US20220263677A1 US17/674,390 US202217674390A US2022263677A1 US 20220263677 A1 US20220263677 A1 US 20220263677A1 US 202217674390 A US202217674390 A US 202217674390A US 2022263677 A1 US2022263677 A1 US 2022263677A1
Authority
US
United States
Prior art keywords
docsis
timing
clock
phase error
cmts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US17/674,390
Inventor
Yair Neugeboren
Gregory J. Cyr
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Arris Enterprises LLC
Original Assignee
Arris Enterprises LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Arris Enterprises LLC filed Critical Arris Enterprises LLC
Priority to US17/674,390 priority Critical patent/US20220263677A1/en
Assigned to ARRIS ENTERPRISES LLC reassignment ARRIS ENTERPRISES LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: CYR, GREGORY J., NEUGEBOREN, Yair
Publication of US20220263677A1 publication Critical patent/US20220263677A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N21/00Selective content distribution, e.g. interactive television or video on demand [VOD]
    • H04N21/60Network structure or processes for video distribution between server and client or between remote clients; Control signalling between clients, server and network components; Transmission of management data between server and client, e.g. sending from server to client commands for recording incoming content stream; Communication details between server and client 
    • H04N21/61Network physical structure; Signal processing
    • H04N21/6106Network physical structure; Signal processing specially adapted to the downstream path of the transmission network
    • H04N21/6118Network physical structure; Signal processing specially adapted to the downstream path of the transmission network involving cable transmission, e.g. using a cable modem
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04JMULTIPLEX COMMUNICATION
    • H04J3/00Time-division multiplex systems
    • H04J3/02Details
    • H04J3/14Monitoring arrangements
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/28Data switching networks characterised by path configuration, e.g. LAN [Local Area Networks] or WAN [Wide Area Networks]
    • H04L12/2801Broadband local area networks
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/28Data switching networks characterised by path configuration, e.g. LAN [Local Area Networks] or WAN [Wide Area Networks]
    • H04L12/2854Wide area networks, e.g. public data networks
    • H04L12/2856Access arrangements, e.g. Internet access
    • H04L12/2858Access network architectures
    • H04L12/2861Point-to-multipoint connection from the data network to the subscribers
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/28Data switching networks characterised by path configuration, e.g. LAN [Local Area Networks] or WAN [Wide Area Networks]
    • H04L12/2854Wide area networks, e.g. public data networks
    • H04L12/2856Access arrangements, e.g. Internet access
    • H04L12/2869Operational details of access network equipments
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N21/00Selective content distribution, e.g. interactive television or video on demand [VOD]
    • H04N21/40Client devices specifically adapted for the reception of or interaction with content, e.g. set-top-box [STB]; Operations thereof
    • H04N21/43Processing of content or additional data, e.g. demultiplexing additional data from a digital video stream; Elementary client operations, e.g. monitoring of home network or synchronising decoder's clock; Client middleware
    • H04N21/442Monitoring of processes or resources, e.g. detecting the failure of a recording device, monitoring the downstream bandwidth, the number of times a movie has been viewed, the storage space available from the internal hard disk
    • H04N21/4425Monitoring of client processing errors or hardware failure
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04JMULTIPLEX COMMUNICATION
    • H04J3/00Time-division multiplex systems
    • H04J3/02Details
    • H04J3/06Synchronising arrangements
    • H04J3/0635Clock or time synchronisation in a network
    • H04J3/0638Clock or time synchronisation among nodes; Internode synchronisation
    • H04J3/0658Clock or time synchronisation among packet nodes
    • H04J3/0661Clock or time synchronisation among packet nodes using timestamps
    • H04J3/0667Bidirectional timestamps, e.g. NTP or PTP for compensation of clock drift and for compensation of propagation delays

Definitions

  • the subject matter of this application generally relates to synchronization of clocks in a transmission network that supports DOCSIS used to deliver data to and from mobile networks.
  • CATV Cable Television
  • CMTS Cable Modem Termination System
  • CMTS Cable Modem Termination System
  • CMTS Cable Modem Termination System
  • RF interfaces so that traffic that is coming from the Internet can be routed (or bridged) through the Ethernet interface, through the CMTS, and then onto the optical RF interfaces that are connected to the cable company's hybrid fiber coax (HFC) system.
  • Downstream traffic is delivered from the CMTS to a cable modem in a subscriber's home, while upstream traffic is delivered from a cable modem in a subscriber's home back to the CMTS.
  • HFC CATV systems have combined the functionality of the CMTS with the television delivery system (EdgeQAM) in a single platform called the Converged Cable Access Platform (CCAP) using Data-Over-Cable Service Interface Specifications (DOCSIS).
  • EdgeQAM television delivery system
  • CCAP Converged Cable Access Platform
  • DOCSIS Data-Over-Cable Service Interface Specifications
  • R-PHY Remote PHY
  • PHY physical layer
  • CCAP Remote PHY
  • the R-PHY device in the node receives the downstream data sent by the core, performs the downstream PHY functions, converts it from digital to an analog RF signal, and distributes it to the cable modems.
  • the R-PHY device in the node receives the upstream RF data sent by cable modems, converts it from analog to digital, performs the upstream PHY functions, and then transmits the digital data optically to the core.
  • the CMTS and R-PHY devices use DOCSIS.
  • the DOCSIS architecture has been employed as a mechanism for exchanging data in cellular communications between the core network of a cellular system (typically the global Internet) and the local networks it's communicating with, e.g. a cell tower.
  • This exchange is typically referred to as the “x-haul” portion of cellular communications which includes backhaul, midhaul, and fronthaul.
  • Cellular networks however, also require synchronization of the backhaul, midhaul, and fronthaul portion of the network with the mobile base stations, with its own set of unique timing requirements.
  • the DOCSIS network may also be used to provide synchronization to the mobile network.
  • the DOCSIS network could be a traditional CMTS, remote PHY system, a remote MAC-PHY system, or otherwise.
  • the CMTS may need to make large phase adjustments in order to re-lock to its time source, such as, when switching between two master clock sources, which may have a large time offset, such as 20 microseconds.
  • FIG. 1 illustrates an exemplary timing arrangement for an R-PHY architecture where a CCAP core is used as a timing grandmaster (GM) and Remote PHY Devices (RPDs) are the timing slaves.
  • GM timing grandmaster
  • RPDs Remote PHY Devices
  • FIG. 2 illustrates an exemplary timing arrangement for an R-PHY architecture where both a CCAP core and its RPDs are timing slaves to an external grandmaster.
  • FIG. 3 illustrates an exemplary CMTS architecture used as a backhaul for a cellular network.
  • FIG. 4 illustrates an exemplary R-PHY architecture used as a backhaul for a cellular network.
  • FIG. 5 illustrates DTP delay parameters
  • FIG. 6 illustrates one technique to synchronize timing.
  • FIG. 7 illustrates the technique to synchronize timing of FIG. 6 .
  • FIG. 8 illustrates another technique to synchronize timing.
  • FIG. 9 illustrates the technique to synchronize timing of FIG. 8 .
  • the DOCSIS Timing Protocol specifies a method of providing a timing reference, and in particular a specific time with respect to another clock reference, at the cable modem. Several common topologies are used to provide proper such synchronization.
  • the DOCSIS Timing Protocol is part of the CableLabs DOCSIS 3.1 specification, “Data-Over-Cable Service Interface Specifications DOCSIS® 3.1, MAC and Upper Layer Protocols Interface Specification, CM-SP-MULPIv3.1-I21-201020”, incorporated by reference herein in its entirety.
  • a first topology may include a CCAP core 2 synchronized with an RPD 3 connected together via a plurality of network switches 4 .
  • the RPD 3 is in turn is connected to one or more cable modems 5 . Synchronization is attained by a grandmaster clock 6 in the core 2 which sends timing information to a slave clock 7 in the RPD 3 .
  • a grandmaster clock 6 in the core 2 which sends timing information to a slave clock 7 in the RPD 3 .
  • FIG. 1 shows only one RPD 3 connected to the core 2 , many such RPDs may be simultaneously connected to the core 2 , with each RPD having a slave clock 7 receiving timing information from the grandmaster clock 6 in the core.
  • the switches 4 may be any combination of participating and non-participating switches.
  • FIG. 1 shows the RPD 3 connected to the core 2
  • the RPD 3 may be omitted, with each CM having a slave clock receiving timing information from the grandmaster clock 6 in the core typically through the CCAP core 2 .
  • FIG. 2 shows a second topology 10 to provide synchronization between a CCAP core 14 and an RPD 16 , which again is connected to one or more cable modems 18 .
  • a separate timing grandmaster device 12 provides timing information to both the CCAP core 14 and the RPD 16 .
  • the timing grandmaster 12 has a first master port 20 a connected to a boundary clock 22 in the CCAP core 14 and a second master port 20 b connected to a slave clock 24 in the RPD 16 .
  • the boundary clock 22 may therefore be a slave to the grandmaster 12 but a master to the slave clock 24 in the RPD.
  • the CCAP core 14 may be connected to the timing grandmaster 12 through one or more switches 26 while the RPD 16 may be connected to the timing grandmaster 12 through one or more switches 28 .
  • the switches 26 may be any combination of participating and non-participating switches.
  • FIG. 2 shows only one RPD 16 connected to the timing grandmaster 12 , many such RPDs may be simultaneously connected to the grandmaster 12 , with each RPD having a slave clock 24 receiving timing information from a port 20 b in the grandmaster clock 12 .
  • FIG. 2 shows the RPD 16 connected to the timing grandmaster 12 , such RPDs may be omitted, with each cable modem having a slave clock receiving timing information from a port 20 b in the grandmaster clock 12 .
  • CMTS 14 and/or the RPD 16 and/or the cable modem 18 are locked with the timing grandmaster 12 , no significant problems occur, but problems will occur when either the RPD 16 and/or the CMTS 14 and/or the cable modem 18 lose connection to the timing grandmaster 12 .
  • the unconnected devices will drift in frequency and phase from the timing grandmaster 12 and from the other device(s). The magnitude of that drift will depend on many factors, including the length of the holdover period, temperature variations, internal oscillator performance, etc. For example, an RPD with a typical TCXO oscillator might drift 1 ms in phase even within one hour.
  • the CMTS 14 and/or the RPD 16 and/or the cable modem 18 When connection to the timing grandmaster 12 is restored, the CMTS 14 and/or the RPD 16 and/or the cable modem 18 , would measure its phase offset from the grandmaster 12 and would need to adopt one of two methods to correct the offset and re-establish synchronization in both phase and frequency.
  • the RPD 16 and/or core 14 only changes its frequency relative to that of the grandmaster 12 to compensate for the phase offset, until such time as the phases are within tolerances, after which the frequency would be set to that of the grandmaster 12 .
  • frequency adjustments must be less than a specified threshold, so compensating for phase drift by frequency adjustments may often take a long time to achieve a desired phase adjustment.
  • LTE Long Term Evolution
  • 5G Fifth Generation
  • FDD frequency division duplex
  • HFC hybrid fiber coaxial
  • DAA Cable Distributed Access Architecture
  • R-PHY Remote-PHY
  • non-distributed architecture may be employed as an x-haul mechanism.
  • an architecture 200 may include a CMTS 210 connected to a grandmaster clock 214 through a wide area network 216 , e.g., the Internet, where the GM clock in turn receives its timing information from a GNSS satellite 218 .
  • the CMTS 210 provides the transmission path for CATV services to a cable modem 220 , which may include television channels, Internet services, video-on demand, and any other service provided to a customer via a transmission network.
  • the architecture 200 also serves as an x-haul for a cell network 222 that includes an eNB 224 that relays communications between user equipment such as cell phones and the x-haul network to the Internet.
  • the eNB 224 may be, or part of, a picocell, a small cell, a femto cell, a macro cell, or otherwise.
  • the architecture 200 shown in FIG. 3 implements a combination of IEEE 1588 and SyncE.
  • the GM clock 214 may include a master port 230 that provides IEEE 1588 timing protocols to a slave port 232 on a device within the network 216 .
  • the same or another device within the network may provide a master port 234 that provides IEEE 1588 timing protocols to a slave port 236 on the CMTS 210 .
  • the CMTS 210 may use other timing protocols, as desired.
  • the GM clock 214 may also include an EEC clock 240 that provides SyncE to an EEC clock 242 on a device within the network 216 .
  • the same or another device within the network may include an EEC clock 244 that provides SyncE to an EEC clock 246 on the CMTS 210 .
  • the network 216 may include one or more boundary clocks 250 synchronized to the grandmaster clock 214 and the CMTS 210 may include a boundary clock 252 synchronized to the grandmaster clock 214 .
  • the cable modem 220 may include a master port 260 that provides IEEE 1588 timing protocols to a slave port 262 on the eNB 224 .
  • the cable modem may also include an EEC clock 264 that provides SyncE to an EEC clock 266 on the eNB 224 .
  • the cable modem 220 may use other timing protocols to the eNB 224 .
  • the eNB 224 may include an ordinary clock 268 .
  • the CMTS 210 includes a master entity 270 that provides DOCSIS Timing Protocol (DTP) messages to a slave entity 274 on the cable modem 220 .
  • the CMTS 210 includes a master port 276 that provides IEEE 1588 timing protocols to a slave port 278 on the cable modem 220 .
  • the cable modem 220 may use other timing protocols, as desired.
  • the mobile base station needs to be frequency synchronized within 16 ppb (parts per billion) and phase synchronized with up to 1.5 microseconds compared to an absolute time reference.
  • This error budget represents the total error accumulated in the path between the source of time, such as the grandmaster clock 214 , and the mobile station end application.
  • IEEE-1588 assumes that the network delay in the forwarding and reverse paths is symmetrical. Any delay asymmetry in the network will effectively cause a phase error of 50% of the asymmetry value.
  • the phase synchronization is sensitive to packet delay variations in the network. With the use of hybrid fiber coaxial networks in combination with DOCSIS as an x-haul for mobile communications, it is challenging to provide accurate frequency and phase over the network.
  • DOCSIS is a packet based network, and as such, it has the issue of network asymmetry and packet delay variations. Moreover, DOCSIS presents additional challenges related to asymmetry due to the nature of DOCSIS upstream scheduling, packet delay variations due to upstream scheduling, low bandwidth channels which causes larger packet transition times, and unknown delays and asymmetries in the CMTS and the cable modems.
  • FIG. 4 a system similar to that illustrated in FIG. 3 , that is applicable to systems that include a Remote PHY Device (RPD). Also, a system similar to that illustrated in FIG. 3 is appliable to systems that includes a Remote MACPHY Device (RMD).
  • RPD Remote PHY Device
  • the DOCSIS Timing Protocol is a series of extensions to the DOCSIS protocol and the implementations of the DOCSIS cable modem and the CMTS are intended to support precise timing delivery over DOCSIS by leveraging the OFDM extended timestamp 272 and ranging functionality of the DOCSIS system.
  • Frequency is addressed by coupling the cable modem Ethernet timing to the DOCSIS downstream symbol frequency, while time is addressed by coupling the cable modem PTP timestamp message to the DOCSIS extended timestamp.
  • Time offset and asymmetry compensation over the DOCSIS segment is addressed through measurement, signalling, and ranging by providing time adjust values through the DTP messages.
  • the DTP involves synchronization of phase (e.g., time).
  • the CMTS may be locked to a northbound GM clock (directly or through a series of one or more boundary clocks) using traditional PTP messages.
  • the cable modem may provide PTP master functionality to applications that reside on its network.
  • DOCSIS has strict limits on phase and frequency changes, while mobile does not have the same limitations.
  • the CMTS may need to make a large phase and/or frequency adjustment in order to re-lock to its time source. These can be, for example, when switching between two master clock sources which may have some time-offset, such as 20 microseconds between them. Or after a long holdover when there isn't a connection to the grandmaster clock, where the phase of one of the devices has drifted away significantly.
  • the CMTS may compensate for such phase offsets by only slow frequency changes, as DOCSIS does not allow performing phase steps and is bounded by a limited frequency change rate of 10 ppb/s.
  • the correction of large phase offsets is traditionally corrected using various techniques.
  • a technique involves using a sufficiently large step to the DOCSIS extended timestamp.
  • Another technique would allow the DOCSIS symbol rate to exceed the permitted frequency change rate to quickly align the DOCSIS symbol rate and the extended timestamp (and the cable modems clock which relies on it) to the mobile requirements. These result in a significant outage on the entire DOCSIS system as cable modems may need to reset and/or re-range.
  • Another technique involves phase corrections only by adjusting the DOCSIS symbol rate within the DOCSIS limitations. This may substantially extend an outage on the mobile backhaul path until the phase is corrected to the mobile requirements. A 50 microsecond phase offset may take up to 8 minutes to correct.
  • an exemplary diagram shows the parameters that are modelled and measured for asymmetry calculation for the DTP.
  • the delay asymmetries inside the CMTS and the cable modems data paths and the PHYs may need to be determined, modelled, and measured per deployment. Also, delay asymmetries in the HFC (amplifiers, etc.) are also measured. After these parameters are characterized, the main factor that would influence the time adjust parameter (e.g., “t-cm-adj”) would be changes in ranging that would be reflected in t-tro.
  • the DTP compensation mechanism which is traditionally a static parameter used to compensate for DOCSIS and HFC asymmetries, as a dynamic parameter modified to also compensate for ingress timing offsets, such as from PTP, that cannot be compensated for quickly within the limitations imposed by DOCSIS.
  • the DOCSIS DTP master such as the CMTS, RPD, RMD, or otherwise, determines whether a phase step (for large phase offsets) and/or a series of phase steps and/or a frequency slew up to the DOCSIS limit of 10 ppb/s can be used with a synchronized adjustment of the DOCSIS and DTP parameters. This allows the PTP master clock or other timing output in the cable modem to jump to the time as detected by the boundary clock slave in the CMTS (or otherwise) without causing the cable modem to reset and/or re-range.
  • a technique suitable for phase step recovery involves modifying the DTP time adjustment parameter 700 (e.g., “t-cm-adj”) by the phase error detected by the CMTS on its ingress PTP interface 710 .
  • This ‘jumps’ the cable modem's PTP master clock timestamp output 720 to align with the detected CMTS ingress PTP thereby effectively eliminating the timing error out of the CM.
  • a “virtual” phase step 730 is introduced by incrementing the CMTS PTP ingress timestamp by the required offset which “spoofs” the PTP technique that the phase error has been effectively eliminated.
  • the DOCSIS symbol frequency, and thus the extended timestamp 740 is slowly pushed, always in a manner within the limitations of DOCSIS specifications, to recover the large phase offset and align it back to the PTP ingress timestamp. This may be accomplished by dividing the large phase offset into small phase recovery corrections (e.g., 100 ns every 1-2 minutes), each of which may be completed relatively quickly by frequency changes. Each small phase recovery correction will change both the “virtual” ingress phase step and the DTP time adjust parameter.
  • the DTP time adjust parameter 800 may be modified by the phase error detected by the CMTS on its ingress PTP interface 810 .
  • This “jumps” the cable modem's PTP master clock timestamp output 820 to align with the detected CMTS ingress PTP, substantially eliminating the CM output timing error.
  • the DOCSIS clock is slewing slowly within the limitations of DOCSIS to align the DOCSIS timestamp back to the PTP ingress 840 .
  • the DTP time adjust parameter 800 is adjusted, e.g., every few seconds, compensating for the phase adjustment of the DOCSIS timestamp 840 , and may be calculated by the amount of phase recovered by the average DOCSIS clock frequency offset over that period (or in another manner). For example, if the DOCSIS clock is averaging a 100 ppb offset in a 1 second interval to reduce the large phase offset, the DOCSIS timestamp will appear to have moved 100 ns. The DTP adjust is also changed 100 ns over the same period and communicated to the cable modem through frequent DTP signalling (or in another manner).

Abstract

A method for adjusting a phase error includes a first device detecting a phase error at a timing interface of the first device. The first device modifying a DOCSIS timing protocol parameter based upon the detected phase error. The first device causing a modification of a second device's timestamp output in a manner based upon the detected phase error by the modification of the DOCSIS timing protocol parameter.

Description

    CROSS REFERENCE TO RELATED APPLICATIONS
  • The present application claims the benefit of U.S. Provisional Patent Application Ser. No. 63/150,966 filed Feb. 18, 2021.
  • BACKGROUND
  • The subject matter of this application generally relates to synchronization of clocks in a transmission network that supports DOCSIS used to deliver data to and from mobile networks.
  • Although Cable Television (CATV) networks originally delivered television content to subscribers over large distances using exclusively coaxial cable, modern CATV transmission systems have replaced much of that coaxial cable with a more effective optical network, creating a hybrid transmission system where cable content is transmitted over the bulk of the distance from the head using optical fiber and terminating at the subscriber over coaxial cables.
  • Historically, the head end also included a Cable Modem Termination System (CMTS), used to provide high speed data services such as video, cable Internet, Voice over Internet Protocol, etc. Typically, a CMTS will include both Ethernet interfaces (or other high-speed data interfaces) as well as RF interfaces so that traffic that is coming from the Internet can be routed (or bridged) through the Ethernet interface, through the CMTS, and then onto the optical RF interfaces that are connected to the cable company's hybrid fiber coax (HFC) system. Downstream traffic is delivered from the CMTS to a cable modem in a subscriber's home, while upstream traffic is delivered from a cable modem in a subscriber's home back to the CMTS. Many modern HFC CATV systems have combined the functionality of the CMTS with the television delivery system (EdgeQAM) in a single platform called the Converged Cable Access Platform (CCAP) using Data-Over-Cable Service Interface Specifications (DOCSIS).
  • As networks have expanded and head ends have accordingly become increasingly congested with equipment, many content providers have recently used distributed architectures to spread the functionality of the CMTS/CCAP throughout the network. This distributed architecture keeps the data and video signals in digital format as long as possible, extending the digital signals beyond the CMTS/CCAP deep into the network before converting them to RF. It does so by replacing the analog links between the head end and the access network with a digital fiber (Ethernet/PON) connection.
  • One such distributed architecture is the Remote PHY (R-PHY) distributed access architecture, which relocates the physical layer (PHY) of a traditional CMTS or CCAP by pushing it into the network's fiber nodes. Thus, while the core in the CMTS/CCAP performs the higher layer processing, the R-PHY device in the node receives the downstream data sent by the core, performs the downstream PHY functions, converts it from digital to an analog RF signal, and distributes it to the cable modems. In the reverse direction, the R-PHY device in the node receives the upstream RF data sent by cable modems, converts it from analog to digital, performs the upstream PHY functions, and then transmits the digital data optically to the core. The CMTS and R-PHY devices use DOCSIS.
  • In addition, the DOCSIS architecture has been employed as a mechanism for exchanging data in cellular communications between the core network of a cellular system (typically the global Internet) and the local networks it's communicating with, e.g. a cell tower. This exchange is typically referred to as the “x-haul” portion of cellular communications which includes backhaul, midhaul, and fronthaul. Cellular networks, however, also require synchronization of the backhaul, midhaul, and fronthaul portion of the network with the mobile base stations, with its own set of unique timing requirements. The DOCSIS network may also be used to provide synchronization to the mobile network. Thus, using the DOCSIS network as the x-haul for cellular communications presents a challenge because the DOCSIS compliant devices have timing considerations that they must adhere to that may conflict with the timing and synchronizing requirements of the mobile network especially when phase corrections are needed such as, for example, after regaining connection to a master clock following a holdover. The DOCSIS network could be a traditional CMTS, remote PHY system, a remote MAC-PHY system, or otherwise. In some cases, the CMTS may need to make large phase adjustments in order to re-lock to its time source, such as, when switching between two master clock sources, which may have a large time offset, such as 20 microseconds.
  • What is desired, therefore, are improved systems and methods for synchronizing a network device, such as a CMTS, to the timing requirements of a cellular network.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • For a better understanding of the invention, and to show how the same may be carried into effect, reference will now be made, by way of example, to the accompanying drawings, in which:
  • FIG. 1 illustrates an exemplary timing arrangement for an R-PHY architecture where a CCAP core is used as a timing grandmaster (GM) and Remote PHY Devices (RPDs) are the timing slaves.
  • FIG. 2 illustrates an exemplary timing arrangement for an R-PHY architecture where both a CCAP core and its RPDs are timing slaves to an external grandmaster.
  • FIG. 3 illustrates an exemplary CMTS architecture used as a backhaul for a cellular network.
  • FIG. 4 illustrates an exemplary R-PHY architecture used as a backhaul for a cellular network.
  • FIG. 5 illustrates DTP delay parameters.
  • FIG. 6 illustrates one technique to synchronize timing.
  • FIG. 7 illustrates the technique to synchronize timing of FIG. 6.
  • FIG. 8 illustrates another technique to synchronize timing.
  • FIG. 9 illustrates the technique to synchronize timing of FIG. 8.
  • DETAILED DESCRIPTION
  • For purposes of the disclosure and the claims, the following terms are defined so as to more easily understand the subject matter described and claimed:
      • Master Clock: a clock that sends timing information to a slave clock for that clock to synchronize its time to that of the master clock.
      • Slave Clock: a clock that receives timing information from a master clock to synchronize its time to that of the master clock.
      • Grandmaster Clock: a clock that only operates as a master clock and is the source of time to the packet network:
      • Ordinary Clock: a slave clock that has a single port receiving timing information from a master clock.
      • Boundary Clock: a clock that operates as both a slave and a master by having one port in a slave state receiving time from a master clock, and one or more ports in a maser state which disseminate timing information to downstream slaves.
      • Evolved Node B (eNB): a base station used in cellular networks, and which includes not only antennas, receivers, and transmitters, but also resource management and logic control functions historically included in separate base station controllers, thus allowing eNB stations to communicate with each other directly. In addition, a next generation base station (gNB), or otherwise, may be used.
      • Synchronous Ethernet (SyncE): a computer networking standard that facilitates the transfer of timing signals over an Ethernet physical layer to be used by devices that need them. In this embodiment, the SyncE timing should originate from the same source as the grandmaster.
      • Ethernet Equipment Clock (EEC): slave clocks in the SyncE protocol that receive synchronization data from an interface connected to an upstream master clock.
  • The DOCSIS Timing Protocol (DTP) specifies a method of providing a timing reference, and in particular a specific time with respect to another clock reference, at the cable modem. Several common topologies are used to provide proper such synchronization. The DOCSIS Timing Protocol (DTP) is part of the CableLabs DOCSIS 3.1 specification, “Data-Over-Cable Service Interface Specifications DOCSIS® 3.1, MAC and Upper Layer Protocols Interface Specification, CM-SP-MULPIv3.1-I21-201020”, incorporated by reference herein in its entirety.
  • Referring to FIG. 1, for example, a first topology may include a CCAP core 2 synchronized with an RPD 3 connected together via a plurality of network switches 4. The RPD 3 is in turn is connected to one or more cable modems 5. Synchronization is attained by a grandmaster clock 6 in the core 2 which sends timing information to a slave clock 7 in the RPD 3. Those of ordinary skill in the art will appreciate that, although FIG. 1 shows only one RPD 3 connected to the core 2, many such RPDs may be simultaneously connected to the core 2, with each RPD having a slave clock 7 receiving timing information from the grandmaster clock 6 in the core. The switches 4 may be any combination of participating and non-participating switches. Those of ordinary skill in the art will appreciate that, although FIG. 1 shows the RPD 3 connected to the core 2, the RPD 3 may be omitted, with each CM having a slave clock receiving timing information from the grandmaster clock 6 in the core typically through the CCAP core 2.
  • FIG. 2 shows a second topology 10 to provide synchronization between a CCAP core 14 and an RPD 16, which again is connected to one or more cable modems 18. Unlike the system of FIG. 1, however, a separate timing grandmaster device 12 provides timing information to both the CCAP core 14 and the RPD 16. Specifically, the timing grandmaster 12 has a first master port 20 a connected to a boundary clock 22 in the CCAP core 14 and a second master port 20 b connected to a slave clock 24 in the RPD 16. The boundary clock 22 may therefore be a slave to the grandmaster 12 but a master to the slave clock 24 in the RPD. Those of ordinary skill in the art will recognize that the respective clocks of the CCAP core 14 and the RPD 16 may both be connected to a single master port in the timing grandmaster device 12, and the use of separate timing ports 20 a and 20 b in FIG. 2 is used merely to more easily describe the separate timing processes. The CCAP core 14 may be connected to the timing grandmaster 12 through one or more switches 26 while the RPD 16 may be connected to the timing grandmaster 12 through one or more switches 28. The switches 26 may be any combination of participating and non-participating switches. Again, those of ordinary skill in the art will appreciate that, although FIG. 2 shows only one RPD 16 connected to the timing grandmaster 12, many such RPDs may be simultaneously connected to the grandmaster 12, with each RPD having a slave clock 24 receiving timing information from a port 20 b in the grandmaster clock 12. Again, those of ordinary skill in the art will appreciate that, although FIG. 2 shows the RPD 16 connected to the timing grandmaster 12, such RPDs may be omitted, with each cable modem having a slave clock receiving timing information from a port 20 b in the grandmaster clock 12.
  • While the CMTS 14 and/or the RPD 16 and/or the cable modem 18 are locked with the timing grandmaster 12, no significant problems occur, but problems will occur when either the RPD 16 and/or the CMTS 14 and/or the cable modem 18 lose connection to the timing grandmaster 12. In that holdover period where one or more devices have no connection to the timing clock of the grandmaster 12, the unconnected devices will drift in frequency and phase from the timing grandmaster 12 and from the other device(s). The magnitude of that drift will depend on many factors, including the length of the holdover period, temperature variations, internal oscillator performance, etc. For example, an RPD with a typical TCXO oscillator might drift 1 ms in phase even within one hour.
  • When connection to the timing grandmaster 12 is restored, the CMTS 14 and/or the RPD 16 and/or the cable modem 18, would measure its phase offset from the grandmaster 12 and would need to adopt one of two methods to correct the offset and re-establish synchronization in both phase and frequency. Ideally, because any sufficiently large phase step adjustment would cause connected cable modems to go offline, the RPD 16 and/or core 14 only changes its frequency relative to that of the grandmaster 12 to compensate for the phase offset, until such time as the phases are within tolerances, after which the frequency would be set to that of the grandmaster 12. However, to maintain DOCSIS compliance (e.g., CableLabs DOCSIS 3.1), frequency adjustments must be less than a specified threshold, so compensating for phase drift by frequency adjustments may often take a long time to achieve a desired phase adjustment.
  • As previously noted, growth in mobile data consumption has put pressure on mobile network operators to build out small cell networks, where all the network traffic needs to be x-hauled to the mobile core. Modern cell architectures employ the LTE (Long Term Evolution) 4G standard, or 5G standard, or otherwise, which provides for high speed wireless communications for mobile users sufficient to access the Internet to experience services such as data, voice and video from a mobile network. While such standards permit both time division duplex (TDD) and frequency division duplex (FDD), this disclosure will assume that the disclosed systems employ FDD merely for purposes of illustration.
  • While such backhaul has been traditional accomplished via fiber and microwave, hybrid fiber coaxial (HFC) networks have been employed as an x-haul mechanism due to its capacity growth, cost efficiency and speed of deployment. Cable Distributed Access Architecture (DAA), including a Remote-PHY (R-PHY) architecture, or a traditional non-distributed architecture may be employed as an x-haul mechanism.
  • Referring for example to FIG. 3, an architecture 200 may include a CMTS 210 connected to a grandmaster clock 214 through a wide area network 216, e.g., the Internet, where the GM clock in turn receives its timing information from a GNSS satellite 218. The CMTS 210 provides the transmission path for CATV services to a cable modem 220, which may include television channels, Internet services, video-on demand, and any other service provided to a customer via a transmission network. In addition to providing CATV services traditionally delivered over the transmission network, the architecture 200 also serves as an x-haul for a cell network 222 that includes an eNB 224 that relays communications between user equipment such as cell phones and the x-haul network to the Internet. In some embodiments, the eNB 224 may be, or part of, a picocell, a small cell, a femto cell, a macro cell, or otherwise.
  • The architecture 200 shown in FIG. 3 implements a combination of IEEE 1588 and SyncE. The GM clock 214 may include a master port 230 that provides IEEE 1588 timing protocols to a slave port 232 on a device within the network 216. The same or another device within the network may provide a master port 234 that provides IEEE 1588 timing protocols to a slave port 236 on the CMTS 210. The CMTS 210 may use other timing protocols, as desired. The GM clock 214 may also include an EEC clock 240 that provides SyncE to an EEC clock 242 on a device within the network 216. The same or another device within the network may include an EEC clock 244 that provides SyncE to an EEC clock 246 on the CMTS 210. The network 216 may include one or more boundary clocks 250 synchronized to the grandmaster clock 214 and the CMTS 210 may include a boundary clock 252 synchronized to the grandmaster clock 214.
  • The cable modem 220 may include a master port 260 that provides IEEE 1588 timing protocols to a slave port 262 on the eNB 224. The cable modem may also include an EEC clock 264 that provides SyncE to an EEC clock 266 on the eNB 224. The cable modem 220 may use other timing protocols to the eNB 224. The eNB 224 may include an ordinary clock 268.
  • The CMTS 210 includes a master entity 270 that provides DOCSIS Timing Protocol (DTP) messages to a slave entity 274 on the cable modem 220. The CMTS 210 includes a master port 276 that provides IEEE 1588 timing protocols to a slave port 278 on the cable modem 220. The cable modem 220 may use other timing protocols, as desired.
  • The mobile base station needs to be frequency synchronized within 16 ppb (parts per billion) and phase synchronized with up to 1.5 microseconds compared to an absolute time reference. This error budget represents the total error accumulated in the path between the source of time, such as the grandmaster clock 214, and the mobile station end application. Also, IEEE-1588 assumes that the network delay in the forwarding and reverse paths is symmetrical. Any delay asymmetry in the network will effectively cause a phase error of 50% of the asymmetry value. In addition, the phase synchronization is sensitive to packet delay variations in the network. With the use of hybrid fiber coaxial networks in combination with DOCSIS as an x-haul for mobile communications, it is challenging to provide accurate frequency and phase over the network. DOCSIS is a packet based network, and as such, it has the issue of network asymmetry and packet delay variations. Moreover, DOCSIS presents additional challenges related to asymmetry due to the nature of DOCSIS upstream scheduling, packet delay variations due to upstream scheduling, low bandwidth channels which causes larger packet transition times, and unknown delays and asymmetries in the CMTS and the cable modems.
  • Referring to FIG. 4, a system similar to that illustrated in FIG. 3, that is applicable to systems that include a Remote PHY Device (RPD). Also, a system similar to that illustrated in FIG. 3 is appliable to systems that includes a Remote MACPHY Device (RMD).
  • As generally previously described, the DOCSIS Timing Protocol (DTP) is a series of extensions to the DOCSIS protocol and the implementations of the DOCSIS cable modem and the CMTS are intended to support precise timing delivery over DOCSIS by leveraging the OFDM extended timestamp 272 and ranging functionality of the DOCSIS system. Frequency is addressed by coupling the cable modem Ethernet timing to the DOCSIS downstream symbol frequency, while time is addressed by coupling the cable modem PTP timestamp message to the DOCSIS extended timestamp. Time offset and asymmetry compensation over the DOCSIS segment is addressed through measurement, signalling, and ranging by providing time adjust values through the DTP messages. In general, the DTP involves synchronization of phase (e.g., time). The CMTS may be locked to a northbound GM clock (directly or through a series of one or more boundary clocks) using traditional PTP messages. The cable modem may provide PTP master functionality to applications that reside on its network.
  • When using DOCSIS as an x-haul for mobile networks, one of the challenges is the ability to support two different timing applications with different timing requirements on the single clock that resides in the CMTS. DOCSIS has strict limits on phase and frequency changes, while mobile does not have the same limitations. In some cases, the CMTS may need to make a large phase and/or frequency adjustment in order to re-lock to its time source. These can be, for example, when switching between two master clock sources which may have some time-offset, such as 20 microseconds between them. Or after a long holdover when there isn't a connection to the grandmaster clock, where the phase of one of the devices has drifted away significantly. When the connection to the master clock is recovered or switched, the CMTS may compensate for such phase offsets by only slow frequency changes, as DOCSIS does not allow performing phase steps and is bounded by a limited frequency change rate of 10 ppb/s. The correction of large phase offsets is traditionally corrected using various techniques. A technique involves using a sufficiently large step to the DOCSIS extended timestamp. Another technique would allow the DOCSIS symbol rate to exceed the permitted frequency change rate to quickly align the DOCSIS symbol rate and the extended timestamp (and the cable modems clock which relies on it) to the mobile requirements. These result in a significant outage on the entire DOCSIS system as cable modems may need to reset and/or re-range. Another technique involves phase corrections only by adjusting the DOCSIS symbol rate within the DOCSIS limitations. This may substantially extend an outage on the mobile backhaul path until the phase is corrected to the mobile requirements. A 50 microsecond phase offset may take up to 8 minutes to correct.
  • Referring to FIG. 5, an exemplary diagram shows the parameters that are modelled and measured for asymmetry calculation for the DTP. The delay asymmetries inside the CMTS and the cable modems data paths and the PHYs may need to be determined, modelled, and measured per deployment. Also, delay asymmetries in the HFC (amplifiers, etc.) are also measured. After these parameters are characterized, the main factor that would influence the time adjust parameter (e.g., “t-cm-adj”) would be changes in ranging that would be reflected in t-tro.
  • Rather than causing an outage, it is desirable to use the DTP compensation mechanism, which is traditionally a static parameter used to compensate for DOCSIS and HFC asymmetries, as a dynamic parameter modified to also compensate for ingress timing offsets, such as from PTP, that cannot be compensated for quickly within the limitations imposed by DOCSIS. When a large phase correction is required, the DOCSIS DTP master, such as the CMTS, RPD, RMD, or otherwise, determines whether a phase step (for large phase offsets) and/or a series of phase steps and/or a frequency slew up to the DOCSIS limit of 10 ppb/s can be used with a synchronized adjustment of the DOCSIS and DTP parameters. This allows the PTP master clock or other timing output in the cable modem to jump to the time as detected by the boundary clock slave in the CMTS (or otherwise) without causing the cable modem to reset and/or re-range.
  • Referring to FIG. 6 and FIG. 7, a technique suitable for phase step recovery involves modifying the DTP time adjustment parameter 700 (e.g., “t-cm-adj”) by the phase error detected by the CMTS on its ingress PTP interface 710. This ‘jumps’ the cable modem's PTP master clock timestamp output 720 to align with the detected CMTS ingress PTP thereby effectively eliminating the timing error out of the CM. In order to avoid not actually jumping the DOCSIS timestamps, a “virtual” phase step 730 is introduced by incrementing the CMTS PTP ingress timestamp by the required offset which “spoofs” the PTP technique that the phase error has been effectively eliminated. The DOCSIS symbol frequency, and thus the extended timestamp 740 is slowly pushed, always in a manner within the limitations of DOCSIS specifications, to recover the large phase offset and align it back to the PTP ingress timestamp. This may be accomplished by dividing the large phase offset into small phase recovery corrections (e.g., 100 ns every 1-2 minutes), each of which may be completed relatively quickly by frequency changes. Each small phase recovery correction will change both the “virtual” ingress phase step and the DTP time adjust parameter.
  • Referring to FIG. 8 and FIG. 9, for a frequency slew recovery the DTP time adjust parameter 800 may be modified by the phase error detected by the CMTS on its ingress PTP interface 810. This “jumps” the cable modem's PTP master clock timestamp output 820 to align with the detected CMTS ingress PTP, substantially eliminating the CM output timing error. The DOCSIS clock is slewing slowly within the limitations of DOCSIS to align the DOCSIS timestamp back to the PTP ingress 840. The DTP time adjust parameter 800 is adjusted, e.g., every few seconds, compensating for the phase adjustment of the DOCSIS timestamp 840, and may be calculated by the amount of phase recovered by the average DOCSIS clock frequency offset over that period (or in another manner). For example, if the DOCSIS clock is averaging a 100 ppb offset in a 1 second interval to reduce the large phase offset, the DOCSIS timestamp will appear to have moved 100 ns. The DTP adjust is also changed 100 ns over the same period and communicated to the cable modem through frequent DTP signalling (or in another manner).
  • It will be appreciated that the invention is not restricted to the particular embodiment that has been described, and that variations may be made therein without departing from the scope of the invention as defined in the appended claims, as interpreted in accordance with principles of prevailing law, including the doctrine of equivalents or any other principle that enlarges the enforceable scope of a claim beyond its literal scope. Unless the context indicates otherwise, a reference in a claim to the number of instances of an element, be it a reference to one instance or more than one instance, requires at least the stated number of instances of the element but is not intended to exclude from the scope of the claim a structure or method having more instances of that element than stated. The word “comprise” or a derivative thereof, when used in a claim, is used in a nonexclusive sense that is not intended to exclude the presence of other elements or steps in a claimed structure or method.

Claims (14)

We claim:
1. A method for adjusting a phase error comprising:
(a) a first device detecting a phase error at a timing interface of the first device;
(b) the first device modifying a DOCSIS timing protocol parameter based upon the detected phase error;
(c) the first device causing a modification of a second device's timestamp output in a manner based upon the detected phase error by the modification of the DOCSIS timing protocol parameter.
2. The method of claim 1 wherein the first device is a CMTS.
3. The method of claim 1 wherein the second device is a cable modem.
4. The method of claim 1 wherein the first device includes one or more devices in an R-PHY architecture.
5. The method of claim 1 wherein the DOCSIS timing protocol parameter is decreased over time after the modification.
6. The method of claim 5 wherein a DOCSIS timestamp is modified over time as the DOCSIS timing protocol parameter is modified in an opposing direction.
7. The method of claim 1 wherein the phase error is detected at an ingress precision time protocol interface of the first device.
8. The method of claim 6 wherein the DOCSIS timestamp is modified at a rate within a range specified by a corresponding DOCSIS protocol.
9. The method of claim 1 wherein said timing interface is a precision timing protocol interface.
10. The method of claim 1 wherein the DOCSIS timing protocol parameter is t-cm-adj.
11. The method of claim 1 wherein the second device's timestamp output is a precision time protocol clock timestamp output.
12. The method of claim 1 wherein the first device includes a R-MACPHY device.
13. The method of claim 1 wherein the first device includes a RPD device.
14. A method for adjusting a phase error comprising:
(a) a first device detecting a phase error at a first interface of the first device;
(b) the first device modifying a DOCSIS timing protocol parameter based upon the detected phase error;
(c) modifying of a second device's timestamp output based upon the modification of the DOCSIS timing protocol parameter.
US17/674,390 2021-02-18 2022-02-17 Systems and methods for supporting phase adjustments over docsis Abandoned US20220263677A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US17/674,390 US20220263677A1 (en) 2021-02-18 2022-02-17 Systems and methods for supporting phase adjustments over docsis

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US202163150966P 2021-02-18 2021-02-18
US17/674,390 US20220263677A1 (en) 2021-02-18 2022-02-17 Systems and methods for supporting phase adjustments over docsis

Publications (1)

Publication Number Publication Date
US20220263677A1 true US20220263677A1 (en) 2022-08-18

Family

ID=80683106

Family Applications (1)

Application Number Title Priority Date Filing Date
US17/674,390 Abandoned US20220263677A1 (en) 2021-02-18 2022-02-17 Systems and methods for supporting phase adjustments over docsis

Country Status (8)

Country Link
US (1) US20220263677A1 (en)
EP (1) EP4295512A1 (en)
JP (1) JP2024506952A (en)
AU (1) AU2022224588A1 (en)
CA (1) CA3208880A1 (en)
CL (1) CL2023002418A1 (en)
CO (1) CO2023010715A2 (en)
WO (1) WO2022178098A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20230021450A1 (en) * 2021-07-23 2023-01-26 Charter Communications Operating, Llc Automated determination of a timing offset for docsis time protocol to provide precision time protocol accuracy

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150295669A1 (en) * 2014-04-14 2015-10-15 Cisco Technology, Inc. Managing time offset and frequency drift in asynchronous docsis remote phy network environments
US20180205452A1 (en) * 2017-01-17 2018-07-19 Nokia Solutions And Networks Oy Method and apparatus for synchronization

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012166569A1 (en) * 2011-05-27 2012-12-06 Cisco Technology, Inc. Precision timing in a data over cable service interface specification (docsis) system
US9320003B2 (en) * 2013-11-27 2016-04-19 Cisco Technology, Inc. Detecting a narrow band ranging signal in an OFDM frame
BR112021011396A2 (en) * 2018-12-14 2021-08-31 Arris Enterprises Llc SYSTEMS AND METHODS TO IMPROVE HOLDOVER PERFORMANCE IN R-PHY NETWORK ARCHITECTURES

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150295669A1 (en) * 2014-04-14 2015-10-15 Cisco Technology, Inc. Managing time offset and frequency drift in asynchronous docsis remote phy network environments
US20180205452A1 (en) * 2017-01-17 2018-07-19 Nokia Solutions And Networks Oy Method and apparatus for synchronization

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"MAC and Upper Layer Protocols Interface Specification", Cable Television Laboratories, 2019 (Year: 2019) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20230021450A1 (en) * 2021-07-23 2023-01-26 Charter Communications Operating, Llc Automated determination of a timing offset for docsis time protocol to provide precision time protocol accuracy
US11844037B2 (en) * 2021-07-23 2023-12-12 Charter Communications Operating, Llc Automated determination of a timing offset for DOCSIS time protocol to provide precision time protocol accuracy

Also Published As

Publication number Publication date
CO2023010715A2 (en) 2023-11-20
CL2023002418A1 (en) 2024-03-01
AU2022224588A1 (en) 2023-08-03
WO2022178098A1 (en) 2022-08-25
EP4295512A1 (en) 2023-12-27
JP2024506952A (en) 2024-02-15
CA3208880A1 (en) 2022-08-25

Similar Documents

Publication Publication Date Title
US9252902B2 (en) Precision timing in a data over cable service interface specification (DOCSIS) system
CN102237941B (en) Time synchronization system and method
US11503560B2 (en) Time synchronization offset adjustment method and apparatus, terminal, and access layer device
US20110286560A1 (en) Network system with synchronization and method of operation thereof
JP2017050730A (en) Wireless device and base station system
US11489605B2 (en) Systems and methods to improve holdover performance in R-PHY network architectures
US11902605B2 (en) Partial video async support using R-MACPHY device
US20220263677A1 (en) Systems and methods for supporting phase adjustments over docsis
CA3123009A1 (en) Systems and methods to improve holdover performance in r-phy network architectures
US20210175991A1 (en) Systems and methods for large phase correction in r-phy network architectures
US11546072B2 (en) Systems and methods to improve holdover performance in R-PHY network architectures
US11581971B2 (en) DOCSIS clock emulation in distributed access architectures
US20230291597A1 (en) Systems and methods for r-macphy partial service support

Legal Events

Date Code Title Description
STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

AS Assignment

Owner name: ARRIS ENTERPRISES LLC, GEORGIA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:NEUGEBOREN, YAIR;CYR, GREGORY J.;SIGNING DATES FROM 20220222 TO 20220228;REEL/FRAME:060707/0505

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STPP Information on status: patent application and granting procedure in general

Free format text: FINAL REJECTION MAILED

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION