US3796054A - Method for the construction of impermeable walls - Google Patents

Method for the construction of impermeable walls Download PDF

Info

Publication number
US3796054A
US3796054A US00207916A US3796054DA US3796054A US 3796054 A US3796054 A US 3796054A US 00207916 A US00207916 A US 00207916A US 3796054D A US3796054D A US 3796054DA US 3796054 A US3796054 A US 3796054A
Authority
US
United States
Prior art keywords
concrete
slot
membrane
slots
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US00207916A
Inventor
U Piccagli
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US3796054A publication Critical patent/US3796054A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/185Bulkheads or similar walls made solely of concrete in situ with flexible joint members between sections

Definitions

  • a method for the construction of an impermeable concrete wall in the ground the wall constitutes a series of vertical concrete panels cast in individual consecutive slots, made in such a way that each slot intersects the cross-section of the adjacent previously formed vertical panel.
  • a first series of slots are first excavated and at the same time the soil is removed from these slots and it is replaced with a thixotropic fluid after the slot has been excavated.
  • a vertical flexible membrane is inserted in at least one end of the slot, the concrete is then poured into the slot leaving half the vertical membrane within the concrete panel. The spaces between the slots are then excavated and the second series of concrete panels poured surrounding the exposed half of the flexible membrane.
  • each concrete panel there is a -flexible membrane to stop water leaking through the wall.
  • PATENTEDIIARIZ m4 37961354 saw u or 5 I HEW PAIENTEBIAR 12 m4 3396354 sum 5 or 5 METHOD FOR THE CONSTRUCTION OF IMPERMEABLE WALLS
  • the present invention relates to a method for constructing a concrete wall in the ground and more particularly a method for forming impermeable partition walls in the ground, the wall constituting a series of vertical concrete panels cast in individual consecutive slots, made in such a way that each slot intersects the cross-section of the adjacent previously formed vertical panel.
  • a method of digging slots or trenches having vertical walls by the use of thixotropic clay is known.
  • the method consists essentially in that after the proposed line of the slot has'been indicated on the ground with the aid of any known means, the earth is removed from beneath the line by a toothed grab, a chisel or some other means, to the exact width of the slot.
  • the grab displaces the earth in the slot and this is constantly refilled with a liquid thixotropic clay mixture so that the slot is constantly full.
  • the slot has been dug the required width, depth and length it may then be filled with concrete.
  • this procedure is generally carried out by digging a seriesof slots spaced apart at a predetermined distance pouring concrete into these slots to form panels and subsequently moving the earth from the space between the first dug slots and then filling these spaces with concrete to form a continuous wall.
  • the slots are'first excavated preferably by means of a chisel similar to that shown in Canadian Pat. No. 671,872 or in the case of soft sandy soil, a toothed grab similar to that shown in Applicant's Canadian application Ser. No. 092,867 filed Sept. 10, 1970.
  • shoulder pipes which are round steel pipes having a diameter approximately the same as the width of the slot are lowered into either one or both ends of the slot so that they stand vertically. Concrete is poured into the slot through the tremie pipe to form a panel and the shoulder pipes are then removed as the concrete hardens. The removal of these steel pipes is a tricky operation and involves raising the pipe slowly as the concrete sets in the slot.
  • the shoulder pipe need not necessarily be a pipe, but may be any rolled steel section or may be fabricated from plate. In some instances the shoulder pipe or steel section is left in the slot to strengthen the concrete wall.
  • the present invention provides a method for the construction of an impermeable concrete wall in the ground comprising the steps of: excavating a first series of slots at a predetermined length, width and depth along a predetermined line of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical flexible membranes in at least one end of the first series of slots for their full depth adjacent the spaces, filling the first series of slots with concrete to form first concrete panels such that approximately half the cross-sections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abutts at least one end of the first concrete panels and the remaining half of the cross-sections of each of the flexible membrane
  • FIG. 1 is perspective view showing a flexible membrane of the present invention, attached by clips to a steel support frame.
  • FIGS. 2, 3, 4, 5, 6 and 7 are top plan diagrammatic views illustrating flexible membranes supported by different embodiments of support frames located at one end of a slot, one .half of the flexible membrane being within the first concrete panel.
  • FIG. 8 is a perspective view showing a further embodiment of a support frame for a flexible membrane.
  • FIG. -9 is a perspective view showing another embodi-' ment of a removable clip for attaching a flexible mem-. brane to a support frame similar to that shown in FIG. 1.
  • the line of the required concretewall is generally laid out on the ground and the decision determining how many slots required is made. In this manner the length of each slot is measured, together with the width.
  • the excavation itself is carried out by a number of ways such as an excavating shovel or a chisel. Methods of excavation depend on the consistency of the ground, if soft or sandy ground is present then a toothed grab or clam shell bucket is used, frequently with a suction hose, to suck out the sand as it is replaced with the thixotropic fluid. If it is rock or hard ground then the excavation is achieved by chiselling'and sucking out the excavated rock or flakes of rock as they come to the surface of the thixotropic clay in the excavation.
  • thixotropic fluid As the soil, earth, or rock is removed from the slot it is replaced by thixotropic fluid.
  • the soil, earth or rock tends to float to the top of this fluid where it is removed by a suction pipe and passed through a filter mechanism to separate it from the thixotropic clay which is then returned to the trench.
  • a flexible membrane is attached to a steel channel 11 by two clips 12 and 13 so that the membrane 10 rests against an outside face 14 of one flange of the channel 11.
  • FIG. 2 shows a membrane 10 and a supporting frame 11 similar to that shown in FIG. I inserted into one end of a first slot 15.
  • a first concrete panel 16 is poured into the slot 15 using a tremie pipe so that the concrete enters the slot 15 below the thixotropic fluid.
  • the tremie pipe is slowly raised, and the thixotropic fluid is pumped out at the same rate the concrete is poured into the excavation so the top level of the thixotropic fluid remains constant.
  • the supporting channel 11 When the concrete commences to harden, the supporting channel 11 is slowly withdrawn vertically from the first slot 15. As the concrete has been poured at the bottom of the slot 15 first, it tends to harden at the bottom first, therefore the channel 11 is withdrawn very slowly allowing the concrete to harden up the height of the concrete panel 16 at approximately the same rate as the channel 11 is raised leaving the flexible membrane 10 in place.
  • the removal of the channel 11 is a very tricky operation, if the channel is removed too soon, the concrete will not have hardened sufficiently and it will fall into the space in the slot 15 left by the channel 11. Alternately if the channel 11 is left in place too long the concrete tends to bond to the channel 11, and then cannot be removed at all.
  • the channel 11 is left in the slot 15, and this forms a supporting structure in the concrete wall.
  • the channel 11 usually takes another shape thanthe channel 11 shown in FIG. 2.
  • the next step involved in constructing the wall is to excavate the second slot 17 adjacent to the first concrete panel 16. This is done by methods previously described for excavating the first slot 15. A second concrete panel is poured in this second slot 17 by the same manner in which the first concrete panel 15 was poured, so
  • the resulting joint between the first concrete panel 16 and the second concretepanel has the flexible membrane 10 between the two.
  • this flexible membrane 10 extends into both ends of the adjacent concrete panels, it acts as a complete waterproof seal.
  • FIG. 3 shows a flexible membrane 20 supported between a first channel 21- and a second channel 22.
  • the two channels have a spacer 23 located between the tips of the adjacent flanges of the channels 21 and 22 so that no pressure occurs from either channel on the membrane 20.
  • the membrane 20 is located in the centre of the slot 24 so that on completion of the first concrete panel 25, one half of the cross-section of the membrane 20 is completely surrounded by concrete.
  • the structural frame may be removed after the first concrete panel 25 has been poured or it may be left in this location to form reinforcing in the concrete wall.
  • a shoulder pipe 26 is shown in FIG.'4 having an aperture 27 facing in the direction of the first slot 28.
  • the aperture 27 has two lips 29 and is wide enough to allow a flexible membrane 30 to slide in the aperture 27 between the lips 29.
  • the flexible membrane 30 is shown having two bulbous ends 31 to allow the concrete panels to grip the membrane 30.
  • the shoulder pipe 26 with the membrane 30 in place is inserted into the first slot 28 after it has been excavated.
  • the membrane 30 extends to the bottom of the slot 28.
  • a first concrete panel 32 is then poured and this firmly grips the portion of the membrane 30 exposed to the concrete.
  • the shoulder pipe 26 is slowly removedverti' cally from the slot 28 after the concrete has commenced to harden and the second slot 33 adjoining the first concrete panel 32 is excavated in preparation for pouring a second concrete panel.
  • the joint between the first concrete panel 32 and the second concrete panel is curved in shape to produce a strong connection, and the two bulbous ends 31 of the flexible membrane 30 join the panels together and act as a water seal to stop water passing through the joint.
  • FIGS. 5 and 6 show further embodiments of shoulder type pipes where the pipes are not round but in the case of FIG. 5 are square and in the case of FIG. 6 are sloped back so that the joint between the two concrete panels is not straight across.
  • FIG. 7 and FIG. 8 show another frame 40 for supporting a flexible membrane 41.
  • the frame is made from two Z-rolled steel sections 42 with a space 43 therebetween for the web of the membrane 41 to slide freely.
  • the two Z sections 42 are held apart by means of a series of spacer bars 44 spaced down the length of the Z sections 42.
  • the spacer bars 44 are welded to the outside flange of the Z sections 42 and have support plates 45 between'the spacer bars 44 and the centre web of the Z sections '42 to add ridgidity to the two Z sections 42 and retain the space 43 between these Z sections 42 at the correct distance.
  • the method of inserting the membrane 41 is similar to that described for FIGS. 2 and 3.
  • the flexible membrane 41 is not held by the frame 40, thus after the first concrete panel 46 has been poured the frame 40 may be slowly withdrawn leaving the flexible membrane surrounded by the concrete.
  • FIG. 9 shows a channel frame 50 similar to the type shown in FIGS. 1 and 2.
  • the frame has a special device for holding the flexible membrane 51 to the one flange of the channels 50, with a small hook 53 welded to the flange of the channel frame 50 adjacent the flexible membrane 51.
  • the hook 53 fits into a strap attachment 54 which is attached to the flexible membrane 51.
  • a method for the construction of an impermeable concrete wall in the ground comprising the steps of excavating a first series of slots of predetermined length, width and depth along a predetermined line and of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical membranes in at least one end of the first series of slots with concrete to form first concrete panels such that approximately half the cross-sections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots, and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abuts atleast one end of the first concrete panels and the remaining half of the cross-sections of each of the flexible membranes are within the second concrete panels, the method being further characterized in that during the pouring of the trixothropic fluid and subsequently the
  • This device includes a square aperture 52 in membrane is supported by a steel frame bordering the end of the slot, the steel frame engaging the membrane with at least one rigid vertical edge which supports the membrane in a vertical position and slides freely vertically relative thereto so that it supports the membrane where it engages it regardless of its vertical position relative to the membrane, and including the step of removing the steel frame gradually as the concrete starts to harden at its lower end, and at essentially the same vertical rate as the concrete hardens from the bottom upwardly so that the bottom of the steel frame gradually moves above concrete hard enough to be selfsupporting but not sufficiently hard to bond to the steel frame, the steel frame moving slidably along and still supporting the vertical membrane as it moves upwardly therealong.
  • the shoulder pipe being inserted into at least one end i of the slot with the aperture facing the excavation.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A method is disclosed for the construction of an impermeable concrete wall in the ground, the wall constitutes a series of vertical concrete panels cast in individual consecutive slots, made in such a way that each slot intersects the cross-section of the adjacent previously formed vertical panel. A first series of slots are first excavated and at the same time the soil is removed from these slots and it is replaced with a thixotropic fluid after the slot has been excavated. A vertical flexible membrane is inserted in at least one end of the slot, the concrete is then poured into the slot leaving half the vertical membrane within the concrete panel. The spaces between the slots are then excavated and the second series of concrete panels poured surrounding the exposed half of the flexible membrane. Thus between each concrete panel there is a flexible membrane to stop water leaking through the wall.

Description

United States Patent [191 Piecagli 1 Mar. 12, 1974 METHOD FOR THE CONSTRUCTION OF IMPERMEABLE WALLS Primary Examiner.Mervin Stein Assistant Examiner-Alex Grosz 76 I t U Pi l' 4511Har L 1 nven or ia ff l ry S n Attorney, Agent, or FzrmFetherstonhaugh & Co.
[22] Filed: Dec. 24, 1971 [57] ABSTRACT Appl. No.: 207,916
US. Cl 61/35, 52/396, 61/59,
A method is disclosed for the construction of an impermeable concrete wall in the ground, the wall constitutes a series of vertical concrete panels cast in individual consecutive slots, made in such a way that each slot intersects the cross-section of the adjacent previously formed vertical panel. A first series of slots are first excavated and at the same time the soil is removed from these slots and it is replaced with a thixotropic fluid after the slot has been excavated. A vertical flexible membrane is inserted in at least one end of the slot, the concrete is then poured into the slot leaving half the vertical membrane within the concrete panel. The spaces between the slots are then excavated and the second series of concrete panels poured surrounding the exposed half of the flexible membrane. Thus between each concrete panel there is a -flexible membrane to stop water leaking through the wall.
6 Claims, 9 Drawing Figures PATENTEDIAR 12 m4 SHEET .1 [If 5 PATENTEDIAR 12 mm SHEET 2 UF 5 F/GZ PATENTEDIIAR 2 m4 SHEET 3 BF 5 Fla.
PATENTEDIIARIZ m4 37961354 saw u or 5 I HEW PAIENTEBIAR 12 m4 3396354 sum 5 or 5 METHOD FOR THE CONSTRUCTION OF IMPERMEABLE WALLS The present invention relates to a method for constructing a concrete wall in the ground and more particularly a method for forming impermeable partition walls in the ground, the wall constituting a series of vertical concrete panels cast in individual consecutive slots, made in such a way that each slot intersects the cross-section of the adjacent previously formed vertical panel.
A method of digging slots or trenches having vertical walls by the use of thixotropic clay is known. The method consists essentially in that after the proposed line of the slot has'been indicated on the ground with the aid of any known means, the earth is removed from beneath the line by a toothed grab, a chisel or some other means, to the exact width of the slot. The grab displaces the earth in the slot and this is constantly refilled with a liquid thixotropic clay mixture so that the slot is constantly full. After the slot has been dug the required width, depth and length it may then be filled with concrete. This is done by inserting what is referred to as a tremie pipe into the slot so that the bottom of the pipe is at the bottom of the slot and then pouring concrete through the tremie pipe into the slot. As the concrete is poured into the slot, the tremie pipe is slowly raised, so the end of the pipe is just below the level of the liquid concrete. Thus the'thixotropic clay, which is considerably less dense than liquid concrete, is displaced and is generally pumped out of the slot to avoid the clay pouring over the ground. Once the slot has been filled, the concrete is allowed to set to form a first concrete panel, and a second slot is dug adjacent and in line with the first slot using the same procedure of replacing the displaced earth with thixotropic clay. Following this step the tremie pipe is again inserted into the new slot, concrete is poured'into the slotdisplacing .the thixotropic clay to form a second concrete panel,
and you thus have two panels which are joined into one to form a wall. In effect this procedure is generally carried out by digging a seriesof slots spaced apart at a predetermined distance pouring concrete into these slots to form panels and subsequently moving the earth from the space between the first dug slots and then filling these spaces with concrete to form a continuous wall.
In another method of pouring concrete panels in staggered slots in the ground, the slots are'first excavated preferably by means of a chisel similar to that shown in Canadian Pat. No. 671,872 or in the case of soft sandy soil, a toothed grab similar to that shown in Applicant's Canadian application Ser. No. 092,867 filed Sept. 10, 1970. Then shoulder pipes, which are round steel pipes having a diameter approximately the same as the width of the slot are lowered into either one or both ends of the slot so that they stand vertically. Concrete is poured into the slot through the tremie pipe to form a panel and the shoulder pipes are then removed as the concrete hardens. The removal of these steel pipes is a tricky operation and involves raising the pipe slowly as the concrete sets in the slot. After the pipe has been removed, the end face of the concrete panel is curved to the circumference of the pipe. When the adjacent slot is dug and the next concrete panel formed, the join between the panels is curved rather than straight, resulting in a structurally stronger inter locking joint. The shoulder pipe need not necessarily be a pipe, but may be any rolled steel section or may be fabricated from plate. In some instances the shoulder pipe or steel section is left in the slot to strengthen the concrete wall.
One of the problems that can occur with this type of wall construction is leakage or seepage through the joints between the concrete panels. This leakage occurs with straight joints or curved joints made by the shoulder pipe method. The reason for the leakage may be due to a layer of thixotropic clay between the panels or to pockets of sand or soil which stay in the slot and stop the concrete forming a bond or seal therein. Various methods of forming a sea] at this joint have been tried, none have proved completely successful.
It is an object of the present invention-to provide a method for forming an impermeable concrete wall in the ground.
It is'a further object to provide a method of inserting a water tight flexible membrane between the first and second elements of a concrete wall in the ground.
These and other objects will become apparent by referring to the present invention which provides a method for the construction of an impermeable concrete wall in the ground comprising the steps of: excavating a first series of slots at a predetermined length, width and depth along a predetermined line of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical flexible membranes in at least one end of the first series of slots for their full depth adjacent the spaces, filling the first series of slots with concrete to form first concrete panels such that approximately half the cross-sections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abutts at least one end of the first concrete panels and the remaining half of the cross-sections of each of the flexible membranes are within the second concrete panels.
In drawings which illustrate embodiments of the invention:
FIG. 1 is perspective view showing a flexible membrane of the present invention, attached by clips to a steel support frame.
FIGS. 2, 3, 4, 5, 6 and 7 are top plan diagrammatic views illustrating flexible membranes supported by different embodiments of support frames located at one end of a slot, one .half of the flexible membrane being within the first concrete panel.
FIG. 8 is a perspective view showing a further embodiment of a support frame for a flexible membrane.
FIG. -9 is a perspective view showing another embodi-' ment of a removable clip for attaching a flexible mem-. brane to a support frame similar to that shown in FIG. 1.
In the construction of a concrete wall according to the present invention, the line of the required concretewall is generally laid out on the ground and the decision determining how many slots required is made. In this manner the length of each slot is measured, together with the width. The excavation itself is carried out by a number of ways such as an excavating shovel or a chisel. Methods of excavation depend on the consistency of the ground, if soft or sandy ground is present then a toothed grab or clam shell bucket is used, frequently with a suction hose, to suck out the sand as it is replaced with the thixotropic fluid. If it is rock or hard ground then the excavation is achieved by chiselling'and sucking out the excavated rock or flakes of rock as they come to the surface of the thixotropic clay in the excavation.
As the soil, earth, or rock is removed from the slot it is replaced by thixotropic fluid. The soil, earth or rock tends to float to the top of this fluid where it is removed by a suction pipe and passed through a filter mechanism to separate it from the thixotropic clay which is then returned to the trench.
After the slot has reached the required depth and before the concrete is poured, it is necessary to place the flexible membrane in position at one end or both ends of the slot. This is preferably achieved by taking the flexible membrane and supporting it on a support frame similar to those shown in the drawings. In the embodiment shown in FIG. 1, a flexible membrane is attached to a steel channel 11 by two clips 12 and 13 so that the membrane 10 rests against an outside face 14 of one flange of the channel 11.
The flexible membrane is generally made from rubber however flexible synthetic materials such as plastics are also suitable. The membrane is preferably in the order of half an inch thick, and generally 8 to 12 inches long. The maximum movement that occurs between panels does not generally exceed one quarter inch. FIG. 2 shows a membrane 10 and a supporting frame 11 similar to that shown in FIG. I inserted into one end of a first slot 15. A first concrete panel 16 is poured into the slot 15 using a tremie pipe so that the concrete enters the slot 15 below the thixotropic fluid. As the concrete is poured in, the tremie pipe is slowly raised, and the thixotropic fluid is pumped out at the same rate the concrete is poured into the excavation so the top level of the thixotropic fluid remains constant. When the concrete commences to harden, the supporting channel 11 is slowly withdrawn vertically from the first slot 15. As the concrete has been poured at the bottom of the slot 15 first, it tends to harden at the bottom first, therefore the channel 11 is withdrawn very slowly allowing the concrete to harden up the height of the concrete panel 16 at approximately the same rate as the channel 11 is raised leaving the flexible membrane 10 in place. The removal of the channel 11 is a very tricky operation, if the channel is removed too soon, the concrete will not have hardened sufficiently and it will fall into the space in the slot 15 left by the channel 11. Alternately if the channel 11 is left in place too long the concrete tends to bond to the channel 11, and then cannot be removed at all. In some instances, either on purpose or otherwise, the channel 11 is left in the slot 15, and this forms a supporting structure in the concrete wall. However in a situation when it is planned to leave the support frame in the slot, it usually takes another shape thanthe channel 11 shown in FIG. 2. The next step involved in constructing the wall is to excavate the second slot 17 adjacent to the first concrete panel 16. This is done by methods previously described for excavating the first slot 15. A second concrete panel is poured in this second slot 17 by the same manner in which the first concrete panel 15 was poured, so
that the resulting joint between the first concrete panel 16 and the second concretepanel has the flexible membrane 10 between the two. As this flexible membrane 10 extends into both ends of the adjacent concrete panels, it acts as a complete waterproof seal.
FIG. 3 shows a flexible membrane 20 supported between a first channel 21- and a second channel 22. The two channels have a spacer 23 located between the tips of the adjacent flanges of the channels 21 and 22 so that no pressure occurs from either channel on the membrane 20. In this construction of support frame, the membrane 20 is located in the centre of the slot 24 so that on completion of the first concrete panel 25, one half of the cross-section of the membrane 20 is completely surrounded by concrete. The structural frame may be removed after the first concrete panel 25 has been poured or it may be left in this location to form reinforcing in the concrete wall.
A shoulder pipe 26 is shown in FIG.'4 having an aperture 27 facing in the direction of the first slot 28. The aperture 27 has two lips 29 and is wide enough to allow a flexible membrane 30 to slide in the aperture 27 between the lips 29. The flexible membrane 30 is shown having two bulbous ends 31 to allow the concrete panels to grip the membrane 30. In this configuration, the shoulder pipe 26 with the membrane 30 in place is inserted into the first slot 28 after it has been excavated. The membrane 30 extends to the bottom of the slot 28. A first concrete panel 32 is then poured and this firmly grips the portion of the membrane 30 exposed to the concrete. The shoulder pipe 26 is slowly removedverti' cally from the slot 28 after the concrete has commenced to harden and the second slot 33 adjoining the first concrete panel 32 is excavated in preparation for pouring a second concrete panel. After the second concrete panel has been poured, the joint between the first concrete panel 32 and the second concrete panel is curved in shape to produce a strong connection, and the two bulbous ends 31 of the flexible membrane 30 join the panels together and act as a water seal to stop water passing through the joint.
FIGS. 5 and 6 show further embodiments of shoulder type pipes where the pipes are not round but in the case of FIG. 5 are square and in the case of FIG. 6 are sloped back so that the joint between the two concrete panels is not straight across.
FIG. 7 and FIG. 8 show another frame 40 for supporting a flexible membrane 41. The frame is made from two Z-rolled steel sections 42 with a space 43 therebetween for the web of the membrane 41 to slide freely. The two Z sections 42 are held apart by means of a series of spacer bars 44 spaced down the length of the Z sections 42. The spacer bars 44 are welded to the outside flange of the Z sections 42 and have support plates 45 between'the spacer bars 44 and the centre web of the Z sections '42 to add ridgidity to the two Z sections 42 and retain the space 43 between these Z sections 42 at the correct distance. The method of inserting the membrane 41 is similar to that described for FIGS. 2 and 3. The flexible membrane 41 is not held by the frame 40, thus after the first concrete panel 46 has been poured the frame 40 may be slowly withdrawn leaving the flexible membrane surrounded by the concrete.
FIG. 9 shows a channel frame 50 similar to the type shown in FIGS. 1 and 2. The frame, however, has a special device for holding the flexible membrane 51 to the one flange of the channels 50, with a small hook 53 welded to the flange of the channel frame 50 adjacent the flexible membrane 51. The hook 53 fits into a strap attachment 54 which is attached to the flexible membrane 51. Thus when the channel frame 50 is raised relative to the flexible membrane 51, the hook 53 is lifted out of the strap 54 and the channel frame 50 may be removed leaving the flexible membrane 51 in place.
While several methods of locating the flexible membrane in the first slot have been illustrated in some detail herein, it will be appreciated by those skilled in the art that many variations can be accomplished without departing from the spirit of the present invention, and
that the scope of this invention should be limited only by the scope of the appended claims.
The embodiments of the invention in which an exclusive property or privilege is claimed are defined as follows:
1. A method for the construction of an impermeable concrete wall in the ground, comprising the steps of excavating a first series of slots of predetermined length, width and depth along a predetermined line and of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical membranes in at least one end of the first series of slots with concrete to form first concrete panels such that approximately half the cross-sections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots, and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abuts atleast one end of the first concrete panels and the remaining half of the cross-sections of each of the flexible membranes are within the second concrete panels, the method being further characterized in that during the pouring of the trixothropic fluid and subsequently the concrete, the
frame 50. This device includes a square aperture 52 in membrane is supported by a steel frame bordering the end of the slot, the steel frame engaging the membrane with at least one rigid vertical edge which supports the membrane in a vertical position and slides freely vertically relative thereto so that it supports the membrane where it engages it regardless of its vertical position relative to the membrane, and including the step of removing the steel frame gradually as the concrete starts to harden at its lower end, and at essentially the same vertical rate as the concrete hardens from the bottom upwardly so that the bottom of the steel frame gradually moves above concrete hard enough to be selfsupporting but not sufficiently hard to bond to the steel frame, the steel frame moving slidably along and still supporting the vertical membrane as it moves upwardly therealong.
2. The method according to claim 1 wherein the steel frame comprises a channel with a width extending across the face of the slots and the vertical flexible membranes are attached to one flange of the channel resulting in the membranes being positioned at one side of the first concrete panels,
3. The method according to claim 1 wherein the steel frames support the flexible membranes so that they are located in the centre of the width of the concrete panels.
4. The method according to claim 1 wherein the steel frame comprises a shoulder pipe having two lips and an aperture therebetween to support a flexible membrane,
the shoulder pipe being inserted into at least one end i of the slot with the aperture facing the excavation.
5. The method according to claim 1 which is further characterized in that said vertical flexible membranes have bulbous opposite side edges which become embedded in the concrete panels.
6. The method according to claim 1 which is further characterized in that said steel frame is a round pipe provided at one side thereof with a pair of spaced longitudinal lips between which the flexible membrane is received.

Claims (6)

1. A method for the construction of an impermeable concrete wall in the ground, comprising the steps of excavating a first series of slots of predetermined length, width and depth along a predetermined line and of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical membranes in at least one end of the first series of slots with concrete to form first concrete panels such that approximately half the crosssections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots, and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abuts at least one end of the first concrete panels and the remaining half of the crosssections of each of the flexible membranes are within the second concrete panels, the method being further characterized in that during the pouring of the trixothropic fluid and subsequently the concrete, the membrane is supported by a steel frame bordering the end of the slot, the steel frame engaging the membrane with at least one rigid vertical edge which supports the membrane in a vertical position and slides freely vertically relative thereto so that it supports the membrane where it engages it regardless of its vertical position relative to the membrane, and including the step of removing the steel frame gradually as the concrete starts to harden at its lower end, and at essentially the same vertical rate as the concrete hardens from the bottom upwardly so that the bottom of the steel frame gradually moves above concrete hard enough to be self-supporting but not sufficiently hard to bond to the steel frame, the steel frame moving slidably along and still supporting the vertical membrane as it moves upwardly therealong.
2. The method according to claim 1 wherein the steel frame comprises a channel with a width extending across the face of the slots and the vertical flexible membranes are attached to one flange of the channel resulting in the membranes being positioned at one side of the first concrete panels.
3. The method according to claim 1 wherein the steel frames support the flexible membranes so that they are located in the centre of the width of the concrete panels.
4. The method according to claim 1 wherein the steel frame comprises a shoulder pipe having two lips and an aperture therebetween to support a flexible membrane, the shoulder pipe being inserted into at least one end of the slot with the aperture facing the excavation.
5. The method according to claim 1 which is further characterized in that said vertical flexible membranes have bulbous opposite side edges which become embedded in the concrete panels.
6. The method according to claim 1 which is further characterized in that said steel frame is a round pipe provided at one side thereof with a pair of spaced longitudinal lips between which the flexible membrane is received.
US00207916A 1971-12-14 1971-12-24 Method for the construction of impermeable walls Expired - Lifetime US3796054A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US20791671A 1971-12-14 1971-12-14

Publications (1)

Publication Number Publication Date
US3796054A true US3796054A (en) 1974-03-12

Family

ID=22772494

Family Applications (1)

Application Number Title Priority Date Filing Date
US00207916A Expired - Lifetime US3796054A (en) 1971-12-14 1971-12-24 Method for the construction of impermeable walls

Country Status (3)

Country Link
US (1) US3796054A (en)
AU (1) AU463693B2 (en)
CA (1) CA965624A (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4346670A (en) * 1979-12-03 1982-08-31 Bunger Richard E Prefabricated mold inserts for forming flume platforms for animal confinement pens and method of construction
WO1984003315A1 (en) * 1983-02-22 1984-08-30 Finic Bv Environmental cut-off for deep excavations
FR2542780A1 (en) * 1983-03-18 1984-09-21 Intrafor Cofor Method and device for improving the joint between successive panels of a reinforced concrete wall cast in the ground
US4582453A (en) * 1984-08-16 1986-04-15 Finic, B.V. Method and apparatus for in situ forming underground panelized concrete walls with improved joint structure
DE3444077A1 (en) * 1984-12-04 1986-06-19 Ed. Züblin AG, 7000 Stuttgart Paring tube
US4741644A (en) * 1985-04-11 1988-05-03 Finic, B.V. Environmental cut-off and drain
FR2626024A1 (en) * 1987-11-30 1989-07-21 Soletanche Process to ensure leaktightness between panels cast in holes drilled in the ground and walls obtained by this process
EP0333577A1 (en) * 1988-03-18 1989-09-20 Sondages Injections Forages "S.I.F." Entreprise Bachy Digging-tool guiding system for use in erecting a moulded wall in the soil
US6164873A (en) * 1997-09-12 2000-12-26 Finic B.V. Double-wing deformable stop-end pipe for forming the joining surfaces of concrete-cast wall elements
US6276106B1 (en) * 1997-05-12 2001-08-21 Kvaerner Cementation Fondations Limited Hydrophilic waterbar for diaphragm wall joints
WO2006083976A2 (en) * 2005-02-01 2006-08-10 Ben C. Gerwick, Inc. Wall structural member and method for contructing a wall structure
FR2949492A1 (en) * 2009-08-27 2011-03-04 Le Clos Les Perdrix VERTICAL STOP DEVICE OF A CONSTRUCTION CASTING MATERIAL
US20130255180A1 (en) * 2012-04-03 2013-10-03 Bauer Spezialtiefbau Gmbh Shuttering element for a trench wall and method for producing the trench wall
US9371623B2 (en) 2011-07-14 2016-06-21 Ccmj Systems Ltd Diaphragm wall apparatus and methods
WO2018197828A1 (en) * 2017-04-26 2018-11-01 Ccmj Systems Ltd Diaphragm walls
US11225769B2 (en) 2018-02-15 2022-01-18 Ccmj Systems Ltd Shear key former apparatus and method(s)
US11560684B2 (en) * 2018-06-27 2023-01-24 Soletanche Freyssinet Formwork element provided with sacrificial sections
DE202022100579U1 (en) 2022-02-02 2023-02-03 Gud Geotechnik Und Dynamik Consult Gmbh joint component

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2834198A (en) * 1957-03-21 1958-05-13 James E Goodman Sealing strip
US3128576A (en) * 1960-11-25 1964-04-14 Detroit Macoid Corp Waterstop
US3310952A (en) * 1957-03-07 1967-03-28 I C O S Impresa Di Costruzioni Method for the construction of a wall in the ground
US3412562A (en) * 1967-11-14 1968-11-26 Ben C Gerwick Inc Structural wall and method
US3422627A (en) * 1964-04-27 1969-01-21 Soletanche Method for interconnecting successive sections of walls and partitions cast in the ground
US3431736A (en) * 1966-02-12 1969-03-11 Shinhachiro Ueda Method of constructing underground concrete walls
US3464665A (en) * 1964-11-11 1969-09-02 Tot Aanneming Van Werken Voorh A template adapted for use in producing a concrete wall
US3465532A (en) * 1967-12-29 1969-09-09 Robertson L Belden Concrete pile and joint
US3601943A (en) * 1967-11-21 1971-08-31 Danois & Fils Ets J Expansion joint for sealing a gap between panels
US3729164A (en) * 1969-12-16 1973-04-24 Co Int Des Pieux Armes Frankig Device for forming continuous walls, by means of consecutive, reinforced-concrete panels

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3310952A (en) * 1957-03-07 1967-03-28 I C O S Impresa Di Costruzioni Method for the construction of a wall in the ground
US2834198A (en) * 1957-03-21 1958-05-13 James E Goodman Sealing strip
US3128576A (en) * 1960-11-25 1964-04-14 Detroit Macoid Corp Waterstop
US3422627A (en) * 1964-04-27 1969-01-21 Soletanche Method for interconnecting successive sections of walls and partitions cast in the ground
US3464665A (en) * 1964-11-11 1969-09-02 Tot Aanneming Van Werken Voorh A template adapted for use in producing a concrete wall
US3431736A (en) * 1966-02-12 1969-03-11 Shinhachiro Ueda Method of constructing underground concrete walls
US3412562A (en) * 1967-11-14 1968-11-26 Ben C Gerwick Inc Structural wall and method
US3601943A (en) * 1967-11-21 1971-08-31 Danois & Fils Ets J Expansion joint for sealing a gap between panels
US3465532A (en) * 1967-12-29 1969-09-09 Robertson L Belden Concrete pile and joint
US3729164A (en) * 1969-12-16 1973-04-24 Co Int Des Pieux Armes Frankig Device for forming continuous walls, by means of consecutive, reinforced-concrete panels

Cited By (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4346670A (en) * 1979-12-03 1982-08-31 Bunger Richard E Prefabricated mold inserts for forming flume platforms for animal confinement pens and method of construction
WO1984003315A1 (en) * 1983-02-22 1984-08-30 Finic Bv Environmental cut-off for deep excavations
US4601615A (en) * 1983-02-22 1986-07-22 Finic, B.V. Environmental cut-off for deep excavations
FR2542780A1 (en) * 1983-03-18 1984-09-21 Intrafor Cofor Method and device for improving the joint between successive panels of a reinforced concrete wall cast in the ground
US4582453A (en) * 1984-08-16 1986-04-15 Finic, B.V. Method and apparatus for in situ forming underground panelized concrete walls with improved joint structure
DE3444077A1 (en) * 1984-12-04 1986-06-19 Ed. Züblin AG, 7000 Stuttgart Paring tube
US4741644A (en) * 1985-04-11 1988-05-03 Finic, B.V. Environmental cut-off and drain
FR2626024A1 (en) * 1987-11-30 1989-07-21 Soletanche Process to ensure leaktightness between panels cast in holes drilled in the ground and walls obtained by this process
AT397675B (en) * 1987-11-30 1994-06-27 Soletanche METHOD FOR ENSURING THE TIGHTNESS BETWEEN MOLDED PANELS IN RECESSES MILLED OUT IN THE BOTTOM, AND DEVICE FOR CARRYING OUT THIS METHOD
EP0333577A1 (en) * 1988-03-18 1989-09-20 Sondages Injections Forages "S.I.F." Entreprise Bachy Digging-tool guiding system for use in erecting a moulded wall in the soil
FR2628772A1 (en) * 1988-03-18 1989-09-22 Sif Entreprise Bachy SYSTEM FOR GUIDING THE EXCAVATION TOOL USED FOR PRODUCING A MOLDED WALL IN THE SOIL
US4930940A (en) * 1988-03-18 1990-06-05 Sondages Injections Forages "S.I.F." Enterprise Bachy System for guiding the excavation tool used for constructing a wall cast in the ground
US6276106B1 (en) * 1997-05-12 2001-08-21 Kvaerner Cementation Fondations Limited Hydrophilic waterbar for diaphragm wall joints
US6164873A (en) * 1997-09-12 2000-12-26 Finic B.V. Double-wing deformable stop-end pipe for forming the joining surfaces of concrete-cast wall elements
WO2006083976A2 (en) * 2005-02-01 2006-08-10 Ben C. Gerwick, Inc. Wall structural member and method for contructing a wall structure
WO2006083976A3 (en) * 2005-02-01 2007-10-04 Ben C Gerwick Inc Wall structural member and method for contructing a wall structure
FR2949492A1 (en) * 2009-08-27 2011-03-04 Le Clos Les Perdrix VERTICAL STOP DEVICE OF A CONSTRUCTION CASTING MATERIAL
EP2299030A1 (en) * 2009-08-27 2011-03-23 Le Clos Les Perdrix Device for vertically shuttering a cast material end surface
US9371623B2 (en) 2011-07-14 2016-06-21 Ccmj Systems Ltd Diaphragm wall apparatus and methods
US20130255180A1 (en) * 2012-04-03 2013-10-03 Bauer Spezialtiefbau Gmbh Shuttering element for a trench wall and method for producing the trench wall
US8820015B2 (en) * 2012-04-03 2014-09-02 Bauer Spezialtiefbau Gmbh Shuttering element for a trench wall and method for producing the trench wall
WO2018197828A1 (en) * 2017-04-26 2018-11-01 Ccmj Systems Ltd Diaphragm walls
CN110637126A (en) * 2017-04-26 2019-12-31 Ccmj系统有限公司 Water-proof wall
AU2018257981B2 (en) * 2017-04-26 2021-01-28 Ccmj Systems Ltd Diaphragm walls
US10988911B2 (en) 2017-04-26 2021-04-27 Ccmj Systems Ltd Diaphragm walls
CN110637126B (en) * 2017-04-26 2021-09-24 Ccmj系统有限公司 Water-proof wall
US11225769B2 (en) 2018-02-15 2022-01-18 Ccmj Systems Ltd Shear key former apparatus and method(s)
US11560684B2 (en) * 2018-06-27 2023-01-24 Soletanche Freyssinet Formwork element provided with sacrificial sections
DE202022100579U1 (en) 2022-02-02 2023-02-03 Gud Geotechnik Und Dynamik Consult Gmbh joint component

Also Published As

Publication number Publication date
CA965624A (en) 1975-04-08
AU463693B2 (en) 1975-07-31
AU5007372A (en) 1974-06-20

Similar Documents

Publication Publication Date Title
US3796054A (en) Method for the construction of impermeable walls
US4005582A (en) Method of constructing underground concrete walls and reinforcement cage therefor
US3431736A (en) Method of constructing underground concrete walls
US3412562A (en) Structural wall and method
KR20210119861A (en) Slurry wall, construction method for the same and wire mesh assembly
US1943800A (en) Sectional wall and method of erecting it
US4146348A (en) Method for executing impermeable construction joints for diaphragm walls
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
US4453366A (en) Process of forming a continuous wall in the ground
US3326003A (en) Method of forming ground cut-off wall
CN108316237B (en) Revetment retaining wall
US4056154A (en) Squaring off and reaming tool for deep elongated trench excavations
EP0393032A1 (en) Reinforcement for continuously-cast concrete walls
JPH0438846B2 (en)
US2338110A (en) Graving dry dock and method of construction
JPS5841227Y2 (en) Element for mountain retainer
CN111519603A (en) Device for comprehensively treating uneven settlement of underground buried pipe of soft soil foundation by combination of replacement and filling and grouting and construction method
CN210562118U (en) Novel combined steel sheet pile
AU603257B2 (en) A precast diaphragm wall method
JPS5853321Y2 (en) Element for mountain retainer
JPS5934324A (en) Construction of cell revetment
CN117569341A (en) Construction method of gravity type pit-in-pit supporting structure in soft soil area
CN105544504A (en) Cement grouting sheet pile
CN116356798A (en) Construction process of underground continuous wall
US1444622A (en) John a