US2702424A - Process of manufacturing prestressed concrete - Google Patents

Process of manufacturing prestressed concrete Download PDF

Info

Publication number
US2702424A
US2702424A US275369A US27536952A US2702424A US 2702424 A US2702424 A US 2702424A US 275369 A US275369 A US 275369A US 27536952 A US27536952 A US 27536952A US 2702424 A US2702424 A US 2702424A
Authority
US
United States
Prior art keywords
concrete
reinforcement
relatively
setting
hardening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US275369A
Inventor
Bakker Johannes
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US2702424A publication Critical patent/US2702424A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/046Post treatment to obtain pre-stressed articles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/10Ducts

Definitions

  • PRoCEss oF MANUFACTURING PREsTREssED CONCRETE Filed March 7, 1952 1N VEN TOR. .Johan/ves ,Bakker United States Patent O PROCESS F MANUFACTURING PRESTRESSED CONCRETE Johannes Bakker, Lange Ruige Weide, Netherlands Application March 7, 1952, Serial No. 275,369
  • the invention relates to a process of manufacturing prestressed concrete.
  • two kinds of concrete with different hardening times are used and the filling of the mould occurs in such a manner that the reinforcement lies surrounded along its whole length by a layer of the relatively slower setting concrete in the relatively quicker setting concrete, after which, after suiiicient hardening 40 of the relatively quicker setting concrete, ⁇ but before the relatively slower setting concrete has hardened, the reinforcement is stretched.
  • the invention makes use of the known fact that it is possible to retard or accelerate the hardening time of normal concrete by adding definite chemical substances to it.
  • the process according to the invention can be performed in several ways, dependent on the needs.
  • normal concrete it is possible to use normal concrete round the reinforcement and for the rest so called accelerated concrete.
  • This method will be the most suitable for small or simple work pieces, with which the surrounding of the reinforcement requires 5 only little time.
  • retarded concrete round the reinforcement and for the rest normal concrete.
  • This latter method besides, has the advantage that only a relatively small amount of specially prepared concrete is necessary.
  • the relatively quicker setting concrete is poured in to the level of the reinforcement or of a part thereof, after which grooves are pressed in the concrete which is still in a soft condition, in which grooves the reinforcement or the concerned part thereof is laid and then is surrounded by the relatively slower setting concrete, whereafter the mould is further lled with the relatively quicker setting concrete, if necessary interrupted for surrounding the higher parts of the reinforcement with relatively slower setting concrete.
  • the invention at the same time comprises the articles or constructionsof prestressed concrete manufactured according to the above method.
  • the numeral 1 indicates a mould for a beam or girder 2 with a reinforcement consisting of three reinforcing elements 4 lying in the same horizontal plane 3.
  • the relatively quicker setting concrete for instance normal concrete
  • the mould is further filled with the relatively quicker setting concrete.
  • this latter concrete is suticiently hardened, the reinforcement can be stretched while the relatively slower setting concrete has not yet hardened.
  • Figure 2 shows a cross-section of a beam or girder like that of Figure l, but of greater height with a reinforcement, of which the reinforcing elements 4 lie in several ⁇ three ⁇ Aplanes above one another.
  • a reinforcement of which the reinforcing elements 4 lie in several ⁇ three ⁇ Aplanes above one another.
  • the deep slots or grooves need not be pressed in the concrete, but may also be formed with the aid of filling pieces.
  • non-mai concret has reference to a concrete containing no agents for increasing or decreasing or otherwise influencing the setting time of the concrete.
  • a process as defined in claim l including the further step of introducing a relatively faster setting concrete into the molding zone above the slower setting concrete.
  • a process of making prestressed concrete comprising the steps of introducing a relatively quick setting concrete into a molding zone, forming at least one seat in the quick setting concrete prior to hardening of the quick setting concrete, locating a reinforcement in the seat, surrounding the reinforcement with a slower setting concrete, stretching the reinforcement after sufficient hardening of the quick setting concrete but prior to hardening of 'the slow setting concrete and thereafter adding a relatively quick setting concrete into the molding zone above the quick setting concrete, the slower setting concrete and the reinforcement.

Description

Feb. 22, 1955 J, BAKKER 2,702,424
PRoCEss oF MANUFACTURING PREsTREssED CONCRETE Filed March 7, 1952 1N VEN TOR. .Johan/ves ,Bakker United States Patent O PROCESS F MANUFACTURING PRESTRESSED CONCRETE Johannes Bakker, Lange Ruige Weide, Netherlands Application March 7, 1952, Serial No. 275,369
(Jiaims priority, application Netherlands March 3, 1951 Claims. (Cl. 25--154) The invention relates to a process of manufacturing prestressed concrete.
Usually such concrete is manufactured in heavy moulds with respect of which the reinforcement is stretched, after which the concrete is poured in the mould and after sufficient hardening of the concrete the stress of the rcinforcement is enabled to exercise a prestressing pressure on the concrete.
Beside the known method also a method, in which the concrete piece is manufactured with channels for the reinforcement or the reinforcing elements. through which the reinforcement or the reinforcing elements are inserted after hardening of the concrete, which reinforcing elements are Athen stretched, after which the channels are filled with mortar under pressure. With this method indeed no heavy moulds are necessary, but the degree to which the channels are lled is not verifiable, so that no certainty exists about the goed quality.
'Ihe invention now aims at providing a process which gives the advantages of the above methods without the drawbacks thereof.
According to the invention two kinds of concrete with different hardening times are used and the filling of the mould occurs in such a manner that the reinforcement lies surrounded along its whole length by a layer of the relatively slower setting concrete in the relatively quicker setting concrete, after which, after suiiicient hardening 40 of the relatively quicker setting concrete,` but before the relatively slower setting concrete has hardened, the reinforcement is stretched. With this method, as well as with the last described known method, no heavy moulds are necessary, but at the same time certainty is obtained that the armouring lies well embedded along its whole length in the concrete and is' thus protected against corrosion. Besides a very good adhesion between the reinforcement and the surrounding concrete is guaranteed.
The invention makes use of the known fact that it is possible to retard or accelerate the hardening time of normal concrete by adding definite chemical substances to it.
The process according to the invention can be performed in several ways, dependent on the needs. Thus when it is desired to use normal concrete, it is possible to use normal concrete round the reinforcement and for the rest so called accelerated concrete. This method will be the most suitable for small or simple work pieces, with which the surrounding of the reinforcement requires 5 only little time. In other cases it will be recommendable to use so called retarded concrete round the reinforcement and for the rest normal concrete. This latter method, besides, has the advantage that only a relatively small amount of specially prepared concrete is necessary. 55
In practice appropriately first the relatively quicker setting concrete is poured in to the level of the reinforcement or of a part thereof, after which grooves are pressed in the concrete which is still in a soft condition, in which grooves the reinforcement or the concerned part thereof is laid and then is surrounded by the relatively slower setting concrete, whereafter the mould is further lled with the relatively quicker setting concrete, if necessary interrupted for surrounding the higher parts of the reinforcement with relatively slower setting concrete. u
The invention at the same time comprises the articles or constructionsof prestressed concrete manufactured according to the above method.
The invention will now be further elucidated with reference to a pair of examples of performance shown dia- .o 2,413,990
grammatically in cross-section in the drawing.
2,702,424 Patented Feb. 22, 1955 In Figure l the numeral 1 indicates a mould for a beam or girder 2 with a reinforcement consisting of three reinforcing elements 4 lying in the same horizontal plane 3. When manufacturing such a girder first the relatively quicker setting concrete 2, for instance normal concrete, is poured in the mould to the level 3 of the reinforcement. Then grooves 5 are pressed in the concrete when ir is still soft, after which the reinforcing elements are arranged and are surrounded on all sides along their whole length with the relatively slower setting concrete 5. This can take place by hand or with a syringe. Thereafter the mould is further filled with the relatively quicker setting concrete. When this latter concrete is suticiently hardened, the reinforcement can be stretched while the relatively slower setting concrete has not yet hardened.
After hardening of the relatively slower setting concrete the stress of the reinforcement can be transmitted to the concrete. Under definite circumstances, namely when the reinforcement is anchored with respect of the relatively quicker setting concrete, it is even not necessary to await the hardening of the relatively slower setting concrete.
Figure 2 shows a cross-section of a beam or girder like that of Figure l, but of greater height with a reinforcement, of which the reinforcing elements 4 lie in several {three} Aplanes above one another. In this case, if desired` it is possible to pour first the relatively quicker setting concrete to the level 6 of the second row of reinforcing elements, but it is also possible to pour the relatively quicker setting concrete immediately to the level 7 and to press grooves or slots in the soft concrete and further to act according to the method described with reference to Figure l.
The deep slots or grooves need not be pressed in the concrete, but may also be formed with the aid of filling pieces.
When the concrete is first poured in to the level 6, it will be necessary to interrupt the pouring of the relatively quicker setting-concrete at thc level 7, after surrounding of the two undermost rows of reinforcing elements, for surrounding the uppermost row with relatively slower setting concrete.
The term "normai concret has reference to a concrete containing no agents for increasing or decreasing or otherwise influencing the setting time of the concrete.
Having now particularly described and ascertained the nature of my said invention and in what manner the same is to 'oe performed I declare that what I claim is:
1. A process of making prestressed concrete comprising the steps of introducing concrete into a molding zone, forming a seat in the concrete, locating a reinforcement within the seat, surrounding the reinforcement with a relatively slower setting concrete and stretching the reinforcement after suiicient hardening of the concrete but prior to hardening of the slower setting concrete.
2. A process as defined in claim l including the further step of introducing a relatively faster setting concrete into the molding zone above the slower setting concrete.
3. A process of making prestressed concrete comprising the steps of introducing a relatively quick setting concrete into a molding zone, forming at least one seat in the quick setting concrete prior to hardening of the quick setting concrete, locating a reinforcement in the seat, surrounding the reinforcement with a slower setting concrete, stretching the reinforcement after sufficient hardening of the quick setting concrete but prior to hardening of 'the slow setting concrete and thereafter adding a relatively quick setting concrete into the molding zone above the quick setting concrete, the slower setting concrete and the reinforcement.
4. A process as dened in claim 3 wherein said slower setting concrete is normal concrete.
. 5. A process as delined in claim 3, wherein said quick setting concrete is normal concrete.
References Cited in the tile of this patent UNITED STATES PATENTS Muntz Ian. 7, 1947 Abeles Nov. 30, 1948
US275369A 1951-03-08 1952-03-07 Process of manufacturing prestressed concrete Expired - Lifetime US2702424A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NL2702424X 1951-03-08

Publications (1)

Publication Number Publication Date
US2702424A true US2702424A (en) 1955-02-22

Family

ID=19875407

Family Applications (1)

Application Number Title Priority Date Filing Date
US275369A Expired - Lifetime US2702424A (en) 1951-03-08 1952-03-07 Process of manufacturing prestressed concrete

Country Status (1)

Country Link
US (1) US2702424A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3086273A (en) * 1959-12-28 1963-04-23 Super Concrete Emulsions Ltd Method for pre-stressing concrete
US3156169A (en) * 1964-11-10 Finsterwalder
US3295278A (en) * 1963-04-03 1967-01-03 Plastitect Ets Laminated, load-bearing, heat-insulating structural element
US3317189A (en) * 1960-08-19 1967-05-02 Rubenstein David Traffic control bumper guard rail structures
US3398493A (en) * 1963-02-12 1968-08-27 Atomic Energy Authority Uk Concrete pressure vessels
US4205029A (en) * 1974-02-06 1980-05-27 Forrest Esli J Pre-stressed concrete construction
US5149385A (en) * 1986-12-28 1992-09-22 Shinko Kosen Kogyo Kabushiki Kaisha Tendons for prestressed concrete structures and method of using such tendons
US5168008A (en) * 1985-01-29 1992-12-01 National House Industrial Co., Ltd. Glazed cement product and method for manufacturing thereof
US5254190A (en) * 1986-12-28 1993-10-19 Shinko Kosen Kogyo Kabushiki Kaisha Tendons for prestressed concrete structures and method of using such tendons
CH685042A5 (en) * 1993-06-21 1995-03-15 Saw Schmitter Ag Widnau Process for producing a composite element cast from concrete and/or plastic and composite element produced by this process
US6054088A (en) * 1988-12-06 2000-04-25 Alhamad; Shaikh Ghaleb Mohammad Yassin Method of making a highly fire resistant construction board

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2413990A (en) * 1943-01-25 1947-01-07 Eric P Muntz Process of making prestressed reinforced concrete
US2455153A (en) * 1942-03-03 1948-11-30 Abeles Paul William Composite structural member

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2455153A (en) * 1942-03-03 1948-11-30 Abeles Paul William Composite structural member
US2413990A (en) * 1943-01-25 1947-01-07 Eric P Muntz Process of making prestressed reinforced concrete

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3156169A (en) * 1964-11-10 Finsterwalder
US3086273A (en) * 1959-12-28 1963-04-23 Super Concrete Emulsions Ltd Method for pre-stressing concrete
US3317189A (en) * 1960-08-19 1967-05-02 Rubenstein David Traffic control bumper guard rail structures
US3398493A (en) * 1963-02-12 1968-08-27 Atomic Energy Authority Uk Concrete pressure vessels
US3295278A (en) * 1963-04-03 1967-01-03 Plastitect Ets Laminated, load-bearing, heat-insulating structural element
US4205029A (en) * 1974-02-06 1980-05-27 Forrest Esli J Pre-stressed concrete construction
US5168008A (en) * 1985-01-29 1992-12-01 National House Industrial Co., Ltd. Glazed cement product and method for manufacturing thereof
US5149385A (en) * 1986-12-28 1992-09-22 Shinko Kosen Kogyo Kabushiki Kaisha Tendons for prestressed concrete structures and method of using such tendons
US5254190A (en) * 1986-12-28 1993-10-19 Shinko Kosen Kogyo Kabushiki Kaisha Tendons for prestressed concrete structures and method of using such tendons
US6054088A (en) * 1988-12-06 2000-04-25 Alhamad; Shaikh Ghaleb Mohammad Yassin Method of making a highly fire resistant construction board
CH685042A5 (en) * 1993-06-21 1995-03-15 Saw Schmitter Ag Widnau Process for producing a composite element cast from concrete and/or plastic and composite element produced by this process

Similar Documents

Publication Publication Date Title
US2702424A (en) Process of manufacturing prestressed concrete
US1893430A (en) Building unit and method of making the same
US2371882A (en) Tensioning and anchoring of cables in concrete or similar structures
DE69908273T2 (en) Pressing tool made of concrete and process for its production
US3260020A (en) Concentric chambered prestressed unit
SE9103042D0 (en) SET TO MANUFACTURE WALL ELEMENTS, AND WALL PARTS MANUFACTURED AS SET
US2315894A (en) Concrete construction
US2535100A (en) Process for prestressing cement products
CZ70293A3 (en) Process for producing a panel-like concrete element
US2152190A (en) Composite block
US1709035A (en) Manufacture of veneered blocks
CN206696098U (en) A kind of highway cement mortar detecting device for pressure strength
US3233027A (en) Method of making prestressed concrete beams
JP3308664B2 (en) Centrifugally formed steel tube concrete column and its manufacturing method
ES418411A1 (en) Manufacturing reinforced concrete elements
FR2440258A1 (en) METHOD AND DEVICE FOR ADJUSTING THE HEIGHT OF BUILDING BLOCKS AND THE LIKE
JPS6049731B2 (en) Manufacturing method of steel pipe concrete pile
US3271497A (en) Method for producing wall units
JP2893275B2 (en) Method for manufacturing high-strength concrete members that do not explode
SU908606A1 (en) Method of moulding ferroconcrete pressure pipes from concrete mixes
US3055077A (en) Method for the manufacture of concrete structures
GB1342420A (en) Method of providing a transverse bond between precast floor slabs
JPS6333544B2 (en)
JP3548257B2 (en) Lightweight aerated concrete panel
JPS5985023A (en) On-site pile driving work