the presence of liquid throughout the height of the formation where fracturing will occur. With horizontal cavities, the liquid level in the rock around the cavity should be at least as high as the radius of fracture to be produced by the detonation of the charge therein. When the segment of rock to be fractured is located below the water table, the position of the water table above it will conform to the water levels in undisturbed holes, and may be inferred at other locations by interpolation between the elevations of the water levels in undisturbed holes. As a practical matter, the water table will almost always be sufficiently horizontal that the first charge can be detonated when the elevation of the liquid level in any nearby hole is at least as high as the elevation to be reached by the top of the charge (or radius of fracture in the horizontal cavity case). If the liquid level is measured in the cavity in which the charge is to be detonated, the level before loading of the explosive into the cavity should be the level measured. After the detonation, the liquid level in cavities within the resulting fracture zone drops in proportion to the new fracture volume produced, the expulsion of liquid from the immediate vicinity of the charge by the gaseous products of detonation, and the drainage of liquid into the cavity created by the detonation. The detonation of the next charge in the sequence in a cavity adjacent to the first is delayed until the liquid in the formation around the next cavity (including the new fracture volume produced by the previous detonation in an adjacent cavity) returns to its required level. It is understood, however, that explosive charges in blast cavities elsewhere in a section of the formation that is not strongly influenced by a previous detonation (i.e., where the liquid level has not dropped below the required elevation as a result of the previous detonation) can be detonated at any time after the previous detonation. The delay to allow flooding applies to detonations in cavities which are adjacent to previously detonated cavities, where the previously formed fracture zones will be subject to the effect of the next detonation.
As was stated previously, some of the holes in an assemblage of substantially vertical holes preferably are left uncharged with explosive, these holes providing passageways to the fractured rock to allow the introduction of gases and/or liquids thereto, e.g., in a subse' quent leaching operation. These holes, which can thus be looked upon as injection holes (although they may serve as ejection or recovery holes depending on the required flow pattern), are also useful in preparing the ore body for leaching, as will be described more fully hereinafter, and it is preferred, on the basis of ease of drilling, that they be drilied prior to the sequential det onation process in holes surrounding them. Pre-drilled injection holes are provided with a support casing, e.g., unperforated pipe grouted to the upper part of the hole wall, at least in the section thereof located in the segment of rock to be fractured, and ungrouted perforated pipe or a wellscreen in the bottom section of the hole, in order to prevent hole collapse as a result of the detonations. Inasmuch as fulllength casing will be required for subsequent leaching operations, however, the full length of the injection holes usually will be cased prior to blasting. Damage to the injection piping is minimized in the present blasting process owing to the sequential, long-delay character of the multiple detonations.
The location and pattern of the injection holes are selected on the basis of their intended function during the fracturing and leaching processes, which will be described in detail hereinafter. The overall purpose of these holes usually is to provide a means for introducing gases and/or liquids into the fracture network produced, or being produced, and therefore the injection holes should be distributed throughout the segment of rock among the blast cavities in a manner such that they lie within the fracture zones produced by the detonations. After the detonation of the charge in a substantially vertical shot hole, the resulting fracture zone permits communication between a neighboring injection hole and the portion of the shot hole remaining in the overburden. The shot hole remnants thereby act as passageways to complete the liquid circuit through the fractured rock.
If injection holes are present in the formation during the sequential detonation process, an injection hole lying within the fracture zone produced by a previous detonation in a cavity adjacent to a cavity to be shot can be employed to determine whether the liquid level in the rock surrounding the cavity to be shot has recovered sufficiently to flood the section to be blasted. Whenever an hydraulic potential (e.g., a liquid level) measurement is required after a blast cavity has been loaded with explosive, a nearby injection hole can be used. When the segment of rock to be blasted is at least partly above the water table, liquid is introduced into the rock in the cavity to be shot, in previously detonated cavities adjacent thereto, and/or in nearby injection holes. Flooding via multiple cavities is preferred Liquid is run into a blast cavity after the explosive charge has been emplaced therein (if the charge is stable in the presence of water), and liquid level measurements, if required, are made in nearby injection holes. It should be understood that, in practice, hydraulic potential measurements, e.g., pressure measurements made with a piezometer, or liquid level measurements, will not be required after each detonation, inasmuch as the experience gained in determining the necessary delay times to permit recovery of hydraulic potential between a few of the early detonations in the sequence will usually allow the practitioner to select with confidence suitable delay times to be used between subsequent detonations.
Although the exact delay required depends on the size of each blast, the void volume to be filled, the elevation of the segment to be blasted relative to the water table, and the hydraulic transmissibility of the surrounding rock, delays on the order of hours or days generally will be needed. As a practical matter, the time required for a shot hole to be drilled, or a tunnel to be driven, and loaded with explosive usually will be more than sufficient for the hydraulic potential around the cavity and the previously detonated adjacent cavities to recover to the minimum required level either by natural influx of water from the surrounding rock or by introduction through cavities made in the formation. In general, delay times between detonations of at least about 1 hour, and typically in the range of about from 4 to 24 hours, are sufficient for flooding to take place, although much longer delays, e.g., in the range of about from 4 to 30 days, may be employed in order to prepare the next blast cavity for blasting. It will be understood that these delays refer to the time between detonations of adjacent charges, and that one or more charges whose zones of fracture are non-adjacent (i.e., whose regions of influence are mutually exclusive) can be detonated at much shorter delay times or even simultaneously.
l have found that when sequential blasting is carried out in less competent, broken, or clayey rock, the permeability of the rock may be decreased, although the fracture volume is increased, by the blasting. Lost permeability can be restored by flushing of the fractured rock, i.e., by sweeping or driving liquid through the fractures at high velocity and removing the fines-laden liquid from the rock, preferably after each detonation. The flushing procedure appears to remove from the fractures the clogging fines that prevent free irrigation around the rock fragments. Such fines are present in the form of existing clays and rock crushed or abraded during blasting.
The flushing can be accomplished by the pressure injection of liquid and gas into the fractured rock through one or more injection holes, and removal of the finesladen liquid from the fractured rock by bringing it to the surface through one or more detonated shot holes, in the preserved sections of the latter which pass through the overburden to the surface. Liquid and gas, e.g., water or other aqueous liquid and air or oxygen, can both be injected; or gas alone can be injected so as to sweep ahead the liquid already present in the fractures. Alternatively, a liquefied gas, such as air, nitrogen, oxygen, can be introduced into the injection holes and allowed to vaporize therein and thereafter drive the liquid through the fractures. Inasmuch as there is a two-phase flow in a generally upward direction and laterally in the direction of the detonated shot holes, the circulation of the liquid is powered by gas lift such that the gas chases the liquid upward and outward through the broken formation, and fines are driven toward the zones of severest fracture, where their concentration is heaviest, from which zones they are ejected with the liquid. This direction of sweep is preferred inasmuch as the reverse direction drives the fines more deeply into the less severely worked zones of the formation away from their point of heaviest concentration and can cause an intensified clogging of the fractures. The surging high-velocity flow which develops with the upward two-phase flushing system removes fines that prevent free irrigation around the fragments. If necessary to achieve the required lateral circulation of liquid between injection hole and ejection hole throughout the length of the fracture zones being flushed, two or more vertically separated injection zones in a given injection hole can be employed, one substantially at the bottom of the fractured rock and one or more others above it.
The buoyancy of the pressurized gas alone can be sufficient to raise the fines-laden liquid to the surface of the ground when the water table is relatively close to the surface. When the water table is so deep that the buoyancy is insufficient, the liquid can be pumped up the collar of the shot hole.
At the start of flushing, the gas injection pressure should be higher than the ambient hydrostatic pressure at the position in the injection hole where injection occurs, and preferably higher than the lithostatic pressure at this position. The minimum gas pressure required for flushing is highest at the start of the operation and falls as gas injection proceeds.
Although there can be much variation in the number of fracture zones being flushed out at any given time,
and the nature and number of other operations which can be performed during flushing, it is preferred that a detonation in any given cavity be followed by detonations in no more than two or three adjacent cavities, and most preferably by a detonation in no adjacent cavity, before the fracture zone produced by the detonation in the given cavity has been flushed out as described. In some formations, if a given fracture zone is subjected to a number of subsequent detonations without the intervention of flushing, restoration of permeability by a later flushing becomes difficult because the fractures may have become plugged up too tightly with fines. Therefore, a cyclic blast/flush/blast/flush, etc. process is preferred. One or more fracture zones can be flushed at the same time, and flushing of the same zone can be repeated, if desired. An already flushed zone can be left untreated during the flushing of adjacent zones by plugging the ejection hole in that zone. Flushing of one or more zones can be carried out while adjacent blast cavities are being drilled and loaded.
In the present process, the detonation of the charges in sequence permits the preservatioon of the sections of substantially vertical shot holes that pass through the overburden (the strata overlying the rock segment being worked), and these sections of the shot holes can serve as ejection holes in the flushing process, as described above. The' reduced fragment size and unclogged fracture network achieved after all of the charges have been detonated, and the detonations followed by a flushing procedure, produce, in the case of an ore body, an ore which is well-prepared for in situ leaching.
The present invention also provides a leaching process wherein fines are flushed out of a mass of ore by driving lixiviant through the mass by means of highpressure gas, e.g., in a specific circulation pattern. According to one embodiment of the present leaching process, an ore body which has been prepared for leaching by detonating explosive charges in separate cavities therein, e.g., according to a process of this invention, is leached in situ by introducing lixiviant for the ore into the prepared ore body through a plurality of injection holes therein and intermittently or continuously driving the lixiviant through the ore body to a plurality of recovery holes by means of high-pressure oxidizing gas, the lixiviant moving laterally and upwardly from zones that have been less severely worked, to others that have been most severely worked, by the detonations, whereby fines are removed from the ore body. When the ore body has been prepared for leaching by means of the above-described blast/flush process the lixiviant for the ore can be injected into the ore body through injection holes which have previously been used in the flushing steps, and fines-laden pregnant leach solution recovered from the ore body through the preserved upper portions of shot holes, piping having been grouted into all holes used to circulate lixiviants and pumps provided as necessary to inject lixiviants in one set of holes and remove pregnant liquor from another set of holes. The bottom ends of the pipes and any other positions along the pipes where lixiviants are to be injected or collected are provided with perforations or wellscreens.
The lixiviant (e.g., sulfuric acid/water or sulfuric acid/nitric acid/water for ores whose acid consumption is within tolerable levels, or Ni-LOH/water for ores having a high acid consumption), which is a liquid, and a gas, usually an oxidizing gas, preferably oxygen, air, N or mixtures thereof, are injected into the base of the prepared ore body at high pressure. As in the case of flushing between blasts, this type of injection gives a circulation powered by gas lift such that the gas chases the liquid through the broken rock. Even with constant flow rates of gas and liquid at the injection holes, a surging, highvelocity flow develops in the rock which is believed to be beneficial in l removing fines around the ore fragments (such fines being created during the leaching process in forms as decrepitated ore slimes and precipitated iron salts), (2) increasing the leaching rate as a result of the cyclic squeezing of the ore fragments from the pressure fluctuations associated with the surging flow, and (3) working the ore gently so as to collapse wide openings among the fragments that may develop during the leaching process and can cause channelling of leaching solution. Sweeping the lixiviant laterally toward collection points in the more severely worked fracture regions of the ore body,
and from injection points in the less severely worked regions reduces the chances that a more intense clog ging of the ore body with fines will occur.
The circulation pattern employed in the leaching process as well as in the flushing steps of the fracturing process may be understood more clearly by reference to the accompanying drawing. In FIG. 1, the holes designated by the letter S are substantially vertical shot holes. Within the blasted segment of rock, these holes are destroyed by the detonations which have taken place therein in the fracturing process and are replaced by the adjacent, overlapping fracture zones shown in the upper half of the figure, and also denoted by the letter S, to indicate a previous shot hole. The shot holes rather than the fracture zones are shown in the lower half of the figure so that liquid circulation lines can be indicated clearly. It should be understood, however, that upon completion of the entire blast sequence all shot holes are surrounded by fracture zones (as depicted in the upper half of the figure) in the sections thereof located in the rock segment that was blasted. In the sections overlying the blasted segment, the shot holes remain substantially intact and in these sections all shot holes appear as they are shown in the lower half of the figure. The preserved upper sections of the shot holes are ejection holes in the flushing steps of the blasting process, and recovery holes in the leaching process. In the hole arrangement illustrated in FIG. 1, the shot holes are arranged in a trigonal pattern wherein lines between adjacent holes form substantially equilateral triangles.
The holes designated I are injection holes. These holes are uniformly distributed among the shot holes as shown. The arrows indicate the direction of flow of liquid from injection holes 1,, l I I 1;, and I to the preserved upper section of shot hole S and from injection holes I,,, I I I,,, and two other undepicted injection holes to the preserved upper section of shot hole S The preserved upper section of shot hole S is plugged off while shot holes S and S are being used for flushing or as recovery holes for pregnant leach solution. At the same time, liquid injected into these injection holes is being driven to other open shot holes.
In FIG. 2, piping in injection hole I and shot hole S is shown as it passess through overburden 1 to the fractured rock segment 2. Piping 6 in injection hole I leads from the earths surface 3 to substantially the bottom of rock segment 2. Piping 7 in shot hole S leads from the earth s surface 3 to the top of rock segment 2. Fracture zone 4 has been produced by the detonation of an explosive charge in shot hole S, which before the detonation led to substantially the bottom of rock segment 2. Piping 7 terminates in well screen 5, and piping 6 is provided with perforations vertically spaced along the length thereof located in rock segment 2. In the flushing steps of the fracturing process, and in the leaching process, liquid is injected into fractured rock segment 2 through the perforations in piping 6, then is driven by pressurized gas through the fractured rock as indicated by the arrows, and leaves the top of the rock segment through piping 7. Lateral as well as upward flow occurs from the less severely worked zone around hole I to the most severely worked zone, i.e., fracture zone 4.
Regulation of the rate at which gas and liquid lixiviant are injected and collected at the various injection and collection holes allows a high degree of control of the in situ leaching process. By the operation of control valves, the injection and collection pressures can be regulated to obtain a relatively uniform flow through the ore body in spite of variations in permeability from place to place. Shifting the injection or collection from one set of holes to another will change the direction of flow through the ore and can be used to frustrate channelling. The regulation of pressures and flow rates at the various holes can be used to maintain a net flow of ground water toward the operation under conditions that might otherwise result in the escape of leach solution. Leakage of the leach solution is also reduced in the present process as a result of the carriage of some of the fines away from the area of gas agitation where they settle out and plug the leak. In leaching, the gasliquid pressure injection can be intermittent or continuous, depending upon the degree to which the ore tends to plug up, and the frequency with which flow patterns are changed to obtain uniform and complete leaching throughout the ore.
When lixiviant is introduced into an injection hole simultaneously with gas, its injection pressure should be equal to that of the gas, i.e., higher than the ambient hydrostatic pressure at the injection point, and preferably higher than the lithostatic pressure at this point. In some cases, especially at greater depths, the injection of lixiviant and oxidizing gas at sufficient pressure to exceed the lithostatic pressure may be necessary in order to get sufficient flow rate through the ore. If, in some or all of the injection holes, there are periods of time when lixiviant alone is introduced into the ore, this introduction preferably is done at a pressure at least as high as the lithostatic pressure at the injection position. That is, the pumping pressure preferably is at least as high as the lithostatic pressure minus the heads of fluid in the piping leading from the pump to the injection po sition.
According to the present invention, permeability can be increased also in ore masses such as mine waste dumps by driving lixiviant through fractures therein by means of gas at sufficiently high pressure that the lixiviant is swept through at a rate sufficiently high to entrain fines present in the fractures, and removing the finesladen lixiviant from the ore mass.
In a preferred embodiment of the present process, the sections of substantially vertical shot holes which are located in the segment of rock to be fractured are first chambered to larger diameter, and the explosive charges positioned in the chambered portions. In this procedure, drilling costs are reduced by drilling widely spaced-apart shot holes of smaller diameter than is required to accommodate the size of explosive charges to be employed, and enlarging or springing the lower parts of the shot holes to produce chambers having the volume required to hold the explosive charge. The sections of the holes in the rock segment are chambered either by drilling them out, e.g., with an expansion bit, or by detonating explosive charges therein. The chambering method is not critical, the preferred method generally being the one that results in the lowest overall cost per unit of chamber volume for the particular rock segment in question. In the present process, explosive charges used for springing may be 20 feet or more in length. If rock fragments tend to fall from the walls of an explosively sprung hole and thus to occupy some of the volume required for the explosive charge subsequently to be used in producing the fracture zone, the
, hole to be sprung can be drilled deeper so that the bottom of the hole is located below the bottom of the formation. In this manner, any loss in volume that is to be available for explosive loading is minimized since a portion of the chamber volume below the segment of rock to be fractured can hole the fallen rock fragments.
The advantage of chambering the shot holes before loading them with the charges which will be detonated to produce the fracture network becomes evident when it is considered that an explosively sprung hole typically will hold about ten times as much explosive as an unsprung hole. Thus, for example, a pattern of 30-inchdiameter charges on l-foot spacings (center-tocenter) typically can be achieved by drilling 9-inchdiameter holes on l00-foot spacings.
Although the blast/flush process has utility in deep underground blasting with explosives of all types, the use of chemical explosive charges is much preferred for several reasons. The many technical as well as civil (le gal, political, public relations) problems associated with the undertaking of nuclear blasting are selfevidentv Vibration effects and radioactivity are the two major roots of these problems. A nuclear blast which is large enough to be economically feasible must be set off at sufficient depth, e.g., preferably appreciably deeper than 1000 feet, in order to be safely contained and not release radioactivity to the atmosphere. Many potentially workable ore bodies will not be located as deep as the safe containment depth. Furthermore, the extreme magnitude and concentration of the energy produced in a nuclear blast imply that it will be difficult, if not impossible, to achieve (a) a high degree of uniformity in explosion-energy distribution and ore breakage, (b) close hydraulic control of the flow of lixiviants without an appreciable amount of additional drilling to increase the number of injection and extraction points, and (c) a close match of the broken volume with the outline of the ore body, particularly for small or irregular ore bodies, such a match resulting in economies in the use of the available explosive energy and in the consumption of lixiviants.
While single explosive charges generally will be deto nated in sequence to produce the fracture zones, the charges also can be multi-component charges positioned in separate cavities and detonated substantially simultaneously as a group to produce each fracture zone, each detonation in the sequence of detonations in such a case being a group of detonations.
The following example illustrates specific embodiments of the process of the invention.
The formation to be fractured was a bedded series of shales and silt stones, dipping about 45, located at a depth of to feet below the surface, and therefore subjected to a lithostatic pressure of about 70 to 90 p.s.i. The water table was at a depth of about 15 feet below the surface. A 3-inch-diameter hole was drilled into the formation to a depth of feet. This hole was used as a coresampling and permeability-testing hole, and also as an injection hole for purposes of flushing surrounding shot holes. A core test revealed a competent silty shale at the 70-90 foot depth. A well screen was installed in the hole at the 7090 foot level, and piping to the well screen was grouted to the hole. Cement filled the hole below the well screen.
The pattern of shot holes used is shown in FIG. 3. Three shot holes (SH 1, SH 2, and SH 3) were located 16.25 feet from the injection hole I, their centers lying on radii from the center of hole I and the lines joining them forming an equilateral triangle. The distance between these shot holes was 28 feet. Three shot holes (SH 4, SH 5, and SH 6) were located 32.5feet from hole 1, their centers also lying on120 radii from the center of hole 1, and the lines joining them (also forming an equilateral triangle) being bisected by the centers of holes SH 1, SH 2, and SH 3. The distance between holes SH 4, SH 5, and SH 6 was 56 feet. It is seen that in this arrangement the lines joining adjacent (i.e., nearest neighbor) shot holes formed equilateral triangles. SH 1, SH 2, and SH 3 each had four shot holes adjacent thereto (SH 2, SH 3, SH 4, and SH 5 for SH 1; SH 1, SH 3, SH 5, and SH 6 for SH 2; and SH 1, SH 2, SH 4, and SH 6 for SH 3), and SH 4, SH 5, and SH 6 each had two shot holes adjacent thereto (SH 1 and SH 3 for SH 4; SH 1 and SH 2 for SH 5; and SH 2 and SH 3 for SH 6).
Shot hole SH 1 was drilled first. The hole was 5 inches in diameter and 91 feet deep and was loaded with 255 pounds of an aluminized water gel explosive having the following composition: 18.9% ammonium nitrate, 10.5% sodium nitrate, 29.6% methylamine nitrate, 30% aluminum, and 11% water. The explosive column was 21.7 feet high, and was covered by a layer of water which naturally flowed into and filled the remainder of the hole and stemmed the explosive charge. The water level in the injection hole was above the level of the top of the explosive charge in the shot hole, indicating that the rock surrounding the shot hole was properly flooded. Before the explosive charge was initiated, the permeability and sound velocity of the rock surrounding the injection hole were measured. The permeability was determined by slug tests, in which the permeability is inferred from the rate at which the head of liquid subsides toward the ambient level in a hole after the rapid introduction of a slug of liquid therein (see Ferris, .I. G., et 21]., Theory of Aquifer Tests, US. Geological Survey, Water-Supply Paper l536-E, 1962). The sound velocity, measured at depths of 74.5 feet to 85 feet between the injection hole, shot hole SH 1, and a test hole collared 13 feet on the opposite side of the injection hole, was 3970 meters per second.
The explosive charge in shot hole SH 1 in the flooded formation was detonated, whereupon the water level in the injection hole dropped to below its pre-detonation level, as a result of the formation of a new fracture volume around shot hole SH 1, the chasing of water from the rock fractures by the gaseous detonation products, and the flow of water into the cavity created by the explosive charge. After partial recovery of the water level in the injection hole, the second shot hole (shot hole SH 2) was drilled to the same size as shot hole SH 1, and the rock surrounding shot hole SH 1 was then flushed with water by (a) blowing compressed air into the bottom of the open injection hole (b) injecting water through a packer in the injection hole, and (c) three long air injections, and then (d) 18 short air injections through a packer in the injection hole. The total flushing time was about 4 hours. Silt-laden water was ejected from shot hole SH 1 (but not shot hole SH 2) during the flushing, indicating the preservation of the top of shot hole SH 1, the circulation of the water from the bottom of the rock segment (bottom of the injection hole) laterally and upward through the fracture network to the top of the rock segment (bottom of shot hole SH 1 and the removal of fines from the fractures.
The permeability was measured in the injection hole (as described above) before and after the flushing operations.
Shot hole SH 2 and subsequently drilled shot hole SH 3 were loaded and the charges therein detonated as described for shot hole SH 1.
The water level in the injection hole returned to its pre-detonation level, above the level of the top of the explosive charge in shot hole SH 1 before detonation, in about 18 hours. Thereafter, the charge in shot hole SH 2 was detonated, whereupon the water level in the injection hole again dropped to below its predetonation level. The rock surrounding shot hole SH 2 was flushed with water, and siltladen water ejected from shot hole SH 2, by sealing off shot hole SH 1 and (a) injecting air through a packer in the injection hole, (b) blowing compressed air into the bottom of the open injection hole, and (c) injecting air through a packer while blowing compressed air into the bottom of shot hole SH 3. The total flushing time was about 1 1 hours. The permeability was again measured before and after the flushing operations.
After the water level in the injection hole had returned to its pre-detonation level, the charge in shot hole SH 3 was detonated, and the surrounding rock flushed by (a) air injection through a packer in the injection hole, followed by sealing off shot hole SH 1 and blowing air down shot hole SH 2 and shot hole SH 3 to drive water to each slot hole in turn until water was exhausted from the broken rock; and (b) two air injection flushings, each followed by water injection. The total flushing time was about 7 hours. The permeability was again measured before and after the flushing operations.
The remaining shot holes SH 4, SH 5, and SH 5, were drilled, loaded, and detonated in the same manner as holes SH 1, SH 2, and SH 3, with the detonations occurring after the return of the water level in the injection hole to its predonation level. Between the shooting of shot holes SH 4 and SH 5, the rock surrounding hole SH 4 was flushed by three air injections in the injection hole, each followed by water injection; between the shooting of shot holes SH 5 and SH 6, the rock surrounding hole SH 5 was flushed by injecting air into the injection hole, and blowing air down hole SH 6 (unshot), separately and simultaneously; and after hole SH 6 was shot, the rock surrounding it was flushed by alternately injecting air into the injection hole and blowing air down the surviving section of hole SH 6.
The permeabilities measured by slug tests in the injection hole before the blast/flush process began and after each blast and flush operation at each of the six holes are plotted in FIG. 4 as a function of the operation performed, the permeabilities being presented in millidarcys on a logarithmic scale as the ordinate. Nineteen points are shown, including those obtained after the four flushing procedures (a, b, c, and d) described above after the shooting of hole SH 1; three flushing procedures (a, b, and c) after the shooting of hole SH 2; and two flushing procedures (a and b) after the shooting of hole SH 3. Each point denotes the average permeability measured after a given operation.
The plot shows that the permeability of the rock was increased considerably (from 500 to over 2000 millidarcys) by the total six-cycle blast/flush process, and that variations in permeability occurring during the cyclical shooting and flushing tend to decrease as the rock is broken and swelled. The plotted experimental values also show that the rapid flow of water to the remnant of a shot hole achieved by means of air injection through another hole or by strong pumping from a shot hole (by blowing air into the bottom of an open shot hole, for example) increases the permeability after blasting, best results having been achieved when both air injection at the injection hole and strong pumping at a nearby shot hole was used. While blasting was found generally to decrease the permeability, permeability which had previously been reduced by the injection of water (alone or as a final flushing step after blasting) was increased by blasting.
The degree of dilation produced in the rock by the first three of the above-described detonations in flooded rock was estimated from calculations of poros ity based on sound velocity measurements. The sound velocity around the injection hole after the three blasts was 3650 meters per second at a 12 foot radius from the hole, and 2530 meters per second through paths in the blasted rock running from the shot holes in to the injection hole (compared with 3970 meters per second in the same prism of rock before blasting). The total porosity in the rock (111) was calculated from the following empirical equation for the sound velocity (or, in m/sec) as a function of porosity, for flooded ocean sediments having various degrees of lithification:
Total porosity before blasting: l 1.7%
Total porosity after blasting: (l2-ft. radiu) 16.0%
Total porosity after blasting: (center to shot holes) These porosities imply that the fracture volumes caused by the blasting were 4.3% (12-ft. radius) and 22.9% (center to shot holes).
I claim:
1. A process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment;
b. positioning chemical explosive charges in a plurality of said cavities in the sections thereof located in said rock segment;
c. allowing liquid to fill the fractures existing in the rock around the cavities in the sections thereof located in said rock segment as can be evidenced by a liquid level which is at least as high as the top of said rock segment; and
d. detonating said explosive charges sequentially, each detonation in the sequence producing a zone of fracture in said segment and a drop in the level of said liquid, as measurable in the cavity which contained the detonated charge or in a cavity adjacent thereto, said charges being sufficiently large and spaced sufficiently close together that the fracture zones produced in said segment by the detonations of charges in adjacent cavities overlap, the detonation of the charge in each cavity being delayed until after the level of the liquid, as measurable in the cavity containing the charge to be detonated or in a cavity lying within the zone of fracture produced by a previous detonation in a cavity adjacent thereto, has ceased to drop and is at least as high as the top of said rock segment.
2. A process of claim 1 wherein said liquid is water.
3. A process of claim 2 wherein said water is naturally occurring in said rock.
4. A process of claim 1 wherein, in groups of adjacent cavities in which explosive charges are to be detonated, the detonation of the charge in each cavity takes place before charges are positioned in cavities adjacent thereto.
5. A process of claim 1 where in the time elapsing between any two consecutive detonations in a group of adjacent cavities is at least one hour.
6. A process of claim 5 wherein said liquid is introduced into at least one of said cavities and enters said rock by permeating the cavity walls.
7. A process of claim 1 wherein the cavities in which explosive charges are to be detonated form a pattern in which each internal cavity of the pattern is surrounded by at'least four adjacent cavities.
8. A process of claim 1 wherein said cavities are substantially vertical drill holes.
9. A process of claim 8 wherein the sections of the holes which are located in said rock segment to be are chambered to larger diameter, and the explosive charges are positioned in the chambered sections.
10. A process of claim 9 wherein said chambered sections are produced by the previous detonation of springing explosive charges in the holes.
11. A process of claim 10 wherein the springing explosive charges employed to produce the chambered sections of said holes are at least about feet long and the bottoms thereof are located below the bottom of said segment of rock.
12. A process of claim 8 wherein a pluraity of holes of said assemblage are drilled from the earths surface and are left uncharged with explosive, said holes forming passageways within the fracture network from the earths surface to substantially the bottom of said segment of rock.
13. A process of claim 12 wherein said plurality of uncharged holes are drilled and their walls provided with support casing, at least in the portions thereof located in the said segment of rock, prior to the detonation of the explosive charges in holes adjacent thereto.
14. A process of claim 13 wherein liquid is injected into said segment of rock through said uncharged holes.
15. A process of claim 8 wherein, in groups of adjacent holes in which explosive charges are to be detonated, the detonation of the charge in each hole takes place before adjacent holes are drilled.
16. A process of claim 8 wherein said substantially vertical holes are drilled into the segment of rock from the surface, and branch holes are drilled into the segment of rock from said substantially vertical holes at small angles thereto starting at locations overlying said segment of rock.
17. A process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment;
b. positioning explosive charges in a plurality of said cavities in the section thereof located in said rock segment;
0. detonating said explosive charges sequentially to produce a plurality of fracture zones;
(1. driving liquid through said fracture zones by injecting gas therein at sufficiently high pressure that fines present in said fracture zones as a result of the crushing or abrading of existing clays or rocks are entrained by said liquid; and
e. removing fines-laden liquid from said rock whereby the permeability of said rock segment is restored.
18. A process of claim 15 wherein liquid is driven through, and fines-laden liquid removed from, the fracture zone produced by the detonation of an explosive charge in a given cavity prior to the detonation of explosive charges in cavities adjacent thereto.
19. A process of claim 15 wherein an assemblage of substantially vertical holes is drilled into said rock from the earths surface; explosive charges are detonated in the sections of a plurality of said holes in said segment of rock in a manner such that the sections of said detonated holes located in the overburden that overlies said segment of rock survive the detonations and form a first set of passageways from the earths surface to said segment of rock, said first set of passageways leading substantially to the top of said segment of rock; a remaining plurality of holes of said assemblage are left uncharged with explosive and form a second set of passageways from the earths surface to said segment of rock, said second set of passageways leading substantially to the bottom of said segment of rock; and liquid is driven through said fracture zones laterally and upwardly from said second set of passageways to said first set of passageways and is brought to the surface through said first set of passageways.
20. A process of claim 17 wherein said uncharged holes are drilled prior to the detonation of said charges, and have their walls provided with support casing at least in the sections thereof located in said segment of rock.
21. A process of claim 19 wherein liquid present in the fracture zones is driven therethrough by gas injected therein through said holes which form said second set of passageways.
22. A process 'of claim 21 wherein said liquid is watter, and said gas is selected from the group consisting of air, oxygen, and nitrogen.
23. A process of claim 19 wherein said segment of rock is an ore body, and, after the detonation of said explosive charges, a lixiviant for said ore is driven through the fracture zones in said ore body from said holes which form said second set of passageways to said holes which form said first set of passageways, and is brought to the surface through said first set of passage ways.
24. A process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment;
b. positioning chemical explosive charges in a plurality of said cavities in the sections thereof located in said rock segment;
c. allowing liquid to fill the fractures existing in the rock around the cavities in the sections thereof located in said rock segment as can be evidenced by a liquid level which is at least as high as the top of said rock segment;
d. detonating said explosive charges sequentially, each detonation in the sequence producing a zone of fracture in said segment and a drop in the level of said liquid, as measurable in the cavity which contained the detonated charge or in a cavity adjacent thereto, said charges being sufficiently large driving liquid through said fracture zones by injecting gas therein at sufficiently high pressure that fines present in said fracture zones as a result of the crushing or abrading of existing clays or rocks are entrained by said liquid; and
. removing fines-laden liquid from said rock whereby the permeability of said rock segment is restored.
25. A process of claim 24 wherein liquid is driven through, and fines-laden liquid removed from, the fracture zone produced by the detonation of an explosive charge in a given cavity prior to the detonation of explosive charges in cavities adjacent thereto.
UNITED STATES PATENT OFFICE CERTIFICATE OF CORRECTION PATENT NO. 3,902,422 DATED September 2, 1975 INVENTOR(S) David Linn Course'n It is certified that error appears in the above-identifi ed potent and that said Letters Patent are hereby corrected as shown below:
Claims 18 and 19, line 1, the numeral "15" each occurrence, should read l7 Claim 20, line 1, the numeral "17" should read l9 Claim 9, line 2, cancel "to be". Claim 19, line 4, insert located after "holes".
Signed and Scaled this twenty-third D ay 0f December 1 9 75 [SEAL] A ttes t:
RUTH C. MASON ,Atresring Officer UNITED STATES PATENT OFFICE CERTIFICATE OF CORRECTION PATENT NO. 2 3,902,422
DATED September 2, 1975 INVENTOR(S) 1 David Linn Coursen It is certified that error appears in the above-identified patent and that said Letters Patent are hereby corrected as shown below:
Claims 18 and 19, line 1, the occurrence, should read l7 Claim 20, line 1, the numeral "17" should read l9 Claim 9, line 2, cancel "to be". Claim 19, line 4, insert located after "holes".
numeral "15" each Signed and Scaled this twenty-third D ay Of December I 9 75 [SE AL] A ttest:
RUTH C. MfKfiSON C. MARSHALL DANN i? 11 Commissioner uflatenls and Trademarks

Claims (25)

1. A process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment; b. positioning chemical explosive charges in a plurality of said cavities in the sections thereof located in said rock segment; c. allowing liquid to fill the fractures existing in the rock around the cavities in the sections thereof located in said rock segment as can be evidenced by a liquid level which is at least as high as the top of said rock segment; and d. detonating said explosive charges sequentially, each detonation in the sequence producing a zone of fracture in said segment and a drop in the level of said liquid, as measurable in the cavity which contained the detonated charge or in a cavity adjacent thereto, said charges being sufficiently large and spaced sufficiently close together that the fracture zones produced in said segment by the detonations of charges in adjacent cavities overlap, the detonation of the charge in each cavity being delayed until after the level of the liquid, as measurable in the cavity containing the charge to be detonated or in a cavity lying within the zone of fracture produced by a previous detonation in a cavity adjacent thereto, has ceased to drop and is at least as high as the top of said rock segment.
2. A process of claim 1 wherein said liquid is water.
3. A process of claim 2 wherein said water is naturally occurring in said rock.
4. A process of claim 1 wherein, in groups of adjacent cavities in which explosive charges are to be detonated, the detonation of the charge in each cavity takes place before charges are positioned in cavities adjacent thereto.
5. A process of claim 1 where in the time elapsing between any two consecutive detonations in a group of adjacent cavities is at least one hour.
6. A process of claim 5 wherein said liquid is introduced into at least one of said cavities and enters said rock by permeating the cavity walls.
7. A process of claim 1 wherein the cavities in which explosive charges are to be detonated form a pattern in which each internal cavity of the pattern is surrounded by at least four adjacent cavities.
8. A process of claim 1 wherein said cavities are substantially vertical drill holes.
9. A process of claim 8 wherein the sections of the holes which are located in said rock segment to be are chambered to larger diameter, and the explosive charges are positioned in the chambered sections.
10. A process of claim 9 wherein said chambered sections are produced by the previous detonation of springing explosive charges in the holes.
11. A process of claim 10 wherein the springing explosive charges employed to produce the chambered sections of said holes are at least about 20 feet long and the bottoms thereof are located below the bottom of said segment of rock.
12. A process of claim 8 wherein a pluraity of holes of said assemblage are drilled from the earth''s surface and are left uncharged with explosive, said holes forming passageways within the fracture network from the earth''s surface to substantially the bottom of said segment of rock.
13. A process of claim 12 wherein said plurality of uncharged holes are drilled and their walls provided with support casing, at least in the portions thereof located in the said segment of rock, prior to the detonation of the explosive charges in holes adjacent thereto.
14. A process of claim 13 wherein liquid is injected into said segment of rock through said uncharged holes.
15. A process of claim 8 wherein, in groups of adjacent holes in which explosive charges are to be detonated, the detonation of the charge in each hole takes place before adjacent holes are drilled.
16. A process of claim 8 wherein said substantially vertical holes are drilled into the segment of rock from the surface, and branch holes are drilled into the segment of rock from said substantially vertical holes at small angles thereto starting at locations overlying said segment of rock.
17. A process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment; b. positioning explosive charges in a plurality of said cavities in the section thereof located in said rock segment; c. detonating said explosive charges sequentially to produce a plurality of fracture zones; d. driving liquid through said fracture zones by injecting gas therein at sufficiently high pressure that fines present in said fracture zones as a result of the crushing or abrading of existing clays or rocks are entrained by said liquid; and e. removing fines-laden liquid from said rock whereby the permeability of said rock segment is restored.
18. A process of claim 15 wherein liquid is driven through, and fines-laden liquid removed from, the fracture zone Produced by the detonation of an explosive charge in a given cavity prior to the detonation of explosive charges in cavities adjacent thereto.
19. A process of claim 15 wherein an assemblage of substantially vertical holes is drilled into said rock from the earth''s surface; explosive charges are detonated in the sections of a plurality of said holes in said segment of rock in a manner such that the sections of said detonated holes located in the overburden that overlies said segment of rock survive the detonations and form a first set of passageways from the earth''s surface to said segment of rock, said first set of passageways leading substantially to the top of said segment of rock; a remaining plurality of holes of said assemblage are left uncharged with explosive and form a second set of passageways from the earth''s surface to said segment of rock, said second set of passageways leading substantially to the bottom of said segment of rock; and liquid is driven through said fracture zones laterally and upwardly from said second set of passageways to said first set of passageways and is brought to the surface through said first set of passageways.
20. A process of claim 17 wherein said uncharged holes are drilled prior to the detonation of said charges, and have their walls provided with support casing at least in the sections thereof located in said segment of rock.
21. A process of claim 19 wherein liquid present in the fracture zones is driven therethrough by gas injected therein through said holes which form said second set of passageways.
22. A process of claim 21 wherein said liquid is watter, and said gas is selected from the group consisting of air, oxygen, and nitrogen.
23. A process of claim 19 wherein said segment of rock is an ore body, and, after the detonation of said explosive charges, a lixiviant for said ore is driven through the fracture zones in said ore body from said holes which form said second set of passageways to said holes which form said first set of passageways, and is brought to the surface through said first set of passageways.
24. A process for producing a network of fractures in a deep segment of mineralized rock to prepare said segment for the in situ recovery of mineral values therefrom comprising a. forming an assemblage of cavities in said rock segment; b. positioning chemical explosive charges in a plurality of said cavities in the sections thereof located in said rock segment; c. allowing liquid to fill the fractures existing in the rock around the cavities in the sections thereof located in said rock segment as can be evidenced by a liquid level which is at least as high as the top of said rock segment; d. detonating said explosive charges sequentially, each detonation in the sequence producing a zone of fracture in said segment and a drop in the level of said liquid, as measurable in the cavity which contained the detonated charge or in a cavity adjacent thereto, said charges being sufficiently large and spaced sufficiently close together that the fracture zones produced in said segment by the detonations of charges in adjacent cavities overlap, the detonation of the charge in each cavity being delayed until after the level of the liquid, as measurable in the cavity containing the charge to be detonated or in a cavity lying within the zone of fracture produced by a previous detonation in a cavity adjacent thereto, has ceased to drop and is at least as high as the top of said rock segment; e. driving liquid through said fracture zones by injecting gas therein at sufficiently high pressure that fines present in said fracture zones as a result of the crushing or abrading of existing clays or rocks are entrained by said liquid; and f. removing fines-laden liquid from said rock whereby the permeability of said rock segment is restored.
25. A process of claim 24 wherein liquid is driven through, and fines-laden liquid removed from, the fracture zone produced by the detonAtion of an explosive charge in a given cavity prior to the detonation of explosive charges in cavities adjacent thereto.
US382845A 1973-07-26 1973-07-26 Explosive fracturing of deep rock Expired - Lifetime US3902422A (en)

Priority Applications (8)

Application Number Priority Date Filing Date Title
US382845A US3902422A (en) 1973-07-26 1973-07-26 Explosive fracturing of deep rock
CA000205542A CA1123726A (en) 1973-07-26 1974-07-24 Explosive fracturing of deep rock
AU71586/74A AU489283B2 (en) 1974-07-24 Explosive fracturing of deep rock
GB32879/74A GB1482023A (en) 1973-07-26 1974-07-25 Explosive fracturing of deep rock
GB5174/77A GB1482024A (en) 1973-07-26 1974-07-25 Process for leaching mineral values from ores
US05/535,808 US3999803A (en) 1973-07-26 1974-12-23 In situ leaching of explosively fractured ore bodies
US05/547,750 US4239286A (en) 1973-07-26 1975-02-06 In situ leaching of ore bodies
CA000397641A CA1144473A (en) 1973-07-26 1982-03-04 Explosive fracturing of deep rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US382845A US3902422A (en) 1973-07-26 1973-07-26 Explosive fracturing of deep rock

Related Child Applications (2)

Application Number Title Priority Date Filing Date
US05/535,808 Division US3999803A (en) 1973-07-26 1974-12-23 In situ leaching of explosively fractured ore bodies
US05/547,750 Division US4239286A (en) 1973-07-26 1975-02-06 In situ leaching of ore bodies

Publications (1)

Publication Number Publication Date
US3902422A true US3902422A (en) 1975-09-02

Family

ID=23510633

Family Applications (1)

Application Number Title Priority Date Filing Date
US382845A Expired - Lifetime US3902422A (en) 1973-07-26 1973-07-26 Explosive fracturing of deep rock

Country Status (3)

Country Link
US (1) US3902422A (en)
CA (1) CA1123726A (en)
GB (2) GB1482024A (en)

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3980339A (en) * 1975-04-17 1976-09-14 Geokinetics, Inc. Process for recovery of carbonaceous materials from subterranean deposits
US4037657A (en) * 1975-09-05 1977-07-26 Lekas Mitchell A Process for recovery of carbonaceous materials from subterranean deposits by in situ processing
US4205610A (en) * 1978-04-10 1980-06-03 Geokinetics Inc. Shale oil recovery process
USRE31677E (en) * 1975-04-17 1984-09-18 Geokinetics, Inc. Process for recovery of carbonaceous materials from subterranean deposits
US4690058A (en) * 1986-04-09 1987-09-01 C-I-L Inc. Smooth wall blasting in rock
US4703798A (en) * 1986-06-30 1987-11-03 Texaco Inc. In situ method for recovering hydrocarbon from subterranean oil shale deposits
US4757764A (en) * 1985-12-20 1988-07-19 The Ensign-Bickford Company Nonelectric blasting initiation signal control system, method and transmission device therefor
WO1991004455A1 (en) * 1989-09-12 1991-04-04 Tsentralny Nauchno-Issledovatelsky I Proektno-Experimentalny Institut Organizatsii, Mekhanizatsii I Tekhnicheskoi Pomoschi Stroitelstvu Method for making cavities in hard ground
WO1994016283A1 (en) * 1993-01-13 1994-07-21 Applied Energetic Systems, Inc. Detonator device and method for making same
US6460462B1 (en) * 1999-04-23 2002-10-08 Roboth Vertriebsgesellshaft Mbh Method of blasting of rock mass
CN102071922A (en) * 2011-01-15 2011-05-25 胜利油田鲁明油气勘探开发有限公司 Low permeable oil deposit virtual horizontal well development method
CN102619496A (en) * 2012-04-12 2012-08-01 中国科学院力学研究所 Method for layering, stage multi-level blasting, hole expanding and crack expanding of oil-gas-bearing rock
WO2012143168A2 (en) * 2011-04-18 2012-10-26 Sandvik Materials Technology Deutschland Gmbh Method for extracting hydrocarbon compounds, especially crude oil, from underground oil sands deposits
CN102877823A (en) * 2012-09-29 2013-01-16 肖功宽 Cracking method adopting blasting principle for improving gas output for shale gas
WO2014146624A1 (en) * 2013-08-09 2014-09-25 Kashafutdinov Varis Method for delivering or for preparing the delivery of fluid media
CN104389637A (en) * 2014-10-14 2015-03-04 河南理工大学 A method for determining loosening blasting danger-relieving range of coal beds with rock burst
US9057261B2 (en) 2010-03-19 2015-06-16 Exxonmobil Upstream Research Company System and method for fracturing rock in tight reservoirs
CN104987270A (en) * 2015-04-28 2015-10-21 安徽雷鸣科化股份有限公司 Anti-compressive water gel explosive
CN105242327A (en) * 2015-10-27 2016-01-13 山东科技大学 Method for testing shake penetration capacity of coal body
CN105403910A (en) * 2015-10-27 2016-03-16 山东科技大学 Roadway disturbance range field test method
CN108034815A (en) * 2017-12-01 2018-05-15 北京高能时代环境技术股份有限公司 A kind of tailing original position extract technology and tailing original position leaching system
CN108222939A (en) * 2018-02-10 2018-06-29 广西华洋矿源材料有限公司 A kind of recovery method of tin ore
CN108222940A (en) * 2018-02-10 2018-06-29 广西华洋矿源材料有限公司 A kind of recovery method of manganese ore
RU2691794C1 (en) * 2018-08-30 2019-06-18 Федеральное государственное унитарное предприятие "Российский федеральный ядерный центр - Всероссийский научно-исследовательский институт технической физики имени академика Е.И. Забабахина" Method for increasing reservoir recovery by dynamic formation action
CN110030889A (en) * 2019-04-17 2019-07-19 中国人民解放军军事科学院国防工程研究院 A kind of method of deep hole subregion triangulation network slotting shaft formatting by one blasting
CN110306967A (en) * 2019-08-20 2019-10-08 河南理工大学 A kind of coal seam hydraulic fracture couples anti-reflection method and device with hydraulic pressure demolition
CN113251879A (en) * 2021-05-12 2021-08-13 鞍钢矿业爆破有限公司 Method for analyzing blasting rock breaking energy consumption ratio
CN114688930A (en) * 2022-03-30 2022-07-01 西北核技术研究所 Blasting method and blasting structure for controlling blasting dust range in hard rock
CN114754644A (en) * 2022-06-01 2022-07-15 北京科技大学 Cut blasting method for optimizing number of blast holes in rock roadway tunneling
CN114993125A (en) * 2022-06-28 2022-09-02 北京科技大学 Deep high-stress rock roadway medium-deep hole efficient cut blasting method based on ground stress induction effect
CN115182713A (en) * 2022-08-15 2022-10-14 中国矿业大学 Shale reservoir three-dimensional horizontal well blasting close-cutting three-dimensional development method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5645322A (en) * 1995-03-14 1997-07-08 Tarim Associates For Scientific Mineral & Oil Exploration In-situ chemical reactor for recovery of metals and salts
RU2696714C1 (en) * 2018-06-14 2019-08-05 Акционерное общество "Сибнефтемаш" Method for thermo-chemical treatment of oil reservoir

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2630182A (en) * 1947-02-19 1953-03-03 Seismograph Service Corp Method for shooting oil wells
US2630307A (en) * 1948-12-09 1953-03-03 Carbonic Products Inc Method of recovering oil from oil shale
US2952449A (en) * 1957-02-01 1960-09-13 Fmc Corp Method of forming underground communication between boreholes
US3434757A (en) * 1967-02-02 1969-03-25 Shell Oil Co Shale oil-producing process
US3465818A (en) * 1967-11-07 1969-09-09 American Oil Shale Corp Undercutting of nuclearly detonated formations by subsequent nuclear detonations at greater depth and uses thereof in the recovery of various minerals
US3466094A (en) * 1968-02-05 1969-09-09 Us Interior Blasting arrangement for oil shale mining
US3650564A (en) * 1970-06-15 1972-03-21 Jacobs Associates Mining method for methane drainage and rock conditioning
US3710718A (en) * 1971-02-04 1973-01-16 Dow Chemical Co Method for creating underground cavities employing explosives
US3777815A (en) * 1970-06-17 1973-12-11 Cer Geonuclear Corp Explosive fracturing method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2630182A (en) * 1947-02-19 1953-03-03 Seismograph Service Corp Method for shooting oil wells
US2630307A (en) * 1948-12-09 1953-03-03 Carbonic Products Inc Method of recovering oil from oil shale
US2952449A (en) * 1957-02-01 1960-09-13 Fmc Corp Method of forming underground communication between boreholes
US3434757A (en) * 1967-02-02 1969-03-25 Shell Oil Co Shale oil-producing process
US3465818A (en) * 1967-11-07 1969-09-09 American Oil Shale Corp Undercutting of nuclearly detonated formations by subsequent nuclear detonations at greater depth and uses thereof in the recovery of various minerals
US3466094A (en) * 1968-02-05 1969-09-09 Us Interior Blasting arrangement for oil shale mining
US3650564A (en) * 1970-06-15 1972-03-21 Jacobs Associates Mining method for methane drainage and rock conditioning
US3777815A (en) * 1970-06-17 1973-12-11 Cer Geonuclear Corp Explosive fracturing method
US3710718A (en) * 1971-02-04 1973-01-16 Dow Chemical Co Method for creating underground cavities employing explosives

Cited By (42)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3980339A (en) * 1975-04-17 1976-09-14 Geokinetics, Inc. Process for recovery of carbonaceous materials from subterranean deposits
USRE31677E (en) * 1975-04-17 1984-09-18 Geokinetics, Inc. Process for recovery of carbonaceous materials from subterranean deposits
US4037657A (en) * 1975-09-05 1977-07-26 Lekas Mitchell A Process for recovery of carbonaceous materials from subterranean deposits by in situ processing
US4205610A (en) * 1978-04-10 1980-06-03 Geokinetics Inc. Shale oil recovery process
US4757764A (en) * 1985-12-20 1988-07-19 The Ensign-Bickford Company Nonelectric blasting initiation signal control system, method and transmission device therefor
US4690058A (en) * 1986-04-09 1987-09-01 C-I-L Inc. Smooth wall blasting in rock
US4703798A (en) * 1986-06-30 1987-11-03 Texaco Inc. In situ method for recovering hydrocarbon from subterranean oil shale deposits
WO1991004455A1 (en) * 1989-09-12 1991-04-04 Tsentralny Nauchno-Issledovatelsky I Proektno-Experimentalny Institut Organizatsii, Mekhanizatsii I Tekhnicheskoi Pomoschi Stroitelstvu Method for making cavities in hard ground
WO1994016283A1 (en) * 1993-01-13 1994-07-21 Applied Energetic Systems, Inc. Detonator device and method for making same
US5359935A (en) * 1993-01-13 1994-11-01 Applied Energetic Systems, Inc. Detonator device and method for making same
US6460462B1 (en) * 1999-04-23 2002-10-08 Roboth Vertriebsgesellshaft Mbh Method of blasting of rock mass
US9057261B2 (en) 2010-03-19 2015-06-16 Exxonmobil Upstream Research Company System and method for fracturing rock in tight reservoirs
CN102071922A (en) * 2011-01-15 2011-05-25 胜利油田鲁明油气勘探开发有限公司 Low permeable oil deposit virtual horizontal well development method
CN102071922B (en) * 2011-01-15 2013-07-03 胜利油田鲁明油气勘探开发有限公司 Low permeable oil deposit virtual horizontal well development method
WO2012143168A2 (en) * 2011-04-18 2012-10-26 Sandvik Materials Technology Deutschland Gmbh Method for extracting hydrocarbon compounds, especially crude oil, from underground oil sands deposits
WO2012143168A3 (en) * 2011-04-18 2013-03-14 Sandvik Materials Technology Deutschland Gmbh Method for extracting hydrocarbon compounds, especially crude oil, from underground oil sands deposits
CN102619496B (en) * 2012-04-12 2014-09-24 中国科学院力学研究所 Method for layering, stage multi-level blasting, hole expanding and crack expanding of oil-gas-bearing rock
CN102619496A (en) * 2012-04-12 2012-08-01 中国科学院力学研究所 Method for layering, stage multi-level blasting, hole expanding and crack expanding of oil-gas-bearing rock
CN102877823A (en) * 2012-09-29 2013-01-16 肖功宽 Cracking method adopting blasting principle for improving gas output for shale gas
WO2014146624A1 (en) * 2013-08-09 2014-09-25 Kashafutdinov Varis Method for delivering or for preparing the delivery of fluid media
EA034522B1 (en) * 2013-08-09 2020-02-17 Варис Кашафутдинов Method for delivering or for preparing the delivery of fluid media
CN104389637A (en) * 2014-10-14 2015-03-04 河南理工大学 A method for determining loosening blasting danger-relieving range of coal beds with rock burst
CN104987270A (en) * 2015-04-28 2015-10-21 安徽雷鸣科化股份有限公司 Anti-compressive water gel explosive
CN105242327A (en) * 2015-10-27 2016-01-13 山东科技大学 Method for testing shake penetration capacity of coal body
CN105403910A (en) * 2015-10-27 2016-03-16 山东科技大学 Roadway disturbance range field test method
CN105242327B (en) * 2015-10-27 2017-06-09 山东科技大学 It is a kind of to test the method that coal body shakes penetration capacity
CN105403910B (en) * 2015-10-27 2017-12-05 山东科技大学 A kind of method of on-the-spot test tunnel range of disturbance
CN108034815A (en) * 2017-12-01 2018-05-15 北京高能时代环境技术股份有限公司 A kind of tailing original position extract technology and tailing original position leaching system
CN108222940A (en) * 2018-02-10 2018-06-29 广西华洋矿源材料有限公司 A kind of recovery method of manganese ore
CN108222939A (en) * 2018-02-10 2018-06-29 广西华洋矿源材料有限公司 A kind of recovery method of tin ore
RU2691794C1 (en) * 2018-08-30 2019-06-18 Федеральное государственное унитарное предприятие "Российский федеральный ядерный центр - Всероссийский научно-исследовательский институт технической физики имени академика Е.И. Забабахина" Method for increasing reservoir recovery by dynamic formation action
CN110030889A (en) * 2019-04-17 2019-07-19 中国人民解放军军事科学院国防工程研究院 A kind of method of deep hole subregion triangulation network slotting shaft formatting by one blasting
CN110030889B (en) * 2019-04-17 2021-04-02 中国人民解放军军事科学院国防工程研究院 Method for forming well by deep hole partition triangular net cut through one-time blasting
CN110306967A (en) * 2019-08-20 2019-10-08 河南理工大学 A kind of coal seam hydraulic fracture couples anti-reflection method and device with hydraulic pressure demolition
CN113251879A (en) * 2021-05-12 2021-08-13 鞍钢矿业爆破有限公司 Method for analyzing blasting rock breaking energy consumption ratio
CN113251879B (en) * 2021-05-12 2023-01-24 鞍钢矿业爆破有限公司 Method for analyzing blasting rock breaking energy consumption ratio
CN114688930A (en) * 2022-03-30 2022-07-01 西北核技术研究所 Blasting method and blasting structure for controlling blasting dust range in hard rock
CN114688930B (en) * 2022-03-30 2024-06-07 西北核技术研究所 Blasting method and blasting structure for controlling blasting dust range in hard rock
CN114754644A (en) * 2022-06-01 2022-07-15 北京科技大学 Cut blasting method for optimizing number of blast holes in rock roadway tunneling
CN114993125A (en) * 2022-06-28 2022-09-02 北京科技大学 Deep high-stress rock roadway medium-deep hole efficient cut blasting method based on ground stress induction effect
CN115182713A (en) * 2022-08-15 2022-10-14 中国矿业大学 Shale reservoir three-dimensional horizontal well blasting close-cutting three-dimensional development method
CN115182713B (en) * 2022-08-15 2023-09-22 中国矿业大学 Three-dimensional development method for explosive-tight cutting of shale reservoir three-dimensional horizontal well

Also Published As

Publication number Publication date
GB1482023A (en) 1977-08-03
AU7158674A (en) 1976-01-29
GB1482024A (en) 1977-08-03
CA1123726A (en) 1982-05-18

Similar Documents

Publication Publication Date Title
US3902422A (en) Explosive fracturing of deep rock
US4018293A (en) Method and apparatus for controlled fracturing of subterranean formations
RU2567877C2 (en) Method for efficiency improvement in injection and intensification of oil and gas production
US4398769A (en) Method for fragmenting underground formations by hydraulic pressure
US9062545B2 (en) High strain rate method of producing optimized fracture networks in reservoirs
US4185693A (en) Oil shale retorting from a high porosity cavern
US3118501A (en) Means for perforating and fracturing earth formations
US3434757A (en) Shale oil-producing process
US2970645A (en) Producing multiple fractures in a well
US4220205A (en) Method of producing self-propping fluid-conductive fractures in rock
US4078612A (en) Well stimulating process
EA001243B1 (en) Method for stimulating production from lenticular natural gas formations
US4378949A (en) Production of shale oil by in-situ retorting of oil shale
US3771600A (en) Method of explosively fracturing from drain holes using reflective fractures
US4118071A (en) In situ oil shale retort with a horizontal sill pillar
US3999803A (en) In situ leaching of explosively fractured ore bodies
US4239286A (en) In situ leaching of ore bodies
US4135450A (en) Method of underground mining
US3464490A (en) Formation nuclear fracturing process
US4223734A (en) Process of breaking and rendering permeable a subterranean rock mass
US4239284A (en) Situ retort with high grade fragmented oil shale zone adjacent the lower boundary
RU2044998C1 (en) Method for rock blasting in open pit
US3677342A (en) Method of increasing size of underground nuclear chimney
US3630283A (en) Method of producing particles of rock in a subterranean situs
RU2503799C2 (en) Method for shale gas production

Legal Events

Date Code Title Description
AS Assignment

Owner name: ETI EXPLOSIVES TECHNOLOGIES INTERNATIONAL INC., RO

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST.;ASSIGNOR:E.I. DU PONT DE NEMOURS AND COMPANY;REEL/FRAME:004834/0446

Effective date: 19880118

Owner name: ETI EXPLOSIVES TECHNOLOGIES INTE,STATELESS

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:E.I. DU PONT DE NEMOURS AND COMPANY;REEL/FRAME:004834/0446

Effective date: 19880118

AS Assignment

Owner name: TORONTO DOMINION BANK

Free format text: SECURITY INTEREST;ASSIGNOR:ETI EXPLOSIVES TECHNOLOGIES INTERNATIONAL INC.;REEL/FRAME:004829/0868

Effective date: 19871231

Owner name: TORONTO DOMINION BANK,STATELESS

Free format text: SECURITY INTEREST;ASSIGNOR:ETI EXPLOSIVES TECHNOLOGIES INTERNATIONAL INC.;REEL/FRAME:004829/0868

Effective date: 19871231