Measuring and servicing the drilling fluid in a well Download PDFInfo
- Publication number
- US3729986A US3729986A US00167194A US3729986DA US3729986A US 3729986 A US3729986 A US 3729986A US 00167194 A US00167194 A US 00167194A US 3729986D A US3729986D A US 3729986DA US 3729986 A US3729986 A US 3729986A
- Authority
- US
- United States
- Prior art keywords
- well
- volume
- drilling fluid
- fluid
- counter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000012530 fluid Substances 0.000 title claims abstract description 123
- 238000005553 drilling Methods 0.000 title claims abstract description 70
- 239000011343 solid material Substances 0.000 claims abstract description 15
- 230000005856 abnormality Effects 0.000 claims abstract description 8
- 210000002445 nipple Anatomy 0.000 claims description 17
- 238000000034 method Methods 0.000 abstract description 7
- 230000015572 biosynthetic process Effects 0.000 description 13
- 238000003780 insertion Methods 0.000 description 7
- 230000037431 insertion Effects 0.000 description 7
- 230000002706 hydrostatic effect Effects 0.000 description 4
- 230000015556 catabolic process Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000003466 anti-cipated effect Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 239000007789 gas Substances 0.000 description 1
- 229930195733 hydrocarbon Natural products 0.000 description 1
- 150000002430 hydrocarbons Chemical class 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 239000003208 petroleum Substances 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000000246 remedial effect Effects 0.000 description 1
- 150000003839 salts Chemical class 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B21/00—Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
- E21B21/08—Controlling or monitoring pressure or flow of drilling fluid, e.g. automatic filling of boreholes, automatic control of bottom pressure
Definitions
- Well bores are typically drilled through a geologic formation of several layers. It is anticipated that each such layer will exert a normal pressure on the drilling fluid in the well bore. Those layers containing fluids such as gases, hydrocarbons, water, salt water, etc., can on occasion exert an abnormal pressure on the drilling fluid in the well bore.
- the density of the drilling fluid should be such as to provide a hydrostatic pressure which will prevent formation fluid intrusion into the bore, but not sufficiently great as to cause a formation breakdown.
- FIG. 2 is a diagrammatic representation of a controller which can be used either for a withdrawal trip or for an insertion trip.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
Abstract
This invention relates to a method and system for detecting the condition of a well. During tripping the drilling fluid in the well is controlled to provide an early warning indication of an abnormality in the well. The volume of solid materials moved during each trip is measured and a corresponding required volume of drilling fluid is determined. A measured volume of drilling fluid is delivered in order to restore in the well the drilling fluid to a reference level. The required volume is compared with the measured volume to obtain signals which are indicative of the condition of the well.
Description
i ii United @tates Patent 1 Leonard 1 1 Ma 1 1973 54 MEASURING AND SERVICING THE 2,832.566 4/1958 Bielstein ..73/15s x DRILLING FLUID IN A WELL Primary Examiner.lerry W. Myracle [76] Inventor: Loren W. Leonard, 8345 Triola, No. Anomey Michael p Breston 33, Houston, Tex. 77036 22 Filed: July 29, 1971 [57] ABSTRACT [21] APP] N0.Z 167 194 This invention relates to a method and system for de- Related US. Application Data Continuation-impart of Ser. No. 67,706, Aug. 28, 1970, Pat. No. 3,646,808.
11.8. Cl ..73/155, 166/250 Int. Cl. ..E2lb 47/10 Field of Search ..346/33 WL; 73/152,
References Cited UNITED STATES PATENTS 10/1971 Rehm et a1. ..73/l55 X STAND tecting the condition of a well. During tripping the drilling fluid in the well is controlled to provide an early warning indication of an abnormality in the well. The volume of solid materials moved during each trip is measured and a corresponding required volume of drilling fluid is determined. A measured volume of drilling fluid is delivered in order to restore in the well the drilling fluid to a reference level. The required volume is compared with the measured volume to obtain signals which are indicative of the condition of the well.
I 1 Claims, 2 Drawing Figures 1 couur s d 56 58 42 57 fl w Lg votuue REOU REDr-I 44 COMPARATOR VOLUME 1 l l l l l 1 1 l 1 1 l 1 puuezo 1 1 l 1 l l l l 1 1 Patented May 1', 1973 2 Sheets-Sheet 1 STAND DETECTOR FIG.- I.
VOLUM E COMPARATOR VOLUME "vA LVE CONTRQLE MUD TANK I N VEN TOR LOREN W. LEONARD,
MICHAELP. anssrorv AT TORNEY.
Patented May 1, 1973 2 SheetsSheet 2 sum:
a DETECTOR VOLUME Honing-oh COMPARATOR voLuuE PuuPgso FIG. 2.
N N l VALVE CONTRQL- e4 .66, I I
INVENTOR.
LOR EN W. LEONARD,
MICHAEL P. BRESTON A T TORNEY;
MEASURING AND SERVICING THE DRILLING FLUID IN A WELL CROSS-REFERENCE TO RELATED APPLICATIONS This application is a continuation-in-part of applicants application Ser. No. 67,706 filed Aug. 28, l970 now U.S. Pat. No. 3,646,808.
BACKGROUND OF THE INVENTION Well bores are typically drilled through a geologic formation of several layers. It is anticipated that each such layer will exert a normal pressure on the drilling fluid in the well bore. Those layers containing fluids such as gases, hydrocarbons, water, salt water, etc., can on occasion exert an abnormal pressure on the drilling fluid in the well bore. The density of the drilling fluid should be such as to provide a hydrostatic pressure which will prevent formation fluid intrusion into the bore, but not sufficiently great as to cause a formation breakdown.
If the pressure of the fluids contained in a particular formation layer becomes excessive, or if the hydrostatic drilling fluid pressure drops appreciably, then there will be an intrusion of the formation fluid into the well bore. Such an intrusion will augment and contaminate the volume of drilling'fluid in the well bore. in the event of a formation breakdown, drilling fluid is lost to the formation. A loss of drilling fluid results in a lowering of the hydrostatic pressure head.
When this loss becomes appreciable, the pressure head of the drilling fluid will no longer withstand even the normal formation pressure. In that event, if highpressure fluids exist in the formation, they will intrude into the well bore. Thus, an original loss of drilling fluid into the formation can produce a formation fluid intrusion into the well bore. A low-volume intrusion is generally known as a kick", and a large-volume intrusion as a blowout.
It has been observed that when drilling a well bore, the majority of blowouts occur while tripping, which is an act of moving a pipe string in or out of the well bore, for example to replace drill bits, remove obstructions, perform logging operations, etc. An insertion trip is an act of inserting a volume of solid material, such as pipe joints and drill collars, into the well bore. A withdrawal trip is an act of withdrawing such a volume of solid material from the well bore. A trip means a withdrawal trip, an insertion trip, or both.
Traditional and current withdrawal trip procedures require visual counting of the number of moved pipe i stands, and the filling of the well bore up to a level from which drilling fluid can flow out of the bore. This procedure has certain drawbacks which, in the extreme, can destroy operating personnel, petroleum reserves, drilling equipment, and can cause serious ecological damage. In particular, this procedure is not sufficiently accurate, and above all is subject to human error. For example, if a low-volume gain or loss in drilling fluid is not timely detected, it may become a large-volume gain or loss. lfa blowout is to be positively averted, drilling fluid gains or losses must be detected preferably soon after they occur in order to allow for remedial steps to be effectively undertaken.
it is a broad object of this invention to provide a method and system for automatically maintaining while tripping the drilling fluid in a well bore at or near a reference level, and to provide an early warning indication of the existence of an abnormality in the drilling fluid condition. Also, the drilling fluid level in the well bore is continuously and automatically monitored during a trip and subsequent thereto.
The invention can be carried out by relatively-unskilled personnel and within a minimum of time, thereby substantially reducing the cost as well as the potential hazard of the drilling operation. The invention allows the drilling crew to attend to chores other than those connected with moving drilling fluid into or out of the well bore.
SUMMARY OF THE INVENTION This application describes subject matter claimed in said copending application and additionally describes and claims a method and system for detecting the condition of a well by controlling, while inserting drill pipe into a well, the drilling fluid in the well, ther'eby providing an early warning indication of an abnormality in the well. A count is made of the units of solid materials inserted into the well to obtain a required volume of drilling fluid to be delivered from the well. A measured volume of drilling fluid is then delivered from the well in order to restore in the well the drilling fluid to a reference level. The required volume and the measured volume as compared, and from the results of the comparison signals are obtained which are indicative of the condition of the well.
If fluid is being lost to the formation after a trip, the invention also contemplates automatically delivering drilling fluid to the well bore in an attempt to restore the hydrostatic pressure head and to thereby avert a possible blowout.
In a preferred system ofa trip controller of the inven-- tion, a count is made of the number of pipe stands,
moved during each trip. This count is multiplied by a suitable scaling factor, depending upon the physical characteristics of the pipe stands, in order to obtain the required volume of drilling fluid for the well bore. This required volume is then compared with a metered volume of the actually delivered drilling fluid in order for the drilling fluid in the well bore to reach its normal reference level. This comparison automatically provides an indication of the drilling fluid condition in the well bore.
The invention will be better understood with reference to the accompanying drawings, in which:
FIG. 1 is a diagrammatic representation of a controller used in connection with a withdrawal trip; and
FIG. 2 is a diagrammatic representation of a controller which can be used either for a withdrawal trip or for an insertion trip.
CONTROLLER FOR WITHDRAWAL TRIP FIG. 1 illustrates a conventional well ll being drilled through a formation 13. Well ll typically includes a casing 10, a well head 12, surface blowout preventers .14 and 16, and a bell nipple 17. A surface drilling fluid tionally employed to fill the well bore. A fill line 25 is connected to a suitable valve 30 having ports 26, 27 and 29 and a control element 31. Ordinarily, valve 30 maintains fluid flow in line 24 through normally- open ports 26 and 27. When element 31 becomes actuated by a power line 28, valve 30 will close ports 26 and 27 and establish fluid communication between its normally-closed ports 26 and 29.
To measure the volume of fluid pumped and delivered into the well bore, there is provided in fill line 25 a fluid meter 32 whose readout is preferably an electric signal fed via line 33 to a volume-delivered counter 62. Such fluid flow meters are manufactured, for example, by the Foxboro Company in the U.S.A. and are known as magnetic or turbine flow meters.
Mounted on the derrick floor 36 are a conventional rotary table 37 and a trip controller 40 which is shown enclosed in a dotteddine box. Controller 40 is preferably a digital system for it provides faster response and greater versatility. It will be understood, however, that an analog rather than a digital system could be equally employed, as will be apparent to those skilled in the art.
Above the derrick floor 36 are the elevators 42 coupled between a drill pipe stand 44, which it is desired to withdraw, and a hook 46. Hook 46 is carried by a block 48 in a conventional manner. Each pipe stand 44 normally comprises a number, say three, of drill pipe joints 45. The pipe stands, drill collars, and auxiliary tools form a conventional drill string To count the number of pipe stands 44 withdrawn by block 48 during each trip, there is provided a stand detector 50 which detects the withdrawal of each pipe stand and provides an appropriate electric or pneumatic signal through a line 51 to advance the count in a stand counter- 52. The stand detector 50 is preferably positioned on the side wall of the derrick at a distance of the derrick floor 36 which is approximately equal to the length of a pipe stand. Detector 50 can be a mechanical system, an optical system employing a light beam and photo cells, a pneumatic system, or an electro-mechanical system including microswitches for closing an electric circuit after the passage of each pipe stand 44.
Whichever system is employed for the stand? detector 50, line 51 can be made to receive a number of signals or pulses equal to the number of pipe stands withdrawn. This number, illustrated as 3, will be displayed in the window of stand-counter 52 as 003.
A volume-required counter 56, which may be a solid state electronic digital multiplier device, manually receives a scaling factor through a knob 57. The scaling factor is determined from the physical parameters of the pipe stands being withdrawn. Counter 56 actually multiplies this scaling factor by the count of stands pulled. This count is received on a line 58 from the stand-counter 52. The count in the window of counter 56 is the volume required for the three stands pulled by the block 48.
The required fluid volume is the volume of fluid necessary to restore the fluid level in the well bore back to a reference level 60'. This level is monitored by a normal level detector 60 coupled to bell nipple 17. The required volume is a volume of fluid necessary to replace the volume of solid material (pipe stands) withdrawn from the well bore.
If the delivered volume of fluid equals the required volume, and the fluid level in the bell nipple 17 is still below reference level 60', pump 18 will continue to deliver fluid into the well bore, but an alarm or warning signal will be given as hereinafter described.
If the fluid in the well bore suddenly rises above a high-level 61', a high-level" detector 61 coupled to bell nipple 17 will detect this rise in the level of the drilling fluid and will provide a warning signal.
The count of the delivered volume is displayed in the window of counter 62. Assuming normal operation, and for a scaling factor of 0.59, the volume delivered will be 1.77 units of volume.
A suitable comparator 64 receives on line 66 the count from the volume-required counter 56, and on line 68 the count from the volume-pumped counter 62. Comparator 64 compares the counts received on lines 66 and 68. in the event that the volume required is substantially equal to the volume delivered, the result will be indicated by a fluid normal indicating device 70. If the volume delivered is greater than the volume required, comparator 64 will provide an output signal to a fluid loss indicating device 72. If the volume pumped is less than the volume required, comparator 64 will provide an output signal to a fluid gain" or kick indicating device 74.
Prior to starting the withdrawal trip, the driller selects, in the manner previously described, a suitable scaling factor and inserts it into the volume-required counter 56. He also selects the number of pipe stands to be pulled during each withdrawal trip and adjusts counter 56 accordingly. Then the withdrawal trip is initiated. Stand detector causes the count in standcounter 52 to increase by one for each pipe stand withdrawn.
As previously mentioned, at the completion of the withdrawal trip, stand detector 50 will have detected three stands, the count in the window of stand-counter 52 will be 003, and the count in the volume-required counter 56 will be 1.77. Thereafter a signal will be supplied from counter 56 via a line 53 to a valve controller mechanism which actuates via line 28 valve 30 and causes it to establish fluid flow between its ports 26 and 29. This marks the beginning of the refilling operation through the fill line 25 and the metering operation through the fluid meter 32. The refilling operation ends when the fluid reaches the reference level Assuming that the refilling operation is normal, after the fluid meter 32 has measured a delivered volume which is equal to the required volume, the fluid level in the well bore will be at the reference level 60', as detected by the normal level detector 60, and the normal lamp 70 will become actuated. If the measured delivered volume is greater than the required volume, comparator 64 will actuate the loss warning light 72. If the delivered volume is less than the required volume, the kick lamp 74 will become actuated.
After the fluid in the well bore is restored to its reference level 60, the normal level detector 60 will provide a signal via line 63 to the valve controller 55 for actuation of valve 30, thereby stopping fluid flow between its ports 26 and 29 and re-establishing fluid flow between its ports 26 and 27. Counters 52, 56 and 62 will then be ready to begin the next withdrawal trip.
if after valve 30 has switched back to its normal condition, whereby fluid flows between ports 26 and 27,
there should occur a sudden rise in the fluid level above the reference level 60' and up to level 61', the highlevel detector 61 will then provide a signal to a warning light 71 via line 73.
While in the above description specific reference was made to particular component parts and sub-assemblies, it will be appreciated that variations are possible. For example, pump 18 need not be the fluid circulating pump of the fluid pit 22. Instead, a pump independent of the fluid circulation system 19 could be employed for pumping fluid from pit 22 into well bore 11 and, hence, valve 30 could be eliminated. Also, other valves could be employed and other volume measuring means could be used to measure the volume of solid material withdrawn.
To facilitate the understanding of the trip controller shown in FIG. 2, to the extent possible the same numerals were used in both FIGS. 1 and 2. Accordingly, only those elements in FIG. 2 which are either new or different will be specifically described in connection with FIG. 2.
Whereas in FIG. 1, detector 61 served as a high-level detector, in FIG. 2 detector 61 serves as a low-level detector. The valve controller 55 now has three input lines 53, 63, 73 and two output lines 28 and 85.
WITI-IDRAWAL TRIP MODE To illustrate the withdrawal trip mode operation of the trip controller 40 in FIG. 2, assume that counter 52 counts one stand and that 0.59 is the volume of-fluid displaced by one pipe stand. The scaling factor to be inserted through knob 57 will be 0.59. Counter 56 will count 059 and emit a signal via line 53 to the valve controller 55. Controller 55 will send a signal via line 28 to valve element 31 and will also send a signal via line 85 to valve element 81. Valve will establish fluid flow between ports 27 and 29, and valve 80 will establish fluid flow between ports 82 and 83. The flow of the drilling fluid then is from pit 22, through pump 18, discharge line 23, valve 30, meter 32, valve 80, and fill line 25.
When the fluid level in the bell nipple l7 rises to the reference level 60', detector 60 will transmit a signal to valve controller 55 via line 73. This signal will cause valve controller 55 to break fluid flow between ports 82, 83 as well as between ports 27, 29. The delivered volume of fluid as measured by meter 32 will be indicated in the window of counter 62. Assuming normal drilling operation, with no loss or gain in the volume of drilling fluid in the well bore and for the numbers previously given, counter 62 will read 059. Comparator 64 will compare the counts in counters 56 and 62 and will provide signals to lights 70, 72 and 74 in the manner described in connection with the controller of FIG. 1.
INSERTION TRIP MODE When the controller shown in FIG. 2 is used in its insertion trip mode, each pipe stand 44 lowered into the well bore will again be detected by detector 50. Counter 56 will indicate the volume of fluid which corresponds to the volume of the solid material inserted into the well bore. After counter 52 counts one stand, counter 56 will issue a command signal via line 53 to the valve controller 55. Controller 55 will then establish fluid flow between ports 83 and 84 of valve 80, and between ports 26 and 29 of valve 30.
Whereas in the withdrawal trip mode drilling fluid is delivered from pit 22 into the well bore 11, in the insertion trip mode drilling fluid is delivered from the well bore 11 into pit 22. The volume of drilling fluid flowingout of the well bore into the pit 22 is again measured by the flow meter 32.
With the insertion of solid material into the well bore, the level of the drilling fluid in the bell nipple l7 rises above reference level 60'. Therefore, the delivery of drilling fluid from the well bore will continue until the level of the fluid in bell nipple 17 drops to the reference level 60. Then, detector 60 will transmit a signal via line 73 to the valve controller 55 which will stop fluid flow between ports 82, 83 and between ports 26, 29.
The delivered volume of fluid from the well bore to pit 22, as measured by meter 32, will be counted by counter 62. The counts in counters 56 and 62 will again be compared by comparator 64 and the results of that comparison will again be indicated by lights 70, 72 and 74.
AUTOMATIC MAINTAIN MODE In addition to serving as a trip controller, the system shown in FIG. 2 can automatically maintain the drilling fluid level in the well bore above a minimum level 61' as detected by the low-level detector 61. In this automatic maintain mode, when the drilling fluid level drops below level 61, a command signal is issued by detector 61 via line 63 to valve controller 55. Controller 55 will then allow fluid flow between ports 28, 29 and ports 82, 83. In this manner fluid will flow from the discharge line 23 into the fill line 25 and down into the well bore 11.
This flow will continue until the level of the drilling fluid in the bell nipple 17 is raised back to the minimum level 61'. Then, detector 61 will cause valve controller 55 to stop fluid flow between ports 27, 29 and ports 82 83.
Again, it should be understood that the trip controller 40 shown in FIG. 2 will lend itself to modifications, as will be apparent to those skilled in the art.
What is claimed is:
l. A system for detecting the condition of a well by controlling, while inserting solid materials into the well, the drilling fluid in said well and providing an early warning indication of an abnormality in said well, comprising:
means for measuring a required volume of drilling fluid corresponding to a volume of solid materials moved into the well during each trip;
means for delivering from the well a measured volume of drilling fluid in order to restore in the well the drilling fluid to a reference level; and
means including comparing means for comparing said required volume with said measured volume to obtain said early warning indication.
2. The system of claim 1 wherein said well includes a bell nipple and said reference level is monitored in said bell nipple.
3. The system of claim 2 wherein said means for delivering include a fluid flow meter.
4. The system of claim 3 wherein said means for measuring include:
a first counter for counting the units of said solid materials moved; and
a second counter responsive to said first counter,
said second counter providing an indication of said required volume.
5. The system according to claim 4 wherein said means for delivering includes a circulating pump associated with the drilling fluids surface circulation system.
6. A system for detecting the condition of a well by controlling, while tripping, the drilling fluid in said well and providing an early warning indication of an abnormality in said well, said system comprising:
means for measuring a required volume of drilling fluid corresponding to a volume of a number of pipe stands moved during each trip;
means for delivering a measured volume of drilling fluid in order to restore in the well the drilling fluid to a reference level; and
means including comparing means for comparing said required volume with said measured volume to obtain said early warning indication.
7. The system of claim 6 wherein said well includes a bell nipple and said reference level is monitored in said bell nipple.
8. The system of claim 7 wherein said means for delivering include a fluid flow meter.
9. The system of claim 8 wherein said means for measuring include: I
a first counter for counting the number of said pipe stands moved, and
a second counter, responsive to the output of said first counter, for providing an indication of said required volume.
10. The system of claim 8 wherein said means for delivering and further including a circulating pump.
11. The system of claim 8 wherein said flow meter is a turbine flow meter.
Claims (11)
1. A system for detecting the condition of a well by controlling, while inserting solid materials into the well, the drilling fluid in said well and providing an early warning indication of an abnormality in said well, comprising: means for measuring a required volume of drilling fluid corresponding to a volume of solid materials moved into the well during each trip; means for delivering from the well a measured volume of drilling fluid in order to restore in the well the drilling fluid to a reference level; and means including comparing means for comparing said required volume with said measured volume to obtain said early warning indication.
2. The system of claim 1 wherein said well includes a bell nipple and said reference level is monitored in said bell nipple.
3. The system of claim 2 wherein said means for delivering include a fluid flow meter.
4. The system of claim 3 wherein said means for measuring include: a first counter for counting the units of said solid materials moved; and a second counter responsive to said first counter, said second counter providing an indication of said required volume.
5. The system according to claim 4 wherein said means for delivering includes a circulating pump associated with the drilling fluid''s surface circulation system.
6. A system for detecting the condition of a well by controlling, while tripping, the drilling fluid in said well and providing an early warning indication of an abnormality in said well, said system comprising: means for measuring a required volume of drilling fluid corresponding to a volume of a number of pipe stands moved during each trip; means for delivering a measured volume of drilling fluid in order to restore in the well the drilling fluid to a reference level; and means including comparing means for comparing said required volume with said measured volume to obtain said early warning indication.
7. The system of claim 6 wherein said well includes a bell nipple and said reference level is monitored in said bell nipple.
8. The system of claim 7 wherein said means for delivering include a fluid flow meter.
9. The system of claim 8 wherein said means for measuring include: a first counter for counting the number of said pipe stands moved, and a second counter, responsive to the output of said first counter, for providing an indication of said required volume.
10. The system of claim 8 wherein said means for delivering and further including a circulating pump.
11. The system of claim 8 wherein said flow meter is a turbine flow meter.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US6770670A | 1970-08-28 | 1970-08-28 | |
US16719471A | 1971-07-29 | 1971-07-29 |
Publications (1)
Publication Number | Publication Date |
---|---|
US3729986A true US3729986A (en) | 1973-05-01 |
Family
ID=26748175
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US00167194A Expired - Lifetime US3729986A (en) | 1970-08-28 | 1971-07-29 | Measuring and servicing the drilling fluid in a well |
Country Status (2)
Country | Link |
---|---|
US (1) | US3729986A (en) |
ES (1) | ES394567A1 (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3857281A (en) * | 1973-03-22 | 1974-12-31 | Warren Automatic Tool Co | Method and apparatus for detecting potentially dangerous conditions in a well bore during trips of the well string in and out of the well bore |
US3963077A (en) * | 1975-06-18 | 1976-06-15 | Faulkner Ben V | Method of preventing well bore drilling fluid overflow and formation fluid blowouts |
US3973626A (en) * | 1975-09-24 | 1976-08-10 | Atlantic Richfield Company | Well completion in permafrost |
US4413511A (en) * | 1982-03-12 | 1983-11-08 | Mobil Oil Corporation | System for measuring cuttings and mud carryover during the drilling of a subterranean well |
US4476715A (en) * | 1983-03-11 | 1984-10-16 | Murphy Jack L | Mud metering tank monitoring system |
FR2562147A1 (en) * | 1984-03-30 | 1985-10-04 | Nl Industries Inc | METHOD OF OPTIMIZING THE MANEUVER SPEED OF A DRILL ROD TRAIN |
US4553429A (en) * | 1984-02-09 | 1985-11-19 | Exxon Production Research Co. | Method and apparatus for monitoring fluid flow between a borehole and the surrounding formations in the course of drilling operations |
US4953618A (en) * | 1989-01-12 | 1990-09-04 | Haliburton Company | Injection manifold and method |
US5115871A (en) * | 1990-03-12 | 1992-05-26 | Schlumberger Technology Corporation | Method for the estimation of pore pressure within a subterranean formation |
US5205165A (en) * | 1991-02-07 | 1993-04-27 | Schlumberger Technology Corporation | Method for determining fluid influx or loss in drilling from floating rigs |
US5205166A (en) * | 1991-08-07 | 1993-04-27 | Schlumberger Technology Corporation | Method of detecting fluid influxes |
US5975219A (en) * | 1996-12-23 | 1999-11-02 | Sprehe; Paul Robert | Method for controlling entry of a drillstem into a wellbore to minimize surge pressure |
US20150211362A1 (en) * | 2014-01-30 | 2015-07-30 | Chevron U.S.A. Inc. | Systems and methods for monitoring drilling fluid conditions |
US20220213752A1 (en) * | 2021-01-04 | 2022-07-07 | Saudi Arabian Oil Company | Convertible bell nipple for wellbore operations |
US20230160270A1 (en) * | 2021-11-19 | 2023-05-25 | Saudi Arabian Oil Company | Method and apparatus of smart pressures equalizer near bit sub |
US20230167736A1 (en) * | 2021-11-30 | 2023-06-01 | Aramco Overseas Company Uk Ltd | System and method to measure changes in the mud level and gas properties when drilling through a total loss zone with no returns to surface |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2832566A (en) * | 1953-04-10 | 1958-04-29 | Exxon Research Engineering Co | Method for maintaining level of drilling fluid |
US3614761A (en) * | 1969-11-03 | 1971-10-19 | Dresser Ind | Method and apparatus for monitoring potential or lost circulation in an earth borehole |
-
1971
- 1971-07-29 US US00167194A patent/US3729986A/en not_active Expired - Lifetime
- 1971-08-26 ES ES394567A patent/ES394567A1/en not_active Expired
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2832566A (en) * | 1953-04-10 | 1958-04-29 | Exxon Research Engineering Co | Method for maintaining level of drilling fluid |
US3614761A (en) * | 1969-11-03 | 1971-10-19 | Dresser Ind | Method and apparatus for monitoring potential or lost circulation in an earth borehole |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3857281A (en) * | 1973-03-22 | 1974-12-31 | Warren Automatic Tool Co | Method and apparatus for detecting potentially dangerous conditions in a well bore during trips of the well string in and out of the well bore |
US3963077A (en) * | 1975-06-18 | 1976-06-15 | Faulkner Ben V | Method of preventing well bore drilling fluid overflow and formation fluid blowouts |
US3973626A (en) * | 1975-09-24 | 1976-08-10 | Atlantic Richfield Company | Well completion in permafrost |
US4413511A (en) * | 1982-03-12 | 1983-11-08 | Mobil Oil Corporation | System for measuring cuttings and mud carryover during the drilling of a subterranean well |
US4476715A (en) * | 1983-03-11 | 1984-10-16 | Murphy Jack L | Mud metering tank monitoring system |
US4553429A (en) * | 1984-02-09 | 1985-11-19 | Exxon Production Research Co. | Method and apparatus for monitoring fluid flow between a borehole and the surrounding formations in the course of drilling operations |
FR2562147A1 (en) * | 1984-03-30 | 1985-10-04 | Nl Industries Inc | METHOD OF OPTIMIZING THE MANEUVER SPEED OF A DRILL ROD TRAIN |
US4953618A (en) * | 1989-01-12 | 1990-09-04 | Haliburton Company | Injection manifold and method |
US5115871A (en) * | 1990-03-12 | 1992-05-26 | Schlumberger Technology Corporation | Method for the estimation of pore pressure within a subterranean formation |
US5205165A (en) * | 1991-02-07 | 1993-04-27 | Schlumberger Technology Corporation | Method for determining fluid influx or loss in drilling from floating rigs |
US5205166A (en) * | 1991-08-07 | 1993-04-27 | Schlumberger Technology Corporation | Method of detecting fluid influxes |
US5975219A (en) * | 1996-12-23 | 1999-11-02 | Sprehe; Paul Robert | Method for controlling entry of a drillstem into a wellbore to minimize surge pressure |
US20150211362A1 (en) * | 2014-01-30 | 2015-07-30 | Chevron U.S.A. Inc. | Systems and methods for monitoring drilling fluid conditions |
US20220213752A1 (en) * | 2021-01-04 | 2022-07-07 | Saudi Arabian Oil Company | Convertible bell nipple for wellbore operations |
US11828128B2 (en) * | 2021-01-04 | 2023-11-28 | Saudi Arabian Oil Company | Convertible bell nipple for wellbore operations |
US20230160270A1 (en) * | 2021-11-19 | 2023-05-25 | Saudi Arabian Oil Company | Method and apparatus of smart pressures equalizer near bit sub |
US11982142B2 (en) * | 2021-11-19 | 2024-05-14 | Saudi Arabian Oil Company | Method and apparatus of smart pressures equalizer near bit sub |
US20230167736A1 (en) * | 2021-11-30 | 2023-06-01 | Aramco Overseas Company Uk Ltd | System and method to measure changes in the mud level and gas properties when drilling through a total loss zone with no returns to surface |
US11814952B2 (en) * | 2021-11-30 | 2023-11-14 | Saudi Arabian Oil Company | System and method to measure changes in the mud level and gas properties when drilling through a total loss zone with no returns to surface |
Also Published As
Publication number | Publication date |
---|---|
ES394567A1 (en) | 1974-04-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3729986A (en) | Measuring and servicing the drilling fluid in a well | |
US3646808A (en) | Method for automatically monitoring and servicing the drilling fluid condition in a well bore | |
US6234250B1 (en) | Real time wellbore pit volume monitoring system and method | |
US4430892A (en) | Pressure loss identifying apparatus and method for a drilling mud system | |
US5184508A (en) | Method for determining formation pressure | |
Edwardson et al. | Calculation of formation temperature disturbances caused by mud circulation | |
CA2477683C (en) | Method and system for controlling well circulation rate | |
US5857522A (en) | Fluid handling system for use in drilling of wellbores | |
EP2610427A1 (en) | Apparatuses and methods for determining wellbore influx condition using qualitative indications | |
AU763632B2 (en) | Method and apparatus for safely operating radiation generators in while-drilling and while-tripping applications | |
US20030029611A1 (en) | System and method for actuating a subterranean valve to terminate a reverse cementing operation | |
NO321471B1 (en) | Method and apparatus for evaluating well conditions during well fluid circulation | |
EP0263772A2 (en) | Pump differential pressure monitor system | |
CA1223807A (en) | Method and apparatus for determining formation pressure | |
GB2363847A (en) | Measuring fluid density and determining hole cleaning problems using differential pressure measurements | |
US2832566A (en) | Method for maintaining level of drilling fluid | |
US11994017B2 (en) | Method and system for monitoring and controlling fluid movement through a wellbore | |
US2617941A (en) | Measurement of fluid flow in boreholes by radioactivity | |
US3103812A (en) | Fluid analyzing tool | |
US3673864A (en) | Methods and apparatus for detecting the entry of formation gases into a well bore | |
US4290305A (en) | Drilling fluid circulating and monitoring system and method | |
US3209835A (en) | Inflatable packer apparatus | |
US3882474A (en) | System for monitoring the instantaneous velocity of a pipe string being tripped relative to a well bore | |
US5956995A (en) | Lubricant level detection system for sealed mud motor bearing assembly | |
WO2001027432A2 (en) | Methods and apparatus for making measurements on fluids produced from underground formations |